Document No:
USE/SI/13/JTC/TSS6/7/10/RPT-1
Submitted to:
M/s. Jurong Town Corporation
Prepared by:
Nanda
No.27 Mandai Estate, #06-11 Innovation Place, Singapore 729931; Tel: 6896 8718 * Fax: 6896 8879
* E-mail: soilinfolee@yahoo.com; *Website: www.unitedsoilengineering.com.sg
Contents
1.
Introduction ........................................................................................................... 1
2.
3.
4.
5.
6.
7.
Conclusions .......................................................................................................... 8
Prepared by
United Soil Engineering
27 Mandai Estate
#06-11 Innovation Place
Singapore 729931
Tel: 6896 8718 Fax: 6896 8879
E-mail: thlee@unitedsoil.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
Method of Drilling
Commence drilling with HW 100mm casing with tungsten shoe using wash boring
method. Clean casings and rods before use.
b)
Drill bits, which can produce a 100mm diameter hole, are used and 100mm diameter
casing with 0.5,1 and 1.5m length were joint and advanced to protect the borehole from
collapsing.
c)
Wash bore to the first sampling depth i.e. UD/SPT @ typically at the specified intervals
below ground level. (Intervals of sampling will be according to specifications).
d)
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
4.2
1.
a)
b)
Lower drill rods with attached SPT split spoon sampler with liner (optional) and catcher
(optional) into borehole to required depth.
c)
On upper portion of rods (protruding out of borehole above ground) mark on rods 3
sections of 150mm each.
d)
Attach hammer coupling to rods and automatic free fall hammer to coupling.
e)
Commence SPT by lifting the hammer weight of standard 63.5kg. vertically by way of a
wire line pulley until hammer automatically drops from height of 30 inches standard. This
indicates 1 blow count. Use guide rods to ensure that the hammer falls vertically onto the
coupling.
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
Supervisor will count and record nos. of blows required to complete each section of
75mm length each (total 6 sections) eg.3:5:7:7:6:6.
g)
Record all penetration in field log e.g. 3:5:7:7:6:6 = 26 blows/300mm. seating drive
criteria for SPT: the seating drive recommendation as stated in BS: 1377: part 9:1990
clauses 3.3.4.2 (a). Based on the clause, the seating drive shall be a penetration of
150mm or 25blows whichever is first reached. The n value would be the subsequent blow
counts over four consecutive 75mm penetration or 100 blows.
h)
i)
Clean outside of split spoon sampler and open the split spoon for visual inspection.
j)
k)
Collect 2 sets of samples and place them in appropriate clear plastic container and cap
the container.
l)
Record details on the label and stick onto the plastic container with sample.
m)
Tape container securely to prevent moisture loss or total loss of sample. One set of
sample is to be delivered to the lab daily while the other set is to be retained on site until
borehole completion.
n)
When test is completed, record sampling / testing details and soil type into the Borehole
Log.
o)
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
a)
At required depth of 3.0m (as example). Halt drilling of borehole with casings at 2.90m. In
soft and stiff soils, the casing is advanced by chopping with water pressure and driven
respectively.
b)
Allow continued flushing of borehole with water, until borehole is cleared of cuttings, with
loose and disturbed material removed.
c)
Detach casings from drilling head, check borehole depth with weighed down measuring
tape (reference used will be the ground level).
d)
Before sampling, the Supervisor/Operator shall check that the tubes are clean, dent free
and cutting edge of the tube is sharp. Check sampling tubes before commencement of
drilling works on a daily basis. With UD sampling equipment ready (open drive sample
tube attached to coupling, attached to drill / sampling rods), lower sampling tube and rods
to the required depth.
e)
h) At top end of sampling rods (protruding out above ground level), mark out on the rods
using appropriate marking tool and rule (chalk and small measuring tape) the length of
sample required. (Say 1m). Usually, a minimum length of 700mm is sufficient.
f)
After marking out, align the rods with the hydraulic drill head maintaining absolute
verticality.
g)
Using the hydraulic drill head, depress the rods into the ground (at the required depth)
until the mark on the drill rods or sampling length is achieved.
h)
Once accomplished, withdraw the drill rods with sample tube which is attached to it
smoothly from borehole. Work Procedure BH Drilling, Sampling and Standard
Penetration Testing Supervisor to check on condition of sample and if necessary, record any indentation, obstructive material like boulder or timber etc., recovery of sample i.e.
