Documente Academic
Documente Profesional
Documente Cultură
CHANTIERS/WORKSITES
Andrea BELLOCHIO
Stone Spa
Rosanna SICILIA
Stone Spa
Figure 1 - Extrait de la carte montrant le trac du mtro de Brescia / Map extract of the route of the Brescia underground.
Astaldi S.p.A.
Trac
331
CHANTIERS/WORKSITES M
Gologie
La zone urbaine de Brescia se situe au
pied de la partie terminale du Val
Trompia et concide avec le cne alluvial de la rivire Mella son dbouch
sur la plaine de Lombardie ; morphologiquement, elle se prsente en gros
comme une plaine. Les collines qui
entourent la plaine de Brescia sont des
formations sdimentaires du Msozoque, essentiellement de nature
marno-calcaire. Ces formations rsultent de dplacements dus des chevauchements caractre rgional et,
localement, des failles transversales.
La zone concerne correspond une
formation msozoque fortement marque par un processus drosion du
Cnozoque et remplie de dpts alluvionnaires disposition variable de
subhorizontale localement incline.
Les processus morphogntiques qui
ont profondment modifi cette zone
peuvent dans lensemble tre schmatiss comme une expansion de glaciers
qui, dans les formations msozoques,
provoque des phnomnes intenses
et gigantesques de broyage et de
transports solides ; le travail des cours
deau, en contribuant la destruction
des formations msozoques et
miocniques, a remodel les dpts
glaciaires, leur donnant ainsi des caractristiques granulomtriques complexes.
Au plan lithologique, ces dpts sont
composs de sables, graviers et galets
dans une matrice argilo-limoneuse
plus ou moins importante, parfois plus
abondante. Cest sur ce type de terrain
quest situ le cur de la ville de Brescia.
Lanalyse dtaille des dpts situs
au-dessus de la base carbonifre qui
forment le cne alluvial de la Mella
conduit distinguer trois horizons sdimentaires, avec des dpts subhorizontaux et de frquentes htrognits
parmi les lithotypes en prsence dues
des variations lors des processus
rosion-dpt. Ces trois horizons, du
plus superficiel sur lequel reposent
les structures urbaines au plus pro-
332
2G
2GS
2GSL
Geology
The urban area of Brescia is in the
foothills at the end of Val Trompia
coinciding with the alluvial fan of the
River Mella, at its outlet onto the
Lombard plain and, overall, has the
morphology of a plain. The hills
around the Brescia plain consist of
Mesozoic sedimentary formations
mainly of a limestone-marl nature.
These formations are distributed with
CHANTIERS/WORKSITES
Hydrologie
Lhydrologie de surface de la zone est
rgule par plusieurs cours deau dont
Sous-groupe
Sub unit
Poids spcifique
Weight / unit of volume (kN/m3)
Angle de frottement
Friction angle
2G
22,00
38-42
2GS
21,00
37-40
2GSL
20,00
36-38
()
Hydrology
Surface hydrology in the area is regulated by the development of many
water-courses, of which the most
important are the Rivers Mella and
Garza, the latter being intersected in
several points by the Metrobus route.
Artificial canals and ditches connecting to the main water-courses complete the surface water network.
The subsoil of Brescia is the site of
considerable water circulation, fed by
the catchment and hydrogeological
basin of Val Trompia, which permeates the alluvial deposits with a
piezometric oscillation field confined
to the upper deposits. Low permeability horizons (silt-clay) in the alluvial
succession are often the site of local
suspended water-tables which justify
irregular depth to water table values.
The rainfall in the area has been quite
constant in the last 200 years and is
about 1,000 mm/year with rare
peaks of more than 1,250 mm/year.
Considering the run-off and evapotranspiration component, as well as
human channelling of rainwater, an
infiltration rate of 15% of the annual
rainfall can, very approximately, be
considered in the area.
333
CHANTIERS/WORKSITES M
Figure 4 - Section longitudinale du
tunnelier / Longitudinal section
of the EPB-S.
2 - Procdure dtablissementdu projet pour lvaluationde linteraction sol-structureNous dcrivons ci-aprs une synthse
de la procdure adopte par le Mtro
de Brescia pour lvaluation du risque
potentiel de dommages aux structures
existantes, ainsi que la procdure pratique au plan international laquelle
334
Astaldi SpA
2 - The project procedurefor the assessment of thesoil-structure interactionA summary of the project procedure
adopted for Brescia underground in
the sphere of the assessment of the
potential risk of damage to buildings
is shown below.
The project procedure used at international level, to which refinements
were applied in the definition of the
class of damage, is also shown
below.
