SECTION 01150

MEASUREMENT AND PAYMENT


PART 1 - GENERAL
1.0
A.

FIXED PRICE ITEMS


Payment for all Fixed Price Items shall be made in accordance with Contractor's approved
detailed breakdown of cost as required by the Article entitled "Progress Payment Schedule
for Fixed Price Items" included in Part VI, Price, and Payment Provisions. The Fixed Price
includes full compensation for all items of Work required by the Special Specifications and
Drawings, which are not specifically identified by individual Unit Price Pay Items.
Mobilization and Demobilization:

1.1

Mobilization: This item provides for the expenses involved in mobilization of Contractor's
plant and personnel. It includes but is not limited to providing temporary facilities, housing
and messing, transportation, visas, residential permits, customs clearance and customs
claims, work permits, and all applicable licenses and authorizations, and for immigration of
personnel as appropriate.

1.2

Demobilization and Clean up: This item provides for the expenses involved in
demobilization of Contractor's plant and personnel. It includes but is not limited to
transportation, exit visas, custom clearance, all applicable authorizations, and for
emigration of all personnel as appropriate. Upon completion of all work, the premises within
the areas embraced by the work shall be clean and free from refuse resulting from work
performed.

2.0

UNIT PRICE ITEMS

A.

Unless otherwise specifically stated in the Price and Payment Provisions or herein, the
following shall be deemed to be included with all items:
1. Fitting and fixing materials and goods in position.
2. Plant and all costs in connection therewith.
3. Removal and restoration of facilities, structures, utilities or pavement removed during
performance of the work.
4. Waste of materials and disposal of same.
5. Disposal of all debris and excess materials, as directed by Royal Commission.
6. Testing of materials and systems and all quality control and assurance

requirements.

7. General and administrative charges, overhead charges, and profit.

May 2014

01150-1

Contract No. PIC F-8159

B.

All unit price items shall be paid at the rates set forth in the Price and Payment Provisions
and subject to inspection(s) by the Royal Commission's Authorized Site Representative. Unit
prices include all labor, material, transportation, placement, testing consumable supplies,
preparation of shop drawings and as-built drawings, equipment and services necessary to
deliver complete and functioning installations, units and systems built in accordance with
specifications, plans, and drawings approved by the Royal Commission, whether or not
specifically mentioned below. Compensation for work which may be required to produce a
complete operating system, but which may not be specifically included in one of the pay
items, shall be deemed to be included in one or more of the pay items listed of which it is an
integral part, and no additional compensation will be provided. All field measurements,
surveys, and calculations of quantities for payment purposes shall be performed by the
Contractor and confirmed by the Royal Commission.

C.

The scope of work of each unit price is not necessarily limited to the items given in the
descriptions but shall include everything necessary to complete the work in accordance with
the detailed drawings and these specifications.

D.

Where reference is made to "earth work" or "excavation and backfill" in the descriptions, this
shall be deemed to include excavation in whatever material encountered, to the lines and
grades specified as shown on drawings; backfill and compaction in layers as specified,
testing and quality control and the disposal of surplus material.

E.

Where reference is made to "concrete" or "reinforced concrete" in the descriptions, this shall
be deemed to include all necessary formwork, reinforcement, moisture/vapor barrier, damp
proofing/waterproofing, embedded steel, ladder rungs, water stops, expansion jointing
materials, sealing and jointing compounds, all accessories, curing and testing.

F.

The Contractor shall be responsible for providing the Royal Commission with accurate
measurements of all work accomplished. The Royal Commission shall have the right to verify
measurements made by the Contractor.

G.

The unit price items defined in the Price and Payment Provisions and listed in the Schedule
of Prices and Quantities are measured in accordance with the methods described below,
which shall also be used for any subsequent re-measurement of the work.
The term meter used in the Schedule shall be either linear, square or cubic, and indicated by
the symbols LM, SM and M3.
Measurement of concrete shall be "neat quantities" and based on the dimensions indicated
on the drawings.
Where the unit of measure is the meter, quantities shall be measured to the nearest whole
unit, fractions of a unit less than half shall be disregarded and all other fractions regarded as
a whole unit.
Where the application of the above paragraph causes an entire item to be eliminated, such
item shall be enumerated stating the size or weight as applicable.

May 2014

01150-2

Contract No. PIC F-8159

PART 2 - DESCRIPTION AND MEASUREMENT OF UNIT PRICE ITEMS


02.00.

SITE WORK:

02.01.

CIVIL

02.01.01.

Site Preparation

02.01.01.01.B

Demolition: Work under this item includes demolition of sidewalk, asphalt


pavement, concrete curb and gutter and other any existing structure necessary
to accommodate new development as per drawings.
Measurement shall be in square meter of sidewalk, asphalt pavement and
concrete curb and gutter and other obstructions to include disposal of materials
is as per Royal Commission designated area.

02.01.01.02.B

Site Clearing and Grading: Work under this item includes, but is not
necessarily limited to, removal and disposal of all unsuitable material, debris,
stones, waste, rubble (dumped), organic matters, other deleterious material,
vegetations, stumps, roots and other obstructions interfering with clearing
operations, scarifying the surface to a depth of 150 mm minimum from the
existing surface elevation and proof rolling. It shall include excavation to
required levels shown on the drawings, backfilling with suitable material and
compaction. All unsuitable materials shall be hauled and disposed to Royal
Commission Sanitary Landfill Area (located near KM32) for disposal.
Measuring for payment shall be measured by square meter of materials for the
clearing and grading work performed within the limits of the work for the entire
job site.

02.01.01.03.B

Borrow Material for Grading and Backfilling: Borrow material for grading
and backfilling includes, furnishing all borrow material from a borrow pit
outside Royal Commission property; all hauling, stockpiling, scarification of
existing surfaces, spreading, watering, mixing, compacting, grading and/or
backfilling to achieve design elevations by filling with borrow material, and all
associated sampling and testing, all in accordance with contract drawings and
specifications. Borrow material shall not be utilized until all suitable on-site cut
material has been exhausted.
Borrow material and rough grading shall be measured by the cubic meter,
complete in place. Prior to initiating placement of borrow material, crosssections of the compacted surface upon which the borrow material will be
placed shall be made at uniform intervals not exceeding 25 meters. Upon
completion of the construction of the compacted borrow material; crosssections of the compacted surface shall be made at the same locations and in
the same plane as the original cross-sections. The volume shall be calculated
from the cross-sections using the Average End Area method.

May 2014

01150-3

Contract No. PIC F-8159

02.01.02.

Roads and Roadside Facilities

02.01.02.01.B

Stamped concrete (12 cm thick): Work shall include all necessary


excavation, formwork, supply, placement, finishing and curing of concrete for
stamped concrete along concrete curbs, preparation of substrate to receive
material with leveling and compaction; jointing, screed layer, and all incidental
item as required to complete the work as per detailed drawing an
specifications.
Measurement shall be per square meter of stamped concrete tiles installed in
place.

