Documente Academic
Documente Profesional
Documente Cultură
DAIHO CORPORATION
JAPAN
AND
23-May-13
ITEM DESCRIPTION
UNIT
QTY
AMOUNT
(RS)
AMOUNT (JPY)
CW(1)
CONSTRUCTION WORK
Water Intake and Water Treatment Plant
L.Sum
1.00
148,991,256
112,023,497
CW(2)
L.Sum
1.00
83,088,969
62,472,910
CW(3)
L.Sum
1.00
51,950,334
39,060,405
CW(4)
Transmission Pipe
L.Sum
1.00
40,187,869
30,216,444
CW(5)
L.Sum
1.00
150,183,976
112,920,285
CW(6)
L.Sum
1.00
56,802,215
42,708,432
CW(7)
L.Sum
1.00
12,963,303
9,746,848
CW(8)
L.Sum
1.00
37,913,471
28,506,361
582,081,393
437,655,182
Sub Total 01
PWE(a)
L.Sum
1.00
8,422,800
6,332,932
PWE(b)
Labouratory Instruments
L.Sum
1.00
1,778,400
1,337,141
PWE(c)
L.Sum
1.00
322,400
242,406
10,523,600
7,912,479
592,604,993
445,567,661
Sub Total 02
Narayananan Associates
ITEM NO
ITEM DESCRIPTION
UNIT
QTY
1Yen=1.33 SL Rs
AMOUNT
(RS)
1.33
AMOUNT (JPY)
CW(1)
CONSTRUCTION WORK
Water Intake and Water Treatment Plant
L.Sum
1.00
130,751,338
98,309,273
CW(2)
L.Sum
1.00
72,916,990
54,824,805
CW(3)
L.Sum
1.00
45,590,432
34,278,523
CW(4)
Transmission Pipe
L.Sum
1.00
35,267,960
26,517,264
CW(5)
L.Sum
1.00
131,798,042
99,096,274
CW(6)
L.Sum
1.00
49,848,332
37,479,949
CW(7)
L.Sum
1.00
11,376,300
8,553,612
CW(8)
L.Sum
1.00
33,272,000
25,016,534
510,821,394
384,076,234
Sub Total 01
PWE(a)
L.Sum
1.00
8,422,800
6,332,932
PWE(b)
Labouratory Instruments
L.Sum
1.00
1,778,400
1,337,141
PWE(c)
L.Sum
1.00
322,400
242,406
10,523,600
7,912,479
Sub Total 02
IC(a)
INDIRECT COST
Common Temporary Work
L.Sum
1.00
27,750,000
20,864,662
IC(b)
Onsite Expences
L.Sum
1.00
43,510,000
32,714,286
71,260,000
53,578,948
592,604,994
445,567,661
Sub Total 03
Narayananan Associates
Description
Unit
Qty
WI 01
WATER INTAKE
NEW INTAKE PIT
L.Sum
1.00
4,443,120
3,340,692
WI 02
INTAKE SUMP
L.Sum
1.00
1,210,040
909,802
WI 03
L.Sum
1.00
646,000
485,713
WI 04
L.Sum
1.00
1,050,000
789,474
RW 01
L.Sum
1.00
656,240
493,413
WTP 01
L.Sum
1.00
39,925,312
30,019,032
WTP 02
L.Sum
1.00
1,320,080
992,541
WTP 03
L.Sum
1.00
41,148,642
30,938,831
WTP 04
L.Sum
1.00
4,591,652
3,452,371
WTP 05
STORAGE POND
L.Sum
1.00
3,366,154
2,530,942
WTP 06
ADMINISTRATION BUILDING
L.Sum
1.00
877,440
659,728
WTP 07
GENERATOR HOUSE
L.Sum
1.00
5,741,501
4,316,917
WTP 08
GUARD HOUSE
L.Sum
1.00
891,054
669,965
WTP 09
YARD PIPING
L.Sum
1.00
8,550,260
6,428,767
WTP 10
LANDSCAPING
L.Sum
1.00
14,983,843
11,266,047
WTP 11
L.Sum
1.00
1,350,000
1,015,038
130,751,338
98,309,273
CW(1) 4
Remarks
Narayananan Associates
Item No
Description
WI-01
Unit
Qty
Rate
(Rs)
WI-01-01
Site Clearance
L.sum
1.00
160,000
160,000
120,301
WI-01-02
L.sum
1.00
400,000
400,000
300,752
WI-01-03
m3
21.00
960
20,160
15,158
WI-01-04
m3
1.00
8,000
8,000
6,015
WI-01-05
m3
21.00
640
13,440
10,105
WI-01-06
Back filling
item
1.00
40,000
40,000
30,075
WI-01-07
m3
1.00
5,600
5,600
4,211
WI-01-08
m3
25.00
5,760
144,000
108,271
WI-01-09
nr
51.00
14,000
714,000
536,842
WI-01-10
nr
2.00
8,800
17,600
13,233
nr
1.00
1,760,000
1,760,000
1,323,308
WI-01-12
nr
1.00
7,520
7,520
5,654
WI-01-13
nr
1.00
7,520
7,520
5,654
WI-01-14
nr
1.00
4,880
4,880
3,669
nr
1.00
6,720
6,720
5,053
nr
1.00
4,640
4,640
3,489
WI-01-11
WI-01-15
WI-01-16
CW(1) 5
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Pipe Fittings
Supply and fixing all DCI fittings including
rubber rings, lubricant, gaskets, bolts & nuts
and all other associated material required for
complete installation.
WI-01-17
nr
1.00
8,080
8,080
6,075
Bend
WI-01-18
nr
2.00
37,440
74,880
56,301
WI-01-19
Bell Mouth
250mm dia DCIP flange bell mouth
nr
2.00
16,400
32,800
24,662
15.00
5,440
81,600
61,353
m2
14.00
720
10,080
7,579
nr
3.00
3,200
9,600
7,218
27.00
32,000
864,000
649,624
nr
4.00
12,000
48,000
36,090
4,443,120
3,340,692
WI-01-21
WI-01-22
WI-01-23
WI-01-24
CW(1) 6
Narayananan Associates
Item No
Description
WI-02
INTAKE SUMP
Unit
Qty
Rate
(Rs)
INSITU CONCRETE
Rate shall include supplying and placing
concrete (with temperature control) and
curing as specified. Reinforcement &
formwork measured separately.
WI-02-01
WI-02-02
m3
4.00
23,600
94,400
70,977
nr
2.00
1,600
3,200
2,406
0.30
210,000
63,000
47,368
nr
172.00
320
55,040
41,383
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
placing in position tied with GI binding wire fix
with cover blocks complete as depicted in
drawings.
WI-02-03
WI-02-04
WI-02-05
m2
17.00
2,560
43,520
32,722
WI-02-06
m2
6.00
2,560
15,360
11,549
nr
1.00
24,000
24,000
18,045
WI-02-07
MANHOLE COVER
Class A 150 Manhole cover 600mm dia clear
opening with circular base
PIPEWORK - PIPES
Supply and laying all DI pipes and fittings,
valves & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
Suction Pipe
Rate included under mechanical works
CW(1) 7
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
MISCELLANEOUS WORK
WI-02-18
nr
14.00
1,760
24,640
18,526
WI-02-19
18.00
4,800
86,400
64,962
WI-02-20
nr
2.00
240
480
361
WI-02-21
L.sum
1.00
40,000
40,000
30,075
WI-02-22
L.sum
1.00
64,000
64,000
48,120
WI-02-23
L.sum
1.00
160,000
160,000
120,301
WI-02-24
L.sum
1.00
480,000
480,000
360,902
WI-02-25
L.Sum
1.00
8,000
8,000
6,015
WI-02-26
L.Sum
1.00
48,000
48,000
36,090
1,210,040
909,802
CW(1) 8
Narayananan Associates
Item No
Description
WI-03
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Supply and laying all DI pipes and fittings,
valves & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
Delivery pipe (upto existing pipe)
WI-03-01
nr
4.00
23,600
94,400
70,977
WI-03-02
nr
2.00
17,120
34,240
25,744
WI-03-03
nr
2.00
22,880
45,760
34,406
WI-03-04
nr
2.00
19,920
39,840
29,955
WI-03-05
nr
6.00
17,760
106,560
80,120
WI-03-06
nr
2.00
21,120
42,240
31,759
WI-03-07
Radial Tee
150mm dia DI flanged radial Tee
nr
4.00
47,600
190,400
143,158
WI-03-08
Blank flange
150mm dia DI
nr
2.00
3,440
6,880
5,173
WI-03-09
Bend
150mm dia DI double flanged 90 Bend
nr
6.00
14,160
84,960
63,880
WI-03-10
Gate valve
150mm dia DI double flanged
nr
4.00
WI-03-11
Flange Adaptor
150mm dia DI
nr
4.00
WI-03-12
nr
1.00
WI-03-13
Reducer
200-150mm dia DI double flanged
nr
2.00
nr
3.00
MISCELLANEOUS WORK
WI-03-14
CW(1) 9
240
720
541
646,000
485,713
Narayananan Associates
Description
WI-04
WI-04-01
L.sum
1.00
100,000
N/A
N/A
WI-04-02
L.sum
1.00
500,000
N/A
N/A
WI-04-03
Nr
1.00
50,000
50,000
37,594
WI-04-04
Nr
6.00
50,000
300,000
225,564
WI-04-05
Commemorative Plaque
Nr
1.00
100,000
100,000
75,188
WI-04-06
34.00
Nill
WI-04-07
Coffer dam
L.sum
1.00
Nill
WI-04-08
L.sum
1.00
4,700,000
WI-04-09
Safety measures
Tenderers 6.1
L.sum
1.00
WI-04-10
L.sum
WI-04-11
L.sum
-Vol
I,
Unit
Instruction
to
Qty
Rate
(Rs)
Item No
N/A
N/A
500,000
500,000
375,940
1.00
100,000
N/A
N/A
1.00
100,000
100,000
75,188
1,050,000
789,474
CW(1) 10
Narayananan Associates
Item No
Description
RW 01
RW-01-01
RW-01-02
RW-01-03
Unit
Qty
Rate
(Rs)
L.Sum
1.00
400,000
400,000
300,752
nr
2.00
24,000
48,000
36,090
nr
1.00
24,000
24,000
18,045
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
RW-01-04
DI, Coupling
200mm dia
nr
3.00
19,200
57,600
43,308
RW-01-05
nr
1.00
46,560
46,560
35,008
RW-01-06
nr
1.00
32,080
32,080
24,120
RW-01-07
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Gate valve (Flanged Type)
200mm dia
nr
1.00
48,000
48,000
36,090
656,240
493,413
CW(1) 11
Narayananan Associates
Item No
Description
WTP 01
RAUGHING FILTER
Unit
Qty
Rate
(Rs)
EARTH WORKS
WTP 01 - 01 Site Clearance
L.Sum
1.00
80,000
80,000
60,150
L.Sum
1.00
160,000
160,000
120,301
Nill
m3
223.00
800
178,400
134,135
25.00
8,000
200,000
150,376
m2
225.00
120
27,000
20,301
m3
223.00
640
142,720
107,308
Concrete in Grade 15
WTP 01 - 08 Mass concrete blinding, 75mm thick
m3
169.00
18,400
3,109,600
2,338,045
m3
115.00
23,600
2,714,000
2,040,602
m3
5.00
23,600
118,000
88,722
WTP 01 - 11 in walls
m3
208.00
23,600
4,908,800
3,690,827
WTP 01 - 12 in columns
m3
0.50
23,600
11,800
8,872
WTP 01 - 13 in beams
m3
3.40
23,600
80,240
60,331
m3
14.00
23,600
330,400
248,421
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 01 - 15 Tor steel (T10 - T20)
51.30
210,000
10,773,000
8,100,000
0.30
208,000
62,400
46,917
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
CONCRETE ANCILLARIES
CW(1) 12
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 01 - 17 Fair finish, plane horizontal
m2
63.00
2,560
161,280
121,263
m2
1,077.00
2,560
2,757,120
2,073,023
PRECAST CONCRETE
Rate to include supply and placing in position
PCC units.
