1. Project Outline
2. Risks Assessment & Impact to
Surrounding Neighborhood
3. ECM Criteria & Considerations
4. Earth Control Measures
5. Silt Water Treatment & Recycling
System
6. Construction Sequence
Project Outline
1.1
Project Outline
Phase 2
Proposed to Develop an Open Space (Urban Park) including a
Sunken Plaza and Outdoor Refreshment Area within the above
mentioned compound
Owner :
Architect :
Retail Consultant :
Quantity Surveyors:
M&E Engineer :
Parsons Brinckerhoff
Structural Engineer
Contract Period
33.5 Months
GFA
65,642 m2
Site Area
14,620 m2
9 STOREY
TOWER
SERANGOON
Phase 1
Proposed Erection of a 9th Storey Development comprising a Retail
Podium from the 1st to 5th Storey, an Annex Tower from the 6th to
9th Storey and 4 level Basement consisting 2 level of Basement
Carpark, 2 level of Basement Retail and other Ancillary Facilities at
Serangoon Area Bounded by Serangoon Road, Kitchener and
Kitchener Link
ROAD
Site :
SUNKEN
PLAZA
KITCH
EN
6 STOREY
PODIUM
ER
ROAD
Serangoon Road
SITE
Kitchener Road
Internal View Of
Internal View Of
Farrer Park MRT
Farrer Park MRT
Existing Commercial
Existing Commercial
Building at Kitchener Road
Building at Kitchener Road
GATE 2
GATE 3
OUTLINE OF CONSTRUCTION
OUTLINE OF CONSTRUCTION
SITE HOARDING
SITE HOARDING
OUTLINE OF BASEMENT
OUTLINE OF BASEMENT
DIAPHRAGM WALL
DIAPHRAGM WALL
Site office
Site office
AD D
O
R A
N RO
O
O N
G OO
N
G
RA AN
E
R
S E
S
NEIGHBORING CONSTRUCTION
NEIGHBORING CONSTRUCTION
SITE CITY RESIDENCES (By
SITE CITY RESIDENCES (By
Others)
Others)
MRT
MRT
Entrance
Entrance
Gate 2
Gate 2
KITCH
ENER
KITCH
ENERROAD
ROAD
Gate 3
Gate 3
discharge into the storm water drainage system shall not contain Total
Suspended Solids in concentrations greater than 50 milligrams
per litre of the discharge.
Calculations:
Surface Area of Basement
Exposed to Weather
12,500 m2
IL=102.093
300m m WIDE
SILT CUT-OFF DRAIN
Z2
SUMMIT
IL=102.370
102.920
102.670
102.670
HOARDING ALONG TOL LAND
102.840
102.970
IL=101.967
103.900
WA
T
TR ER P
AN
SF IPE/ H
ER
SIL OSE
TO
TY
WA
TE
R
PORTION OF EXISTING
HOARDING TO BE REMOVED
UPON APPROVAL OF T.O.L
TEMPORARY
SILT FENCE
IL=102.530
GATE 1
102.890
103.270
4
NEW HOARDING
LOCATION OF SILTWATER
PIT FROM MONTH-0 TO MONTH-4
LOCATION OF SILTWATER
PIT FROM MONTH-5 TO MONTH-8
Z1
SUMMIT
IL=103.200
5
103.670
300mm WIDE
SILT CUT-OFF DRAIN
103.050
102.700
102.870
6
102.830
102.830
8
IL=102.530
IL=102.384
SILT TRAP
1m X 1m X 1m(D)
SILTW ATER
TREATMENT
PLANT
102.290
GATE 2
SUMMIT
IL=101.990
GATE 3
Silt Traps
DETAIL OF INTERMEDIATE
SILT TRAP
S E C T I O N
X - X
TEMPORARY
SILT FENCE
BOUNDARY / HOARDING LINE
WORKING AREA
DIAPHRAGM WALL
Extra Precautionary Measures for the Control of Slurry & Silt during Diaphragm Wall Works
Earth Control Measures - Bentonite Control for Diaphragm Wall & Bored Piling
Works
To reduce risk of bentonite being washed away into the public drains, a bentonite
recycling plant will be installed on site.
,
/
- .
&
"(
Construction Water
< 1 m3/day
!"
$
%
Ground Water
10 m3/hr
$
&
'
'
#
From site
From ISR
Discharging
Construction Sequence
Construction Sequence
The whole structure will be constructed in a top-down sequence. As such, the bare
earth surface at ground level will not be exposed to weather for a long period of time.
By the 14th month, the basement structure will be gradually covered by a permanent
slab at ground level which will also serve as a working and access platform. Hence, the
risk of the bare earth surface being exposed to rainfall is minimized.
0 to Month 6
Month 7 to Month 13