02.01.02.02.B

Concrete Curbs (170 x 400mm): Work includes all necessary excavation,


formwork, concrete work, expansion joints, joint fillers and sealers, backfilling
and compacting, painting etc. complete including testing for curbs and
depressed curbs at the ramps.
Measurement shall be per linear meter, as verified by field measurement along
the top of the curb.

02.01.02.03.B

Concrete Edger (100 x 300 mm): Work includes all necessary excavation,
formwork, concrete work, expansion joints, joint fillers and sealers, backfilling
and compacting, painting etc. complete.
Measurement shall be per linear meter, as verified by field measurement.

02.01.02.04.B

Precast Concrete Wheelstops: Work includes supply and construction of


concrete wheelstops in pattern as shown on drawings.
Measurement shall be per each unit of concrete wheelstop installed in place.

02.01.02.05.B

Reflectorized Thermoplastic Pavement Markings: Work includes


preparation of pavement surface, setting out and pre-marking, furnishing and
application of markings strips, lines and symbols as shapes as detail shown on
drawings, including hand application where required.
Pavement marking shall be measured by linear meter of painted lines
and per each marking shapes, as calculated from drawings and verified in
field.

02.01.02.06.B

Granular Base Course: Work under this item includes the supply, placement
and compaction to 100 mm thickness of granular base course material in the
number of layers specified, and testing and quality control. Where applicable.
Measurement shall be by the square meter of compacted granular base
course in place, as calculated from the Contract Drawings and verified by field
measurements. Field measurements shall include verification of the required
thickness.

May 2014

01150-4

Contract No. PIC F-8159

02.01.02.07.B

Asphalt Concrete Base Course (65mm Thick): The work under this item
includes, surface preparation and application of prime coat; the procurement,
hauling, spreading, rolling and compaction of asphaltic concrete layer (65 mm
thick for roads) ; and the necessary testing and quality control, all in
accordance with the Contract Drawings and Specifications where applicable.
Measurement shall be by the square meter of paving installed, as calculated
from the Contract Drawings and verified by field measurements. Field
measurements shall include verification of the required thickness.
Measurement shall be to the extent of the required constant thickness and
shall exclude tapered edges and paving over-runs which shall be deemed
included in the price of the full thickness asphaltic concrete base course.

02.01.02.08.B

Asphalt concrete Wearing Course: The work under this item includes,
surface preparation and application of tack coat; the procurement, hauling
spreading, rolling and compaction of asphaltic concrete (50 mm thick ); and
the necessary testing and quality control, all in accordance with the Contract
Drawings and Specifications. Where applicable.
Measurement shall be by the square meter of paving installed, as Calculated
from the Contract Drawings and verified by field measurements. Field
measurements shall include verification of the required thickness.
Measurement shall be to the extent of the required constant thickness and
shall exclude tapered edges and paving over- runs which shall be deemed
included in the price of the full thickness asphalt concrete wearing course.

02.01.03.

Sanitary Sewer System

02.01.03.01.

Gravity Sewer Pipes (Class III Pipe):

02.01.03.01.01. B
02.01.03.01.02. B

Work includes supply and installation of Class-III pipe (material as shown on


drawing and specification), excavation, backfilling and compaction, sheet piling
and dewatering as needed, concrete encasement, warning/detection tape,
jointing, interface connections, connection to the existing lines/system, stub
outs, and concrete encasement, cutting of road, restoration of surface to its
original conditions, disposal of waste materials to the designated areas etc. all
the works to be inclusive of all testing and commissioning.
Measurement shall be per linear meter for each diameter of pipe installed and
tested. Measurement shall be made along the centerline of the pipe with no
deductions made for manholes.

02.01.03.02.B

Manholes: Work includes supply and installation of fiberglass manholes with


frames and covers, including excavation, backfilling, concrete work, fiberglass
ladder, and pipe connection to manhole, waterproofing/damp proofing, grading
etc. complete as detailed on drawings.
Measurement shall be per each manhole completed and tested.

May 2014

01150-5

Contract No. PIC F-8159

02.01.03.03.B

Clean out: shall include supply and installation of Cleanouts, including pipes,
bends, concrete surround, cover and frame, excavation, concrete beds and
surrounds of cover and frame.
Measurement shall be per each cleanout completed and tested.

02.01.03.04.B

Sewer Services Connection : shall include supply and installation of


Sewer Services Connection, including pipes, bends, concrete surround, cover
and frame, excavation, concrete beds and surrounds of cover and frame.
Measurement shall be per each Sewer Services Connection completed and
tested.

02.01.04.

Potable Water System

02.01.04.01.

uPVC Pressure Pipes (Class V Pipe):

02.01.04.01.01.B
02.01.04.01.02.B

Work includes supply and installation of uPVC class-V pipe-work, excavation,


backfilling and compaction, warning/ detection tape, jointing, thrust block,
anchor block, concrete encasement, fitting, trenching, road cutting, interface
connections, connection to the existing lines/system, stub outs, reducers, and
concrete encasement, cutting of road, restoration of surface to its original
conditions, disposal of waste materials to the designated areas etc. and
restoration of surface to its original conditions. Also, includes disinfectioning
(flushing out and subsequent chlorination of all pipe runs and fittings and
testing of all pipes.
Measurement shall be per linear meter for each diameter of pipe installed and
tested. Measurement shall be made along the centerline of the pipe with no
deductions made for fittings and valves chambers.

02.01.04.02.B

Gate Valve: Work includes supply and installation of gate valve, Surface box
associated fittings and accessories, for a complete and Operate able valve
assembly, corrosion protection coating, testing and disinfecting.
Measurement shall be per each valve assembly of applicable size,
installed and tested.

02.01.04.03.B

Water Meter Assembly: Work includes supply and installation of water meter
assembly, Surface box associated fittings and accessories, for a complete and
Operate able meter assembly, corrosion protection coating, testing and
disinfecting.
Measurement shall be per each complete assembly installed and tested and
as shown on drawings.

02.01.05.

Irrigation System

02.01.05.01.

uPVC Pipe Class 5 and Sleeve uPVC Class 3:

May 2014

01150-6

Contract No. PIC F-8159

02.01.05.01.
02.01.05.01.01.B
02.01.05.01.02.B
02.01.05.01.03.B

Work includes supply and installation of uPVC class-V pipe-work and sleeve
uPVC Class 3, excavation, backfilling and compaction, warning/ detection
tape, jointing, thrust block, anchor block, concrete encasement, fitting,
trenching, road cutting, interface connections, connection to the existing
lines/system, stub outs, reducers and concrete encasement, cutting of road,
restoration of surface to its original conditions, disposal of waste materials to
the designated areas etc. and restoration of surface to its original conditions.
Also, includes testing of all pipes.
Measurement shall be per linear meter for each diameter of pipe installed and
tested. Measurement shall be made along the centerline of the pipe with no
deductions made for fittings and valves chambers.

