Sunteți pe pagina 1din 44

NED University of Engineering and Technology, Karachi

Civil Engineering Department

CE-545
Construction Claim Management

Term Paper
Claims in the Construction Industry of Pakistan Issues on the Contractor side and Recommendations
for Improvement

Prepared by:
Mr. Waleed Mazhar Kalhoro/CE-107

Course Instructor:
Prof. Rizwam Ul Haque Farooqui

Abstract

This study was carried out to highlight the issues faced by contractors in Pakistani
construction industry and recommend plausible solution for such. In this study it was found
that there are three major that prevails in Pakistani Construction industry. They are poor and
insufficient documentation, secondly concerned individual with innate knowledge of site
work play mere or no part in generating claims and lastly communication barrier stalls the
claim management pace and entail huge cost. Therefore its recommended that step for
better site work documentation, encouraging concerned people to play their part in claim
preparation and better communication amid Contractors and Engineers should be taken to
scrap of such issues in Pakistani construction industry.

ii

TABLE OF CONTENTS
TITLE PAGE
ABSTRACT
TABLE OF CONTENTS

i
ii
iii

Chapter 1: Introduction
1.1 Scope
1.2 Objective
1.3 Methodology
1.4 Limits and Exclusions
1.5 Term Paper Timeline

1-2
1
1
1
1
2

Chapter 2: Literature Review


2.1 Introduction
2.2 Issues amid Claims
2.2.1 Record keeping and Documentation
2.2.2 Contract Knowledge
2.2.3 Change Orders
2.2.4 Planning and Schedules
2.2.5 Future relations concerns
2.3 Claim Management
2.3.1 Record Keeping and Documentation
2.3.2 Notification of Change
2.3.3 Contract
2.3.4 Planning and Schedules
2.3.5 Proactive Action

3-12
3-4
4-7
4-5
5
6-7
7
7
8-12
8-9
9
9-10
10-11
11-12

Chapter 3: Methodology
3.1 Record keeping
3.2 Change Order
3.3 Contract Knowledge
3.4 Claim Preparation

12-15
12-13
13-14
14
14-15

Chapter 4: Data Analysis


4.1 Mean
4.2 Standard Deviation
4.3 Importance Index

15-16
15
15-16
16

Chapter 5: Results and Discussion


5.1 Record keeping
5.2 Extent of use of project documentation
5.3 Change Order
5.4 Contract Knowledge
5.5 Claims Preparation
5.5.1 Responsibility of Claim preparation
5.5.2 Time Involved in preparing Claim
5.5.3. Cost of preparing claim
5.5.4 Reasons for Delay in Claim preparation

17-24
17-18
18-19
19-21
21-22
22-24
22
22-23
23
24

Chapter 6: Conclusion and Recommendations

24-25

APPENDIX A
APPENDIX B
REFERENCES

26-30
31-40
41

iii

Claims in the Construction Industry of Pakistan

1. Term Paper Introduction


1.1 Project Scope
Identifying the reasons behind claim generation and its respective preparation issues
from Contractors perspective in Pakistan construction industry.
1.2 Objective
In the study we will identify reasons incurred by Pakistani contractor for claim
generation and simultaneously study the issues that lingers contractors in the midst of
claim preparation.
1.3 Methodology
1. Firstly Literature Review will be carried out to identify skill and attributes.
2. A questionnaire will be developed, and response will be sought from contractors
3. Statistical analysis will follow to evaluate respondents response; coherence will be
evaluated and key issues will be highlighted.
4. Conclusion will be drawn as per analysis.
5. Recommendation will cease the term paper.
1.4 Limits and Exclusion

Study will be limited to Contractor working within Karachi only.

Statistical analysis will include Mean, Standard Deviation, and Importance Index.

Claims in the Construction Industry of Pakistan

1.5 Plausible Table of Content


The chronology of Content can be estimated as follow
1. Abstract
2. Literature Review
3. Methodology
4. Result Compilation/Statistical Analysis
5. Analysis and Discussion
6. Conclusion
1.6 Term Paper Time Line

2
Exhibit 1Term Paper Timeline

Claims in the Construction Industry of Pakistan

2. Literature Review
2.1 Introduction
The term "construction claim" is commonly referred as any application by the contractor
for payment that arises other than under the ordinary contract payment procedures.
Potential of claims rises when the contractor incurs additional costs and/or there is a delay
amid his contract. The clam is an instrument used by contractors to request more time
and/or money. Claims can also originate with the owner and are defined as the assertion
of right to payment arising under the contract for neglect or delay on the part of the
contractor (Jergeas & Hartman, 1994).
Claims may arise during a construction project from numerous reasons. Such reason
include: (Jergeas & Hartman, 1994)

Increase in scope of work pertaining to changes, extras and errors.

Insufficient bid information

Faulty and/or late owner-supplied equipment and material

Inferior quality of drawings and/or specifications, giving rise to ambiguities in contract


requirements.

Insufficient time for bid preparation

Stop-and-go operations because of lack of coordination, design information,


equipment, or material

Work in congested areas and overcrowding

Acceleration to regain schedule

Inadequate investigation before bidding


3

Claims in the Construction Industry of Pakistan

Unbalanced bidding and underestimation.

Authors Dickmann and Nelson have found that the most common causes for a contract
claim are design changes and errors. A comprehensive analysis of claims indicates that 46%
resulted from design errors. An additional 26% were due to either discretionary or
mandatory changes. Thus 72% of all contract claims can be traced to design changes, extra
work, and errors (Jergeas & Hartman, 1994).
Contractors normally adopt a claims-conscious attitude and utilize claims as a profit center
(Hassanein & El Nemr, 2008).
2.2 Issues amid Claims
2.2.1

Record Keeping and Documentation

Contractors generally fail to protect their contractual position in the case of a claim. This
situation arises from failure to completely understand and actively manage the contract,
or failure to keep proper records (Jergeas & Hartman, 1994).
Maintain proper job records on a timely manner including time sheets, diary records,
reports, photographs, records of labors and weather and its effect on progress, progress
of the construction, site instructions, etc. (Zaneldin, 2006).
Proper documentation is imperative for Contractor as they eventually allow them to justify
and quantify requests for adjustment to the contract price and/or duration. Generally it
has been observed that most Contractors dislike paperwork an attitude easily
understood, but difficult to defend in litigation or arbitration. Notice provisions in
contracts are often neglected, extra work is routinely performed without written
authorization (on a limited scale), change orders are not qualified, erroneous or biased
4

Claims in the Construction Industry of Pakistan

minutes of site meetings are not objected to, self-serving letters are left unanswered,
written notes of important telephone conversations or verbal instructions are rarely
maintained, and contractual defaults by the owner are not documented or confirmed by
letter. (Jergeas & Hartman, 1994).
In a research conducted in the UK concerning the reasons for consultants' rejection of
contractors' claims, one of the main causes were poor information systems and
documentation practices by contractors (Vidogah & Ndekugri, 1997).
A cultural factor has been identified as a possible cause for the lack of notification and
documentation in construction sector, namely the "fear of consultant phenomenon"
(Hassanein & El Nemr, 2008).
2.2.2

Contract Knowledge

All too often contractors do not read the contract document before bidding and, in many
instances, not even when they execute the document. Its imperative that contractors'
site superintendent should fully review the contract documents and compare them with
those that were bid; (Jergeas & Hartman, 1994).
A significant number of contractors do not quote a contract clause when preparing a claim
(Hassanein & El Nemr, 2008)
In the event of ambiguity, the courts of most jurisdictions will decide against the author
of a contract, this was assumed to stem form their lack of knowledge with contract and
its relevant clauses (Hassanein & El Nemr, 2008).

