Sunteți pe pagina 1din 19

1.

SOW
For survey,commissioning,ATP,Dismantle,document requirement,follow Huawei requirement.
1.1 BTS Installation SOW: Installation(including receiving material on site,Must offer document as GCI required )
Standard SOW

Unit

Quantity

BTS Rack

Site

1 or 2

Battery Rack

Site

Feeder system

Site

Antenna system

Site

Mounting Bracket

Site

Others

Site

1 LOT

No.

Including accessories such as LAN cable,g

1.2 MW Installation SOW:MW Installation&Pointing(including receiving material on site,Must offer document as GCI required )
No.
Standard SOW
Unit
Quantity
1

IDU

Hop

IF Cable

Hop

ODU

Hop

1
1 or 2

Antenna

Hop

5
Others
Hop
1 LOT Including accessories such as LAN cable,g
2.PriceIncluding all duties and expenses.
(if can provide NPWP number,deduct 2% PPH23-Withold Tax,if can not provide NPWP number,deduct 4% PPH23-With hold Ta

3.Payment terms:
For survey:100% payment after submit TSSR(PASS Huawei verification)
4.Reciept or Invoice: Must have signature with Team Leader/PM/Other GCI Staff

5.Project Regulation
All the subcons, engineers must obey the following regulations. Any subcon disobeys these rules we will stop the contract and g
damage, any engineer disobeys this rules, which will be given warning letter and be kicked out from the project until stop contra
a.Firstly before any activity you must get permission letter.Secondly when you enter and leave the site you must inform NOC.Es
site you must confirm with NOC everything is ok then you can leave site.
b. Activity of power supply, when you change MCB or any other power/rectifier work you must report to Huawei and NOC first, e
of these activities you must get approval from Huawei and Operator by email or hardcopy.
c. Immediate communication and information feedback. Once any issue or trouble happens you must report to GCI PM ASAP (
regarded as disobeying this rule.
d. Personal safety of subcon teams. According to the contract between GCI and subcon,all the subcon should take full respons
memberes/engineers.please pay more attention to this issue
and take enough protection actions and ensure the personal safety of your guys.

Partner

PT.GCI Indonesia

Signature:

Signature:

Date:

Date:

s GCI required )

essories such as LAN cable,gronding bar,combiner(if have),and so on.

r document as GCI required )

essories such as LAN cable,gronding bar,and so on(if have).

educt 4% PPH23-With hold Tax).

we will stop the contract and give punishment according to our


m the project until stop contract.
site you must inform NOC.Especially when you are ready to leave the

