Documente Academic
Documente Profesional
Documente Cultură
CONSULTANT:
CONTRACTOR:
Table of Contents
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
QA/QC REPORTS...................................................................................................................................................... 29
17.
18.
19.
20.
Page 1
1.
Project Particulars
Client:
Consultant:
Contractor:
30.10.2013
Mobilization Period:
60 Days
Construction Period:
548 Days
Completion date:
29.06.2015
R.O. 17,884,403.000
Amount of Contingencies:
R.O. 1,402,155.613
R.O. 16,482,247.387
9.09%
9.38%
39.87%
39.18%
Page 2
2. Scope of Work
This project is located in Batinah Region on existing Batinah Highway in the Wilayat Sohar and
consists of construction of an interchange in place of existing roundabout along with allied works.
Total length of the project along Batinah highway is about 4.0 km which shall be converted from four
lanes to six lanes with tapering back to 4lanes, all as shown on plans. Also included in the scope of
work is the construction of service roads, pedestrian underpasses.
The work also includes expropriation of properties, relocation/protection of services (sewerage,
telephone, electricity, water, irrigation) road lighting works and traffic signals.
Major items within the scope of work consist of but not limited to the following:
Page 3
Page 4
Page 5
Date
07.09.2014
11.09.2014
15.09.2014
Meeting
Director
Deputy.
17.09.2014
28.09.2014
30.09.2014
Page 6
Designation
Date of
Joining
2.
Muneer Abdul
Resident Engineer
19.03.2014
3.
Hussein Shah
Material Engineer
04.01.2014
4.
Ernesto B. Paredes
Bridge Engineer
16.04.2014
5.
Sande H Tangaras
Civil Engineer
08.06.2014
6.
Danilo
Quantity Surveyor
19.06.2014
6.
Mohamed Safie
Land Surveyor
04.01.2014
7.
Aseef Iqbal
Site Inspector
10.02.2014
8.
Site Inspector
30.03.2014
9.
Material Inspector
01.04.2014
Secretary
13.04.2014
Page 7
6. Progress S-Curve
UPGRADING OF FALAJ AL QABAIL ROUNDABOUT PROJECT - OMAN
MONTHLY CL 14 PLANNED VS. ACTUAL MANHOURS
12
120.00
MONTHS
2013
2014
Jan
Feb
Mar
Apr
May
Jun
Actual Cumulative
2015
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
0.01
0.25
1.42
4.23
7.25
10.06
9.42
9.73
10.21
9.79
8.49
5.72
4.55
3.56
2.79
3.83
3.55
3.47
1.67
0.11
0.14
0.23
0.28
1.71
3.18
6.84
9.16
9.14
9.08
8.49
7.90
8.08
6.71
6.25
4.68
3.59
3.34
4.42
0.28
Oct
Sep
Aug
Jul
Jun
May
Apr
Feb
2015
Dec
CUMULATIVE PROGRESS
Jan
2014
MONTHLY PROGRESS
Nov
Sep
Jun
2013
Mar
0.00
Dec
Oct
20.00
Aug
Jul
40.00
May
Apr
60.00
Mar
Feb
80.00
Jan
% Cumulative
100.00
Dec
% MONTHLY
10
0.18
1.01
3.01
5.53
5.18
7.36
7.30
9.33
Jul
Aug
3.29
-
1.64
-
Sep
1.11
-
Oct
0.62
-
0.01
0.26
1.67
5.91
13.15
23.21
32.64
42.37
52.58
62.37
70.86
76.59
81.13
84.69
87.48
91.31
94.86
98.33
100.00
100.00
100.00
100.00
100.00
0.11
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
48.35
56.26
64.34
71.05
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.48
10.01
15.19
22.55
29.86
39.18
REV.:
0
PERIOD ENDING:
Sep-14
Item
Description
Budgeted
Man-Hrs
56,423
Road Diversions
Wtd.
%
2.73
Plan/
Actual
2013
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
CL14 Plan %
0.30
8.67
19.23
26.89
31.77
36.64
41.51
46.39
51.26
56.13
61.01
65.88
70.76
75.63
80.50
85.38
90.25
95.13
100.00
100.00
100.00
100.00
100.00
80.93
84.74
88.56
92.37
96.18
100.00
100.00
100.00
100.00
100.00
100.00
100.00
80.66
87.59
88.57
100.00
100.00
100.00
Revised Plan %
Actual
CL14 Plan %
Clearing &
Removal of
Obstructions
19,558
Embankment
74,043
0.95
3.59
14,821
Subbase &
Aggregate Base
50,004
Bituminous
Pavement
73,724
0.72
42.78
46.60
50.41
44.11
51.21
56.24
60.13
0.00
0.38
20.37
47.70
48.33
48.33
48.33
48.33
3.57
48.33
29.85
78.13
78.13
78.13
Actual
10.09
10.09
17.59
19.52
77.42
69.96
70.18
70.18
70.18
0.00
0.00
0.78
0.00
Revised Plan %
Actual
Revised Plan %
Revised Plan %
0.00
0.00
-
0.00
0.00
-
1.01
0.00
-
9.21
5.00
0.00
-
6.58
4.35
29.30
5.00
0.00
-
16.76
4.89
45.91
29.38
41.37
58.64
Revised Plan %
66.60
3.32
12.89
28.83
5.27
14.93
29.52
56.90
62.24
64.59
67.94
4.26
8.17
16.03
32.68
53.13
53.23
0.00
62.16
0.00
74.91
0.00
78.29
11.07
91.86
26.27
Actual
54.23
48.33
78.13
74.18
43.89
69.08
67.05
41.98
-
58.04
48.33
78.13
82.85
60.03
69.08
67.47
59.98
3.58
61.86
48.33
78.13
84.75
74.82
75.05
67.47
78.73
17.42
65.67
59.91
78.13
84.75
90.03
82.85
67.90
79.90
31.37
69.48
77.84
78.13
85.24
95.24
93.48
68.32
79.90
51.32
73.30
90.27
78.13
92.34
95.95
98.64
68.32
85.20
75.82
77.11
94.93
78.13
92.34
100.00
100.00
100.00
100.00
100.00
95.95
96.09
98.30
99.46
99.54
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
68.32
81.11
93.02
97.11
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
75.82
87.25
87.25
98.60
100.00
100.00
100.00
100.00
100.00
100.00
51.97
86.66
90.05
93.03
100.00
89.45
75.82
98.36
92.60
75.82
1.26
0.00
-
0.00
-
0.00
-
0.00
-
0.00
-
0.00
-
0.00
-
0.00
-
0.00
-
0.08
-
7.77
-
19.32
-
31.22
-
44.94
0.08
51.98
8.44
52.14
22.42
90.14
46.57
90.14
51.97
Actual
CL14 Plan %
Concrete for
Box Culvert
/Underpas
788,138
Concrete for
Bridge
456,522
38.19
22.12
1.50
Incidental
Construction
275,037
MSE walls
141,190
13.33
6.84
83,264
2,063,644
4.03
100.000
0.00
0.23
1.43
2.97
10.17
51.47
63.06
0.26
2.64
7.33
20.62
35.14
50.06
62.76
Actual
0.48
1.26
5.59
14.93
27.72
40.08
55.38
Revised Plan %
0.00
0.00
0.00
0.00
4.02
0.00
Revised Plan %
Actual
0.00
0.00
0.00
15.21
0.01
0.00
2.50
0.00