Claims in the Construction Industry of Pakistan

2.2.3

Change Orders

Change order claims constitute the majority of claims in the industrial sector, as they
represent approximately 54 percent of the total number of claims (Hassanein & El Nemr,
2008).
Site supervisors should not develop the habit of waiving claim rights by negotiating and
signing off on change orders that pay part of the extra costs. If the site superintendent
cannot assess in detail the aforementioned impact costs at the time of issue, contractors
must consider indicating that the change only covers the direct costs incurred in
performing the work and should formally preserve their right to recover other costs
associated with the added work at a later date (Jergeas & Hartman, 1994).
Have signed change orders before starting doing these changes on site (Zaneldin, 2006).
Oral change order have to contractual weight (Hassanein & El Nemr, 2008). The
relationship between oral change orders and documentation is that frequent verbal
instructions with no supporting documentation bar the contractor from recovering the
associated incurred expenses (Hassanein & El Nemr, 2008).
Two Canadian construction lawyers advise contractors to include the following two
qualifications in the change-order quotation to preserve the contractor's right to bring the
impact claim of the cumulative effect of change orders later (Jergeas & Hartman, 1994):
'We hereby reserve all our rights to claim subsequently for the costs, of any nature
whatsoever, other than direct costs, associated with the performance of this extra work
and the delays which may result. (Blaikie 1986)

Claims in the Construction Industry of Pakistan

"The above price does not include any impact or delay costs that may result from this
change in the work or from the cumulative effect of this and other changes, and the right
to claim such costs is hereby reserved." (Kenny 1990).
2.2.4

Planning and Schedules

Finishing a project on schedule is a difficult task to accomplish in the uncertain, complex,


multiparty, and dynamic environment of construction projects (Zaneldin, 2006)
Planning is pivotal amid project, and must be based on clearly defined objectives. With
proper planning, adequate resources are timely available, adequate time is allowed for
each activity. Planning and scheduling should be cost effective, simple, and practical
(Jergeas & Hartman, 1994).
Scheduling techniques range from simple hand-drawn bar charts to computerized
network analysis. The most suitable presentation of schedules for contractors is the bar
chart, which should be based on the critical path method (CPM) (Jergeas & Hartman,
1994).
2.2.5

Future relation concerns

Contractors sometimes waive their contractual rights due to fear of bruising their business
relations with the owners and consultants, which could affect their chances as candidates
for future potential projects (Hassanein & El Nemr, 2008). Fear of losing bargaining power
of the Client and the Engineers, were highlighted as limits of the external environment
(Klee, 2013).

Claims in the Construction Industry of Pakistan

2.3 Claim Management


1. Record Keeping and Documentation
Records and documentation play a very important role in the settlement of contract claims
(Chovichien, n.d.). "The paperwork" is an important part of project management and
claims have to be solved in formal way (Klee, 2013).
Contractors must establish and maintain a good record-keeping system that documents
job progress and problems as they occur. Such a record system should monitor cost, time,
scope, and quality. Daily-progress reports should be kept and should indicate the date,
weather and temperature, type of work in progress and quantities produced, and
hindrance to job progress and by whom. Photographs and video films (in cases where not
prevented by contract documents) should be taken on a routine basis (dated and with
commentary) to show construction progress, site conditions, and particular problems
encountered (Jergeas & Hartman, 1994).
One of the most important tools for proper documentation management is the use of
daily records from the site team, particularly if these documents were signed by the
consultant (Hassanein & El Nemr, 2008).
Record should be maintained in form of memoranda pertaining to conversations,
inspections, directions, or observations. Further records of correspondence between
parties to the contract; minutes of weekly job-site meetings and other meetings; notes of
telephone conversations, progress-billing certificates and all data submitted to support
such requests; cost and productivity reports; delivery reports of owner-supplied material
and equipment; diaries; job schedules (periodically updated); transmittals; drawings and
8

Claims in the Construction Industry of Pakistan

specifications; shop drawings; vendors' drawings and specifications; change orders and
associated documentation; inspection reports; and accident and site safety reports
(Jergeas & Hartman, 1994).
Another form of record management is that of information technology system within the
organization. Electronic document management systems allow information stored in
different forms to be linked and accessed in a flexible manner (Vidogah & Ndekugri, 1997).
It is recommended that contract awareness should not be restricted to high-level site
management, but should be directed to site engineers directly dealing with the consultant
or owner's representative (Hassanein & El Nemr, 2008).
2. Notification of Change
Construction claim notification involves alerting the other party a potential problem in a
manner that is non-adverserial. Time limit requirements are very crucial and critical
(Chovichien, n.d.). An initial letter of a claim notice to the other should be concise, clear,
simple, conciliatory, and cooperative. It should indicate the problem and alert the other
party of the potential increase in time or cost (Kululanga, et al., 2001)
3. Contract
Articles in the section of the contract entitled "General Conditions" dealing with the
following matters should be considered to ensure the contract is complete with respect
to the terms and conditions to have a dispute mechanism (Jergeas & Hartman, 1994):
a. Changes/extras
b. Disputes
c. Disclaimer
9

Claims in the Construction Industry of Pakistan

d. Authority/roles/definitions
e. Soil/sit conditions
f. Delay
g. Payment
h. Notice provisions.
To enhance the chances of success, contractors submitting claims must closely follow the
steps stipulated in the contract conditions, provide a breakdown of alleged additional
costs and time, and present sufficient documentation (Zaneldin, 2006).
Clauses regarding the requirements for documenting minutes of meetings as well as
exchanged correspondence should be included in contracts. In case of either party's
failure to fulfill such contract requirements, it should be clearly stated that the party at
fault must waive its right regarding the matter in request (Hassanein & El Nemr, 2008).
Have a clearly written contract with no ambiguity, read the contract several times before
signing it, to understand any unclear clauses, its advised that a third party should be asked
to read contract documents before the bidding stage. Use special contracting provisions
and practices that have been used on past projects, which proved to be successful in
avoiding and resolving disputes during construction (Zaneldin, 2006).
4. Planning and Schedules
The regular updates and issuance of the schedule to the owner is a very effective
communication tool and is generally considered to satisfy the legal requirements for
providing notice of problems and associated delays (Jergeas & Hartman, 1994).

10

Claims in the Construction Industry of Pakistan

The schedule can be used to determine the impact of changes to the plan and to establish
a cause-and-effect relationship in a claim situation, i.e. the impact of delays, reduced or
increased resources, scope changes, resequencing and other workflow changes to current
activities (Jergeas & Hartman, 1994).
5. Proactive Action
Contractors' site supervisors and project managers should consider the following
proactive steps to protect contractors' interests and reduce liability (Jergeas & Hartman,
1994):
1. Request appropriate extension of time whenever significant events occur which may
entitle you to an extension of time and make it clear who pays for the costs of
extended duration.
2. Make it clear who pays for acceleration.
3. Respond as quickly as possible to every complaint initiated by the owner.
4. Analyze job progress in detail prior to any job-site-progress meetings that are held.
Such meetings should be used as a forum for discussing and notifying potential or
current delays, extra work, etc.
5. Record in detail all delays and man-hours lost, conflicts, and discrepancies. Inform the
owner when delays occur so that the contractor does not incur responsibility due to
lack of information.
6. Carefully read all correspondence and minutes of meetings and promptly record any
disagreements you may have with them.