ort to Huawei and NOC first, especially for the existing equipments. All

must report to GCI PM ASAP (Within 5 Minutes), any delay will be

bcon should take full responsibility for all your team

L3.1 BTS Baseline

Item Description

Unit

01 Survey
BTS0101_Survey: BTS or BTS&MW Engineering Survey + Report

Site

BTS0102_Survey: BTS or BTS&MW Engineering Survey + Simple Report

Site

02 New
BTS0201_New: BTS/NodeB (1 system) + Power System + Antenna&Feeder

site

BTS0202_New: BTS/NodeB (1 system) + Power System + No Antenna&Feeder

site

BTS0203_New: BTS/NodeB (1 system) + No Power System + Antenna&Feeder

site

BTS0204_New: BTS/NodeB (1 system) + No Power System + No Antenna&Feeder


BTS0205_New: DBS RRU on tower (1 system) + Power System + Antenna
BTS0206_New: DBS RRU on tower (1 system) + Power System + No Antenna
BTS0207_New: DBS RRU on tower (1 system) + No Power System + Antenna
BTS0208_New: DBS RRU on tower (1 system) + No Power System + No Antenna
BTS0209_New: BTS/NodeB (2 system) + Power System + Antenna&Feeder
BTS0210_New: BTS/NodeB (2 system) + Power System + No Antenna&Feeder
BTS0211_New: BTS/NodeB (2 system) + No Power System + Antenna&Feeder
BTS0212_New: BTS/NodeB (2 system) + No Power System + No Antenna&Feeder
BTS0213_New: DBS RRU on tower (2 system) + Power System + Antenna
BTS0214_New: DBS RRU on tower (2 system) + Power System + No Antenna
BTS0215_New: DBS RRU on tower (2 system) + No Power System + Antenna
BTS0216_New: DBS RRU on tower (2 system) + No Power System + No Antenna
BTS0217_New: BTS/NodeB (3 system) + Power System + Antenna&Feeder
BTS0218_New: BTS/NodeB (3 system) + Power System + No Antenna&Feeder
BTS0219_New: BTS/NodeB (3 system) + No Power System + Antenna&Feeder
BTS0220_New: BTS/NodeB (3 system) + No Power System + No Antenna&Feeder
BTS0221_New: DBS RRU on tower (3 system) + Power System + Antenna
BTS0222_New: DBS RRU on tower (3 system) + Power System + No Antenna
BTS0223_New: DBS RRU on tower (3 system) + No Power System + Antenna
BTS0224_New: DBS RRU on tower (3 system) + No Power System + No Antenna

site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site
site

04 Codeploy with MW
BTS0401_Codeploy with MW: BTS/NodeB (1 system) + Power System + Antenna&Feeder

site

Item Description

Unit

BTS0402_Codeploy with MW: BTS/NodeB (1 system) + Power System + No Antenna&Feeder

site

BTS0403_Codeploy with MW: BTS/NodeB (1 system) + No Power System + Antenna&Feeder

site

BTS0404_Codeploy with MW: BTS/NodeB (1 system) + No Power System + No Antenna&Feeder

site

BTS0405_Codeploy with MW: DBS RRU on tower (1 system) + Power System + Antenna

site

BTS0406_Codeploy with MW: DBS RRU on tower (1 system) + Power System + No Antenna

site

BTS0407_Codeploy with MW: DBS RRU on tower (1 system) + No Power System + Antenna

site

BTS0408_Codeploy with MW: DBS RRU on tower (1 system) + No Power System + No Antenna

site

BTS0409_Codeploy with MW: BTS/NodeB (2 system) + Power System + Antenna&Feeder

site

BTS0410_Codeploy with MW: BTS/NodeB (2 system) + Power System + No Antenna&Feeder

site

BTS0411_Codeploy with MW: BTS/NodeB (2 system) + No Power System + Antenna&Feeder

site

BTS0412_Codeploy with MW: BTS/NodeB (2 system) + No Power System + No Antenna&Feeder

site

BTS0413_Codeploy with MW: DBS RRU on tower (2 system) + Power System + Antenna

site

BTS0414_Codeploy with MW: DBS RRU on tower (2 system) + Power System + No Antenna

site

BTS0415_Codeploy with MW: DBS RRU on tower (2 system) + No Power System + Antenna

site

BTS0416_Codeploy with MW: DBS RRU on tower (2 system) + No Power System + No Antenna

site

BTS0417_Codeploy with MW: BTS/NodeB (3 system) + Power System + Antenna&Feeder

site

BTS0418_Codeploy with MW: BTS/NodeB (3 system) + Power System + No Antenna&Feeder

site

BTS0419_Codeploy with MW: BTS/NodeB (3 system) + No Power System + Antenna&Feeder

site

BTS0420_Codeploy with MW: BTS/NodeB (3 system) + No Power System + No Antenna&Feeder

site

BTS0421_Codeploy with MW: DBS RRU on tower (3 system) + Power System + Antenna

site

BTS0422_Codeploy with MW: DBS RRU on tower (3 system) + Power System + No Antenna

site

BTS0423_Codeploy with MW: DBS RRU on tower (3 system) + No Power System + Antenna

site

Item Description

BTS0424_Codeploy with MW: DBS RRU on tower (3 system) + No Power System + No Antenna