34.62
39.02
49.64
59.51
71.33
26.30
3.42
30.75
4.23
5.50
6.08
6.08
61.45
74.69
90.19
24.07
14.39
13.24
16.19
16.72
27.56
0.00
0.00
2.80
0.00
Actual
0.00
0.00
0.00
Revised Plan %
Actual
Revised Plan
Actual Cum
0.11
-
4.43
6.16
0.00
-
99.96
29.64
22.33
2.63
Actual
92.89
22.09
0.00
84.50
74.07
18.14
1.21
83.46
77.37
13.76
0.00
83.38
72.78
7.75
81.40
75.97
14.73
0.38
0.00
69.26
68.40
6.05
0.00
Revised Plan %
Revised Plan %
57.89
74.26
2.77
17.23
9.87
0.00
-
0.13
5.52
2.61
33.36
4.98
49.13
6.42
65.07
17.87
8.31
80.79
43.85
93.82
2.30
17.26
33.64
49.01
17.63
25.69
35.90
49.03
65.95
0.17
0.79
1.43
5.65
61.59
72.98
81.15
80.05
100.00
100.00
100.00
100.00
100.00
74.67
83.42
84.04
84.30
87.32
95.58
98.11
99.44
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
85.14
87.00
93.50
100.00
100.00
100.00
100.00
100.00
100.00
100.00
99.76
100.00
100.00
100.00
100.00
100.00
100.00
94.70
98.41
100.00
100.00
100.00
100.00
34.35
94.70
83.94
82.40
99.38
94.70
84.42
88.97
99.76
94.70
85.35
92.13
94.70
92.86
98.55
100.00
100.00
100.00
100.00
100.00
7.02
20.33
38.29
50.60
59.52
72.89
81.07
96.39
83.55
86.89
90.26
95.34
98.27
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
64.70
79.88
95.44
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
100.00
70.94
75.04
94.02
96.43
10.67
0.99
13.41
0.33
2.34
9.42
9.26
13.38
16.87
17.75
20.45
21.84
100.00
100.00
100.00
100.00
100.00
100.00
17.07
30.56
23.51
32.94
31.40
41.66
47.49
47.55
47.55
83.28
93.95
97.61
100.00
100.00
100.00
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
48.35
56.26
64.34
71.05
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.48
10.01
15.19
22.55
29.86
39.18
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jun
Jul
Aug
2014
2013
Jan
Feb
Mar
Apr
2015
Jan
Feb
Mar
Apr
May
Sep
Oct
0.01
0.25
1.42
4.23
7.25
10.06
9.42
9.73
10.21
9.79
8.49
5.72
4.55
3.56
2.79
3.83
3.55
3.47
1.67
0.11
0.14
0.23
0.28
1.71
3.18
6.84
9.16
9.14
9.08
8.49
7.90
8.08
6.71
6.25
4.68
3.59
3.34
4.42
3.29
1.64
1.11
0.62
CUMULATIVE PROGRESS
36.51
Dec
MONTHLY PROGRESS
23.65
Actual
CL14 Plan %
30,920
0.00
Revised Plan %
CL14 Plan %
Drainage Works
TOTAL
38.97
43.00
7.40
CL14 Plan %
35.16
37.31
-
CL14 Plan %
30.90
22.36
-
CL14 Plan %
24.18
13.03
-
CL14 Plan %
17.58
6.62
-
Actual
CL14 Plan %
2.42
0.00
9.30
CL14 Plan %
Structural
Excavation
2015
Revised Plan %
CL14 Plan %
4.11
2014
0.28
0.18
1.01
3.01
5.53
5.18
7.36
7.30
9.33
0.01
0.26
1.67
5.91
13.15
23.21
32.64
42.37
52.58
62.37
70.86
76.59
81.13
84.69
87.48
91.31
94.86
98.33
100.00
100.00
100.00
100.00
100.00
0.11
0.25
0.48
0.76
2.47
5.64
12.48
21.64
30.78
39.87
48.35
56.26
64.34
71.05
77.31
81.99
85.59
88.93
93.35
96.64
98.27
99.38
100.00
0.28
0.45
1.46
4.48
10.01
15.19
22.55
29.86
39.18
7.
Sl. No.
Description
Unit
BOQ Qty.
(Revised)
M2
162,000
129,901
80.19%
340,000
71,000
20.88%
Granular Sub-base
M3
28,700
1,500
5.23%
M3
15,000
9,950
66.33%
M3
13,805
2,793
20.23%
ton
4,900
1,778
36.28%
Working Piles
M3
2,826
2,826
100.00%
M3
5,210
0.00
0.00%
MSE Walls
M2
13,200
5,045
38.22%
11
LM
4,530
712
15.71%
PIER
AB1 L
P1L
P2L
P3L
P4L
P5L
AB2 L
N/A
N/A
2nd Lift
12-Aug-14
19-Aug-14
24-Jul-14
28-Sep-14
4-Sep-14
Height (m)
6.920
6.920
6.920
6.920
6.920
1st Lift
23-Jul-14
7-Aug-14
29-Jun-14
15-Sep-14
10-Aug-14
Height (m)
1.153
1.210
1.440
1.248
1.225
BIT. PAINTING
28-May-14
26-Jun-14
17-May-14
4-Sep-14
23-Jun-14
17-May-14
18-Jun-14
8-May-14
25-Aug-14
11-Jun-14
N/A
11-May-14
11-Jun-14
1-May-14
17-Aug-14
3-Jun-14
N/A
AB2 R
AB1 R
P1R
P2R
P3R
P4R
P5R
N/A
N/A
N/A
9-Jun-14
28-Jun-14
22-Jun-14
21-Sep-14
10-Jul-14
N/A
6.920
6.920
6.920
6.920
6.920
N/A
20-May-14
11-Jun-14
26-May-14
10-Sep-14
22-Jun-14
N/A
0.366
0.423
0.649
0.461
0.438
BIT. PAINTING
12-May-14
25-May-14
8-May-14
4-Sep-14
31-May-14
4-May-14
13-May-14
4/30/2014
27-Aug-14
20-May-14
N/A
27-Apr-14
7-May-14
22-Apr-14
20-Aug-14
14-May-14
N/A
PEDESTAL
PIER
2nd Lift
Height (m)
1st Lift
Height (m)
PREVIOUS
PREVIOUS MONTH
THIS MONTH
Page 11
FROM
TO
22+702.653
22+825
DATE
-
13-Jul-14
14-Jul-14
El. 20.40
6-Jul-14
22+840
22+880
13-Jul-14
22+880 22+908.387 10-Aug-14
11-Aug-14
22+908.387 22+969.478 3-Jul-14
El. 21.20
5-Jul-14
4-Aug-14
22+969.478 23+000
5-Aug-14
20-Jul-14
23+000
23+025
21-Jul-14
17-Jul-14
23+025
23+070
El. 22.00
18-Jul-14
30-Jun-14
23+070
23+140
1-Jul-14
23+140 23+164.573 16-Jun-14
17-Jun-14
22+825
El. 22.80
22+840
El. 22.00
Elevation
FOUNDATION
/BLINDING
El. 20.40
El. 21.20
El. 22.00
El. 22.80
El. 22.00
LOCATION (RHS)
FROM
TO
22+718.936
22+810
22+810
22+893.032
22+893.032 22+976.294
22+976.294
23+040
23+040
23+088.046
23+088.046
23+130
23+130
23+191.774
23+191.774 23+270.800
LOCATION (AB 1)
Elevation
El. 22.00
FROM
TO
DATE
FOUNDATION
/BLINDING
17-Sep-14
18-Sep-14
9-Aug-14
10-Aug-14
13-Aug-14
14-Aug-14
18-Aug-14
19-Aug-14
26-Jul-14
27-Jul-14
21-Jul-14
22-Jul-14
7-Jul-14
10-Jul-14
26-Jun-14
27-Jun-14
DATE
FOUNDATION
/BLINDING
26-Jun-14
27-Jun-14
18-Jun-14
El. 23.30
FROM
TO
23+508.239
23+520
23+520
23+580.877
El. 24.10
Elevation
El. 23.30
FROM
TO
DATE
FOUNDATION
/BLINDING
15-Sep-14
16-Sep-14
23+580.877 20-Aug-14
23+650
23+650
23+750
23+730
23+827.635
21-Aug-14
26-Aug-14
27-Aug-14
1-Sep-14
2-Sep-14
El. 24.90
LOCATION (AB 2)
DATE
FOUNDATIO
N /BLINDING
23+827.635 23+949.895
PREVIOUS
P R E V IO US
M ON T H
LOCATION (RHS)
Elevation
El. 23.30
El. 24.10
DATE
FOUNDATION
/BLINDING
FROM
TO
23+508.1
23+607.6
8-Sep-14
9-Sep-14
23+607.6
23+950.1
THIS MONTH
Page 12
ELEV.
