Sunteți pe pagina 1din 97

WHITESANDS EXPERIMENTAL

PILOT PROJECT
DESIGN BASIS MEMORANDUM

Submitted to:
ORION OIL CANADA LTD.

February 27, 2004

Norwest Corporation
Suite 400, 205 9th Ave SE
Calgary, Alberta
T2G 0R3
Tel:
(403) 237-7763
Fax: (403) 263-4086
Email calgary@norwestcorp.com
www.norwestcorp.com

T ABLE OF CONTENTS

EXECUTIVE SUMMARY ............................................................................................................................................. 1-1

INTRODUCTION............................................................................................................................................................. 2-1
2.1
2.2
2.3
2.4
2.5
2.6

THAI RECOVERY PROCESS................................................................................................................................. 3-1


3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14

PROCESS O VERVIEW .................................................................................................................................................3-1


RECOVERY STRATEGY ..............................................................................................................................................3-2
PLANNED AND EMERGENCY SHUTDOWN AND RESTART .....................................................................................3-4
3-D CELL TEST RESULTS..........................................................................................................................................3-5
NUMERICAL SIMULATION PREDICTIONS................................................................................................................3-5
W ATER DISPOSAL......................................................................................................................................................3-8
PRODUCED GAS .........................................................................................................................................................3-8
RESERVOIR CONTROL PARAMETERS....................................................................................................................3-10
PRODUCTION CONTROL METHOD AND WELL PROTECTION .............................................................................3-10
RESERVOIR RECOVERY CONFORMANCE METHOD.............................................................................................3-11
PRODUCED A IR/GAS CONTROL..............................................................................................................................3-11
DATA COLLECTION REQUIREMENTS- RESERVOIR..............................................................................................3-11
DATA COLLECTION REQUIREMENTS SURFACE ................................................................................................3-12
CORROSION...............................................................................................................................................................3-12

WELL DESIGN AND COMPLETIONS .................................................................................................................... 4-1


4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8

PURPOSE OF THE DESIGN BASIS M EMORANDUM..................................................................................................2-1


PROJECT OVERVIEW..................................................................................................................................................2-2
PROJECT OBJECTIVES................................................................................................................................................2-3
GUIDING PRINCIPLES AND KEY A SSUMPTIONS.....................................................................................................2-4
RISK M ANAGEMENT..................................................................................................................................................2-4
PROJECT EXECUTION ................................................................................................................................................2-4

W ELL PATTERN AND LOCATIONS ...........................................................................................................................4-1


VERTICAL INJECTION W ELLS ..................................................................................................................................4-1
HORIZONTAL PRODUCTION WELLS ........................................................................................................................4-2
OBSERVATION W ELLS ..............................................................................................................................................4-2
W ATER DISPOSAL W ELLS........................................................................................................................................4-3
W ATER SOURCE WELLS...........................................................................................................................................4-4
SURFACE REQUIREMENTS (DRILL PADS, ROADS, M UD DISPOSAL) ..................................................................4-4
LIFT SYSTEM ..............................................................................................................................................................4-4

SURFACE FACILITIES DESIGN............................................................................................................................... 5-1


5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11

FACILITIES OVERVIEW..............................................................................................................................................5-1
RAW W ATER SUPPLY................................................................................................................................................5-2
STEAM GENERATION AND W ATER SOFTENING.....................................................................................................5-2
A IR COMPRESSION.....................................................................................................................................................5-3
PIPING, INSULATION , SUPPORTS AND CONTROLS.................................................................................................5-3
PRODUCTION WELLHEAD CONTROLS.....................................................................................................................5-3
INJECTION WELLHEAD CONTROLS .........................................................................................................................5-3
PRODUCTION TREATMENT AND SEPARATION (EMULSIONS)...............................................................................5-3
PRODUCTION GAS VENT...........................................................................................................................................5-4
PRODUCED W ATER TREATMENT AND DISPOSAL..................................................................................................5-4
TANKS AND PRODUCT SHIPPING/TRUCKING FACILITIES.....................................................................................5-4

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
TOC 1

5.12
5.13
5.14
5.15
5.16
5.17
6

SITE DEVELOPMENT, UTILITIES AND OFF-SITES ....................................................................................... 6-1


6.1
6.2
6.3
6.4
6.5

START -UP , SHUTDOWN PROCESS ............................................................................................................................7-1


DATA A CQUISITION AND REPORTING.....................................................................................................................7-2
W ELL INTEGRITY.......................................................................................................................................................7-3
SAFETY AND ENVIRONMENTAL PROTECTION .......................................................................................................7-4

REGULATORY COMPLIANCE................................................................................................................................. 8-1


8.1
8.2
8.3
8.4

POWER.........................................................................................................................................................................6-1
NATURAL GAS ...........................................................................................................................................................6-1
COMMUNICATIONS....................................................................................................................................................6-1
CAMP FACILITIES.......................................................................................................................................................6-2
CONSTRUCTION FACILITIES .....................................................................................................................................6-2

OPERATING DESIGN.................................................................................................................................................... 7-1


7.1
7.2
7.3
7.4

PROCESS UTILITIES ...................................................................................................................................................5-4


CONTROL ROOM AND OFFICE..................................................................................................................................5-4
CHEMICAL A DDITION SYSTEM................................................................................................................................5-4
SPACE HEATING & LINE TRACING..........................................................................................................................5-4
HEAT RECOVERY.......................................................................................................................................................5-5
DILUENT SYSTEM ......................................................................................................................................................5-5

A LBERTA ENERGY AND UTILITIES BOARD............................................................................................................8-1


A LBERTA ENVIRONMENT AND ALBERTA SUSTAINABLE RESOURCE DEVELOPMENT .....................................8-1
REGIONAL M UNICIPALITY OF W OOD BUFFALO....................................................................................................8-2
OTHER.........................................................................................................................................................................8-2

PRELIMINARY RISK ASSESSMENT...................................................................................................................... 9-1

Appendix A Geology
Appendix B Preliminary Project Schedule

List of Tables

Table 3-1
Table 3-2
Table 3.3
Table 3-4
Table 3-5
Table 7-1
Table 9-1

Reservoir Design Parameters ............................................................................ 3-2


Laboratory Physical Model Results with Wolf Lake Bitumen ............................ 3-5
Orion Numerical Model Input ............................................................................. 3-7
Produced Gas Composition ............................................................................... 3-9
Preliminary Flare and Vent Stack Parameters and Emissions........................ 3-10
Waste Streams ................................................................................................... 7-5
Preliminary Design and Operations Risk Summary.......................................... 9-1

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
TOC 2

List of Figures
Figure 2-1
Figure 2-2
Figure 2-3
Figure 2-4
Figure 3-1
Figure 4-1
Figure 4-2
Figure 4-3
Figure 4-4
Figure 4-5
Figure 4-6
Figure 4-7
Figure 4-8
Figure 4-9
Figure 4-10
Figure 5-1
Figure 5-2
Figure 5-3
Figure 5-4
Figure 5-5
Figure 5-6
Figure 5-7
Figure 5-8
Figure 5-9
Figure 5-10
Figure 5-11
Figure 5-12
Figure 5-13
Figure 6-1

Project Location
Infrastructure in Project Vicinity
THAI Schematic
Preliminary Project Schedule
THAI Process Schematic
Well Spacing
Spacing Detail
Vertical Injection Well
Wellhead Design Vertical Injector Well
Horizontal Production Well
Wellhead Design Horizontal Production Well
Observation Well Completed for Temperature Measurement
Temperature Observation Well
Pressure Observation Well
Water Disposal Well
Production Facilities and Access
Project Site Plan
Plant Layout
Process Flow Diagram
P&ID Block Diagram
Water Treatment P&ID
Steam Generator P&ID
Air Compressor P&ID
Wellhead, Inlet Separator and Cooler P&ID
Secondary Separator P&ID
Aerial Cooler, Treater and Vent Stack P&ID
Storage Tank and Pump P&ID
Process Utilities P&ID
Development Area Terrain

Figure A-1
Figure A-2
Figure A-3
Figure A-4
Figure A-5
Figure A-6
Figure A-7
Figure A-8
Figure A-9
Figure A-10
Figure A-11
Figure A-12
Figure A-13
Figure A-14

McMurray Seismic Character Correlation


Generalized Stratigraphic Section
Project Site Structural Cross-section
Devonian Unconformity Structure
Clearwater Marker Base to Devonian Isopach
McMurray Structure
Base of Clearwater Marker Structure
Wabiskaw Gas Pay Meters of Crossover
Caprock to McMurray Isopach
Clearwater Sandstone Isopach
Clearwater Sandstone Gas Pay
Preserved Colorado Isopach
McMurray Incised Valley Sandstone Isopach
McMurray Bitumen Pay Isopach

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
TOC 3

Abbreviations
AENV ..........................................................................................Alberta Environment
AOSTRA.................................... Alberta Oil Sands Technology and Research Authority
ASRD .........................................................Alberta Sustainable Resource Development
AXYS................................................................. AXYS Envir onmental Consulting Ltd.
CCME .............................................. Canadian Council of Ministers of the Environment
CMG ..................................................................................Computer Modelling Group
CO.................................................................................................... Carbon monoxide
CO2 ...................................................................................................... Carbon dioxide
COFCAW.......................................Combination Forward Combustion and Water Flood
EDTA.....................................................................Ethylene Diamine TetraAcetic Acid
EUB ........................................................................ Alberta Energy and Utilities Board
GJ/hr ............................................................................................... Gigajoule per hour
H2 S..................................................................................................Hydrogen sulphide
IHS........................................................................... Inclined Heterolithic Stratification
km................................................................................................................Kilometre
kPa.............................................................................................................. Kilopascal
m........................................................................................................................Metre
m3 /d...............................................................................................Cubic metre per day
MJ/m3 .................................................................................. Megajoule per cubic metre
mKB........................................................................................ Metres below Kelly Bar
MW..............................................................................................................Megawatt
NO2 ........................................................................................... Nitrogen dioxide (gas)
NOx ..................................................................... Oxides of Nitrogen (NO, NO2) (gas)
Orion ......................................................................................... Orion Oil Canada Ltd.
POB .....................................................................................Pressure Observation Well
ppm .................................................................................................... Parts per million
S.....................................................................................................................Standard
SAGD.........................................................................Steam Assisted Gravity Drainage
SARA..........................................................Saturates, aromatics, resins and asphaltenes
SO2 ...................................................................................................... Sulphur dioxide
STARS .............................Steam, Thermal and Advanced Processes Reservoir Simulator
THAI ................................................................................. Toe-to-Heel Air Injection
TOB .............................................................................. Temperature Observation Well
TRS...........................................................................................Total Reduced Sulphur
VAPEX ............................................................................... Vapour Extraction Process
C......................................................................................................... Degree Celsius

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
TOC 1

EXECUTIVE SUMMARY
Orion Oil Canada Ltd. (Orion), a wholly owned subsidiary of Petrobank Energy and Resources
Ltd., plans to construct and operate the WHITESANDS Experimental Pilot Project (the Project).
The Project will be located on Orions oil sands lease (Agreement 7400010012) approximately 13
km west of Conklin, Alberta. The Project will be designed to evaluate the THAI (Toe-to-HeelAir-Injection) in-situ combustion process under actual field conditions. It will produce up to 300
m3 /d of partially upgraded oil, referred to as THAI OIL. Orion has the right to use the patented
THAI process.
This document provides the design basis for the WHITESANDS Experimental Pilot Project.
THAI is a revolutionary combustion technology for the in-situ recovery of bitumen and heavy
oil by using a vertical air injection well at the toe of a horizontal production well. During this
process a combustion front is created where approximately 10% of the bitumen in the reservoir is
combusted. This generates heat, which reduces the viscosity of the bitumen and enables it to flow
by gravity drainage to horizontal production wells. The combustion front sweeps the oil from the
toe to the heel of the horizontal producing well efficiently recovering an estimated 80% of oil in
place while upgrading the crude oil in-situ. The process has been extensively tested in laboratory
physical models and its potential at a field scale confirmed through numerical simulations.
The major advantages and benefits of the THAI process include:
lower capital and operating costs,
significantly higher recovery potential than current in-situ processes,
minimal use of natural gas and fresh water,
lower greenhouse gas emissions,
production of partially upgraded crude oil (THAIOIL),
potential to operate in thinner and deeper reservoirs than steam-based processes, and
potential application as a steam follow-up process.
The design provides for a wide range of flexibility in the operation appropriate for the worlds
first field pilot of the THAI process. The pilot is aimed at demonstrating the commercial
viability of the technology in a safe manner with a robust approach to the design. The pilot will
have three vertical/horizontal well pairs plus several temperature and pressure observation wells.
Data collection is a major objective of the pilot with an array of observation wells and facility
instrumentation to obtain production and analytical compositional measurements. The pilot will
have a small foot print and will be designed and operated to meet or exceed all environmental
regulations. The pilot facilities will be designed for an anticipated five-year operating life, with
start-up planned for late 2004 or early 2005.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
1-1

In addition to the WHITESANDS regulatory application, information on Petrobank and Orion is


provided on Petrobanks website at www.petrobank.com.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
1-2

