Sunteți pe pagina 1din 4

Liability after take-over: the English position

November 2009

1. Describe the system of The limitation time periods most relevant to


construction projects are:
liability after take-over
according to the rules used a. Contract claims - 6 years from the
most often date the cause of action accrued,2
which is the date of the breach of
Under English law, upon take-over of a contract complained of. In construction Christopher Wong1
project, the relevant statutory provisions contracts, if the contractor is White & Case
governing liability of a contractor, sub- responsible for completing the works
contractor or consultant are found primarily under an entire contract, the limitation
in the Limitation Act 1980 (the ‘Act’). period for defective work generally
runs from the date of completion. As to
There is no statutory defects liability
liability for defective design, the English
period whereby the contractor has a
courts have held that while the cause A version of this article was first published
positive obligation to rectify defects. of action accrues generally on practical by Instituut voor Bouwrecht (Institute
Rather, it is usual practice for the parties completion (at the latest), the designer of Construction Law - Netherlands)
to agree a defects liability period as a may have a duty to reconsider the in Tijdschrift voor Bouwrecht,
matter of contract. The period is typically design as a result of defects arising after nr. 9 - September 2009
12 to 24 months for general construction completion. Such duty could arise either
contracts. In the absence of an agreed under the existing contract or the terms
defects liability period, or if the contractor of a new retainer; 3
refuses to rectify a defect notwithstanding
b. Tort actions - 6 years from the date the
an agreed defects liability period, the
cause of action accrued,4 which is the
aggrieved party will have to commence date the physical damage occurs; and
legal proceedings in order to recover
any damages or losses occurring after c. Deed claims - 12 years from the date
take-over. There is no guarantee that the the cause of action accrued,5 which is
aggrieved party will succeed, as it will need the date of the breach of the obligation
to prove that the other party was at fault in the deed.
and that it suffered damage or loss as a
It is possible for the parties to reduce or
result. The time for the aggrieved party to
increase the limitation periods prescribed
commence legal proceedings is limited
by the Act in their contracts.6 Generally, the
by the Act so that if the time has expired,
courts will not interfere with the parties’
the aggrieved party is ‘time-barred’ from
contractual agreement, especially if the
pursuing its claim.
parties are experienced commercial entities

1 Senior Associate at the London office of White & Case LLP and a member of the UK Society of Construction Law.
2 Section 5 of the Act.
3 See New Islington & Hackney Housing Association v Pollard Thomas & Edwards [2001] BLR 74.
4 Section 2 of the Act.
5 Section 8 of the Act.
6 See for example Oxford Architects Partnership v Cheltenham Ladies College [2006] EWHC 3156.
Liability after take-over: the English position