WTP 01 - 19 1000x1000x200mm, PCC Slab with holes
nr
110.00
30,400
3,344,000
2,514,286
WATERPROOFING
WTP 01 - 20 Two layer of Epoxy resin coating
m2
803.00
720
578,160
434,707
m2
347.00
560
194,320
146,105
nr
2.00
43,840
87,680
65,925
nr
2.00
93,520
187,040
140,632
nr
1.00
73,280
73,280
55,098
nr
1.00
60,960
60,960
45,835
nr
1.00
52,640
52,640
39,579
nr
2.00
73,520
147,040
110,556
nr
2.00
35,920
71,840
54,015
nr
2.00
32,320
64,640
48,602
nr
1.00
18,832
18,832
14,159
PAINTING
Apply one under coat & two finishing coats of
WTP 01 - 21 approved weather proof emulsion paint on all
exposed surface of external walls.
Inlet, Washout, Outlet, Overflow & Drain Pipe
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Double flange pipe with puddle flange
200mm dia 960mm long, puddle flange 450mm
WTP 01 - 22
away from one end.
CW(1) 13
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
54,480
54,480
40,962
nr
1.00
45,760
45,760
34,406
WTP 01 - 32
WTP 01 - 33
nr
2.00
42,400
84,800
63,759
WTP 01 - 34
nr
1.00
40,400
40,400
30,376
WTP 01 - 35
nr
1.00
40,400
40,400
30,376
WTP 01 - 36
nr
2.00
40,400
80,800
60,752
WTP 01 - 37
nr
1.00
39,040
39,040
29,353
WTP 01 - 38
nr
1.00
20,000
20,000
15,038
WTP 01 - 39
nr
1.00
19,120
19,120
14,376
WTP 01 - 40
nr
1.00
20,640
20,640
15,519
WTP 01 - 41
nr
2.00
18,800
37,600
28,271
WTP 01 - 42
nr
1.00
17,760
17,760
13,353
nr
1.00
63,520
63,520
47,759
nr
1.00
36,160
36,160
27,188
nr
1.00
21,520
21,520
16,180
nr
2.00
20,560
41,120
30,917
nr
2.00
8,400
16,800
12,632
nr
2.00
36,800
73,600
55,338
CW(1) 14
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
2.00
9,040
18,080
13,594
DI, Coupling
WTP 01 - 50 250mm dia
nr
3.00
25,520
76,560
57,564
nr
1.00
19,120
19,120
14,376
nr
2.00
8,560
17,120
12,872
nr
7.00
48,480
339,360
255,158
nr
6.00
34,400
206,400
155,188
nr
1.00
23,200
23,200
17,444
nr
1.00
30,880
30,880
23,218
nr
3.00
21,760
65,280
49,083
nr
2.00
16,420
32,840
24,692
nr
1.00
11,920
11,920
8,962
nr
2.00
8,560
17,120
12,872
nr
2.00
68,560
137,120
103,098
nr
2.00
43,600
87,200
65,564
nr
1.00
25,600
25,600
19,248
nr
2.00
14,400
28,800
21,654
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks and protection of joints (Chamber
measured under yard piping).
CW(1) 15
Narayananan Associates
Item No
Description
Rate
(Rs)
Unit
Qty
FILTRATION MEDIA
WTP 01 - 65 Filtration Gravel, 4-8mm dia pebbles
m3
112.00
16,800
1,881,600
1,414,737
m3
112.00
15,000
1,680,000
1,263,158
m3
112.00
13,600
1,523,200
1,145,263
m3
73.00
12,000
876,000
658,647
825.00
224
184,800
138,947
nr
4.00
88,000
352,000
264,662
92.00
7,200
662,400
498,045
item
1.00
180,000
180,000
135,338
39,925,312
30,019,032
MISCELLANEOUS WORK
20mm dia UPVC pipe fixed to PCC slab (300mm
WTP 01 - 69
long)
CW(1) 16
Narayananan Associates
Item No
Description
WTP 02
REPAIR WORK
Allow for necessary improvement and cleaning
WTP 02 - 1 concrete surface of damaged structures
completely.
Unit
Rate
(Rs)
1.00
640,000
640,000
481,203
nr
16.00
80
1,280
962
m2
107.00
2,000
214,000
160,902
m2
107.00
720
77,040
57,925
m2
77.00
560
43,120
32,421
L.Sum
1.00
80,000
80,000
60,150
nr
1.00
17,440
17,440
13,113
nr
1.00
13,760
13,760
10,346
PRECAST CONCRETE
Rate to include supply and placing as shown in
drawing PCC blocks.
WTP 02 - 2 450x75x75mm PCC block
WATERPROOFING
Chipping or grinding internal concrete surface
WTP 02 - 3
and apply concrete repair mortar.
WTP 02 - 4 Two layer of Epoxy resin coating
PAINTING
Apply one under coat & two finishing coats of
WTP 02 - 5 approved weather proof emulsion paint on all
surface of external walls.
L.Sum
Qty
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
CW(1) 17
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
24,160
24,160
18,165
nr
1.00
19,520
19,520
14,677
nr
1.00
9,920
9,920
7,459
nr
1.00
7,040
7,040
5,293
nr
1.00
14,400
14,400
10,827
nr
1.00
12,000
12,000
9,023
nr
1.00
80,000
80,000
60,150
L.Sum
1.00
16,000
16,000
12,030
WTP 02 - 17 V Notch
nr
1.00
32,000
32,000
24,060
Chequer Plate
WTP 02 - 18 650x850x6mm Chequer Plate
nr
1.00
10,400
10,400
7,820
nr
1.00
8,000
8,000
6,015
1,320,080
992,541
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
MISCELLANEOUS WORK
WTP 02 - 15 Stainless steel ladder 450mm wide 4.75m long
WTP 02 - 16 MS Steps, 450mm wide in Receiving well
CW(1) 18
Narayananan Associates
Item No
Description
WTP 03
EARTH WORKS
WTP 03 - 01 Site Clearance
Allow for necessary improvement and cleaning
WTP 03 - 02 concrete surface of damaged structures
completely.
Unit
Qty
Rate
(Rs)
L.Sum
1.00
240,000
240,000
180,451
L.Sum
1.00
800,000
800,000
601,504
m3
2,500.00
480
1,200,000
902,256
m3
2,500.00
160
400,000
300,752
m3
1,137.00
960
1,091,520
820,692
m3
0.81
20,000
16,200
12,180
m3
14.00
23,600
330,400
248,421
m3
0.03
23,600
708
532
m3
0.22
23,600
5,192
3,904
1.00
240,000
240,000
180,451
nr
20.00
320
6,400
4,812
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 03 - 12 Fair finish, plane horizontal
m2
2.00
2,560
5,120
3,850
m2
160.00
2,560
409,600
307,970
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 03 - 10 Tor steel
WTP 03 - 11
CW(1) 19
Narayananan Associates
Item No
Description
PRECAST CONCRETE
Rate to include supply and placing in position
PCC cover slab.
600x480x50mm PCC cover slab with lifting
WTP 03 - 14
handle in collecting chamber.
Unit
Qty
Rate
(Rs)
nr
18.00
800
14,400
10,827
WTP 03 - 15
nr
85.00
640
54,400
40,902
WTP 03 - 16
nr
180.00
640
115,200
86,617
m2
2,027.00
2,000
4,054,000
3,048,120
m2
2,187.00
720
1,574,640
1,183,940
m2
942.00
2,000
1,884,000
1,416,541
m2
942.00
560
527,520
396,632
L.Sum
1.00
160,000
160,000
120,301
nr
3.00
70,720
212,160
159,519
nr
3.00
29,920
89,760
67,489
nr
1.00
46,400
46,400
34,887
nr
1.00
42,320
42,320
31,820
nr
3.00
29,920
89,760
67,489
WATERPROOFING
Chipping or grinding internal concrete surface
WTP 03 - 17
and apply concrete repair mortar.
WTP 03 - 18 Two layer of Epoxy resin coating
PAINTING
Chipping or grinding external concrete surface
WTP 03 - 19
and apply concrete repair mortar.
Apply one under coat & two finishing coats of
WTP 03 - 20 approved weather proof emulsion paint on all
surface of external walls.
PIPEWORK - EXISTING PIPES AND FITTINGS
Rate to include cleaning & repairing of existing
pipes & removal of pipes.
WTP 03 - 21 Clearing, repairing and removal as shown
Collecting, Overflow & Drain Pipe
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
CW(1) 20
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
33,120
33,120
24,902
nr
2.00
32,560
65,120
48,962
2.11
4,560
9,622
7,235
490.00
1,520
744,800
560,000
nr
3.00
46,960
140,880
105,925
nr
3.00
29,600
88,800
66,767
FILTRATION MEDIA
WTP 03 - 33 Filtration Sand, 0.32mm dia pebbles
m3
1,113.00
17,400
19,366,200
14,561,053
m3
86.00
16,800
1,444,800
1,086,316
m3
86.00
15,200
1,307,200
982,857
m3
248.00
14,400
3,571,200
2,685,113
nr
2.00
72,000
144,000
108,271
nr
6.00
40,000
240,000
180,451
nr
3.00
64,000
192,000
144,361
nr
3.00
8,000
24,000
18,045
L.Sum
1.00
16,000
16,000
12,030
L.Sum
1.00
7,200
7,200
5,414
nr
3.00
24,000
72,000
54,135
nr
2.00
24,000
48,000
36,090
1.00
24,000
24,000
41,148,642
18,045
30,938,831
WTP 03 - 30
MISCELLANEOUS WORK
WTP 03 - 37 Stainless steel ladder 450mm wide 3.96m long
WTP 03 - 38
CW(1) 21
Narayananan Associates
Item No
Description
WTP 04
Unit
Qty
Rate
(Rs)
EARTH WORKS
WTP 04 - 01 Site Clearance
L.sum
1.00
80,000
80,000
60,150
L.sum
1.00
40,000
40,000
30,075
m3
73.00
960
70,080
52,692
m3
10.00
8,000
80,000
60,150
m3
73.00
640
46,720
35,128
m2
163.00
120
19,560
14,707
m3
0.50
2,400
1,200
902
m3
8.00
18,400
147,200
110,677
m3
53.00
23,600
1,250,800
940,451
m3
38.00
23,600
896,800
674,286
7.30
210,000
1,533,000
1,152,632
149.00
2,560
381,440
286,797
WTP 04 - 07
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 04 - 11 Tor steel (T10 - T12)
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 04 - 12 Fair finish, plane vertical
m2
CW(1) 22
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Plain ended pipe
DI, 100mm dia 750mm long with puddle flange
WTP 04 - 13
75mm away form one end.
nr
1.00
15,840
15,840
11,910
4.24
2,510
10,642
8,002
DI, Coupling
WTP 04 - 15 100mm dia
nr
1.00
8,560
8,560
6,436
PVC, 90 Bend
WTP 04 - 16 110mm dia
nr
1.00
2,610
2,610
1,962
L.Sum
1.00
7,200
7,200
5,414
4,591,652
3,452,371
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
MISCELLANEOUS WORK
Allow for providing concrete anchor blocks,
WTP 04 - 17 Thrust blocks for fittings as depicted in
drawing.
Total WTP 04 - Wsah Sand Storage Yard carried to CW(1) Bill Summary
CW(1) 23
Narayananan Associates
Item No
Description
WTP 05
STORAGE POND
Unit
Qty
Rate
(Rs)
EARTH WORKS
WTP 05 - 01 Site Clearance
L.sum
1.00
80,000
80,000
60,150
L.sum
1.00
40,000
40,000
30,075
WTP 05 - 03 Shoring
L.sum
Nill
m3
316.00
960
303,360
228,090
m3
30.00
8,000
240,000
180,451
m3
316.00
640
202,240
152,060
m2
77.00
120
9,240
6,947
m2
202.00
120
24,240
18,226
item
1.00
96,000
96,000
72,180
m3
3.20
18,400
58,880
44,271
m3
4.62
20,800
96,096
72,253
m3
12.11
20,800
251,888
189,389
m3
13.20
20,800
274,560
206,436
1.88
210,000
394,800
296,842
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire and concrete blocks complete as
depicted in drawings.