INTRODUCTION

2.1

PURPOSE OF THE DESIGN BASIS MEMORANDUM


The purpose of the Design Basis Memorandum (DBM) is to assemble in one document the
objectives, guiding principles, risks/uncertainties, preliminary design, and operations plan for the
WHITESANDS Experimental Pilot Project (the Project).
The DBM provides:
the basis to support the cost estimate and preliminary schedule ,
the basis for the final design and execution planning of the Project, and
a summary for potential partners and financial institutions.
Norwest Corporation provided the engineering design and support team. This included:
J. Aiello, P.Eng., Project Advisor (Norwest Corporation)
R. Luhning, Ph.D., P. Eng., Project Manager (Arkril Enterprises)
L. McKeary, RET, Surface Facilities (McKeary Technical Services Ltd.)
J. Donnelly, Ph.D., P.Eng., Surface and Subsurface Interface (Marengo Energy Research
Limited)
W. Boddy, P.Eng, Drilling and Completions (Marlex Engineering Ltd.)
S. Crevolin, P.Eng, Surface Facilities (Petrotherm)
Z. Lukacs, P.Eng, Schedule Coordination (Norwest Corporation)
B. Noble, M.A., Regulatory Management (L.B. Noble Resource Management Limited)
AXYS Environmental Consulting Ltd. coordinated the environmental design team for the Project.
This included:
K. Venner, Ph.D., Technical Leader, AXYS
H. McGrath, M.Sc., P.Ag., Terrain and Soils, AXYS
M. Davies, M.Sc., Air Quality, RWDI West Inc.
C. Serdula, M.Sc., Air Quality, RWDI West Inc.
G. McClymont, M.Sc., P. Geol., Groundwater, Westwater Environmental Ltd.
J. Saldana, Groundwater, Westwater Environmental Ltd.
Orion Oil Canada Ltd. staff provided input on objectives, guiding principles, reservoir simulation,
project execution, geology, geophysics and site selection. This included:
C. Bloomer, P. Geol., Project Executive
T. Pantalone, P. Geol., Geology
R. Baird, P. Geoph., Geophysics
C. Ayasse, Ph.D., Director, Technology, Reservoir Numerical Simulation.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
2-1

2.2

PROJECT OVERVIEW
Orion Oil Canada Ltd. (Orion) , a wholly-owned subsidiary of Petrobank Energy and Resources
Ltd., plans to conduct a field pilot of the THAI (Toe-to-Heel-Air-Injection) in-situ combustion
oil sands technology. The Project will be located on Orions oil sands leases approximately 13
km west of Conklin, Alberta (see Figure 2-1).
The surface facilities and access roads for the Project will be located in Sections 12 and 13,
Township 77, Range 9, west of the 4th Meridian (see Figure 2-2). The reservoir target is wholly
contained within Section 12. The Project is in an area that has been extensively explored and
developed for natural gas and oil sands. The Leismer Gas Plant (BP Energy Canada) is located
approximately 3 km north of the development area. Delineation drilling on the site in November,
2003 confirmed the presence of a high quality oil sands reservoir in which to conduct the Project.
A summary of the geology and oil sands resource in the development area is provided in
Appendix A. A separate report (Resource Assessment WHITESANDS Project Area, January,
2004, Fekete Associates) on the results of the 2003 drilling program is also available.
Three pairs of vertical air injector and horizontal producer wells will each have a peak productive
capacity of 100m3 /d of partially upgraded bitumen, hereinafter referred to as THAIOIL.
Production will be treated onsite and produced water will be disposed of via deep wells.
Additional information on the production process is found in Section 3. THAIOIL will be
stored on site in tankage and trucked to a market outlet.
THAI is an innovative new combustion process for the in-situ recovery of bitumen, which
combines a vertical air injection well with a horizontal production well as shown in Figure 2-3.
During this process a combustion front is created where a portion of the bitumen in the reservoir
is combusted. This generates heat, which reduces the viscosity and partly upgrades the bitumen
enabling it to flow, by a combination of induced pressure gradient and gravity drainage, to the
horizontal production well. The combustion front sweeps the oil from the toe to the heel of the
horizontal producing well efficiently recovering an estimated 80% of bitumen in place. The
process has been extensively tested in laboratory physical models and its potential at a field scale
confirmed through numerical simulations. Orion has the right to use the patented THAI
process.
The potential advantages/benefits of the THAI process include :
lower capital and operating costs,
significantly higher recovery potential than current in-situ processes,
minimal use of natural gas and fresh water,
lower greenhouse gas emissions,
production of partially upgraded crude oil,

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
2-2

potential to operate in thinner and deeper reservoirs than steam-based processes, and
potential application as a steam follow-up process.

The preliminary project schedule is illustrated in Figure 2-4. A preliminary detailed schedule is
provided in Appendix B. Pending regulatory approval, site preparation and delineation drilling is
expected to begin in early 2004 with start-up scheduled for late 2004. The initial phase of the
Project is anticipated to last five years with the potential for a second phase if operating results
warrant.
FIGURE 2-4
PRELIMINARY PROJECT SCHEDULE
2003

2004

2005 - 2010

Design Basis Engineering


Public Consultation
AEUB/AENV Application
AEUB/AENV Approval
Construction Permitting
Detailed Engineering
Site Preparation
Production Drilling
Plant Construction
Commissioning
Start-up
Operation: 5 Years

2.3

PROJECT OBJECTIVES
The purpose of the Project is to evaluate the THAI process under actual reservoir conditions, in
commercial length horizontal wells, in order to advance the technology to commercial
application. The pilot will generate an array of technical, environmental and economic
information on which to plan and evaluate a commercia l scale operation.
The principle objectives of the pilot are to:
Understand the dynamics and operating characteristics of the process,
Obtain information on the THAIOIL, water and gas production rates,
Enhance the numerical simulation model using field data,
Obtain information on the characteristics of the produced THAIOIL to evaluate its
commercial value,
Obtain information on produced water to evaluate its corrosion characteristics and
recycle potential,

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
2-3

2.4

Obtain information on produced gases to evaluate their corrosion characteristics and


emission management requirements,
Obtain information in support of a commercial scale project design, and
Obtain additional information on capital and operating costs for a commercial scale
project.

GUIDING PRINCIPLES AND KEY ASSUMPTIONS


The Project has been developed based on the following guiding principles:
operational safety is number one priority,
development and operation have minimal environmental impact,
proven technology and conventional equipment utilized in areas of limited operational
risk,
robust design applied in critical areas relating to process success,
capital and operating costs minimized through innovation,
design is consistent with anticipated five-year operating life,
rental or leased equipment used where appropriate, and
all regulatory requirements met or exceeded.

2.5

RISK MANAGEMENT
All experimental projects have a number of technical, operational, execution and business risks
and uncertainties. The challenge is to accurately identify and rank these at each stage in the
project development to determine the significance and undertake appropriate design mitigation or
management actions. Several of these will be resolved during the detailed engineering design
stage. Others will have to be managed during the operational phase of the Project. A preliminary
assessment of the design and operational risks is provided in Section 9.

2.6

PROJECT EXECUTION
The preliminary detailed schedule shown in Appendix B lists the major project execution
activities required to take the Project through to start-up. During detailed engineering a Project
Execution Plan (PEP) will be prepared to address these activities in more detail and develop plans
for:
contracting and procurement,
QA/QC,
modularization,
staffing,
change management,
safety systems,
environmental protection systems,

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
2-4

regulatory compliance,
start-up and commissioning, and
operation.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
2-5

THAI RECOVERY PROCESS

3.1

PROCESS OVERVIEW
The THAI recovery process for the pilot will be a dry combustion process operated at a high
temperature in the reservoir to promote in-situ upgrading of the bitumen and avoid the need to
inject fresh water with the air. In the event that production rates are too low or there is a need to
lower the combustion front temperature, water can be injected with the air. Steam may be
injected to control oxygen levels if necessary.
The THAI process operates with an array of parallel horizontal production wells (producers)
placed near the base of the oil sands zone. Vertical air injector wells (injectors) are drilled with
an offset from the toe of the producers and are opened at the top of the pay zone as shown in
Figure 3-1. A near-well steam preheat is then conducted to establish communication between the
injector and the producer. When air is injected, ignition occurs and a combustion front develops.
The front is quasi-vertical and remains vertical for the entire duration of the reservoir
exploitation. This ensures that a high-oxygen flux is maintained and only high-temperature
oxidation occurs.

Toe

Cold Heavy
Oil

Production Well

Mo
bile
Oil
Zon
e

Air
Co
mb
us
Co
tion
ke
Zo
Zo
ne
ne

Vertical Injection Well

FIGURE 3-1
THAI P ROCESS SCHEMATIC

Heel

Hot combustion gases contact the bitumen ahead of the coke-burning (combustion) zone and heat
the bitumen to over 400C. The high temperatures, in the presence of reservoir clays , cause
thermal cracking and upgrading of the bitumen by 7 to 10 API gravity to form THAIOIL. The
PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-1

hot, lighter cracked oil, reservoir water and combustion gases drain downward into the horizontal
well for transmission directly to the surface by gas lift. Some bitumen warmed by conductive
heating ahead of and behind the combustion front also drains into the horizontal well. Up to
ten percent of the bitumen, the heavier, higher boiling point fraction, is left behind on the sand
matrix and becomes the combustion fuel as the burning front advances. In addition to bitumen,
the only other raw materials consumed by the THAI process are the associated gases and
interstitial water in the oil sands formation. The reservoir design parameters are provided in
Table 3-1.
TABLE 3-1
R ESERVOIR D ESIGN PARAMETERS
Steam
Preheat
Period
(months)

Water
Rate
3
(m /d/well)

Frontal
Advance
Rate
(m/d)

Peak
Temperature
(C)

Temperature
in Swept Zone
(C)

Wellbore
Temperature
(C)

Gas/oil
Ratio
3
3
(m /m )

20

0.28

>600

215260 after
5 years

200300

944

Injection Forecast
During the start-up period, steam requirements will be 500 m3 /d/well pair. Each well pair will be
treated separately for approximately a three-month period. Computer simulation studies indicated
an optimum air injection rate of 85,000 Sm3 /d per injector, with a well spacing of 100 m and a
pay thickness of 20 m.
Production Forecast
Total gas production is expected to be very close to the air injection rate of 85,000 Sm/d, because
the combined volume of the generated N2 , CO and CO2 and hydrocarbon gas will be
approximately equal to the volume of oxygen consumed. The anticipated steady state production
temperature is expected to average 250C.
THAIOIL production is forecast to commence at 20 m3 /d/well and increase to 90 to 100
m3 /d/well over a five-year period. The water cut is expected to be 23 percent.

3.2

RECOVERY STRATEGY
The THAI recovery process strategy consists of three stages:
steam preheat,
combustion ignition, and
steady-state combustion

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-2

Steam Preheat
The purpose of the steam preheat is to ensure that there is a heated communication channel
between the vertical injection and horizontal production well. The steam preheat also ensures
that the production well is heated through its entire length so that mobilized bitumen does not
cool and plug the well.
The steam preheat occurs in three steps:
1. Steam injection, accompanied by circulation into the horizontal production well at below
fracture pressure, will begin with injection of steam into the long tubing landed near the
toe of the horizontal production well. The condensed steam and mobilized bitumen will
be produced via short tubing landed a short distance above the liner in the horizontal
well. The steam circulation will continue with pressure/rate cycles to promote bitumen
production.
2. The total section of reservoir around the vertical injection well must be heated to a high
enough temperature (100C) for spontaneous ignition to occur upon subsequent injection
of air. Following the development of heat communication between the toe of the
horizontal well and the vertical injection well, steam injection from the heel of the
horizontal well will end and continuous injection of steam via the vertical well into the
toe of the horizontal well will be conducted for a period of time until the horizontal well
temperature rises to steam temperature less 50C. Bitumen, liquid water and steam will
be produced at the heel end of the horizontal well.
3. In preparation for ignition, steam will be injected into the upper part of the reservoir to
create a heated volume, approximately 10 m in radius around the well at the top of the
reservoir, which will become linked to the lower steam heated area and the horizontal
well.
Combustion Ignition
At the conclusion of steam preheat, air will be injected at up to 85,000 m3 /day, at below
formation fracture pressure, through the upper screens of the vertical well to ignite the reservoir
and initiate the THAI recovery process. The objective is to ignite the reservoir without
damaging the vertical injection well while avoiding fracturing the reservoir. Any flow-back of
gas or fluid into the injection well is to be avoided as this has a high probability of drawing
combustion fuel into the well and damaging or destroying the well. Data from a large number of
combustion tube tests indicates that spontaneous ignition of Athabasca bitumen will readily occur
at temperatures exceeding 100C. Ignition will be confirmed from the analysis of the produced
gas. Once ignition is confirmed, the air injection rate will be gradually brought up to the design
rate. Once at design rate, it is expected that the combustion front will move progressive ly from
the toe toward the heel of the horizontal production well. If high temperatures in the production
well occur or if there are difficulties in distributing heat along the well, hot water or steam may be
injected along with the air.
PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-3

The steam stimulation and ignition process will be conducted in sequence for the three THAI
well pairs in order to learn from each preceding well pair how to improve the start-up and
production methods for the next pair.
Steady state combustion
Steady state combustion will be maintained throughout the projected five-year life of the wells. It
is anticipated that the air injection rate will be constant in order to obtain steady-state data for
computer model history-matching.