11

Claims in the Construction Industry of Pakistan

7. Obtain written confirmation of all oral directives issued by the owner or engineer. If
they do not confirm in writing, the contractor should write a confirmation letter to
them.
8. Forward any significant information received from or sent to the owner to senior
management so that they can keep current with the project and determine if further
specific activity is required
9. Wait for authorization before proceeding with changes and extras. Without proper
directive to do such work, contractors will typically be deemed to be a volunteer in the
performance of the extra work and may not be paid.
10. Qualify the basis of, and limitations to, the pricing of your change.
Gregorc and Weiner (2009) mention that within a project of certain value there should be
a resident Claim Manager on the project team. This specialist would be responsible for CM
(Klee, 2013).
3. Methodology
3.1 Record Keeping
To ascertain proper paperwork amid construction endeavor, we asked whether they had
defined, isolated and tangible procedure of maintaining site paperwork.
In order to evaluate contractor keenness in timely maintenance of daily reports and other
related paper works pertaining to site works, we asked them to rate their answer on scale
of 1-4, with 1-never, 2-sometimes, 3-mostly and 4-always
In order to evaluate the extent of how many time contractors did lose their claim (given
any claim was ever filled) or faced difficulties in defending their claims in litigation,
12

Claims in the Construction Industry of Pakistan

pertaining to insufficient data provided at their end, we asked contractor to rate such
instance on a Likert scale of 1-5. Where 1-Always, 2-mostly lost/ faced difficulties, 3-Never
filled any claim, 4-few times lost/faced difficulties and 5-Never.
Further we inquired of contractor of any electronic document management system
(EDMS) or any software of same essence.
Lastly contractor were asked to rate extent of use of Project documentation while
preparing claim, for this reason 12 different documents were rated on a scale of 1-4, with
1-never used, 2-sometime used, 3-moderatly used and 4-always used.
3.2 Change Orders
In order to evaluate the frequency of change order received from client, we asked
contractor to rate the extent of such frequency on scale of 1-4, where 1-never received, 2sometimes received, 3-most of times, 4-all the times.
Contactor were also asked whether they used to issue notification before commencing
work on change order, oral change order or any other change exercised.
We also inquired contractors of any oral change order and their respective frequency,
similarly the responses were rated on scale of 1-4, with 1-never received, 2-sometimes
received, 3-most of times, 4-all the times.
Further we evaluated the extent to which contractor succeeded in defending such oral
change amid claims, similarly the responses were rate on a scale of 1-4, with 1-never
defended, 2-sometimes defended, 3-most of times defended and 4-always defended.

13

Claims in the Construction Industry of Pakistan

Were there any occasions where contractor waived it right by signing of change order
without explicitly mentioning cost and time repercussion, for such we asked contactors in
affirmation or negation.
3.3 Contract Knowledge
We asked contractors to rate the extent to which they study and analyze bidding
documents. Reponses were evaluated on percentage of document studied, i.e. 0-30%, 30%50%, 50%-80% and 80%-100%.
In order to evaluate the contractors knowledge pertaining to bidding documents, we
asked them whether they had included the claim clause when filing such claims.
3.4 Claim Preparation
The preparation and evaluation of claims require some effort and skill on the part of the
contractor. Naturally the level of skill and experience applied to the claims management
function can determine the success or failure of the claim (Vidogah & Ndekugri, 1997).
In order to evaluate the extent to which different entities of contractors involved during
claim management, we asked contractor to rate the involvement of each professional on
a Likert scale of 1-5.
Where 1-no involvement, 2-meagre involvement, 3-no concerned, 4-moderate
involvement and 5-total involvement
Preparation of claims is a tedious process. For such reason contractors tend to leave claims
until project completion (Vidogah & Ndekugri, 1997). With that in mind contractors were
asked to rate eight aspects of the claims preparation process in term of time involved,

14

Claims in the Construction Industry of Pakistan

responses were evaluated on a scale of 1-4, with 1-readily available 2-minimum time
required, 3-moderate amount of time, 4-huge amount of time.
Further contractor were asked to rate the cost incurred pertaining to acquisition of
different information, for that reason similar 8 aspect were rated on scale of 1-4, with 1very cheap, 2-meagre cost 3-substantial cost 4-very costly.
Reason for delay amid claim preparation were also evaluated, for this reason 10 reason
were rated on a scale of 1-4, with 1-not responsible, 2-mere responsible, 3-moderately
responsible and 4-very much responsible.
4. Data Analysis
Statistical analysis included Mean, Standard Deviation, and Importance Index.
4.1 Mean
Mean ranking (where applicable) was calculated for each case, using following expression.
Calculation of mean was of prime importance in calculating importance index, which
would ultimately rank particular options under various heads.
=
Where;
ai= Rank by each respondent.
4.2 Standard Deviation
Standard Deviation evaluates the extent of variation or dispersion from the average.
Following expression is used for the purpose
=

[( ) ]

15

Claims in the Construction Industry of Pakistan

Where
= Standard Deviation
= mean
X = Individual Rank by respondents.
4.3 Importance Index
Information incurred from respondent was used to develop an Importance Index (II). In
calculating Importance Index (II) mean and standard deviation were calculated. Numerical
score of each option from various heads were converted into relative importance index to
assess the relative ranking.
The importance index will be calculated using following calculation

, (0

1)

Where
w=

average weighting given to each factor by the respondent, in our

different heads were evaluated on scale of 1-5, and 1-4, for case where scale was 1-5, 1
being least respective rank 5 being most respective rank, similar is the case for scale of
1-4 scale.
A=

the highest weighting; and

N=

the total number of respondents

16

Claims in the Construction Industry of Pakistan

5. Results and Discussion


5.1 Record Keeping
As part of my research I intended to know to what extent, contractors austerely maintain
daily reports and other paperwork related to site work, upon research it was found out
that 47% of contractors never or sometimes

TIMELY_MAINTAIN

maintain such documents. In the absence of


any

tangible,

concrete

and

Never
12%
Always
35%

timely

Sometim
es
35%

maintained data indigenous to site, this fact


could be established with certainty that any

Mostly
18%

resulting efforts will prove to be tedious and


in worst case scenario futile to defend contractors claim. However this condition is
balanced , but such condition cant be classified as promising because basic site paperwork
are essential and pivotal when it comes to claims, especially in Contractors perspective.
In continuum with previous discussion, Contractors were also inquired about instances
where they failed to defend their claim pertaining to insufficient data, the results
advocates for previous discussion. The

INSUFFICIENT DATA
biggest number amid this paradigm is where
Few
Always
times
Lost
lost/face
12% Mostly
d
Lost/face
difficultie
d
s
difficultie
29%
s
Never
24%
filled a
claim
35%

contractors never filed a claim, this situation


could be traced back to our previous
discussion where almost half of time
contactors

dont

maintain

timely

site

paperwork, and in such situation where


17

Claims in the Construction Industry of Pakistan

contractor lack the prove, filling a claim would be adding insult to injury. Upon research
36% of Contractor always lost or mostly faced difficulties proving their claim, such situation
is another testament to previous discussion. Holistically speaking its a 70-30 ratio where
contractor lost or faced difficulties amid proving their claim.
Lastly we inquired is there were any

