SULTANATE OF OMAN

MINISTRY OF TRANSPORT AND COMMUNICATIONS


DIRECTORATE GENERAL OF ROADS & LAND TRANSPORT
MUSCAT

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT


TENDER NO. 51/2012
MONTHLY PROGRESS REPORT NO. 9
SEPTEMBER 2014

CONSULTANT:

CONTRACTOR:

RENARDET S.A. & PARTNERS CONSULTING


ENGINEERS LLC.
P.O. Box 579, Muscat, P.C. 100,
Sultanate of Oman

CONSOLIDATED CONTRACTORS CO. LLC


P.O. Box 614,
Muscat, P.C. 100,
Sultanate of Oman

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Table of Contents
1.

PROJECT PARTICULARS .............................................................................................................................................. 2

2.

SCOPE OF WORK ....................................................................................................................................................... 3

3.

TYPICAL CROSS SECTIONS .......................................................................................................................................... 4

4.

SITE VISITS/ MEETINGS .............................................................................................................................................. 6

5.

ENGINEERS SITE STAFF ............................................................................................................................................. 7

6.

PROGRESS S-CURVE ................................................................................................................................................... 8

7.

STATUS OF MAJOR ACTIVITIES ................................................................................................................................ 10

8.

BRIDGE SUB-STRUCTURE PROGRESS SCHEDULE ...................................................................................................... 11

9.

MSE WALLS PROGRESS SCHEDULE ........................................................................................................................... 12

10.

BOX CULVERTS PROGRESS SCHEDULE...................................................................................................................... 14

11.

PROGRESS STATUS OF UTILITY CROSSING DUCTS .................................................................................................... 16

12.

PROJECT STRIP CHART ............................................................................................................................................. 19

13.

FINANCIAL STATUS OF PAYMENTS .......................................................................................................................... 24

14.

DETAILS OF EQUIPMENT AVAILABLE AT SITE ........................................................................................................... 25

15.

DETAILS OF MANPOWER AVAILABLE AT SITE .......................................................................................................... 27

16.

QA/QC REPORTS...................................................................................................................................................... 29

17.

STATUS OF MATERIAL APPROVALS .......................................................................................................................... 34

18.

ENGINEERS COMMENTS ......................................................................................................................................... 35

19.

DETAILS OF CORRESPONDENCE DURING THE MONTH ............................................................................................. 36

20.

PROGRESS PHOTOGRAPHS ...................................................................................................................................... 38

RENARDET S.A. & PARTNERS

Page 1

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

1.

Project Particulars

Client:

Ministry of Transport & Communications


P.O. Box 684, Muscat, Postal Code 113
Directorate General of Roads
Sultanate of Oman.

Consultant:

Renardet S.A & Partners L.L.C.


P.O. Box 579, Muscat, Postal Code 100
Sultanate of Oman.

Contractor:

Consolidated Contractors Company L.L.C.


P.O. Box 614, Muscat, Postal Code 100
Sultanate of Oman.

Project Commencement Date:

30.10.2013

Mobilization Period:

60 Days

Construction Period:

548 Days

Completion date:

29.06.2015

Original Contract Value:


(Including Contingencies)

R.O. 17,884,403.000

Amount of Contingencies:

R.O. 1,402,155.613

Original Contract Value:


(Excluding Contingencies)

R.O. 16,482,247.387

Planned Physical Progress for September


2014

9.09%

Actual Physical Progress for September


2014

9.38%

Planned physical progress cumulative up to


end of September 2014
Achieved physical progress cumulative up
to end of September 2014

RENARDET S.A. & PARTNERS

39.87%

39.18%

Page 2

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:

Removal of existing asphalt surface, extension of existing embankment and earthwork to


achieve the designed profile and gradient.
Removal of existing drainage structures and construction of new ones including protection
works as shown on construction drawings and as directed.
Expropriation of open/built up properties and removal of existing structures thereupon.
Construction of interchange ramps, Box Girder Bridge, roundabout, pedestrian underpasses and
service roads.
Provision of new street lighting system/traffic signals and removal/disposal of existing street
light poles including conductors/cables, transformers, feeder pillars, foundations etc., all for the
proper completion of the job.
Construction of earthen embankment/sub grade, sub-base, aggregate base course, bituminous
base course and bituminous wearing course as per details on the construction drawings.
Installation of road side furniture (traffic signs, road marking etc.) and protection works on
embankment slopes.
Relocation/Protection of existing LT, 11KV and 33KV transmission lines and allied items
(transformers etc.) as per the requirements of concerned authority.
Relocation/Protection of existing utilities (sewerage, telephone, electricity, water lines and
irrigation) as per the requirements of concerned authorities.
Provision of ducts for future utilities as per the requirements of utility operator.
Construction of concrete safety barriers, fixing of guard rails and paving tiles.
Provision of traffic diversion in coordination with concerned authorities.

RENARDET S.A. & PARTNERS

Page 3

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

3. Typical Cross Sections

RENARDET S.A. & PARTNERS

Page 4

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 5

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

4. Site visits/ Meetings


S. No.

Details of Site Visit

Date

Final Outcome/ Decisions

Site Inspection of DGR Projects


Manager and Materials Engineer

07.09.2014

Site construction activities and


Testing of materials/ works are
audited.

Meeting with Ministry of Water


Resources, Sohar

11.09.2014

Discussed about the cross drainage


facilities those are proposed in the
Project and requested for details of
Flood Limits for 44 Cell Box
Culvert. Ministry asked to submit
a request officially to their Muscat
office.

Meeting with Projects Manager and


Materials Engineer of DGR at their
office in Muscat.

15.09.2014

Discussed regarding the Rock Soil


and Rockfill embankments proposed
by Contractor and agreed the general
methodology.

Meeting
Director
Deputy.

with Sohar Municipality


of Maintenance and his

17.09.2014

Discussed regarding proposed Taxi


Parking areas and Pipe Culvert in
Buraimi Road Ch. 0+260.

DGR Projects Managers site inspection


and meeting at Project Office.

28.09.2014

Agreed to proceed with Rock Soil


embankment filling of 400mm loose
layer and testing method.

Meeting with Omantel Team Leader


OSP, CCC and Subcontractor

30.09.2014

Discussed and agreed the general


methodology
of
Construction,
Supervision and Certification of
Telecom relocation works in the
Project.

RENARDET S.A. & PARTNERS

Page 6

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

5. Engineers Site Staff


S.
Name
No.
1. Roberto Benigni

Designation

Date of
Joining

Head Supervision Projects

2.

Muneer Abdul

Resident Engineer

19.03.2014

3.

Hussein Shah

Material Engineer

04.01.2014

4.

Ernesto B. Paredes

Bridge Engineer

16.04.2014

5.

Sande H Tangaras

Civil Engineer

08.06.2014

6.

Danilo

Quantity Surveyor

19.06.2014

6.

Mohamed Safie

Land Surveyor

04.01.2014

7.

Aseef Iqbal

Site Inspector

10.02.2014

8.

Alaa Aldin Abdelfatah

Site Inspector

30.03.2014

9.

Walid Samy Abdoh Mostafa

Material Inspector

01.04.2014

Secretary

13.04.2014

10. Haneefa Mohmmed Al Zadjali

RENARDET S.A. & PARTNERS

Page 7

6. Progress S-Curve
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN
MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS

12

120.00

MONTHS

Actual per Month

2013

CL14 Org Plan Cumulative %

Revised Sch. Cummulative %

2014
Jan

Feb

Mar

Apr

May

Jun

Actual Cumulative

2015
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

8.49

7.90

8.08

6.71

6.25

4.68

3.59

3.34

4.42

Actual per Month

0.28

Oct

Sep

Aug

Jul

Jun

May

Apr

Feb

2015

Revised Sch. per Month %

Dec

CUMULATIVE PROGRESS

Jan

2014

CL14 Org Plan per Month %

MONTHLY PROGRESS

Nov

Sep

Jun

2013

Mar

0.00

Dec

Oct

20.00

Aug

Jul

40.00

May

Apr

60.00

Mar

Feb

80.00

Jan

% Cumulative

100.00

Dec

% MONTHLY

10

0.18

1.01

3.01

5.53

5.18

7.36

7.30

9.33

Jul

Aug

3.29
-

1.64
-

Sep
1.11
-

Oct
0.62
-

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

Actual Cum ulative

0.28

0.45

1.46

4.48

10.01

15.19

22.55

29.86

39.18

UPGRADING OF FALAJ AL QABAIL ROUNDABOUT - OMAN

REV.:
0
PERIOD ENDING:

