Sunteți pe pagina 1din 2

RE-FRACKING

Ron Craik
March 27, 2015

Over the last five years I have heard countless references to lost productivity, usually
around 40%, pertaining to horizontal wells. It is still a mystery and no-one has been able
to say that it was due to one particular thing. My back ground is 25 years of Drill Stem
Testing (DST) on vertical wells both land and offshore. One comment that always came
up prior to horizontal wells was once a vertical well was completed and put on
production it quite often only did 50% of the flow rate that it showed when it was being
tested open hole (DST) for that zone.
When I started to hear this same comment for horizontal wells of an elusive 40% of
production that was lost it didnt sound that strange to me. There could be a multitude of
reasons why a horizontal well is not performing. This could be said of each of the many
stages (frac spacing) or laterals (parallel horizontal legs). Lets list some of the
possibilities: the well bore was drilled in and out of the formation, contacts with water
and/or non-productive formations, the cheapest mud system was used resulting in near
well bore damage, the hole was drilled too small 6.25 instead of 7.875 inches to save
money, a weird completion string was run that provided no access through the center of
the wellbore (Internal Diameter / I.D.) for remedial work or surveys, the frac sand
washed away or was degraded close to the well bore so the fractures closed and
healed cutting off production, etc.
The common thread for all these issues or any other that you can come up with is short
term thinking and lack of initiative to investigate. The personnel and corporations were
just too busy drilling new wells at $100.00 per barrel that it just didnt matter; any
mistakes wouldnt show up for years, they could make money regardless; it wasnt
going to affect their next quarterly bonus.
There is a new price regime for the near future and that is $55-65 per barrel oil. As we
have seen no one is willing to do unconventional drilling at these prices since there isnt
any way to recover their investment from the early flush production phase (first three
months). Someone started asking the important questions: can we do better, should we
gather more data on the horizontal well bore, did we by-pass any pay? There are some
fields in Texas that are on their third Re-Fracks. That statement by itself says a lot about
the viability of Re-Fracking.

Our Slim Hole 3.5 inch Re-Frack tool system can be used to isolate the stage frac and
evaluate the reservoir parameters such as: permeability, reservoir pressure, fracture
half lengths, etc., prior to any completion string or stimulation program. It can then be
used to evaluate after any remedial work has been done. This is an E-coil system but it
can be run on jointed pipe as well, which we have done over the last 15 years here in
Canada and USA. Over 1500 DST's done so far in all kinds of well bore conditions and
with many different test objectives (vertical, deviated and 6.25 inch open hole).
Most of the horizontal wells that have been drilled in North America have not utilized
tracers. The operators have just followed the whims of the big service companies like
Big Blue or whoever they hired for their frac jobs. Unfortunately little attention was paid
to doing it correctly the first time. No real science was done so very little was
understood, hence the phrase Indiscriminate Fracing. The situation has changed with
oil in the $55-65 / BBL range.
Everyone has to pay attention to doing it right the first time. Our system is more like a
"surgical tool" than a giant sledge hammer. Everyone in our industry is prone to using a
bigger hammer: more stages, more sand, bigger pumps, drop more balls, etc. That is
not the best methodology at lower prices and for maximizing recoverable reserves.
We propose our system be run in to the last stage at the toe and the packers set to
isolate that stage and a draw down and build up done to see what the reservoir
pressure is and what that stage has contributed in fluids and flow rates. An analysis of
the data and full evaluation would be done on the fly, during the test. If remedial work is
required it would be identified and carried out prior to moving up-hole to the next stage.
This process would be continued until there was a map of the entire well bore. This will
show where the production was coming from, where improvements could be made and
those procedures could be carried out using our system on the same run. Acidizing,
nitrogen clean-up of near well bore damage or re-fracking at various levels as required
and specialized for each stage in order to restore flush production levels at greatly
reduced costs. How about recovering your re-fracking costs in the first 3 weeks instead
of 2 months?
So lets embrace the new paradigm shift to $55-65 per barrel oil and put on our thinking
caps. Leave the giant sledge hammers at home; forget about the $500,000 microseismic and Black Box software simulations. Lets get down to basics and use a simple
age old proven concept (DST) to map your horizontal well bores and Re-Frack only
where you need to and put all that extra cash to your bottom lines and pay bigger
dividends to your shareholders.

S-ar putea să vă placă și