22+825
34.800
34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400
ELEV.
22+810
34.000
33.200
32.400
31.600
30.800
30.000
29.200
28.400
27.600
26.800
26.000
25.200
24.400
23.600
22.800
22.000
21.200
20.400
22+840
22+880
23+164.573
23+237.536
23+270.762
20-Sep-14
9-Sep-14
4-Sep-14
16-Sep-14 26-Aug-14
4-Sep-14 18-Aug-14
21-Sep-14 17-Sep-14 27-Aug-14 13-Aug-14
22-Sep-14 22-Sep-14 22-Sep-14 11-Sep-14 24-Aug-14 9-Aug-14 28-Jul-14
3-Sep-14 3-Sep-14 3-Sep-14 28-Aug-14
28-Aug-14 28-Aug-14 28-Aug-14
-
22+908.387
22+969.478
22+991
23+084
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
-
18-Sep-14
15-Sep-14
28-Aug-14
19-Aug-14
6-Aug-14
24-Jul-14
13-Jul-14
-
22+976.294
23+035
23+088.046
23+191.774
AB 1 Face
23+270.800
18-Sep-14
13-Sep-14 13-Sep-14
2-Sep-14 31-Aug-14
24-Aug-14 18-Aug-14
20-Sep-14 20-Sep-14 13-Aug-14 6-Aug-14
8-Sep-14 8-Sep-14 9-Aug-14 24-Jul-14
18-Sep-14 21-Aug-14 18-Aug-14
13-Jul-14
23-Sep-14 26-Aug-14
4-Sep-14
PREVIOUS
P R E V IO US
M ON T H
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-
19-Sep-14
11-Sep-14
28-Aug-14
18-Aug-14
7-Aug-14
24-Jul-14
13-Jul-14
-
THIS MONTH
Page 13
STATION
1
LHS
RHS
2
21+260
Block 1
Block 2
21+485
Block 1a
Block 1b
Block 2a
Block 2b
21+838
Block 1a
Block 1b
Block 2
Block 3
Block 4a
Block 4b
Block 5
Block 6
21+972.4
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
Block 13
Block 14
Block 15
Block 16
Block 17
Block 18
Block 19
Block 20
Block 21
Block 22
21+972.4
Block 23
Block 24
Block 25
Block 26
Block 27
Block 28
Block 29
Block 30
Block 31
Block 32
Block 33
22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
LHS
RHS
3
LHS
RHS
LHS
RHS
4
LHS
RHS
RHS
5
LHS
RHS
LHS
RHS
LHS
RHS
LENGTH SKEW (
F/P &
(m)
BLINDING
)
43.039
19.526
23.493
49.750
3.000
17.290
7.710
21.730
57.210
5.000
17.600
22.600
11.970
5.000
17.600
22.600
11.970
57.629
28.038
28.031
28.026
28.022
28.019
28.018
28.019
28.022
28.026
28.031
28.038
21.015
21.010
21.006
21.003
21.001
21.000
21.001
21.003
21.006
21.010
21.015
57.629
6.635
6.782
6.819
7.217
7.975
8.571
9.267
9.949
10.260
10.262
10.265
95.482
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
45 R
9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
1-Jul-14
1-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
21-Jul-14
3-Jul-14
3-Jul-14
24-May-14
24-May-14
17-May-14
18-May-14
18-May-14
18-May-14
18-May-14
26-May-14
26-May-14
28-May-14
28-May-14
10-Aug-14
27-Jul-14
27-Jul-14
24-Jul-14
16-Jun-14
16-Jun-14
12-Jun-14
12-Jun-14
8-Jun-14
8-Jun-14
8-Jun-14
30-Jun-14
24-Jun-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
-
BASE SLAB
Rebars
Concrete
WALL
Rebars
TOP SLAB
Concrete
Rebars
Concrete
5-Jun-14
10-Jul-14
25-May-14
13-Jul-14
29-May-14
31-Jul-14
10-Jun-14
10-Aug-14
15-Jun-14
18-Aug-14
19-Jun-14
26-Aug-14
22-Sep-14
23-Aug-14
27-Jul-14
15-Sep-14
30-Sep-14
2-Sep-14
25-Jun-14
7-Aug-14
21-Jul-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
-
24-Jun-14
3-Aug-14
3-Jun-14
5-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
25-Aug-14
7-Jul-14
14-Sep-14
20-Jul-14
2-Sep-14
29-Sep-14
8-Sep-14
14-Aug-14
23-Sep-14
22-Sep-14
30-Jul-14
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
-
24-Jun-14
4-Aug-14
3-Jun-14
6-Aug-14
8-Jun-14
12-Aug-14
1-Jul-14
26-Aug-14
8-Jul-14
14-Sep-14
20-Jul-14
3-Sep-14
29-Sep-14
8-Sep-14
14-Aug-14
24-Sep-14
22-Sep-14
30-Jul-14
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
-
15-Jul-14
13-Aug-14
23-Jun-14
18-Aug-14
2-Jul-14
27-Aug-14
23-Jul-14
9-Sep-14
4-Aug-14
24-Sep-14
2-Sep-14
18-Sep-14
3-Sep-14
30-Sep-14
16-Sep-14
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
-
Bituminous Paint
(2 Coats)
1-Sep-14
1-Sep-14
-
16-Jul-14 16-Aug-14
13-Aug-14 8-Sep-14
23-Jun-14 8-Sep-14
19-Aug-14
2-Jul-14
28-Aug-14
24-Jul-14
10-Sep-14
5-Aug-14
25-Sep-14
3-Sep-14 25-Sep-14
19-Sep-14
4-Sep-14
30-Sep-14
17-Sep-14 25-Sep-14
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
-
Page 14
NO.