EDMS
Electronic Document Management System
Yes
18%

or any sort prevalent amid contractors, and


results were no different than previous
situation, 82% of the contractors asked,
answered in negation of any EDM system

No
82%

prevailing in their company, with so much


complexity and huge quantum of information, contractor should seek an EDM system to
timely and prudently maintain there documentation, which could yield favorable
outcomes for them and even result in profitability.
5.2 Extent of use of project documentation
One needs tangible data to substantiate it claims. Therefore in order to substantiate their
claim contractors were asked to rate the extent of usage of particular project
documentation. Results indicate that revised drawings, conditions of contract and
specifications are most intensely used documentation. It is fair to say all these
documentation are drafted during the phase where conflicts are minimal or absent, such
documents are based on assumption and by the book, referring such documents while
preparing a claim will not be wise decision, because any claim that arises is because of the
18

Claims in the Construction Industry of Pakistan

disparity amid whats written and whats been done, and since youre not using any
documents to highlight the second part which whats been done, you cant balance the
situation and resultantly will face backlash when preparing and defending a claim. Results
show that contractors merely used site diaries and minutes of site meeting to substantiate
their claims, and such information is most useful in defending what actually happened on
site.
Document
Importance Index Rank
Bill of quantity
0.779
4
Claim documentation
0.691
10
Minutes of Site meetings
0.721
10
Schedules
0.750
7
Photographs
0.765
6
Site Diaries
0.691
10
Conditions of Contract
0.853
2
Correspondence
0.779
4
Daily Diaries
0.662
12
Records of Delay and Disturbance
0.721
8
Specification
0.794
3
Revised Drawings
0.912
1

5.3 Change Orders


Change

order

are

integral

part

of

construction business, there is hardly a


project where contractors dont taste the
medicine of change order. Upon research
94% of contractors received a change order
differing

in

frequency.

Such

fact

19

CHANGE_ORDER
Never
received
All the
6%
times
received
24%
sometim
Most of
the times
received
23%

es
received
47%

Claims in the Construction Industry of Pakistan

adamants that there is a dire need to establish a protocol where contractors are at better
place to defend any discrepancies resulting from change orders.
Another nightmare for contractors are Oral Change orders, there frequency is no more
different or should I say more than formal

OCO_RECEIVED

change orders. It is evident that there was no


contractor who did not received an oral
change order, all contractors asked, did
received an oral change order with differing
frequencies. Further we also enquired to

All the
times
received
30%

sometim
es
received
35%

Most of
the times
received
35%

what extent were such change orders defended successfully, results depicts that 88% of
contractor never or sometimes defended their oral change orders. 29% of never defending
oral change order is quite evident and self-explanatory however 59% of contractors stating
that they sometimes succeed in defending their change oral change order, was further
enquired and they stated that only payments

OCO_DEFENDED
were reimbursed on the basis on quantum
Most of
the times
Never
defended
defended
12%
29%
sometim
esdefend
ed
59%

majeure. Thus its imperative that contractors


should seek a formal change order, however
pertaining to local hiccups contractor cant
afford such a luxury pertaining to social and
time issues.

20

Claims in the Construction Industry of Pakistan

Further contractor were asked, were there any

WAIVING_CLAUSE

occasions where they waived their right by


signing of change order without explicitly

Yes
24%

mentioning cost and time repercussion, results


are promising with 76% of contractors answering
No
76%

in negation.
5.4 Contract Knowledge

Studying bidding documents is tedious yet imperative job, upon research this fact was
established that 47% of Contractors study about

BID STUDYING
50% of the bidding documents, with 12% on
80%100%
24%

0%-30%
12%

documents such dismal study of bid documents


30%-50%
35%

50%-80%
29%

contractors only studying 0-30% of bidding

from substantial amount of contractors is


alarming

and

astonishing,

such

inferior

information of bidding document lead contractors


into Claim dilemma. Again relevant situation is
balanced, but balanced is not an option here

CLAIM CLAUSE
ADDITION

contract bid documents are core document and


every other contemporary document finds its
foundation on bid documents, therefore
contractors must show resolve on studying bids
21

NO
35%
Yes
65%

Claims in the Construction Industry of Pakistan

documents to their fullest. Also 65% of contractors add a claim clause when preparing a claim,
and 35% dont. Such number should be higher.
5.5 Claim Preparation
5.5.1

Responsibility of Claim preparation

Contractors rated different entities amid contractors on the extent to which they play a part
in preparing a claim. Results indicates that claim managers and project manager are the most
enthusiast in preparing a claim, while site engineer is least involved in preparing a claim.
Project Manager even though heads the project, but he doesnt have any firsthand
information of site work similar is the case with Claim Manager, he is completely alien to site
work, still they are mostly involved in preparing a claim, on the other hand site engineer who
has firsthand and indigenous information pertain to site work is least used when preparing a
claim, such a situation is self-explanatory where most suited individual is absent in the process
of claim preparation and individuals with merge and alien knowledge are most enthusiast
while preparing a claim.
Staff
Importance Index Rank
Project Manager
0.282
2
Project Quantity Surveyor
0.211
5
Head Office-based Quantity Surveyor
0.236
3
Site Engineer
0.166
7
Claim Manager
0.283
1
External Claim Consultants
0.186
6
Others
0.236
3

5.5.2

Time Involved in preparing Claim

Time is of essence, so is the case while preparing a claim. Contractors were asked to rate the
extent of time involved in preparing claim. Results indicate that most time consuming aspect
22

Claims in the Construction Industry of Pakistan

of preparing claim are responses to architect/Engineers request for information and


quantifying claim, indicating lack of timely correspondence amid engineer and contractor and
also lack of specific knowledge of quantifying claim. Interpretation of contract took the least
amount of time, referring to innate knowledge contractors possess about contract.
Aspect of Claim preparation
Importance Index Rank
Identifying relevant information
0.721
6
Identifying sources of information
0.779
3
Retrieving relevant information
0.706
7
Archiving relevant information
0.725
5
Interpretation of contract and justifying claim
0.686
8
Responses to architect/engineers request for information
0.804
2
Quantifying claims
0.824
1
Prepare claim documentation for claims
0.745
4
5.5.3 Cost of preparing Claim
Cost is something that imparts everybody and money is something that everybody holds most
dear. For that reason contractors were asked to indicate which aspects of claim preparation
entails the most cost. Results depicts that quantifying claim and responses to
architect/Engineers request for information are the most costly and preparing
documentation for presentation are cheapest. Such result are coherent with above
discussion, things taking the most time, are the things requiring the most capital while
preparing a claim.
Aspect of Claim preparation
Importance Index Rank
Identifying relevant information
0.647
5
Identifying sources of information
0.603
6
Retrieving relevant information
0.691
3
Archiving relevant information
0.691
3
Interpretation of contract and justifying claim
0.603
6
Responses to architect/engineers request for information
0.706
2
Quantifying claims
0.721
1
Prepare claim documentation for claims
0.544
8

