Documente Academic
Documente Profesional
Documente Cultură
CIRCUIT-BREAKERS/ SUBSTATIONS
Introduction
HOME takes you to the start page after you have read these Topics. Start page has links to other topics.
CIRCUIT -BREAKERS - OBJECTIVE TYPE QUESTIONS
1. Which of the following results when a resistance is placed across the contacts of a circuit breaker
i successful and effective interruption of current
ii undue power loss in the resistor
iii effective fault power dissipation
iv control of rate of rise of restriking voltage.
a. all four above
(b) i and iii
(c) i and iv.
Ans: (c)
1. The circuit breaker rating relevant to transient stability is
a. rated voltage
b. rated operating time
c. rated breaking current
Ans:
TOP
Introduction
Switchgear in a broad sense covers a wide range of equipment connected with switching and protection. A circuit breaker is a switching i.e. current interrupting or making device in switchgear. Th basic requirements of switching in power system practice are
two-fold:
1. to permit apparatus and circuits to be conveniently put into or taken out of service
2. to permit appropriate and safe isolation of apparatus and circuits automatically, in a pre-determined time period, when they develop faults.
Devices used for circuit breaking (or making)
1.
Fuse is an overcurrent switch in the sense that when the current exceeds a pre-assigned value in a circuit or device, it melts and causes current interruption. The supply is restored only when a healthy one replaces the damaged (melted) fuse in the line. To permit
this without any danger of shock to the operator, fuses are connected on the load side of an ironclad switch.
2. Isolators
An isolator is a switch connected after a circuit breaker. When a circuit or a busbar is taken out of service by tripping the circuit breaker, the isolator is then open circuited and the isolated line is earthed through earth switch so that the trapped line charges are
safely conducted to ground.
3. Circuit breakers
A circuit breaker is a complex circuit -breaking device with the following duties:
Appropriately manage the high-energy arc associated with current interruption. The problem has become more acute due to interconnection of power stations resulting in very high fault levels
Effect current interruption only when it is called upon to do so by the relay circuits. In fact they are required to trip for a minimum of the internal fault current and remain inoperative for a maximum of through fault current
Rapid and successive automatic breaking and making to aid stable system operation
Short-circuit interruption
Capacitor switching
Asynchronous switching
Classification of circuit breakers
Sketch the constructional details of he following:
1. Air-break circuit breaker or miniature C.B
2. Oil circuit breaker
3. Minimum oil circuit breaker
4. Air blast circuit breaker
5. SF6 circuit breaker
6. Vacuum circuit breaker
Explain DC and Ac arc interruptions and bring out the difference between the two
Describe briefly the methods adopted for rapid increase of the dielectric strength in various types of circuit breakers
Explain the phenomenon of AC circuit braking and the factors upon which the restriking voltage depends.
Explain current chopping and effects of breaking capacitive currents. How are these problems met in practice?
Ratings of circuit breakers
Rated voltage
Rated insulation
Rated frequency
Rated normal current
Rated short circuit breaking current
Rated short circuit making current
Rated opening sequence for auto-reclose CBs
Rated transient recovery voltage for terminal faults (Representation of TRV by 4-parameters and 2- parameters
CB interrupting time-its components in relation to fault clearing time
Single-pole auto reclosing & its effects on system performance
Substations
Indoor switchgear
a. Stationary cubicle type
b. Draw-out or truck type
c. SF6 filled switchgear
d. Fuse-switch units
e. Flame proof or explosion proof switchgear
f.
g.
h.
i.
j.
Cellular type
Corridor switchboard
Mimic diagram board
Metal-clad switchgear
Isolator and earthing switch-vertical break isolator-Double break isolator
2
3
4
5
Type test
Verification
of
Constructional
Requirements
Verification of Marking
Verification of dimensions
Test for capacity
Tests for voltage during discharge
7
8
Purpose
To verify materials of container, top cover, connector, &
positive & negative element (lead/calcium) of a cell
To know the type of cell, make, manufacturing date etc
To verify dimensions as per rated capacity
To confirm the rated capacity of a cell
To observe cell voltage during AH capacity test as under;
a) Voltage after 10 min. load 1.98 V
b) Voltage after 6 hours load- 1.92 V
c) Voltage after 10 hours load completed- 1,85 V
a) AH capacity shall not be less than 90%
b) WH capacity shall not be less than 75%
Shall be less than 10%
To apply 13 cycles of 2000 hours (charging & discharging) and
to observe capacity of cell after each cycle discharge. Capacity
should exceed 90 %
ACCEPTANCE TESTS Type test Nos. 2, 3, 4, and 5 will be used as the Acceptance tests.
Sample Scheme
No. of
cells in a
Lot
Up to 50
51-300
301-500
501-1000
1001 &
above
Stage 1
Stage 2
2
3
5
8
13
2
3
5
8
13
Stage 1+
stage 2
4
6
10
16
26
Permissible defectives
Stage 1
Stage 2
Stage 1+ stage 2
0
0
0
0
0
1
1
1
1
2
2
4
2
2
3
S. No.
Type test
Dielectric tests
2
3
Purpose
To check characteristics of Circuit breaker for the following tests:
I)
Dry, wet, power frequency
II)
Lightning impulse voltage
III)
Switching impulse voltage ( applicable for 420 kV
CB and above)
To determine RIV on CB pole in both close & open position
To record circuit resistance during temp. rise test at 200 C
To ensure capability of contacts to carry rated normal current
within specified temp. rise limits
To check the ability of the circuit to carry the maximum rated
short-circuit withstand current ( 2.5 times the RMS value) at 50 Hz
in close position during the specified short-term duration of 1 or 3
sec.