Sep-14

MANHOURS OVERALL PROJECT S-CURVE

Item

Description

Budgeted
Man-Hrs

56,423

Road Diversions

Wtd.
%

2.73

Plan/
Actual

2013
Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

CL14 Plan %

0.30

8.67

19.23

26.89

31.77

36.64

41.51

46.39

51.26

56.13

61.01

65.88

70.76

75.63

80.50

85.38

90.25

95.13

100.00

100.00

100.00

100.00

100.00

80.93

84.74

88.56

92.37

96.18

100.00

100.00

100.00

100.00

100.00

100.00

100.00

80.66

87.59

88.57

100.00

100.00

100.00

Revised Plan %
Actual

CL14 Plan %

Clearing &
Removal of
Obstructions

19,558

Embankment

74,043

0.95

3.59

14,821

Subbase &
Aggregate Base

50,004

Bituminous
Pavement

73,724

0.72

42.78

46.60

50.41

44.11

51.21

56.24

60.13

0.00

0.38

20.37

47.70

48.33

48.33

48.33

48.33

3.57

48.33

29.85

78.13

78.13

78.13

Actual

10.09

10.09

17.59

19.52

77.42

69.96

70.18

70.18

70.18

0.00

0.00

0.78

0.00

Revised Plan %

Actual

Revised Plan %

Revised Plan %

0.00
0.00
-

0.00
0.00
-

1.01
0.00
-

9.21
5.00
0.00
-

6.58
4.35
29.30
5.00
0.00
-

16.76
4.89
45.91

29.38

41.37

58.64

Revised Plan %

66.60

3.32

12.89

28.83

5.27

14.93

29.52

56.90

62.24

64.59

67.94

4.26

8.17

16.03

32.68

53.13

53.23
0.00

62.16
0.00

74.91
0.00

78.29
11.07

91.86
26.27

Actual

54.23
48.33
78.13
74.18
43.89
69.08
67.05
41.98
-

58.04
48.33
78.13
82.85
60.03
69.08
67.47
59.98
3.58

61.86
48.33
78.13
84.75
74.82
75.05
67.47
78.73
17.42

65.67
59.91
78.13
84.75
90.03
82.85
67.90
79.90
31.37

69.48
77.84
78.13
85.24
95.24
93.48
68.32
79.90
51.32

73.30
90.27
78.13
92.34
95.95
98.64
68.32
85.20
75.82

77.11
94.93
78.13
92.34

100.00

100.00

100.00

100.00

100.00

95.95

96.09

98.30

99.46

99.54

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

68.32

81.11

93.02

97.11

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

75.82

87.25

87.25

98.60

100.00

100.00

100.00

100.00

100.00

100.00

51.97

86.66

90.05

93.03

100.00

89.45
75.82

98.36

92.60
75.82

1.26
0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.00
-

0.08
-

7.77
-

19.32
-

31.22
-

44.94
0.08

51.98
8.44

52.14
22.42

90.14
46.57

90.14
51.97

Actual
CL14 Plan %

Concrete for
Box Culvert
/Underpas

788,138

Concrete for
Bridge

456,522

38.19

22.12

1.50

Incidental
Construction

275,037

MSE walls

141,190

13.33

6.84

MEP Works &


Ducts

83,264

2,063,644

4.03

100.000

0.00

0.23

1.43

2.97

10.17

51.47

63.06

0.26

2.64

7.33

20.62

35.14

50.06

62.76

Actual

0.48

1.26

5.59

14.93

27.72

40.08

55.38

Revised Plan %

0.00
0.00

0.00
0.00

4.02
0.00

Revised Plan %

Actual

0.00

0.00

0.00

15.21
0.01
0.00
2.50
0.00

34.62

39.02

49.64

59.51

71.33

26.30
3.42

30.75
4.23

5.50

6.08

6.08

61.45

74.69

90.19

24.07

14.39

13.24

16.19

16.72

27.56

0.00

0.00

2.80

0.00

Actual

0.00

0.00

0.00

Revised Plan %

Actual

Revised Plan
Actual Cum

0.11
-

4.43
6.16
0.00
-

99.96

29.64

22.33
2.63

Actual

92.89

22.09

0.00

84.50

74.07

18.14
1.21

83.46

77.37

13.76

0.00

83.38

72.78

7.75

81.40

75.97

14.73
0.38

0.00

69.26

68.40

6.05
0.00

Revised Plan %

Revised Plan %

57.89

74.26

2.77

17.23
9.87
0.00
-

0.13

5.52

2.61
33.36

4.98
49.13

6.42
65.07

17.87
8.31
80.79

43.85
93.82

2.30

17.26

33.64

49.01

17.63

25.69

35.90

49.03

65.95

0.17

0.79

1.43

5.65

61.59

72.98

81.15

80.05

100.00

100.00

100.00

100.00

100.00

74.67

83.42

84.04

84.30

87.32

95.58

98.11

99.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

85.14

87.00

93.50

100.00

100.00

100.00

100.00

100.00

100.00

100.00

99.76

100.00

100.00

100.00

100.00

100.00

100.00

94.70

98.41

100.00

100.00

100.00

100.00

34.35
94.70
83.94

82.40

99.38
94.70
84.42

88.97

99.76
94.70
85.35

92.13

94.70
92.86

98.55

100.00

100.00

100.00

100.00

100.00

7.02

20.33

38.29

50.60

59.52

72.89

81.07

96.39
83.55

86.89

90.26

95.34

98.27

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

64.70

79.88

95.44

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

100.00

70.94

75.04

94.02

96.43

10.67

0.99

13.41

0.33

2.34

9.42

9.26

13.38

16.87

17.75

20.45

21.84

100.00

100.00

100.00

100.00

100.00

100.00

17.07

30.56
23.51

32.94
31.40

41.66

47.49

47.55

47.55

83.28

93.95

97.61

100.00

100.00

100.00

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.48

10.01

15.19

22.55

29.86

39.18

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jun

Jul

Aug

2014

2013
Jan

Feb

Mar

Apr

2015
Jan

Feb

Mar

Apr

May

Sep

Oct

CL14 Org Plan per Month %

0.01

0.25

1.42

4.23

7.25

10.06

9.42

9.73

10.21

9.79

8.49

5.72

4.55

3.56

2.79

3.83

3.55

3.47

1.67

Revised Sch. per Month %

0.11

0.14

0.23

0.28

1.71

3.18

6.84

9.16

9.14

9.08

8.49

7.90

8.08

6.71

6.25

4.68

3.59

3.34

4.42

3.29

1.64

1.11

0.62

Actual per Month

CUMULATIVE PROGRESS

36.51

Dec

MONTHLY PROGRESS

23.65

Actual
CL14 Plan %
30,920

0.00

Revised Plan %
CL14 Plan %

Drainage Works

TOTAL

38.97

43.00
7.40

CL14 Plan %

35.16

37.31
-

CL14 Plan %

30.90

22.36
-

CL14 Plan %

24.18

13.03
-

CL14 Plan %

17.58

6.62
-

Actual
CL14 Plan %
2.42

0.00

9.30

CL14 Plan %

Structural
Excavation

2015

Revised Plan %
CL14 Plan %

4.11

2014

0.28

0.18

1.01

3.01

5.53

5.18

7.36

7.30

9.33

CL14 Org Plan Cum ulative %

0.01

0.26

1.67

5.91

13.15

23.21

32.64

42.37

52.58

62.37

70.86

76.59

81.13

84.69

87.48

91.31

94.86

98.33

100.00

100.00

100.00

100.00

100.00

Revised Sch. Cum m ulative %

0.11

0.25

0.48

0.76

2.47

5.64

12.48

21.64

30.78

39.87

48.35

56.26

64.34

71.05

77.31

81.99

85.59

88.93

93.35

96.64

98.27

99.38

100.00

0.28

0.45

1.46

4.48

10.01

15.19

22.55

29.86

39.18

Actual Cum ulative

7.

Sl. No.

Status of Major Activities

Description

Unit

BOQ Qty.
(Revised)

Actual Qty. % Completion

Clearing & Grubbing

M2

162,000

129,901

80.19%

Borrow Excavation (to embankment) M3

340,000

71,000

20.88%

Granular Sub-base

M3

28,700

1,500

5.23%

Concrete for Culverts

M3

15,000

9,950

66.33%

Concrete for Bridge

M3

13,805

2,793

20.23%

Steel reinforcement Fixing

ton

4,900

1,778

36.28%

Working Piles

M3

2,826

2,826

100.00%

Mortared Stone Riprap

M3

5,210

0.00

0.00%

MSE Walls

M2

13,200

5,045

38.22%

11

RCC Drainage Pipes

LM

4,530

712

15.71%

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

8. Bridge Sub-Structure Progress Schedule


SUB-STRUCTURE WORK PROGRESS (LHS)
ACTIVITY
PEDESTAL

PIER

AB1 L

P1L

P2L

P3L

P4L

P5L

AB2 L

N/A

N/A

2nd Lift

12-Aug-14

19-Aug-14

24-Jul-14

28-Sep-14

4-Sep-14

Height (m)

6.920

6.920

6.920

6.920

6.920

1st Lift

23-Jul-14

7-Aug-14

29-Jun-14

15-Sep-14

10-Aug-14

Height (m)

1.153

1.210

1.440

1.248

1.225

BIT. PAINTING

28-May-14

26-Jun-14

17-May-14

4-Sep-14

23-Jun-14

PILE CAP (Pier & Abut.)

