Documente Academic
Documente Profesional
Documente Cultură
1.1
Mobilization: This item provides for the expenses involved in mobilization of Contractor's
plant and personnel. It includes but is not limited to providing temporary facilities, housing
and messing, transportation, visas, residential permits, customs clearance and customs
claims, work permits, and all applicable licenses and authorizations, and for immigration of
personnel as appropriate.
1.2
Demobilization and Clean up: This item provides for the expenses involved in
demobilization of Contractor's plant and personnel. It includes but is not limited to
transportation, exit visas, custom clearance, all applicable authorizations, and for
emigration of all personnel as appropriate. Upon completion of all work, the premises within
the areas embraced by the work shall be clean and free from refuse resulting from work
performed.
2.0
A.
Unless otherwise specifically stated in the Price and Payment Provisions or herein, the
following shall be deemed to be included with all items:
1. Fitting and fixing materials and goods in position.
2. Plant and all costs in connection therewith.
3. Removal and restoration of facilities, structures, utilities or pavement removed during
performance of the work.
4. Waste of materials and disposal of same.
5. Disposal of all debris and excess materials, as directed by Royal Commission.
6. Testing of materials and systems and all quality control and assurance
requirements.
May 2014
01150-1
B.
All unit price items shall be paid at the rates set forth in the Price and Payment Provisions
and subject to inspection(s) by the Royal Commission's Authorized Site Representative. Unit
prices include all labor, material, transportation, placement, testing consumable supplies,
preparation of shop drawings and as-built drawings, equipment and services necessary to
deliver complete and functioning installations, units and systems built in accordance with
specifications, plans, and drawings approved by the Royal Commission, whether or not
specifically mentioned below. Compensation for work which may be required to produce a
complete operating system, but which may not be specifically included in one of the pay
items, shall be deemed to be included in one or more of the pay items listed of which it is an
integral part, and no additional compensation will be provided. All field measurements,
surveys, and calculations of quantities for payment purposes shall be performed by the
Contractor and confirmed by the Royal Commission.
C.
The scope of work of each unit price is not necessarily limited to the items given in the
descriptions but shall include everything necessary to complete the work in accordance with
the detailed drawings and these specifications.
D.
Where reference is made to "earth work" or "excavation and backfill" in the descriptions, this
shall be deemed to include excavation in whatever material encountered, to the lines and
grades specified as shown on drawings; backfill and compaction in layers as specified,
testing and quality control and the disposal of surplus material.
E.
Where reference is made to "concrete" or "reinforced concrete" in the descriptions, this shall
be deemed to include all necessary formwork, reinforcement, moisture/vapor barrier, damp
proofing/waterproofing, embedded steel, ladder rungs, water stops, expansion jointing
materials, sealing and jointing compounds, all accessories, curing and testing.
F.
The Contractor shall be responsible for providing the Royal Commission with accurate
measurements of all work accomplished. The Royal Commission shall have the right to verify
measurements made by the Contractor.
G.
The unit price items defined in the Price and Payment Provisions and listed in the Schedule
of Prices and Quantities are measured in accordance with the methods described below,
which shall also be used for any subsequent re-measurement of the work.
The term meter used in the Schedule shall be either linear, square or cubic, and indicated by
the symbols LM, SM and M3.
Measurement of concrete shall be "neat quantities" and based on the dimensions indicated
on the drawings.
Where the unit of measure is the meter, quantities shall be measured to the nearest whole
unit, fractions of a unit less than half shall be disregarded and all other fractions regarded as
a whole unit.
Where the application of the above paragraph causes an entire item to be eliminated, such
item shall be enumerated stating the size or weight as applicable.
May 2014
01150-2
SITE WORK:
02.01.
CIVIL
02.01.01.