Step A - Preliminary Assessment
This is the project assessment of the
deformation situation induced by the
excavation of the tunnel. This leads
CHANTIERS/WORKSITES
Type de btiment
Type of building
Btiments BA
Buildings in reinforced concrete
1/2
1
0/1
3 - Traverse du complexe Punto e Virgola :estimations relativesau projetLa traverse du complexe immobilier
Punto e Virgola mrite une attention
3 - Crossing the Punto eVirgola complex - projectforecastsThe passage of the Punto e Virgola
complex merits special attention.
Passing under the Punto e Virgola
building was within the scope of the
excavation of the long stretch from
Lamarmora station (pk 8+686.80) to
Brescia 2 station (pk 7+867.78) and
saw the excavation by EPB-S of
about 530 m of tunnel. Consider the
difference in progress between the
start of the south stretch, pk
8+148.73, and the end of the north
part, pk 7+918.50.
Under the project procedure of analysis of the soil-structure interaction
described above, the deformation
behaviour of the soil, i.e. the extent
of the subsidence and the distortions
induced by excavation and also the
effects in terms of risk for the buildings, was examined. The project
analyses made took into account the
335
CHANTIERS/WORKSITES M
Cuvettes de tassement
Subsidence basins
Niveau rgional
Country level
Couverture [m]
Level cover [m]
i [m]
Largeur de
cuvette [m] Smax
3i [m]
Basin
[cm]
width [m]
8+600
17,02
7,56
22,67
45,35
-1,74
8+540
16,70
7,45
22,34
44,68
-1,76
8+518
16,78
7,47
22,42
44,85
-1,75
8+490
16,51
7,38
22,14
44,28
-1,78
8+479
16,92
7,52
22,57
45,14
-1,74
8+417
16,63
7,42
22,27
44,53
-1,77
8+394
18,40
8,04
24,12
48,25
-1,63
8+370
18,17
7,96
23,88
47,76
-1,65
8+302
20,12
8,64
25,93
51,86
-1,52
8+237
19,65
8,48
25,44
50,87
-1,55
8+200
20,35
8,72
26,17
52,34
-1,50
Progr. [km]
336
n immeuble / n Building
Figure 6 - Classification des dommages sur la section entre les stations St.Lamarmora et Brescia 2 /
Classes of damage on the section from Lamarmora station to Brescia 2 station.
CHANTIERS/WORKSITES
est reste constante 17 m environ
sur la longueur dexcavation concerne, entre la station Lamarmora (pk 8
+ 686,80) et le pk 8 + 417. Ensuite,
la couverture augmente jusqu 20 m
environ la station Brescia 2 (pk 7 +
867,78).
Lexamen de ltat de dformation
induit par lexcavation, dtermin selon
les mthodes empiriques de la littrature technique (Peck 1969, Attwell et
Fermer 1974, Attwell et Woodman
1982, OReilly et New 1982, Rankine
1987 et Shirlaw & Doran 1988), montre une augmentation progressive de
lemprise de la cuvette transversale de
tassement en fonction de la variation
de couverture (de 44 52 m) et une
diminution progressive du tassement
prvu au niveau du sol, en adoptant une
valeur moyenne de k=0,35, valeur confirme par le plot dessai, et une valeur de
0,50 % de perte de volume (Tab. 3).
Il est noter que le tassement maximum prvu au stade du projet tait
de Smax = 1,50 - 1,78 cm. Sur la base
de ce tassement induit par le creusement et au vu des caractristiques
gomtriques et structurelles des
immeubles et de leur tat de conservation, la catgorie de dommages fut
Figure 8A et 8B - Extrait de la coupe gologique au niveau du complexe Punto e Virgola / Extract of the geological section of the Punto e Virgola complex.
337
CHANTIERS/WORKSITES M
Variations de pertes de volume / Variations in volume losses
Vp = 0,5 %
Position of building
Couver[m]
ture
pm
Progressive
Building
Vp = 0,7 %
Dplacement
Tasse- Dplacement
vertical
ment
horizontal
max.
max. Vertical movement
Max Max horizontal
subsi- moveL
R
dence... ment
Dommage/
Type
dimmeuble
Damage
/building
category
Dplacement
Tasse- Dplacement
vertical
ment
horizontal
max.
max. Vertical movement
max
Max Max horizontal
subsi- moveL
R
dence... ment
Vp = 1 %
Dommage/
Type
dimmeuble
Damage/
building
category
Dplacement
Tasse- Dplacement
vertical
ment
horizontal
max.