To check the characteristics of the breaker for 2000 operations on
each pole ( with multiple circuit breaker with individual drive) OR
complete assembled breaker (mechanically gang-operated breaker
with one common drive)
To check ability of the CB to clear the current on different tests in
symmetrical & asymmetrical conditions as per provisions of IEC
To check withstand capability of the CB for no load transient lines,
cables , and capacitor banks
ROUTINE TESTS
S. No.
1
Routine test
Dielectric test on main circuit
Measurement of resistance of
main circuit
Purpose
To check the dielectrics withstand capability of live terminals to
live terminals and to earth in both close & open condition of CB
To check the dielectrics withstand capability of auxiliary & control
circuit of CB subject to short duration (60 sec) voltage withstand
test for 2 kV . ( For motor or other devices , they are subjected to
a dielectric test as per appropriate specs.)
Verifies the CB for compliances in terms of language of name
plate, identification of aux. Equipment, colour & quality of paint
etc.
Includes
1)
5 open-close operations at max. rated and minimum
control voltage
2) 5 close-open operation at rated control voltage
3) recording opening & closing times at the rated operating
pressure & voltage
To record contact resistance of CB for mechanical operations to
be within specified limits
S. No
1
Type test
Short time current test
Purpose
To measure current density of winding w. r. t rated short time
current
2
3
4
5
a)
b)
Notes
1.
2.
After the CTs have been subjected to dielectric tests (3, 4, and 5), all routine tests will be carried out.
Type tests may be omitted when the manufacturer hold certificate of type tests on a similar transformer, which is acceptable to the purchaser.
Routine Tests
S. No.
Routine test
Verification of terminal marking &
polarity
Purpose
To ensure correct marking & function of CT
OPTIONAL TESTS
S. No.
1
Optional test
Chopped lightning impulse test as a type test
Purpose
To verify negative polarity lightning
impulse voltage withstand capacity
of external insulation
To measure dielectric dissipation
factor (tan d) of primary winding
between ambient temperature &
equipment temperature under test
To measure withstand capacity of
primary winding at 80% of rated
over voltage at site
ACCEPTANCE TESTS
The routine tests are to be considered as acceptance tests
SAMPLE CRITERIA
It is general practice to select samples equal to 20 % of offered lot
TOP
Indian Standards for Isolators, Lightning Arrestors, Switchgear Panels, LV Panels, and Gas insulated substations
AC DISCONNECTORS
(ISOLATORS) & EARTHING SWITCHES FOR VOLTGAE > 1000 V [IS: 9921 (Part-4-1985]
TYPE TESTS
S. No
1
2
3
Type test
(A) NORMAL TYPE TESTS
Dielectric tests
Temperature rise tests
Purpose
Note: All the test shall be carried out on complete isolator or earth switch on their operating devices & auxiliary equipments. Single pole tests are however permitted in certain cases.
ROUTINE TESTS
S. No
Routine test
Purpose
TOP
METAL OXIDE SURGE ARRESTORS WITHOUT GAP FOR AC SYSTEM [IEC 60099-4 &IS: 3070 1993]
TYPE TESTS [as per IEC]
S. No
Type test
Purpose
Routine Tests
S. No
Routine test
Purpose
NOTE:
SPECIAL TEST
S. No
Special test
Purpose
Metal
oxide
arrester
temperature
or
resistive
component of current or
power
dissipation
be
monitored
during
power
frequency voltage application
to prove thermal stability
SAMPLE CRITERIA
[As per clause No. 8.2.1 of IEC: 60099-4:1998]
The acceptance test shall be made on the nearest lower whole number in the cube root of the number of arrestors to be supplied.
TOP
Indian Standards for LV Panel Boards
[IS: 8623-1993]
There is no specific Indian Standard for the tests to be performed. However the manufacturer shall carry out following tests on the low voltage panel board and ask for type/routine tests of bought out items like switch
fuse units, meter, fuses, copper strip, indicating instruments etc.
Ref.: [IS 8623-1993]
TYPE TEST
S. No
1
2
3
Type test
Temperature rise test
4
5
8
9
10
11
Purpose
To verify the temperature rise of lT panel board
including all bus bars and equipments like MCCB,
ACB, MCB, Switch disconnectors
To verify withstand capacity in HV test
To verify connection between the exposed
conductive parts and the protective circuit
Notes:
The routine tests are to be considered as acceptance tests
The routine test certificates of manufacturer of all bought out items are to be verified.
SAMPLING CRITERIA
Select samples equal to 10 % of offered lot. Alternatively, as per sampling criteria given in IS: 2500
TOP
Type test
Dielectric tests:
1.1 Lightning & switching impulse voltage test
1.2 Power frequency voltage test
1.3 Artificial pollution test
1.4 Partial discharge test
1.5 Tests on auxiliary & control circuits
Radio interference voltage test (on one pole of CB during open
& closed position
Temperature rise test
Humidity test
7
10
11
12
Purpose
To verify that complete circuit
breaker panel along with auxiliary
and control circuits can withstand
relevant dielectric tests
13
14
ROUTINE TESTS
S. No
Routine test
Dielectric tests:
Dry power frequency test
Voltage withstand tests on auxiliary & control circuits
3
4
Purpose
Notes:
The routine tests are to be considered as acceptance tests
The routine test certificates of manufacturer of all bought out items are to be verified.
SAMPLING CRITERIA
TOP