Unit

site

06 Redeploy

BTS0601_Redeploy: BTS/NodeB (1 system) + Power System + Antenna&Feeder

site

BTS0602_Redeploy: BTS/NodeB (1 system) + Power System + No Antenna&Feeder

site

BTS0603_Redeploy: BTS/NodeB (1 system) + No Power System + Antenna&Feeder

site

BTS0604_Redeploy: BTS/NodeB (1 system) + No Power System + No Antenna&Feeder

site

07 Additional-1
BTS0702_Expansion: BTS/NodeB RF/TRX Board
BTS0703_Expansion: BTS/NodeB Cabinet
BTS0704_Expansion: Sector + Antenna&Feeder
BTS0705_Expansion: Sector + No Antenna&Feeder
BTS0706_Expansion: RRU on Tower
08 Dismantlement&Packing

site
site
site
site
site

BTS0801_Dismantlement&Packing: BTS/NodeB (1 system) + Power System + Antenna& Feeder

site

BTS0802_Dismantlement&Packing: BTS/NodeB (1 system) + Power System + No Antenna&Feeder

site

BTS0803_Dismantlement&Packing: BTS/NodeB (1 system) + No Power System + Antenna&Feeder

site

BTS0804_Dismantlement&Packing: BTS/NodeB (1 system) + No Power System + No Antenna&Feeder

site

BTS0805_Dismantlement&Packing: BTS/NodeB (2 system) + Power System + Antenna& Feeder

site

Item Description

Unit

BTS0806_Dismantlement&Packing: BTS/NodeB (2 system) + Power System + No Antenna&Feeder

site

BTS0807_Dismantlement&Packing: BTS/NodeB (2 system) + No Power System + Antenna&Feeder

site

BTS0808_Dismantlement&Packing: BTS/NodeB (2 system) + No Power System + No Antenna&Feeder

site

BTS0809_Dismantlement&Packing: BTS/NodeB (3 system) + Power System + Antenna& Feeder

site

BTS0810_Dismantlement&Packing: BTS/NodeB (3 system) + Power System + No Antenna&Feeder

site

BTS0811_Dismantlement&Packing: BTS/NodeB (3 system) + No Power System + Antenna&Feeder

site

BTS0812_Dismantlement&Packing: BTS/NodeB (3 system) + No Power System + No Antenna&Feeder

site

10 Additional-2
BTS0901_E1 cross-connection from BTS/NodeB to BSC/RNC
BTS1003_Optional: Power System Replacement&Packing
BTS1004_Optional: Power Rectifier Installation
BTS1005_Optional: BTS/NodeB Battery Test with Dummy Load
BTS1006_Optional: E1 Checking
BTS1007_Optional: Antenna Replacement&Packing
BTS1008_Optional: Antenna Dismantlement&Packing
BTS1009_Optional: Feeder Dismantlement&Packing
BTS1010_Optional: Combiner/Diplexer/Triplexer/TMA/Filter Dismantlement&Packing

site
site
site
site
site
site
site
site
site

L3.1 BTS Baseline


Jakarta

Scenario

BTS or BTS&MW co-engineering survey(with report), include RF survey


BTS or BTS&MW co-engineering survey(with simple report), include RF survey, including summary and layout
only, without TSSR.

CJ

Completed
SOW(Install+commission+ Installation SOW
document+atp)

Completed
SOW(Install+commission+
document+atp)

850,000

935,000

700,000

770,000
0

complete new site, with power system, with antenna&feeder


can be used for Macro BTS, Micro BTS, DBS RRU not on tower
IBC site, with power system
new site, without power system;
can be used for Macro BTS, Micro BTS, DBS RRU not on tower
IBC site, without power system
DBS RRU on tower, with power system
DBS RRU on tower, with power system, without antenna
DBS RRU on tower, without power system
DBS RRU on tower, without power system, without antenna