02.01.05.02.B

Water Meter Assembly and Concrete Chamber: Work includes supply and
installation of water meter including flexible couplings, flanged adapter,
associated fittings and accessories, jointing, excavation, reinforced concrete
chamber, cover and frame, fiberglass ladder, pipework inside chambers and
outside up to the limit of pay item.
Measurement shall be per each Water meter with chamber completely
installed and tested.

02.01.05.03.B

Remote Control Valve: Work includes supply and installation of gate valves,
associated fittings, flange adapters, accessories, jointing, concrete pads,
collars, bases and surrounds, excavation, concrete chamber and making
connections to pie work complete as detailed on drawings.
Measurement shall be per each gate valve with chamber installed and tested.

02.01.05.04.B

Isolation Valve: Work includes supply and installation of isolation valve,


jointing, coating, wrapping and corrosion protection, etc. and making
connection to pipe work complete as detailed on drawings.
Measurement shall be per each Isolation valve with chamber installed and
tested.

02.01.05.05.B

Field Control Module (FCM) Assembly: Work includes supply and


installation of Irrigation field control module: electrical wiring in trench,
excavation, bakfilling, warning tape, associated fittings complete as per
specifications and drawings.
Measurement shall be per each completely irrigation field control module
installed in place.

02.01.05.06.B

Flush Valve: Work includes supply and installation of Flush valve, jointing,
coating, wrapping and corrosion protection, etc. and making connection to
pipe work complete as detailed on drawings.
Measurement shall be per each Flush valve installed and tested.

May 2014

01150-7

Contract No. PIC F-8159

02.01.06.

LANDSCAPING:

02.01.06.01.B

General Trees and Palms: Supply and planting of trees with straight trunk and
healthy foliage and free from any pests and diseases. Include excavation of
tree pit, wood stakes, gravel mulch, sweet sand mix with peatmoss, fertilizers
for planting, GI Steel (2 Ea) painted with green color, transporting to a place
determined by the Royal Commission, disposal of excavated material and all
other related works necessary to complete the work as per contract drawing.
The Item shall be measured as lot unit planted in place.

02.01.06.02.B

Shrubs: Work includes supply and planting of shrubs, staking, necessary


materials for landscaping sweet sand mix with peatmoss and fertilizers for
planting area, tying as shown in site-layout plan and as per RC standard
drawing detail No. RCL-L-1.
The item shall be measured as lot unit planted in place.

02.01.06.03.B

Succulent Plants: Work shall include supply and planting of succulents, sweet
sand mix and peatmoss, fertilizer for planting area, drainage stone, stone
mulch, permeable filter membrane , transportation to a place determined by
the Royal Commission and all accessories according to contract drawing and
specifications.
The item shall be measured as lot unit planted in place.

02.01.06.04.B

Ground Cover: Work includes ground covers, sand layers, gravel layer as
shown in detail drawing.
The item shall be measured as lot unit planted in place.

02.01.06.05.B

Grass: Work includes installation of grass by sodding and other associated


materials for landscaping and as shown in detail drawing.
The item shall be measured as lot of complete area of ground cover grass.

02.01.07.

HARDSCAPE:

02.01.07.01.B

Concrete Trash Bin: item shall include all necessary excavation, supply,
placement, finishing and curing of concrete trash bin and all incidental item as
required to complete the work as per detailed drawing an specifications.
item shall be measured as lot of complete installation of concrete trash bin.

02.01.07.02.B

May 2014

Water Cooler Fountain: item shall include all necessary excavation, supply,
placement, finishing, plumbing and curing of outdoor water cooler fountain
and all incidental item as required to complete the work as per detailed
drawing.

01150-8

Contract No. PIC F-8159

item shall be measured as lot of complete supply and installation of water


cooler fountain.
02.01.07.03.B

Sitting Bench: item shall include all necessary excavation, supply, placement,
finishing, and curing of outdoor sitting bench and all incidental item as
required to complete the work as per detailed drawing.
item shall be measured as lot of complete supply and installation of sitting
bench.

02.02.

ELECTRICAL POWER, LIGHTING AND TELECOMMUNICATIONS

02.02.01.

15kV Package Sub-station, Outdoor & Oil-filled Type, 13.8kV/400-230V:

02.02.01.01.A
02.02.01.02.B

Supply: This shall include all accessories, and factory installed current
transformers, current limiting and overload sensing removable fuses, terminal
bushing, cable fault indicators and sensors, 4 position loop switch as shown on
the drawings; it shall also include delivery to site, storage, field verification of
material at site in good condition, free of any damage in transit, and
construction of concrete pad with ducts.
Installation: This shall include setting of the unit on foundation with concrete
protection, anchoring, seal around pad, grounding, connection and supporting
of high voltage cables, and field tests of equipment for electrical and
mechanical performance in accordance with the manufacturer's
recommendations and all associated sampling and testing, all in accordance
with the contract drawings and specifications.
Package Substation shall be measured per each unit complete in place, tested
and ready for energizing.

02.02.02.

Metering System:

02.02.02.01.A
02.02.02.02.B

Work includes the supply and delivery of factory assembled 400-2000A


Service, Transformer Rated or Single Service, 200A 400/230VAC, 3 Phase
metering system comprises of but not limited to meter socket, circuit breaker
and test switch, current transformer, wiring and associated materials for a
complete electric energy metering in NEMA 4x cabinet with hinged and keyed
door.
Installation includes but shall not be limited to support on concrete base,
mounting, alignment, punching and drilling for conduit entry, grounding and
testing.
Measurement shall be per each of metering system completely installed,
tested and ready for energizing.

May 2014

01150-9

Contract No. PIC F-8159

02.02.03.
02.02.03.01.A
02.02.03.02.B

Medium Voltage Cables, Un-armored, 15kV, 25kA:


Work includes supply of 15kV cables of given sizes, pulling and laying the
cables in prepared concrete encased ducts and splicing as required including
testing. The cables shall be XLPE insulated. Installation includes but not
limited to splicing and termination of the cables and sealing of ducts.
Measurement shall be per linear meter of triplex single core cables as installed
and tested.

02.02.04.

Medium Voltage Duct banks, PVC Conduit encased in Concrete:

02.02.04.01.A
02.02.04.02.B

Work includes supply and installation of ducts with duct supports and spacers,
grounding cable, trenching and excavations, concrete bed, encasement of
concrete with expansion joints where required, sealing of spare ducts, duct
sealant, warning paint and mandrel test.
Scope includes but shall not to be limited to backfilling, compaction and
restoration of area to required finish grade state.
Measurement shall be per linear meter of duct bank installed and surface area
to finish grade state.