WTP 05 - 14 Tor steel (T12)
CW(1) 24
Narayananan Associates
Item No
Description
Rate
(Rs)
Unit
Qty
m2
173.00
2,560
442,880
332,992
m3
24.00
13,600
326,400
245,414
nr
1.00
45,760
45,760
34,406
nr
1.00
13,760
13,760
10,346
nr
1.00
43,120
43,120
32,421
nr
1.00
6,880
6,880
5,173
nr
1.00
11,280
11,280
8,481
nr
1.00
5,330
5,330
4,008
nr
1.00
47,520
47,520
35,729
nr
1.00
70,720
70,720
53,173
nr
1.00
6,640
6,640
4,992
nr
2.00
25,440
50,880
38,256
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 05 - 15 Fair finish, plane vertical
MASONRY WORK
Rubble work 150-250mm sized including insitu
WTP 05 - 16 concrete 15MPa as per drawing no
KWSP/WTP/SP/C-01
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Flange and plain ended pipe with puddle
flange
250mm dia 1000mm long, puddle flange
WTP 05 - 17
300mm away from plain end.
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Coupling
WTP 05 - 26 250mm dia
CW(1) 25
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
21,760
21,760
16,361
PVC, Tee
WTP 05 - 28 280x280x280mm dia
nr
1.00
96,180
96,180
72,316
PVC, 90 Bend
WTP 05 - 29 280mm dia
nr
2.00
14,990
29,980
22,541
nr
1.00
68,560
68,560
51,549
L.Sum
1.00
7,200
7,200
5,414
3,366,154
2,530,942
PIPEWORK - VALVES
Rate to include supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Gate valve (Flanged Type)
WTP 05 - 30 250mm dia
MISCELLANEOUS WORK
Allow for providing concrete anchor blocks,
WTP 05 - 31 Thrust blocks for fittings as depicted in
drawing.
CW(1) 26
Narayananan Associates
Item No
Description
WTP 06
ADMINISTRATION BUILDING
SUCTION PIPE
150mm dia DI flange strainer including foot
WTP 06 - 01
valve
Unit
Qty
Rate
(Rs)
nr
2.00
nr
2.00
nr
2.00
nr
2.00
nr
2.00
nr
2.00
nr
2.00
nr
2.00
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Double Flanged 90 Medium Bend
WTP 06 - 05 150 mm dia
DI, Flexible Coupling
150mm dia flexible joint including Stapered
WTP 06 - 06
Coupling.
PIPEWORK - VALVES
Rate to include for supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
Sluice valve
150 mm dia double flanged Sluice valve with
WTP 06 - 07
hand wheel
CIVIL WORK
WTP 06 - 08
CW(1) 27
1,600
3,200
2,406
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
DELIVERY PIPE
PIPEWORK - PIPES
Rate to include supply, delivery and laying all
pipes & specials including rubber rings,
lubricant, gaskets, bolts & nuts and all other
associated material required for complete
installation.
DI, Double flange pipe
WTP 06 - 09 300 mm dia , 900 mm long (approx.)
nr
1.00
53,440
53,440
40,180
nr
1.00
60,160
60,160
45,233
nr
2.00
25,280
50,560
38,015
nr
2.00
23,600
47,200
35,489
nr
2.00
20,560
41,120
30,917
nr
1.00
18,880
18,880
14,195
nr
1.00
18,800
18,800
14,135
nr
2.00
11,120
22,240
16,722
nr
2.00
45,760
91,520
68,812
nr
3.00
14,400
43,200
32,481
nr
3.00
48,240
144,720
108,812
nr
1.00
6,560
6,560
4,932
nr
1.00
212,320
212,320
159,639
nr
1.00
13,120
13,120
9,865
WTP 06 - 15
PIPEWORK - FITTINGS
Rate to include supply, delivery and fixing all
fittings including all associated material
required for complete installation.
DI, Flexible Coupling
150mm dia flexible joint including Stapered
WTP 06 - 16
Coupling.
CW(1) 28
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
37,600
nr
1.00
nr
4.00
nr
2.00
nr
1.00
37,600
28,271
PIPEWORK - VALVES
Rate to include for supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured under
yard piping).
DI, Sluice valve/ Gate valve (Flanged Type)
CIVIL WORKS
WTP 06 - 27
nr
2.00
5,600
11,200
8,421
WTP 06 - 28
nr
1.00
1,600
1,600
1,203
877,440
659,728
CW(1) 29
Narayananan Associates
Item No
Description
WTP 07
GENERATOR HOUSE
Unit
Qty
Rate
(Rs)
item
1.00
40,000
40,000
30,075
item
1.00
40,000
40,000
30,075
m3
69.00
800
55,200
41,504
m3
14.00
8,000
112,000
84,211
m2
62.00
120
7,440
5,594
WTP 07 - 06
m3
21.00
1,600
33,600
25,263
WTP 07 - 07
m3
73.00
1,600
116,800
87,820
WTP 07 - 08
m3
12.00
4,000
48,000
36,090
m2
60.00
2,240
134,400
101,053
m3
92.00
160
14,720
11,068
m3
0.50
18,400
9,200
6,917
m3
6.90
18,400
126,960
95,459
m3
16.50
20,800
343,200
258,045
m3
5.00
20,800
104,000
78,195
m3
2.40
20,800
49,920
37,534
m3
3.10
20,800
64,480
48,481
m3
9.60
20,800
199,680
150,135
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified (R/F & F/W measured separately).
Concrete in Grade 15
CW(1) 30
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
WTP 07 - 18 In column
m3
3.00
20,800
62,400
46,917
WTP 07 - 19 In Beam
m3
6.10
20,800
126,880
95,398
REINFORCEMENT
High yield steel (fy = 460N/mm2) in foundation
base, ground floor slab, column, ramp, beam
and plinth beams
WTP 07 - 20 Tor steel (T10 - T20)
3.02
210,000
634,200
476,842
0.12
208,000
24,960
18,767
FORMWORK
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 07 - 22 For sides of Screed concrete
m2
14.50
1,600
23,200
17,444
m2
15.00
1,600
24,000
18,045
m2
32.50
2,560
83,200
62,556
m2
15.40
2,560
39,424
29,642
m2
30.20
2,560
77,312
58,129
m2
40.00
2,560
102,400
76,992
m2
57.00
2,560
145,920
109,714
m3
30.20
5,920
178,784
134,424
m2
29.00
760
22,040
16,571
m2
265.00
1,520
402,800
302,857
m2
132.20
120
15,864
11,928
m2
6.30
800
5,040
3,789
57.60
80
4,608
3,465
MASONRY WORK
Random rubble work
150x225mm sized Random rubble masonry in
WTP 07 - 29
foundation in cement sand mortar 1:6
Block Work
75mm thick block lining in both sides of plinth
WTP 07 - 30
beam in cement sand mortar 1:5
WTP 07 - 31
WATER PROOFING
Single layer of 1000 gauge polythene DPM laid
WTP 07 - 32 with 150mm end and side lap on sand fill to
receive concrete floor
CW(1) 31
Narayananan Associates
Item No
Description
Rate
(Rs)
Unit
Qty
m2
158.00
1,280
202,240
152,060
52.00
800
41,600
31,278
m2
158.00
1,280
202,240
152,060
32.70
1,384
45,257
34,028
40.00
1,960
78,400
58,947
28.00
2,160
60,480
45,474
WTP 07 - 37
ROOF PLUMBING
Rain water down pipe to be connected to the
rain water Drain
WTP 07 - 39
m2
52.00
560
29,120
21,895
WTP 07 - 42
m2
65.00
720
46,800
35,188
WTP 07 - 43
58.00
80
4,640
3,489
m2
308.00
520
160,160
120,421
m2
228.00
480
109,440
82,286
CW(1) 32
Narayananan Associates
Item No
Description
Rate
(Rs)
Unit
Qty
m2
308.00
520
160,160
120,421
m2
228.00
480
109,440
82,286
m2
154.00
560
86,240
64,842
PAINTING
Prepare and apply one under coat and two
WTP 07 - 46 finishing coats of approved Emulsion paint on
all internal plastered surface.
WTP 07 - 49
nr
2.00
40,000
80,000
60,150
WTP 07 - 50
nr
1.00
53,500
53,500
40,226
WTP 07 - 51
nr
2.00
106,080
212,160
159,519
WTP 07 - 52
nr
1.00
111,600
111,600
83,910
nr
2.00
20,000
40,000
30,075
15.80
2,240
35,392
26,611
nr
1.00
400,000
400,000
300,752
L.Sum
1.00
Nill
L.Sum
1.00
Nill
CW(1) 33
5,741,501
4,316,917
Narayananan Associates
Item No
Description
WTP 08
GUARD HOUSE
Unit
Qty
Rate
(Rs)
L.sum
1.00
50,000
50,000
37,594
L.sum
1.00
50,000
50,000
37,594
m3
2.71
1,000
2,710
2,038
m3
0.27
10,000
2,700
2,030
m2
3.71
150
557
419
m3
2.70
2,000
5,400
4,060
m3
0.19
18,400
3,496
2,629
m3
2.17
20,800
45,136
33,937
WTP 08 - 09 In Beam
m3
0.23
20,800
4,784
3,597
REINFORCEMENT
High yield steel (fy = 460N/mm2) in foundation
base, ground floor slab, column, ramp, beam
and plinth beams
WTP 08 - 10 Tor steel (T10 - T20)
kg
0.80
210,000
168,000
126,316
kg
0.01
208,000
2,080
1,564
FORMWORK
All formwork shall be plywood sheet. Rate
includes formwork support system.
WTP 08 - 12 For sides and soffits of Beam
m2
2.76
3,200
8,832
6,641
m3
3.34
7,400
24,716
18,583
WTP 08 - 06
Concrete in Grade 15
Mass concrete blinding in wall foundation,
WTP 08 - 07
50mm thk
MASONRY WORK
Random rubble work
150x225mm sized Random rubble masonry in
WTP 08 - 13
foundation in cement sand motor 1:6
CW(1) 34
Narayananan Associates
Item No
Description
Block Work
Block wall masonry 150mm thick in cement
WTP 08 - 14
sand mortar 1:5
Unit
Qty
Rate
(Rs)
m2
23.02
1,900
43,738
32,886
m2
22.00
150
3,300
2,481
m2
3.71
1,000
3,710
2,789
m2
27.03
1,600
43,248
32,517
20.80
1,000
20,800
15,639
m2
27.03
1,600
43,248
32,517
10.20
1,730
17,646
13,268
12.00
2,450
29,400
22,105
18.92
2,700
51,084
38,409
m2
6.00
700
4,200
3,158
m2
21.76
650
14,144
10,635
WATER PROOFING
Single layer of 1000 gauge polythene DPM laid
WTP 08 - 15 with 150mm end and side lap on sand fill to
receive concrete floor
WTP 08 - 16 Floor Acrylic polymer water proofing.
ROOF WORK AND CEILING
All timber sections and ceiling planks to be
treated with two coats of sealer and wood
preservatives as per specification.
WTP 08 - 19
ROOF PLUMBING
Rain water down pipe to be connected to the
rain water Drain
Gutter 150x150 mm sized metal sheet fixed on
WTP 08 - 20 valance board with Galvanized mild steel
brackets 300mm c/c
WTP 08 - 21
CW(1) 35
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
m2
25.10
600
15,060
11,323
m2
21.76
650
14,144
10,635
m2
25.10
600
15,060
11,323
m2
27.03
700
18,921
14,226
PAINTING
Prepare and apply one under coat and two
WTP 08 - 26 finishing coats of approved Emulsion paint on
all internal plastered surface.