4,500,000

3500000

4,950,000

2,750,000

2000000

3,025,000

4,000,000

3000000

4,400,000

2,350,000
3,800,000
2,900,000
3,400,000
2,450,000
5,400,000
3,300,000
4,800,000
2,820,000
4,560,000
3,480,000
4,080,000
2,940,000
6,300,000
3,850,000
5,600,000
3,290,000
5,320,000
4,060,000
4,760,000
3,430,000

1700000
3000000
2000000
2600000
1700000
4200000
2400000
3600000
2040000
3600000
2400000
3120000
2040000
4900000
2800000
4200000
2380000
4200000
2800000
3640000
2380000

2,585,000
4,180,000
3,190,000
3,740,000
2,695,000
5,940,000
3,630,000
5,280,000
3,102,000
5,016,000
3,828,000
4,488,000
3,234,000
6,930,000
4,235,000
6,160,000
3,619,000
5,852,000
4,466,000
5,236,000
3,773,000

Scenario for BTS/NobeB codeploy with MW, need to used together with "Codeploy with BTS/NobeB in
MW BOQ.

0
3,600,000

3150000

3,960,000

Scenario

Completed
SOW(Install+commission+ Installation SOW
document+atp)

Completed
SOW(Install+commission+
document+atp)

2,200,000

1800000

2,420,000

3,200,000

2700000

3,520,000

1,880,000

1530000

2,068,000

3,040,000

2700000

3,344,000

2,320,000

1800000

2,552,000

2,720,000

2340000

2,992,000

1,960,000

1530000

2,156,000

4,320,000

3780000

4,752,000

2,640,000

2160000

2,904,000

3,840,000

3240000

4,224,000

2,256,000

1836000

2,481,600

3,648,000

3240000

4,012,800

2,784,000

2160000

3,062,400

3,264,000

2808000

3,590,400

2,352,000

1836000

2,587,200

5,040,000

4410000

5,544,000

3,080,000

2520000

3,388,000

4,480,000

3780000

4,928,000

2,632,000

2142000

2,895,200

4,256,000

3780000

4,681,600

3,248,000

2520000

3,572,800

3,808,000

3276000

4,188,800

Scenario

Completed
SOW(Install+commission+ Installation SOW
document+atp)
2,744,000

Completed
SOW(Install+commission+
document+atp)
2142000

exclude dismantlement&packing.
ONLY for 3rd party equipment redeploy; for Huawei equipment redeploy use "02 New".

3,018,400
0

complete redeploy, include BTS (or BBU, RRU), power system, antenna&feeder.
Can be used for Macro BTS, Micro BTS, DBS RRU on tower, DBS RRU not on tower.

4,950,000

3850000

5,445,000

redeploy, include BTS(or BBU, RRU), power system, exclude antenna&feeder


Can be used for Macro BTS, Micro BTS, DBS RRU on tower, DBS RRU not on tower.

3,025,000

2200000

3,327,500

redeploy, include BTS(or BBU, RRU), antenna&feeder, exclude power system.


Can be used for Macro BTS, Micro BTS, DBS RRU on tower, DBS RRU not on tower.

4,400,000

3300000

4,840,000

redeploy, include BTS(or BBU, RRU), exclude power system, antenna&feeder.


Can be used for Macro BTS, Micro BTS, DBS RRU on tower, DBS RRU not on tower.

2,585,000

1870000

2,843,500

include RRU not on tower.


cabinet expansion.
sector expansion, include main equipment, antenna&feeder.
sector expansion, include main equipment, exclude antenna&feeder.
expansion for RRU on tower.
include simple packing material.
dismantle&packing, include BTS (or BBU, RRU), power system, antenna&feeder

0
550,000
825,000
1,430,000
770,000
825,000
0

500,000
750,000
1,300,000
700,000
750,000
1600000

dismantle&packing, include BTS (or BBU, RRU), power system, exclude antenna&feeder

850000

dismantle&packing, include BTS (or BBU, RRU), antenna&feeder, exclude power system.

1400000

dismantle&packing, include BTS (or BBU, RRU), exclude antenna&feeder, power system.