02.02.05.

Medium Voltage Duct banks, PVC Conduit encased in Structural


Concrete:

02.02.05.01.B

Same as item 02.02.04 but structural concrete.

02.02.06.

Low Voltage Duct banks, PVC Conduit encased in Concrete:

02.02.06.01.A
02.02.06.02.B
02.02.06.03.B

Same as item 02.02.04 but without grounding cable.

02.02.07.A&B

Equipment Pad, Concrete: This shall include concrete foundation compacting


the foundation soil beneath each pad, furnishing and installing forms;
furnishing and placement of reinforcing; placing and terminating the
underground PVC conduits; placing bare copper grounding conductors;
furnishing, placing, finishing, and curing Portland cement concrete for pads;
disposing of excavated material.
Measurement shall be per each equipment pad completely installed in place.

02.02.08.

Low Voltage single-core Cables, 0.6/1.0 kV, CU/XLPE/PVC:

02.02.08.01.A
02.02.08.02.B
02.02.08.03.B

Work includes supply, delivery and installation of XLPE insulated un-armored


copper, single-core cables. Installation includes but shall not be limited to
conduit, trenching, concrete encasement, splices, termination, duct sealant
and cable identifications.

May 2014

01150-10

Contract No. PIC F-8159

Installation includes excavation, backfilling and compaction, and clean up.


Measurement shall be per linear meter of single-core cables installed and
tested.
02.02.09.

Parking and Area Lighting System

02.02.09.01

Light Pole Foundation, Concrete:

02.02.09.01.01.B

This shall include excavation, compaction foundation soil beneath each


foundation, furnishing and installing forms; furnishing and placement of
reinforcement; furnishing, placing, finishing, and curing Portland cement
concrete; and disposing of excavated material.
Measurement shall be per each light pole foundation installed.

02.02.09.02.

Light Pole:

02.02.09.02.01.B
to 03.B

Work includes supply and installation of lighting poles with one or two arm
extender, or for top mount complete with pole base cover, fuse holder with
fuse, bolts & nuts and other required materials as shown on drawings and
specifications.
Measurement shall be per each of light pole of given type completely installed
and tested.

02.02.09.03.

Lighting Fixtures:

02.02.09.03.01.A
02.02.09.03.01.B
02.02.09.03.02.B
02.02.09.03.03.A
02.02.09.03.03.B

Work includes supply, delivery and installation of lighting fixture including all
materials and works required to complete the installation in accordance with
the drawings and specifications.

02.02.09.04.

Low Voltage Multi-core Cables, 0.6/1.0 kV, CU/XLPE/PVC direct buried:

02.02.09.04.01.B
02.02.09.04.02.B

Work includes supply, delivery and installation of XLPE insulated un-armored


copper, multi-core cables. Installation includes but shall not be limited to
conduit, trenching, concrete cap, warning tape, laying in trench, splices, taps,
termination and cable identifications.

Measurement shall be per each lighting fixture of given type completely


installed and tested.

Installation includes excavation, sand bedding, backfilling and compaction,


and clean up.
Measurement shall be per lot of multi-core cables installed and tested.
02.02.09.05.

Low Voltage single-core Cables, 0.6/1.0 kV, CU/XLPE/PVC:

02.02.09.05.01.B

Same as item 02.02.09.04 except single core cable installed in conduit.

May 2014

01150-11

Contract No. PIC F-8159

02.02.09.06.B

Lighting Panel (LPO), NEMA 4x Enclosure: Work includes purchase, supply,


delivery and installation of lighting panel in NEMA type 4x enclosure complete
with contactor, weekly digital programmable timer, circuit breakers, auto-handoff switch and other materials as per project specifications and as shown on
the drawings. Scope includes cable/ wire terminations, testing and
commissioning.
Installation includes but shall not be limited to concrete base, mounting,
alignment, punching and drilling for conduit entry, grounding, posting of panel
directory and testing.
Measurement shall be per each lighting panel completely installed and tested.

02.02.10.A&B

Grounding Electrode System (Groundings, Grounding cables, Earth pit):


Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of grounding system consisting but
not limited to, supply, delivery and installation of ground rods, grounding
cables, conduit sleeves, Earth Pit (Ground Well); testing of rod resistance to
earth; connection (exothermic in general and bolted at ground wells and
equipment), excavation, backfilling & compaction, and cleaning of debris.
Measurement shall be per lot of grounding electrode system installed and
tested.

02.02.11.A

Equipment Enclosure, Concrete: Work shall be as shown on the drawings


which includes but shall not be limited to concrete block, cement plaster, padlockable double swing door, concrete, curing, clean-up and other.
Measurement shall per each equipment enclosure completely installed in
place.

02.03.

Telecommunication System

02.03.01.

Telecommunication Duct bank, PVC Conduit encased in Concrete:

02.03.01.01.A&B

Work includes supply and installation of ducts, couplings and other associated
fittings, draw wires, excavation, concrete bed and surround, warning tape,
backfilling and soil reinstatement and making all the ducts clear of obstruction
on completion. The number and diameter of ducts shall be as shown on
drawings.
Measurement shall be as per linear meter for each size of duct bank
completed.

02.03.02.

Telecommunication Pullbox Concrete:

02.03.02.01.B

This work item is the same as item 02.13.02 except pullbox.

May 2014

01150-12

Contract No. PIC F-8159

BUILDING WORKS
03.

STRUCTURAL

03.01.

Concrete:

03.01.01.A&B

Reinforced Concrete in Sub-structure: Reinforced concrete to be used for


all below grade work up to the top of grade slab including base slabs with
thickenings, equipment supports, walls, columns below grade, pedestals,
lean concrete, foundation and steps etc.
a). Unit price shall include the execution of excavation, compaction,
preparation of sub-grade, application of termite control treatment to the
entire soil within the building area and up to the surrounding 200mm strip
beyond the building perimeter, and to all vertical areas of the excavation;
placing and compacting granular bed or hardcore under slab on grade;
placing of moisture vapor barrier (polyethylene); fixing the required
construction joint materials; application of concrete protection; fixing
formworks, preparation of bar bending schedule; placing and fixing steel
reinforcements; pouring concrete, fixing all embedded items; application of
approved curing material; clean-up, removal and disposal of all debris and
surplus materials into dump site area as directed by the Royal Commission;
and material testing for soil compaction and concrete.
b). Unit price shall further include the supply of all the materials as above
mentioned items - such as borrow or selected fill material, vapor barrier
(polyethylene), granular bed under slab on grade; concrete protection as
defined in section 07100 & 07110; formworks or epoxy coated reinforcement;
embedded items, termiticide solution for termite control treatment; and all
construction joints as indicated on the detailed drawings; water stop (if any)
etc.
Measurement shall be per cubic meter of reinforced concrete installed in
place.