23

Claims in the Construction Industry of Pakistan

5.5.4

Reasons for Delay in Claim Preparation

Analysis shows that most responsible reasons for delays are awaiting responses from
architect/engineer, poor records and lack of contemporary records, in that order.
Reason for delay in preparing claim
Importance Index
Lack of resources
0.676
Showing cause and effect
0.721
Lack of contemporary records
0.765
Poor records
0.809
Identifying and retrieving information
0.765
Awaiting responses from architect/engineer
0.868
Time limitations
0.706
Others
0.544

Rank
7
5
3
2
3
1
6
8

6. Conclusion and Recommendation


During the course of research, this fact could be established with certainty that
contractors have issues pertaining to claims and their respective management, however
the essence of issues of point of debate. Some issues are inherent to construction industry
in Pakistan, yet some issues could be rectified with proper and austere efforts. Upon
research it was found that contractor faced three essential issues concerning claim
management;
1. Poor or no documentation of site work, only documentation would not suffice here,
real issue is their timely maintenance.
2. Lack of communication amid Engineer/Architect and Contractor, once again timely
communication is imperative.
3. Lastly concerned individuals are not enthusiastically while preparing claim for instance
in our research Project Managers and Claim Manager were intensely involved in

24

Claims in the Construction Industry of Pakistan

preparing claims and site engineer , individual with indigenous knowledge of site is
least involved.
Therefore its recommended that issues highlighted above should be catered for with
following recommendation is curbing such issues. In order to eradicate the ever
lingering menace of poor and insufficient documentation, contractors should establish
a program that should motivate concerned individuals to maintain austere site
documentation. An EDM system could aide in this regard as Contraction Industry is on
the road of spurt and complexity.
Further, concerned individuals should be allowed to play their pivotal part while
preparing claim, as they possess first hand and innate knowledge pertaining to site
work. Lastly more efficient way of communication should be established amid
Contractors and Engineers, and if necessary such communication should be bound by
some contractual provisions, violation of such should be punishable by law.

25

Claims in the Construction Industry of Pakistan

Appendix A

Claims in the Construction Industry of Pakistan Issues on the


Contractor side and Recommendations for Improvement
In the study we will identify reasons incurred by Pakistani contractor for claim generation and simultaneously study the
issues that lingers contractors in the midst of claim preparation.
Name
Designation
Company
Current Project

Record Keeping
Do you timely maintain daily reports and other related paper works pertaining to site works

o Never

o Sometimes

o Mostly

o Always

On how many instances you lost or faced difficulties to defend your claim for insufficient data provided?

o Always Lost

o Mostly lost/faced

o Never filed a

difficulties

claims

o Few times
lost/faced
difficulties

o Never lost

Is there a prevalent electronic document management system or any sort in your organization?

o Yes

o No

Rate the extent to which following project documentation were used while preparing claim
1.

Bills of Quantity

o Never used
2.

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

Site diaries

o Never used
7.

o Moderately used

Photographs

o Never used
6.

o Sometimes used

Schedules

o Never used
5.

o Always used

Minutes of Site meeting

o Never used
4.

o Moderately used

Claim Documentation

o Never used
3.

o Sometimes used

Conditions of Contract

o Never used

26

Claims in the Construction Industry of Pakistan


8.

Correspondence

o Never used
9.

Appendix A

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

o Sometimes used

o Moderately used

o Always used

Daily diaries

o Never used

10. Records of Delay and disturbance

o Never used
11. Specification

o Never used
12. Revised Drawings

o Never used
Change Orders

State the extent of frequency of Change Orders received from Owner/Engineer

o Never received

o Sometimes received

o Most of the times

o All the time

State the extent of frequency of Oral Change Orders received from Owner/Engineer

o Never received

o Sometimes received

o Most of the times

o All the time

How many times were you able to defend such oral change orders during claims?

o Never defended

o Sometimes

Most of the times


Always defended
defended
Were there any occasions where you as a contractor waived your right by signing of change order without explicitly
mentioning cost and time repercussion?

o Yes

o No

Contract Knowledge
Rate the extent to which you thoroughly study bidding documents

o 0-30%

o 30%-50

o 50%-80%

Do you add claim clause from the contract when filing a claim?

o No

o Yes

27

o 80%-100%.

Claims in the Construction Industry of Pakistan

Appendix A

Claim Preparation
Rate the extent of involvement of following entities of contractors involved during claim preparation.
Project Manager

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Project Quantity Surveyor

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Head office based quantity surveyor

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Site Engineer

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Claim Manager

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

External Claim Consultants

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Others Involved

o No
Involvement

o Meagre
Involvement

o Not

o Moderate

Concerned

o Total

Involvement

involvement

Rate the flowing eight aspects of the claims preparation processes in term of time involved
1.

Identifying relevant information

o Readily available
2.

o Moderate time

required
Identifying sources of information

o Readily available
3.

o Minimum time

required

o Minimum time

o Moderate time

required
Retrieving relevant information

required

28

o Huge amount of
time required

o Huge amount of
time required

Claims in the Construction Industry of Pakistan

o Readily available

Appendix A

o Minimum time

o Moderate time

required
4.

o Moderate time required


o Moderate time required

o Huge amount of time required

o Moderate time required

o Huge amount of time required

o Huge amount of time required

o Moderate time required

o Huge amount of time required

Quantifying claims

o Minimum time required


8.

o Huge amount of time required

Responses to architect/engineers request for information

o Minimum time required


7.

time required

Interpretation of contract and justifying claim

o Minimum time required


6.

o Huge amount of

Archiving relevant information

o Minimum time required


5.

required

Moderate time required


Prepare claim documents for presentation

o Minimum time required

Rate the cost incurred pertaining to acquisition of different information to prepare claim
Identifying relevant information

o Very cheap

o Meagre cost

o Substantial cost

o Very costly

o Meagre cost

o Substantial cost

o Very costly

o Meagre cost

o Substantial cost

o Very costly

o Meagre cost

o Substantial cost

o Very costly

o Substantial cost

o Very costly

o Meagre cost

o Substantial cost

o Very costly

o Meagre cost

o Substantial cost

o Very costly

o Substantial cost

o Very costly

Identifying sources of information

o Very cheap
Retrieving relevant information

o Very cheap
Archiving relevant information

o Very cheap

Interpretation of contract and justifying claim

o Very cheap

o Meagre cost

Responses to architect/engineers request for information

o Very cheap
Quantifying claims

o Very cheap

Prepare claim documents for presentation

o Very cheap

o Meagre cost
29

Claims in the Construction Industry of Pakistan

Appendix A

Rate the following 10 reason for delay in claim preparation


Lack of resources

o Not responsible

o Mere responsible

o Moderately

o Mere responsible

o Moderately

o Mere responsible

o Moderately

o Mere responsible

o Moderately

responsible

o Very much
responsible

Showing cause and effect

o Not responsible

responsible

o Very much
responsible

Lack of contemporary records

o Not responsible

responsible

o Very much
responsible

Poor records

o Not responsible

responsible

o Very much
responsible

Identifying and retrieving information

o Not responsible

o Moderately

o Mere responsible

responsible

o Very much
responsible

Awaiting responses from architect/engineer

o Not responsible

o Mere responsible

o Moderately

o Mere responsible

o Moderately

o Mere responsible

o Moderately

responsible

o Very much
responsible

Time limitations

o Not responsible

responsible

o Very much
responsible

Other

o Not responsible

responsible

30

o Very much
responsible

Claims in the Construction Industry of Pakistan

Appendix B

Respondents (Contractors) Response Compilation


Timely
maintain

Always

Sometimes

Always

Sometimes

Never

Always

Always

Mostly

Sometimes

10

Always

11

Sometimes

12

Sometimes

13

Mostly

14

Never

15

Mostly

Insufficient
data
Few times
lost/faced
difficulties
Mostly
Lost/faced
difficulties
Never filled
a claim
Never filled
a claim
Always
Lost
Never filled
a claim
Few times
lost/faced
difficulties
Few times
lost/faced
difficulties
Mostly
Lost/faced
difficulties
Never filled
a claim
Mostly
Lost/faced
difficulties
Never filled
a claim
Never filled
a claim
Mostly
Lost/faced
difficulties
Few times
lost/faced
difficulties