Site Preparation
02.01.01.01.B
02.01.01.02.B
Site Clearing and Grading: Work under this item includes, but is not
necessarily limited to, removal and disposal of all unsuitable material, debris,
stones, waste, rubble (dumped), organic matters, other deleterious material,
vegetations, stumps, roots and other obstructions interfering with clearing
operations, scarifying the surface to a depth of 150 mm minimum from the
existing surface elevation and proof rolling. It shall include excavation to
required levels shown on the drawings, backfilling with suitable material and
compaction. All unsuitable materials shall be hauled and disposed to Royal
Commission Sanitary Landfill Area (located near KM32) for disposal.
Measuring for payment shall be measured by square meter of materials for the
clearing and grading work performed within the limits of the work for the entire
job site.
02.01.01.03.B
Borrow Material for Grading and Backfilling: Borrow material for grading
and backfilling includes, furnishing all borrow material from a borrow pit
outside Royal Commission property; all hauling, stockpiling, scarification of
existing surfaces, spreading, watering, mixing, compacting, grading and/or
backfilling to achieve design elevations by filling with borrow material, and all
associated sampling and testing, all in accordance with contract drawings and
specifications. Borrow material shall not be utilized until all suitable on-site cut
material has been exhausted.
Borrow material and rough grading shall be measured by the cubic meter,
complete in place. Prior to initiating placement of borrow material, crosssections of the compacted surface upon which the borrow material will be
placed shall be made at uniform intervals not exceeding 25 meters. Upon
completion of the construction of the compacted borrow material; crosssections of the compacted surface shall be made at the same locations and in
the same plane as the original cross-sections. The volume shall be calculated
from the cross-sections using the Average End Area method.
May 2014
01150-3
02.01.02.
02.01.02.01.B
02.01.02.02.B
02.01.02.03.B
Concrete Edger (100 x 300 mm): Work includes all necessary excavation,
formwork, concrete work, expansion joints, joint fillers and sealers, backfilling
and compacting, painting etc. complete.
Measurement shall be per linear meter, as verified by field measurement.
02.01.02.04.B
02.01.02.05.B
02.01.02.06.B
Granular Base Course: Work under this item includes the supply, placement
and compaction to 100 mm thickness of granular base course material in the
number of layers specified, and testing and quality control. Where applicable.
Measurement shall be by the square meter of compacted granular base
course in place, as calculated from the Contract Drawings and verified by field
measurements. Field measurements shall include verification of the required
thickness.
May 2014
01150-4
02.01.02.07.B
Asphalt Concrete Base Course (65mm Thick): The work under this item
includes, surface preparation and application of prime coat; the procurement,
hauling, spreading, rolling and compaction of asphaltic concrete layer (65 mm
thick for roads) ; and the necessary testing and quality control, all in
accordance with the Contract Drawings and Specifications where applicable.
Measurement shall be by the square meter of paving installed, as calculated
from the Contract Drawings and verified by field measurements. Field
measurements shall include verification of the required thickness.
Measurement shall be to the extent of the required constant thickness and
shall exclude tapered edges and paving over-runs which shall be deemed
included in the price of the full thickness asphaltic concrete base course.
02.01.02.08.B
Asphalt concrete Wearing Course: The work under this item includes,
surface preparation and application of tack coat; the procurement, hauling
spreading, rolling and compaction of asphaltic concrete (50 mm thick ); and
the necessary testing and quality control, all in accordance with the Contract
Drawings and Specifications. Where applicable.
Measurement shall be by the square meter of paving installed, as Calculated
from the Contract Drawings and verified by field measurements. Field
measurements shall include verification of the required thickness.
Measurement shall be to the extent of the required constant thickness and
shall exclude tapered edges and paving over- runs which shall be deemed
included in the price of the full thickness asphalt concrete wearing course.
02.01.03.
02.01.03.01.
02.01.03.01.01. B
02.01.03.01.02. B
02.01.03.02.B
May 2014
01150-5
02.01.03.03.B
Clean out: shall include supply and installation of Cleanouts, including pipes,
bends, concrete surround, cover and frame, excavation, concrete beds and
surrounds of cover and frame.