17-May-14

18-Jun-14

8-May-14

25-Aug-14

11-Jun-14

N/A

11-May-14

11-Jun-14

1-May-14

17-Aug-14

3-Jun-14

N/A

AB2 R

F/P & BLINDING

SUB-STRUCTURE WORK PROGRESS (RHS)


ACTIVITY

AB1 R

P1R

P2R

P3R

P4R

P5R

N/A

N/A

N/A

9-Jun-14

28-Jun-14

22-Jun-14

21-Sep-14

10-Jul-14

N/A

6.920

6.920

6.920

6.920

6.920

N/A

20-May-14

11-Jun-14

26-May-14

10-Sep-14

22-Jun-14

N/A

0.366

0.423

0.649

0.461

0.438

BIT. PAINTING

12-May-14

25-May-14

8-May-14

4-Sep-14

31-May-14

PILE CAP (Pier & Abut.)

4-May-14

13-May-14

4/30/2014

27-Aug-14

20-May-14

N/A

27-Apr-14

7-May-14

22-Apr-14

20-Aug-14

14-May-14

N/A

PEDESTAL

PIER
2nd Lift
Height (m)
1st Lift
Height (m)

F/P & BLINDING

PREVIOUS

RENARDET S.A. & PARTNERS

PREVIOUS MONTH

THIS MONTH

Page 11

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

9. MSE Walls Progress Schedule


MSE WALLS SCHEDULE (FOUNDATION AT APPROACH 1)
LOCATION (LHS)
Elevation

FROM

TO

22+702.653

22+825

DATE
-

13-Jul-14
14-Jul-14
El. 20.40
6-Jul-14
22+840
22+880
13-Jul-14
22+880 22+908.387 10-Aug-14
11-Aug-14
22+908.387 22+969.478 3-Jul-14
El. 21.20
5-Jul-14
4-Aug-14
22+969.478 23+000
5-Aug-14
20-Jul-14
23+000
23+025
21-Jul-14
17-Jul-14
23+025
23+070
El. 22.00
18-Jul-14
30-Jun-14
23+070
23+140
1-Jul-14
23+140 23+164.573 16-Jun-14
17-Jun-14

22+825

El. 22.80

22+840

23+164.573 23+237.536 23-Jun-14


24-Jun-14

El. 22.00

Elevation

FOUNDATION
/BLINDING

23+237.536 23+270.762 17-Jun-14

El. 20.40

El. 21.20

El. 22.00

El. 22.80

El. 22.00

LOCATION (RHS)
FROM

TO

22+718.936

22+810

22+810

22+893.032

22+893.032 22+976.294
22+976.294

23+040

23+040

23+088.046

23+088.046

23+130

23+130

23+191.774

23+191.774 23+270.800

LOCATION (AB 1)
Elevation
El. 22.00

FROM

TO

23+270.7 (L) 23+270.8 (R )

DATE
FOUNDATION
/BLINDING

17-Sep-14
18-Sep-14
9-Aug-14
10-Aug-14
13-Aug-14
14-Aug-14
18-Aug-14
19-Aug-14
26-Jul-14
27-Jul-14
21-Jul-14
22-Jul-14
7-Jul-14
10-Jul-14
26-Jun-14
27-Jun-14

DATE
FOUNDATION
/BLINDING

26-Jun-14
27-Jun-14

18-Jun-14

MSE WALL MONTHLY SCHEDULE (FOUNDATION @ APPROACH 2)


LOCATION (LHS)
Elevation

El. 23.30

FROM

TO

23+508.239

23+520

23+520
23+580.877

El. 24.10

Elevation
El. 23.30

FROM

TO

23+508.2 (L) 23+508.1 (R )

DATE
FOUNDATION
/BLINDING

15-Sep-14
16-Sep-14

23+580.877 20-Aug-14
23+650

23+650

23+750

23+730

23+827.635

21-Aug-14
26-Aug-14
27-Aug-14
1-Sep-14
2-Sep-14

El. 24.90

LOCATION (AB 2)

DATE
FOUNDATIO
N /BLINDING

23+827.635 23+949.895

PREVIOUS

RENARDET S.A. & PARTNERS

P R E V IO US
M ON T H

LOCATION (RHS)
Elevation
El. 23.30
El. 24.10

DATE
FOUNDATION
/BLINDING

FROM

TO

23+508.1

23+607.6

8-Sep-14
9-Sep-14

23+607.6

23+950.1

THIS MONTH

Page 12

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

MSE WALL MONTHLY SCHEDULE (PANELS FIXING AT APPROACH 1)


LHS (AB 1), from Sta. 22+702.653 to Sta. 23+270.762

ELEV.

22+825

34.800
34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

ELEV.

22+810

34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400

22+840

22+880

23+164.573

23+237.536

23+270.762

20-Sep-14
9-Sep-14
4-Sep-14
16-Sep-14 26-Aug-14
4-Sep-14 18-Aug-14
21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14
22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14
3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14
28-Aug-14 28-Aug-14 28-Aug-14
-

22+908.387

22+969.478

22+991

23+084

18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
-

18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-

RHS (AB 1), from Sta. 22+718.936 to Sta. 23+270.800


22+893.032

22+976.294

23+035

23+088.046

23+191.774

AB 1 Face
23+270.800

18-Sep-14
13-Sep-14 13-Sep-14
2-Sep-14 31-Aug-14
24-Aug-14 18-Aug-14
20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14
8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14
18-Sep-14 21-Aug-14 18-Aug-14
13-Jul-14
23-Sep-14 26-Aug-14
4-Sep-14
PREVIOUS

RENARDET S.A. & PARTNERS

P R E V IO US
M ON T H

23+270.7 (L) 23+270.8(R )

19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-

19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-

THIS MONTH

Page 13

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

10. Box Culverts Progress Schedule


NO.

STATION

TYPE & DIMENSION

1
LHS
RHS
2

21+260
Block 1
Block 2
21+485
Block 1a
Block 1b
Block 2a
Block 2b
21+838
Block 1a
Block 1b
Block 2
Block 3
Block 4a
Block 4b
Block 5
Block 6
21+972.4
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
Block 13
Block 14
Block 15
Block 16
Block 17
Block 18
Block 19
Block 20
Block 21
Block 22
21+972.4
Block 23
Block 24
Block 25
Block 26
Block 27
Block 28
Block 29
Block 30
Block 31
Block 32
Block 33
22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12

3 cells - 2.0 x 1.5


3 cells - 2.0 x 1.5
3 cells - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
2 x 4 cells (8) - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5
1 x 4 cells - 2.0 x 1.5

LHS
RHS
3
LHS
RHS
LHS
RHS
4

LHS

RHS

RHS

5
LHS
RHS
LHS
RHS
LHS
RHS

LENGTH SKEW (
F/P &
(m)
BLINDING
)

2 x 4 cells (8) - 2.0 x 2.0

43.039
19.526
23.493
49.750
3.000
17.290
7.710
21.730
57.210
5.000
17.600
22.600
11.970
5.000
17.600
22.600
11.970
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038
21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015
57.629
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
45 R

1 cell - 2.0 x 2.0


1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0

9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960

45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R

11 x 4 cells (44) - 3.0 x 2.0

1 x 4 cells - 3.0 x 2.0


1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
11 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0

RENARDET S.A. & PARTNERS

1-Jul-14
1-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14
10-Aug-14
27-Jul-14
27-Jul-14
24-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14
30-Jun-14
24-Jun-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
-

BASE SLAB
Rebars

Concrete

WALL
Rebars

TOP SLAB
Concrete

Rebars

Concrete

31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14


31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14 31-Aug-14
20-Aug-14 20-Aug-14
5-Jun-14
9-Jul-14
25-May-14
12-Jul-14
29-May-14
31-Jul-14
10-Jun-14
9-Aug-14
15-Jun-14
17-Aug-14
19-Jun-14
25-Aug-14
22-Sep-14
23-Aug-14
27-Jul-14
14-Sep-14
29-Sep-14
1-Sep-14
25-Jun-14
6-Aug-14
21-Jul-14
27-Jul-14
28-Aug-14
20-Aug-14
3-Aug-14
-

5-Jun-14
10-Jul-14
25-May-14
13-Jul-14
29-May-14
31-Jul-14
10-Jun-14
10-Aug-14
15-Jun-14
18-Aug-14
19-Jun-14
26-Aug-14
22-Sep-14
23-Aug-14
27-Jul-14
15-Sep-14
30-Sep-14
2-Sep-14
25-Jun-14
7-Aug-14
21-Jul-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
-

24-Jun-14
3-Aug-14
3-Jun-14
5-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
25-Aug-14
7-Jul-14
14-Sep-14
20-Jul-14
2-Sep-14
29-Sep-14
8-Sep-14
14-Aug-14
23-Sep-14
22-Sep-14
30-Jul-14
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
-

24-Jun-14
4-Aug-14
3-Jun-14
6-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
26-Aug-14
8-Jul-14
14-Sep-14
20-Jul-14
3-Sep-14
29-Sep-14
8-Sep-14
14-Aug-14
24-Sep-14
22-Sep-14
30-Jul-14
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
-

15-Jul-14
13-Aug-14
23-Jun-14
18-Aug-14
2-Jul-14
27-Aug-14
23-Jul-14
9-Sep-14
4-Aug-14
24-Sep-14
2-Sep-14
18-Sep-14
3-Sep-14
30-Sep-14
16-Sep-14
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
-

Bituminous Paint
(2 Coats)

1-Sep-14
1-Sep-14
-

16-Jul-14 16-Aug-14
13-Aug-14 8-Sep-14
23-Jun-14 8-Sep-14
19-Aug-14
2-Jul-14
28-Aug-14
24-Jul-14
10-Sep-14
5-Aug-14
25-Sep-14
3-Sep-14 25-Sep-14
19-Sep-14
4-Sep-14
30-Sep-14
17-Sep-14 25-Sep-14
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
-

Page 14

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

NO.