03.01.02.A&B

Reinforced Concrete in Super-structure: This item includes reinforced


concrete to be used for the entire work above grade such as (normal/fair
faced as shown on drawings) in super structure for columns, suspended &
up-stand beams, suspended slabs, walls, stair, parapet, and canopies.
a) Unit price shall include the execution of fixing formworks, preparation of
bar bending schedule; placing and fixing steel reinforcements; pouring
concrete, fixing all embedded items; fixing all construction joint materials as
indicated on the detailed drawings; application of approved curing material;
clean-up, removal and disposal of all debris materials into dump site area as
directed by the Royal Commission; and material testing for concrete.
b) Unit price shall further include the supply of all the materials as above
mentioned items - such as formworks, uncoated or coated reinforcement;
embedded items, approved curing materials, block works, and all materials
for construction joints as indicated on the drawings, etc..

May 2014

01150-13

Contract No. PIC F-8159

Measurement shall be per cubic meter of reinforced concrete installed in


place.
03.01.03.B

Hordi Slab System: This item includes reinforced concrete slabs, joists and
bricks used for the roofing system as shown on drawings.
a). Unit price shall include the execution of fixing formworks, preparation of
bar bending schedule; placing and fixing steel reinforcements; pouring
concrete, fixing all embedded items; fixing all construction joint materials as
indicated on the detailed drawings; application of approved curing material;
clean-up, removal and disposal of all debris materials into dump site area as
directed by the Royal Commission; and material testing for concrete.
b). Unit price shall further include the supply of all the materials as above
mentioned items - such as formworks, uncoated reinforcement; embedded
items, approved curing materials, block works, and all materials for
construction joints as indicated on the drawings, etc..
Measurement shall be per square meter of reinforced concrete
place.

installed in

04.

MASONRY WORKS

04.01.

Concrete Masonry Unit (CMU) Walls:

04.01.01.A&B
04.01.02.A&B
04.01.03.A&B

Shall include all work, materials, equipment & all associated work necessary
for complete installation of specified types of CMU exterior & interior walls,
pipe chase at toilets & downspouts, rails for ramps & steps in approved
mortar & grout to include lintel & bond beams, reinforcing steel & solidgrouting of fire-rated walls.
Item shall be measured per square meter of installed CMU wall system.

04.02.A&B

Precast Concrete Scuppers: Shall include all work, materials, equipment


& all associated work necessary for complete installation of the scupper
drain system including splash block to include gravel stops, sealants &
specified paint finish.
Item shall be measured per each installed scupper assembly.

04.03.A

Ablution Seats: Shall include all work, materials, equipment & all
associated work necessary for complete installation of ablution seats to
include reinforced concrete seat base, marble work, mortar bedding,
adhesives & accessories required for a complete installation.
Item shall be measured per each installed ablution seat.

04.04.A&B

May 2014

Curbs at Ablution & Harris Toilet: Shall include all work, materials,
equipment & all associated work necessary for complete installation of curbs
to include reinforced concrete base, ceramic tile work, mortar bedding,
01150-14

Contract No. PIC F-8159

adhesives & accessories required for a complete installation.


Item shall be measured per linear meter per installed finishing works at curbs
of ablution and harris toilet areas.
05.

METALS

05.01.

Metal Flashing:

05.01.01A&B
05.01.02.A&B

Shall include all work, materials, equipment & all associated work necessary
for a weather tight installation of sheet aluminum flashings, sheet lead flashing
for pipe penetrations in true & precise line with movement provision, to include
corrosion-resistant fasteners & clips, & sealants.
Item shall be measured per linear meter of installed flashing except where
noted per each item on the Schedule of Prices and Quantities.

05.02.A&B

Handrail Assembly for Ramps Steps and Guard rails: Shall include all
work, materials, equipment & all associated work necessary for complete
installation of stainless steel pipe handrails in true & precise line including
corrosion-resistant anchors, brackets, fixings; & accessories required for
complete installation of handrail assembly.
Item shall be measured per linear meter of installed handrail assembly for
ramps and steps.

05.03.
05.03.01.A&B
05.03.02.A&B

Steel Ladder Assembly:


Shall include all work, materials, equipment & all associated work necessary
for complete installation of steel ladder; to include but not limited to; security
lock, anchors, brackets & fixings, paint finish & accessories required for
complete installation of ladder assembly in true & precise line.
Item shall be measured per each installed steel ladder assembly.

05.04.A&B

Hilal Assembly: Shall include all work, materials, equipment & all associated
work necessary for complete installation of hilal; to include but limited to;
anchors, brackets & fixings; & accessories required for complete installation
of hilal assembly in true & precise line as detailed on drawings and
specifications.
Item shall be measured per each installed hilal assembly.

05.05.A&B

Steel Grating Platform: Shall include all work, materials, equipment & all
associated work necessary for complete installation of grating Platform; to
include but limited to; anchors, brackets & fixings; & accessories required for
complete installation of steel grating platform.
Item shall be measured per linear meter installed steel grating platform.

May 2014

01150-15

Contract No. PIC F-8159

05.06.B

Aluminum Parapet Railing Assembly: Shall include all work, materials;


but not limited to extruded aluminum tubular frames; corrosion-resistant
anchors and fixings; and all associated work necessary for complete
installation of parapet decorative element assembly in true and precise line.
Item shall be measured per linear meter installed decorative element.

06.

WOOD AND PLASTIC

06.01.

Niche for Shoe Rack:

06.01.01.A&B
06.01.02.A&B

Shall include all work, materials, equipment & all associated work necessary
for complete installation of niches for shoe racks to include reinforced CMU
wall, reinforced concrete top & base, cement plaster, gypsum cornice
moulding, marble skirting, mortar bedding, adhesives, sealants &
accessories required for a complete installation.
Item shall be measured per each installed niche for shoe racks.

06.02.
06.02.01.A&B
06.02.02.A&B
06.02.03.A&B

Quran Shelf:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of Quran shelves to include hardware, anchors,
shims and paint finish.
Item shall be measured per each installed quaran shelf.

06.03.A&B

Mihrab & Minber: Shall include all work, materials, equipment & all
associated work necessary for complete installation of marble & wood works
with paint finish at mihrab & minber as shown on contract drawings &
specifications.
Item shall be measured per each installed mihrab & minber.

06.04.A&B

Corian Vanity Counters: Shall include all work, materials; but not limited to
marble countertop, backsplash & fascia; reinforced concrete slab base; with
opening for lavatory; and all associated work necessary for complete
installation of counter assembly in true and precise line.
Item shall be measured per each completely installed counter assembly.