max. Vertical movement
max
Max Max horizontal
subsi- moveL
R
dence... ment
Dommage/
Type
dimmeuble
Damage/
building
category
max
Cover
[m]
8+237 573 l
-45
-7,6
-3,08
0,65
0,00
-1,55
0,119 -4,31
0,91
0,00
-2,16
0,167 -6,16
1,31
0,00
-3,09
0,238
8+237 573 ll
-5
43,5
-7,6
-3,08
0,65
-1,55
0,00
0,033 -4,31
0,91
-2,16
0,00
0,047 -6,16
1,31
-3,09
0,00
0,066
8+200 573 l
-38
12,5
-7,3
-3,16
0,67
0,00
-0,03
0,125 -4,42
0,94
0,00
-0,05
0,175 -6,31
1,34
0,00
-0,07
0,251
8+200 573 ll
12,5
51
-7,3
-3,16
0,67
-0,03
0,00
0,001 -4,42
0,94
-0,05
0,00
0,002 -6,31
1,34
-0,07
0,00
0,002
Tableau 4 : Dfinition des classes de dommages au complexe Punto e Virgola pour Vp = 0,50%, 0,70% et 1% / The definition of the classes of damage by Vp = 0.50%,
0.70% and 1% in the Punto e Virgola complex
Synthse des valeurs maximum de et des classes de dommages / Max values and damage classes
Section
Figure 9A
338
Punto and the Virgola - with another eight floors and a technical
connection floor between the plate
and the towers, emerge above this
vast plate. The circular tunnel 9.15 m
in diameter has a cover of about
7.60 m with respect to the foundation
level of the building in the area of
interaction with the line of the underground. The existence of such little
cover, less than the diameter of excavation and not found in the previously
excavated parts, induced in-depth
analysis through a series of inter-disciplinary activities. The on-site inspections made highlighted a series of
cracks, concentrated mainly on partitions and cladding. As far as the
plate of the building was concerned,
these were generally obvious threads
that, in some cases, had the size of
lesions in the underground floors. The
most important phenomena for
extent and distribution were found on
the cladding along the joints and/or
near to these with a scale of importance that decreases from the third
underground level to the first floor
above ground.
There were only threads on some of
the partitions and along the vertical
joints of the internal faade panelling of the Punto tower, with a circular plan.
A more obvious situation of cracks,
both by amount and spread, was
found on the Virgola tower (although
not by much), limited, however, to the
architectural apparatus, particularly
in the area of the elbow on the plan
corresponding to the projection of the
joint. From the geological point of
view, the soil under the foundation
level of the plinths of the building
consists of a formation with alternating gravel, sand and silt; the tunnel
was concerned with a stratification
of medium to fine silty sand, with
polygenic gravel, for most of the
excavation. An extract of the section
with the geology of the part under
consideration is shown herein.
The maximum subsidence (Fig. 9B, 9C,
9D), referring to the cover between the
foundation level and the keystone of
the roof, is calculated for that building
with the project hypothesis of k = 0.35
and Vp = 0.50% and is then equal to
Smax = 3.16 cm. The complex in
consideration therefore had a series of
critical elements such as:
the low cover value between the
CHANTIERS/WORKSITES
Section
Gauche / Left
Droit / Right
Building
Tassement / Settlement
Section
Tassement / Settlement
Section
Tassement / Settlement
339
CHANTIERS/WORKSITES M
Sans traitement /
Without treatment
340
Thorique /
Theoretical
Trac du tunnel /
tunnel layout
Figure 12 A
Avec traitement /
With treatment
CHANTIERS/WORKSITES
Figure 12A, 12 B et 12 C - Vue en plan et coupes-types du traitement
de consolidation du complexe / Diagram and typical sections of the consolidation
operation of the complex.
Figure 12 C
Figure 12 B
Technique dinjection
Les injections furent ralises au
moyen de tubes plastiques de diamtre
Injection technology
Injections were performed using
11/8 plastic tubes fitted with rubber
341
CHANTIERS/WORKSITES M
Figure 13 - Extrait de la vue en plan du systme de surveillance du complexe pendant les travaux /
Extract of the monitoring plan of the complex during construction.
5 - Surveillance prvueen cours de travauxAu cours des injections de consolidation puis pendant les phases davancement de lexcavation, a t dfini et
intgr le systme de surveillance dj
mis en place sur toute la longueur
excave du tunnel.
En fait, pour le complexe Punto e Virgola , tant donne la particularit des
travaux de consolidation dont il faisait
lobjet, il a fallu mettre en place un systme de surveillance automatis qui a
342
The monitoring system already prepared along the whole line of the
shielded tunnel was defined and integrated during the consolidation injections and subsequently during the
stages of progress of the excavation.
Given the special nature of the
consolidation work that the building
in question was subjected to, an
automated monitoring system also
used during the stages relating to the
passage of the TBM was arranged for
the complex so that continuous
control could be made of the movements induced in the reinforced
concrete structures above. Therefore,
movements in the structures were
monitored through automated topographic levelling with readings made,
on average, every hour. The measurement points were placed on the pillars of the structure on the garage
floor about 7 m above the level of
work.
