Documente Academic
Documente Profesional
Documente Cultură
Preamble
The amount of wind generation is growing rapidly and wind farms
are growing in size and complexity.
Wind farms are being installed consisting of hundreds of units, with
the wind farm capable of producing hundreds of MW.
The location of a wind farm is selected primarily based on good
wind conditions.
Good wind conditions often coincide with relatively remote parts of the power
system.
Bantul
Sukabumi
Lebak
South Sulawesi (Jeneponto and Sidrap)
East Nusa Tenggara (Oelbubuk)
Summary data from conducted activity on wind resources assessment and research that have been
selected for 166 sites (source: Soeripno Martosaputro, (WHyPGen Project) )
Resources
potential
Wind
Speed at
50 m
Wind Power
density, at 50m,
(W/sq.m)
Number of
sites
Provinces
Marginal
3-4
<75
84
Fair
4-5
75-150
34
good
>5
>150
35
North Sulawesi
Gorontalo
South Sulawesi
South East Sulawesi
11
12
14
Equivalent modeling
the concern is not on the individual wind turbines but on the aggregate
effect of the entire farm on the power system.
individual generators are lumped into equivalent machines, generally
represented at the collector buses.
Thus size of system representation of the wind farm is reduced to a few
buses and the data requirements are significantly reduced.
This level of modeling is often used in system studies where the effects of
the injection into the system on system flows and voltages are the concern,
and internal wind farm conditions do not need to be determined
Therefore for the large scale wind penetration studies, detailed modeling may
not be required and thus lumped representation in which an equivalent of the
wind farm with PQ bus modeling, would suffice for the evacuation studies
15
16
Running production cost simulations to see how wind power impacts the
scheduling & dispatch of conventional generation, and operational costs of
the system
and base
Wind
generation
System demand
Local demand
Local conventional
Local nonconventional
Peak wind
season
corresponding local
load
Maximum
Maximum
Peak wind
season
corresponding local
load
corresponding
conventional
generation
Minimum
Peak wind
season
Maximum
Maximum
Peak wind
season
corresponding
conventional
generation
Minimum
Off-Peak
wind
season
Off-Peak
wind
season
corresponding local
load
Maximum
Maximum
corresponding local
load
corresponding
conventional
generation
Minimum
19
20
2015
Sidrap 70MW
Year
2019
Jeneponto-1 62.5MW
Jeneponto-2 64.5MW
Sidrap
Jeneponto
Particulars
Name of the wind farm
project
Details
Sidrap
Jeneponto 1
Jeneponto 2
70MW
62.5 MW
64.8 MW
Goldwind / 2.5MW
WTG
GE / 2.5MW
GE / 1.62MW
UPC Renewables
Desa Mangepong
2016
2017/18
600
5
6
Name of the
region/province of the wind Sulawesi Selatan
farm
Name of town/village
Not available
2015 (based on the
initial information
Assumed year of
commissioning of wind farm collected during site
visit of IWE)
Not available
600
Not available
Farming
S0536'11.77" E11936'14.14"
S0535'00" E11943'00"
10
Assumedcompletion date
Not available
11
Not available
12
Not available
Particulars
Sidrap
Jeneponto 1
Jeneponto 2
MVA Rating
85
72
72
Number of transformers
Voltage level in kV
150/33
150/33
150/33
15
15
15
15
15
15
Winding configuration
Star grounded/Delta
Star grounded/Delta
Star grounded/Delta
On-load
On-load
On-load
21
21
21
10
Nominal tap
11
11
11
11
12.5%
12.5%
12.5%
12
12.5%
12.5%
12.5%
Transmission Lines
150kV, 19.1km D/C hawk
conductor line from Sidrap
substation to Pare substation.
150kV, 53.8km D/C hawk
conductor line from Sidrap
substation to Sopeng
substation.
150kV, 62.33km D/C 2xzebra
conductor line from Sengkang
substation to Sidrap substation.
150kV, 126.54km D/C 2xzebra
conductor line from Sidrap
substation to Maros substation.
150kV, 105.48km D/C zebra
conductor line from Sidrap
substation to Makale substation.
Transmission Lines
150kV, 46.35km D/C hawk
conductor line from Jeneponto
substation to Bulukumba
substation.
150kV, 24.5km D/Chawk
conductor line from Jeneponto
substation to Punagaya Tip.
150kV, 19.1km D/C 2xzebra
conductor line from Punagaya
Tip to Tallasa substation.
150kV, 63.87km S/C hawk
conductor line from Bulukumba
substation to Sinjai substation.
150kV, 137.2km S/C hawk
conductor line from Bulukumba
substation to Bone substation.