EDMS

BOQ

Claim
Documentation

Minutes
Site
Meeting

Schedules

Photographs

Site
Diaries

Contract
Condition

Correspondence

Daily
diaries

Delay
records

No

Always
used

Always used

Never Used

Always
used

Never Used

Sometimes
Used

Always used

Always used

Always
used

Sometimes
Used

No

Moderately
Used

Moderately
Used

Always
used

Always
used

Always used

Sometimes
Used

Always used

Moderately
Used

Sometimes
Used

Always
used

Moderately
Used
Sometimes
Used
Never
Used
Always
used

Sometimes
Used
Moderately
Used
Sometimes
Used

Moderately
Used
Sometimes
Used
Moderately
Used
Sometimes
Used

Moderately
Used
Sometimes
Used
Sometimes
Used
Always
used

Always used

Always used

Moderately
Used
Moderately
Used

Moderately
Used
Moderately
Used

Always used

Always used

Moderately
Used
Sometimes
Used
Never
Used
Sometimes
Used

Moderately
Used
Sometimes
Used
Never
Used
Moderately
Used

No
No
No
No

Always used

Always used
Sometimes
Used
Sometimes
Used
Always used

Always
used
Always
used
Sometimes
Used
Sometimes
Used

Yes

Moderately
Used

Always used

Always
used

Always
used

Always used

Always
used

Always used

Always used

Always
used

Always
used

Yes

Sometimes
Used

Moderately
Used

Always
used

Moderately
Used

Always used

Sometimes
Used

Moderately
Used

Always used

Moderately
Used

Always
used

No

Always
used

Always used

Sometimes
Used

Sometimes
Used

Never Used

Sometimes
Used

Moderately
Used

Sometimes
Used

Sometimes
Used

Never
Used

No

Always
used

Never Used

Always
used

Always
used

Sometimes
Used

Sometimes
Used

Moderately
Used

Moderately
Used

Sometimes
Used

Always
used

No

Sometimes
Used

Sometimes
Used

Sometimes
Used

Sometimes
Used

Moderately
Used

Moderately
Used

Moderately
Used

Moderately
Used

Moderately
Used

Moderately
Used

Sometimes
Used
Always
used

Moderately
Used
Moderately
Used

Moderately
Used

Sometimes
Used
Always
used

Sometimes
Used
Moderately
Used

Never
Used
Moderately
Used

Moderately
Used
Always
used

No
Yes

Sometimes
Used
Moderately
Used

Never Used
Sometimes
Used

Always used

Never Used
Always used

No

Always
used

Never Used

Sometimes
Used

Never
Used

Always used

Sometimes
Used

Always used

Sometimes
Used

Sometimes
Used

Moderately
Used

No

Always
used

Moderately
Used

Always
used

Always
used

Always used

Moderately
Used

Always used

Always used

Moderately
Used

Moderately
Used

31

Claims in the Construction Industry of Pakistan

16

Always

17

Sometimes

Few times
lost/faced
difficulties
Always
Lost

Appendix B

No

Always
used

Always used

Always
used

Always
used

Always used

Always
used

Always used

Always used

Always
used

Always
used

No

Always
used

Always used

Sometimes
Used

Sometimes
Used

Sometimes
Used

Moderately
Used

Moderately
Used

Never Used

Always
used

Never
Used

Specification

Revised
drawing

Change
Order
All the
times
received

Always used

Always used

Moderately
Used

Always used

Always used

Always used

Sometimes
Used

Always used

Sometimes
Used

Sometimes
Used

Always used

Always used

Always used

Moderately
Used

Moderately
Used

Always used

sometimes
received

Sometimes
Used

Always used

All the
times
received

10

Always used

Moderately
Used

sometimes
received

11

Moderately
Used

Moderately
Used

12

Sometimes
Used

Always used

13

Sometimes
Used

Moderately
Used

sometimes
received
All the
times
received
Most of
the times
received
Never
received
Most of
the times
received
Most of
the times
received

Most of
the times
received
sometimes
received
sometimes
received

OCO
recieved
All the
times
received
All the
times
received

OCO
defened

CO
clause

Bidding
study

Clause
Claim

Project
Manager

Project
QC

Headoffice
QC

Site
engineer

Claim
Manager

Sometimes
defended

No

80%-100%

Yes

Moderate
Involvement

Total
Involvement

Meagre
Involvement

Total
Involvement

Meagre
Involvement

Sometimes
defended

No

80%-100%

Yes

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Total
Involvement

Total
Involvement

Most of the
times defended

Yes

30%-50%

NO

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Never
defended

No

30%-50%

NO

Meagre
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Meagre
Involvement

Sometimes
defended

No

0%-30%

Yes

No
Involvement

Moderate
Involvement

No
Involvement

Not
Concerned

Meagre
Involvement

Sometimes
defended

No

50%-80%

Yes

Total
Involvement

Total
Involvement

Total
Involvement

Moderate
Involvement

Total
Involvement

Sometimes
defended

No

50%-80%

Yes

Total
Involvement

Not
Concerned

Moderate
Involvement

Total
Involvement

Total
Involvement

Sometimes
defended

No

50%-80%

NO

Moderate
Involvement

Moderate
Involvement

Total
Involvement

Moderate
Involvement

Total
Involvement

Never
defended

No

0%-30%

Yes

Not
Concerned

Moderate
Involvement

Meagre
Involvement

Total
Involvement

Meagre
Involvement

Never
defended

No

50%-80%

NO

Not
Concerned

Meagre
Involvement

Moderate
Involvement

Meagre
Involvement

No
Involvement

sometimes
received

Most of the
times defended

Yes

30%-50%

Yes

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

sometimes
received
Most of
the times
received

Never
defended

No

30%-50%

NO

Not
Concerned

Moderate
Involvement

Meagre
Involvement

Total
Involvement

Moderate
Involvement

Sometimes
defended

Yes

30%-50%

Yes

Total
Involvement

Total
Involvement

Moderate
Involvement

Moderate
Involvement

Total
Involvement

sometimes
received
All the
times
received
sometimes
received
Most of
the times
received
Most of
the times
received
Most of
the times
received
All the
times
received
Most of
the times
received