STATION
22+655
(9 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
Block 9
Block 10
Block 11
Block 12
23+492
(5 cells)
Block 1
Block 2
Block 3
Block 4
Block 5
Block 6
Block 7
Block 8
23+756.5
Block 1
Block 2
Block 3a
Block 3b
Block 4
23+997
Block 1
Block 2a
Block 2b
Block 3a
Block 3b
Block 4a
Block 4b
24+235
Block 1a
Block 1b
Block 2a
Block 2b
Block 2c
24+570
Block 1
Block 2a
Block 2b
LHS
RHS
LHS
RHS
LHS
RHS
6
LHS
RHS
LHS
RHS
7
LHS
RHS
8
LHS
RHS
9
LHS
RHS
10
LHS
RHS
LENGTH SKEW (
F/P &
(m)
BLINDING
)
95.482 45 R
30-Jun-14
24-Jun-14
29-Jun-14
24-Jun-14
28-Jun-14
29-Jun-14
24-Jun-14
24-Jun-14
9/172014
24-Jun-14
24-Jun-14
9/172014
12-Jul-14
12-Jul-14
11-Aug-14
8-Jul-14
8-Jul-14
10-Aug-14
10-Aug-14
BASE SLAB
WALL
TOP SLAB
Rebars
Concrete
Rebars
Concrete
6-Aug-14
21-Jul-14
27-Jul-14
28-Aug-14
20-Aug-14
3-Aug-14
9-Jul-14
14-Jul-14
23-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
7-Aug-14
21-Jul-14
28-Jul-14
28-Aug-14
23-Aug-14
4-Aug-14
9-Jul-14
15-Jul-14
24-Sep-14
5-Aug-14
6-Aug-14
28-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
30-Jul-14
3-Aug-14
28-Sep-14
-
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
30-Jul-14
3-Aug-14
28-Sep-14
-
Rebars
1-Sep-14
17-Aug-14
13-Sep-14
24-Sep-14
16-Aug-14
21-Aug-14
9 & 20/8/2014 9 & 23/8/2014 28-Aug-14
11 & 25/8/2014 11 & 26/8/2014 31-Aug-14
23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14
26-Aug-14 26-Aug-14 26-Aug-14
23-Jul-14 23-Jul-14 23-Jul-14
23-Jul-14 23-Jul-14 23-Jul-14
26-Aug-14 26-Aug-14 26-Aug-14
26-Aug-14 26-Aug-14 26-Aug-14
Concrete
Bituminous Paint
(2 Coats)
2-Sep-14
18-Aug-14
14-Sep-14
26-Sep-14
17-Aug-14
21-Aug-14
28-Aug-14
1-Sep-14
23-Jul-14
23-Jul-14
26-Aug-14
23-Jul-14
23-Jul-14
26-Aug-14
26-Aug-14
6-Sep-14
6-Sep-14
4-7/9/2014
4-7/9/2014
24-Jul-14
24-Jul-14
28-Aug-14
24-Jul-14
24-Jul-14
31-Aug-14
31-Aug-14
9.675
32.711
32.711
20.315
19.035
32.711
32.711
10.95
25.03
32.711
32.711
4.960
79.065
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
45 R
15 R
6.457
31.546
31.546
7.982
7.039
31.546
31.546
5.525
67.550
12.090
20.180
14.430
8.700
12.090
70.268
16.128
4.933
13.860
16.300
4.942
7.848
6.197
59.106
15.566
15.000
8.900
15.600
4.020
51.953
25.846
13.500
12.587
15 R
15 R
15 R
15 R
15 R
15 R
15 R
15 R
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
0
12-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 23-Jul-14 24-Jul-14
0 10-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 26-Aug-14 31-Aug-14
0
0
0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
0 14-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 25-Aug-14 31-Aug-14
0
-
Note: Precast RCBC were used for all 1 cell - 2.0m x 1.5m locations.
PREVIOUS
PREVIOUS MONTH
THIS MONTH
Page 15
4A
DRAWING No.
STAGES
LEFT STAGE
CCC/FQI/IR/06 SERVICE
MIDDLE STAGE
ROAD-3
RIGHT STAGE
LEFT STAGE
CCC/FQR/IR/11 SOL-2 MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
CCC/FQR/IR/10 SOL-3 MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
CCC/FQR/WA/05 SR-1 MIDDLE STAGE
RIGHT STAGE
RHS OF SOL-01
CCC/FQI/SL/01
CCC/FQI/IR/01
CCC/FQI/EL/02
CCC/FQI/IR/02
CCC/FQI/EL/03
10
CCC/FQI/EL/04
11
CCC/FQI/EL/05
12
CCC/FQI/IR/03
13
CCC/FQI/IR/04
JUNCTION CROSSING
14
CCC/FQI/IR/05
JUNCTION CROSSING
15
CCC/FQI/EL/06
16
CCC/FQI/WA/02
JUNCTION
17
CCC/FQI/WA/01
18
CCC/FQI/EL/07
19
CCC/FQI/EL/13
20
CCC/FQI/EL/08
DIA
TYPE
0+030
200
UPVC
0+150
300
UPVC
0+300
200
UPVC
0+600
300
UPVC
21+160
150
UPVC
150
UPVC
300
LEFT STAGE
MIDDLE STAGE 21+360
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+460
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+660
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+780
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+880
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+260
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+510
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+520
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE22+520 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE22+587 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+760
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE23+008 LHS
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+020
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+060
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+210
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+240
RIGHT STAGE
PIPE
CHAINAGE
9/24/2014
9/24/2014
5/15/2014
6/11/2014
5/15/2014
6/11/2014
5/18/2014
6/12/2014
6/12/2014
7/10/2014
UPVC
5/19/2014
6/14/2014
5/19/2014
14/06/014
5/20/2014
6/14/2014
6/4/2014
6/21/2014
UPVC
5/19/2014
6/15/2014
5/19/2014
6/15/2014
5/20/2014
6/15/2014
5/31/2014
150
300
UPVC
5/20/2014
6/15/2014
5/20/2014
6/15/2014
5/25/2014
6/15/2014
6/4/2014
7/8/2014
150
UPVC
5/25/2014
6/16/2014
5/25/2014
6/16/2014
5/25/2014
6/17/2014
6/4/2014
7/10/2014
150
UPVC
6/17/2014
7/20/2014
6/17/2014
7/20/2014
6/18/2014
7/21/2014
7/9/2014
7/27/2014
150
UPVC
6/19/2014
7/20/2014
6/19/2014
7/20/2014
6/19/2014
7/21/2014
7/6/2014
7/17/2014
200
UPVC
6/19/2014
7/20/2014
6/19/2014
7/20/2014
6/19/2014
7/21/2014
7/5/2014
7/17/2014
200
UPVC
200
UPVC
150
UPVC
5/26/2014
6/11/2014
5/26/2014
6/11/2014
5/26/2014
6/11/2014
6/8/2014
7/22/2014
300
UPVC
900
RC
6/16/2014
7/8/2014
6/16/2014
7/8/2014
6/16/2014
7/9/2014
7/20/2014
7/27/2014
150
UPVC
5/25/2014
11/06/201
5/25/2014
6/11/2014
5/26/2014
6/11/2014
6/14/2014
6/23/2014
5/27/2014
5/27/2014
5/27/2014
6/17/2014
150
UPVC
4
5/28/2014
5/28/2014
5/28/2014
6/17/2014
150
UPVC
Page 16
S.NO.
