Documente Academic
Documente Profesional
Documente Cultură
Inc.
548
MAIN
,P,
/
1,.
~
CITY
\
L._
LIMITS
ExTENT
/
OF CONTRACT/
~.,.)
L..
AMHERST
\/
ST.
/f
HUMBOLOT
KENSING
t ON
EXPRESSWAY
I
I
lx
u
~
z
/
ST.
)
:\f
/l
II
/
/
i BEST
NORTH S~
ST.
N
o
LAKE
ERIE
m
Fig. 1 Location Plan
ECONOMICS
.
m
.r
L
549
550
mitic limestone with some thin interbedded shale layers. No appreciable gas was encountered. The original water table,which was at or
above the crown of the tunnels,was lowered below the invert by an extensive deep well dewatering system. The tunnels start at the northeast end of the project and were both driven concurrently toward the
southwest. The tunnels go downgrade (up to 2%) to the mid-point of the
project at the pump station and then upgrade (up to 0.5%) to the termination. Temporary support requirements included three percent (460
linear ft) of structural steel rib-supported and ninety-seven percent
(14,170 linearft) of rock bolted tunnel. (see Fig. 3, Typical Cross
Sections)
S & M as Project Sponsor was delegated complete managerial responsibility for this project by the Joint Venture partners. The company,
which is today called S & M Constructors, Inc. had its start in the
construction business in the late 20s and has completed hundreds of
miles of tunnels. As a company with a major commitment to tunnel work,
we perceived a need for an efficient and reliable mechanized rock tunneling machine. Consequently, in the fall of 1953, we initiated the
design of a T.B.M. and place our first machine in operation in October,
1965. Since that date the T.B.M. manufacturing company - Jarva Inc. has manufactured 29 T.B.M.s ranging in size from 6 ft O in. diam to
32 ft 3 in. diam utilizing cutter head drive from 200 hp to 2,400 hp.
After firmly establishing Jarva as the second most successful T.B.M.
manufacturing company,we decided to turn the full focus of our attention to contracting and sold Jarva to Atlas Copco A. B. headquartered
in Stockholm, Sweden in August, 1979.
With this background, after the award of the C-31 contract, S & M
decided to employ two existing T.B.M.s for the boring of these tunnels. The first machine we committed was manufactured by The Robbins
Company in 1976 and currently owned by James McHugh Construction Co.
The machine, Robbins Model 185-178, was 18 ft 2 in. diam, had a cutter
head drive of 900 hp and was completely suitable for this project.
The machine was located in Chicago and had been stored in an as is
condition after completing 11,000 linear feet of tunnel, logging
approximately 1,500 hrs of operations at this time. The second machine
was manufactured by The Robbins Company for White Pine Copper Company
in 1967. (see Fig. 4, Robbins 185-178, White Pine Copper Co.) This
machine, Robbins Model 181-122 , was 18 ft O in. diam and had 1,200 hp
at the cutter head. After boring 8,500 linear feet at the mine, this
machine was purchased by S & M, rebuilt to 18 ft 6 in. diam and drove
an additional 8,000 linear feet of tunnel in Rochester, New York.
This machine suffered major structural failures and after ten years in
the field was technologically obsolete.
The rebuild of 181-122 consisted of a major redesign of the cutter
head, modification of the front support, modification of the rear supports, redesign of the operators area, redesign of roof drills, and
the rebuilding and replacement of existing machine components. (see
Fig. 5, Original White Pine TBM and Fig. 6, Modifications to White
L
TYPE
MACH,.,
.
EXCAVATION
MUFALO
LIGHT
RAll
.Wio
,.s,,
,OJC(
!.
,
,,,..
..
mo.r!.
u-.
-W-
.C.
t-SUPPORT:
PRIMARY
a
CONCRETE
LINING
DETAILS
a
UJ
1-
,,
,,
7,...,
, .,.
ECONOMICS
I
I
553
554
ECONOMICS
555
Pine TBM)
The cutter head was redesigned from the domed style to the flat
style. The cutter head was redesigned around the existing bearing a
though the bearing cavity seal was changed from a grease seal to an
air oil mist seal.