WTP 08 - 29
nr
1.00
50,000
50,000
37,594
WTP 08 - 30
nr
1.00
132,600
132,600
99,699
0.90
2,600
2,340
1,759
891,054
669,965
MISCELLANEOUS WORK
Reinforced concrete Lintel, Gr C 25 concrete
WTP 08 - 31 including all necessary formwork and
reinforcement.
CW(1) 36
Narayananan Associates
Item No
Description
WTP 09
YARD PIPING
Unit
Qty
Rate
(Rs)
L.Sum
1.00
200,000
200,000
150,376
nr
1.00
47,420
47,420
35,654
nr
2.00
34,520
69,040
51,910
nr
3.00
23,160
69,480
52,241
nr
1.00
31,885
31,885
23,974
nr
2.00
23,160
46,320
34,827
31.00
12,800
396,800
298,346
14.00
11,710
163,940
123,263
105.00
11,025
1,157,625
870,395
35.00
9,550
334,250
251,316
70.00
14,050
983,500
739,474
WTP 09 - 12 225mm
25.00
9,880
247,000
185,714
PIPEWORK - FITTINGS
Rate to include for Supply & fixing specials
fittings, thrust blocks, anchor blocks etc.
CW(1) 37
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
25,400
25,400
19,098
nr
5.00
19,200
96,000
72,180
nr
1.00
64,210
64,210
48,278
nr
1.00
46,470
46,470
34,940
nr
2.00
64,310
128,620
96,707
nr
2.00
21,715
43,430
32,654
nr
1.00
16,500
16,500
12,406
nr
2.00
58,790
117,580
88,406
nr
4.00
33,370
133,480
100,361
nr
2.00
22,640
45,280
34,045
nr
1.00
68,580
68,580
51,564
nr
2.00
43,725
87,450
65,752
CHAMBER
Rate to include excavation, shoring &
dewatering, compaction & disposal and
concreting, reinforcement & formwork and
finishing including cover & steps where
necessary.
WTP 09 - 25 Type A 1000x900x800mm, CH-16
nr
1.00
150,000
150,000
112,782
nr
1.00
180,000
180,000
135,338
PIPEWORK - VALVES
Rate to include for Supply & fixing Valves and
providing supports, thrust blocks and
protection of joints (Chamber measured
separately).
CW(1) 38
Narayananan Associates
Item No
Description
Unit
Qty
Rate
Amount (Rs) Amount (JPY)
(Rs)
180,000
360,000
270,677
nr
2.00
nr
1.00
180,000
180,000
135,338
nr
1.00
180,000
180,000
135,338
nr
2.00
180,000
360,000
270,677
nr
1.00
180,000
180,000
135,338
nr
2.00
180,000
360,000
270,677
nr
1.00
180,000
180,000
135,338
nr
1.00
180,000
180,000
135,338
nr
2.00
180,000
360,000
270,677
nr
2.00
180,000
360,000
270,677
nr
1.00
180,000
180,000
135,338
nr
1.00
180,000
180,000
135,338
nr
2.00
180,000
360,000
270,677
nr
1.00
180,000
180,000
135,338
8,550,260
6,428,767
WTP 09 - 40
CW(1) 39
Narayananan Associates
Item No
Description
WTP 10
LANDSCAPING
EARTH WORKS
WTP 10 - 01 Site Clearance
Unit
Rate
(Rs)
1.00
80,000
80,000
60,150
m3
1,810.00
1,300
2,353,000
1,769,173
m3
540.00
960
518,400
389,774
m2
1,321.00
120
158,520
119,188
m2
860.00
120
103,200
77,594
m2
860.00
480
412,800
310,376
m2
711.00
120
85,320
64,150
m3
142.14
4,000
568,560
427,489
m2
1,018.06
2,400
2,443,344
1,837,101
Concrete Pavement
WTP 10 - 10 Trimming and Compacting
m2
233.26
120
27,991
21,046
m3
23.33
20,800
485,264
364,860
PCC Curbs
WTP 10 - 12 Curbs Type I, 100x300mm
167.86
2,400
402,864
302,905
126.99
1,600
203,184
152,770
4,012.02
1,780
7,141,396
5,369,471
311.74
N/A
N/A
nr
1.00
N/A
N/A
45.24
N/A
N/A
14,983,843
11,266,047
WTP 10 - 02
Drain channels
R/F Conc. road drains, 300x300mm internal
WTP 10 - 14
sized 100mm thick
item
Qty
CW(1) 40
Narayananan Associates
Item No
Description
WTP-11
WTP 11 - 01
Unit
Qty
L.sum
N/A
nr
1.00
50,000
50,000
37,594
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
300,000
300,000
225,564
L.sum
1.00
500,000
500,000
375,940
1,350,000
1,015,038
Rate
(Rs)
CW(1) 41
Narayananan Associates
Description
Unit
Qty
WT-1.0
L. Sum
1.00
63,571,984
47,798,485
WT-1.1
LANDSCAPING
L. Sum
1.00
2,465,526
1,853,778
WT-1.2
L. Sum
1.00
5,829,480
4,383,068
WT-1.3
L. Sum
1.00
1,050,000
789,474
72,916,990
54,824,805
CW(2) 42
Remarks
Narayananan Associates
Item No
Description
WT-1.0
EARTH WORKS
WT-1.0- 01 Care of water and Dewatering
Unit
Qty
L.Sum
1.00
Rate
(Rs)
80,000
80,000
60,150
NIL
m3
353.43
800
282,744
212,589
m3
173.18
960
166,253
125,002
m3
NIL
m3
52.66
8,000
421,280
316,752
m2
176.72
120
21,206
15,944
m3
427.25
1,600
683,600
513,985
m3
78.97
4,000
315,880
237,504
m3
290.12
640
185,677
139,607
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified.
Concrete in Grade 15
WT-1.0- 11 75 mm thick blinding in tower base
m3
14.14
18,400
260,176
195,621
m3
2.12
18,400
39,008
29,329
m3
8.26
20,800
171,808
129,179
m3
5.98
20,800
124,384
93,522
Reinforced
concrete
in
Grade
25,
reinforcement and formwork measued
separately
WT-1.0- 15 Reinforced concrete for circular base `
m3
176.62
20,800
3,673,696
2,762,177
m3
23.40
20,800
486,720
365,955
m3
35.29
21,200
748,148
562,517
m3
34.95
22,000
768,900
578,120
WT-1.0- 09
WT-1.0 - 18
CW(2) 43
Narayananan Associates
Qty
Rate
(Rs)
Item No
Description
Unit
WT-1.0 - 19
m3
34.95
22,800
796,860
599,143
WT-1.0 - 19
m3
37.43
23,600
883,348
664,171
WT-1.0 - 20
m3
14.39
24,000
345,360
259,669
WT-1.0- 21
m3
26.53
20,800
551,824
414,905
m3
191.93
24,800
4,759,864
3,578,845
m3
14.56
24,800
361,088
271,495
m3
30.10
25,600
770,560
579,368
m3
6.42
24,800
159,216
119,711
m3
13.32
24,800
330,336
248,373
m3
0.49
25,600
12,544
9,432
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire, cover blocks; complete as
depicted in drawings.
WT-1.0- 28 Tor steel T10,T12, T16,T20,T25
97.44
210,000
20,462,400
15,385,263
0.04
208,000
8,320
6,256
CONCRETE ANCILLARIES
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WT-1.0- 30 Fair finish, Type 1 (upto 23m level)
m2
1,007.91
5,200
5,241,132
3,940,701
m2
1,673.57
6,000
10,041,420
7,549,940
CW(2) 44
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
17.00
28,800
489,600
368,120
nr
2.00
18,400
36,800
27,669
nr
1.00
72,000
72,000
54,135
nr
1.00
39,200
39,200
29,474
m2
87.30
520
45,396
34,132
m2
8.44
480
4,051
3,046
m2
2.03
600
1,218
916
m2
205.55
608
124,974
93,965
FINISHES
Plastering
Rendering 20mm thick cement sand (1:3) and
finished smooth with neat cement floating
WT-1.0- 40
m2
982.22
520
510,754
384,026
WT-1.0- 41
m2
773.85
480
371,448
279,284
Nil
657.73
720
ELECTRICAL INSTALLATION
WT-1.0- 42 Measured under Electrical works
WATERPROOFING
Two layer of Epoxy resin coating, inside the
WT-1.0- 43
water tank
m2
CW(2) 45
473,566
356,065
Narayananan Associates
Item No
Description
MISCELLANIOUS
Supply and install water level indicator with
WT-1.0- 44
protection pipe fixed
Unit
Rate
(Rs)
Qty
nr
1.00
48,000
48,000
36,090
nr
1.00
64,000
64,000
48,120
nr
3.00
56,000
168,000
126,316
WT-1.0- 47
nr
2.00
100,000
200,000
150,376
WT-1.0- 48
nr
1.00
48,000
48,000
36,090
nr
3.00
167,128
501,384
376,980
nr
3.00
167,128
501,384
376,980
121.44
4,800
582,912
438,280
WT-1.0- 52
nr
12.11
6,400
77,504
58,274
WT-1.0- 53
m2
2.13
24,000
51,120
38,436
nr
nr
8.00
400
3,200
2,406
L. Sum
1.00
8,000
8,000
6,015
WT-1.0- 57
L. Sum
1.00
7,200
7,200
5,414
WT-1.0- 58
L. Sum
1.00
640,000
640,000
481,203
CW(2) 46
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Rate to include supply , delivery, laying and
fixing to wall, all pipes & specials including
rubber rings, lubricant, gaskets, bolts & nuts,
all other associated material required for
complete installation.