DRAWING No.
20
CCC/FQI/EL/08
21
CCC/FQI/EL/09
22
CCC/FQI/EL/10
23
CCC/FQI/WA/03
23A
24
CCC/FQI/EL/11
25
CCC/FQI/WA/04
26
CCC/FQI/IR/07
27
CCC/FQI/EL/12
28
CCC/FQI/EL/14
29
CCC/FQI/IR/08
30
CCC/FQI/EL/15
31
CCC/FQI/EL/16
32
CCC/FQI/IR/09
33
CCC/FQI/EL/17
34
CCC/FQI/NAW.2
35
CCC/FQI/NAW.3
36
CCC/FQI/NAW.4
37
CCC/FQI/OMANTEL.1
38
CCC/FQI/OMANTEL.2
39
CCC/FQI/SL/03
40
CCC/FQI/SL/04
STAGES
LEFT STAGE
MIDDLE STAGE 23+240
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+560
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+900
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+960
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+980
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+000
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+020
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+120
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+220
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+340
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+520
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+960
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 25+160
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 21+870
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 23+580
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 24+720
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+810
RIGHT STAGE
LEFT STAGE
0+140 SOL-3
MIDDLE STAGE
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+820
RIGHT STAGE
LEFT STAGE
MIDDLE STAGE 22+990
RIGHT STAGE
PIPE
CHAINAGE
DIA
TYPE
150
UPVC
150
UPVC
150
600
5/28/2014
5/28/2014
5/28/2014
6/17/2014
5/29/2014
7/30/2014
5/29/2014
8/12/2014
5/29/2014
8/26/2014
6/17/2014
8/26/2014
UPVC
5/29/2014
7/14/2014
6/2/2014
7/14/2014
6/2/2014
7/14/2014
6/17/2014
8/20/2014
RC
5/29/2014
7/14/2014
6/2/2014
7/14/2014
6/2/2014
7/15/2014
6/17/2014
8/20/2014
UPVC
8/10/2014
8/11/2014
8/11/2014
8/26/2014
150
UPVC
5/29/2014
8/6/2014
6/2/2014
8/6/2014
6/3/2014
8/9/2014
6/19/2014
8/13/2014
600
RC
300
UPVC
6/3/2014
8/11/2014
6/4/2014
8/11/2014
6/4/2014
8/19/2014
6/23/2014
8/26/2014
150
UPVC
6/4/2014
7/23/2014
6/5/2014
7/24/2014
6/10/2014
8/19/2014
23/06/201
8/26/2014
150
UPVC
6/9/2014
8/6/2014
6/9/2014
8/6/2014
6/10/2014
8/6/2014
6/23/2014
8/26/2014
7/5/2014
7/5/2014
7/5/2014
7/13/2014
300
UPVC
2
7/16/2014
7/16/2014
7/17/2014
7/27/2014
150
UPVC
3
9/14/2014
9/14/2014
150
UPVC
3
9/16/2014
9/20/2014
300
UPVC
150
UPVC
100
UPVC
5/21/2014
6/16/2014
5/21/2014
6/16/2014
5/21/2014
6/18/2014
6/4/2014
7/10/2014
100
UPVC
5/29/2014
7/10/2014
5/31/2014
7/10/2014
5/31/2014
8/13/2014
6/17/2014
8/26/2014
100
UPVC
100
UPVC
8/6/2014
8/8/2014
9/16/2014
7/7/2014
8/12/2014
8/6/2014
8/9/2014
9/16/2014
7/8/2014
8/13/2014
8/5/2014
8/9/2014
9/16/2014
7/8/2014
8/14/2014
100
UPVC
150
UPVC
7/9/2014
8/12/2014
7/9/2014
8/13/2014
8/14/2014
150
UPVC
7/2/2014
7/10/2014
7/22/2014
7/3/2014
7/10/2014
7/22/2014
7/3/2014
7/14/2014
7/23/2014
9/22/2014
8/15/2014
8/20/2014
Page 17
S.NO.
DRAWING No.
STAGES
PIPE
CHAINAGE
DIA
TYPE
CCC/FQI/SL/02
BOTTOM
TOP
22+080
150
UPVC
42
CCC/FQI/EL/19
BOTTOM
TOP
23+740
150
UPVC
42
CCC/FQI/SL/05
BOTTOM
TOP
24+850
150
UPVC
43
CCC/FQI/SD/07
21+500
450
44
CCC/FQI/SD/08
21+560
450
45
CCC/FQI/SD/09
21+620
450
BOTTOM
TOP
CONC PIPE
41
8/30/2014
8/31/2014
9/14/2014
9/15/2014
9/15/2014
9/16/2014
9/17/2014
10/2/2014
10/2/2014
10/2/2014
10/2/2014
10/2/2014
10/2/2014
Settingout
excav/lay
concrete
19/16/2014
9/17/2014
9/30/2014
9/30/2014
9/30/2014
CCC/FQI/Omantel/02
BOTTOM
TOP
CCC/FQI/SL/13
BOTTOM
TOP
0+130
150
UPVC
CCC/FQI/SL/14
BOTTOM
TOP
0+415
151
UPVC
CCC/FQI/SL/15
BOTTOM
TOP
0+054.459
152
UPVC
CCC/FQI/SL/16
BOTTOM
TOP
153
UPVC
CCC/FQI/SL/17
BOTTOM
TOP
154
UPVC
0+138.348
110
UPVC
Existing
Road front
SOL-3 Ch.