3.3

PLANNED AND EMERGENCY SHUTDOWN AND RESTART


Through the pilot life the production operations will be shutdown in a pla nned manner for such
things as yearly maintenance of facilities and special tests. The operations may also need to be
shutdown due to emergency situations such as detection of high levels of oxygen in the produced
gas. The main concern is the manner in which the wells are shutdown and restarted so as not to
damage the wells or impede restarting of the THAI process.
The THAI process is driven by air injection. When air injection is stopped, the advancement of
the combustion front will slow and flow will continue until the bottom hole pressure is not
sufficient to lift the fluids to surface. For the air injection wells, the main concern is to eliminate
the possibility of back flowing of combustion material into the well. A constant pressure will be
kept on the well to prevent influx of hot reservoir material that could damage the well or by influx
of sand that could plug the well. This will be accomplished by injecting steam or hot water (to
avoid thermal shock) to prevent the flow back and then filling the well with water to prevent
inflow.
The horizontal production wells should be shut down under pressure to eliminate the possibility
of oxygen entering the well and causing damage by combustion in the wellbore. The horizontal
well design has the capability to allow the well to be circulated to flush out material that may
have settled in the well or to reheat the well as necessary if shut down for an extended period.
The main risk, which is unique to an in-situ combustion project, is the possibility of high oxygen
content in the produced gas. This could lead to risk of fire or explosion in the surface facilities.
For this reason the produced gases will be monitored continuously for oxygen content. In the
event that oxygen content becomes excessive, the rate of air injection will be reduced or stopped
and the well may be shut in.
High temperature in the horizontal production wells could lead to production problems. The
temperature distribution in the production wells will be monitored continuously using
thermocouples placed strategically along the wells. If excessive temperature is observed, hot

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-4

water or steam will be injected to cool the wells. In addition, the air injection rate may be
reduced.

3.4

3-D CELL TEST RESULTS


In June 2003, a THAI test in the University of Bath 3-D Cell was commissioned by Orion. The
Cell contained 60% saturation of Wolf Lake bitumen. The results are summarized in Table 3-2.
The THAI process operated effectively even at low oil saturation, producing substantially
upgraded oil with high reservoir sweep.
TABLE 3-2
LABORATORY PHYSICAL MODEL R ESULTS WITH W OLF LAKE BITUMEN
Process
Dry in-situ combustion

3.5

Oil
Recovery
74%

Air:Oil Ratio
3

1650 Sm /m

Peak
Temperatures
500600C

Frontal Advance
Rate
1.2 m/d

NUMERICAL SIMULATION PREDICTIONS


The in-situ combustion version of the Computer Modelling Group (CMG) numerical simulation
model STARS was used for simulation modeling to generate the forecast for the Project.
The simulation had the following dimensions:
thickness = 20 m,
spacing = 100 m,
length = 500 m , and
grid sizes were 1.0 m, 2.5 m 2.5 m respectively.
Geological parameters from the nearby Kirby Lake Project (see Figure 2-1) reservoir , which
represent typical conditions in the area, were used. These parameters were consistent with the
results of the November 2003 drilling program on the Project site. Simulations were conducted to
assess the sensitivity of the process to:
start-up heating procedures,
air rate,
air injector location,
well length,
well spacing,
well diameter,
well perforations,
grid size, and
bottom hole pressure.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-5

Field Scale Numerical Simulations


The commercialization of the THAI process will be similar to that followed in the development
of SAGD and VAPEX. These processes began with laboratory-scale physical model tests
followed by computer simulation modeling of these results, and then by field-scale reservoir
simulation computer modeling, field piloting and finally commercial application. It is important
to note that many commercial-scale SAGD projects begin with a field pilot to test the process
performance in specific reservoirs.
The purpose of Orions numerical simulation work is to scale -up the process to reservoir
conditions and to develop a DESIGN model for the Project engineering team.
In 2001, Petrobank conducted the first field-level numerical simulation of the THAI process
using the CMG STARS thermal simulator. Studies have been completed to determine the
sensitivity of THAI to reservoir pay zone thickness, horizontal well spacing, horizontal well
length, horizontal well diameter, the frequency of sand screens in the horizontal well, reservoir
temperature, draw-down pressure, air injection rate, reservoir permeability, grid block size, startup procedures and a number of other key variables required for design of the field pilot. The
studies led to the Design Case, the basis for the THAI Project wells and facilities design.
Numerical Simulation Input Data
The reservoir parameters of the nearby Kirby Lake Project were used in the initial model runs
(Table 3-3). The model will be re-run in February 2004 using reservoir data from the Orion
November 2003 drilling program.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-6

TABLE 3-3
ORION NUMERICAL MODEL INPUT
Simulator
Components (8)
Grid size, m
Number of grids
Wells

Heterogeneity
Permeability
Porosity
Oil viscosity, cP
(bitumen)
Temperature, C
Reservoir pressure,
kPa

STARS 2003.1
water, bitumen, upgrade, methane, CO2 , CO/N2, oxygen,
coke
2.5 x 2.5 x 1.0
40,000 in element of symmetry (design model)
1 vertical steam injector for communication pre-heating, 1
vertical air injector, 1 discretized horizontal well with tubing
for well pre-heating.
Homogeneous
6.4 D (horizontal), 3.4 D (vertical) (Kirby Lake)
33 % (Kirby Lake)
340,900 @ 10C (Kirby Lake)
20 (WHITESANDS)
2600 (Kirby Lake)

Numerical Simulation Sensitivity Studies


Sensitivity studies were conducted with 100 m horizontal wells and a well spacing of 50 m,
looking at:
start-up procedures (steaming for inter-well communication),
pay thickness (20 m, 25 m),
permeability(vertical) (3.4 D, 1.0 D),
drawdown pressure (500 kPa, 1250 kPa, 4000 kPa),
grid block size (1 m x 1 m x 1 m), and
air injection rate (50,000 m3 /d, 75,000 m3 /d, 85,000 m3 /d, 100,000 m3 /d).
Sensitivity studies were conducted for 500 m horizontal wells using the following parameters:
well spacing (50 m and 100 m),
well diameter (152.4 mm, 177.8 mm), and
well completion (fully perforated, 50 % perforated).
Sensitivity to well length was tested at 50 m, 100 m, 250 m, 500 m and 750 m lengths.
In summary, the computer modelling confirmed on a field scale basis the observations in the
laboratory 3-D cell tests: the THAI process operated with a stable quasi-vertical combustion
front, generated high temperatures at the front, indicating high-temperature combustion and
showed complete utilization of the oxygen. Unique features were high oil rates and acceptable
wellbore temperatures.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-7

3.6

WATER DISPOSAL
The produced water generated by the Project will be separated from the THAIOIL at the plant
site and then disposed of into the Clearwater Sandstone via deep well injection. The amount of
produced water will depend on whether the continuous co-injection of steam (wet combustion)
is required for process control purposes. With normal dry combustion, the produced water will
consist of condensed start-up steam (first year only) and interstitial water from the reservoir.
With the wet combustion method, the produced water will consist of condensed start-up steam
(first year only), interstitial reservoir water and the optional injected steam as noted above. The
estimated disposal volumes for Year 1, Year 2 and Years 3 to 5 are 244,550 m3 , 229,950 m3 and
251,850 m3 , respectively, with approximate disposal rates of 670 m3 /d, 630 m3 /d and 690 m3 /d,
respectively. The recycle of produced water is not required because the Project will use less than
500,000 m3 /y of fresh water. The pilot will collect data on produced water quality to allow the
design of treatment facilities for reuse in future commercial operations or for export off-site to
other potential water users.

3.7

PRODUCED GAS
The anticipated produced gas composition is provided in Table 3-4. Produced gas will be cooled
to 80C and vented.
The vent stack will be 75 m in height and will be equipped with a chemical sweetener to remove
H2 S. The vent stack will discharge in-situ combustion gases that are entrained within, and
removed from, the produced THAIOIL stream. While these combustion product gases will be
comprised primarily of N2 , CO2 , and CO, they are also expected to contain trace amounts of
hydrocarbons and other compounds. Because of the high N2 , CO2 , and CO content (~97 to 98%
on a dry basis), the heating value of the vent gas is low. The maximum H2 S content is expected
to be 150 ppm (on a dry basis). Following sweetening, the maximum H2 S content will be less
than 10 ppm. Representative carbon disulphide (CS2 ), benzene (C6 H6 ), and ethylene (C2 H4 )
emission values are also provided in the table to account for the other TRS (Total Reduced
Sulphur) compounds and other hydrocarbon species that are of potential interest. Table 3-5
provides the preliminary parameters for the vent and flare stack design.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-8

TABLE 3-4
PRODUCED GAS COMPOSITION
Compound
CH4
C2H4 (Ethylene)
C2H6
C3 H6
C3H8
C4H10
C5H12
N2
CO2
CO
O2
H2
SO2
H2O
H2S
C6H6 (Benzene)
CS 2
3
Heating value (MJ/m )

Dry Basis

Wet Basis

(mole %)
0.96
0.01
0.04
0.03
0.08
0.07
82.05
12.12
3.04
1.45
0.12
0.01
0.00

(mole %)
0.88
0.01
0.04
0.03
0.07
0.06
74.99
11.08
2.78
1.33
0.11
0.01
8.60

(ppm)
150
11
13
0.91

(ppm)
137
10
12
0.83

Note: A dash (-) indicates that the parameter is not applicable.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-9

TABLE 3-5
PRELIMINARY FLARE AND V ENT STACK PARAMETERS AND EMISSIONS

6168879
484286
13.0
0.152
425
13.72
1.445
25
1000
1273
0.27
-3
5.6 10
-5
6.5 10

Vent Stack
(Wet Basis)
6168851
484315
75.0
0.203
277,000
80
353
121.2
75.1
0.869

Flare Stack
Stack Location
Stack Location
Stack Height
Stack Diameter
Gas Flow Rate
Effective Stack Height
Pseudo Stack Diameter
Fraction Heat Radiated
Stack Exit Temperature
Stack Exit Velocity
SO2 Emission Rate

(UTM m N)
(UTM m E)
(m)
(m)
3
(m /d)
(m)
(m)
(%)
(C)
(K)
(m/s)
(kg/d)
(g/s)

CO Emission Rate

(kg/d)
(g/s)

9124
105.6

NO X Emission Rate

(kg/d)
(g/s)

0.41
0.0048

H2S Emission Rate


(based on 10 ppm dry basis)

(kg/d)
(g/s)

>4
>.05

CS 2 Emission Rate

(kg/d)
(g/s)

10.7
0.124

Ethylene Emission Rate

(kg/d)
(g/s)

32.8
0.380

Benzene Emission Rate

(kg/d)
(g/s)

9.2
0.106

Note: A dash (-) indicates that the parameter is not applicable.

3.8

RESERVOIR CONTROL PARAMETERS


There are two basic control parameters for the THAI process: the rate and pressure of air
injection and the back pressure maintained on the production well.

3.9

PRODUCTION CONTROL METHOD AND WELL PROTECTION


The production control methods relate to the manner in which the injection and production wells
are operated to prevent the wells from being overheated or burned, clogged by deposited bitumen
or having live oxygen in the wells. The control methods are as follows:
Adjust the air injection and production rates so that the horizontal production well is
covered by a pool of liquid oil that prevents oxygen from enterin g.
Coke will be deposited in the well immediately behind the burn front to provide a gas
tight seal to keep air out of the well.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-10

3.10

The coke plug will be continuously removed by burning as the front advances and new
coke will be deposited. Oxygen must not be allowed to enter the wellbore ahead of the
burning front as this will overheat the wellbore and also reduce production rates.
Should the pool of oil or coke plug not adequately restrict the entry of oxygen, water
and/or steam can be injected at the lower perforations of the vertical injection well to
restrict oxygen from entering the horizontal production well.
Should temperatures in the horizontal well become excessive, steam and/or water can be
circulated through the well using the long tubing to reduce the temperature. In this
regard, it is important that the long tubing be regularly pulled back to a point near the
combustion front so that the tubing will not become stuck in the wellbore because of coke
deposits. Wellbore temperatures measured by the thermocouples will be used to locate
the position of the combustion front. The long tubing will also be available to plug-off a
section of the wellbore in case of screen failure or to isolate a tail section for any reason.
If the oxygen content of the production gas exceeds a level (for example 1-3%) that may
pose a possibility of explosion or combustion in production lines, the air injection will be
reduced or stopped.

RESERVOIR RECOVERY CONFORMANCE METHOD


Part of the objective is to have a regular conformance of the recovery zone so that as full a
volume of the reservoir as possible will be swept by the THAI process for high ultimate
recovery.
In addition to the parameters described above, it may be necessary to occasionally inject water or
convert to wet combustion (co-injection of air and steam) to achieve the desired oil rates and
recovery of the original oil in place. The array of observation wells described earlier will provide
ongoing data to monitor the conformance of the recovery process. This conformance data will be
essential for designing the placement of follow-up horizontal wells.

3.11

PRODUCED AIR/GAS CONTROL


The air/produced oil ratio is a critical factor in the THAI process economics. The design ratio
is 85,000 m3 /day/well of air for 100 m3 /day/well oil at full production.
Oxygen by-passing the combustion front or indications of starved combustion by high CO
concentration will indicate that the injection/production operations need to be adjusted.

3.12

DATA COLLECTION REQUIREMENTS- RESERVOIR


The data collection for the reservoir is aimed at monitoring and controlling reservoir conditions
mainly pressure and temperature. The observation well data collection will be focused on the
conformance and spread of the combustion recovery through the reservoir. The spread of the

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-11

recovery between the horizontal production wells and outside of the unconfined THAI pilot
pattern will be key to the design of the well spacing to be used for commercial operations.

3.13

DATA COLLECTION REQUIREMENTS SURFACE


The surface data collection is aimed mainly at measurements of the volume and composition of
injected and produced material (e.g. injected air, produced THAIOIL, produced water, and
produced gas). The surface measurements will provide the basic data for calculating the
economics of the THAI process, controlling the THAI process and for the design of
commercial facilities. Environmental monitoring, such as vent stack analyses, is mandated.
These will also be used to monitor the efficiency of the process.