Measurement shall be per each cleanout completed and tested.
02.01.03.04.B
02.01.04.
02.01.04.01.
02.01.04.01.01.B
02.01.04.01.02.B
02.01.04.02.B
Gate Valve: Work includes supply and installation of gate valve, Surface box
associated fittings and accessories, for a complete and Operate able valve
assembly, corrosion protection coating, testing and disinfecting.
Measurement shall be per each valve assembly of applicable size,
installed and tested.
02.01.04.03.B
Water Meter Assembly: Work includes supply and installation of water meter
assembly, Surface box associated fittings and accessories, for a complete and
Operate able meter assembly, corrosion protection coating, testing and
disinfecting.
Measurement shall be per each complete assembly installed and tested and
as shown on drawings.
02.01.05.
Irrigation System
02.01.05.01.
May 2014
01150-6
02.01.05.01.
02.01.05.01.01.B
02.01.05.01.02.B
02.01.05.01.03.B
Work includes supply and installation of uPVC class-V pipe-work and sleeve
uPVC Class 3, excavation, backfilling and compaction, warning/ detection
tape, jointing, thrust block, anchor block, concrete encasement, fitting,
trenching, road cutting, interface connections, connection to the existing
lines/system, stub outs, reducers and concrete encasement, cutting of road,
restoration of surface to its original conditions, disposal of waste materials to
the designated areas etc. and restoration of surface to its original conditions.
Also, includes testing of all pipes.
Measurement shall be per linear meter for each diameter of pipe installed and
tested. Measurement shall be made along the centerline of the pipe with no
deductions made for fittings and valves chambers.
02.01.05.02.B
Water Meter Assembly and Concrete Chamber: Work includes supply and
installation of water meter including flexible couplings, flanged adapter,
associated fittings and accessories, jointing, excavation, reinforced concrete
chamber, cover and frame, fiberglass ladder, pipework inside chambers and
outside up to the limit of pay item.
Measurement shall be per each Water meter with chamber completely
installed and tested.
02.01.05.03.B
Remote Control Valve: Work includes supply and installation of gate valves,
associated fittings, flange adapters, accessories, jointing, concrete pads,
collars, bases and surrounds, excavation, concrete chamber and making
connections to pie work complete as detailed on drawings.
Measurement shall be per each gate valve with chamber installed and tested.
02.01.05.04.B
02.01.05.05.B
02.01.05.06.B
Flush Valve: Work includes supply and installation of Flush valve, jointing,
coating, wrapping and corrosion protection, etc. and making connection to
pipe work complete as detailed on drawings.
Measurement shall be per each Flush valve installed and tested.
May 2014
01150-7
02.01.06.
LANDSCAPING:
02.01.06.01.B
General Trees and Palms: Supply and planting of trees with straight trunk and
healthy foliage and free from any pests and diseases. Include excavation of
tree pit, wood stakes, gravel mulch, sweet sand mix with peatmoss, fertilizers
for planting, GI Steel (2 Ea) painted with green color, transporting to a place
determined by the Royal Commission, disposal of excavated material and all
other related works necessary to complete the work as per contract drawing.
The Item shall be measured as lot unit planted in place.
02.01.06.02.B
02.01.06.03.B
Succulent Plants: Work shall include supply and planting of succulents, sweet
sand mix and peatmoss, fertilizer for planting area, drainage stone, stone
mulch, permeable filter membrane , transportation to a place determined by
the Royal Commission and all accessories according to contract drawing and
specifications.
The item shall be measured as lot unit planted in place.
02.01.06.04.B
Ground Cover: Work includes ground covers, sand layers, gravel layer as
shown in detail drawing.
The item shall be measured as lot unit planted in place.
02.01.06.05.B
02.01.07.