Existing
Road front
SOL-3 Ch.
backfill
Page 18
21+150-21+500
COMPLETED
As of September 30 2014
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Subgra de
La yr 9
La yr 8
La yr 7
La yr 6
La yr 5
La yr 4
La yr 3
La yr 2
21+360
21+380
21+400
21+420
21+440
21+460
21+860
21+880
21+900
21+920
21+940
21+960
21+500
21+340
21+840
22+000
21+320
21+820
21+480
21+300
21+800
21+980
21+280
21+780
21+260
21+240
21+220
21+200
21+180
21+160
21+140
21+120
21+100
21+080
21+060
21+040
21+020
21+000
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
Subgra de
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
21+500-22+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
s ub gra de
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
21+760
21+740
21+720
21+700
21+680
21+660
21+640
21+620
21+600
21+580
21+560
21+540
21+520
21+500
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
s ub gra de
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
Page 19
22+500
22+480
22+460
22+440
22+420
22+400
22+380
22+360
22+320
22+300
22+280
As of September 30 2014
22+260
22+240
22+220
22+200
22+180
22+160
22+120
22+100
22+080
22+060
22+040
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
22+020
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
22+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
22+140
22+000-22+500
COMPLETED
22+340
RHS
23+000
22+960
22+940
22+920
22+900
22+880
22+860
22+840
22+820
22+800
22+780
22+760
22+740
22+720
22+700
22+680
22+660
22+640
22+620
22+600
22+580
22+560
22+540
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
22+980
rock 1
layer 15
rock soil layer no 2
rock soil layer no 1
22+520
22+500
22+500-23+000
Page 20
As of September 30 2014
23+380
23+400
23+420
23+440
23+880
23+900
23+920
23+940
23+500
23+360
23+860
24+000
23+340
23+840
23+480
23+320
23+820
23+980
23+300
23+800
23+460
23+280
23+780
23+960
23+260
23+760
23+240
23+220
23+200
23+180
23+160
23+140
23+120
23+100
23+080
23+060
23+040
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
23+020
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layer 10
Layer 9
Layer 8
Layer 7
Layer 6
Layer 5
Layer 4
Layer 3
Layer 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
23+000
LHS
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
layer 6
layer 15
layer 7
Rock siol no 1
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
LHS
23+000-23+500
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
Layr 10
Layr 9
rock soil layer 1
Layr 8
layer 15
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
COMPLETED
layer no 28
rock siol layer no 1
23+740
23+720
23+700
23+680
23+660
23+640
23+620
23+600
23+580
23+560
23+540
23+520
23+500
23+500-24+000
Page 21
COMPLETED
As of September 30 2014
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
24+360
24+380
24+400
24+420
24+440
24+860
24+880
24+900
24+920
24+940
24+500
24+340
24+840
25+000
24+320
24+820
24+480
24+300
24+800
24+980
24+280
24+780
24+460
24+260
24+760
24+960
24+240
24+740
24+220
24+200
24+180
24+160
24+140
24+120
24+100
24+080
24+060
24+040
24+020
24+000
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
24+500-25+000
LHS
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
La yer 10
La yer 9
La yer 8
La yer 7
La yer 6
La yer 5
La yer 4
La yer 3
La yer 2
24+720
24+700
24+680
24+660
24+640
24+620
24+600
24+580
24+560
24+540
24+520
24+500
EMBANKMENT Layer 1
BED PREPRATION
OGL SURVEY
RHS
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
l a yer 2
l a yer 3
l a yer 4
l a yer 5
l a yer 6
l a yer 7
l a yer 8
l a yer 9
l a yer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
Page 22
COMPLETED
25+000-25+500
As of September 30 2014
BWC 6 cm
Tack Coat
BBC 12 cm
PRIME COAT
ABC 2 ND 15 cm
ABC 1 ST 15 cm
GSB 20 cm
LHS
Layr 10
Layr 9
Layr 8
Layr 7
Layr 6
Layr 5
Layr 4
Layr 3
Layr 2
EMBANKMENT Layer 1
BED PREPRATION
25+500
25+480
25+460
25+440
25+420
25+400
25+380
25+360
25+340
25+320
25+300
25+280
25+260
25+240
25+220
25+200
25+180
25+160
25+140
25+120
25+100
25+080
25+060
25+040
25+020
25+000
OGL SURVEY
OGL SURVEY
BED PREPRATION
EMBANKMENT Layer 1
layer 2
layer 3
layer 4
layer 5
RHS
layer 6
layer 7
layer 8
layer 9
layer 10
GSB 20 cm
ABC 1 ST 15 cm
ABC 2 ND 15 cm
PRIME COAT
BBC 12 cm
Tack Coat
BWC 6 cm
Page 23
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
DESCRIPTION
PAYMENT
APPLICATION No. 1
(ADVANCE)
PAYMENT
APPLICATION No. 2
PAYMENT
APPLICATION No. 3
PAYMENT
APPLICATION No. 4
PAYMENT
APPLICATION No. 5
PAYMENT
APPLICATION No. 6
PAYMENT
APPLICATION No. 7
PAYMENT
APPLICATION No. 8
PAYMENT
APPLICATION No. 9
PAYMENT
APPLICATION No. 10
PAYMENT
APPLICATION No. 11
PAYMENT
APPLICATION No. 12
PAYMENT
APPLICATION No. 13
PAYMENT
APPLICATION No. 14
PAYMENT
APPLICATION No. 15
PAYMENT
APPLICATION No. 16
PAYMENT
APPLICATION No. 17
PAYMENT FOR
THE MONTH OF
GROSS
AMOUNT
(R.O.)
GROSS
NET AMOUNT
AMOUNT
CLAIMED
CLAIMED (R.O.)
(R.O.)
DATE
SUBMITTED
AMOUNT
DATE CERTIFIED
CERTIFIED (R.O.)
AMOUNT
RECEIVED
(R.O.)