32

Claims in the Construction Industry of Pakistan

14

Moderately
Used

Always used

15

Always used

Always used

16

Always used

Always used

17

Always used

Always used

Claim
Consultants

Others
involved

Moderate
Involvement

Not
Concerned

Total
Involvement

Meagre
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

No
Involvement

Meagre
Involvement

Not
Concerned

Meagre
Involvement

Moderate
Involvement

Total
Involvement

Moderate
Involvement

Not
Concerned

Not
Concerned

Total
Involvement

Not
Concerned

10

Moderate
Involvement

No
Involvement

11

Moderate
Involvement

Moderate
Involvement

sometimes
received
sometimes
received
sometimes
received
All the
times
received
Identify
info
moderate
time
required
moderate
time
required
minimum
time
required
huge
time
required
moderate
time
required
moderate
time
required
moderate
time
required
minimum
time
required
moderate
time
required
huge
time
required
moderate
time
required

Appendix B
Most of
the times
received
sometimes
received
sometimes
received
All the
times
received
Identify
sources
huge time
required
moderate
time
required
moderate
time
required
huge time
required
moderate
time
required
minimum
time
required
huge time
required
moderate
time
required
moderate
time
required
moderate
time
required
minimum
time
required

Sometimes
defended
Sometimes
defended
Sometimes
defended
Never
defended

Retrieve
info
huge
time
required
moderate
time
required
minimum
time
required
minimum
time
required
moderate
time
required
moderate
time
required
huge
time
required
minimum
time
required
moderate
time
required
moderate
time
required
moderate
time
required

Yes

30%-50%

NO

No

80%-100%

Yes

No

80%-100%

Yes

No

50%-80%

Yes

No
Involvement

No
Involvement

Moderate
Involvement

Moderate
Involvement

Moderate
Involvement

Total
Involvement
Not
Concerned

Total
Involvement
Moderate
Involvement

Moderate
Involvement
Moderate
Involvement

Moderate
Involvement
Total
Involvement

Total
Involvement
Moderate
Involvement

No
Involvement

Moderate
Involvement

Meagre
Involvement

Total
Involvement

Meagre
Involvement

Identify
info_1

Identify
sources_1

Retrieve
info_1

very cheap

very cheap

Substantial
cost

Substantial
cost

very costly

Substantial
cost

Substantial
cost

meagre cost

Substantial
cost

Substantial
cost

Substantial
cost

Substantial
cost

meagre
cost

meagre cost

Substantial
cost

meagre
cost

Substantial
cost

meagre
cost

huge time
required

Substantial
cost

Substantial
cost

Substantial
cost

Archiving
info
moderate
time
required

Interpretation
_contract

Architect
response

Claim
quantifying

minimum time
required

huge time
required

huge time
required

huge time
required

huge time
required

huge time
required

huge time
required

huge time
required

moderate time
required

moderate
time
required

moderate
time
required

moderate time
required

huge time
required

huge time
required

moderate time
required

moderate
time
required

huge time
required

huge time
required

huge time
required

huge time
required

minimum
time
required
moderate
time
required
moderate
time
required

huge time
required

huge time
required

moderate
time
required

huge time
required

huge time
required

Substantial
cost

meagre cost

Substantial
cost

huge time
required

moderate time
required

huge time
required

huge time
required

huge time
required

Substantial
cost

Substantial
cost

Substantial
cost

moderate time
required

huge time
required

huge time
required

Substantial
cost

meagre cost

meagre
cost

moderate time
required

moderate
time
required

moderate
time
required

Substantial
cost

Substantial
cost

Substantial
cost

moderate
time
required
moderate
time
required
minimum
time
required
moderate
time
required

moderate
time
required
moderate
time
required

33

Prepare
claim
moderate
time
required
moderate
time
required
moderate
time
required
minimum
time
required
minimum
time
required
moderate
time
required

moderate
time
required
moderate
time
required

Claims in the Construction Industry of Pakistan

12

Moderate
Involvement

No
Involvement

13

Moderate
Involvement

Meagre
Involvement

14

Total
Involvement

No
Involvement

15

Moderate
Involvement

No
Involvement

16

Not
Concerned

Meagre
Involvement

17

Moderate
Involvement

Not
Concerned

1
2
3
4
5
6
7
8
9
10
11
12

Archiving
info_1
Substantial
cost
Substantial
cost
meagre
cost
meagre
cost
Substantial
cost
Substantial
cost
meagre
cost
very costly
Substantial
cost
meagre
cost
Substantial
cost
very costly

Interpretation
contract_1

moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required

readily
available

huge time
required

readily
available

moderate
time
required
moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required
moderate
time
required

Architect
response_1

meagre cost

very costly

Substantial
cost

Substantial
cost
Substantial
cost
meagre
cost
meagre
cost

very costly
meagre cost
meagre cost
very cheap
meagre cost
meagre cost
very cheap
meagre cost
Substantial
cost
Substantial
cost

Appendix B

very costly

Quantifying
claim_1
Substantial
cost
Substantial
cost
Substantial
cost
Substantial
cost
Substantial
cost
Substantial
cost

very costly

very costly

Substantial
cost
meagre
cost
Substantial
cost
Substantial
cost
Substantial
cost

Substantial
cost
meagre
cost
Substantial
cost
Substantial
cost
meagre
cost

Prepare
claim_1
meagre
cost
very cheap
meagre
cost
Substantial
cost
meagre
cost
meagre
cost
Substantial
cost
meagre
cost
meagre
cost
Substantial
cost
Substantial
cost
very cheap

moderate
time
required
moderate
time
required
moderate
time
required
moderate
time
required
moderate
time
required
moderate
time
required

Lack
resources
very much
responsible
very much
responsible
moderately
responsible
mere
responsible
mere
responsible
moderately
responsible
moderately
responsible
Not
responsible
very much
responsible
very much
responsible
mere
responsible
moderately
responsible

moderate time
required
moderate time
required
minimum time
required
moderate time
required
moderate time
required
minimum time
requried

Showing
Cause
effect
mere
responsible
moderately
responsible
very much
responsible
very much
responsible
mere
responsible
mere
responsible
moderately
responsible
moderately
responsible
moderately
responsible
moderately
responsible
moderately
responsible
very much
responsible

34

moderate
time
required
minimum
time
required

moderate
time
required

moderate
time
required

Substantial
cost

Substantial
cost

meagre
cost

huge time
required

huge time
required

meagre
cost

meagre cost

Substantial
cost

huge time
required

huge time
required

huge time
required

Substantial
cost

very cheap

very costly

moderate
time
required
moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required

moderate
time
required
moderate
time
required

meagre
cost

very cheap

very cheap

meagre
cost

Substantial
cost

Substantial
cost

huge time
required

huge time
required

Substantial
cost

Substantial
cost

Substantial
cost

Architect
response
very much
responsible
very much
responsible
very much
responsible
very much
responsible
moderately
responsible
very much
responsible
very much
responsible
very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible
very much
responsible

Time
limitation
moderately
responsible
very much
responsible
moderately
responsible
moderately
responsible
mere
responsible
moderately
responsible
very much
responsible
mere
responsible
moderately
responsible
very much
responsible
mere
responsible
moderately
responsible

Others
Not
responsible
moderately
responsible
moderately
responsible
moderately
responsible
mere
responsible
mere
responsible
mere
responsible
mere
responsible
moderately
responsible
mere
responsible
moderately
responsible
Not
responsible