06.05.B

Decorative GRC panel at Dome: Shall include all associated work,


materials, and accessories and all work necessary for complete installation of
grc decorative molding as shown on contract drawings and specifications.
Item shall be measured per lot of installed GRC.

07.00
May 2014

THERMAL AND MOISTURE PROTECTION


01150-16

Contract No. PIC F-8159

07.01.

Thermal and moisture protection

07.01.01.A&B

Inverted Roofing System: Shall include all work, materials, equipment,


accessories & all associated work necessary for complete installation of
roofing system to include substrate preparation, gravel & paver ballasts,
protection layer, insulation, modified bitumen membrane waterproofing &
flashing, preformed extruded aluminum counter-flashings, cant strips, &
sloping cement mortar screeds.
Item shall be measured per square meter of installed roofing system.

07.01.02.A&B

Spray-Applied Polyurethane Foam Roofing (SPUF) system: Shall


include all work, materials, equipment & all associated work necessary for
complete installation of specified SPUF system to include substrate
preparation, elastomeric waterproofing, cement plaster on corrosion-resistant
metal lath, fasteners, clips & accessories.
Item shall be measured per square meter installed SPUF roofing system.

07.01.03.A&B

Waterproofing Membrane Wet Areas: Shall include all work, materials,


equipment, accessories & all associated work necessary for complete
installation of waterproofing membrane for wet areas to include substrate
preparation and modified bitumen membrane waterproofing.
Item shall be measured per square meter of installed waterproofing
membrane at wet areas.

08.

DOORS AND WINDOWS


Item under this Division is Separated for Mosque Type (A) as shown on
the drawings.

08.01.
08.01.01.A to 13.A

Wood Doors on Metal Frames with Hardware Sets:


Shall include all work, materials, equipment and all associated work
necessary for complete installation of wood doors & hollow metal frames in
true & precise line; to include but not limited to; hardware, glazing, fire rating
as required, corrosion-resistant anchors, shims, sealants, & paint finish.
Item shall be measured per each installed door assembly.

08.02.
08.02.01.A to 03.A

Aluminum Windows with Glass and Glazing:


Shall include all work, materials, equipment and all associated work
necessary for complete installation of aluminum windows in true and precise
line; to include but not limited to; glazing, corrosion-resistant anchors, shims,
and sealants.
Item shall be measured per each installed window assembly.

May 2014

01150-17

Contract No. PIC F-8159

08.03.
08.03.01.A

Arabic Pattern Window Grilles and Screen:


Shall include all work, materials and all associated work necessary for
complete installation of this arabic pattern metal grilles and screen.
Item shall be measured square meter of installed window grille/screen
assembly.

08.

DOORS AND WINDOWS


Item under this Division is Separated for Mosque Type (B) as Shown on
the drawings.

08.01.

Wood Doors on Metal Frames with Hardware Sets:

08.01.01.B to 09.B Shall include all work, materials, equipment and all associated work

necessary for complete installation of wood doors & hollow metal frames in
true & precise line; to include but not limited to; hardware, glazing, fire rating
as required, corrosion-resistant anchors, shims, sealants, & paint finish.
Item shall be measured per each installed door assembly.
08.02.
08.02.01.B to 08.B

Aluminum Windows with Glass and Glazing:


Shall include all work, materials, equipment and all associated work
necessary for complete installation of aluminum windows in true and precise
line; to include but not limited to; glazing, corrosion-resistant anchors, shims,
and sealants.
Item shall be measured per each installed window assembly.

08.03.

Mashrabia:

08.03.01.B

Shall include all work, materials, equipment and all associated work
necessary for complete installation of hardwood mashrabia with arabic pattern
in true and precise line; to include but not limited to; wood framing, anchors,
shims, sealants, and paint finish.
Item shall be measured per square meter of installed mashrabia assembly.

09.

FINISHES

09.01.

Floor Finishes:

09.01.01.A&B
09.01.02.A&B
09.01.03.A
09.01.04.B
09.01.05.A&B
May
2014
09.01.06.A&B
09.01.07.A &B
09.01.08.B

Shall include all work, materials, equipment and all associated work
necessary for complete installation of terrazzo slabs; marble finish for steps,
01150-18

Contract No. PIC F-8159

stair treads and risers; marble thresholds; ceramic porcelain tiles; ceramic
unglazed tiles, ceramic rib-form tiles, vinyl tiles, epoxy paint; and carpet with
cushion including substrate preparation, self-levelling compounds, adhesives,
mortar bedding, grouting, liquid-applied waterproofing with separation layer at
toilet and ablution areas, and any other items or accessories required for a
complete installation.
Items shall be measured per square meter of installed flooring system
except where noted per linear meter item on the Schedule of Prices and
Quantities.
09.02.
09.02.01.A&B
09.02.02.A&B
09.02.03.A&B
09.02.04.B
09.02.05.A&B
09.02.06.A&B

Wall Finishes:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of cement plaster; marble cladding, GRC cladding,
marble casings, trims & sills for doors & windows; stone cladding, fire rated &
regular gypsum boards with metal support system; ceramic tile glazed;
ceramic tile corner trims; including substrate preparation, adhesives, mortar
bedding, grouting, lathing, corrosion-resistant anchors & clips required for
stone & marble cladding; & any other items or accessories required for a
complete installation.
Item shall be measured per square meter of installed wall finish except where
noted per linear meter on the Schedule of Prices & Quantities.

09.03.
09.03.01.A&B
09.03.02.A

Wall Skirting:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of specified wall skirting including substrate
preparation, adhesives, mortar bedding, & any other items or accessories
required for a complete installation.
Items shall be measured per linear meter of installed wall skirting.

09.04.
09.04.01.A&B
09.04.02.A&B
09.04.03.A&B

Ceiling Finishes:
Shall include all work, materials, equipment & all associated work necessary
for complete installation of suspended seamless gypsum wallboards, gypsum
board false beams, ceiling tiles, cement plaster, gypsum cornice moldings,
wood trims for ceiling tiles, water resistant gypsum board, access panels,
metal support systems, & accessories required for a complete installation.
Item shall be measured per square meter of installed ceiling finish except
where noted per linear meter & each on the Schedule of Prices &
Quantities.

09.05.
09.05.01.A&B
09.05.02.A&B
09.05.03.A&B
May
2014
09.05.04.A&B

Paint Systems:
Shall include all work, materials, equipment & all associated work necessary
01150-19

Contract No. PIC F-8159

for complete application of specified paint systems.


Item shall be measured per square meter of wall or ceiling areas to include GRC,
gypsum cornice and minaret wall.
10.

SPECIALTIES

10.01.

Toilet Accessories:

10.01.01.A&B
10.01.02.A&B
10.01.03.A&B
10.01.04.B
10.01.05.B
10.01.06.A&B
10.01.07.A&B
10.01.08.A&B

12.