with equal bargaining power. However, the modified limitation ii. that the damage was attributable to the act or omission
period may be deemed unreasonable under the Unfair Contract which is alleged to constitute negligence; and
Terms Act 1977 if the period appears unfair, the contract parties
iii. the identity of the defendant,10
are of unequal bargaining power and the dominant party insisted
on the unreasonable period. subject to an overall long-stop period of 15 years from the date
Where a limitation period is about to expire, a party may: of the defendant’s negligent act or omission to which the damage
is attributable.11
i. commence legal proceedings straightaway, even if it does not
have the full facts to support its case. As a minimum, the party The issue of the defendant’s knowledge in (b) above has been the
must be able to formulate its claim properly according to the subject of various case law and the English courts have held that
procedural rules of the English courts. If the party wishes to add constructive knowledge as well as actual knowledge is relevant.
a new claim to its pleading subsequently (even after expiry of In Haward v Fawcetts (a firm) [2006] UKHL 9, the House of Lords
the limitation period), it will generally have to show that the new (England’s highest court) held that the 3 year period starts to run
claim arises out of the same facts or substantially the same from the time the claimant had knowledge of the ‘factual essence’
facts as the existing claim; 7 or of the alleged negligent acts or omissions, namely the material
facts supporting the substance of the claimant’s case and that
ii. enter into a ‘standstill agreement’ to temporarily suspend the
running of the limitation period. The agreement of the other there was a real possibility that the damage was caused by such
party is required in this case. acts or omissions. The claimant did not need to be certain or show
conclusively that the defendant’s acts or omissions had caused
In relation to residential property, the Defective Premises Act 1972 the losses alleged. Haward involved a case on negligent financial
provides that a developer or contractor doing work in connection advice and a recent construction case is Harris Springs Ltd v
with the provision of a dwelling owes a duty of care to any person Howes [2007] EWHC 327, which applied Haward and found that
acquiring an interest in the dwelling to ensure the work is done the owner was not time barred from making a claim for latent
in a workmanlike or professional manner with proper materials so defects against its engineers.
that the dwelling will be fit for habitation.8 A claimant has 6 years
from the time the dwelling was completed to bring an action It is important to note that the limitation periods for latent defects
for a breach of the duty. If further work to rectify the completed as above apply only to actions for negligence in tort, and not to
dwelling was done, the 6 years shall run from the time the further contractual claims. In practice, parties often attempt to negotiate
work was finished.9 liability for latent defects in their contracts.

2. How are hidden or latent defects 2.1. Does it make a difference if prior to take-over
dealt with? or during take-over, the employer was assisted by
professionals (like an architect or civil engineer)?
A party may bring an action in tort for negligence in relation to
If the contract is a ‘construct-only’ contract, the contractor will
latent defects on the later of:
generally not be liable for a defect in design, whether before,
a. 6 years from the date the cause of action accrued, which is during or after take-over. As between the employer and the
the date the damage or loss is suffered; or contractor, the responsibility for a design defect lies with
the employer. As between the employer and its professional
b. 3 years from the date the party knows or ought to consultants (eg. architect or civil engineer), the responsibility
have known: lies with the consultant who bears the risk of the design. The
i. the material facts about the damage or loss suffered; employer will look to the relevant consultant for relief and the
considerations mentioned in paragraph 1 above apply.

7 Section 35(5) of the Act and Civil Procedure Rules 17.4(2).


8 Section 1(1) Defective Premises Act 1972.
9 Section 1(5) Defective Premises Act 1972.
10 Section 14A of the Act, which was introduced into the Act by the enactment of the Latent Damage Act 1986. This was prompted by the House of Lords’ decision in
Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] 2 AC 1 which held that the claimant was time barred from bringing a claim against its architect for damage to
its chimney, which first occurred in 1970, even though the claimant only found out about the damage in 1977. More than 6 years had passed from the date the cause of action
arose in 1970 when the claimant commenced proceedings in 1978.
11 Section 14B of the Act, which was also introduced into the Act by the enactment of the Latent Damage Act 1986 following the Pirelli case.

White & Case 2


Liability after take-over: the English position

If the contract is a design and build contract, the contractor will If the defect is a latent defect discovered after take-over, the
generally be responsible for a defect in design and construction. position as discussed in paragraph 2.1(b) applies.
In principle, there should be no difference to a contractor’s liability
for any defects in the works prior to, during or after take-over 4. How long can the employer take action
even if the employer was assisted by professional consultants against the contractor after take-over?
(eg. architect or civil engineer) who carry out inspection of the
works prior to issue of the take-over certificate. This question has been addressed in paragraphs 1 and 2.1 above.