650000

1920000

Scenario

Completed
SOW(Install+commission+ Installation SOW
document+atp)

Completed
SOW(Install+commission+
document+atp)
1020000

1680000

780000

2240000

1190000

1960000

910000

700000
1000000
750000
450000
550000
950000
520000
700000
550000

0
0
0
0
0
0
0
0
0
0

CJ

Installation SOW

3850000
2200000
3300000
1870000
3300000
2200000
2860000
1870000
4620000
2640000
3960000
2244000
3960000
2640000
3432000
2244000
5390000
3080000
4620000
2618000
4620000
3080000
4004000
2618000
0
3465000

Installation SOW

1980000
2970000
1683000
2970000
1980000
2574000
1683000
4158000
2376000
3564000
2019600
3564000
2376000
3088800
2019600
4851000
2772000
4158000
2356200
4158000
2772000
3603600

Installation SOW

2356200
0

4235000

2420000

3630000

2057000
0
0
0
0
0
0
0
1760000
935000
1540000
715000
2112000

Installation SOW

1122000
1848000
858000
2464000
1309000
2156000
1001000
0
770000
1100000
825000
495000
605000
1045000
572000
770000
605000

L3.2 MW Baseline

Item Description

01 Survey
MW0101_MW Engineering Survey
MW0102_MW LOS survey
02 New
MW0201_New: MW 0.3/0.6m 2
MW0202_New: MW 0.3/0.6m 4
MW0203_New: MW 0.9/1.2m 2
MW0204_New: MW 0.9/1.2m 4
MW0205_New: MW 1.8m 2
MW0206_New: MW 1.8m 4
MW0207_New: MW >= 2.4m 2
MW0208_New: MW >= 2.4m 4
MW0209_New: MW(Without mounting pole) 0.3/0.6m 2
MW0210_New: MW(Without mounting pole) 0.9/1.2m 2
MW0211_New: MW(Without E2E commissioning) 0.3/0.6m 2
MW0212_New: MW(Without E2E commissioning) 0.9/1.2m 2

Unit

Site
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop

03 Codeploy with BTS/NodeB


MW0301_Codeploy with BTS/NobeB: MW
MW0302_Codeploy with BTS/NobeB: MW
MW0303_Codeploy with BTS/NobeB: MW
MW0304_Codeploy with BTS/NobeB: MW
MW0305_Codeploy with BTS/NobeB: MW
MW0306_Codeploy with BTS/NobeB: MW
MW0307_Codeploy with BTS/NobeB: MW
MW0308_Codeploy with BTS/NobeB: MW
05 Redeploy
MW0501_Redeploy: MW 0.3/0.6m 2
MW0502_Redeploy: MW 0.3/0.6m 4
MW0503_Redeploy: MW 0.9/1.2m 2
MW0504_Redeploy: MW 0.9/1.2m 4
MW0505_Redeploy: MW 1.8m 2
MW0506_Redeploy: MW 1.8m 4

0.3/0.6m 2
0.3/0.6m 4
0.9/1.2m 2
0.9/1.2m 4
1.8m 2
1.8m 4
>= 2.4m 2
>= 2.4m 4

Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop

Item Description

Unit

MW0507_Redeploy: MW >= 2.4m 2


MW0508_Redeploy: MW >= 2.4m 4
06 Dismantlement&Packing
MW0601_Dismanlement&Packing: MW 0.3/0.6m 2
MW0602_Dismanlement&Packing: MW 0.3/0.6m 4
MW0603_Dismanlement&Packing: MW 0.9/1.2m 2
MW0604_Dismanlement&Packing: MW 0.9/1.2m 4
MW0605_Dismanlement&Packing: MW 1.8m 2
MW0606_Dismanlement&Packing: MW 1.8m 4
MW0607_Dismanlement&Packing: MW >= 2.4m 2
MW0608_Dismanlement&Packing: MW >= 2.4m 4
07 Replacement
MW0702_Replacement: MW IDU
MW0703_Replacement: MW ODU
MW0704_Replacement: MW Antenna 0.3/0.6m
MW0705_Replacement: MW Antenna 0.9/1.2m
MW0706_Replacement: MW Antenna 1.8m
MW0707_Replacement: MW Antenna >= 2.4m
09 Optional
MW0901_Optional: MW Frequency scanning
MW0902_Optional: MW Frequency License Application until ISR
MW0904_Optional: MW IDU installation and Commissioning
MW0906_Optional: MW Hardware Upgradation and comissioing from 1+0 to 1+1/2+0