Conductor type
Voltage in
kV
Zero sequence
R
(ohm / km/ckt)
X
(ohm /
km/ckt)
B/2
(mho /
km/ckt)
R
(ohm /
km/ckt)
X
(ohm /
km/ckt)
B/2
(mho /
km/ckt)
Thermal
rating in
MVA/ckt
70
0.23602
0.43327
9.42E-07
0.268
1.272
4.87E-07
48.5
30
0.29899
0.42587
1.11E-06
0.268
1.272
1.11E-06
20.78
150
0.118
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
ACSR_Hawk_240b
150
0.118
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
ACSR_Hawk_240c
150
0.118
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
150
0.1183
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
150
0.1183
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
150
0.119
0.424
1.50E-06
0.268
1.272
7.30E-07
155.88
150
0.0897
0.3222
1.50E-06
0.268
1.272
7.30E-07
155.88
10
150
0.236
0.4333
1.50E-06
0.268
1.272
7.30E-07
155.88
11
150
0.067
0.4026
1.50E-06
0.268
1.272
7.30E-07
207.84
12
150
0.0397
0.272
3.00E-06
0.268
1.272
9.11E-07
415.68
150
0.059
0.2807
2.09E-06
0.3207
1.197
1.27E-06
311.76
0.0397
0.2952
2.00E-06
0.2688
1.141
9.11E-07
762.1
15
150
0.0619
0.1414
2.12E-05
0.1547
0.3535
1.90E-05
137.69
16
70
0.0781
0.132
3.14E-05
0.1953
0.33
2.83E-05
56.98
13
14
275
0:00:00
0:30:00
1:00:00
1:30:00
2:00:00
2:30:00
3:00:00
3:30:00
4:00:00
4:30:00
5:00:00
5:30:00
6:00:00
6:30:00
7:00:00
7:30:00
8:00:00
8:30:00
9:00:00
9:30:00
10:00:00
10:30:00
11:00:00
11:30:00
12:00:00
12:30:00
13:00:00
13:30:00
14:00:00
14:30:00
15:00:00
15:30:00
16:00:00
16:30:00
17:00:00
17:30:00
18:00:00
18:30:00
19:00:00
19:30:00
20:00:00
20:30:00
21:00:00
21:30:00
22:00:00
22:30:00
23:00:00
23:30:00
Wind generation
60
50
40
30
20
10
Time in hour
38
600
500
400
300
200
100
0
1
211
421
631
841
1051
1261
1471
1681
1891
2101
2311
2521
2731
2941
3151
3361
3571
3781
3991
4201
4411
4621
4831
5041
5251
5461
5671
5881
6091
6301
6511
6721
6931
7141
7351
7561
7771
7981
8191
8401
8611
Load in MW
700
41
Fuel Mix
Description
Year
2015
1300
607
870
Year
2019
2266
1029
1560
Time
period in
a day
Wind generation
18:00 hrs
to 21.00
hrs
3:00hrs
to
5:00hrs
9:00 hrs
to 11:00
hrs
Demand Profile
Sl. No.
Province name
Minimum
(MW)
384
Maximum
(MW)
1303
Minimum
(MW)
547
South Sulawesi
Maximum
(MW)
914
West Sulawesi
54
23
35
91
38
58
Central Sulawesi
150
63
96
274
115
175
Southeast Sulawesi
217
91
139
Sub-Total*
1119
470
716
1885
792
1206
39
16
25
39
16
25
Average
(MW)
585
Average
(MW)
834
Barwaja
Bosowa
32
13
20
32
13
20
105
105
105
105
105
105
200
100
200
181
137
154
381
237
354
1300
607
870
2266
1029
1560
5
B
Total (A+B)
Banteang smelter
plant
Sub-total*
With Sidrap 70MW wind integration in 2015 system voltages and line
loadings are within acceptable limits
The system voltages and loading are acceptable during N-1 contingency
scenario
In 2015 maximum wind penetration is 5.4% during maximum demand
condition and 11.5% during minimum demand condition
Import of power from Central Sulawesi to South Sulawesi reduces from
76MW in Scenario -2 (minimum wind generation & maximum demand) to
32MW in Scenario-1 (maximum wind generation & system demand).
To have the load generation balance during varying wind generation from
maximum to minimum, reserve capacity is accommodated through
2x63MW Bakaru & 3x65MW Poso hydro generations
With Jeneponto wind farms integrated in 2019 the system voltages & line loadinggs are
within acceptable limits
The system voltages and loading are acceptable during N-1 contingency scenario
In 2019 maximum wind penetration is 8.7% during maximum demand condition and
19.1% during minimum demand condition
Import of power from Central Sulawesi to South Sulawesi reduces from 112MW in
Scenario -2 (minimum wind generation & maximum demand) to 78MW in Scenario-1
(maximum wind generation & system demand). Also import of power from West Sulawesi
to South Sulawesi reduces from 316MW in Scenario -2 to 220MW in Scenario-1
To have the load generation balance during varying wind generation from maximum to
minimum, reserve capacity is accommodated through 2x63MW Bakaru, 3x65MW Poso,
3x150MW Karama, 2x55MW Bontobatu, 2x45MW Malea hydro generations
Discussions ???
57
Dr. Balaraman K.
CGM, PRDC.
balaraman@rdcinfotech.com
58