3.14

CORROSION
The THAI process will produce CO2 and SO 2 in a wet environment, so corrosion can be
expected. The minimum production temperature in the horizontal well is expected to be 250C.
At temperatures over 190C all water will be in the vapour phase. The water in the production
well is expected to be as steam at the production temperature, but corrosion will still be a concern
as the production cools as it passes through the horizontal production well. Turbulent flow in the
horizontal well is expected to coat the wellbore with bitumen (the metal is oleophilic), which may
reduce the corrosive effect of the acids.
In the surface facilities, the steam will condense upon cooling and the combination of liquid
water, CO2 and SO 2 can be expected to cause corrosion. The timely separation of produced
THAIOIL from produced gas and neutralization of the fluids may reduce the opportunity for
corrosion. The coating of the insides of wells and vessels by the produced THAIOIL will help
to provide corrosion protection.
Orion has commissioned a corrosion study by Dr. Bill Shaw at the University of Calgary. The
program is to evaluate the performance of a variety of material compositions under a range of
temperature, pressure and fluid conditions that may be experienced in the THAI process. It is
expected that the study conditions will represent the worst case scenario by exposing bare metal
to the potentially corrosive fluids. The program will define the potential severity of corrosion and
identify design or operating solutions. The results of this study will be available for consideration
during the detailed design stage of the Project.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
3-12

WELL DESIGN AND COMPLETIONS

4.1

WELL PATTERN AND LOCATIONS


The pilot will have three horizontal production wells , three vertical air injection wells (one at the
toe of each horizontal well) and 19 observation wells. The locations are shown in Figure 4-1.

4.2

VERTICAL INJECTION WELLS


The vertical well at the toe end of each horizontal production well has two purposes: 1) to inject
steam to pre-heat the reservoir as part of the THAI start-up process, 2) to inject air for the
combustion process.
In the preheat operation 500 m3 /d of 80% quality steam will be available at a wellhead pressure of
8,000 kPa at 295C. For the combustion operation, air injection will be injected at up to 85,000
m3 /d well at a maximum wellhead pressure of 8,000 kPa and a temperature of 175C.
The vertical injection wells are placed 15 m past the end of the last screen liner joint
(approximately 17 m from the end of the horizontal liner) and 3 m off the line of the horizontal
well as shown in Figure 4-2. This exact location (15 m) was chosen by numerical simulation as
optimal for the start-up of the combustion process. The placement of the well 3 m off line was to
avoid unintentionally intersecting the horizontal well when drilling the vertical well.
The three vertical injection wells will be drilled and completed as shown in Figure 4-3. The
material list for each injection well is as follows:
Surface Casing:
Production Casing:
Screen Section:
Tubing:
Tubing:
Packer:
Packer:
Wellhead:

244.5 mm, 48.1 kg/m, H-40, Round Thread Conn., length 150 m
177.8 mm, 34.3 kg/m, L-80, VAM-SW Conn., length 420 m
177.8 mm x 3 m length, 316LSS Rib with 0.006 open, 2 required
114.3 mm, 18.8 kg/m, J-55, Premium Conn., length 400 m
60.3 mm, 6.85 kg/m, J-55, Premium Conn. , length 410 m
177.8 mm x 120.6 mm retrievable, thermal element
177.8 mm x 101.6 mm retrievable, thermal element
working pressure 14,800 kPa @ 345C

The completion is designed to inject air at the top of the McMurray zone and provide for the
option of injecting steam or hot water at the bottom of the zone if required for temperature control
in the horizontal well and or prevention of air breakthrough to the horizontal well. The design
pressure rating for the injection wellhead is 14,800 kPa at 345C. A wellhead drawing is
provided in Figure 4-4.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
4-1

4.3

HORIZONTAL PRODUCTION WELLS


Each horizontal production well is expected to produce up to 100 m3 /d THAIOIL with 30 m3 /d
water and 85,000 m3 /d combustion gas at a temperature of 250C.
The wells will be drilled and completed as shown on Figure 4-5. The 500 m horizontal sections
will have a 177.8 mm liner with wire-wrapped screens. A 73.0 mm endless tubing string will be
landed at the toe end for circulation and production capability. An 88.9 mm endless tubing
landed at the heel end will be the primary production string. A 38.1 mm endless tubing string
landed near the toe will contain up to eighteen thermocouples for temperature monitoring. The
material list for each production well is as follows:
Surface Casing:
Intermediate Casing:
Horizontal Casing:
Screen Section:
Tubing-Heel:
Tubing-Toe:
Tubing Thermocouple :
Thermocouples:
Wellhead:

339.7 mm, 71.4 kg/mm, H-40, Round Thread Conn., length 150 m
244.5 mm, 59.5 kg/m, L-80, VAM-SW Conn., length 550 m
177.8 mm, 38.7 kg/m, L-80, VAM-SW Conn., length 535 m
177.8 mm, 316LSS Rib with 0.008 open
73.0 mm, 4.77 mm, WT, QT700, length 1050 m
88.9 mm, 4.77 mm, WT, QT700, length 500 m
38.1 mm, 2.77 mm, WT, QT700, length 1020 m
Underground Type K, 18 measuring points, cable length 1020 m
working pressure 14,800 kPa @ 345C

The intermediate and horizontal casings require premium connections such as the VAM-SW
shown above. Another equivalent premium connection may be used depending on the
determination of the casing supplier.
Produced fluids are expected to flow to the surface. If lift assist is required during start-up, then
steam can be injected at the toe end through the 73.0 mm tubing, or gas lift can be implemented
by injecting natural gas down the intermediate casing for return up the 88.9 mm production
tubing. The wellhead is designed for top access to the 88.9 mm tubing for swabbing or pumping.
Figure 4-6 shows the horizontal wellhead design. Pressure rating is 14,800 kPa at 345C.
Provision has been made for top entry into the 73.0 mm and the 88.9 mm tubing strings and the
ability to pull the 73.0 mm tubing back as the combustion front advance from toe to heel.

4.4

OBSERVATION WELLS
Seventeen temperature observation wells and two pressure observation wells are planned. Their
locations relative to the horizontal production wells and the vertical air injectors are shown on
Figure 4-1.
The observation wells numbered one through nine will be drilled first and used to position the
horizontal sections and vertical air injectors. They will then be completed as temperature

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
4-2

measurement wells as shown on Figure 4-7. Eleven thermocouples will be placed through the
production zone at 2 m spacing and five thermocouples will be placed above the production zone
at 10 m spacing. The material list for each observation well is as follows:
Surface Casing:
Production Casing:
Tubing:
Thermocouples:

177.8 mm, 25.3 kg/m, H-40, Round Thread Conn., length 150 m
114.3 mm, 14.1 kg/m, J-55, Round Thread Conn., length 430 m
60.3 mm, 6.99 kg/m, J-55, EUE, 8R, length 420 m
Underground Type K, 16 measurement points, cable length 420 m

The temperature observation wells (TOBs) numbered one through five will be completed as
shown in Figure 4-8. They will have the same arrangement of thermocouples as the temperature
measurement wells. The temperature observation wells numbered six through eight are planned
for the future. The material list for each TOB well is as follows:
Surface Casing:
Tubing:
Thermocouples:

114.3 mm, 14.1 kg/m, J-55, Round Thread Conn., length 150 m
60.3 mm, 6.99 kg/m, J-55, EUE, 8R, length 430 m
Underground Type K, 16 measurement points, cable length 420 m

Two pressure observation wells are planned. One will be drilled and completed at the start of the
Project (POB1), and the other (POB2) will be added in the future. They will be completed as
shown on Figure 4-9. Pressure will be measured at the top of the Wabiskaw Formation and at the
top of the lower Clearwater Shale. The placement of perforations will be determined during
detailed engineering, giving due consideration to the relative location of the water disposal wells.
The material list for each POB well is as follows:
Surface Casing:
Production Casing:
Tubing:

4.5

177.8 mm, 25.3 kg/m, H-40, Round Thread Conn., length 150 m
114.3 mm, 14.1 kg/m, J-55, Round Thread Conn., length 350 m
60.3 mm, 6.99 kg/m, J-55, EUE, 8R, length 320 m

WATER DISPOSAL WELLS


The produced water generated by the Project will be separated from the THAIOIL at the plant
site and then disposed of into the Clearwater Sandstone at a depth of approximately 325 m. The
amount of produced water for disposal will depend on whether the dry combustion or wet
combustion method is used as outlined in Section 3.6.
Water for disposal into the disposal wells will come from condensed steam during the start-up
procedure, produced water during the oil production procedure and domestic requirements.
670 m3 /d water during start-up total for three wells , and
690 m3 /d water during the oil production operations total for three wells based on the wet
combustion method.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
4-3

Water disposal wells will be completed as shown on Figure 4-10. Surface casing will be set 25 m
into the Clearwater Sandstone with thermal cement to surface. Production casing will be set
through the Clearwater Sandstone with thermal cement to surface. Two or more disposal wells
may be required depending on injectivity test results. The material list for each disposal well is as
follows:
Surface Casing:
Production Casing:
Tubing:
Packer:

4.6

244.5 mm, 48.1 kg/m, H-40, Round Thread Conn., length 320 m
177.8 mm, 29.8 kg/m, J-55, Round Thread Conn., length 335 m
73.0 mm, Fibreglass, length 325 m
177.8 mm x 73 mm

WATER SOURCE WELLS


There are plans for two water source wells as necessary to meet process water needs.
expected water source zone is the Empress at an estimated depth of 145 m to 155 m.

4.7

The

SURFACE REQUIREMENTS (D RILL PADS , ROADS, MUD DISPOSAL )


The drilling pads and roads will be integrated into the Project surface facility plan. Mud disposal
and borrow pits are available in the area.

4.8

LIFT SYSTEM
The production lift will be provided by the combustion gas flow with the THAIOIL/water
production. The minimum gas/liquid ratio will be 650. The down hole pressure will be
maintained at a minimum of 4000 kPa to ensure sufficient lift pressure. Provision for a gas lift
system should be incorporated into the detailed design.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
4-4

177.8mm SURFACE CASING


Set at 150mKB. Thermal Cement to Surface
114.3mm CASING
Set at 425mKB. Thermal Cement to Surface
60.3mm TUBING
Thermal Cement To Surface
Inside and Out
THERMOCOUPLE CABLE

5 TEMP POINTS OVER 50m


( 10m INTERVALS )
c

TOP OF M MURRAY ZONE


400mKB

11 TEMP POINTS OVER 20m


( 2m INTERVALS )

BASE OF McMURRAY
420mKB

114.3mm SURFACE CASING


Set at 150mKB. Thermal Cement to Surface

60.3mm TUBING
Set at 425mKB. Thermal Cement To Surface
Inside and Out

THERMOCOUPLE CABLE

5 TEMP POINTS OVER 50m


( 10m INTERVALS )
c

TOP OF M MURRAY ZONE


400mKB

11 TEMP POINTS OVER 20m


( 2m INTERVALS )

BASE OF McMURRAY
420mKB

177.8mm SURFACE CASING


Set at 150mKB. Thermal Cement to Surface

114.3mm CASING
Thermal Cement to Surface
60.3mm TUBING

TOP OF CLEARWATER SAND

PERFORATIONS

PACKER

TOP OF WABISKAW ZONE

PERFORATIONS
TOP OF Mc MURRAY ZONE
400mKB

SURFACE FACILITIES DESIGN

5.1

FACILITIES OVERVIEW
Site access will be via an all-weather road, which will intersect the BP well access road to the gas
plant about 2 km northwest of the Project site (Figure 5-1).The surface facility will consist of
connections to the three injection wells and three production wells, a steam generation plant, an
air compression plant and a production treating facility. Plot plans of the facilities are shown in
Figures 5-2 and 5-3.
As shown in the Process Flow Diagram (PFD) (Figure 5-4), the production consisting of
THAIOIL, water and gas will flow directly from the wellheads to the production treatment
facility. The facilities are designed on the basis of the predictions provided in Section 3.4. The
block Process and Instrument Diagram (P&ID) corresponding to the PFD is shown in Figure 5-5.
The first element in the production facility is a wellhead separator. This provides damping for
production slugs and separates the produced gas from the liquids.
The produced liquids are cooled to an operating temperature (to approximately 90C) acceptable
for separating partially upgraded bitumen and water. The liquid production (total fluid and water
cut) of each production well will be metered. The metered data from each well will be reconciled
with THAIOIL sales volumes and the metered produced water volumes.
The produced gas will be cooled to approximately 80C, passed through a liquid knockout vessel
and then vented to the atmosphere through a stack. The vented gas from each production well
will be metered and analyzed for composition. A gas sweetening unit will be installed and
operating at all times.
Water and hydrocarbons condensed from the produced gas will be combined with the other
produced liquids. The water will flow to the produced water tanks and ultimately be sent to deep
well disposal. As the production wells will have a screened liner, the amount of produced solids
is expected to be small; it will be periodically removed from the treater and tankage and disposed
of in an environmentally acceptable manner.
THAIOIL will flow to production tanks from where it will be trucked to sales. Tank gauging
will be used to meter the produced THAIOIL volume.
The injection steam is to be used to preheat the injection and production wells. It is expected that
the preheating of the three THAI well pairs will be completed in less than a year, after which
time the steam generation facilities will be retained for stand-by.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
5-1

Compression is required to provide a maximum of 255,000 m3 of injection air at a maximum


pressure of 8000 kPa. The current design basis includes three 0.79 MW air compressors and
three 0.29 MW air compressors, however, other configurations could be considered provided a
minimum of two air injection trains are included to ensure that continuous air injection can be
maintained. Air injection will begin after the steam preheat phase is complete and the in-situ
combustion phase is to be initiated.
During the in-situ combustion phase, hot water injection (to prevent thermal shock of cold water)
may be required to cool the production well or to redistribute the heat in the reservoir. This
injection water will be metered. The water will be heated with the steam generator that was used
in the pre-heat phase.