DATE
PAYMENT
RECEIVED
Dec-13
1,648,225
1,648,225
1,648,225
23-Nov-13
1,648,225
29-Jan-14
1,648,225
6-Feb-14
Jan-14
2,291,277
643,052
514,442
12-Feb-14
514,442
02-Apr-14
513,608
10-Apr-14
Feb&Mar-14
2,808,644
517,367
504,147
06-Apr-14
434,917
03-May-14
414,674
6-Aug-14
Apr-14
3,315,692
507,048
417,900
08-May-14
407,538
05-Jun-14
395,257
6-Aug-14
May-14
4,109,460
793,768
650,802
05-Jun-14
445,708
04-Jul-14
374,172
6-Aug-14
Jun-14
4,293,764
184,304
382,116
15-Jul-14
382,116
16-Jul-14
418,721
9-Sep-14
Jul&Aug-14
5,749,546
1,455,782
1,164,626
14-Sep-14
1,123,023
18-Sep-14
5,749,546
5,749,546
5,282,258
Sep-14
Oct-14
Nov-14
Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
4,955,969
3,764,656
Page 24
DESCRIPTION
CCC
HIRED
TOTAL
AVAILABLE
AT SITE
COMPRESSOR
AIR COMPRESSOR
GENERATOR
CRANES
4
-
DIESEL TANKER
FLAT TRAILER
10
HIAB TRUCK
11
12
TIPPER TRUCKS
13
14
13
14
15
BOBCAT
16
EXCAVATOR
17
18
19
DOZER D9N/D8R
20
TELEHANDLER
21
22
23
DYNAPAC S/ROLLER
24
E/WORK ROLLER
25
MOTOR GRADER
26
27
28
PAVER MACHINE
29
1
-
30
DYNA TRUCK
31
MAINTENANCE TRUCKS
32
33
34
TOYOTA COROLLA/CIVIC/YARIS
35
TOYOTA PICKUP/ISUZU
36
37
38
12
12
13
NISSAN PATHFINDER/X-TRAIL
55
109
Total
54
Page 25
20
40
60
33
Jan-14
No. of EQUIPMENT
80
55
Feb-14
100
68
Apr-14
120
66
Mar-14
115
55
88
202
66
154
77
May-14
297
68
222
390
77
299
68
86
Jun-14
47
33
33
87
88
Jul-14
110
87
545
88
473
95
100
Aug-14
108
95
640
100
573
93
109
Sep-14
107
68
458
86
385
107
102
93
733
109
682
Oct-14
108
107
93
95
87
68
47
93
110
110
100
102
PROJECT MONTHS
100
98
82
79
77
102
100
98
1,160 1,260 1,358
Sep-15
53
1,802
Aug-15
66
1,749
Jul-15
77
1,683
87
41
1,843
Oct-15
82
79
77
66
53
53
82
1,527
41
79
1,606
66
87
1,445
2015
Jan-15 Feb-15 Mar-15
102
87
108
1,058
108
98
110
950
100
107
840
98
95
Nov-14
87
Dec-14
68
82
47
Jan-15
87
Dec-14
79
Nov-14
Feb-15
Oct-14
77
Aug-14 Sep-14
Mar-15
Jul-14
66
2014
Apr-15
Jun-14
53
May-14
May-15
Apr-14
41
Mar-14
Jun-15
Feb-14
Jul-15
Jan-14
Aug-15
EQUIPMENT HISTOGRAM
Sep-15
Total
682
1500
41
Oct-15
Page 26
EXPATRIATES
NATIONALS
TOTAL
A - MANAGEMENT ***
B - COMMERCIAL STAFF *
C - ENGINEERS
20
22
E - ENGINEERING TECHNICIANS **
23
29
1 - SKILLED CRAFTSMEN
142
69
211
2 - SEMI-SKILLED/UNSKILLED
507
55
562
710
133
843
10
G - SUBCONTRACTORS
Number of Personnel employed by Subcontractor
on Company Work :
25
*
Page 27
100
200
300
400
391
Jan-14
500
596
Feb-14
No. of Men
600
425
222
340
340
18
322
11
731
391
26
365
68
848
2,202
748
3,362
638
1,353
603
54
657
2,614
425
715
581
49
630
1,957
1,327
596
46
550
291
851
57
691
4,135
773
64
709
3,052
627
851
63
59
565
4,960
825
69
756
3,910
840
858
84
59
756
5,762
802
68
734
4,764
838
854
84
6,605
843
70
773
0
7,365
741
442
74
61
667
Dec-14
381
7,691
616
326
61
57
554
Jan-15
269
7,988
573
297
57
51
516
Feb-15
246
PROJECT MONTHS
306
9,033
330
340
351
8,693
429
31
33
8,342
354
43
35
276
44
297
387
47
May-15
305
Apr-15
307
2015
Mar-15
307
725
6,923
778
6,383
541
833
764
72
61
652
5,618
854
78
63
61
83
700
750
60
754
858
825
Jul-14
222
854
57
57
802
Aug-14
630
Mar-14
700
11
52
854
843
Sep-14
11
638
657
Apr-14
800
340
Dec-13
50
764
Nov-14
480
0
Oct-14
900
57
36
541
0
Nov-14
23
848
Oct-14
701
442
0
Dec-14
748
May-14
Sep-14
793
326
0
Jan-15
773
Jun-14
Aug-14
794
297
Jul-14
799
9,212
406
179
40
30
365
Jun-15
149
301
30
271
Jul-15
6
57
10
102
15
150
6605
521
6084
9,212
8651
9215
862
914
7788
51
Total
8301
Oct-15
92
Sep-15
135
Aug-15
Aug-15
2014
Feb-15 0
Jun-14
792
354
May-14
791
0
Mar-15
Apr-14
586
351
0
Apr-15
Mar-14
375
340
0
May-15
Feb-14
186
Jul-15
Jan-14
34
Sep-15
2013
Oct-15
Dec-13
6
179
0
Page 28
Page 29
Page 30
Page 31
Page 32
Page 33
MAS/CCC/FQI/HDPE/005
MAS/CCC/FQI/PW/006
MAS/CCC/FQI/MC/007
MAS/CCC/FQI/RS/008
MAS/CCC/FQI/PT/009-1
MAS/CCC/FQI/PT/009-2
MAS/CCC/FQI/PT/009-3
MAS/CCC/FQI/PB/010A-Rev.1
MAS/CCC/FQI/PB/010B
MAS/CCC/FQI/HDPE/011
MAS/CCC/FQI/RCBC/012
MAS/CCC/FQI/BP/013
MAS/CCC/FQI/BP/013A
MAS/CCC/FQI/EJ/014A-Rev.1
MAS/CCC/FQI/RC/015
MAS/CCC/FQI/WS/016 B
MAS/CCC/FQI/TW/017
MAS/CCC/FQI/EW/019
MAS/CCC/FQI/EC/020
MAS/CCC/FQI/PS/021
MAS/CCC/FQI/PS/021A
MAS/CCC/FQI/LL/022
MAS/CCC/FQI/LP/023A
MAS/CCC/FQI/FP/024
MAS/CCC/FQI/JS/025
MAS/CCC/FQI/GT/026
MAS/CCC/FQI/GT/026A
CCC/FQI/REN/MAS/005
CCC/FQI/REN/MAS/006
CCC/FQI/REN/MAS/007
CCC/FQI/REN/MAS/008
CCC/FQI/REN/MAS/009-1
CCC/FQI/REN/MAS/009-2
CCC/FQI/REN/MAS/009-3
CCC/FQI/REN/MAS/010A-Rev.1
CCC/FQI/REN/MAS/010B
CCC/FQI/REN/MAS/011
CCC/FQI/REN/MAS/012
CCC/FQI/REN/MAS/013
CCC/FQI/REN/MAS/013A
CCC/FQI/REN/MAS/014A-Rev.1
CCC/FQI/REN/MAS/015
CCC/FQI/REN/MAS/016 B
CCC/FQI/REN/MAS/017
CCC/FQI/REN/MAS/019
CCC/FQI/REN/MAS/020
CCC/FQI/REN/MAS/021
CCC/FQI/REN/MAS/021A
CCC/FQI/REN/MAS/022
CCC/FQI/REN/MAS/023A
CCC/FQI/REN/MAS/024
CCC/FQI/REN/MAS/025
CCC/FQI/REN/MAS/026
CCC/FQI/REN/MAS/026A
MAS/CCC/FQI/GG/028
MAS/CCC/FQI/PVC/004
CCC/FQI/REN/MAS/004
CCC/FQI/REN/MAS/028
MAS/CCC/FQI/MSE/003
CCC/FQI/REN/MAS/003
MAS/CCC/FQI/MS/027
MAS/CCC/FQI/GTI/002
CCC/FQI/REN/MAS/027
MAS/CCC/FQI/BBC/001
CCC/FQI/REN/MAS/002
MAR No.