To provide for a flat cutter mounting surface from the cutter head
to the bore, the eight existing muck buckets were modified and four
new cutter mounting platforms were made-- for a total of twelve spokes,
or mounting platforms. The muck paddles were also changed to conform
with the new face profile.
To complete the redesign of the front of the machine, the front supports were reworked. A new stationary lower front support was made to
replace the existing movable lower front support. The side supports
were extended above springline and the side support cylinders were replaced with new shorter stroke larger bore cylinders.
The existing 4,160 v 200 hp motors were replaced with new460
hp motors.
v 200
The existing thrust cylinders were replaced with larger bore cylinders to give the machine greater thrust potential. The thrust cylinder rod diam and rod clevis thread diam were also increased for a
greater safety factor.
The main beam was lengthened by four feet between the gripper housingand the cutter head support to give the operator better control of
the machine for both line and grade.
New wear plates were installed in the gripper housing guide shoes.
New Torque cylinders were also installed in the gripper housing.
At the back of the machine the single rear support leg was replaced
by two legs. This was done to give better control and stability when
resetting the machine.
Also, at the rear of the machine, the operators area was redesigned
A new platform was fabricated to accommodate the operators hydraulic
control station, all the electrical controls, and the hydraulic pumping station. The new platform was mounted to existing mounting pads
on the rear support housing.
Above the operators platform the main beam was extended with a
bolt-on section. This section helps support the operators platform,
provides a mounting for a new 320 gal hydraulic resevoir, and encloses
the conveyor.
The conveyor was lengthened to accommodate the lengthened main beam
and new operators platform. The conveyor was refitted with all new
components, including head and foot rollers, return and troughing
I
556
ECONOMICS
557
1981RETC PROCEEDINGSVOLUME 1
Itern
McHugh
Overhauled
185-178
White Pine
Modified
181-122
New Quotation
Typical
Excavation Diam
18 ft 7 in.
18 ft 6 in.
18 ft 6 in.
Gross Wt
235 tons
350 tons
280 tons
900 hp
1,200 hp
1,000 hp
5.1
7.5
7.8
1,911,000 lbs
2,155,000 lbs
2,000,000 lbs
924,286
ft-1bs
1,720,000
ft-1bs
1,000,000 ft-lbs
Cutter Size
15% in.
15% in.
15% in.
No. of Cutters
43
43
42
Total hp
1,025 hp
1,375 hp
1,100 hp
Estimated Maximum
Penetration Rate
10 fph
12 fph
10 fph
ECONOMICS
Itern
McHugh
Overhauled
185-178
White Pine
Modified
181-122
New Quotation
Typical
Estimated
Delivery Tiem
3 mons
6 mons
12 mons
Actual
Delivery Time
4 mons
9 mons
First Cost
$1,500,000
Modifications
Including Operating Expense
$1,090,000
$2,115,000
$1,790,000
$3,200,000
$1,000,000
Total
Job Cost
Estimated Salvage
Estimated
Job
615,000
750,000
700,000
500,000
$2,900,000
300,000
$2,200,000
$1,365,000
$1,290,000
Linear Feet
Bored
7,003
7,000
Operating hrs
1,750
1,750
Penetration
Linear fph
4.0
4.0
Cutter Cost
Total Cost
$1,525,000
$1,450,000
$2,400,000
$217.86
$207.14
$342.86
cost
160,000
4.5
160,000
200,000
559
560
The tabulations presented are based upon actual records and the estimates for new equipment. Due to the vagaries of field cost reporting and the limited data from this project, a recapitulation tempered
by experience and logic leads me to the following conclusions:
A minor modification of a relatively new machine is more economical than a new machine.
3.
4.
5.
6.
7.
Due to the lower initial cost, a used T.B.M. will generally prove
to be more economical than a new machine.
8.
9.
11. The operating costs of overhauled, rebuilt and new T.B.M.s are
not distinguishable.
12. The cutter costs of new, overhauled or rebuilt T.B.M.s are not
distinguishable. The economic life of T.B.M.s is certainly
greater than 10,000 hrs as has been proven in the field.
13. The ownership of a used T.B.M. can be a major asset for underground construction contractors, limited only by the versatility
of its diam and the inevitable structural deterioration.
ECONOMICS
REFERENCES
Jarva,
561