STATION

TYPE & DIMENSION

22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
23+492
(5 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b

2 x 4 cells (8) - 2.0 x 2.0

LHS
RHS
LHS
RHS
LHS
RHS
6
LHS
RHS
LHS
RHS
7
LHS
RHS
8
LHS

RHS
9
LHS
RHS
10
LHS
RHS

1 cell - 2.0 x 2.0


1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 x 4 cells - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 cell - 2.0 x 2.0
1 x 4 cells (4) - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 x 4 cells - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 3.0 x 2.0
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5
1 cell - 2.0 x 1.5

LENGTH SKEW (
F/P &
(m)
BLINDING
)

95.482 45 R

30-Jun-14
24-Jun-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
24-Jun-14
24-Jun-14
9/172014
24-Jun-14
24-Jun-14
9/172014
12-Jul-14
12-Jul-14
11-Aug-14
8-Jul-14
8-Jul-14
10-Aug-14
10-Aug-14

BASE SLAB

WALL

TOP SLAB

Rebars

Concrete

Rebars

Concrete

6-Aug-14
21-Jul-14
27-Jul-14
28-Aug-14
20-Aug-14
3-Aug-14
9-Jul-14
14-Jul-14
23-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

7-Aug-14
21-Jul-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
9-Jul-14
15-Jul-14
24-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
30-Jul-14
3-Aug-14
28-Sep-14
-

2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
30-Jul-14
3-Aug-14
28-Sep-14
-

Rebars

1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
16-Aug-14
21-Aug-14
9 & 20/8/2014 9 & 23/8/2014 28-Aug-14
11 & 25/8/2014 11 & 26/8/2014 31-Aug-14
23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14
26-Aug-14 26-Aug-14 26-Aug-14
23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14
26-Aug-14 26-Aug-14 26-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14

Concrete

Bituminous Paint
(2 Coats)

2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
17-Aug-14
21-Aug-14
28-Aug-14
1-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14

6-Sep-14
6-Sep-14
4-7/9/2014
4-7/9/2014
24-Jul-14
24-Jul-14
28-Aug-14
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14

9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960
79.065

45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
15 R

6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525
67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587

15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
0
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14
0
0
0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
0
-

Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.
PREVIOUS

RENARDET S.A. & PARTNERS

PREVIOUS MONTH

THIS MONTH

Page 15

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

11. Progress Status of Utility Crossing Ducts


S.NO.

4A

DRAWING No.

STAGES

LEFT STAGE
CCC/FQI/IR/06 SERVICE
MIDDLE STAGE
ROAD-3
RIGHT STAGE
LEFT STAGE
CCC/FQR/IR/11 SOL-2 MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
CCC/FQR/IR/10 SOL-3 MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
CCC/FQR/WA/05 SR-1 MIDDLE STAGE
RIGHT STAGE
RHS OF SOL-01
CCC/FQI/SL/01

CCC/FQI/IR/01

CCC/FQI/EL/02

CCC/FQI/IR/02

CCC/FQI/EL/03

10

CCC/FQI/EL/04

11

CCC/FQI/EL/05

12

CCC/FQI/IR/03

13

CCC/FQI/IR/04
JUNCTION CROSSING

14

CCC/FQI/IR/05
JUNCTION CROSSING

15

CCC/FQI/EL/06

16

CCC/FQI/WA/02
JUNCTION

17

CCC/FQI/WA/01

18

CCC/FQI/EL/07

19

CCC/FQI/EL/13

20

CCC/FQI/EL/08

NO. OF SETOUT/EXCV INSTALLATIO


BACKFILLIN
CONCRETE
/BED PREP
WAYS
N
G

DIA

TYPE

0+030

200

UPVC

0+150

300

UPVC

0+300

200

UPVC

0+600

300

UPVC

21+160

150

UPVC

150

UPVC

300

LEFT STAGE
MIDDLE STAGE 21+360
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+460
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+660
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+780
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+880
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+260
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+510
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+520
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE22+520 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE22+587 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+760
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE23+008 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+020
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+060
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+210
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+240
RIGHT STAGE

RENARDET S.A. & PARTNERS

PIPE

CHAINAGE

9/24/2014

9/24/2014

5/15/2014
6/11/2014

5/15/2014
6/11/2014

5/18/2014
6/12/2014

6/12/2014
7/10/2014

UPVC

5/19/2014
6/14/2014

5/19/2014
14/06/014

5/20/2014
6/14/2014

6/4/2014
6/21/2014

UPVC

5/19/2014
6/15/2014

5/19/2014
6/15/2014

5/20/2014
6/15/2014

5/31/2014

150

300

UPVC

5/20/2014
6/15/2014

5/20/2014
6/15/2014

5/25/2014
6/15/2014

6/4/2014
7/8/2014

150

UPVC

5/25/2014
6/16/2014

5/25/2014
6/16/2014

5/25/2014
6/17/2014

6/4/2014
7/10/2014

150

UPVC

6/17/2014
7/20/2014

6/17/2014
7/20/2014

6/18/2014
7/21/2014

7/9/2014
7/27/2014

150

UPVC

6/19/2014
7/20/2014

6/19/2014
7/20/2014

6/19/2014
7/21/2014

7/6/2014
7/17/2014

200

UPVC

6/19/2014
7/20/2014

6/19/2014
7/20/2014

6/19/2014
7/21/2014

7/5/2014
7/17/2014

200

UPVC

200

UPVC

150

UPVC

5/26/2014
6/11/2014

5/26/2014
6/11/2014

5/26/2014
6/11/2014

6/8/2014
7/22/2014

300

UPVC

900

RC

6/16/2014
7/8/2014

6/16/2014
7/8/2014

6/16/2014
7/9/2014

7/20/2014
7/27/2014

150

UPVC

5/25/2014
11/06/201

5/25/2014
6/11/2014

5/26/2014
6/11/2014

6/14/2014
6/23/2014

5/27/2014

5/27/2014

5/27/2014

6/17/2014

150

UPVC

4
5/28/2014

5/28/2014

5/28/2014

6/17/2014

150

UPVC

Page 16

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

S.NO.

DRAWING No.

20

CCC/FQI/EL/08

21

CCC/FQI/EL/09

22

CCC/FQI/EL/10

23

CCC/FQI/WA/03

23A

24

CCC/FQI/EL/11

25

CCC/FQI/WA/04

26

CCC/FQI/IR/07

27

CCC/FQI/EL/12

28

CCC/FQI/EL/14

29

CCC/FQI/IR/08

30

CCC/FQI/EL/15

31

CCC/FQI/EL/16

32

CCC/FQI/IR/09

33

CCC/FQI/EL/17

34

CCC/FQI/NAW.2

35

CCC/FQI/NAW.3

36

CCC/FQI/NAW.4

37

CCC/FQI/OMANTEL.1

38

CCC/FQI/OMANTEL.2

39

CCC/FQI/SL/03

40

CCC/FQI/SL/04

STAGES

LEFT STAGE
MIDDLE STAGE 23+240
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+560
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+900
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+960
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+980
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+000
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+020
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+120
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+220
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+340
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+520
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+960
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 25+160
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+870
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+580
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+720
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+810
RIGHT STAGE
LEFT STAGE
0+140 SOL-3
MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+990
RIGHT STAGE