5.2

RAW WATER SUPPLY


Raw water will be from fresh water wells and will be used for the following:
softened for use in the conventional steam generator,
well cooling,
wet combustion (if required), and
domestic use.
The groundwater source will be a water supply well completed in the basal sand and gravel
(Empress Formation aquifer) of the buried Christina Valley. A second well may be installed to
serve as a backup, and for monitoring water levels and the chemical quality of the groundwater.
The water supply well will be located within the plant site if a sufficient thickness of the Empress
aquifer is present. Otherwise, the well will be located approximately 500 to 1000 m south of the
plant site, closer to the aquifer thalweg. Based on current information, it is anticipated that the
minimum depth of the top of the aquifer at the site of the well will be 145 m.

5.3

STEAM GENERATION AND WATER SOFTENING


A rented steam generator complete with a water softening module will be used for the well start
up procedure. The horizontal/vertical will pairs will be started up one at a time over the first year
of pilot operations.
The 53 GJ/hr once-through steam generator, fired by natural gas, will be used to produce
approximately 500 m3 per day of 80% quality steam. The steam will be metered as it flows to
the steam injection wells. The water treatment and steam generator P&IDs are shown in Figures
5-6 and 5-7 respectively.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
5-2

5.4

AIR COMPRESSION
The drivers are expected to run on natural gas (about 23,300 m3 per day of natural gas) but
alternatively may be designed to run on electricity that could be made available by power line
extension from a nearby existing line. The air compressor P&ID is provided in Figure 5-8. The
P&ID indicates three trains of compressors, however, two larger trains could be incorporated as
an alternate design approach.

5.5

PIPING, INSULATION, SUPPORTS AND CONTROLS


The pilot facilities will be split between the injection wells and the horizontal wells production
end as shown in Figure 5-1. There will be three flow lines on racks to take air, water and steam
from the main facilities to the injection well end. The three separate lines are required to allow
full flexibility during start-up and production operations. The water and steam lines will be
insulated and electrically heat traced. Alternatively, they may be insulated and designed for quick
drainage in the event of an interruption in flow.

5.6

PRODUCTION WELLHEAD CONTROLS


The production wellhead will have controls on production from both the long and short tubing.
Capability to inject into the long and short tubing will also be available. The inlet separators are
to provide dampening for the production, which is expected to slug, and to separate the produced
gas from the produced liquid. The P&ID covering the wellheads, inlet separators and produced
gas coolers is provided in Figure 5-9. The separated gas will be cooled to 80C to condense the
THAIOIL and water for secondary separation. The P&ID for the secondary separator is shown
in Figure 5-10. The gas from each of the three secondary separators will be monitored
continuously for oxygen and hydrogen sulphide content. The measurement of the oxygen content
is a safety issue as described in Section 3.9. The stream will also be sampled at least once a day
for full chromatographic analysis.

5.7

INJECTION WELLHEAD CONTROLS


The injection wells will be designed to inject water, air or steam alone or simultaneously into the
upper and lower perforations of the injection well. This is an important feature of the pilot to
provide the maximum flexibility to control the in-situ combustion operations.

5.8

PRODUCTION TREATMENT AND SEPARATION (EMULSIONS )


The produced liquid will be cooled to approximately 90C before it proceeds to the treater where
chemical and diluent will be added to separate the THAIOIL and water. The gas from the
treater will be combined with the gas from the secondary separators before proceeding to the vent
stack. The P&ID for the produced liquid coolers, treater and vent gas stack is shown in Figure 510.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
5-3

5.9

PRODUCTION GAS VENT


The produced gas will be vented through a 75 metre high vent stack. The H2 S content of the gas
will be monitored at the inlet to the vent stack. An in-line H2 S sweetener will be used to reduce
the H2 S content. The aerial cooler, treater and vent stack P&ID is provided as Figure 5-11.

5.10

PRODUCED WATER TREATMENT AND DISPOSAL


Orion proposes to dispose of produced water into the Clearwater Sandstone as described in
Section 3.6. Water is currently being disposed into the Clearwater Sandstone by Devon Canada
Corporation at rates as high as 509 m3 per day. The petrophysical log studies suggest that the
Clearwater Sandstone will be similar in the development area to that encountered at Devon
Canadas 3-7 disposal well.
An application for disposal approval will be made separately to the EUB.

5.11

TANKS AND PRODUCT SHIPPING/TRUCKING FACILITIES


There will be tanks for water, THAIOIL, diluent and slop. There will be oil storage capacity
for three days of production. Truck loading facilities will be incorporated into the design. The
tanks will be blanketed with natural gas. Gases evolving from the produced fluids in the tanks
and excess blanket gas will be collected and sent to the flare stack. The P&ID for the tanks,
pumps and flare is shown in Figure 5-12.

5.12

PROCESS UTILITIES
Process utilities will include a fuel gas scrubber and instrument air package as shown in the P&ID
(Figure 5-13).

5.13

CONTROL ROOM AND OFFICE


A control room will be provided for operations at the main plant site and for control of the
injection end site. Computerized data collection with direct link to the Orion Calgary office will
be installed.

5.14

CHEMICAL ADDITION SYSTEM


Chemicals will be required in the separators for emulsion treatment, in the H2 S sweetener, and
in the steam generation water treatment.

5.15

SPACE HEATING & LINE TRACING


Gas fired space heaters and electricity will provide heating and line tracing.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
5-4

5.16

HEAT RECOVERY
Heat recovery will not be incorporated into the pilot design, but data necessary to evaluate and
design a heat recovery system for a commercial operation will be collected. Production stream
volumes, temperatures and pressures will be measured to support an assessment of the
commercial viability of a heat recovery system to reduce net process energy intensity.

5.17

DILUENT SYSTEM
Diluent will be available to blend with the THAIOIL to reduce the gravity and promote
separation.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
5-5

SITE DEVELOPMENT, UTILITIES AND OFF-SITES


The Project development area (see Figure 6-1) is approximately 84 ha in size. Elevations range
from 620 ASL in the SW sector to 580 in the NE sector. The central portion is well drained and
provides a suitable locatio n for the plant site. Based on the results of the November 2003 drilling
program the facility footprint within the development area may be reoriented into a more E-W
configuration to take advantage of the of the higher quality reservoir and to avoid low lying
ground in the NE sector.
Earthwork requirements have not yet been defined. During final engineering the development
area will be surveyed and a site plan prepared including plant site, well pads, roads, pipeline
corridor, drainage pond, berms, soil storage locations, fresh water well and other Project facilities.
A 3.5 km all-weather access road will be constructed, connecting with the existing all-weather BP
well access road and the all-weather municipal road near the Leismer gas plant.

6.1

POWER
An existing 3-phase electricity line is located approximately 2.5 km NE of the Project site.
Discussions with Aquila Networks indicate that once an agreement is signed it takes up to 20
weeks to install the service. The electrical demand for the Project will depend on whether
electrical drivers or gas drivers are specified for the compressors.

6.2

NATURAL GAS
Discussions with ATCO Gas indicate that a high-pressure natural gas pipeline is located north of
the development area. Approximately eight months lead-time is required to install gas service
once an agreement is signed.

6.3

COMMUNICATIONS
A computerized data collection with direct link to the Orion Calgary office will be installed with
the capability to provide 24-hour continuous real-time access to the data generation, control
measurements and data base material at the site from the Orion office. The objective is to provide
the identical access to site information at the Calgary office as is available at the Project site.
Direct control of the Project operations will be restricted to the control room on site.
Discussions with Telus indicate that the area is covered by cell phone service and that both
conventiona l copper wire and high speed fibre optic cable service is available from the Highway
881 corridor. The estimated time for telecom service installation is three to six months depending
on the type of service required.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
6-1

6.4

CAMP FACILITIES
Two large full-service open camps are located at the Conklin 4-corners intersection,
approximately 13 km east of the site. It is planned that both construction and operating personnel
will use these camps. Contractors may opt to provide on-site facilities.

6.5

CONSTRUCTION FACILITIES
Temporary construction facilities will include:
construction office,
warehouse,
lay-down yard, and
parking lot.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
6-2

OPERATING DESIGN

7.1

START-UP, SHUTDOWN PROCESS


The objective is to ignite the reservoir without damaging the vertical injection well while
avoiding fracturing the reservoir. Any flow-back of gas or fluid into the injection well is to be
avoided as this has a high probability of drawing combustion into the well and damaging or
destroying the well. The procedure is as follows:
Inject steam low in the reservoir with the vertical well to heat the reservoir near the
vertical well and to develop heated communications with the horizontal production well.
The horizontal well will be preheated with steam along its entire length by injecting
steam into the well and cycling the hot water out of the well. This will prevent plugging
of the well by cold bitumen.
After heated communication has been achieved from the lower injection point on the
vertical well to the horizontal production well, steam will be injected continuously into
the lower injection point to enter the horizontal well. The cycling/injection into the
horizontal well will be discontinued to allow the steam entering from the vertical well to
flow through the horizontal well to complete the heating of the horizontal well to a
predetermined temperature (steam temperature less 50C).
At this point, steam injection at the base of the vertical well will be terminated and steam
will be injected into the upper part of the reservoir to create a heated volume (10 m in
radius) around the well at the top of the reservoir that is linked to the lower steam heated
area and the horizontal well in preparation for ignition.
After creation of heated communication between the horizontal and vertical well, air will
be injected high in the reservoir via the vertical well to ignite the oil by spontaneous
combustion and start the recovery process.
The air injection, at rates of up to 85,000 m3 /day of air into each vertical injection well,
will be below fracture pressure.
Through the pilot life, the production operations will be shut down in a pla nned manner for such
things as yearly maintenance of facilities and special tests.
The operations may also need to be shut down due to emergency situations such as detection of
high levels of oxygen in the produced gas. The main concern is the manner in which the wells
are shutdown and restarted so as not to damage the wells or impede resta rting of the THAI
process. The shutdown will be conducted in a planned, safe manner.
For the air injection wells, the main concern is to eliminate the possibility of back
flowing combustion material into the well. A constant pressure should be kept on the
well to prevent influx of hot reservoir material that could damage the well with
combustion in the well or by influx of sand that could plug the well. This will be

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-1

7.2

accomplished by injecting steam or hot water (to avoid thermal shock) to prevent the
flow back and then filling the well with water to prevent inflow.
The horizontal production wells should be shut down under pressure to eliminate the
possibility of oxygen entering the well and causing damage by combustion in the well in
the manner described for vertical wells. The horizontal well design incorporates the
capability of circulating the well to flush out material that may have settled in the well or
to reheat the well as necessary if shut down for an extended period.

DATA ACQUISITION AND REPORTING


Data collection for the reservoir is aimed at monitoring and controlling reservoir conditions,
mainly pressure and temperature. Observation well data collection will be focused on the
conformance and spread of the combustion recovery through the reservoir. The spread of
recovery between the horizontal production wells and outside of the unconfined THAI pilot
pattern will be key to the design of the well spacing to be used for commercial operations.
Surface data collection is aimed primarily at measurements of the volume and composition of
injected and produced material (e.g. injected air, THAIOIL, produced water, and produced
gas). Surface measurements will provide the basic data for calculating the economics of the
THAI process, controlling the THAI process, designing commercial facilities and meeting
mandated environmental regulations.
The data acquisition, reporting and comparison will include the following:
production and injection data,
observation wells data,
material balance for water and air usage,
composition of produced gas, disposal water and flare,
oxygen, hydrogen sulphide, carbon monoxide and carbon dioxide measurements,
pilot injection and production performance (daily and cumulative),
individual well performance (daily and cumulative),
pressure and temperature at well heads,
air/oil ratio (daily and cumulative for pilot and wells),
steam and/or water/air ratio (if wet combustion used),
water/oil and gas/oil ratios for production,
pressure and temperature within wells,
observation wells temperature and pressure,
reservoir pressure and temperature contours,
measurements of surface vent gas concentration in surrounding area,
produced fluid heat content measurements, and
water analyses (pH and ions).

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-2

The focus of the data collection program will be to address the uncertainties in the experimental
parameters and to achieve regulatory compliance.

THAIOIL, water and gas production, and water and air injection are to be
metered for each well and reconciled with total THAIOIL sales, total water
disposal and total gas production.
Produced gas will be monitored continuously for O2 , H2 S and CO content. On a
routine basis, gas chromatography will be used to obtain a full compositional
analysis including CO2 .
On a routine basis, THAIOIL samples will be analyzed for density, viscosity
and SARA (saturates, aromatics, resins and asphaltenes) components.
On a routine basis, produced water will be analyzed for pH, anions, cations,
dissolved solids and entrained oil.
A test program will be initiated to analyze potential corrosion problems with the
downhole tubulars.
Thermocouples will be installed in the injection wells, the production wells and a
number of observation wells to monitor in-situ temperatures.
A systematic program will be initiated to test various chemical additives in the
breaking of the produced emulsions.
A corrosion- monitoring program will be in place for the surface facilities.
A number of benchmarks will be placed strategically in and around the Project
site. Baseline elevations will be checked periodically to confirm that there is no
ground movement.
THAIOIL samples will be collected on a routine basis and forwarded to an
external lab for analysis.

The Project performance data will be used to develop a history match and improve the predictive
capability of the numerical simulation.