DI Inlet pipe
DI, Double Spigot pipe with puddle flange
300mm dia 1700mm long, puddle flange 600
WT-1.0- 59
away from one end
nr
1.00
47,910
47,910
36,023
nr
1.00
72,005
72,005
54,139
nr
4.00
122,918
491,672
369,678
nr
1.00
89,047
89,047
66,953
nr
1.00
97,568
97,568
73,359
nr
1.00
39,390
39,390
29,617
nr
1.00
51,298
51,298
38,570
DI, Coupling
WT-1.0- 66 300mm dia
nr
1.00
25,983
25,983
19,536
nr
2.00
49,045
98,090
73,752
nr
2.00
73,654
147,308
110,758
nr
4.00
39,043
156,172
117,423
nr
1.00
127,150
127,150
95,602
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Butterfly Valve
WT-1.0- 70 300mm dia
CW(2) 47
Narayananan Associates
Item No
Description
DI Outlet Pipe
DI, Double Spigot pipe with puddle flange
400dia 1700mm long, puddle flange 600 away
WT-1.0- 71
from one end
Unit
Qty
Rate
(Rs)
nr
1.00
74,810
74,810
56,248
nr
4.00
189,469
757,876
569,832
nr
1.00
115,958
115,958
87,186
nr
1.00
108,231
108,231
81,377
nr
1.00
77,314
77,314
58,131
DI, Coupling
WT-1.0- 76 400mm dia
nr
1.00
33,703
33,703
25,341
nr
1.00
138,769
138,769
104,338
nr
3.00
54,322
162,966
122,531
nr
1.00
32,500
32,500
24,436
nr
1.00
306,003
306,003
230,077
nr
1.00
40,754
40,754
30,642
nr
1.00
45,791
45,791
34,429
nr
5.00
100,948
504,740
379,504
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Butterfly Valve
WT-1.0- 80 400mm dia
DI, Overflow and washout pipe
DI, Double Spigot pipe with puddle flange
250mm dia 1800mm long, puddle flange 600
WT-1.0- 81
away from one end
CW(2) 48
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
73,638
73,638
55,367
nr
1.00
52,673
52,673
39,604
nr
1.00
55,403
55,403
41,656
nr
1.00
49,606
49,606
37,298
nr
1.00
55,936
55,936
42,057
nr
1.00
43,593
43,593
32,777
nr
2.00
53,668
107,336
80,704
nr
4.00
27,475
109,900
82,632
nr
1.00
55,961
55,961
42,076
nr
1.00
13,160
13,160
9,895
nr
1.00
67,776
67,776
50,959
nr
1.00
40,754
40,754
30,642
nr
4.00
100,948
403,792
303,603
nr
1.00
59,554
59,554
44,777
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Gate Valve
WT-1.0- 94 250mm dia
DI, Transmission line to Paranthan Tower
DI, Double Spigot pipe with puddle flange
250mmdia 1700mm long, puddle flange 600
WT-1.0- 95
away from one end
CW(2) 49
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
49,286
49,286
37,057
nr
1.00
49,054
49,054
36,883
DI, Coupling
WT-1.0- 100 250mm dia
nr
1.00
19,058
19,058
14,329
nr
1.00
53,668
53,668
40,352
nr
3.00
27,475
82,425
61,974
nr
1.00
13,160
13,160
9,895
nr
1.00
49,780
49,780
37,429
63,571,984
47,798,485
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Gate Valve
WT-1.0- 104 250mm dia
CW(2) 50
Narayananan Associates
Item No
Description
WT-1.1
LANDSCAPING
EARTH WORKS
cleaning site, uprooting trees and disposal of
WT-1.1 - 01
debris
Unit
Qty
Rate
(Rs)
m2
1,634.85 By NWS&DB
245.23 By NWS&DB
WT-1.1 - 02
m3
WT-1.1 - 03
m3
N/A
By NWS&DB
m3
N/A
By NWS&DB
m2
1,213.78
480
582,614
438,056
m3
20.24
800
16,192
12,174
m2
67.47
120
8,096
6,087
m3
40.40
34,000
1,373,600
1,032,782
m2
8.47
20,000
169,400
127,368
ROAD WORKS
WT-1.1 - 10 Trimming and Compacting existing ground
m2
322.87
120
38,744
29,131
m3
61.09
4,000
244,360
183,729
m2
13.55
2,400
32,520
24,451
KERBS
WT-1.1 - 13 Kerbs Type I, 100x300mm
N/A
2,400
N/A
By NWS&DB
nr
N/A
By NWS&DB
CW(2) 51
2,465,526
1,853,778
Narayananan Associates
Item No
Description
WT-1.2
MANHOLE 01
Excavation including
WT-1.2 - 01
material
disposal
Unit
of
surplus
Qty
Rate
(Rs)
m3
6.32
800
5,056
3,802
m2
3.61
120
433
326
m3
0.18
18,400
3,312
2,490
m3
2.53
48,000
121,440
91,308
nr
1.00
40,000
40,000
30,075
m3
35.58
800
28,464
21,402
m2
16.82
120
2,018
1,517
m3
0.84
18,400
15,456
11,621
m3
12.14
20,800
252,512
189,859
1.67
210,000
350,700
263,684
m2
92.11
2,560
235,802
177,295
nr
6.00
8,000
48,000
36,090
nr
1.00
130,924
130,924
98,439
nr
1.00
253,120
253,120
190,316
nr
1.00
8,728
8,728
6,562
nr
1.00
41,401
41,401
31,129
WT-1.2 - 04
of
surplus
WT-1.2 - 11 Formwork
WT-1.2 - 12
CW(2) 52
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
HDPE, 22 1/2 Bend
WT-1.2 - 17 355mm dia
nr
1.00
43,406
43,406
32,636
HDPE, 45 Bend
WT-1.2 - 18 355mm dia
nr
1.00
43,406
43,406
32,636
nr
1.00
16,626
16,626
12,501
nr
1.00
96,998
96,998
72,931
nr
1.00
70,899
70,899
53,308
nr
1.00
96,890
96,890
72,850
nr
4.00
162,377
649,508
488,352
nr
1.00
94,013
94,013
70,686
nr
2.00
38,744
77,488
58,262
nr
2.00
49,850
99,700
74,962
nr
1.00
87,333
87,333
65,664
nr
1.00
100,704
100,704
75,717
DI, Coupling
WT-1.2 - 29 400mm dia
nr
3.00
33,703
101,109
76,022
nr
1.00
1,028,910
1,028,910
773,617
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
CW(2) 53
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
78,323
78,323
58,889
nr
1.00
76,994
76,994
57,890
nr
2.00
58,141
116,282
87,430
nr
2.00
54,322
108,644
81,687
nr
2.00
161,238
322,476
242,463
nr
1.00
92,290
92,290
69,391
nr
1.00
59,050
59,050
44,398
nr
1.00
48,494
48,494
36,462
Gravity main
HDPE, Pipe piece
WT-1.2 - 39 280mm dia 26900mm long
nr
1.00
181,686
181,686
136,606
nr
1.00
84,426
84,426
63,478
nr
1.00
24,620
24,620
18,511
nr
1.00
47,410
47,410
35,647
nr
1.00
62,792
62,792
47,212
nr
2.00
9,861
19,722
14,829
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Flange Gate valve
WT-1.2 - 35 400mm dia
DI, 250mm dia Washout & overflow
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
CW(2) 54
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
DI, Flow meter
WT-1.2 - 45 150mm dia
nr
1.00
212,299
212,299
159,623
HDPE, 45 Bend
WT-1.2 - 46 280mm dia
nr
1.00
21,880
21,880
16,451
nr
2.00
20,515
41,030
30,850
nr
2.00
14,233
28,466
21,403
nr
1.00
6,420
6,420
4,827
nr
2.00
25,910
51,820
38,962
5,829,480
4,383,068
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Flange Gate Valve
WT-1.2 - 50 150mm dia
Total WT 1.2 - Pipework, Manhole & Chamber carried to CW(2) Bill Summary
CW(2) 55
Narayananan Associates
Description
WT - 1.3
WT-1.3-01
L.sum
1.00
50,000
50,000
37,594
WT-1.3-02
nr
1.00
50,000
50,000
37,594
nr
1.00
100,000
100,000
75,188
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
250,000
250,000
187,970
L.sum
1.00
100,000
100,000
75,188
1,050,000
789,474
Unit
Qty
Rate
(Rs)
Item No
CW(2) 56
Narayananan Associates
Description
Unit
WT-2.0
L. Sum
1.00
42,462,364
31,926,590
WT-2.1
LANDSCAPING
L. Sum
1.00
559,949
421,015
WT-2.2
L. Sum
1.00
1,518,119
1,141,444
WT-2.3
L. Sum
1.00
1,050,000
789,474
45,590,432
34,278,523
CW(3) 57
Qty
Remarks
Narayananan Associates
Item No
Description
WT-2.0
EARTH WORKS
WT-2.0- 01 Care of water and Dewatering
Unit
Rate
(Rs)
Qty
L.Sum
1.00
80,000
80,000
60,150
NIL
m3
265.46
800
212,368
159,675
m3
103.53
960
99,389
74,729
m3
1,040
m3
36.90
8,000
295,200
221,955
m2
132.73
120
15,928
11,976
m3
144.79
1,600
231,664
174,183
m3
82.95
4,000
331,800
249,474
m3
224.74
640
143,834
108,146
IN SITU CONCRETE
Rate to include supplying and placing concrete
(with temperature control) and curing as
specified.
Concrete in Grade 15
WT-2.0 - 11 75 mm thick blinding in tower base
m3
10.62
18,400
195,408
146,923
m3
1.93
18,400
35,512
26,701
m3
7.70
20,800
160,160
120,421
m3
5.55
20,800
115,440
86,797
Reinforced
concrete
in
Grade
25,
reinforcement and formwork measued
separately
WT-2.0 - 15 Reinforced concrete in circular base
m3
119.46
20,800
2,484,768
1,868,247
m3
23.40
20,800
486,720
365,955
m3
32.33
21,200
685,396
515,335
WT-2.0- 09
CW(3) 58
Narayananan Associates
Qty
Rate
(Rs)
Item No
Description
Unit
WT-2.0 - 18
m3
31.99
22,000
703,780
529,158
WT-2.0 - 19
m3
34.49
22,800
786,372
591,257
WT-2.0 - 20
m3
11.65
23,600
274,940
206,722
WT-2.0 - 21
m3
4.66
20,800
96,928
72,878
m3
138.35
24,800
3,431,080
2,579,759
m3
12.21
24,800
302,808
227,675
m3
6.56
25,600
167,936
126,268
m3
3.42
24,800
84,816
63,771
m3
10.37
24,800
257,176
193,365
m3
0.63
25,600
16,128
12,126
61.63
210,000
12,942,300
9,731,053
0.04
208,000
8,320
6,256
CONCRETE ANCILLARIES
Reinforcement
Rate shall include supplying and delivering to
the yard, storing, cutting and bending,
transport to the site, cleaning as specified and
erection placing in position tied with GI
binding wire, cover blocks; complete as
depicted in drawings.
Formwork
All formwork shall be plywood sheet. Rate
includes formwork support system.
WT-2.0 - 30 Fair finish, Type 1 (upto 16.4m level)
m2
962.02
5,200
5,002,504
3,761,281
m2
995.34
6,000
5,972,040
4,490,256
CW(3) 59
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
13.00
28,800
374,400
281,504
nr
2.00
18,400
36,800
27,669
nr
1.00
72,000
72,000
54,135
nr
1.00
39,200
39,200
29,474
m2
81.19
520
42,219
31,744
m2
1.16
480
557
419
m2
0.80
600
480
361
m2
74.06
560
41,474
31,183
FINISHES
Plastering
Rendering 20mm thick cement sand (1:3) and
finished smooth with neat cement floating
WT-2.0 - 41
m2
747.39
520
388,643
292,213
WT-2.0 - 42
m2
538.91
480
258,677
194,494
ELECTRICAL INSTALLATION
WT-2.0 - 43 Measured under Electrical works
WATERPROOFING
Two layer of Epoxy resin coating, inside the
WT-2.0 - 44
water tank
m2
CW(3) 60
Nil
423.89
720
305,201
229,474
Narayananan Associates
Item No
Description
MISCELLANIOUS
Supply and install water level indicator with
WT-2.0 - 45
protection pipe fixed
Unit
Qty
Rate
(Rs)
nr
1.00
48,000
48,000
36,090
nr
1.00
64,000
64,000
48,120
nr
3.00
56,000
168,000
126,316
WT-2.0 - 48
nr
2.00
100,000
200,000
150,376
WT-2.0 - 49
nr
1.00
48,000
48,000
36,090
nr
3.00
167,128
501,384
376,980
nr
3.00
167,128
501,384
376,980
98.38
4,800
472,224
355,056
WT-2.0 - 53
nr
24.92
6,400
159,488
119,916
WT-2.0 - 54
m2
4.76
24,000
114,240
85,895
nr
NIL
nr
8.00
400
3,200
2,406
L. Sum
1.00
8,000
8,000
6,015
WT-2.0 - 58
L. Sum
1.00
7,200
7,200
5,414
WT-2.0 - 59
L. Sum
1.00
640,000
640,000
481,203
CW(3) 61
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Rate to include supply , delivery, laying and
fixing to wall, all pipes & specials including
rubber rings, lubricant, gaskets, bolts & nuts,
all other associated material required for
complete installation.