A defendant who wishes to seek a contribution from anyone 5. Is the liability limited to a certain amount?
else who is liable to the claimant for the same damage (such as If so, describe how.
a sub-contractor), must bring the contribution claim within 2 years
from the date the defendant is held liable under a judgment, or There is no statutory limitation of a party’s liability under
the date on which the amount of damages payable to the claimant English law. A party claiming damages still needs to prove the
is agreed.12 quantum of its loss. Contracting parties frequently impose a
limitation of the contractor’s liability in construction contracts,
including caps for liquidated damages. If the liquidated damages
2.2. Does it make a difference if the employer himself is
provision in a contract is unenforceable (for example, because it
considered to be a professional?
is considered a penalty), the courts in England have found that
In principle, it should not make a difference if the employer is the contractor’s liability for general damages may be limited to
considered to be a professional if it is clear between the parties the cap on the liquidated damages payable agreed by the parties
as to who is responsible for the design and construction aspects in their contract.
of the project. However, the English courts may treat an employer
who is a qualified building professional differently from a lay 6. How do you compare the Dutch position?
person in relation to the knowledge required for a limitation period
to run. For example, an employer who is an experienced architect There are clear differences in the English position and the
could be more readily said to know, or ought to have known, of Dutch position as regards liability after take-over, the main ones
the material facts about the loss or damage suffered arising from a being that:
latent design defect compared to an ordinary lay person. Similarly, a. unlike Dutch law, there is no statutory provision in England
an employer who is an experienced engineer and who chooses an equivalent to the Dutch Uniform Administrative Conditions of
inferior material being fully aware of the risks involved is unlikely 1989 or the Uniform Administrative Conditions for Integrated
to get much sympathy from the court if the material subsequently Contracts 2005 whereby the contractor ceases to be liable for
fails to a greater extent than if better material were used. defective work on take-over, save for specified exceptions;

3. Does it make a difference to the liability of b. English law does not contain an express limitation of the
contractor’s maximum liability (10% of the contract price for
the design and build contractor if a defect design and construction work under Dutch law); and
was or could have been discovered (a) prior
c. the limitation periods for claims against the contractor under
to, or (b) at the time of take-over; or (c) after English law are different from the Dutch position.
take-over? If so, describe the difference.
There is benefit in regulating liability after take-over as in the Dutch
Generally, there is no difference to the liability of the design and position. This must be balanced against the right of the parties to
build contractor as stated in paragraphs 1 and 2 if the defect was enter into their own bargain as appropriate (such as limitations
discovered prior to or at the time of takeover, or after take-over. of liability). Statutory requirements prescribe a ‘one size fits all’
A defect discovered prior to or at the time of take-over will regime which may not always work. A halfway house between
be a patent defect. It may be a patent defect after take-over the Dutch and English positions may be to make statutory
if it falls outside the latent defect provisions discussed in requirements the default position where the parties do not
paragraph 2.1(b). In any of these cases, the limitation periods set expressly provide for liability after take-over in their contracts.
out in paragraph 1 apply.

12 Section 10(4) Civil Liability (Contribution) Act 1978

White & Case 3


36 Offices. 25 Countries.

7. Which specific legal problems play a role in


your system concerning liability after take-
over when the contractor is responsible for
the designing and building?
This is merely an observation and not a ‘problem’ as such but
the obvious comment is that unlike other jurisdictions, there is
no statutory obligation on a contractor (whether responsible for
design and build, or just construction) to positively rectify defects
after take-over, and it is up to the claimant to ensure that this is
covered in the construction contract or pursue legal proceedings
for breach of contract or negligence.

The knowledge required of the ‘factual essence’ of negligence in


the case of latent defects can be problematic, and indeed, in the
Haward case itself, the judges differed on whether the essence
was the giving of deficient advice, or the giving of advice per se.
In the first, the claimant is said to know that something had gone
wrong so that he had a justifiable complaint against his advisers,
while in the second, he need only know that he had invested
money in reliance on the advice and had made losses. Whether
a claimant is successful ultimately depends on the court’s
interpretation of the rules against the facts in question.

www.whitecase.com
In this publication, White & Case means the international legal practice comprising White & Case LLP, a New York State registered limited liability partnership,
White & Case LLP, a limited liability partnership incorporated under English law and all other affiliated partnerships, corporations and undertakings.

LON1009072

S-ar putea să vă placă și