The data acquisition system was set
so that an alarm signal was given
every time that the reading of a measurement point exceeded the pre-set
threshold level. Initially, this was set
at 5 mm for all the measurement
points. These values were changed
to allow effective management of
injection operations in real time
during the work, with the development of lifting of the pillars above the
injection area. The extract from the
monitoring plan is shown below.
CHANTIERS/WORKSITES
also because mechanised excavation wouldnt have required a particularly intense and homogenous
treatment - as would have been
necessary with traditional excavation. The borer passed under the
building between the 15 and 20 May
without any problems.
A summary report of the subsidence
recorded during both the performance of the consolidation operations and the passage of the borer is
shown. The trend in lift induced by
just the injections of cement, in the
form of contour levels, can be deduced from Figure 14. With reference
to the repercussions induced by the
passage of the borer, Figure 15
shows how the maximum subsidence found in the blue area was
between 8 and 11 mm, and relates
to the area not influenced by the
injections. The red areas, not involved in the treatment, recorded subsidence of between 4.5 and 8 mm
while the green areas, involved in the
operation, suffered settlement in the
order of 4.5 mm.
See Figure 16 for a summary of the
movement occurring to the measurement points over the period of time
from the consolidation stage to after
the passage of the borer. This was a
practically definitive situation except
for the tail effect, of a very modest
amount which, however, worked
itself out within a few weeks.
Figure 14 - Soulvements
induits par linjection de
coulis de ciment. En vert,
la zone dans laquelle ont
t relevs des tassements
jusqu un maximum de
3 mm. En bleu, les valeurs
suprieures jusqu un
maximum de 6,5 mm
sous la file de poteaux E /
Uplift induced by the injection of cement mix. The area in which there was lift of up to 3 mm is in
green; higher values up to a maximum of 6.5 mm under the line of columns E are in blue.
343
CHANTIERS/WORKSITES M
7 - Conclusions-
7 - Conclusions-
Il faut souligner ici que les excellents rsultats obtenus pour la traverse
de la zone du complexe Punto e Virgola sont en phase avec les prvisions du projet. Ainsi, lhypothse dune efficacit parfaite de la vote
de consolidation a permis de prvoir une limitation des tassements
effectifs des valeurs proches du centimtre. t
Remerciements
Thanks
Tunnels et Espace Souterrain remercie la revue Strade & Autostrade qui a publi
cet article en italien dans son numro 1-2009 ainsi que Enrico Arini, prsident
de la SIG, et Piergiorgio Grasso, prsident de Geodata, pour leur assistance
auprs du matre douvrage qui nous a autoriss le traduire et le publier.
Tunnels et Espace Souterrain wishes to thank the Strade & Autostrade Editors
who published this paper in Italian (issue 1-2009) as well as Enrico Arini,
president of SIG and Piergiorgio Grasso, president of Geodata, for their help in
getting the agreement of the Owner for translating and publishing this paper.
MMM-Bibliographie [1] P.B. Attewell, J.P. Woodman - Predicting the dynamics of ground settlement and its derivatives caused by tunnelling in soil, Ground Engineering, Vol. 18,
n8, pp. 13-22, 36, 1982.
[2] P.B. Attewell, J. Yeates, A.R. Selby - Soil movements induced by tunnelling and their effects on pipelines and structures, Blackie, 1986.
[3] M.D. Boscardin, E.G. Cording - Building response to excavation-induced settlement, Jnl. Geo Engrg, ASCE 115, 1-21, 1989.
[4] J.B. Burland - Assessment of risk of damage to buildings due to tunnelling and excavations. Invited Special Lecture, Tokyo 95, 1st Int. Conf. on Earthquake
Geotechnical Engineering, 1995.
[5] J.B. Burland, C.P. Worth - Settlement of building and associated damage, SOA Review, Conf. Settlement of structures, Cambridge, Pentech Press. London,
pp. 611-654, 1974.
[6] R.J. Mair, R.N. Taylor, J.B. Burland - Prediction of ground movements and assessment of risk of building damage due to bored tunnelling, Geotechnical
Aspects of Underground Construction in Soft Ground, Balkeman, Rotterdam, 1996.
[7] D.M. Potts, T.I. Addenbrooke - The influence of an existing surface structure on ground movements due to tunnelling, 1996.
[8] H.J. Burd, G.T. Houlsby, C.E. Augarde - Modelling tunnelling-induced settlement of masonry building, Geotech. Engng., 143, 17-29, Jan. 2000.
[9] M. Melis, L. Medina, J.M. Rodriguez - Prediction and analysis of subsidence induced by shield tunnelling in the Madrid Metro extension, Geotech. J.39, 2000.
344