Whenever an employee records time against network activity, costs would be debited to project and credited to
cost center. this cost equals to what rate you maintained against a person in HR master data (cost center).
Now you wanted to see the employee salary on WBS/Network, then either you post the equivalent hours on
NWA or post the delta difference of cost using direct posting. In fact, employee wages costs (cost center) and
booking hours on NWA never co-related because hours are booked as he has worked on NWA not on the
wage basis.
If you wanted to see that all his wages be booked on project objects, change Atype rate and book hours
accordingly.
But this is not a good pratice to be adopted.
Regards,
Sudhakar