DI Inlet pipe
DI, Double Spigot pipe with puddle flange
250mm dia 1700mm long, puddle flange 600
WT-2.0 - 60
away from one end
nr
1.00
39,442
39,442
29,656
nr
1.00
66,434
66,434
49,950
nr
3.00
100,948
302,844
227,702
nr
1.00
52,673
52,673
39,604
nr
1.00
55,403
55,403
41,656
nr
1.00
33,981
33,981
25,550
nr
1.00
42,281
42,281
31,790
DI, Coupling
WT-2.0 - 67 250mm dia
nr
1.00
19,058
19,058
14,329
nr
2.00
48,878
97,756
73,501
nr
2.00
53,668
107,336
80,704
nr
4.00
27,475
109,900
82,632
nr
1.00
108,087
108,087
81,268
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Butterfly Valve
WT-2.0 - 71 250mm dia
CW(3) 62
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
DI Outlet Pipe
DI, Double Spigot pipe with puddle flange
150mm dia 1800mm long, puddle flange 600
WT-2.0 - 72
away from one end
nr
1.00
40,598
40,598
30,525
nr
1.00
32,581
32,581
24,497
nr
3.00
101,279
303,837
228,449
nr
1.00
66,105
66,105
49,703
nr
1.00
30,209
30,209
22,714
DI, Coupling
WT-2.0 - 77 150mm dia
nr
1.00
11,128
11,128
8,367
nr
1.00
22,561
22,561
16,963
nr
2.00
39,043
78,086
58,711
nr
1.00
37,627
37,627
28,291
nr
1.00
17,685
17,685
13,297
nr
1.00
74,886
74,886
56,305
nr
1.00
19,816
19,816
14,899
nr
1.00
24,905
24,905
18,726
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Butterfly Valve
WT-2.0 - 82 150mm dia
DI Overflow and washout pipe
DI, Double Spigot pipe with puddle flange
150mm dia 1800mm long, puddle flange600
WT-2.0 - 83
away from one end
DI, Double flange pipe
WT-2.0 - 84 150mm dia 1500mm long
CW(3) 63
Narayananan Associates
nr
1.00
Rate
(Rs)
35,241
nr
1.00
nr
Item No
Description
Unit
Qty
26,497
42,488
42,488
31,946
3.00
48,986
146,958
110,495
nr
1.00
23,253
23,253
17,483
nr
1.00
21,494
21,494
16,161
nr
1.00
10,141
10,141
7,625
nr
1.00
15,638
15,638
11,758
nr
1.00
22,128
22,128
16,638
DI, Coupling
WT-2.0 - 93 150mm dia
nr
1.00
11,128
11,128
8,367
nr
2.00
22,561
45,122
33,926
nr
5.00
14,233
71,165
53,508
nr
1.00
24,210
24,210
18,203
nr
1.00
7,807
7,807
5,870
nr
1.00
74,886
74,886
56,305
42,462,364
31,926,590
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Butterfly Valve
WT-2.0 - 98 150mm dia
CW(3) 64
Narayananan Associates
Item No
Description
WT-2.1
LANDSCAPING
EARTH WORKS
cleaning site, uprooting trees and disposal of
WT-2.1 - 01
debris
Unit
Qty
Rate
(Rs)
m2
482.36 By NWS&DB
72.35 By NWS&DB
WT-2.1 - 02
m3
WT-2.1 - 03
m3
Nill
By NWS&DB
m3
Nill
By NWS&DB
m2
219.00
480
105,120
79,038
m3
7.13
800
5,704
4,289
m2
66.44
120
7,973
5,995
m3
7.59
34,000
258,060
194,030
m2
1.58
20,000
31,600
23,759
ROAD WORKS
WT-2.1 - 10 Trimming and Compacting existing ground
m2
126.57
120
15,188
11,420
m3
25.31
4,000
101,240
76,120
m2
6.32
2,400
15,168
11,405
KERBS
WT-2.1 - 13 Kerbs Type I, 100x300mm
8.29
2,400
19,896
14,959
SITE PROTECTION
WT-2.1 - 14 Wire mesh fence with foundation and posts
85.53 By NWS&DB
nr
1.00 By NWS&DB
CW(3) 65
559,949
421,015
Narayananan Associates
Item No
Description
WT-2.2
MANHOLE 01
Excavation including
WT-2.2 - 01
material
disposal
Unit
of
surplus
Qty
Rate
(Rs)
m3
5.67
800
4,536
3,411
m2
3.24
120
389
292
m3
0.16
18,400
2,944
2,214
m3
2.40
48,000
115,200
86,617
nr
1.00
40,000
40,000
30,075
m3
22.23
800
17,784
13,371
m2
10.34
120
1,241
933
m3
0.52
18,400
9,568
7,194
m3
7.27
20,800
151,216
113,696
1.09
210,000
228,900
172,105
m2
54.73
2,560
140,109
105,345
nr
3.00
8,000
24,000
18,045
nr
1.00
25,558
25,558
19,217
nr
1.00
145,214
145,214
109,183
nr
1.00
31,450
31,450
23,647
WT-2.2 - 04
of
surplus
CW(3) 66
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
HDPE, 90 Bend
WT-2.2 - 16 280mm dia
nr
1.00
18,666
18,666
14,035
nr
1.00
6,792
6,792
5,107
nr
1.00
75,681
75,681
56,903
nr
1.00
28,274
28,274
21,259
nr
2.00
9,861
19,722
14,829
nr
1.00
11,614
11,614
8,732
nr
1.00
212,299
212,299
159,623
nr
1.00
3,950
3,950
2,970
nr
1.00
10,954
10,954
8,236
nr
3.00
14,233
42,699
32,105
nr
2.00
25,482
50,964
38,319
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Flange Gate valve
WT-2.2 - 26 150mm dia
CW(3) 67
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
nr
1.00
24,620
24,620
18,511
nr
1.00
40,152
40,152
30,189
nr
1.00
11,556
11,556
8,689
nr
1.00
22,067
22,067
16,592
1,518,119
1,141,444
PIPEWORK - FITTINGS
Rate to include supply, delivery and
installation, all fittings including all associated
material required for complete installation.
DI, Double Socket 45 Bend
WT-2.2 - 29 150mm dia
PIPEWORK - VALVES
Rate to include supply and installation,
providing supports and protection of joints.
DI, Flap Valve
WT-2.2 - 30 150mm dia
Total WT 2.2 - Pipework, Manhole & Chamber carried to CW(e) Bill Summary
CW(3) 68
Narayananan Associates
Item No
Description
WT - 2.3
WT-2.3-01
WT-2.3-02
Unit
Qty
L.sum
1.00
50,000
50,000
37,594
nr
1.00
50,000
50,000
37,594
nr
1.00
100,000
100,000
75,188
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
250,000
250,000
187,970
L.sum
1.00
100,000
100,000
75,188
1,050,000
789,474
Rate
(Rs)
CW(3) 69
Narayananan Associates
Description
Unit
Qty
TP 01
TRANSMISSION PIPE
PUMBING MAIN
L.Sum
1.00
3,416,865
2,569,072
TP 02
TRANSMISSION MAIN
L.Sum
1.00
29,301,095
22,030,898
TP 03
L.Sum
1.00
2,550,000
1,917,294
35,267,960
26,517,264
CW(4) 70
Remarks
Narayananan Associates
Item No
Description
TP 01
PUMBING MAIN
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Rate to include excavation, supply & installing
pipes, shoring & dewatering, backfilling or filling
with selected material (where necessary),
compaction & disposal of excess & unsuitable
material and reinstatement of surface etc. and
installation of marker tapes, bedding (Type A) as
required.
TP-01-01
420.00
7,833
3,289,860
2,473,579
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
TP-01-02
HDPE, 90 Bend
355mm dia
nr
1.00
40,195
40,195
30,222
TP-01-03
HDPE, 45 Bend
355mm dia
nr
2.00
43,405
86,810
65,271
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks, anchor blocks etc. and protection of
joints (Chamber measured seperately).
TP-01-04
nr
Nill
365,000
TP-01-05
WASHOUT
Rate to include installation of washout
arrangement as depicted in drawings, Supply &
fixing pipes, fittings & Sluice valve (Chamber
measured seperately).
150mm dia washout
nr
Nill
174,880
CW(4) 71
3,416,865
2,569,072
Narayananan Associates
Item No
Description
TP 02
TRANSMISSION MAIN
Rate
(Rs)
Unit
Qty
3,811.00
5,953
22,686,883
17,057,807
PIPEWORK - PIPES
Rate to include excavation, supply & installing
pipes, shoring & dewatering, backfilling or filling
with selected material (where necessary),
compaction & disposal of excess & unsuitable
material and reinstatement of surface etc. and
installation of marker tapes, bedding (Type A) as
required.
TP-02-01
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
TP-02-02
HDPE, 90 Bend
280mm dia
nr
1.00
18,667
18,667
14,035
TP-02-03
HDPE, 45 Bend
280mm dia
nr
2.00
21,880
43,760
32,902
nr
6.00
315,819
1,894,914
1,424,747
nr
2.00
222,223
444,446
334,170
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks, anchor blocks etc. and protection of
joints (Chamber measured seperately).
TP-02-04
Control valve
Supply & fixing of Control Valves complete with
pipes & fittings as depicted in drawings.
TP-02-05
200mm dia
CW(4) 72
Narayananan Associates
Qty
Rate
(Rs)
Item No
Description
Unit
TP-02-06
WASHOUT
Rate to include installation of washout
arrangement as depicted in drawings,Supply &
fixing pipes, fittings & Gate valve (Chamber
measured seperately).
100mm dia washout
nr
5.00
97,810
489,050
367,707
CROSSING
Rate to include additional excavation, additional
shoring, coffer damming, diversion of waterway,
forming of embankment, rubble pitching, trench
cutoff walls, breaking into existing structures,
supply and installation of pipes, fittings, valves
& supports where necessary, making good and
any other items necessary to complete the
crossing as depicted in drawings.
TP-02-07
nr
1.00
64,747
64,747
48,682
TP-02-08
nr
2.00
91,993
183,986
138,335
TP-02-09
nr
1.00
570,923
570,923
429,265
TP-02-10
Bridge Crossing
Bridge Crossing No. 2 (Drg: KWSP/BC-02)
nr
1.00
302,300
302,300
227,293
TP-02-11
nr
1.00
700,000
700,000
526,316
TP-02-12
Road Crossing
300mm dia DI
nr
5.00
86,319
431,595
324,508
TP-02-13
CHAMBER
Rate to include excavation, shoring &
dewatering, compaction & disposal as directed
by the Engineer and concreting, reinforcement &
formwork and finnishing including cover & steps
where necessary.
Type B, 1100x1000x1400mm for air valve
nr
6.00
130,638
783,828
589,344
TP-02-14
nr
2.00
156,048
312,096
234,659
TP-02-15
nr
5.00
5,536
27,680
20,812
TP-02-16
nr
5.00
69,244
346,220
260,316
29,301,095
22,030,898
CW(4) 73
Narayananan Associates
Item No
Description
TP - 03
Unit
Qty
Rate
(Rs)
TP-03-01
L.sum
1.00
750,000
750,000
563,910
TP-03-02
L.sum
1.00
300,000
N/A
N/A
TP-03-03
L.sum
1.00
750,000
750,000
563,910
TP-03-04
L.sum
1.00
300,000
N/A
N/A
TP-03-05
L.sum
1.00
300,000
300,000
225,564
TP-03-06
L.sum
1.00
750,000
750,000
563,910
TP-03-07
L.sum
1.00
300,000
N/A
N/A
CW(4) 74
2,550,000
1,917,294
Narayananan Associates
Description
Unit
Qty
Amount (Rs)
Amount (JPY)
DP 01
L.Sum
1.00
128,298,042
96,464,694
DP 02
L.Sum
1.00
3,500,000
2,631,580
131,798,042
99,096,274
CW(5) 75
Remarks
Narayananan Associates
Item No
Description
DP 01
DISTRIBUTION PIPE
Unit
Rate
(Rs)
Qty
Amount (Rs)
Amount (JPY)
PIPEWORK - PIPES
Rate to include excavation, supply,delivery
&laying/ installing pipes, shoring &
dewatering, backfilling or filling with
selected material (where necessary),
compaction & disposal of excess &
unsuitable material and reinstatement of
surface etc. and installation of marker tapes,
bedding (Type A) as required.