HARDSCAPE:
02.01.07.01.B
Concrete Trash Bin: item shall include all necessary excavation, supply,
placement, finishing and curing of concrete trash bin and all incidental item as
required to complete the work as per detailed drawing an specifications.
item shall be measured as lot of complete installation of concrete trash bin.
02.01.07.02.B
May 2014
Water Cooler Fountain: item shall include all necessary excavation, supply,
placement, finishing, plumbing and curing of outdoor water cooler fountain
and all incidental item as required to complete the work as per detailed
drawing.
01150-8
Sitting Bench: item shall include all necessary excavation, supply, placement,
finishing, and curing of outdoor sitting bench and all incidental item as
required to complete the work as per detailed drawing.
item shall be measured as lot of complete supply and installation of sitting
bench.
02.02.
02.02.01.
02.02.01.01.A
02.02.01.02.B
Supply: This shall include all accessories, and factory installed current
transformers, current limiting and overload sensing removable fuses, terminal
bushing, cable fault indicators and sensors, 4 position loop switch as shown on
the drawings; it shall also include delivery to site, storage, field verification of
material at site in good condition, free of any damage in transit, and
construction of concrete pad with ducts.
Installation: This shall include setting of the unit on foundation with concrete
protection, anchoring, seal around pad, grounding, connection and supporting
of high voltage cables, and field tests of equipment for electrical and
mechanical performance in accordance with the manufacturer's
recommendations and all associated sampling and testing, all in accordance
with the contract drawings and specifications.
Package Substation shall be measured per each unit complete in place, tested
and ready for energizing.
02.02.02.
Metering System:
02.02.02.01.A
02.02.02.02.B
May 2014
01150-9
02.02.03.
02.02.03.01.A
02.02.03.02.B
02.02.04.
02.02.04.01.A
02.02.04.02.B
Work includes supply and installation of ducts with duct supports and spacers,
grounding cable, trenching and excavations, concrete bed, encasement of
concrete with expansion joints where required, sealing of spare ducts, duct
sealant, warning paint and mandrel test.
Scope includes but shall not to be limited to backfilling, compaction and
restoration of area to required finish grade state.
Measurement shall be per linear meter of duct bank installed and surface area
to finish grade state.
02.02.05.
02.02.05.01.B
02.02.06.
02.02.06.01.A
02.02.06.02.B
02.02.06.03.B
02.02.07.A&B
02.02.08.
02.02.08.01.A
02.02.08.02.B
02.02.08.03.B
May 2014
01150-10
02.02.09.01
02.02.09.01.01.B
02.02.09.02.
Light Pole:
02.02.09.02.01.B
to 03.B
Work includes supply and installation of lighting poles with one or two arm
extender, or for top mount complete with pole base cover, fuse holder with
fuse, bolts & nuts and other required materials as shown on drawings and
specifications.
Measurement shall be per each of light pole of given type completely installed
and tested.
02.02.09.03.
Lighting Fixtures:
02.02.09.03.01.A
02.02.09.03.01.B
02.02.09.03.02.B
02.02.09.03.03.A
02.02.09.03.03.B
Work includes supply, delivery and installation of lighting fixture including all
materials and works required to complete the installation in accordance with
the drawings and specifications.
02.02.09.04.
02.02.09.04.01.B
02.02.09.04.02.B
02.02.09.05.01.B
May 2014
01150-11
02.02.09.06.B
02.02.10.A&B
02.02.11.A
02.03.
Telecommunication System
02.03.01.
02.03.01.01.A&B
Work includes supply and installation of ducts, couplings and other associated
fittings, draw wires, excavation, concrete bed and surround, warning tape,
backfilling and soil reinstatement and making all the ducts clear of obstruction
on completion. The number and diameter of ducts shall be as shown on
drawings.
Measurement shall be as per linear meter for each size of duct bank
completed.
02.03.02.
