Sunteți pe pagina 1din 12

JOB MIX FORMULA

Job Mix Concrete Volume


A trial batch of concrete can be tested to determine how much concrete is to be
delivered by the job mix. To determine the volume obtained for the job, add the
absolute volume V a of the four componentscements, gravel, sand, and water.

Find the V a for each component from

V a = W L / ( SG ) W u

where V a = absolute volume, ft 3 (m 3 )

W L = weight of material, lb (kg)

S G = specific gravity of the material

W u = density of water at atmospheric conditions (62.4 lb/ft 3 1000 kg /m 3 )

Then, job yield equals the sum of V a for cement, gravel, sand, and water.

http://www.engineeringcivil.com/job-mix-concrete-volume.html/comment-page-1

CONCRETE MIS DESIGN PROCEDURE

Concrete mix designs is best defined as a process in selecting suitable ingredients,


which is cement, aggregate, sand and water, and determining their relative
proportions to give the required strength, workability and durability. The mix
designs, which is a performance specification stating required strength and
minimum cement

Objective of Concrete Mix Design

Concrete Mixer Drum type 140L

Two main objectives for concrete mix design:

To determine the proportions of concrete mix constituents of; Cement, Fine aggregate (or

normally Sand), Coarse aggregate, and Water.


To produce concrete of the specified properties.
To produce a satisfactory of end product, such as beam, column or slab as economically as
possible.

Theory of Mix Designs


The Process of Concrete Mix Design
The method of concrete mix design applied here is in accordance to the method published by the
Department of Environment, United Kingdom (in year 1988).
There are two categories of initial information required:
1.
2.

Specified variables; the values that are usually found in specifications.


Additional information, the values normally available from the material supplier.

Reference data consists of published figures and tables is required to determine the design values
including;

Mix parameters such as target mean strength, water-cement ratio and concrete density.
Unit proportions such as the weight of materials.

The design process can be divided into 5 primary stages. Each stage deals with a particular aspect of the
concrete mix design:
Stage 1: Determining the Free Water/ Cement Ratio
i) Specify the required characteristic strength at a specified age, f c
ii) Calculate the margin, M.
M = k x s .. [ F1 ]
where;
k = A value appropriate to the defect percentage permitted below the characteristic strength. [ k = 1.64 for
5 % defect ]
s = The standard deviation (obtained from CCS 1).

CCS 1: Approximate compressive strength (N/mm2) of concrete mixes made with a free-water/cement ratio of 0.5

iii) Calculate the target mean strength, fm


fm = fc + M .. [ F2 ]

where;
fm = Target mean strength
fc = The specified characteristic strength
iv) Given the type of cement and aggregate, use the table of CCS 1 to obtain the compressive strength, at
the specified age that corresponds to a free water/cement ratio of 0.5.

CCS 4: Relationship between compressive strength and free-water/ cement ratio.

v) In figure CCS 4, follow the starting line to locate the curve which passes through the point (the
compressive strength for water/cement ratio of 0.5). To obtain the required curve representing the
strength, it is necessary to interpolate between the two curves in the figure. At the target mean strength

draw horizontal line crossing the curve. From this point the required free water/cement ratio can be
determined.
Stage 2: Determining the Free-Water Content

CCS 2: Approximate free-water contents (kg/m3) required to give various levels of workability.

Given the Concrete Slump or Vebe time, determine the free water content from table CCS 2.
Stage 3: Determining the Cement Content
Cement Content = Free Water Content / Free-water or Cement Ratio

.. [ F3 ]

The resulting value should be checked against any maximum or minimum value that may be specified. If
the calculated cement content from F3 is below a specified minimum, this minimum value must be
adopted resulting in a reduced water/cement ratio and hence a higher strength than the target mean
strength. If the calculated cement content is higher than a specified maximum, then the specified strength
and workability simultaneously be met with the selected materials; try to change the type of cement, the
type and maximum size of the aggregate.
Stage 4: Determining the Total Aggregate Content
This stage required the estimate of the density of fully compacted concrete which is obtained from figure
CCS 5. This value depends upon the free-water content and the relative density of the combined aggregate
in the saturated surface-dry condition. If no information is available regarding the relative density of the
aggregate, an approximation can be made by assuming a value of 2.6 for un-crushed aggregate and 2.7 for
crushed aggregate.

CCS 5: Estimated wet density of fully compacted concrete.

