Sunteți pe pagina 1din 3

Method Statement -Erection of Temporary

Hoarding
1.

OBJECTIVE

To outline the sequence of activities, method and resources needed for the operation of
erecting temporary hoarding.

2.

SCOPE

The work shall include all labour, material, equipment, safety requirement and services
necessary for the execution erecting temporary hoarding.

3.

WORK SEQUENCE FLOW


_to attach drawing_

4.

MATERIAL
Material to be used is as follows:-

5.

4.1

50 x 50 x 1.6mm thick SHS M.S Posts

4.2

50 x 25 x 1.2mm thick RHS M.S Nogging

4.2

50 x 25 x 1.6mm thick SHS M.S Braces

4.3

0.3mm thick metal decking

4.4

Nail

4.5

Cement

4.6

Sand

4.7

Water

EQUIPMENTS & MACHINERIES REQUIRED


Equipments and machineries to be used are as follows:-

5.1

6.

Minimum: One (1) number of JCB Backhoe (if required)


5.2

Minimum: One (1) set of hand excavating equipment

5.3

Minimum: One (1) set of steel work equipment

5.4

Minimum: One (1) set of water levelling

5.5

Minimum: One (1) number of spirit level

SITE PREPARATION WORK


6.1

7.

Setting out boundaries of ground in the proposed perimeter.

METHOD OF WORK

7.1
Determine the location of the temporary hoarding will be established with
confirmation from the surveyor.
7.2
After getting confirmation, using the given point and mark the main pole as per
alignment shown in the drawings (Appendix A). Center to center of the main column is
3000mm.
7.3

Preparation of the main pillars started by using hand digging to the depth 400mm.

7.4
Pole-sized 50X50X1.6mm thk SHS M.S constructed using equipment such as spirit
level, water level, and tape measure. Two workers used to establish the main pillars.
7.5
Pillars need to ensure accurate position along the fence line at 3.0m (panel width)
intervals and make sure the base are sitting on an even level surface.
7.6
Erect the remaining pillars along the line as noted previously until the hoarding line
is complete.
7.7
50x25x1.2mm thk nogging need to install three (3) lines to support metal deck
panels.
7.8
Metal deck panels will be installed with the frame hoarding as per Appendix A
(spacing 4 for every panels).
7.9

This work will be repeated until completion.

7.10
Entrance gate will be erected at remaining area (refer item no.3) with support at
both side (left and right) using welded angles.

8.

QUALITY ISSUES

Boundaries demarcation required to ensure no double handling or trespassing to others


people land.

View inspection required during the process of erection hoarding.

Regular inspection to be carried out by weekly basis to ensure the hoarding in good
condition.

9.

SAFETY ISSUES

Safety helmets and safety footwear should always be worn.

All soft spots or holes shall be identified and barricade if necessary.

The site shall be kept clear of unnecessary obstruction.

First aid kit boxes will be provided at site office.

During raining, no erection hoarding activities are allowed to work.

10.

ENVIRONMENTAL ISSUES

All workers shall ensure that tools and machinery are in a good condition to avoid any
oil leakage that could harm to environment.

Construction waste from construction area must be collected into centralized garbage
bin and disposed at the designated area.

S-ar putea să vă placă și