Shall include all work, materials, equipment & all associated work necessary for
complete installation of accessories.
Item shall be measured per each installed toilet accessory.
FURNITURE AND FURNISHING:

12.01.A&B
12.02.A&B
12.03.A&B
12.04.B to 07.B
12.08.A

Shall include all work, materials, equipment & all associated work necessary
for complete installation of furniture and furnishing such as table, chair, bed
steel cabinet, quran shelves, shoe racks to include hardware, anchors, shims
& paint finish.
Item shall be measured per each installed furniture and furnishing item.

15.

MECHANICAL, PLUMBING, FIRE PROTECTION & HVAC

15.01.

PLUMBING

15.01.01.
15.01.01.
15.01.01.01 A&B to
15.01.01.06.A&B

Domestic Cold and Hot Water System (copper pipe & pipe fittings): The
Item shall include the supply, installation testing and commissioning of pipe,
fittings, supports, sleeves, accessories and equipment necessary for a
complete and operational domestic potable water system within the building.
Item shall be measured per linear meter of each size of pipe installed with
necessary fittings and supports installed as shown on the drawings and
specifications.

15.01.02.
15.01.02.01.A
15.01.02.02.A&B

Domestic Potable Water System (uPVC pipe & fittings, class 5):
The item shall include the supply, installation testing and commissioning of
pipe, fittings, supports, sleeves, accessories and equipment necessary for a
complete and operational domestic potable water system within the building.
Item shall be measured per linear meter of each size of pipe installed with
necessary fittings and supports installed as shown on the drawings and
specifications.

15.01.03.
15.01.03.01.A&B
15.01.03.02.A&B
May 2014
15.01.03.03.B
15.01.03.04.B

Hot Water Pipe Insulation:

01150-20

Contract No. PIC F-8159

Shall include supply, installation of pre- molded Fiberglass sectional pipe


thermal insulation for hot water pipes as per specifications and drawings.
Item shall be measured per linear meter of each size installed.
15.01.04.
15.01.04.01.A&B to
15.01.04.05.A&B

Isolating Valve:
Shall include supply, installation of isolating valves with all fittings, supports
necessary to provide satisfactory operation as per specifications and
drawings.
Item shall be counted per each size installed.

15.01.05.
15.01.05.01.A&B

Water Hammer Arrestor:


Shall include supply, installation of water hammer arrestor (with various
sizes) for cold & hot water pipes as per specifications and drawings.
Item shall be counted as per each size unit installed.

15.01.06.
15.01.06.01.A
15.01.06.02.B
15.01.06.03.B

Electric Water Heater:


Shall include supply, installation of storage water heater complete with
instruments, gauges, control valves, piping connection and all accessories
and devices necessary for satisfactory operation and as per specifications
and drawings. For central water storage heater, circulating pumps shall be
included.
Item shall be counted per each size unit installed.

15.01.07.
15.01.07.01.A&B
15.01.07.02.A&B
15.01.07.03.B
15.01.07.04.A&B

15.01.08.
15.01.08.01.A&B

Soil, Waste, Vent Piping System (piping and fittings):


Shall include supply, installation of uPVC pipe and fittings for internal pipes
and for vent piping on roof as per specifications and drawings.
Item shall be measured per linear meter of each size of pipe installed.
Floor Drain:
Shall include supply, installation of floor drain made of cast iron as per
specifications and drawings.
Item shall be counted as per each size of unit installed.

May 2014

01150-21

Contract No. PIC F-8159

15.01.09.
15.01.09.01.A&B

Floor Cleanout:
Shall include supply, installation of floor cleanout cast iron type and all
necessary work as per specifications and drawings.
Item shall be counted as per each size of unit installed.

15.01.10.
15.01.10.01.A
15.01.10.02.B

Roof Terminal Vent:


Shall include supply, installation of roof terminal vent cast iron type and all
necessary work as per specifications and drawings.
Item shall be counted as per each size of unit installed.

15.02.

PLUMBING FIXTURE

15.02.01.A&B

Western Water Closet (WWC): Shall include supply, installation of western


water closet complete with cover, flush valve, angle valves, flexible
connection and other required accessories as per detailed drawings and
specifications.
Item shall be counted as per each unit installed.

15.02.02.A&B

Eastern Water Closet (EWC): Shall include supply and installation of


eastern water closet T-3 as per detailed drawings and specifications
complete with flush valve, fittings and all accessories necessary for
satisfactory operation.
Item shall be counted per each unit installed.

15.02.03
15.02.03.01. A&B

Lavatory
Lavatory Type (LAV-1): Shall include supply, installation of lavatory LAV-1
complete with mixer pop-up waste, P-trap angle valves, flexible connections
& other required accessories as per detailed drawings and specifications.
Item shall be counted per each unit installed.

15.02.04.A&B

Perineal Spray: Shall include supply, installation of perineal hose spray


complete with vacuum breaker and flexible hose as per specifications and
drawings.
Item shall be counted as per each unit installed.

15.02.05.B
May 2014

Shower Tray: Shall include supply, installation of shower complete with all
accessories as per specifications and drawings.
01150-22

Contract No. PIC F-8159

Item shall be counted per each unit installed.


15.02.06.A&B

Ablution Faucet: Shall include supply, installation of ablution faucet


complete with all accessories as per specifications and drawings.
Item shall be counted as per each unit installed.

15.02.07.A&B

Flushing, Cleaning, Sterilization, Testing and Commissioning: Work


shall include all necessary equipment and tools to be utilized for flushing,
testing and commissioning of all piping system and plumbing equipment as
per specifications.
It shall be measured per lot for completed work.

15.03.

FIRE PROTECTION

15.03.01.

Portable Fire Extinguisher (PFE):

15.03. 01.01. A&B

PFE Dry Chemical (FE-1): Shall include supply and installation of portable
fire extinguisher (i.e. 4.5 kg portable fire extinguisher multi-purpose dry
chemical powder type both 4.5 kg wall-mounted) as shown in drawings and
specifications complete with all accessories meeting the requirements of
NFPA 10.
Item shall be counted as per each unit installed.

15.04.

HVAC

15.04.01.A&B

Mini Split Air Conditioning Unit:


Shall include supply, installation of split air conditioning unit as per type
mentioned in the schedule of equipment with all necessaries for good
operation as per specifications and drawings. The unit shall be factory
tested.
Item shall be counted as per each unit installed

15.04.02.

Exhaust Fans

15.04.02.01.

Roof Mounted Exhaust Fans:

15.04.02.01.01.A&B
15.04.02.01.02.A&B
15.04.02.01.03.A

May 2014

Shall include supply, installation of exhaust fan centrifugal/propeller type, roof


mounted as per type mentioned in the schedule of equipment with all
necessaries for good operation as per specifications and drawings. The unit
shall be factory tested.
01150-23

Contract No. PIC F-8159

Item shall be counted as per each unit installed.