RENARDET S.A. & PARTNERS

PIPE

CHAINAGE

NO. OF SETOUT/EXCV INSTALLATIO


BACKFILLIN
CONCRETE
/BED PREP
WAYS
N
G

DIA

TYPE

150

UPVC

150

UPVC

150

600

5/28/2014

5/28/2014

5/28/2014

6/17/2014

5/29/2014
7/30/2014

5/29/2014
8/12/2014

5/29/2014
8/26/2014

6/17/2014
8/26/2014

UPVC

5/29/2014
7/14/2014

6/2/2014
7/14/2014

6/2/2014
7/14/2014

6/17/2014
8/20/2014

RC

5/29/2014
7/14/2014

6/2/2014
7/14/2014

6/2/2014
7/15/2014

6/17/2014
8/20/2014

UPVC

8/10/2014

8/11/2014

8/11/2014

8/26/2014

150

UPVC

5/29/2014
8/6/2014

6/2/2014
8/6/2014

6/3/2014
8/9/2014

6/19/2014
8/13/2014

600

RC

300

UPVC

6/3/2014
8/11/2014

6/4/2014
8/11/2014

6/4/2014
8/19/2014

6/23/2014
8/26/2014

150

UPVC

6/4/2014
7/23/2014

6/5/2014
7/24/2014

6/10/2014
8/19/2014

23/06/201
8/26/2014

150

UPVC

6/9/2014
8/6/2014

6/9/2014
8/6/2014

6/10/2014
8/6/2014

6/23/2014
8/26/2014

7/5/2014

7/5/2014

7/5/2014

7/13/2014

300

UPVC

2
7/16/2014

7/16/2014

7/17/2014

7/27/2014

150

UPVC

3
9/14/2014

9/14/2014

150

UPVC

3
9/16/2014

9/20/2014

300

UPVC

150

UPVC

100

UPVC

5/21/2014
6/16/2014

5/21/2014
6/16/2014

5/21/2014
6/18/2014

6/4/2014
7/10/2014

100

UPVC

5/29/2014
7/10/2014

5/31/2014
7/10/2014

5/31/2014
8/13/2014

6/17/2014
8/26/2014

100

UPVC

100

UPVC

8/6/2014
8/8/2014
9/16/2014
7/7/2014
8/12/2014

8/6/2014
8/9/2014
9/16/2014
7/8/2014
8/13/2014

8/5/2014
8/9/2014
9/16/2014
7/8/2014
8/14/2014

100

UPVC

150

UPVC

7/9/2014
8/12/2014

7/9/2014
8/13/2014

8/14/2014

150

UPVC

7/2/2014
7/10/2014
7/22/2014

7/3/2014
7/10/2014
7/22/2014

7/3/2014
7/14/2014
7/23/2014

9/22/2014

8/15/2014

8/20/2014

Page 17

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

S.NO.

DRAWING No.

STAGES

PIPE

CHAINAGE

NO. OF SETOUT/EXCV INSTALLATIO


BACKFILLIN
CONCRETE
/BED PREP
WAYS
N
G

DIA

TYPE

CCC/FQI/SL/02

BOTTOM
TOP

22+080

150

UPVC

42

CCC/FQI/EL/19

BOTTOM
TOP

23+740

150

UPVC

42

CCC/FQI/SL/05

BOTTOM
TOP

24+850

150

UPVC

43

CCC/FQI/SD/07

21+500

450

44

CCC/FQI/SD/08

21+560

450

45

CCC/FQI/SD/09

21+620

450

BOTTOM
TOP

CONC PIPE

41

8/30/2014

8/31/2014

9/14/2014

9/15/2014

9/15/2014

9/16/2014

9/17/2014

10/2/2014

10/2/2014

10/2/2014

10/2/2014

10/2/2014

10/2/2014

Settingout

excav/lay

concrete

19/16/2014

9/17/2014

9/30/2014

9/30/2014

9/30/2014

Buraimi Road (SOL-3)


1

CCC/FQI/Omantel/02

BOTTOM
TOP

CCC/FQI/SL/13

BOTTOM
TOP

0+130

150

UPVC

CCC/FQI/SL/14

BOTTOM
TOP

0+415

151

UPVC

CCC/FQI/SL/15

BOTTOM
TOP

0+054.459

152

UPVC

CCC/FQI/SL/16

BOTTOM
TOP

153

UPVC

CCC/FQI/SL/17

BOTTOM
TOP

154

UPVC

RENARDET S.A. & PARTNERS

0+138.348

110

UPVC

Existing
Road front
SOL-3 Ch.
Existing
Road front
SOL-3 Ch.

backfill

Page 18

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

12. Project Strip Chart


SUBGRADE IN CUT

21+150-21+500

COMPLETED

As of September 30 2014

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Subgra de
La yr 9
La yr 8
La yr 7
La yr 6
La yr 5
La yr 4
La yr 3
La yr 2

21+360

21+380

21+400

21+420

21+440

21+460

21+860

21+880

21+900

21+920

21+940

21+960

21+500

21+340
21+840

22+000

21+320
21+820

21+480

21+300
21+800

21+980

21+280
21+780

21+260

21+240

21+220

21+200

21+180

21+160

21+140

21+120

21+100

21+080

21+060

21+040

21+020

21+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
Subgra de

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

21+500-22+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
s ub gra de
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

21+760

21+740

21+720

21+700

21+680

21+660

21+640

21+620

21+600

21+580

21+560

21+540

21+520

21+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
s ub gra de

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 19

Monthly Progress Report September 2014

22+500

22+480

22+460

22+440

22+420

22+400

22+380

22+360

22+320

22+300

22+280

As of September 30 2014

22+260

22+240

22+220

22+200

22+180

22+160

22+120

22+100

22+080

22+060

22+040

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

22+020

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

22+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

22+140

22+000-22+500

COMPLETED

22+340

Project: Upgrading of Falaj Al Qabail Roundabout

RHS

RENARDET S.A. & PARTNERS

23+000

22+960

22+940

22+920

22+900

22+880

22+860

22+840

22+820

22+800

22+780

22+760

22+740

22+720

22+700

22+680

22+660

22+640

22+620

22+600

22+580

22+560

22+540

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

22+980

rock 1
layer 15
rock soil layer no 2
rock soil layer no 1

22+520

22+500

22+500-23+000

rock soil layer no 1


rock soil layer no 2
layer 15
rock 1

Page 20

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

As of September 30 2014

23+380

23+400

23+420

23+440

23+880

23+900

23+920

23+940

23+500

23+360
23+860

24+000

23+340
23+840

23+480

23+320
23+820

23+980

23+300
23+800

23+460

23+280
23+780

23+960

23+260
23+760

23+240

23+220

23+200

23+180

23+160

23+140

23+120

23+100

rock siol layer no 1


layer no 28

23+080

23+060

23+040

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

23+020

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

23+000

LHS
RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 15
layer 7
Rock siol no 1
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

LHS

23+000-23+500

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
rock soil layer 1
Layr 8
layer 15
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

COMPLETED

layer no 28
rock siol layer no 1

RENARDET S.A. & PARTNERS

23+740

23+720

23+700

23+680

23+660

23+640

23+620

23+600

23+580

23+560

23+540

23+520

23+500

23+500-24+000

Page 21

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout


24+000-24+500

COMPLETED

As of September 30 2014

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

24+360

24+380

24+400

24+420

24+440

24+860

24+880

24+900

24+920

24+940

24+500

24+340
24+840

25+000

24+320
24+820

24+480

24+300
24+800

24+980

24+280
24+780

24+460

24+260
24+760

24+960

24+240
24+740

24+220

24+200

24+180

24+160

24+140

24+120

24+100

24+080

24+060

24+040

24+020

24+000

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
24+500-25+000

LHS

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2

24+720

24+700

24+680

24+660

24+640

24+620

24+600

24+580

24+560

24+540

24+520

24+500

EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY

RHS

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10

GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 22

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

COMPLETED

25+000-25+500

As of September 30 2014

BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm

LHS

Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION

25+500

25+480

25+460

25+440

25+420

25+400

25+380

25+360

25+340

25+320

25+300

25+280

25+260

25+240

25+220

25+200

25+180

25+160

25+140

25+120

25+100

25+080

25+060

25+040

25+020

25+000

OGL SURVEY

OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5

RHS

layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm

RENARDET S.A. & PARTNERS

Page 23

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

13. Financial Status of Payments


Sl. No.

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17

DESCRIPTION

PAYMENT
APPLICATION No. 1
(ADVANCE)
PAYMENT
APPLICATION No. 2
PAYMENT
APPLICATION No. 3
PAYMENT
APPLICATION No. 4
PAYMENT
APPLICATION No. 5
PAYMENT
APPLICATION No. 6
PAYMENT
APPLICATION No. 7
PAYMENT
APPLICATION No. 8
PAYMENT
APPLICATION No. 9
PAYMENT
APPLICATION No. 10
PAYMENT
APPLICATION No. 11
PAYMENT
APPLICATION No. 12
PAYMENT
APPLICATION No. 13
PAYMENT
APPLICATION No. 14
PAYMENT
APPLICATION No. 15
PAYMENT
APPLICATION No. 16
PAYMENT
APPLICATION No. 17

PAYMENT FOR
THE MONTH OF

GROSS
AMOUNT
(R.O.)

GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)

DATE
SUBMITTED

AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)

AMOUNT
RECEIVED
(R.O.)