02.03.02.01.B
May 2014
01150-12
BUILDING WORKS
03.
STRUCTURAL
03.01.
Concrete:
03.01.01.A&B
03.01.02.A&B
May 2014
01150-13
Hordi Slab System: This item includes reinforced concrete slabs, joists and
bricks used for the roofing system as shown on drawings.
a). Unit price shall include the execution of fixing formworks, preparation of
bar bending schedule; placing and fixing steel reinforcements; pouring
concrete, fixing all embedded items; fixing all construction joint materials as
indicated on the detailed drawings; application of approved curing material;
clean-up, removal and disposal of all debris materials into dump site area as
directed by the Royal Commission; and material testing for concrete.
b). Unit price shall further include the supply of all the materials as above
mentioned items - such as formworks, uncoated reinforcement; embedded
items, approved curing materials, block works, and all materials for
construction joints as indicated on the drawings, etc..
Measurement shall be per square meter of reinforced concrete
place.
installed in
04.
MASONRY WORKS
04.01.
04.01.01.A&B
04.01.02.A&B
04.01.03.A&B
Shall include all work, materials, equipment & all associated work necessary
for complete installation of specified types of CMU exterior & interior walls,
pipe chase at toilets & downspouts, rails for ramps & steps in approved
mortar & grout to include lintel & bond beams, reinforcing steel & solidgrouting of fire-rated walls.
Item shall be measured per square meter of installed CMU wall system.
04.02.A&B
04.03.A
Ablution Seats: Shall include all work, materials, equipment & all
associated work necessary for complete installation of ablution seats to
include reinforced concrete seat base, marble work, mortar bedding,
adhesives & accessories required for a complete installation.
Item shall be measured per each installed ablution seat.
04.04.A&B
May 2014
Curbs at Ablution & Harris Toilet: Shall include all work, materials,
equipment & all associated work necessary for complete installation of curbs
to include reinforced concrete base, ceramic tile work, mortar bedding,
01150-14
METALS
05.01.
Metal Flashing:
05.01.01A&B
05.01.02.A&B
Shall include all work, materials, equipment & all associated work necessary
for a weather tight installation of sheet aluminum flashings, sheet lead flashing
for pipe penetrations in true & precise line with movement provision, to include
corrosion-resistant fasteners & clips, & sealants.
Item shall be measured per linear meter of installed flashing except where
noted per each item on the Schedule of Prices and Quantities.
05.02.A&B
Handrail Assembly for Ramps Steps and Guard rails: Shall include all
work, materials, equipment & all associated work necessary for complete
installation of stainless steel pipe handrails in true & precise line including
corrosion-resistant anchors, brackets, fixings; & accessories required for
complete installation of handrail assembly.
Item shall be measured per linear meter of installed handrail assembly for
ramps and steps.
05.03.
05.03.01.A&B
05.03.02.A&B
05.04.A&B
Hilal Assembly: Shall include all work, materials, equipment & all associated
work necessary for complete installation of hilal; to include but limited to;
anchors, brackets & fixings; & accessories required for complete installation
of hilal assembly in true & precise line as detailed on drawings and
specifications.
Item shall be measured per each installed hilal assembly.
05.05.A&B
Steel Grating Platform: Shall include all work, materials, equipment & all
associated work necessary for complete installation of grating Platform; to
include but limited to; anchors, brackets & fixings; & accessories required for
complete installation of steel grating platform.
Item shall be measured per linear meter installed steel grating platform.
May 2014
01150-15
05.06.B
06.
06.01.
06.01.01.A&B
06.01.02.A&B
Shall include all work, materials, equipment & all associated work necessary
for complete installation of niches for shoe racks to include reinforced CMU
wall, reinforced concrete top & base, cement plaster, gypsum cornice
moulding, marble skirting, mortar bedding, adhesives, sealants &
accessories required for a complete installation.
Item shall be measured per each installed niche for shoe racks.
06.02.