7.3

WELL INTEGRITY
There are two main issues related to the well operations as follows:
The horizontal production wells have a risk of being damaged by combustion heat. The
main interventions are to inject cooling water or steam into the vertical injector and/or the
horizontal well to cool the production. This can be done on a slug basis or on a
continuous basis. If the overheating cannot be remedied, then reducing or stopping air
injection will be necessary.
Excessive sand production may result if the sand control slots or wire wrap is eroded by
high velocity gas carrying sand into the well. The effect is like sand blasting and the

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-3

holes will become larger. This is a common problem with conventional in-situ
recovery operations between vertical wells. Repair of this problem would be difficult.
However, as the combustion front with the THAI process moves along the horizontal
well, the erosion is most likely at the combustion front where the bulk of the production
and gas will enter. If the sand control is breached at the combustion front, the breached
section will disappear behind the production front as the front moves forward.

7.4

SAFETY AND ENVIRONMENTAL PROTECTION


Personnel Safety
There are two major safety risks at the surface facilities, both associated with the produced gas.
The produced gas is expected to contain H2 S and appropriate safety training and systems must be
in place. The anticipated produced gas can be dispersed via the vent as specified to meet the
ground level guidelines. The H2 S content of the produced gas will be measured and reduced to an
acceptable level using a sweetening system installed at the plant site. There will also be
monitoring stations situated around the area to monitor compliance with environmental
requirements. The sweetening system will be a commercially available and proven system (e.g.
Canwell) that uses a liquid chemical solution to contact the produced gas to chemically capture
the H2 S. The units have been proven effective at much higher gas flow rates and H2 S content
well beyond the conditions anticipated for the pilot. The liquid chemical will be a proprietary
blend of aldehyde/alkanolamine condensates that captures both H2 S and mercaptans. The
supplier of the chemical will collect and dispose of the spent liquid chemical at commercially
licensed facilities.
The oxygen content of the produced gas may get to the level that could cause an explosion. The
oxygen content of the produced gas must be continuously measured and the production stopped if
the oxygen content reaches a critical level.
Waste Management
During regular operation and maintenance of the facilities, a number of waste materials will be
generated. These waste volumes will be small. Commercial approved services will be used to
remove any wastes which are subject to special disposal requirements. Chemicals will be stored
in accordance with EUB guidelines.
All production related waste storage vessels will be sized to allow for a realistic waste removal
schedule. Each vessel will have secondary containment and leak detection as defined under EUB
guidelines. In addition, the entire site will be graded in a manner to contain any spills or releases.
The THAI process will generate a number of waste streams as detailed in Table 7-1 below.
Temporary steam generation will be required only during the THAI well start up and thus

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-4

waste s normally associated with conventional steam generation will only be produced during the
start-up period.
TABLE 7-1
W ASTE STREAMS
Waste Stream
Produced solids

Flow Rate
3
Net solids: 1 m /d

Water softener back


wash
Steam generator
blowdown water
Tank Blanket Gas

7 m /d (during start up
only)
3
20 m /d (during start up
only)
3
3
0.4 10 Sm /d (day)

Combustion Gas

255 10 Sm /d (dry)

Produced Water

120 m /d

Storage/Disposal
Enclosed tank with
vapour recovery &
trucked out
Disposal well
Disposal well
Flared (incinerated)

Vented

Disposal well

Characterization
Sand with a
hydrocarbon constituent
residue
Highly mineralized
water
Highly
mineralized
water
Methane, carbon
dioxide with a H2S
component
Nitrogen, carbon dioxide
with sulphur
components
Water created by the
THAI process & water
from the oil sands

Produced Solids
The production wells are completed with sand exclusion liners to prevent sand and other solid
materials from being carried into the production wells. It is expected that very fine solids will
pass through the sand exclusion liners and be co-produced with the THAIOIL. The solids will
accumulate in the oil/water separation facilities and production tanks. Approximately once per
year the solids (with residual hydrocarbon) will be removed for off-site disposal at a commercial
approved facility.
Lubricants
Various rotating equipment and air compression facilities will require regular change out of
lubricants. The used lubricants will be collected and disposed of by an approved used-oil
handling third party contractor.
Other Oily Wastes
Oily rags, filter cartridges and any other contaminated solid wastes will be stored in a dedicated
oily waste bin and disposed of by a third party contractor.
Sewage and Grey Water
All sewage and grey water will be collected in holding tanks that will be emptied as required by a
third party contractor and disposed of at an approved facility.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-5

Domestic and Dry Wastes


Domestic and dry wastes will be collected in a dumpster and removed by a third party contractor
and disposed of at an approved facility. Dry wastes will not be burned on site.
Other Hazardous Wastes
Other hazardous wastes frequently associated with oil and gas facilities, such as certain types of
spent catalysts, will not be generated at the facility. The use of radioactive tracers or sources is
not anticipated, other than those supplied by third party, properly licensed contractors.
Chemical Storage
As described earlier, a variety of chemicals is used in the process primarily for maintenance (e.g.
lubricants), water treatment chemicals for steam generation and oil/water demulsifiers.
The chemicals used for steam generation water treatment consist of an oxygen scavenger, such as
sodium sulfite , and a hardness-sequestering agent known as a chelant (EDTA) and salt. The
softening unit requires the use of regeneration chemicals consisting of acid and caustic.
All chemicals will be stored in their shipping containers or vessels specifically designed for that
type of service within process buildings that will have containment floors.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
7-6

REGULATORY COMPLIANCE
This section summarizes the regulatory compliance requirements that will impact the final design
and construction of the Project. At the time of writing, February 2004, applications for approval
have been submitted (October, 2003) to the Alberta Energy and Utilities Board (EUB), under the
Oil Sands Conservation Act and to Alberta Environment (AENV) under the Environmental
Protection and Enhancement Act. Approval of these applications is anticipated in the first quarter
of 2004. Applications for several additional approvals will be submitted in 2004, after the
decision to proceed.
Regulatory approvals associated with the provision of natural gas and electrical services will be
the responsibility of those providing the service.

8.1

ALBERTA ENERGY AND UTILITIES BOARD


The EUB application was based on the conceptual design outlined in this DBM. The EUB
approval will be based on that design. Any subsequent significant changes to the approved
Project design will require the approval of the EUB and may require the submission by Orion of
an amendment application. As well the EUB approval may require Orion to implement specific
conditions in the final design.
Following the decision to proceed, applications to the EUB will be required for a deep well
disposal approval and numerous well licences.
The EUB has a number of Interim Directives and other regulatory guidelines covering issues such
as noise control (http://www.eub.gov.ab.ca/BBS/requirements/ils/ids/id99-08.htm) and
production measurement (http://www.eub.gov.ab.ca/BBS/requirements/ils/ids/id91-03.htm),
which should be consulted during the final design phase to ensure compliance.

8.2

ALBERTA ENVIRONMENT AND ALBERTA SUSTAINABLE RESOURCE DEVELOPMENT


The same comments regarding design basis, conditions and changes apply to the AENV approval
as are discussed in Section 8.1 above. In particular, emission standards for SO2 , H2 S, NOx, and
particulates will be specified in the approval. For example final selection of the steam boiler will
be required to meet the CCME National Emission Guidelines for Commercial/Industrial Boilers
and Heaters.
Following the decision to proceed, applications to AENV under the Water Act will be required
for ground water use and surface drainage. Applications to Alberta Sustainable Resource
Development (ASRD) for surface rights (MSL, LOC, MLL, etc.) will be required prior to
construction. These approvals will contain numerous design and construction conditions.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
8-1

AENV and ASRD administer a number of guidelines, standards and codes of practice dealing
with air, water, land and waste management that will impact the Project. These should be
evaluated during final design.

8.3

REGIONAL MUNICIPALITY OF WOOD BUFFALO


The Project will require a development permit from the Regional Municipality of Wood Buffalo.
The application fee is $10 per $100 thousand of construction cost. The permit requires that
developers comply with all the building, mechanical, electrical and safety codes of Alberta.
PermitPro in Fort McMurray administers review of final plans and approvals.

8.4

OTHER
Depending on the final design of the Project, additional approvals and compliance requirements
may arise. These include for example flare stack lighting and tower and radio frequency
approvals from Transport Canada.

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
8-2

PRELIMINARY RISK ASSESSMENT


The WHITESANDS Project is the worlds first field pilot of the THAI process and as such
there are a number of considerations that may or may not actually be areas of significant risk. Insitu combustion projects using combustion drive have generally encountered recovery
conformance issues and well damage by combustion. The gravity drainage aspect of the THAI
process and the design of the Project are aimed at preventing these historical difficulties. A
summary of the potential design and operating risk areas identified to date are outlined in Table
9-1, along with preliminary design mitigation initiatives and remaining issues for the detailed
engineering phase.
It is recommended that a preliminary HAZOP assessment be undertaken at the commencement of
detailed engineering and that a comprehensive HAZOP review be conducted on the Project when
the detailed engineering is between 50% and 80% complete.
TABLE 9-1
PRELIMINARY D ESIGN AND OPERATIONS RISK S UMMARY

Risk Description
Excess heat in the production
well

Ignition of oil in the production


well resulting in damage to the
well

Failure of the coke plugging


process in the formation air
entering the well or coke
combustion in the well

PROPRIETARY AND CONFIDENTIAL

Preliminary Design
Considerations
The injection and production
wells are completed with the
facility to inject steam/water to
control excess heat in the
production well
Thermocouples in the well to
identify heating
Continuous monitoring of O2
content in production gas stream
System to inject steam/water to
control excess heat in the
production well
Control of overheating through
steam/water injection

Issues for Detailed


Engineering
Define instrumentation
systems and operating
procedures

Provide instrumentation
and monitoring system
details

Define air/water/steam
injection rates and
monitoring system

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
9-1

Risk Description
Excessive corrosion in
production well related to
produced fluids

Preliminary Design
Considerations
Ongoing monitoring of well
temperatures
Control well temperatures to
maintain any water in the gas
phase

Excessive sand production in


the horizontal well impairs
production

Well designed includes very


standard keystone slots (or wire
wrap)

Excessive O2 entry into the


production well

Continuous monitoring of O2 in
the produced gas
Operate the well to maintain a
pool of oil or water above the
production well as a seal to
prevent oxygen entry by
increasing bottom hole pressure
Continuous monitoring of O2 in
the produced gas
Adjust air injection to reduce O2
content
Shutdown at specified level
Drilling program in Project area
confirmed existence of
competent cap rock

Explosion due to high O2


content in produced gas stream

No cap rock to contain THAI


process, contamination of
overlying natural gas and/or
groundwater resources by
produced gases and fluids
Gas cap above the target
reservoir area which may be
under lease to other rights
holders is consumed in the
combustion process

PROPRIETARY AND CONFIDENTIAL

Drilling program in Project area


confirmed there is no gas cap

Issues for Detailed


Engineering
Review corrosion test
results
Confirm preliminary
design approach or
identify alternatives
Review simulation results
Metallurgical solutions
Confirm preliminary
design approach or
identify alternate or
additional control systems
Conduct sieve analysis on
subject core
Confirm preliminary
design approach or
identify alternatives

Confirm preliminary
design approach or
identify alternatives

Monitoring program

None

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
9-2

Risk Description
Combustion is not symmetrical
about the production well

Emulsion formation

Preliminary Design
Considerations
The interventions available to
control combustion
conformance are air injection
rates and individual well
production rates and use of wet
combustion
Add diluent and optimize
demulsifying chemicals as
needed

Excessive corrosion in facilities


downstream of the wellhead due
to high CO2 or SO 2 content
gas/water

Ongoing monitoring of well


temperatures
Sparing of key components and
replacement as necessary

Inability to complete all


horizontal wells to 500 m length

Applied conventional horizontal


well drilling

Destruction or damage of the


The production tube is designed
long production tube due to heat to be pulled back as the
or combustion
combustion front advances
through the reservoir
Backflow of air and oil into the Steam/water can be injected into
injection well
the injection well with sufficient
pressure to prevent backflow
Calcium carbonate or calcium
Scale removal through acid
sulphate scale formed in or on
treatment
the production well

PROPRIETARY AND CONFIDENTIAL

Issues for Detailed


Engineering
Verify final well locations
in high quality reservoir

None
Include flexibility to
resolve any issues
following operational
start-up
Review corrosion test
results
Confirm preliminary
design approach or
identify alternatives
Develop corrosion
monitoring program
Identify metallurgical
solutions
Confirm preliminary
design approach
Resolve problems during
drilling and completion
process
Confirm preliminary
design approach or
identify alternatives
Define in start-up,
operating and shutdown
procedures
Confirm preliminary
design approach or
identify alternatives

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
9-3

Risk Description
Erosion of pipes and valves by
sand in the production stream

H2 S in the production gas


stream

PROPRIETARY AND CONFIDENTIAL

Preliminary Design
Considerations
Sparing of key components and
replacement as necessary

Continuous monitoring of H2 S
content in the produced gas
Gas sweetening capability
incorporated
Shutdown at defined level

Issues for Detailed


Engineering
Confirm preliminary
design approach or
identify alternatives
Develop monitoring
program for critical areas
Design to minimize
erosion
Confirm preliminary
design approach or
identify alternatives
Emergency Response Plan