DI, socket & spigot pipe
Depth to invert of pipe not exceeding 1.5m
DP-01-01 300mm dia
350.00
17,860
6,251,000
4,700,000
140.00
25,710
3,599,400
2,706,316
15,030.00
6,286
94,478,580
71,036,526
nr
1.00
66,010
66,010
49,632
nr
1.00
96,880
96,880
72,842
nr
12.00
48,786
585,432
440,174
nr
51,429
nr
17.00
81,593
1,387,081
1,042,918
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks, anchor blocks etc. and protection of
joints (Chamber measured seperately).
CW(5) 76
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
nr
21.00
93,646
1,966,566
1,478,621
Control valve
Rate to include supply and installation,
providing supports and protection of Control
Valves complete with pipes & fittings as
depicted in drawings.
DP-01-10 225mm dia
nr
17.00
125,036
2,125,612
1,598,205
nr
3.00
225,758
677,274
509,229
nr
22.00
93,646
2,060,212
1,549,032
nr
7.00
64,645
452,515
340,237
CROSSING
Rate to include additional excavation,
additional
shoring,
coffer
damming,
diversion of waterway, forming of
embankment, rubble pitching, trench cutoff
walls, breaking into existing structures,
supply and installation of pipes, fittings,
valves & supports where necessary, making
good and any other items necessary to
complete the crossing as depicted in
drawings.
Culvert Crossing (Drg: KWSP/STD/C-02)
DP-01-14 Type A, 225mm dia DI (CH 0+764.15)
nr
2.00
59,421
118,842
89,355
nr
2.00
59,421
118,842
89,355
nr
1.00
79,966
79,966
60,125
WASHOUT
Rate to include supply and installation,
providing supports and protection of
washout arrangement as depicted in
drawings, Complete withpipes, fittings &
Gate valve (Chamber measured seperately).
DP-01-12 80mm dia washout
FIRE HYDRANTS
Rate to include supply and installation,
providing supports and protection of fire
hydrants arrangement as depicted in
drawings, Complete withpipes, fittings &
Gate valve (Chamber measured seperately).
CW(5) 77
Narayananan Associates
nr
2.00
Rate
(Rs)
56,734
nr
2.00
67,485
134,970
101,481
nr
1.00
67,485
67,485
50,741
nr
2.00
67,485
134,970
101,481
nr
2.00
67,485
134,970
101,481
nr
2.00
82,397
164,794
123,905
nr
1.00
90,493
90,493
68,040
nr
2.00
345,593
691,186
519,689
nr
1.00
345,593
345,593
259,844
nr
2.00
345,593
691,186
519,689
Bridge Crossing
DP-01-27 Bridge Crossing (Drg: KWSP/BC-02)
nr
1.00
399,283
399,283
300,213
nr
1.00
399,283
399,283
300,213
nr
1.00
534,504
534,504
401,883
nr
1.00
506,168
506,168
380,577
Road Crossing
DP-01-31 200mm dia DI
nr
18.00
86,319
1,553,742
1,168,227
CHAMBER
Rate to include excavation, shoring &
dewatering, compaction & disposal as
directed by the Engineer and concreting,
reinforcement & formwork and finnishing
including cover & steps where necessary.
DP-01-32 Type A, 1000x800x1300mm for air valve
nr
21.00
114,015
2,394,315
1,800,237
Item No
Description
Unit
Qty
Amount (Rs)
Amount (JPY)
113,468
85,314
DP-01-33
nr
20.00
130,638
2,612,760
1,964,481
DP-01-34
Chamber,
hydrant
nr
7.00
130,638
914,466
687,568
DP-01-35
Surface Box,
washout
nr
22.00
7,908
173,976
130,809
nr
22.00
98,919
2,176,218
1,636,254
128,298,042
96,464,694
1500x1200x1400mm
150x150mm
for
opening
fire
for
CW(5) 78
Narayananan Associates
Item No
DP 02
Description
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
1,000,000
751,880
DP-02-01
L.sum
1.00
1,000,000
DP-02-02
L.sum
1.00
500,000
DP-02-03
L.sum
1.00
1,000,000
L.sum
1.00
500,000
N/A
N/A
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
1,000,000
1,000,000
751,880
L.sum
1.00
500,000
DP-02-05
CW(5) 79
N/A
1,000,000
N/A
3,500,000
N/A
751,880
N/A
2,631,580
Narayananan Associates
Description
Unit
Qty
Amount (Rs)
Amount (JPY)
Remarks
DISTRIBUTION PIPE
L.Sum
1.00
47,848,332
35,976,189
DTK 02
L.Sum
1.00
2,000,000
1,503,760
49,848,332
37,479,949
CW(6) 80
Narayananan Associates
Item No
Description
DPK 01
DISTRIBUTION PIPE
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
PIPEWORK - PIPES
Rate to include excavation, supply & laying
pipes, shoring & dewatering, backfilling or
filling with selected material (where
necessary), compaction & disposal of excess &
unsuitable material and reinstatement of
surface etc. and installation of marker tapes,
bedding (Type A) as required.
PVC (Type 600), Pipe
Depth to invert of pipe not exceeding 1.5m
DPK-01-01 225mm dia
1,621.82
6,286
10,194,761
7,665,234
3,856.91
3,018
11,640,154
8,751,995
2,553.37
1,474
3,763,667
2,829,825
9,208.62
906
8,343,010
6,272,940
nr
3.00
3,780
11,340
8,526
nr
36.00
1,775
63,900
48,045
nr
1.00
3,870
3,870
2,910
nr
5.00
2,275
11,375
8,553
nr
11.00
1,775
19,525
14,680
nr
4.00
6,160
24,640
18,526
nr
10.00
3,870
38,700
29,098
nr
10.00
2,275
22,750
17,105
nr
30.00
1,845
55,350
41,617
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
CW(6) 81
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
nr
1.00
81,620
81,620
61,368
nr
5.00
56,140
280,700
211,053
nr
3.00
53,270
159,810
120,158
nr
9.00
49,000
441,000
331,579
nr
3.00
19,290
57,870
43,511
nr
3.00
18,550
55,650
41,842
nr
8.00
17,550
140,400
105,564
nr
1.00
7,140
7,140
5,368
nr
3.00
8,330
24,990
18,789
nr
17.00
4,690
79,730
59,947
nr
1.00
9,590
9,590
7,211
nr
2.00
7,000
14,000
10,526
nr
5.00
5,400
27,000
20,301
nr
11.00
96,250
1,058,750
796,053
nr
2.00
125,020
250,040
188,000
nr
3.00
78,260
234,780
176,526
nr
2.00
27,700
55,400
41,654
nr
7.00
15,330
107,310
80,684
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks, anchor blocks etc. and protection of
joints (Chamber measured seperately).
Single Orifice Air valve
Supply & fixing of Air Valves as depicted in
drawings, Complete with pipes & fitting and
isolating cock.
DPK-01-27 25mm dia
Control valve
Supply & fixing of Control Valves complete
with pipes & fittings as depicted in drawings.
CW(6) 82
Narayananan Associates
Item No
Description
WASHOUT
Rate to include installation of washout
arrangement as depicted in drawings, Supply
& fixing pipes, fittings & Gate valve (Chamber
measured seperately).
DPK-01-32 80mm dia outlets
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
nr
22.00
113,890
2,505,580
1,883,895
nr
1.00
15,470
15,470
11,632
nr
2.00
22,050
44,100
33,158
nr
1.00
15,470
15,470
11,632
nr
7.00
15,470
108,290
81,421
nr
1.00
17,500
17,500
13,158
nr
2.00
15,470
30,940
23,263
nr
1.00
15,470
15,470
11,632
nr
1.00
15,470
15,470
11,632
nr
2.00
295,750
591,500
444,737
Bridge Crossing
DPK-01-42 Bridge Crossing (Drg: KWSP/BC-04)
nr
1.00
205,870
205,870
154,789
nr
1.00
700,000
700,000
526,316
nr
2.00
560,000
1,120,000
842,105
nr
3.00
420,000
1,260,000
947,368
Road Crossing
DPK-01-46 200mm dia DI
nr
2.00
86,310
172,620
129,789
CROSSING
Rate to include additional excavation,
additional shoring, coffer damming, diversion
of waterway, forming of embankment, rubble
pitching, trench cutoff walls, breaking into
existing structures, supply and installation of
pipes, fittings, valves & supports where
necessary, making good and any other items
necessary to complete the crossing as
depicted in drawings.
CW(6) 83
Narayananan Associates
Item No
Description
CHAMBER
Rate to include excavation, shoring &
dewatering, compaction & disposal as
directed by the Engineer and concreting,
reinforcement & formwork and finnishing
including cover & steps where necessary.
DPK-01-47 Type A, 1000x800x1300mm for air valve
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
nr
11.00
114,030
1,254,330
943,105
DPK-01-48
nr
5.00
130,620
653,100
491,053
DPK-01-49
nr
9.00
22,120
199,080
149,684
nr
22.00
5,530
121,660
91,474
nr
22.00
69,230
1,523,060
1,145,158
47,848,332
35,976,189
DPK-01-51
CW(6) 84
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Amount (Rs)
Amount (JPY)
L.sum
1.00
500,000
500,000
375,940
DPK-02-02
L.sum
1.00
200,000
N/A
N/A
DPK-02-03
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
200,000
N/A
N/A
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
500,000
N/A
N/A
DPK-02-05
CW(6) 85
2,000,000
1,503,760
Narayananan Associates
Description
Unit
Qty
DPP 01
L.Sum
1.00
9,576,300
7,200,228
DPP 02
L.Sum
1.00
1,800,000
1,353,384
11,376,300
8,553,612
CW(7) 86
Remarks
Narayananan Associates
Item No
Description
DPP 01
DISTRIBUTION PIPE
Unit
Qty
Rate
(Rs)
PIPEWORK - PIPES
Rate to include excavation, supply, delivery,
laying or installing pipes, shoring &
dewatering, backfilling or filling with selected
material (where necessary), compaction &
disposal of excess & unsuitable material and
reinstatement of surface etc. and installation
of marker tapes, bedding (Type A) as required.
PVC (Type 600), Pipe
Depth to invert of pipe not exceeding 1.5m
DPP-01-01 160mm dia
900.00
3,018
2,716,200
2,042,256
825.00
1,474
1,216,050
914,323
1,665.00
906
1,508,490
1,134,203
nr
2.00
1,775
3,550
2,669
nr
3.00
18,550
55,650
41,842
nr
7.00
17,550
122,850
92,368
nr
4.00
7,000
28,000
21,053
nr
5.00
5,400
27,000
20,301
nr
1.00
77,000
77,000
57,895
PIPEWORK - FITTINGS
Rate to include for providing fittings, thrust
blocks, anchor blocks etc.
Rate to include for additional excavation,
shoring, dewatering, construction of concrete
thrust block & all necessary items of work
required for complete installation of fittings.
PIPEWORK - VALVES
Rate to include for providing supports, thrust
blocks, anchor blocks etc. and protection of
joints (Chamber measured seperately).
Single Orifice Air valve
Supply and Installation of Air Valves as
depicted in drawings, Complete with pipes &
fitting and isolating cock.
DPP-01-09 25mm dia
CW(7) 87
Narayananan Associates
Item No
Description
Unit
Qty
Rate
(Rs)
Control valve
Supply and Installation of Control Valves
complete with pipes & fittings as depicted in
drawings.
DPP-01-10 150mm dia
nr
4.00
84,000
336,000
252,632
nr
2.00
35,000
70,000
52,632
nr
4.00
35,000
140,000
105,263
nr
9.00
77,000
693,000
521,053
nr
1.00
560,000
560,000
421,053
CHAMBER
Rate to include excavation, shoring &
dewatering, compaction & disposal as directed
by the Engineer and concreting, reinforcement
& formwork and finnishing including cover &
steps where necessary.
DPP-01-15 Type A, 1000x800x1300mm for air valve
nr
1.00
114,030
114,030
85,737
WASHOUT
Rate to include supply and installation of
washout arrangement as depicted in drawings,
Complete withpipes, fittings & Gate valve
(Chamber measured seperately).