06.02.01.A&B
06.02.02.A&B
06.02.03.A&B
Quran Shelf:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of Quran shelves to include hardware, anchors,
shims and paint finish.
Item shall be measured per each installed quaran shelf.
06.03.A&B
Mihrab & Minber: Shall include all work, materials, equipment & all
associated work necessary for complete installation of marble & wood works
with paint finish at mihrab & minber as shown on contract drawings &
specifications.
Item shall be measured per each installed mihrab & minber.
06.04.A&B
Corian Vanity Counters: Shall include all work, materials; but not limited to
marble countertop, backsplash & fascia; reinforced concrete slab base; with
opening for lavatory; and all associated work necessary for complete
installation of counter assembly in true and precise line.
Item shall be measured per each completely installed counter assembly.
06.05.B
07.00
May 2014
07.01.
07.01.01.A&B
07.01.02.A&B
07.01.03.A&B
08.
08.01.
08.01.01.A to 13.A
08.02.
08.02.01.A to 03.A
May 2014
01150-17
08.03.
08.03.01.A
08.
08.01.
08.01.01.B to 09.B Shall include all work, materials, equipment and all associated work
necessary for complete installation of wood doors & hollow metal frames in
true & precise line; to include but not limited to; hardware, glazing, fire rating
as required, corrosion-resistant anchors, shims, sealants, & paint finish.
Item shall be measured per each installed door assembly.
08.02.
08.02.01.B to 08.B
08.03.
Mashrabia:
08.03.01.B
Shall include all work, materials, equipment and all associated work
necessary for complete installation of hardwood mashrabia with arabic pattern
in true and precise line; to include but not limited to; wood framing, anchors,
shims, sealants, and paint finish.
Item shall be measured per square meter of installed mashrabia assembly.
09.
FINISHES
09.01.
Floor Finishes:
09.01.01.A&B
09.01.02.A&B
09.01.03.A
09.01.04.B
09.01.05.A&B
May
2014
09.01.06.A&B
09.01.07.A &B
09.01.08.B
Shall include all work, materials, equipment and all associated work
necessary for complete installation of terrazzo slabs; marble finish for steps,
01150-18
stair treads and risers; marble thresholds; ceramic porcelain tiles; ceramic
unglazed tiles, ceramic rib-form tiles, vinyl tiles, epoxy paint; and carpet with
cushion including substrate preparation, self-levelling compounds, adhesives,
mortar bedding, grouting, liquid-applied waterproofing with separation layer at
toilet and ablution areas, and any other items or accessories required for a
complete installation.
Items shall be measured per square meter of installed flooring system
except where noted per linear meter item on the Schedule of Prices and
Quantities.
09.02.
09.02.01.A&B
09.02.02.A&B
09.02.03.A&B
09.02.04.B
09.02.05.A&B
09.02.06.A&B
Wall Finishes:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of cement plaster; marble cladding, GRC cladding,
marble casings, trims & sills for doors & windows; stone cladding, fire rated &
regular gypsum boards with metal support system; ceramic tile glazed;
ceramic tile corner trims; including substrate preparation, adhesives, mortar
bedding, grouting, lathing, corrosion-resistant anchors & clips required for
stone & marble cladding; & any other items or accessories required for a
complete installation.
Item shall be measured per square meter of installed wall finish except where
noted per linear meter on the Schedule of Prices & Quantities.
09.03.
09.03.01.A&B
09.03.02.A
Wall Skirting:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of specified wall skirting including substrate
preparation, adhesives, mortar bedding, & any other items or accessories
required for a complete installation.
Items shall be measured per linear meter of installed wall skirting.
09.04.
09.04.01.A&B
09.04.02.A&B
09.04.03.A&B
Ceiling Finishes:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of suspended seamless gypsum wallboards, gypsum
board false beams, ceiling tiles, cement plaster, gypsum cornice moldings,
wood trims for ceiling tiles, water resistant gypsum board, access panels,
metal support systems, & accessories required for a complete installation.