60/70 cm, any soil fallen out of bottom of tube etc.
i)
Clean outside of open drive sample tube with clean wet cloth or sponge.
j)
Detach sample tube with soil sample within from drill rod/ adaptor head.
k)
l)
m)
Supervisor to place label onto tube and note down details of sample on label.
n)
After the sealing and labeling process, place the sample tube in an upright position with
bottom of sample tube at ground level. Place tight fitting rubber caps on both ends of the
tube. Wrap the tube with cushion.
Keep sample under the shade on site until ready to be delivered to the office / lab at the
end of each working day.
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
a)
Prepare HX size core barrel with detachable retractable cutting shoe. Fit PVC inner tube
of 2mm thick, 72mm internal diameter and 1m long into the core barrel.
b)
Lower core barrel with Mazier sampler into the borehole and commence drilling. Take
note of rate of penetration by referring to marking on drilling rig next to drill hole axis.
c)
Let cutting of soil in water return pass through sieve to note soil type. (When available
and as appropriate, foam flush will be used).
d)
e)
f)
Mark clearly on the tube the top as TOP and bottom of tube as BOTTOM.
g)
h)
If penetration of Mazier sample is very low and at the discretion of the Supervisor that this
method is not suitable to maximize recovery, drilling will be continued with coring to
facilitate sample extraction.
4.4
Rock Coring
a)
Coring will be generally carried out is soils which are too hard for wash boring method.
b)
Check NMLC triple-tube core barrel, core bit with reamer shell, core boxes to ensure that
they are in proper working conditions.
c)
Advance appropriate casings with diamond tipped casing shoe to rock level and flush
clean of cuttings, sand etc.
d)
Check depth of rock below ground level, lower core barrel and drill rods down to rock
level and commence rock coring.
e)
On achieving core run of 1.00m length, stop coring and extract core barrel and all drill
rods.
f)
Remove core bit and reamer shell, remove core lifter case and core spring, pump out the
split spoon holding the sample, remove one half of the split spoon, identify rock sample,
check recovery of rock sample - quantity and quality.
g)
Lay self clinging sheeting in core box. Remove cores carefully from the core barrel into
core box. Immediately wrap rock sample with the clear sheeting to maintain quality of
sample.
h)
Place sample in the correct order in core box starting with the shallowest core on the left
side nearest the hinge and then working along the slot in sequence. Fill in any core
losses with Styrofoam equal to length of the core lost.
i)
Label the core box inside and outside the lid with the following information - project title,
borehole no, depth of cores, TCR, SCR and RQD (inside lid only), box no and total no. of
boxes. Work Procedure BH Drilling, Sampling and Standard Penetration Testing
j)
Fix up the core barrel and continue with the next core run.
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
l)
m)
Deliver core box to office upon completion of borehole. Take photograph within a week.
The subsurface condition of the site within the vicinity of the borehole is in general,
characterised by the following layers:
BH-01
From GL to 1.5m, trial hole & hand auguring, consists of SAND, from 1.5m to 24.0m, consists
of SAND and from 24.0m to 33.19m, consists of SILT.
Borehole terminated at 33.19m depth (SPT: 20 nos, UD: 2 nos).
BH-02
From GL to 1.5m, trial hole & hand auguring, consists of SAND, from 1.5m to 24.0m, consists
of SAND and from 24.0m to 33.12m, consists of SILT.
Borehole terminated at 33.12m depth (SPT: 19 nos, UD: 1 nos).
BH-03
From GL to 1.5m, trial hole & hand auguring, consists of SAND, from 1.5m to 30.0m, consists
of SAND, from 30.0m to 36.0m consists of CLAY and from 36.0m to 48.23m, consists of SILT.
Borehole terminated at 48.23m depth (SPT: 24 nos, UD: 2 nos).
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
JIMMMY LEE
MANAGER
9367 1409
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
APPENDIX A:
LOG OF BORING
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
APPENDIX B:
SOIL PROFILE CROSS SECTION
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
APPENDIX C:
LABORATORY TEST RESULTS
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg
APPENDIX D:
LOCATION PLAN
No.27, Mandai Estate, #06-11 Innovation Place, Singapore-729931; Tel: 68968718 * Fax: 68968879
* E-mail: soilinfolee@yahoo.com *Website: www.unitedsoilengineering.com.sg