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
9-4

APPENDIX A
GEOLOGY

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM

GEOLOGY
RESOURCE DESCRIPTION
Orion currently holds 45 sections of land under oil sands lease agreements in the Conklin area of northeastern Alberta. The site of the planned Project in Sections 12 and 13, Twp 77, R. 9, W4M is held under
Oil Sands Agreement 7400010012 (Lease 012), which expires in 2015-01-13. The natural gas rights in
the Clearwater Formation are held by BP Canada. The natural gas rights in the McMurray Formation in
Sections 12 and 13 are undisposed Crown rights.
Orion has conducted an extensive review of the regional geological database. Within the six township
(Twp 76 to 77 Ranges 8 to 10 W4M) area surrounding the site, 187 wells have been drilled which
includes 93 gas wells, 46 standing wells, 45 dry and abandoned wells and 3 water disposal wells. Of the
28 wells on Orion oil sands leases, 7 had log results indicating bitumen saturation in McMurray channel
sandstones. Orion has also closely followed the recent review of geological data in the Leismer Field by
the EUB in dealing with the ongoing gas-associated-with-bitumen issue. Based on this abundance of data
and the resulting interpretation, Orion is very confident of its characterization of the regional geology as it
directly relates to the proposed Project site.
In early 2003 Orion conducted a 3-D seismic program of an approximate 20 km2 area in Lease 012, which
includes the Project site (see Figure A-1 McMurray Seismic Character Correlation Map). The objective
was to obtain data that could be correlated to wells in close proximity to the area, which would enable
Orion to identify a Project location with acceptable reservoir characteristics and which also was a suitable
development site within reasonable proximity to existing infrastructure.
REGIONAL GEOLOGY
The bitumen resource target for the Project is found in the McMurray Formation, which is the basal unit
of the Lower Cretaceous Mannville Group. The McMurray Formation contains the significant bitumen
reserves that constitute the Athabasca oil sands deposit of Northeastern Alberta. The study area for this
regional discussion encompasses Township 76 and 77 Ranges 8 to 10 W4M.
The Mannville Group is composed of very weakly consolidated clastic sedimentary rocks that rest
unconformably on the carbonates of the Devonian Beaverhill Lake Group (Figure A-2 Generalized
Stratigraphic Section). In Northeastern Alberta, the Mannville Group is divided into three formations.
From oldest to youngest these formations are: the McMurray, the Clearwater, and the Grand Rapids. The
Mannville Group is overlain by Cretaceous Colorado Shale that is truncated by Quaternary glacial
deposits as shown in Figure A-3 (Project Site Cross-Section).
GEOLOGY OF THE M CM URRAY FORMATION PRODUCTION ZONE
The regional McMurray Formation consists of a lower member of fining upward fluvial to
estuarine sandstones and an upper member of coarsening upwards brackish bay fill deposits,
PROPR IETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
A-1

separated by a mappable flooding surface. Generally, the regional McMurray, especially the
Upper McMurray exhibits a horizontally layered package. The thickness of the Lower
McMurray, however, is controlled by topography on the pre-Cretaceous unconformity surface, as
illustrated by the Devonian Structure map (Figure A-4) and the Clearwater Marker to Devonian
Isopach (Figure A-5).
Due to lowstand sea level events during the Upper McMurray time, at least two incised valley
systems are interpreted to have eroded up to 30 m of the regional McMurray Formation. Stacked
estuarine channel sandstones, which infilled these valleys, comprise the target reservoir for the
Project. A large-scale sedimentary structure, known as inclined heterolithic stratification (IHS) is
often observed within valley fill channel sandstones.
Structure on the top of the McMurray Formation, as shown on the McMurray Structure map
(Figure A-6), is influenced by both drape over the pre-Cretaceous unconformity surface as well as
differential compaction over the incised valley sequences. These structural influences diminish
up the stratigraphic section, as seen on the Base Clearwater Structure map (Figure A-7).
Structurally, the McMurray Formation top dips approximately 1.7 m per km to the southwest (see
McMurray Top Structure Map Figure A-6). Together with the surface topography, the resulting
depth to the McMurray top varies from 300 m to 480 m in the regional study area. Based on an
estimated fracture gradient of 20 kPa per metre of depth, the fracture pressure of the McMurray at
400 m would be 8,000 kPa.
CLEARWATER FORMATION
The Clearwater Formation is made up of two sand-shale sequences in the Project area, described
below:
Wabiskaw Member
The lowermost part of the Clearwater Formation is made up of the Wabiskaw Member,
which directly and sharply overlies the McMurray Formation. This member, typically
around 10 m thick, consists of upward cleaning, transgressive marine silty sands.
Sufficient stratigraphic variability occurs in this member to develop numerous small traps
for gas and some minor amounts of bitumen (Wabiskaw Gas Pay Map, Figure A-8). A
regionally correlatable, initial transgressive shale at the base of the Wabiskaw Member
separates it from the McMurray Formation.
Lower Clearwater Shale - Production Zone Caprock
Abruptly overlying the Wabiskaw Member is a shale sequence that is about 22 m thick
forming a major caprock between the Clearwater Sandstone Member above and the
WabiskawMcMurray below (Figure A-9 Caprock to McMurray Isopach Map). It
includes the five-metre thick Wabiskaw Marker, a regionally correlatable bentonite bed.

PROPR IETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
A-2

Over a five-metre interval, this shale sequence quickly grades into the overlying
Clearwater Sandstone (Figure A-10 Clearwater Sandstone Isopach)
Clearwater Sandstone Water Disposal Zone
The Clearwater Sandstone is a very uniform, 35 m thick marine shoreface complex that
hosts a significant, structurally-controlled gas accumulation, extending into the
northeastern-most part of the Orion lease holdings (Figure A-11 Clearwater Sandstone
Gas Pay Map). This Clearwater Sandstone is the proposed water disposal zone for the
Project.
Upper Clearwater Shale
The Clearwater Sandstone is sharply overlain by a series of interbedded shales and
cleaning-upward sandy siltstone packages that total 22 to 36 m in thickness, which form
the seal for the Clearwater Sandstone gas pool.
The top of the Clearwater Formation has a short, transitional contact with the base of the
Grand Rapids Formation.
GRAND RAPIDS FORMATION
The Grand Rapids Formation can be divided into an upper and lower member:
The Lower Grand Rapids Member is a 30 to 40 m thick upward-coarsening sandstone, which is
water wet throughout the area.
The Upper Grand Rapids member consists of 38 to 60 m of up to four stacked coarseningupwards sand cycles separated by impermeable, thin marine shales. Gas is trapped in combined
structural-stratigraphic traps in the upper cycles in the regional study area.
COLORADO GROUP
Tight marine shales of the Cretaceous Colorado Group overlie the Grand Rapids Formation. The
Colorado Group is dramatically truncated at the unconformable contact with the unconsolidated
Quaternary glacial drift. Preserved Colorado Group thickness varies from as little as 5 m to more
than 80 m in the study area (Figure A-12 Preserved Colorado Isopach Map). In the vicinity of the
proposed Project, 40 to 60 m of Colorado section is expected. The Colorado Group Shale forms
an effective seal between the brackish water- and hydrocarbon-charged Cretaceous sediments
below and the freshwater-bearing glacial sediments above.
QUATERNARY WATER SOURCE HORIZON
The surficial glacial drift is made up of gravel, sand, silt and clay. The Empress Formation is the
proposed fresh water source for the Project at an estimated depth of 145 m to 150 m below
surface in the area of the Project site.

PROPR IETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
A-3

PROJECT SITE GEOLOGY


The proposed Project site is in Sections 12 and 13 Twp 77 Rge 9W4M and within the 20 km2 3-D
seismic survey that Petrobank Energy and Resources Ltd. shot and processed January 2003. Core
test holes on the site were completed in November 2003 and are the basis of current
interpretations. Core was cut to calibrate petrophysical log analyses and provide key engineering
parameters.
As previously discussed, the target reservoir is interpreted to be McMurray Formation comprising
compound incised valley fill sandstones. In general, the incised valley orientation is interpreted
to be northeastsouthwest (see McMurray Incised Valley Sandstone Isopach Figure A-13). The
location of the 3-D seismic was determined based on this interpretation.
There is essentially no gas observed in this valley sandstone complex. Less than 1 m of log
indicated gas in the 8-13-77-9W4 and 10-7-77-8W4 wells, which are at the highest structural area
of the seismic survey. There is also no underlying water apparent from logs in the incised valley
channel sandstones, although wet Lower McMurray sandstone is seen in the 10-7-77-8W4 well
between 388 and 394 mKB.
Seismic Definition of the Project Site
In the area covered by the Orion 3-D seismic program, both McMurray regional and channel
sandstones have been encountered by the existing wells. Seismically, the distinction between the
target channel sandstones and the regional sandstone sequence can be interpreted in part by
differences in the bedding between the two. Within the McMurray time interval, the regional
sequence usually exhibits flat lying reflectors, while portions of the channel packages show
inclined reflectors as a result of IHS, thus allowing for channel or non-channel fairways to be
mapped. This does not necessarily predict channel reservoir quality.
The thickest, most continuous, and best channel sandstone reservoirs do not have any reflectors.
The seismic amplitude characteristics of a thick, continuous channel sandstone at an existing well
was extracted and compared to the other McMurray interval seismic amplitudes within the 3-D
survey. Using a pattern recognition algorithm, the correlation coefficient between the extracted
amplitude and the amplitude recorded and processed at each bin in the survey was calculated.
The results were mapped as seen on the McMurray Seismic Character Correlation Map (Figure
A-1), which shows areas of higher correlation in shades of blue and areas of lower correlation in
red. It must be noted, however, that the amplitude characteristics of the desired reservoir can also
be produced by other variables such as shale; consequently, the McMurray Seismic Character
Correlation Map should be interpreted in conjunction with a review of the actual seismic crosssection in order to place the amplitude in context.

PROPR IETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
A-4

Reservoir Quality
Reservoir quality is considered to be good to excellent based on petrophysical log responses. The
four wells with log indicated bitumen pay in the seismic survey area have a weighted average of
21.4 m of pay at 33 percent sandstone density porosity, using cut-offs of 20 ohm-m and 30
percent porosity as shown in the Net Bitumen Pay Map (Figure A-14). Core from the test holes
in the pilot site area confirmed petrophysical responses. The sands are well sorted, upper fine to
lower medium grained, with local matrix supported intraformational conglomerate. Pay in the
pilot site area is 23 to 24 metres thick with a minimum bitumen saturation of 70 per cent and a
minimum porosity of 30 percent. Porosity values are as high as 39 percent and bitumen
saturation can exceed 90 percent of pore volume. Permeability is greater than one Darcy, with
over 11 Darcies observed. Higher gamma ray values in the pay column corresponded to
intraformational conglomerate.
WATER DISPOSAL ZONE
Orion proposes to dispose of water produced from the Project into the Clearwater Sandstone.
Water is currently being disposed into the Clearwater Sandstone by Devon Canada Corporation
using a well at 3-7-77-7W4M, about 11 km from the proposed Project site. Since 1982, at the 37-77-7W4 well, 240,309 m3 of water have been disposed into the Clearwater Sandstone at rates as
high as 509 m3 per day.
Mapping and correlation based on petrophysical logs indicate that the geology for the Clearwater
Sandstone disposal zone at the proposed Project site is the same as at the 3-7 disposal well. At
the proposed Project site, more than 24 m of wet sandstone underlying 7m of gas charged
sandstone is anticipated. A nearby well at 10-18-77-8W4 cored Clearwater sandstone with
permeabilities from 1.5 to 6 Darcies and porosities consistently above 30 percent. The
Clearwater Sandstone underlies the entire study area and is as thick as 40 m elsewhere on the
Orion lease.
An application, under Section 26 of the Oil and Gas Conservation Act and Guide-51, for
subsurface water disposal into the Clearwater Sandstone will be prepared and submitted under a
separate cover in 2004.