Item shall be measured per square meter of installed ceiling finish except
where noted per linear meter & each on the Schedule of Prices &
Quantities.
09.05.
09.05.01.A&B
09.05.02.A&B
09.05.03.A&B
May
2014
09.05.04.A&B
Paint Systems:
Shall include all work, materials, equipment & all associated work necessary
01150-19
SPECIALTIES
10.01.
Toilet Accessories:
10.01.01.A&B
10.01.02.A&B
10.01.03.A&B
10.01.04.B
10.01.05.B
10.01.06.A&B
10.01.07.A&B
10.01.08.A&B
12.
Shall include all work, materials, equipment & all associated work necessary for
complete installation of accessories.
Item shall be measured per each installed toilet accessory.
FURNITURE AND FURNISHING:
12.01.A&B
12.02.A&B
12.03.A&B
12.04.B to 07.B
12.08.A
Shall include all work, materials, equipment & all associated work necessary
for complete installation of furniture and furnishing such as table, chair, bed
steel cabinet, quran shelves, shoe racks to include hardware, anchors, shims
& paint finish.
Item shall be measured per each installed furniture and furnishing item.
15.
15.01.
PLUMBING
15.01.01.
15.01.01.
15.01.01.01 A&B to
15.01.01.06.A&B
Domestic Cold and Hot Water System (copper pipe & pipe fittings): The
Item shall include the supply, installation testing and commissioning of pipe,
fittings, supports, sleeves, accessories and equipment necessary for a
complete and operational domestic potable water system within the building.
Item shall be measured per linear meter of each size of pipe installed with
necessary fittings and supports installed as shown on the drawings and
specifications.
15.01.02.
15.01.02.01.A
15.01.02.02.A&B
Domestic Potable Water System (uPVC pipe & fittings, class 5):
The item shall include the supply, installation testing and commissioning of
pipe, fittings, supports, sleeves, accessories and equipment necessary for a
complete and operational domestic potable water system within the building.
Item shall be measured per linear meter of each size of pipe installed with
necessary fittings and supports installed as shown on the drawings and
specifications.
15.01.03.
15.01.03.01.A&B
15.01.03.02.A&B
May 2014
15.01.03.03.B
15.01.03.04.B
01150-20
Isolating Valve:
Shall include supply, installation of isolating valves with all fittings, supports
necessary to provide satisfactory operation as per specifications and
drawings.
Item shall be counted per each size installed.
15.01.05.
15.01.05.01.A&B
15.01.06.
15.01.06.01.A
15.01.06.02.B
15.01.06.03.B
15.01.07.
15.01.07.01.A&B
15.01.07.02.A&B
15.01.07.03.B
15.01.07.04.A&B
15.01.08.
15.01.08.01.A&B
May 2014
01150-21
15.01.09.
15.01.09.01.A&B
Floor Cleanout:
Shall include supply, installation of floor cleanout cast iron type and all
necessary work as per specifications and drawings.
Item shall be counted as per each size of unit installed.
15.01.10.
15.01.10.01.A
15.01.10.02.B
15.02.
PLUMBING FIXTURE
15.02.01.A&B
15.02.02.A&B
15.02.03
15.02.03.01. A&B
Lavatory
Lavatory Type (LAV-1): Shall include supply, installation of lavatory LAV-1
complete with mixer pop-up waste, P-trap angle valves, flexible connections
& other required accessories as per detailed drawings and specifications.
Item shall be counted per each unit installed.
15.02.04.A&B
15.02.05.B
May 2014
Shower Tray: Shall include supply, installation of shower complete with all
accessories as per specifications and drawings.
01150-22
15.02.07.A&B
15.03.
FIRE PROTECTION
15.03.01.