DATE
PAYMENT
RECEIVED

Dec-13

1,648,225

1,648,225

1,648,225

23-Nov-13

1,648,225

29-Jan-14

1,648,225

6-Feb-14

Jan-14

2,291,277

643,052

514,442

12-Feb-14

514,442

02-Apr-14

513,608

10-Apr-14

Feb&Mar-14

2,808,644

517,367

504,147

06-Apr-14

434,917

03-May-14

414,674

6-Aug-14

Apr-14

3,315,692

507,048

417,900

08-May-14

407,538

05-Jun-14

395,257

6-Aug-14

May-14

4,109,460

793,768

650,802

05-Jun-14

445,708

04-Jul-14

374,172

6-Aug-14

Jun-14

4,293,764

184,304

382,116

15-Jul-14

382,116

16-Jul-14

418,721

9-Sep-14

Jul&Aug-14

5,749,546

1,455,782

1,164,626

14-Sep-14

1,123,023

18-Sep-14

5,749,546

5,749,546

5,282,258

Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15

TOTAL AMOUNT (R.O.)

RENARDET S.A. & PARTNERS

4,955,969

3,764,656

Page 24

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

14. Details of Equipment Available At Site


Sl.
No.
1

DESCRIPTION

CCC

HIRED

TOTAL
AVAILABLE
AT SITE

COMPRESSOR

AIR COMPRESSOR

MILLER WELDING MECHINE

GENERATOR

CRANES

CRANES 30 TON / 25 TON / 70 TON


VEHICLES H.D.

4
-

DIESEL TANKER

FLAT TRAILER

10

HIAB TRUCK

11

P/MOVER + TIPPING TRAILER

12

TIPPER TRUCKS

13

14

13

WATER TANKER 5000 GAL

14

EARTH MOVING PLANT

15

BOBCAT

16

EXCAVATOR

17

JCB 4CX / 3CX

18

SHOVEL / WHEEL LOADER

19

DOZER D9N/D8R

20

TELEHANDLER

21

CIVIL ENGINEERING EQUIPMENT

22

GREENE STABILIZER PLANT

23

DYNAPAC S/ROLLER

24

E/WORK ROLLER

25

MOTOR GRADER

26

TITAN PAVER MACHINE

27

TYRE / PTR ROLLER

28

PAVER MACHINE

29

1
-

L. D. VEHICLES & TRUCKS

30

DYNA TRUCK

31

MAINTENANCE TRUCKS

32

ASHOK LEYLAND BUS 55 SEAT

33

TOYOTA COASTER BUS 24 S

34

TOYOTA COROLLA/CIVIC/YARIS

35

TOYOTA PICKUP/ISUZU

36
37
38

12

12

13

NISSAN PATHFINDER/X-TRAIL

TOYOTA LAND CRUISER/FORTUNER

55

109

Total

RENARDET S.A. & PARTNERS

54

Page 25

20

40

60

33

Jan-14

No. of EQUIPMENT

80

55

Feb-14

100

68

Apr-14

120

66

Mar-14

115
55
88

202
66
154

77
May-14

297
68
222

390
77
299

68

86
Jun-14

47
33
33

87

88
Jul-14

110
87
545
88
473

95

100
Aug-14

108
95
640
100
573

93

109
Sep-14

107
68
458
86
385

107

102
93
733
109
682

Oct-14

108

107
93

95

87

68

47

93

110

110

100

102

PROJECT MONTHS

100
98

82
79
77
102
100
98
1,160 1,260 1,358

Sep-15

53
1,802

Aug-15

66
1,749

Jul-15

77
1,683

87

41
1,843

Oct-15

82

79

77
66

53

REVISED PLANNED TOTAL PER MONTH

ACTUAL TOTAL PER MONTH

PLANNED TOTAL PER MONTH

53
82
1,527

41
79
1,606

66
87
1,445

Apr-15 May-15 Jun-15

2015
Jan-15 Feb-15 Mar-15

102

87
108
1,058

108

98
110
950

100
107
840

98

95

Nov-14

87

Dec-14

68

82

47

Jan-15

PLANNED TOTAL PER MONTH


REVISED PLANNED TOTAL PER MONTH
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH
ACTUAL CUMULATIVE

87

Dec-14

79

Nov-14

Feb-15

Oct-14

77

Aug-14 Sep-14

Mar-15

Jul-14

66

2014

Apr-15

Jun-14

53

May-14

May-15

Apr-14

41

Mar-14

Jun-15

Feb-14

Jul-15

Jan-14

Aug-15

EQUIPMENT HISTOGRAM

Sep-15

RENARDET S.A. & PARTNERS

Total

682

1500

41

Oct-15

Project: Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report September 2014

Page 26

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

15. Details of Manpower Available At Site


CATEGORY

EXPATRIATES

NATIONALS

TOTAL

A - MANAGEMENT ***

B - COMMERCIAL STAFF *

C - ENGINEERS

D - FOREMAN & C/H

20

22

E - ENGINEERING TECHNICIANS **

23

29

1 - SKILLED CRAFTSMEN

142

69

211

2 - SEMI-SKILLED/UNSKILLED

507

55

562

TOTAL AS OF END OF THE MONTH

710

133

843

10

F - DAILY RATED EMPLOYEES :

G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor
on Company Work :
25
*

Includes all Administrative office functions, personnel, services, camps,


insurance, accounts, EDP, stores and purchase staff

** Includes draftsmen, lab technicians, surveyors, inspectors and Q.S staff


*** Band 11 and above.

RENARDET S.A. & PARTNERS

Page 27

100

200

300

400

391

Jan-14

500

596

Feb-14

No. of Men

600

425

222

340

340

18

322

11

731

391

26

365

68

848
2,202

748
3,362

638
1,353
603
54
657
2,614

425
715
581
49
630
1,957

1,327

596

46

550

291

851

57

691

4,135

773

64

709

3,052

627

851

63

59

565

4,960

825

69

756

3,910

840

858

84

59

756

5,762

802

68

734

4,764

838

854

84

6,605

843

70

773
0

7,365

741

442

74

61

667

Dec-14
381

7,691

616

326

61

57

554

Jan-15
269

7,988

573

297

57

51

516

Feb-15
246

PROJECT MONTHS

306
9,033

330

340

351
8,693

429

31

33

8,342

354

43

35

276

44

297

387
47

May-15
305

Apr-15
307

2015
Mar-15
307

REVISED - PLANNED - ( DIRECT + INDIRECT )

725
6,923

778
6,383

541

833

764

72

61

652

5,618

854

78

63

61
83

700

750

60

754

ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )

858
825
Jul-14

222

854

57

57

802
Aug-14

PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )

630

Mar-14

700

11

52

854
843
Sep-14

11

638
657

Apr-14

800

340

Dec-13

50

764

Nov-14
480

0
Oct-14

900

57

36

541
0
Nov-14

23

848

Oct-14
701

442
0
Dec-14

748
May-14

Sep-14
793

326

0
Jan-15

PLANNED TOTAL PER MONTH - ( DIRECT )


REVISED - PLANNED TOTAL PER MONTH - ( DIRECT )
PLANNED TOTAL PER MONTH - ( INDIRECT )
REVISED - PLANNED TOTAL PER MONTH-(INDIRECT)
PLANNED TOTAL PER MONTH - ( DIRECT + INDIRECT )
REVISED - PLANNED - ( DIRECT + INDIRECT )
PLANNED CUMULATIVE
ACTUAL TOTAL PER MONTH - ( DIRECT )
ACTUAL TOTAL PER MONTH - ( INDIRECT )
ACTUAL TOTAL PER MONTH - ( DIRECT + INDIRECT )
ACTUAL CUMULATIVE

773
Jun-14

Aug-14
794

297

Jul-14
799

9,212

406

179

40

30

365

Jun-15
149

301

30

271

Jul-15

6
57

10
102

15
150

6605

521

6084

9,212

8651

9215

862

914

7788

51

Total
8301

Oct-15

92

Sep-15

135

Aug-15

Aug-15

2014

Feb-15 0

Jun-14
792

354

May-14
791

0
Mar-15

Apr-14
586

351
0
Apr-15

Mar-14
375

340

0
May-15

Feb-14
186

Jul-15

Jan-14
34

Sep-15

2013

Oct-15

Dec-13
6

179
0

RENARDET S.A. & PARTNERS


Jun-15

Project: Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report September 2014