With the estimate of the density of the concrete the total aggregate content is calculated using equation
F4:
Total Aggregate Content = D C W

.. [ F4 ]

where;
D = The wet density of concrete ( in kg/m3)
C = The cement content (in kg/m3)
W = The free-water content (in kg/m3)
Stage 5: Determining of The Fine and Coarse Aggregate Contents
This stage involves deciding how much of the total aggregate should consist of materials smaller than 5
mm, i.e. the sand or fine aggregate content. The figure CCS 6 shows recommended values for the
proportion of fine aggregate depending on the maximum size of aggregate, the workability level, the
grading of the fine aggregate (defined by the percentage passing a 600 m sieve) and the free-water/
cement ratio. The best proportion of fines to use in a given concrete mix design will depend on the shape
of the particular aggregate, the grading and the usage of the concrete.

CCS 6: Recommended proportions of fine aggregate according to percentage passing a 600 m sieve.

The final calculation, equation F5, to determine the fine and coarse aggregate is made using the
proportion of fine aggregate obtained from figure CCS 6 and the total aggregate content derived from
Stage 4.
Fine Aggregate Content = Total Aggregate Content x Proportion of Fines .. [ F5 ]
Coarse Aggregate Content = Total Aggregate Content Fine Aggregate

Procedures of Design Mixing


Production of Trial Mix Design
1.
The volume of mix, which needs to make three cubes of size 100 mm is calculated. The volume of
mix is sufficient to produce 3 numbers of cube and to carry out the concrete slump test.
2.
The volume of mix is multiplied with the constituent contents obtained from the concrete mix
design process to get the batch weights for the trial mix.
3.
The mixing of concrete is according to the procedures given in laboratory guidelines.
4.
Firstly, cement, fine and course aggregate are mixed in a mixer for 1 minute.
5.
Then, water added and the cement, fine and course aggregate and water mixed approximately for
another 1 minute.
6.
When the mix is ready, the tests on mix are proceeding.

Slump Test apparatus for Concrete Workability

Tests on Trial Mix Design


1.
The slump tests are conducted to determine the workability of fresh concrete.
2.
Concrete is placed and compacted in three layers by a tamping rod with 25 times, in a firmly held
slump cone. On the removal of the cone, the difference in height between the uppermost part of the
slumped concrete and the upturned cone is recorded in mm as the slump.

3.

Three cubes are prepared in 100 mm x 100 mm each. The cubes are cured before testing. The
procedures for making and curing are as given in laboratory guidelines. Thinly coat the interior
surfaces of the assembled mould with mould oil to prevent adhesion of concrete. Each mould filled
with two layers of concrete, each layer tamped 25 times with a 25 mm square steel rod. The top
surface finished with a trowel and the date of manufacturing is recorded in the surface of the concrete.
The cubes are stored undisturbed for 24 hours at a temperature of 18 to 22 0C and a relative humidity
of not less than 90 %. The concrete all are covered with wet gunny sacks. After 24 hours, the mould is
striped and the cubes are cured further by immersing them in water at temperature 19 to 21 oC until
the testing date.
4.
Compressive strength tests are conducted on the cubes at the age of 7 days. Then, the mean
compressive strengths are calculated.

The Calculations

Here is one example of calculation from one of the concrete mix design obtained from the laboratory. We
have to fill in all particulars in the concrete mix design form with some calculations

CCS 3: Relationship between standard deviation and characteristic strength.

Firstly, we specified 30 N/mm2 at 7 days for the characteristic strength. Then, we obtained the standard
deviation, s from the figure CCS 3. So, s = 8 N/mm2.
From the formula F1, k = 1.64 for 5 % defect. The margin, M is calculated as below:
M = k x s = 1.64 x 8 = 13.12 N/mm2

With the formula F2, target mean strength, fm is calculated as below:


Target mean strength, fm = fc + M
= 30 + 13.12 = 43.12 N/mm2
The type of cement is Ordinary Portland Cement (OPC). For the fine and course aggregate, the
laboratorys fine aggregate is un-crushed and for coarse aggregate is crushed before producing concrete.
Then, we obtain the free-water/ cement ratio from table CCS 1. For OPC ( 7 days ) using crushed
aggregate, water/cement ratio = 36 N/mm2.
After that, from the figure CCS 4, the curve for 42 N/mm2 at 0.5 free-water ratio is plotted and obtained
the free-water ratio is 0.45 at the target mean strength 43.12 N/mm 2.
Next, we specified the slump test for slump about 20 mm and the maximum aggregate size we used in
laboratory is 10 mm. For the specified above, we can obtained the free-water content from table CCS 2 at
slump 10 30 mm and maximum size aggregate 10 mm, the approximate free-water content for the uncrushed aggregates is 180 kg/m3 and for the crushed aggregates is 205 kg/m3. Because of the coarse and
fine aggregates of different types are used, the free-water content is estimated by the expression:
Free-water Content, W
= 2/3 Wf + 1/3 Wc
= (2/3 x 180) + (1/3 x 205)
= 188.33 kg/m3
where,
Wf = Free-water content appropriate to type of fine aggregate
Wc = Free-water content appropriate to type of coarse aggregate
Cement content also can obtained from the calculation with the expression at F3:
Cement Content, C = Free Water Content / Free-water or Cement Ratio
= 188.33 / 0.45 = 418.52 kg/m3
We assumed that the relative density of aggregate (SDD) is 2.7. Then, from the figure CCS 5 with the freewater content 188.33 kg/m3, obtained that concrete density is 2450 kg/m3. The total aggregate content
can be calculated by:
Total Aggregate Content = D C W
= 2450 418.52 188.33 = 1843.15 kg/m3
The percentage passing 600 m sieve for the grading of fine aggregate is about 60 %. The proportion of
the fine aggregate can be obtained from the figure CCS 6, which is 38 %. Then, the fine and course
aggregate content can be obtained by calculation:
Fine Aggregate Content
= Total Aggregate Content x Proportion of Fines
= 1868.74 x 0.38 = 700.40 kg/m3
Coarse Aggregate Content = Total Aggregate Content Fine Aggregate
= 1843.15 700.40 = 1142.75 kg/m3
The quantity per m3 can be obtained, which is;
Cement
= 418.52 kg
Water
= 188.33 kg

Fine aggregate
= 700.40 kg
Coarse aggregate (10 mm) = 1142.75 kg
The volume of trial mix for 3 cubes
= [(0.1 x 0.1 x 0.1) x 3] + [25% contingencies of trial mix volume]
= 0.006 + 0.00075
= 0.00375 m3
The quantities of trial mix = 0.00375 m3, in which is;
Cement
= 1.57 kg
Water
= 0.71 kg
Fine aggregate
= 2.61 kg
Coarse aggregate (10 mm) = 4.29 kg
The Results of Mix Design
Slump Test = True Slump of 55 mm
All the 3 concrete cubes produced were then cured for 7 days. After that, the compressive cube test is
carried out. The results are as follows:

Sample

Compressive Strength

32.37

33.54

35.70

Average

(32.37 + 33.54 + 35.70) / 3 = 33.87

For cubes after 7 days of curing, compressive strength should not be less than 2/3 target mean strength.
= 2/3 43.12 = 28.75 N/mm2 < 33.9 N/mm2
After 7 days of curing, the compressive strength of concrete cubes produced by the mix design method
pass the specific strength requirements.

Discussions Upon Concrete Mix Designs


Although our compressive strength passes the specific requirements, we still identified several factors
which contribute to the lacking of compressive strength of concrete mixes produced in the
experiment. However, the main factor is the condition of aggregates whether it is exposed to sunlight or
rainfall.
When the free water/cement ration is high, workability of concrete is improved. However, excessive water
causes honey-comb effect in the concrete produced. The concrete cubes become porous, and hence its
compressive strength is well below the design value. Other possible reasons include over compaction,
improper mixing methods and some calculation errors.
Few suggestion upon several steps to avoid the problems previously faced:

All the raw materials, which is cement, aggregates, and sand should be protected from

precipitation or other elements which may affect its physical properties.


The quantity of ingredients may be adjusted if necessary, theoretical values are not always

suitable. For example, if the aggregates are wet or saturated, less amount of water should be added,
vice versa.
Compaction should be done carefully, as either under or over-compaction will bring significant
negative effect on the concrete produced.

The Conclusion
1.

By using the concrete mix design method, we have calculated the quantities of all ingredients, that
is water, cement, fine and coarse aggregate according to specified proportion.
2.
The concrete produced did not fulfill the compressive strength requirements due to several
reasons. Furthermore, some steps mentioned above should be taken into consideration to overcome
this problem.

S-ar putea să vă placă și