PFE Dry Chemical (FE-1): Shall include supply and installation of portable
fire extinguisher (i.e. 4.5 kg portable fire extinguisher multi-purpose dry
chemical powder type both 4.5 kg wall-mounted) as shown in drawings and
specifications complete with all accessories meeting the requirements of
NFPA 10.
Item shall be counted as per each unit installed.
15.04.
HVAC
15.04.01.A&B
15.04.02.
Exhaust Fans
15.04.02.01.
15.04.02.01.01.A&B
15.04.02.01.02.A&B
15.04.02.01.03.A
May 2014
16.
16.01.
16.01.01.A
16.01.02.A&B
16.01.03.A&B
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of Low Voltage Panel consisting of
power circuit breakers, ammeter, voltmeter, busbars, wire ways completely
assembled, wired, adjusted and tested at the factory including but not limited
to supply, delivery to site, storage, field verification of material received in
good condition and free from any damage in transit, mounting, alignment,
testing of components and filling out of directory.
Measurement shall be per each distribution board installed and field tested.
16.02.
16.02.01.B
16.02.02.A
16.03.
16.03.01.A
May 2014
01150-24
16.04.
16.04.01.B
16.05.
16.05.01.A&B
16.05.02.B
16.05.03.A
16.05.04.A&B
16.05.05.B
16.05.06.A
16.05.07.A&B
16.05.08.B to10.B
16.05.11.A
16.05.12.A&B
16.05.13.A
16.05.14.A&B
16.05.15.B
16.05.16.A to 21.A
16.06.
16.06.01.A&B
16.06.02.B
16.06.03.A&B
Lighting Fixtures:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of lighting fixtures including but not
limited to circuit connection, grounding, mounting, alignment, punching and
drilling of sheet metal body for conduit entry when necessary.
Installation shall include delivery of materials from storage to construction site,
handling, inspection, clean up or removal of construction debris.
Measurement shall be by each lighting fixture installed, connected to circuit
and tested.
Light Switches:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of light switches, single gang or
multiple gang outlet boxes with common cover plate and extension ring
when necessary, toggle switches rated 20 ampere, 230 volts, cover plate
including but not limited to circuit connection, grounding, mounting and
alignment.
Installation shall include delivery of materials from storage to construction
site, handling, inspection, clean up or removal of construction debris.
Measurement shall be by each light switch (one or in gang) installed,
connected to circuit and tested.
16.07.
16.07.01.A&B
16.07.02.A&B
16.08.
19.08.01.A&B
May 2014
16.09.A&B
Rigid and flexible conduits (PVC, RGS & EMT) and metal boxes
complete with supports and fittings:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of conduits & boxes including but
not limited to elbows, couplings, flexible conduits, connectors, bushings &
locknuts, boxes (outlet, pull and junction), box covers, supports, hangers
and pull wires.
Installation shall include delivery of materials from storage to construction
site, handling, inspection, clean up or removal of construction debris.
Measurement shall be by lot of completely installed raceways.
16.10.
16.10.01.A&B
16.11.A&B
Lightning Protection:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of lightning protection consisting of
air terminal or lightning rod, base, supports, high conductivity copper cable
or tape, bonding jumper, grounding grid (rods & bare copper cable) and
inspection pit.
Measurement shall be per lot for the completely installed and tested
lightning protection system.
16.12.
Telecommunications:
16.12.01.B
May 2014
01150-26
16.13.A&B
Fire Alarm & Detection System: Shall include all work, materials,
equipment, accessories and all associated work necessary for complete
installation of fire alarm and detection system consisting but not limited to
Fire alarm control panel, detectors, bells, automatic telephone dialer,
raceways and wires.
Installation shall include supply, delivery of materials from storage to
construction site, mounting, alignment, fixation, conduits and boxes, wiring,
testing and all other works required for a complete operational fire alarm and
detection system.
Measurement shall be per lot for the completely installed and tested fire
alarm and detection system.
May 2014
01150-27