CCC/FQI/REN/MAS/001
Re fe re nce No.
Masterseal 915
(formerly known as Masterflow 410 Plus)
17/08/2014
10/08/2014
15/06/2014
21/05/2014
27/03/2014
27/03/2014
22/05/2014
Stars Light LLC
27/03/2014
16/09/2014
22/03/2014
19/03/2014
22/03/2014
12/03/2014
25/03/2014
02/03/2014
07/05/2014
17/06/2014
02/03/2014
22/02/2014
22/02/2014
11/05/2014
07/05/2014
22/02/2014
22/02/2014
22/02/2014
02/02/2014
30/01/2014
26/01/2014
26/12/2013
26/12/2013
26/12/2013
26/12/2013
22/12/2013
Date
Submitte d
Amiantit Oman
Al Ammar International
Amiantit Oman
Amiantit Oman
Al Ammar International
APCC LLC
Amiantit Oman
Amiantit Oman
Manufacture r/Supplie r/
Subcontractor
Geotextile
Package Substation
Package Substation
MV & LV Cables
Electrical Works
Telephone Works
Reinforcing Steel
Piling Works
UPVC Pipes
Geotechnical Investigation
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
Renardet
25/03/2014
09/03/2014
25/05/2014
---
27/03/2014
27/03/2014
27/03/2014
20/03/2014
09/03/2014
19/02/2014
09/02/2014
09/02/2014
02/02/2014
02/02/2014
01/04/2014
SO/FQI/CCC/083
REN/FQI/CCC/131
SO/FQI/CCC/082
REN/FQI/CCC/099
SO/FQI/CCC/077
REN/FQI/CCC/123
REN/FQI/CCC/146
REN/FQI/CCC/105
SO/FQI/CCC/064
SO/FQI/CCC/038
REN/FQI/CCC/122
REN/FQI/CCC/111
SO/FQI/CCC/091
SO/FQI/CCC/090
SO/FQI/CCC/089
SO/FQI/CCC/063
SO/FQI/CCC/069
SO/FQI/CCC/026
SO/FQI/CCC/020
SO/FQI/CCC/019
SO/FQI/CCC/014
SO/FQI/CCC/015
SO/FQI/CCC/087
14/08/2014
---
Required
latest test
Reports
---
No meet the
HDS
APPROVED
16/04/2014
08/06/2014
14/08/2014
14/08/2014
REN/FQI/CCC/166
REN/FQI/CCC/159
REN/FQI/CCC/119
REN/FQI/CCC/100
REN/FQI/CCC/130
REN/FQI/CCC/157
REN/FQI/CCC/158
CANCELLED
27/03/2014
29/05/2014
17/03/2014
16/04/2014
23/03/2014
20/05/2014
03/07/2014
APPROVED
APPROVED
APPROVED
APPROVED
----
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
Not Approved
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
APPROVED
MOTC
Submitte Re marks
Via Re narde t
Comme nt
d To
By MOTC
Le tte r Re f. No.
s date d
24/08/2014
17/08/2014
27/05/2014
28/04/2014
16/06/2014
17/08/2014
17/08/2014
----
03/04/2014
16/06/2014
03/04/2014
28/04/2014
02/04/2014
31/05/2014
13/07/2014
05/05/2014
26/03/2014
11/03/2014
31/05/2014
13/05/2014
14/04/2014
14/04/2014
14/04/2014
24/03/2014
27/03/2014
25/02/2014
18/02/2014
18/02/2014
12/02/2014
12/02/2014
07/04/2014
Re narde t
Le tte r
Date d
Page 34
Page 35
From
Reference
No
Subject
Reply date
Reference
No.
Remarks
9/1/2014
CCC
9/1/2014
CCC
9/2/2014
CCC
FQI-REN-TR082A
9/3/2014
CCC
9/4/2014
CCC
9/4/2014
CCC
9/4/2014
CCC
9/4/2014
CCC
9/4/2014
CCC
10
9/6/2014
CCC
11
9/7/2014
CCC
12
9/8/2014
CCC
REN/FQI/CCC
9/18/2014 /184
13
9/8/2014
CCC
14
9/8/2014
CCC
9/8/2014
15
9/9/2014
CCC
16
9/9/2014
CCC
17
9/9/2014
CCC
18
9/10/2014
CCC
19
9/14/2014
CCC
20
9/14/2014
CCC
21
9/14/2014
CCC
22
9/14/2014
CCC
Approved as
Noted
Approved as
Noted
9/9/2014
9/8/2014
9/7/2014
REN/FQI/CCC
/179
FQIRENARDET/235
FQIRENARDET/236
9/16/2014
Approved as
Noted
Revise &
Resubmit
9/10/2014
Approved as
Noted
9/6/2014
REN/FQI/CCC
/180
9/16/2014
Approved
9/10/2014
Approved
9/29/2014
Approved as
Noted
9/17/2014
9/16/2014
Approved
Approved as
Noted
9/25/2014
Approved
9/25/2014
Approved
Page 36
Date
Received
From
Reference
No
Subject
23
9/14/2014
CCC
24
9/14/2014
CCC
25
9/15/2014
CCC
26
9/15/2014
CCC
27
9/15/2014
CCC
28
9/16/2014
CCC
FQIRENARDET/243
29
9/16/2014
CCC
30
9/16/2014
CCC
31
9/16/2014
CCC
32
9/17/2014
CCC
33
9/18/2014
CCC
Method Statement
Approval for Package
Substation
Project Progress Photographs
FQI& Videos with Hard & printed
RENARDET/246 copy
Under Bridge lighting Location
setting - out at ch.23+269.5FQI-REN-TR-251 Rev.A
Bridge Drain System #200mm
upvc pipe at ch.23+269.50 to
FQI-REN-TR-252 23+509.50-Rev.A
Reply date
Reference
No.
Remarks
FQIRENARDET/241
FQIRENARDET/242
FQI-REN-TR177A
FQIRENARDET/244
FQIRENARDET/245
CCC/FQI/REN/M
AS/021A
9/15/2014
Approved
Retaining walls
9/18/2014
CCC
35
9/18/2014
CCC
36
9/21/2014
CCC
37
9/21/2014
CCC
38
9/21/2014
CCC
39
9/22/2014
CCC
40
9/24/2014
CCC
41
9/25/2014
CCC
42
9/25/2014
CCC
43
9/28/2014
CCC
FQIRENARDET/252
44
9/28/2014
CCC
FQIRENARDET/253
45
9/29/2014
CCC
46
9/30/2014
CCC
47
9/30/2014
CCC
48
9/30/2014
CCC
Approved
34
FQIRENARDET/254
FQIRENARDET/255
9/15/2014
9/25/2014
REN/FQI/CCC
/188
9/25/2014
Approved as
Noted
9/29/2014
Approved as
Noted
9/25/2014
Approved as
Noted
9/24/2014
9/22/2014
9/25/2014
REN/FQI/CCC
/187
REN/FQI/CCC
/186
Approved
Page 37
Page 38
Page 39
Page 40
Page 41
Page 42
Page 43
Page 44
Page 45
Page 46
Page 47