PROPR IETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM
A-5

APPENDIX B
PRELIMINARY PROJECT SCHEDULE

PROPRIETARY AND CONFIDENTIAL

ORION OIL 03-2303


WHITESANDS EXPERIMENTAL PILOT PROJECT
DESIGN BASIS M EMORANDUM

WHITESANDS Experimental Project


Preliminary Project Schedule

Orion Oil Canada Limited


ID
1

Task Name

Duration

Start

Finish

Public Consultation

324 days

Mon 10/20/03

Wed 12/29/04

Business Plan

176 days

Mon 3/15/04

Mon 11/1/04

1 day

Mon 3/15/04

Mon 3/15/04

95 days

Thu 7/1/04

Mon 11/1/04

Qtr 4, 2003
Oct Nov

Dec

Qtr 1, 2004
Jan Feb

Qtr 2, 2004
Apr May

Mar

Jun

Qtr 3, 2004
Jul
Aug

11
12
13

Corporate Project Approval

14

Marketing & Logistics

3/15

15
16

230 days

Mon 3/1/04

Fri 12/31/04

17

Project Management
DBM Complete

1 day

Mon 3/1/04

Mon 3/1/04

18

Project Cost Estimate

1 day

Mon 3/15/04

Mon 3/15/04

3/15

19

Select Engineering Team

1 day

Mon 3/15/04

Mon 3/15/04

3/15

20

Orion Decision to Conduct Site Survey

1 day

Mon 3/15/04

Mon 3/15/04

3/15

21

Project Execution Plan

1 day

Mon 5/3/04

Mon 5/3/04

22

Staffing

228 days

Wed 3/3/04

Fri 12/31/04

23

Assign Production Drill Program Management

1 day

Mon 3/1/04

Mon 3/1/04

174 days

Wed 2/18/04

Mon 10/4/04

1 day

Fri 2/20/04

Fri 2/20/04

3/1

5/3

3/1

24
25

Regulatory Approvals

26

EUB Project Approval Granted

27

EUB & AEPEA Approvals Compliance Plan

10 days

Wed 2/18/04

Tue 3/2/04

28

Conservation & Reclamation Plan Approval

45 days

Thu 4/1/04

Tue 6/1/04

29

Surface Lease Rights

44 days

Mon 3/1/04

Thu 4/29/04

30

RMWB Development Permit Application Submission

23 days

Mon 3/15/04

Wed 4/14/04

31

Safety Codes Act - Submit Application to Permit Pro

77 days

Tue 6/29/04

Mon 10/4/04

2/20

3/15
6/29

32
33

47 days

Wed 10/29/03

Wed 12/31/03

34

2003/04 Exploration Program - Stratigraphic Wells


Well Licence Application

6 days

Wed 10/29/03

Wed 11/5/03

35

Liason with Local Alta Sustainable Resources Development Officer re access road

5 days

Mon 11/3/03

Fri 11/7/03

36

Access Contruction / Drill Pad Prep

3 days

Thu 11/6/03

Sun 11/9/03

37

Drill Three (3) delineation Wells

6 days

Mon 11/10/03

Mon 11/17/03

38
39

23 days

Mon 12/1/03

Wed 12/31/03

40

Core Analysis
Core Analysis at Core Lab

11 days

Mon 12/1/03

Mon 12/15/03

41

Detailed Core Description

11 days

Mon 12/1/03

Mon 12/15/03

42

Integrate core analysis with petrphysics; Generate Bitumen Weight % Maps

23 days

Mon 12/1/03

Wed 12/31/03

1 day

Mon 3/15/04

Mon 3/15/04

43
44

Confirm Observation Well Locations

3/15

45
46
47

Pilot Production Drilling Operations


Observation Well Drilling

48

Select OB Well Drilling Contractors/ Reserve Drill Rigs

49

OB Well Casing & Services Bid

50

Award OB Well Casing & Services Contract

51

Survey Locations of Observation Wells

52
53
54
55

165 days

Mon 3/1/04

Fri 10/1/04

53 days

Mon 3/15/04

Tue 5/25/04

1 day

Mon 3/15/04

Mon 3/15/04

13 days

Tue 3/16/04

Thu 4/1/04

1 day

Fri 4/2/04

Fri 4/2/04

11 days

Fri 4/2/04

Fri 4/16/04

Application for OB Well Licences (9)

5 days

Mon 4/19/04

Fri 4/23/04

Lease Construction / Site Prep

6 days

Mon 4/26/04

Sat 5/1/04

Drilling Programs

24 days

Tue 3/30/04

Fri 4/30/04

Drill OB wells

18 days

Sat 5/1/04

Tue 5/25/04

9 days

Wed 5/26/04

Sat 6/5/04

1 day

Sat 6/5/04

Sat 6/5/04

3/15

4/2

56
57

Evaluate Results of OB Wells

58

Confirm Locations for Horizontal Producers & Vertical Injector wells

6/5

59
60

82 days

Thu 4/1/04

Tue 7/20/04

61

Horizontal Well (3) Drilling


Horizontal Well Casing, Wellheads, Services bids

22 days

Thu 4/1/04

Fri 4/30/04

62

Select Horizontal Well Drilling Contractor

22 days

Thu 4/1/04

Fri 4/30/04
Page 1

Sep

Qtr 4, 2004
Oct Nov

Dec

Qtr 1, 2005
Jan Feb

Mar

Qtr 2, 2005
Apr May

Jun

Qtr 3, 2005
Jul
Aug

Sep

Qtr 4, 2005
Oct Nov

Dec

Qtr 1, 2006
Jan Feb

WHITESANDS Experimental Project


Preliminary Project Schedule

Orion Oil Canada Limited


ID

Task Name

Duration

Start

Finish

63

Survey Horizontal Well Locations

7 days

Sun 6/6/04

Mon 6/14/04

64

Application for Horizontal Production Well Licences

7 days

Tue 6/15/04

Wed 6/23/04

65

Drill Program for Horizontal Wells

12 days

Wed 6/16/04

Thu 7/1/04

66

Lease Construction (Drilling pad & surface facilities)

12 days

Tue 6/15/04

Wed 6/30/04

67

Drill Horizontal Production Wells

13 days

Fri 7/2/04

Tue 7/20/04

Qtr 4, 2003
Oct Nov

Dec

Qtr 1, 2004
Jan Feb

Mar

Qtr 2, 2004
Apr May

Jun

Qtr 3, 2004
Jul
Aug

68
69

111 days

Thu 4/1/04

Sun 8/22/04

70

Air Injection Wells


Air Injection Well Casing, Wellheads, Services bids

22 days

Thu 4/1/04

Fri 4/30/04

71

Select Air Injection Well Drilling Contractor

11 days

Thu 4/1/04

Thu 4/15/04

72

Survey Air Injection Well Locations

11 days

Sun 6/6/04

Fri 6/18/04

73

Well Licences for Air Injection Wells

7 days

Mon 6/21/04

Tue 6/29/04

74

Lease Construction

6 days

Wed 7/21/04

Tue 7/27/04

75

Air Injection Well Drill Program

13 days

Thu 7/22/04

Wed 8/4/04

76

Drill Air Injection Wells

15 days

Thu 8/5/04

Sun 8/22/04

77
78

142 days

Thu 4/1/04

Fri 10/1/04

79

Water Disposal Wells


Water Disposal Well Casing, Wellheads, Services bids

21 days

Thu 4/1/04

Thu 4/29/04

80

Select Water Disposal Well Drilling Contractor

11 days

Thu 4/1/04

Thu 4/15/04

81

Survey

11 days

Sun 6/6/04

Fri 6/18/04

82

Water Disposal Well Licence Application

83

Disposal Well Drill Program

84

Drill Two (2) Water Disposal Wells

85

EUB Water Disposal Application

7 days

Mon 6/21/04

Tue 6/29/04

13 days

Fri 7/16/04

Sat 7/31/04

4 days

Mon 8/23/04

Thu 8/26/04

23 days

Wed 9/1/04

Fri 10/1/04

95 days

Mon 5/10/04

Mon 9/6/04

11 days

Mon 5/10/04

Mon 5/24/04

Assume Spring Breakup


March 15

86
87

Temperature OB wells (5) & Pressure OB Well (1)

88

Select Drilling Contractor for add'l temp / pressure OB wells

89

Confirm Locations based on Horizontal Well Drilling

90

Survey Additional OB Wells

91

Apply for well licences

92

Drill Program for Extra Temp & Press OB wells

93

Drilling Operations

1 day

Fri 7/23/04

Fri 7/23/04

14 days

Sat 7/24/04

Sat 8/7/04

5 days

Sun 8/8/04

Thu 8/12/04

14 days

Mon 8/2/04

Tue 8/17/04

8 days

Fri 8/27/04

Mon 9/6/04

7/23

94
95

79 days

Thu 4/1/04

Thu 7/15/04

96

Two (2) Water Source Wells


Water Source Well Casings and Services Bids

21 days

Thu 4/1/04

Thu 4/29/04

97

Select Water Source Well Drilling Contractor

11 days

Thu 4/1/04

Thu 4/15/04

98

Water Act Licence

77 days

Mon 4/5/04

Thu 7/15/04

99

Water Well Licence

7 days

Thu 4/1/04

Fri 4/9/04

100

Survey

11 days

Mon 5/17/04

Mon 5/31/04

101

Water well Drill Program

14 days

Wed 5/12/04

Mon 5/31/04

102

Drill Water Source Wells

6 days

Tue 6/1/04

Sun 6/6/04

103
104

161 days

Mon 3/1/04

Mon 9/27/04

105

Completion Operations
Confirm Tubular Metalurgy

11 days

Mon 3/1/04

Mon 3/15/04

106

Order Wellheads for Production Wells

69 days

Wed 5/5/04

Mon 8/2/04

107

Bids & Selection of Well Service Contractors

21 days

Mon 5/3/04

Mon 5/31/04

108

Horizontal Well Completion Operations

8 days

Thu 8/12/04

Sun 8/22/04

109

Air Injection Well Completion Operations

5 days

Mon 8/23/04

Fri 8/27/04

110

Water Disposal Well Completion Operations

6 days

Fri 8/27/04

Thu 9/2/04

111

Press OB Well Completion

2 days

Tue 9/7/04

Wed 9/8/04

112

Recompletion of OB Wells

13 days

Thu 9/9/04

Mon 9/27/04

197 days

Mon 3/15/04

Tue 11/30/04

93 days

Mon 3/15/04

Fri 7/16/04

3/1

113
114
115

Engineering; Procurement; Construction


Detailed Facilities Engineering

Page 2

Sep

Qtr 4, 2004
Oct Nov

Dec

Qtr 1, 2005
Jan Feb

Mar

Qtr 2, 2005
Apr May

Jun

Qtr 3, 2005
Jul
Aug

Sep

Qtr 4, 2005
Oct Nov

Dec

Qtr 1, 2006
Jan Feb

WHITESANDS Experimental Project


Preliminary Project Schedule

Orion Oil Canada Limited


ID

Task Name

Duration

Start

Finish

116

Issue Contract for Engineering

1 day

Mon 3/15/04

117

Site Topographic Survey

11 days

Tue 3/16/04

Tue 3/30/04

118

Soils testing

11 days

Wed 3/17/04

Wed 3/31/04

119

Detailed Engineering: Equipment Specification / Site Design

79 days

Mon 3/15/04

Mon 6/28/04

120

Generate RFQ for Equipment

46 days

Tue 5/18/04

Fri 7/16/04

Qtr 4, 2003
Oct Nov

Dec

Qtr 1, 2004
Jan Feb

Mon 3/15/04

Mar

Qtr 2, 2004
Apr May
3/15

Qtr 3, 2004
Jul
Aug

Jun

Sep

Qtr 4, 2004
Oct Nov

Dec

Qtr 1, 2005
Jan Feb

121
122

101 days

Thu 5/27/04

Fri 10/1/04

123

Procurement
Place order for Equipment

50 days

Thu 5/27/04

Fri 7/30/04

124

Equipment Delivery

74 days

Thu 7/1/04

Fri 10/1/04

103 days

Fri 3/19/04

Mon 8/2/04

7 days

Tue 6/1/04

Mon 6/7/04

10 days

Tue 6/1/04

Thu 6/10/04

125
126

Production Site Prep

127

Brushing & Clearing

128

Completed Site Prep Plan including road requirements & facility locations

129

Secure Road Use Agreement with BP

1 day

Mon 5/31/04

Mon 5/31/04

130

Upgrade WHITESANDS Access Road

9 days

Thu 6/3/04

Fri 6/11/04

131

Upgrade BP Road

9 days

Mon 6/14/04

Thu 6/24/04

132

Facilities Site Prep

15 days

Tue 6/15/04

Mon 7/5/04

133

Construction Camp Facilities Move in

1 day

Mon 8/2/04

Mon 8/2/04

5/31

8/2

134
135

9 days

Fri 3/19/04

Wed 3/31/04

136

Utility Contracts - Letters of Intent


Power

1 day

Fri 3/19/04

Fri 3/19/04

3/19

137

Natural Gas

1 day

Fri 3/19/04

Fri 3/19/04

3/19

138

Telecommunications

9 days

Fri 3/19/04

Wed 3/31/04

3/19

Fri 11/26/04

139

Site Utilities

190 days

Mon 3/22/04

140

Gas

190 days

Mon 3/22/04

Fri 11/26/04

141

Power

114 days

Mon 3/22/04

Mon 8/16/04

142

Telecommunication

142 days

Thu 4/1/04

Fri 10/1/04

91 days

Mon 8/2/04

Tue 11/30/04

91 days

Mon 8/2/04

Tue 11/30/04

350 days

Wed 9/1/04

Sat 12/31/05

65 days

Wed 9/1/04

Tue 11/30/04

143
144
145

Construction
Production Facilities Construction

146
147

Commisioning & Startup

148

Inspection

149

Commisioning

150

Start up of Operations

151

Develop Detailed Operating Procedure

23 days

Wed 12/1/04

Fri 12/31/04

261 days

Mon 1/3/05

Sat 12/31/05

186 days

Mon 3/1/04

Mon 11/1/04

152

Start up Plan & Procedure

186 days

Mon 3/1/04

Mon 11/1/04

153

Ignition Procedure

183 days

Mon 3/1/04

Wed 10/27/04

154

Communication Procedure

183 days

Mon 3/1/04

Wed 10/27/04

155

Ongoing Operational Procedure

183 days

Mon 3/1/04

Wed 10/27/04

156

Risk Mitigation Procedure

183 days

Mon 3/1/04

Wed 10/27/04

Fri 11/26/04

1/3

157
158

182 days

Thu 4/1/04

159

HS&E Management
Environment Protection Plan

83 days

Fri 6/11/04

Fri 9/24/04

160

Emergency Response Plan

182 days

Thu 4/1/04

Fri 11/26/04

161

Well Head Emergency Shutoff Valve Write up

1 day

Mon 11/1/04

Mon 11/1/04

162

Global Project Hazops & Risk Analysis

2 days

Thu 4/1/04

Fri 4/2/04

163

Detail Operational Hazop

4 days

Mon 11/15/04

Thu 11/18/04

309 days

Mon 11/10/03

Thu 12/30/04

97 days

Mon 10/20/03

Mon 3/1/04

6/11

11/1

164
165

Reservoir Engineering & Modeling

166
167

Corrosion research Project

Page 3

Mar

Qtr 2, 2005
Apr May

Jun

Qtr 3, 2005
Jul
Aug

Sep

Qtr 4, 2005
Oct Nov

Dec

Qtr 1, 2006
Jan Feb

S-ar putea să vă placă și