Lack
Contemporary
records
very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible
mere
responsible
moderately
responsible
very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible
mere
responsible
mere
responsible

Poor
records
very much
responsible
very much
responsible
mere
responsible
moderately
responsible
moderately
responsible
very much
responsible
very much
responsible
mere
responsible
moderately
responsible
very much
responsible
Not
responsible
very much
responsible

Identifying
Retrieving
info
very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible
moderately
responsible
very much
responsible
moderately
responsible
moderately
responsible
very much
responsible
mere
responsible
moderately
responsible
moderately
responsible

Claims in the Construction Industry of Pakistan


13
14
15
16
17

Substantial
cost
Substantial
cost
very cheap
Substantial
cost
Substantial
cost

very costly
very costly
meagre cost
meagre cost
meagre cost

meagre
cost
meagre
cost
meagre
cost
Substantial
cost
Substantial
cost

Appendix B
very costly
Substantial
cost
meagre
cost
Substantial
cost
meagre
cost

Substantial
cost
meagre
cost
meagre
cost
Substantial
cost
very cheap

very much
responsible
Not
responsible
mere
responsible
mere
responsible
mere
responsible

moderately
responsible
mere
responsible
moderately
responsible
mere
responsible
moderately
responsible

35

very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible
very much
responsible

very much
responsible
very much
responsible
moderately
responsible
moderately
responsible
moderately
responsible

moderately
responsible
mere
responsible
moderately
responsible
moderately
responsible
moderately
responsible

moderately
responsible
moderately
responsible
mere
responsible
moderately
responsible
very much
responsible

mere
responsible
mere
responsible
mere
responsible
moderately
responsible
moderately
responsible

mere
responsible
moderately
responsible
mere
responsible
mere
responsible
Not
responsible

Claims in the Construction Industry of Pakistan

Appendix B

Respondent Data Analysis


B.1 Records Keeping
Timely maintain
Frequency

Percent

Never

Cumulative Percent

11.8

11.8

35.3

47.1

Mostly

17.6

64.7

Always

35.3

100.0

Total

17

100.0

Sometimes

Timely maintain
Frequency

Percent

Always Lost
Mostly Lost/faced
difficulties
Never filled a claim
Few times lost/faced
difficulties
Total

Cumulative Percent

11.8

11.8

23.5

35.3

35.3

70.6

29.4

100.0

17

100

EDMS
Frequency

Percent

Cumulative Percent

Yes

17.6

17.6

No

14

82.4

100.0

Total

17

100.0

36

Claims in the Construction Industry of Pakistan

Appendix B

B.2 Extent of use of project documentation

BOQ
Claim_Documentation
Minutes_Site_Meeting
Schedules
Photographs
Site_Diaries
Contract_Conditions
Correspondence
Daily_diaries
Delay_records
Specification
Revised_drawings

Mean

Importance Index

Rank

17
17
17
17
17
17
17
17
17
17
17
17

3.1176
2.7647
2.8824
3.0000
3.0588
2.7647
3.4118
3.1176
2.6471
2.8824
3.1765
3.6471

0.779
0.691
0.721
0.750
0.765
0.691
0.853
0.779
0.662
0.721
0.794
0.912

4
10
10
7
6
10
2
4
12
8
3
1

B.3 Change Orders

Change Order Received


Frequency

Percent

Cumulative Percent

5.9

5.9

47.1

52.9

23.5

76.5

23.5

100.0

17

100.0

Never received
sometimes received
Most of the times received

All the times received

Total

Oral Change Order


Frequency

Percent

Cumulative Percent

sometimes received

35.3

35.3

Most of the times received

35.3

70.6

All the times received

29.4

100.0

Total

17

100.0

37

Claims in the Construction Industry of Pakistan

Appendix B

OCO Defended
Frequency

Percent

Cumulative Percent

29.4

29.4

10

58.8

88.2

11.8

100.0

17

100.0

Never defended
Sometimes defended

Most of the times defended

Total

Waive Clause
Frequency

Percent

Cumulative
Percent

Yes

23.5

23.5

No

13

76.5

100.0

Total

17

100.0

B.4 Contract Knowledge


Studying Bidding Document
Frequency

Percent

Cumulative Percent

0%-30%

11.8

11.8

30%-50%

35.3

47.1

50%-80%

29.4

76.5

23.5

100.0

17

100.0

80%-100%
Total

Contract Clause Addition


Frequency

Percent

Cumulative Percent

Yes

11

64.7

64.7

NO

35.3

100.0

Total

17

100.0

38

Claims in the Construction Industry of Pakistan

Appendix B

B.5 Claim Preparation individual involvement

Project_Manager
Project_QC
Headoffice_QC
Site_engineer
Claim_Manager
Claim_Consultants
Others_involved

Mean

Importance Index

Rank

17

3.3529

0.282

17

3.8824

0.211

17

3.4706

0.236

17

4.2353

0.166

17

3.5882

0.283

17

3.8824

0.186

17

2.4706

0.236

Time Involved
identify_info
identify_sources
retrieve_info
archiving_info
interpratation_contract
architect_response
Claim_quantifying
prepare_claim

Mean

Importance Index

Rank

17

2.8824

0.721

17

3.1176

0.779

17

2.8235

0.706

17

2.1765

0.725

17

2.0588

0.686

17

2.4118

0.804

17

2.4706

0.824

17

2.2353

0.745

Mean

Importance Index

Rank

17

2.5882

0.647

17

2.4118

0.603

17

2.7647

0.691

17

2.7647

0.691

17

2.4118

0.603

17

2.8235

0.706

17

2.8824

0.721

17

2.1765

0.544

Cost entailed
identify_info
identify_sources
retrieve_info
archiving_info
interpratation_contract
architect_response
Claim_quantifying
prepare_claim

39

Claims in the Construction Industry of Pakistan

Appendix B

Reason in Claim Delay


N

Mean

Importance Index

Rank

lack_resources

17

2.7059

0.676

Showing_cause_effect

17

2.8824

0.721

Lack_contemporary_records

17

3.0588

0.765

Poor_records

17

3.2353

0.809

Identifying_retriving_info

17

3.0588

0.765

achitect_response

17

3.4706

0.868

time_limitation

17

2.8235

0.706

Others

17

2.1765

0.544

40

References
Chovichien, K. T. (n.d.). Contractor's Construction Claims and Claim Management Process.
Hassanein , A., & El Nemr, W. (2008). Claims management in the. Engineering, Construction and
Architectural Management, 15(5), 456-469.
Jergeas, G., & Hartman, F. (1994). Contractors' Construction-Claims Avoidance. Journal of Construction
Engineer, 120(3), 553-560.
Klee, L. (2013). Management of Contractors Claims in.
Kululanga, G., Kutocha, W., McCaffer, R., & Edum-Fotwe, F. (2001). Construction Contractors' Claim Process
Framework. Journal of Construction Engineering and Management, 127(4), 309-314.
Vidogah, W., & Ndekugri, I. (1997). IMPROVING MANAGEMENT OF CLAIMS: Contractor's Perspective.
Journal of Management in Engineering, 13(5), 37-44.
Zaneldin, E. K. (2006). Construction claims in United Arab Emirates: Types, causes and frequency. (24 (2006)).

41

S-ar putea să vă placă și