Hop
Hop

MW0907_Optional: MW Hardware Degradation and comissioing from 1+1/2+0 to 1+0

Hop

MW0910_Optional: Misplace Rectification MW Antenna 0.3/0.6m


MW0911_Optional: Misplace Rectification MW Antenna 0.9/1.2m
MW0912_Optional: Misplace Rectification MW Antenna >= 1.2m

Pcs
Pcs
Pcs

Hop
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Site
Hop
Hop
Hop
Hop
Hop
Hop
Hop
Site
Hop

.2 MW Baseline
Jakarta

Quick SOW

survey+report
survey+report
Installation of IDU,Board,IF cable,ODU,Coupler,Antenna,+PAT

Installation of IDU,Board,IF cable,ODU,Coupler,Antenna(Without Mounting pole),+PAT


Installation of IDU,Board,IF cable,ODU,Coupler,Antenna(Without E2E commissioning),+PAT
Scenario for BTS/NobeB codeploy with MW, need to used together with "Codeploy
with MW" in BTS BOQ.
Installation of IDU,Board,IF cable,ODU,Coupler,Antenna,+PAT

for 3rd party MW redeploy only


Installation of IDU,Board,IF cable,ODU,Coupler,Antenna,+PAT

CJ

Completed
SOW(Install+c Installation
ommission+do SOW
cument+atp)

450,000
750,000
3,800,000
4,500,000
4,500,000
5,400,000
5,400,000
6,400,000
6,400,000
7,600,000
3,420,000
4,050,000
3,150,000
3,780,000

2,200,000
2,640,000
2,600,000
3,120,000
3,000,000
3,600,000
4,000,000
4,800,000
1,980,000
2,376,000
1,820,000
2,184,000

3,040,000
3,600,000
3,600,000
4,320,000
4,320,000
5,120,000
5,120,000
6,080,000

2,013,000
2,415,600
2,379,000
2,854,800
2,745,000
3,294,000
3,660,000
4,392,000

3,990,000
4,725,000
4,725,000
5,670,000
5,670,000
6,720,000

2,310,000
2,772,000
2,730,000
3,276,000
3,150,000
3,780,000

Completed
SOW(Install+commission+ Installation SOW
document+atp)

495,000
825,000
0
4,180,000
4,950,000
4,950,000
5,940,000
5,940,000
7,040,000
7,040,000
8,360,000
3,762,000
4,455,000
3,465,000
4,158,000

2420000
2904000
2860000
3432000
3300000
3960000
4400000
5280000
2178000
2613600
2002000
2402400

3,344,000
3,960,000
3,960,000
4,752,000
4,752,000
5,632,000
5,632,000
6,688,000
0
4,389,000
5,197,500
5,197,500
6,237,000
6,237,000
7,392,000

2214300
2657160
2616900
3140280
3019500
3623400
4026000
4831200
0
2541000
3049200
3003000
3603600
3465000
4158000

Installation of IDU,Board,IF cable,ODU,Coupler,Antenna,+PAT

Quick SOW

Completed
SOW(Install+c Installation
ommission+do SOW
cument+atp)

6,720,000
7,980,000

4,200,000
5,040,000

Dismantlemen of IDU,Board,IF cable,ODU,Coupler,Antenna+Packing

1,200,000
1,400,000
1,400,000
1,600,000
2,000,000
2,500,000
3,200,000
3,800,000

1,200,000
1,400,000
1,400,000
1,600,000
2,000,000
2,500,000
3,200,000
3,800,000

IDU Dismantlement+IDU installation and Commissioning


ODU Dismantlement+ODU installation and Commissioning
Antenna Dismantlement+Antenna installation and Alignment