DPP-01-13 80mm dia outlets
CROSSING
Rate to include additional excavation,
additional shoring, coffer damming, diversion
of waterway, forming of embankment, rubble
pitching, trench cutoff walls, breaking into
existing structures, supply and installation of
pipes, fittings, valves & supports where
necessary, making good and any other items
necessary to complete the crossing as depicted
in drawings.
DPP-01-16
nr
4.00
130,620
522,480
392,842
DPP-01-17
nr
6.00
21,000
126,000
94,737
nr
9.00
14,000
126,000
94,737
nr
9.00
126,000
1,134,000
852,632
9,576,300
7,200,228
DPP-01-19
CW(7) 88
Narayananan Associates
Item No
Description
DPP 02
Unit
Qty
Rate
(Rs)
DPP-02-01
L.sum
1.00
500,000
500,000
375,940
DPP-02-02
L.sum
1.00
100,000
N/A
N/A
DPP-02-03
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
100,000
N/A
N/A
L.sum
1.00
500,000
500,000
375,940
L.sum
1.00
300,000
300,000
225,564
L.sum
1.00
300,000
N/A
N/A
DPP-02-05
CW(7) 89
1,800,000
1,353,384
Narayananan Associates
Description
Unit
Qty
MW 01
MACHINERY WORK
WATER INTAKE
L.Sum
1.00
9,672,000
7,272,178
MW 02
L.Sum
1.00
8,836,000
6,643,608
MW 03
CHLORINATION FACILITIES
L.Sum
1.00
1,688,000
1,269,172
EW 01
ELECRICAL WORKS
WATER INTAKE
L.Sum
1.00
5,492,000
4,129,322
EW 02
L.Sum
1.00
5,940,000
4,466,165
EW 03
CHLORINATION FACILITIES
L.Sum
1.00
204,000
153,383
EW 04
L.Sum
1.00
720,000
541,353
EW 05
PARANTHAN TOWER
L.Sum
1.00
720,000
541,353
33,272,000
25,016,534
CW(8) 90
Remarks
Narayananan Associates
Item No
Description
MW 01
WATER INTAKE
MW-01-04
Unit
Qty
Rate
(Rs)
L.sum
1.00
104,000
104,000
78,195
nr
2.00
1,248,000
2,496,000
1,876,692
L.sum
1.00
520,000
520,000
390,977
nr
1.00
988,000
988,000
742,857
L.sum
1.00
936,000
936,000
703,759
MW-01-06
L.sum
1.00
1,352,000
1,352,000
1,016,541
MW-01-07
L.sum
1.00
832,000
832,000
625,564
L.sum
1.00
1,248,000
1,248,000
938,346
L.sum
1.00
156,000
156,000
117,293
L.sum
1.00
104,000
104,000
78,195
L.sum
1.00
936,000
936,000
703,759
9,672,000
7,272,178
CW(8) 91
Narayananan Associates
Item No
Description
MW 02
Unit
Qty
Rate
(Rs)
L.sum
1.00
88,000
88,000
66,165
nr
2.00
1,232,000
2,464,000
1,852,632
MW-02-03
L.sum
1.00
528,000
528,000
396,992
MW-02-04
nr
1.00
836,000
836,000
628,571
MW-02-05
L.sum
1.00
924,000
924,000
694,737
L.sum
1.00
704,000
704,000
529,323
L.sum
1.00
1,056,000
1,056,000
793,985
L.sum
1.00
132,000
132,000
99,248
L.sum
1.00
88,000
88,000
66,165
L.sum
1.00
1,056,000
1,056,000
793,985
L.sum
1.00
960,000
960,000
721,805
8,836,000
6,643,608
MW-02-07
MW-02-11
CW(8) 92
Narayananan Associates
Item No
Description
MW 03
CHLORINATION FACILITIES
Unit
Qty
Rate
(Rs)
L.sum
1.00
80,000
80,000
60,150
L.sum
1.00
160,000
160,000
120,301
nr
2.00
400,000
800,000
601,504
L.sum
1.00
80,000
80,000
60,150
nr
2.00
160,000
320,000
240,602
L.sum
1.00
40,000
40,000
30,075
nr
2.00
24,000
48,000
36,090
L.sum
1.00
8,000
8,000
6,015
nr
2.00
48,000
96,000
72,180
L.sum
1.00
16,000
16,000
12,030
L.sum
1.00
16,000
16,000
12,030
L.sum
1.00
8,000
8,000
6,015
L.sum
1.00
16,000
16,000
12,030
1,688,000
1,269,172
MW-03-04
MW-03-08
auto
MW-03-09
MW-03-10
Installation Chlorine
Described above.
Neutralization Tankas
CW(8) 93
Narayananan Associates
Unit
Description
EW 01
WATER INTAKE
EW-01-01
Intake pump Starter Panel, indoor selfsupporting, metal enclosed type (11KW x 1
submersible motor,VVVF with DOL bypass) as
specified in page 4-5 and Depicted in drawing nr
WTP-PE-03
L.sum
1.00
1,768,000
1,768,000
1,329,323
EW-01-02
L.sum
1.00
416,000
416,000
312,782
EW-01-03
Power cable
L.sum
1.00
728,000
728,000
547,368
EW-01-04
L.sum
1.00
832,000
832,000
625,564
EW-01-05
L.sum
1.00
624,000
624,000
469,173
EW-01-06
Intake Turbidity
L.sum
1.00
240,000
240,000
180,451
EW-01-07
L.sum
1.00
104,000
104,000
78,195
EW-01-08
L.sum
1.00
104,000
104,000
78,195
EW-01-09
L.sum
1.00
676,000
676,000
508,271
5,492,000
4,129,322
CW(8) 94
Qty
Rate
(Rs)
Item No
Narayananan Associates
Description
EW 02
EW-02-01
L.sum
1.00
1,408,000
1,408,000
1,058,647
EW-02-02
L.sum
1.00
440,000
440,000
330,827
EW-02-03
Power cable
L.sum
1.00
616,000
616,000
463,158
EW-02-04
L.sum
1.00
704,000
704,000
529,323
EW-02-05
L.sum
1.00
264,000
264,000
198,496
EW-02-06
L.sum
1.00
1,600,000
1,600,000
1,203,008
EW-02-07
Monitoring Panel
L.sum
1.00
N/A
EW-02-08
L.sum
1.00
132,000
132,000
99,248
EW-02-09
L.sum
1.00
88,000
88,000
66,165
EW-02-10
L.sum
1.00
528,000
528,000
396,992
L.sum
1.00
160,000
160,000
120,301
5,940,000
4,466,165
EW-02-11
Unit
Qty
Rate
(Rs)
Item No
CW(8) 95
Narayananan Associates
Unit
Qty
Rate
(Rs)
Item No
Description
EW 03
CHLORINATION FACILITIES
EW-03-01
L.sum
1.00
40,000
40,000
30,075
EW-03-02
L.sum
1.00
56,000
56,000
42,105
EW-03-03
L.sum
1.00
4,000
4,000
3,008
EW-03-04
Power cable
L.sum
1.00
24,000
24,000
18,045
EW-03-05
L.sum
1.00
40,000
40,000
30,075
EW-03-06
L.sum
1.00
16,000
16,000
12,030
EW-03-07
L.sum
1.00
8,000
8,000
6,015
EW-03-08
L.sum
1.00
8,000
8,000
6,015
EW-03-09
Spares
L.sum
1.00
8,000
8,000
6,015
204,000
153,383
CW(8) 96
Narayananan Associates
Item No
Description
EW 04
Unit
Qty
Rate
(Rs)
Item
1.00
80,000
80,000
60,150
Item
1.00
240,000
240,000
180,451
nr
1.00
400,000
400,000
300,752
720,000
541,353
CW(8) 97
Narayananan Associates
Item No
Description
EW 05
PARANTHAN TOWER
Unit
Qty
Rate
(Rs)
EW-05 - 03
Item
1.00
80,000
80,000
60,150
Item
1.00
240,000
240,000
180,451
nr
1.00
400,000
400,000
300,752
720,000
541,353
CW(8) 98
Narayananan Associates
Description
Unit
Qty
Rate
(Rs)
set
1,200.00
312.00
374,400
281,504
LE(a)-02
set
150.00
416.00
62,400
46,917
LE(a)-03
set
150.00
1,040.00
156,000
117,293
LE(a)-04
set
1,500.00
1,040.00
1,560,000
1,172,932
LE(a)-05
set
3,000.00
31.00
93,000
69,925
LE(a)-06
6,000.00
208.00
1,248,000
938,346
LE(a)-07
set
3,000.00
31.00
93,000
69,925
LE(a)-08
set
1,500.00
520.00
780,000
586,466
LE(a)-09
set
1,500.00
2,600.00
3,900,000
2,932,331
LE(a)-10
set
1,500.00
104.00
156,000
117,293
8,422,800
6,332,932
LE 99
Narayananan Associates
Description
Unit
Qty
Rate
(Rs)
LOBORATORY INSTRUMENTS
LE(b)-01
set
1.00
20,800
20,800
15,639
LE(b)-02
set
1.00
312,000
312,000
234,586
LE(b)-03
set
1.00
520,000
520,000
390,977
LE(b)-04
set
2.00
31,200
62,400
46,917
LE(b)-05
set
2.00
52,000
104,000
78,195
LE(b)-06
set
2.00
114,400
228,800
172,030
LE(b)-07
set
2.00
223,600
447,200
336,241
LE(b)-08
set
1.00
83,200
83,200
62,556
1,778,400
1,337,141
LE 100
Narayananan Associates
Description
Unit
Qty
Rate
(Rs)
LE(c)-01
set
2.00
52,000
104,000
78,195
LE(c)-02
2.00
62,400
124,800
93,835
LE(c)-03
set
1.00
93,600
93,600
70,376
322,400
242,406
LE 101
Narayananan Associates
Description
Unit
Qty
Rate
(Rs)
IC(a) -01
L.Sum
1.00
N/A
IC(a) -02
L.Sum
1.00
10,000,000
10,000,000
IC(a) -03
L.Sum
1.00
1,150,000
N/A
IC(a) -04
Testing Laboratory
L.Sum
1.00
4,000,000
IC(a) -05
L.Sum
1.00
1,670,000
N/A
N/A
N/A
N/A
4,000,000
7,518,797
N/A
3,007,519
nrs
1.00
2,000,000
IC(a) -07
nrs
4.00
600,000
2,400,000
1,804,511
IC(a) -08
nrs
3.00
400,000
1,200,000
902,256
nrs
1.00
1,500,000
IC(a) -10
nrs
3.00
1,500,000
4,500,000
3,383,459
N/A
N/A
IC(a) -11
L.Sum
1.00
3,500,000
3,500,000
2,631,579
IC(a) -12
L.Sum
1.00
2,150,000
2,150,000
1,616,541
IC(a) -13
L.Sum
1.00
2,000,000
IC 102
N/A
N/A
27,750,000
20,864,662
Narayananan Associates
Description
Unit
Qty
Rate
(Rs)
ON SITE EXPENCES
IC(b) -01
L.Sum
1.00
IC(b) -02
L.Sum
1.00
Nill
IC(b) -03
L.Sum
1.00
By Daiho
IC(b) -04
L.Sum
1.00
2,000,000
IC(b) -05
L.Sum
1.00
By Daiho
IC(b) -06
L.sum
1.00
Nill
IC(b) -07
L.Sum
1.00
40,000,000
40,000,000
IC(b) -08
Furniture
and
Equipments
Communication facilities for KDG
L.Sum
1.00
6,025,000
N/A
N/A
IC(b) -09
L.Sum
1.00
3,000,000
N/A
N/A
IC(b) -10
L.Sum
1.00
500,000
N/A
N/A
IC(b) -11
L.Sum
1.00
500,000
500,000
375,940
IC(b) -12
L.Sum
1.00
10,000
10,000
7,519
43,510,000
32,714,286
and
contractor's
including
IC 103
1,000,000
1,000,000
2,000,000
751,880
-
1,503,759
30,075,188
Narayananan Associates