Page 28

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

16. QA/QC Reports

RENARDET S.A. & PARTNERS

Page 29

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 30

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 31

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 32

Project: Upgrading of Falaj Al Qabail Roundabout

RENARDET S.A. & PARTNERS

Monthly Progress Report September 2014

Page 33

RENARDET S.A. & PARTNERS

MAS/CCC/FQI/HDPE/005

MAS/CCC/FQI/PW/006

MAS/CCC/FQI/MC/007

MAS/CCC/FQI/RS/008

MAS/CCC/FQI/PT/009-1

MAS/CCC/FQI/PT/009-2

MAS/CCC/FQI/PT/009-3

MAS/CCC/FQI/PB/010A-Rev.1

MAS/CCC/FQI/PB/010B

MAS/CCC/FQI/HDPE/011

MAS/CCC/FQI/RCBC/012

MAS/CCC/FQI/BP/013

MAS/CCC/FQI/BP/013A

MAS/CCC/FQI/EJ/014A-Rev.1

MAS/CCC/FQI/RC/015

MAS/CCC/FQI/WS/016 B

MAS/CCC/FQI/TW/017

MAS/CCC/FQI/EW/019

MAS/CCC/FQI/EC/020

MAS/CCC/FQI/PS/021

MAS/CCC/FQI/PS/021A

MAS/CCC/FQI/LL/022

MAS/CCC/FQI/LP/023A

MAS/CCC/FQI/FP/024

MAS/CCC/FQI/JS/025

MAS/CCC/FQI/GT/026

MAS/CCC/FQI/GT/026A

CCC/FQI/REN/MAS/005

CCC/FQI/REN/MAS/006

CCC/FQI/REN/MAS/007

CCC/FQI/REN/MAS/008

CCC/FQI/REN/MAS/009-1

CCC/FQI/REN/MAS/009-2

CCC/FQI/REN/MAS/009-3

CCC/FQI/REN/MAS/010A-Rev.1

CCC/FQI/REN/MAS/010B

CCC/FQI/REN/MAS/011

CCC/FQI/REN/MAS/012

CCC/FQI/REN/MAS/013

CCC/FQI/REN/MAS/013A

CCC/FQI/REN/MAS/014A-Rev.1

CCC/FQI/REN/MAS/015

CCC/FQI/REN/MAS/016 B

CCC/FQI/REN/MAS/017

CCC/FQI/REN/MAS/019

CCC/FQI/REN/MAS/020

CCC/FQI/REN/MAS/021

CCC/FQI/REN/MAS/021A

CCC/FQI/REN/MAS/022

CCC/FQI/REN/MAS/023A

CCC/FQI/REN/MAS/024

CCC/FQI/REN/MAS/025

CCC/FQI/REN/MAS/026

CCC/FQI/REN/MAS/026A

MAS/CCC/FQI/GG/028

MAS/CCC/FQI/PVC/004

CCC/FQI/REN/MAS/004

CCC/FQI/REN/MAS/028

MAS/CCC/FQI/MSE/003

CCC/FQI/REN/MAS/003

MAS/CCC/FQI/MS/027

MAS/CCC/FQI/GTI/002

CCC/FQI/REN/MAS/027

MAS/CCC/FQI/BBC/001

CCC/FQI/REN/MAS/002

MAR No.

CCC/FQI/REN/MAS/001

Re fe re nce No.

RBA Ferro Industries PVT. Ltd.

OBasf The Chemical Company

Masterseal 915
(formerly known as Masterflow 410 Plus)

Modern East Trading & Con.

Al Inma Building Materilal LLC

17/08/2014

10/08/2014

15/06/2014

21/05/2014

27/03/2014

27/03/2014

22/05/2014
Stars Light LLC

27/03/2014

16/09/2014

22/03/2014

19/03/2014

22/03/2014

12/03/2014

25/03/2014

02/03/2014

07/05/2014

17/06/2014

02/03/2014

22/02/2014

22/02/2014

11/05/2014

07/05/2014

22/02/2014

22/02/2014

22/02/2014

02/02/2014

30/01/2014

26/01/2014

26/12/2013

26/12/2013

26/12/2013

26/12/2013

22/12/2013

Al Babtain Power &


Telecomunication Co., S.Arabia

Bonar Technical Fabrics

Gully Gratings & Frames

Date
Submitte d

Majees Lighting Industries LLC

Voltamp Energy SAOG

United Engineering Projects

United Engineering Projects

United Engineering Projects

National Telephone Services

Sika LLC Oman

Amiantit Oman

Al Ammar International

Henkel Polybit Industries Ltd.

Al Inma Building Materilal LLC

Amiantit Oman

Amiantit Oman

Building Supplies & Services

Al Ammar International

Freyssinet Arabian Sea LLC

Freyssinet Arabian Sea LLC

Freyssinet Arabian Sea LLC

Muscat Steel Industries

Emirates Lube Oil Co. (Muscat)

APCC LLC

Amiantit Oman

Amiantit Oman

Freyssinet Arabian Sea LLC

Swissboring & Company LLC

Tarmac Zawawi LLC Oman

Manufacture r/Supplie r/
Subcontractor

Geotextile (Bonar NW16)

Geotextile

Joint Sealant (Polyseal)

Street Lighting Feeder Pillar

Street Lighting Poles (Mid-Hinged)

Street Lighting Luminaries

Package Substation

Package Substation

MV & LV Cables

Electrical Works

Telephone Works

Water Stop G EE-25

Reinforced Concrete Pipe (450,600,700mm dia)

Bridge Expansion Joints

Bituminous Paint Material (Rubberized)

Bituminous Paint Material (Rubberized)

Single cell Precast Box Culvert

HDPE Water Pipes

Bridge Pot Bearings

Bridge Pot Bearings

Post Tensioning Work - Strand

Post Tensioning Work - Duct

Post Tensioning Work - Anchorage

Reinforcing Steel

Bitnuminous Prime Coat (MC-70)

Piling Works

HDPE Pipes & Fittings

UPVC Pipes

MSE Wall System

Geotechnical Investigation

Bituminous Base Course

Mate rial/ Work

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

Renardet

25/03/2014

09/03/2014

25/05/2014

---

27/03/2014

27/03/2014

27/03/2014

20/03/2014

09/03/2014

19/02/2014

09/02/2014

09/02/2014

02/02/2014

02/02/2014

01/04/2014

SO/FQI/CCC/083

REN/FQI/CCC/131

SO/FQI/CCC/082

REN/FQI/CCC/099

SO/FQI/CCC/077

REN/FQI/CCC/123

REN/FQI/CCC/146

REN/FQI/CCC/105

SO/FQI/CCC/064

SO/FQI/CCC/038

REN/FQI/CCC/122

REN/FQI/CCC/111

SO/FQI/CCC/091

SO/FQI/CCC/090

SO/FQI/CCC/089

SO/FQI/CCC/063

SO/FQI/CCC/069

SO/FQI/CCC/026

SO/FQI/CCC/020

SO/FQI/CCC/019

SO/FQI/CCC/014

SO/FQI/CCC/015

SO/FQI/CCC/087

14/08/2014
---

Required
latest test
Reports

---

No meet the
HDS
APPROVED

16/04/2014

08/06/2014

14/08/2014

14/08/2014

REN/FQI/CCC/166

REN/FQI/CCC/159

REN/FQI/CCC/119

REN/FQI/CCC/100

REN/FQI/CCC/130

REN/FQI/CCC/157

REN/FQI/CCC/158

CANCELLED

27/03/2014

29/05/2014

17/03/2014

16/04/2014

23/03/2014

20/05/2014

03/07/2014

APPROVED

APPROVED

APPROVED

APPROVED

----

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

Not Approved 20/04/2014

APPROVED

APPROVED

APPROVED

Not Approved

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

APPROVED

MOTC
Submitte Re marks
Via Re narde t
Comme nt
d To
By MOTC
Le tte r Re f. No.
s date d

24/08/2014

17/08/2014

27/05/2014

28/04/2014

16/06/2014

17/08/2014

17/08/2014

----

03/04/2014

16/06/2014

03/04/2014

28/04/2014

02/04/2014

31/05/2014

13/07/2014

05/05/2014

26/03/2014

11/03/2014

31/05/2014

13/05/2014

14/04/2014

14/04/2014

14/04/2014

24/03/2014

27/03/2014

25/02/2014

18/02/2014

18/02/2014

12/02/2014

12/02/2014

07/04/2014

Re narde t
Le tte r
Date d

Project: Upgrading of Falaj Al Qabail Roundabout


Monthly Progress Report September 2014

17. Status of Material Approvals

Page 34

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

18. Engineers Comments


The Planned progress as per the revised Project Execution Program for the month of
September is 9.09% and the Actual progress is 9.38% which shows significant
recovery of lost progress during the previous months. However the actual
cumulative progress up to September is lagging by 0.7% which shall be recovered
in the coming month.
MSE Wall works are commenced on Abutment No. 2 side, which need to be
speeded up to cope up with the requirement of casting of Abutment Cap.
Eid Al Adha holidays may dampen the rate of progress which may be compensated
by increased productivity.
The Backfilling of Future Utility Ducts and Box Culvert works need to be expedited
to open up work fronts for road works.
Superstructure works are in progress in the Bridge and first batch of Pot Bearings
delivered to site.

RENARDET S.A. & PARTNERS

Page 35

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout

19. Details of Correspondence during the month


S.
Date
No. Received

From

Reference
No

Subject

Reply date

Reference
No.