500,000
1,000,000
2,800,000
3,300,000
4,000,000
6,500,000

450,000
800,000
2,200,000
2,600,000
3,000,000
4,000,000

2,000,000
350,000
550,000

2,000,000

Completed
SOW(Install+commission+ Installation SOW
document+atp)

7,392,000
8,778,000
0
1,320,000
1,540,000
1,540,000
1,760,000
2,200,000
2,750,000
3,520,000
4,180,000
0
550,000
1,100,000
3,080,000
3,630,000
4,400,000
7,150,000
0
2,200,000
385,000
605,000

4620000
5544000
0
1320000
1540000
1540000
1760000
2200000
2750000
3520000
4180000
0
495000
880000
2420000
2860000
3300000
4400000
0
2200000
0
0

2,500,000

2,750,000

1,800,000

1,980,000

1,100,000
1,375,000
1,650,000

880000
1100000
1375000

1,000,000
1,250,000
1,500,000

800,000
1,000,000
1,250,000

L3.3 Core Network Baseline


Item Description

Unit

Jakarta

CJ

Subcon Price

Subcon Price

01 Survey
CN0101_Core Network Engineering Survey + Report
02 Hareware Installation and Supervision
CN0201_Hareware Installation and Supervision: Core Network Cabinet
CN0202_Hardware Installation and Supervision: Core Network Subrack
CN0204_Hardware Installation and Supervision: Rectifier Cabinet
CN0205_Hardware Installation and Supervision: Rectifier Module
CN0206_Hardware Installation and Supervision: Battery 300AH or below
CN0207_Hardware Installation and Supervision: Battery 400AH ~ 650AH
CN0208_Hardware Installation and Supervision: Battery 800AH ~ 1300AH
CN0209_Hardware Installation and Supervision: Battery 1600AH ~ 2600AH
CN0210_Hardware Installation and Supervision: Battery 3000AH and above
CN0211_Hardware Installation and Supervision: UPS system including battery: 10KVA or below

Site

1,200,000

Cabinet
Subrack
Cabinet
Site
BANK
BANK
BANK
BANK
BANK
Set

1,500,000
500,000
1,500,000
500,000
750,000
950,000
1,250,000
1,500,000
2,000,000

1,320,000
0
1,650,000
550,000
1,650,000
550,000
825,000
1,045,000
1,375,000
1,650,000
2,200,000

850,000

935,000

CN0212_Hardware Installation and Supervision: UPS system including battery: 20KVA ~ 30KVA

Set

1,700,000

1,870,000

CN0213_Hardware Installation and Supervision: UPS system including battery: 40KVA ~ 80KVA

Set

2,200,000

2,420,000

Set
Rack

350,000
450,000

Cabinet
Cabinet
BANK
BANK
BANK
BANK
BANK
Set

650,000
600,000
350,000
450,000
650,000
850,000
950,000
180,000

385,000
495,000
0
715,000
660,000
385,000
495,000
715,000
935,000
1,045,000
198,000

CN0214_Hardware Installation and Supervision: Signal Cable


CN0215_Hardware Installation and Supervision: ODF or DDF Rack
03 Dismantlement&Packing
CN0301_Dismantlement&Packing: Core Network Cabinet
CN0302_Dismantlement&Packing: Rectifier Cabinet
CN0303_Dismantlement&Packing: Battery 300AH or below
CN0304_Dismantlement&Packing: Battery 400AH ~ 650AH
CN0305_Dismantlement&Packing: Battery 800AH ~ 1300AH
CN0306_Dismantlement&Packing: Battery 1600AH ~ 2600AH
CN0307_Dismantlement&Packing: Battery 3000AH and above
CN0308_Dismantlement&Packing: Signal Cable

S-ar putea să vă placă și