15.04.02.02.
15.04.02.02.01.B

Wall Mounted Exhaust Fans:


Shall include supply, installation of exhaust fan centrifugal/propeller type, wall
mounted as per type mentioned in the schedule of equipment with all
necessaries for good operation as per specifications and drawings. The unit
shall be factory tested.
Item shall be counted as per each unit installed.

16.

BUILDING ELECTRICAL POWER, LIGHTING AND


TELECOMMUNICATION

16.01.

Low Voltage Panel:

16.01.01.A
16.01.02.A&B
16.01.03.A&B

Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of Low Voltage Panel consisting of
power circuit breakers, ammeter, voltmeter, busbars, wire ways completely
assembled, wired, adjusted and tested at the factory including but not limited
to supply, delivery to site, storage, field verification of material received in
good condition and free from any damage in transit, mounting, alignment,
testing of components and filling out of directory.
Measurement shall be per each distribution board installed and field tested.

16.02.
16.02.01.B
16.02.02.A

16.03.
16.03.01.A

Low voltage multi-core cables, 0.6/1.0 kV, CU/XLPE/PVC:


This item is same as item no. 02.10.03. except for low voltage multi-core,
0.6/1.0, CU/XLPE/PVC.

Disconnecting Switch, Non-Fusible, NEMA Type 4X:


Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of disconnect switch including but not
limited to supply, delivery to site, storage, field verification of material received
in good condition and free from any damage in transit, steel support on
concrete base; mounting, alignment, grounding, testing of components.
Measurement shall be per each disconnect switch installed, connected to
circuit and tested.

May 2014

01150-24

Contract No. PIC F-8159

16.04.
16.04.01.B

Disconnecting Switch Fusible, NEMA Type 4X:


This work item is the same as item 16.03 except with fuse.
Measurement shall be per each disconnect switch installed, connected to
circuit and tested.

16.05.

16.05.01.A&B
16.05.02.B
16.05.03.A
16.05.04.A&B
16.05.05.B
16.05.06.A
16.05.07.A&B
16.05.08.B to10.B
16.05.11.A
16.05.12.A&B
16.05.13.A
16.05.14.A&B
16.05.15.B
16.05.16.A to 21.A

16.06.
16.06.01.A&B
16.06.02.B
16.06.03.A&B

Lighting Fixtures:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of lighting fixtures including but not
limited to circuit connection, grounding, mounting, alignment, punching and
drilling of sheet metal body for conduit entry when necessary.
Installation shall include delivery of materials from storage to construction site,
handling, inspection, clean up or removal of construction debris.
Measurement shall be by each lighting fixture installed, connected to circuit
and tested.

Light Switches:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of light switches, single gang or
multiple gang outlet boxes with common cover plate and extension ring
when necessary, toggle switches rated 20 ampere, 230 volts, cover plate
including but not limited to circuit connection, grounding, mounting and
alignment.
Installation shall include delivery of materials from storage to construction
site, handling, inspection, clean up or removal of construction debris.
Measurement shall be by each light switch (one or in gang) installed,
connected to circuit and tested.

16.07.
16.07.01.A&B
16.07.02.A&B

Receptacle, 20 ampere, 230 volts:


This work item is the same as item 16.07 except outlet boxes with duplex
receptacle rated 20 ampere, 230 volts with cover plate or weather proof
cover plate where required.
Measurement shall be by each receptacle installed, connected to circuit and
tested.

16.08.
19.08.01.A&B

May 2014

Receptacle, 35 ampere, 250 volts:


This work item is the same as item 16.08 except single receptacle rated 35
01150-25

Contract No. PIC F-8159

ampere, 250 volts.


Measurement shall be by each receptacle installed, connected to circuit and
tested.

16.09.A&B

Rigid and flexible conduits (PVC, RGS & EMT) and metal boxes
complete with supports and fittings:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of conduits & boxes including but
not limited to elbows, couplings, flexible conduits, connectors, bushings &
locknuts, boxes (outlet, pull and junction), box covers, supports, hangers
and pull wires.
Installation shall include delivery of materials from storage to construction
site, handling, inspection, clean up or removal of construction debris.
Measurement shall be by lot of completely installed raceways.

16.10.
16.10.01.A&B

Low voltage multi-core cables, 0.6/1.0 kV, CU/XLPE/PVC:


This item includes the supply, installation, delivery to site, storage, and field
verification of materials received in good condition and free of any damage
in transit.
Installation shall include delivery of materials from storage to construction
site, checking and field testing of wires/cables and associated works.
Measurement shall be by lot of multi-core cable installed, terminated and
tested.

16.11.A&B

Lightning Protection:
Shall include all work, materials, equipment, accessories and all associated
work necessary for complete installation of lightning protection consisting of
air terminal or lightning rod, base, supports, high conductivity copper cable
or tape, bonding jumper, grounding grid (rods & bare copper cable) and
inspection pit.
Measurement shall be per lot for the completely installed and tested
lightning protection system.

16.12.

Telecommunications:

16.12.01.B

Telephone System: Work includes purchase, supply, delivery supply and


installation of a telephone system as shown on the drawing complete with
materials such as:

May 2014

01150-26

Contract No. PIC F-8159

Telephone Terminal Cabinet/Box with other accessories.


Telephone outlet, RJ11, including cover plates, cable connection and other
accessories.
Telephone cable category 6 including termination and other accessories.
Scope of work includes but not limited to supply and installation of raceways
(conduits and boxes).
Measurement shall be per lot of completely installed and tested telephone
system.
16.12.02.A&B

Public Address System: Shall include all work, materials, equipment,


accessories and all associated work necessary for complete installation of
public address system consisting but not limited to amplifiers, equipment
cabinet, column and ceiling speakers, horn speakers, microphone and
microphone outlets, cables and wires, 15 A, 125V switch and receptacles;
and raceways.
Installation shall include delivery of materials from storage to construction
site, mounting, alignment, fixation, conduits and boxes, cabling, testing and
all other works required for a complete operational public address system.
Measurement shall be per lot for the completely installed and tested public
address system.

16.13.A&B

Fire Alarm & Detection System: Shall include all work, materials,
equipment, accessories and all associated work necessary for complete
installation of fire alarm and detection system consisting but not limited to
Fire alarm control panel, detectors, bells, automatic telephone dialer,
raceways and wires.
Installation shall include supply, delivery of materials from storage to
construction site, mounting, alignment, fixation, conduits and boxes, wiring,
testing and all other works required for a complete operational fire alarm and
detection system.
Measurement shall be per lot for the completely installed and tested fire
alarm and detection system.

++ END OF SECTION 01150 ++