Remarks

9/1/2014

CCC

9/1/2014

CCC

FQIBituminous Paint Batch


REN/FQI/CCC
RENARDET/233 Certificate
9/1/2014 /174
Grade sheet for Main Road SOL2 CH.0+000 TO 0+388.07 LHS.
Approved as
FQI-REN-TR-236 CL&RHS
2/9/23014
Noted

9/2/2014

CCC

FQI-REN-TR082A

9/3/2014

CCC

9/4/2014

CCC

Dimension & co-ordinates


Details of 9 Cell Box Culvert
Bar Bending Schedule for
Underpass at CH.24+360 Block:
FQI-REN-TR-237 1 to 4
Grade Sheet for Main Road
FQI-REN-TR-238 SOL-5 -Rev.1

9/4/2014

CCC

FQIAsphalt Mix Designs - Base and


RENARDET/234 Wearing Courses

9/4/2014

CCC

9/4/2014

CCC

9/4/2014

CCC

10

9/6/2014

CCC

11

9/7/2014

CCC

Additional Items -Future Utility


Ducts
Additional Items -Friction Slab
for Barrier in MSE Wall
Shop Drawing of 2 way # 150
mm upvc Electrical Ducts at
FQI-REN-TR-239 ch.23+740-Rev.A
General Layout Plan at
FQI-REN-TR-240 ch.0+000 to 0+126.732 SR-6
General Layout Plan at
ch.0+000 to 0+261.338 SR-4 &
FQI-REN-TR-241 CH .0+000 to 0+069.593 sr-5

12

9/8/2014

CCC

FQIAsphalt Mix Designs RENARDET/237 Bituminous Base Course

REN/FQI/CCC
9/18/2014 /184

13

9/8/2014

CCC

14

9/8/2014

CCC

FQIRENARDET/238 Monthly Progress Report No.8


FQIWater pipe Relocation Shop
RENARDET/239 Drawing

9/8/2014

15

9/9/2014

CCC

16

9/9/2014

CCC

17

9/9/2014

CCC

18

9/10/2014

CCC

19

9/14/2014

CCC

20

9/14/2014

CCC

21

9/14/2014

CCC

22

9/14/2014

CCC

Approved as
Noted
Approved as
Noted

9/9/2014
9/8/2014
9/7/2014

REN/FQI/CCC
/179

FQIRENARDET/235
FQIRENARDET/236

FQIAdditional works -Relocation


RENARDET/240 of Electrical Utilites
Retaining Wall plan (SOL-3) at
ch.0+130 to 0+310 LHS ( Sheet
FQI-REN-TR-242 1 to 9 )
2 Way # 150mm upVC street
Lighting Ducts @ SOL-03 CH .
FQI-REN-TR-243 0+130
Extension of Exsting pipe
culvert # 1000 mm at ch.0+260FQI-REN-TR-244 SOL-03-Rev.A
SOL-2 ( Batinah Highway )
FQI-REN-TR-245 Cross Section at ch.0+240
SOL-3 ( Batinah Highway )
FQI-REN-TR-246 Cross Section at ch.0+010
Grade sheet for Main Road SOL4CH.0+000 TO 0+992.46 LHS.
FQI-REN-TR-247 CL- Rev.1
Grade sheet for Main Road SOL5CH.0+000 TO 0+979.9 RHS.
FQI-REN-TR-248 CL- Rev.2

RENARDET S.A. & PARTNERS

9/16/2014

Approved as
Noted
Revise &
Resubmit

9/10/2014

Approved as
Noted

9/6/2014

REN/FQI/CCC
/180

9/16/2014

Approved

9/10/2014

Approved

9/29/2014

Approved as
Noted

9/17/2014
9/16/2014

Approved
Approved as
Noted

9/25/2014

Approved

9/25/2014

Approved

Page 36

Monthly Progress Report September 2014

Project: Upgrading of Falaj Al Qabail Roundabout


S.
No.

Date
Received

From

Reference
No

Subject

23

9/14/2014

CCC

24

9/14/2014

CCC

25

9/15/2014

CCC

26

9/15/2014

CCC

27

9/15/2014

CCC

Approved Shop Drawing from


Majan Electricity
Interim Payment Application
No.07
Detour - 1 RHS cross sections
Rev.B
4 Way # 150 mm upVC street
lighting Ducts at SOL-02
FQI-REN-TR-249 CH.0+270
4Way # 110mm upVC Oman
Tel Ducts at Existing service
Road in front of SOL-1
FQI-REN-TR-250 CH.23+741.958 RHS

28

9/16/2014

CCC

FQIRENARDET/243

29

9/16/2014

CCC

30

9/16/2014

CCC

31

9/16/2014

CCC

32

9/17/2014

CCC

33

9/18/2014

CCC

Method Statement
Approval for Package
Substation
Project Progress Photographs
FQI& Videos with Hard & printed
RENARDET/246 copy
Under Bridge lighting Location
setting - out at ch.23+269.5FQI-REN-TR-251 Rev.A
Bridge Drain System #200mm
upvc pipe at ch.23+269.50 to
FQI-REN-TR-252 23+509.50-Rev.A

Reply date

Reference
No.

Remarks

FQIRENARDET/241
FQIRENARDET/242
FQI-REN-TR177A

FQIRENARDET/244
FQIRENARDET/245
CCC/FQI/REN/M
AS/021A

9/15/2014

Approved

Retaining walls

9/18/2014

CCC

35

9/18/2014

CCC

36

9/21/2014

CCC

37

9/21/2014

CCC

38

9/21/2014

CCC

39

9/22/2014

CCC

40

9/24/2014

CCC

41

9/25/2014

CCC

42

9/25/2014

CCC

FQI-REN-TR-254 Detour - 1 LHS cross sections


Dimension & Details of 3 Cell
FQI-REN-TR-255 Box Culvert Rev C
FQIProposed Vehicular
RENARDET/250 Underpasses
FQIRENARDET/251 Pot Bearing - Variation Order

43

9/28/2014

CCC

FQIRENARDET/252

44

9/28/2014

CCC

FQIRENARDET/253

45

9/29/2014

CCC

46

9/30/2014

CCC

47

9/30/2014

CCC

Eid Al Adha Holidays


Cross Sections at SOL-4 from
CH.0+220 to 0+900 LHS & RHS
FQI-REN-TR-256 ( Rev.A)

48

9/30/2014

CCC

New Jersy Mold Over Bridge


FQI-REN-TR-257 for Falaj Alqabail Roundabout

Pedestrian Underpass Lighting


FQI-REN-TR-253 plan at ch.24+360- Rev-A
Additional request for
Extension of time due to
significant Increase of
FQIQuantities and Additional
RENARDET/247 works
FQIRENARDET/248 Vehicular Underpasses
FQIRENARDET/249 Suspension of the work

RENARDET S.A. & PARTNERS

Approved

Approved Shop Drawing from


Majan Electricity at SOL-03

34

FQIRENARDET/254
FQIRENARDET/255

9/15/2014

9/25/2014

REN/FQI/CCC
/188

9/25/2014

Approved as
Noted

9/29/2014

Approved as
Noted

9/25/2014

Approved as
Noted

9/24/2014
9/22/2014

9/25/2014

REN/FQI/CCC
/187
REN/FQI/CCC
/186

Approved

Approved Shop Drawing from


Majan Electricity at SOL-03
Approved Shop Drawing
Relocation from majan
electricity co
Rock Soil Embankment Proposed Method Statement

Page 37

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

20. PROGRESS PHOTOGRAPHS

Earthworks in Progress on Muscat Side Approach

Formwork for First Segment of Superstructure in Progress

RENARDET S.A. & PARTNERS

Page 38

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Ground Preparation in Progress for Scaffolding of LHS Flyover

Site Inspection of DGR Representatives in Progress

RENARDET S.A. & PARTNERS

Page 39

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Progress of MSE Walls on Muscat Side Approach

Finishing Works of Pier in Progress

RENARDET S.A. & PARTNERS

Page 40

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Site Inspection of DGR Representatives

Engineering Fill on Abutment No. 1 Side Approach

RENARDET S.A. & PARTNERS

Page 41

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Backfilling above 5 Cells Box Culvert in Progress

Construction of 9 Cells Box Culvert in Progress

RENARDET S.A. & PARTNERS

Page 42

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Construction of Pier No. 4 in Progress

Construction of 44 Cells Box Culvert in Progress

RENARDET S.A. & PARTNERS

Page 43

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Pressure Testing of 250mm dia Water Pipeline

Installation of MSE Wall Panels in Progress on Abutment No. 2 Side

RENARDET S.A. & PARTNERS

Page 44

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Sub-Base Works in Progress on Muscat Side Approach

Reinforcement Fixing in 5 Cells Box Culvert in Progress

RENARDET S.A. & PARTNERS

Page 45

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Reinforcement Fixing in 44 Cells Box Culvert in Progress

Waterproofing in Progress in 44 Cells Box Culvert

RENARDET S.A. & PARTNERS

Page 46

Project: Upgrading of Falaj Al Qabail Roundabout

Monthly Progress Report September 2014

Inspection of Site Trials for Rock Soil Embankment Filling

Inspection of Laboratory by DGR Representative

RENARDET S.A. & PARTNERS

Page 47