Sunteți pe pagina 1din 26

Pearl GTL

Project
Shell Project No: HP-3000-QAT
Project Document Number: T- 4.250.916

Purchase Order Number:

2MH127

Tag/Item Number(s):

N/A

Unit(s):

ASU

PCWBS:

LINDE ENGINEERING

Contractor Project No:


Project Rev.: B

Page 2 of 22

5887

QATAR SHELL GTL PROJECT (PEARL)


C2 AIR SEPARATION UNITS CONSTRUCTION

05.10.08

Ready For Construction

SK

EO

AG

RFC

24.04.08

Ready For Construction

BR

UA

ZG

RFC

04.12.07

Issued for Company comments

BR

AU/MC

ZG

ICC

24.11.07

Issued for Review

BR

AU/MC

ZG

IFR

18.11.07

Issued for Internal Review

BR

AU/MC

ZG

IIR

Date

Description

GAMA
Rev.
No.

Project
Rev
No.

Prepared Checked Approved


By
By
By
ORIGINATOR

Status

Document Title:

LINDEGINEERING AG

QUALITY CONTROL PROCEDURE FOR SHOP AND


FIELD PAINTING WORK ON SITE
Document No.

Contractor

Gama Qatar Co. W. L. L.

LOC470
GAM

PRO

QAC

GTL

032

Org.
Code

Doc.
Type

Disc.
Code

Geogr.
Area

Seq.
No

Rev.
No

Project Document Number: T-4.250. 916

Vendor Code

Rev No: B

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

TABLE OF CONTENTS
1.

SCOPE _____________________________________________________________________________ 5

2.

PURPOSE __________________________________________________________________________ 5

3.

HSSE ______________________________________________________________________________ 5

4.

REFERENCE _______________________________________________________________________ 5

5.

DEFINITIONS ______________________________________________________________________ 6

6.

RESPONSIBILITIES _________________________________________________________________ 6

7.

PROCEDURE _______________________________________________________________________ 7
7.1.

Safety _________________________________________________________________________________ 7

7.2.

Qualification ___________________________________________________________________________ 7

7.3.

Pre blast ( shop and field ) ______________________________________________________________ 7

7.4.

Surface preparation ( shop and field ) above ground __________________________________________ 7

7.5.

Surface preparation ( shop and field ) underground __________________________________________ 8

7.6.

Paint storage ___________________________________________________________________________ 9

7.7.

Painting mixing _________________________________________________________________________ 9

7.8.

Weather conditions _____________________________________________________________________ 10

7.9.

Masking ______________________________________________________________________________ 11

7.10.

Pre coating cleaning ________________________________________________________________ 11

7.11.

Priming (shop and field) ______________________________________________________________ 12

7.12.

Painting ____________________________________________________________________________ 12

7.13.

Repair of damage coating _____________________________________________________________ 13

7.14.

Identification marking job stencil _____________________________________________________ 14

8.

QUALITY CONTROL ________________________________________________________________ 14

9.

INSPECTION RECORD ______________________________________________________________ 15


9.1.

SHOP BLASTING AND PRIMING _______________________________________________________ 15

9.2.

SHOP PAINTING _____________________________________________________________________ 15

9.3.

FIELD PAINTING OF ABOVE GROUND PIPING _________________________________________ 16

9.4.

FIELD PAINTING OF UNDERGROUND PIPING__________________________________________ 16

10.

STORAGE AND TRANSPORTATION OF PAINTED PIPES / SPOOLS ____________________ 16

11.

ATTACHMENTS __________________________________________________________________ 17

T-4.250.916 Rev. B

Page 4 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

1. SCOPE
This procedure covers the Quality Control activity for Painting work by either GAMA Qatar
and/or GAMA Qatars subcontractor and is applicable to underground and above ground
shop and field painting at C2 ASU PEARL GTL PROJECT.

2. PURPOSE
The purpose of this procedure is to define the painting application methods, inspection and
documentation of underground and above ground shop and field painting. This procedure
provides general guidelines. The painting application is governed by specifications and paint
manufacture recommendations.

3. HSSE
All works shall be in compliance with the State of Qatar laws and regulations, Ras Laffan
Industrial City and International standards, codes, LINDE ENGINEERING AG and QSGTL and/or
its PMC requirements and instructions.
In addition all employees and GAMA subcontractor employees on site will have through LINDE
ENGINEERING AG Site Safety Induction and GAMA Qatar Safety induction for site safety,
health, environmental and security prior to work activities. Other training courses will be attended
as required by LINDE ENGINEERING AG or QSGTL and/or its PMC as required.

4. REFERENCE
T-13.376.799: Rev.L; Amendments and supplements to DEP 30.48.00.31 Gen (December
1995) incorporating DEP circular 80/03, painting and coating of new equipments.
DEP 30.48.00.31: Gen December 1995; Painting & Coating of new Equipment
T.4.096.672: Specification for corrosion protection painting
T.4.250 .919: ITP Painting & coating
T-4.250.900 Method Statement for Painting and repair works
SSPC-SP1: Surface Preparation Specification No.1 Solvent Cleaning
SSPC-PA2: Paint Application Specification No.2
ISO 8502-6: Bresle Test Method
ISO 8501-1: Sa 1 - Light blast-cleaning
Sa 2 - Thorough blast-cleaning
T-4.250.916 Rev. B

Page 5 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

Sa 2 -Very thorough blast-cleaning


Sa 3 - Blast cleaning to visually clean steel

5. DEFINITIONS
Company

: QSGTL/or its PMC

Contractor

: LINDE ENGINEERING AG

Sub Contractor

: GAMA QATAR

Contract

: QSGTL Pearl Plant - C2 ASU Project

QA/QC

: Quality Assurance / Quality Control

TPI

: Third Party Inspection

DFT

Dry Film Thickness

WFT

Wet Film Thickness

MSDS

: Material Safety Data Sheet

MDS

: Manufacturing Data Sheet

DBT

: Dry Bulb Temperature

WBT

: Wet Bulb Temperature

6. RESPONSIBILITIES
The Painting Engineer is responsible for application of paint in accordance with the Project
Specifications T.13.376.799-Painting & coating of New Equipment (Amendments)
30.48.00.31-Painting & coating of New Equipment and this procedure, appropriate method
statements (T-4.250.900) and the Paint manufacturer's recommendations.
The Painting Supervisor shall complete the painting forms and ensure that they are endorsed
by the responsible party / QC Paint Inspector at the appropriate of the in process paint
inspection activity.
T-4.250.916 Rev. B

Page 6 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

GAMA Qatar shall make sure that painting works have been inspected and painting works are
executed in accordance with the Project specifications and approved Inspection Test Plan.

7. PROCEDURE
7.1.

SAFETY
All works shall be carried out in accordance with manufacturer(s) recommendations site
requirements.
Personal Protective Equipment (PPE) shall be worn all the time and in accordance
with site safety regulations.
All construction activities shall follow Project Safety Procedure.
Discarded paint, empty paint buckets, thinners, or any rags, cloths etc., shall be
discarded into containers and hauled off to an approved dumping site.

7.2.

QUALIFICATION
Painting personnel must have previous experience in the use of the specified surface
preparation and coating systems or similar systems. Only skilled painters shall be used.
For underground coating, the manufacturers technical representative shall witness
the demonstration application of each coating system at the start of the production.

7.3.

PRE BLAST ( SHOP AND FIELD )


The Painting Supervisor shall ensure that pre-blast cleaning is carried out according to
Paint Manufacturer's recommendation and Project Specifications . The surface
of steelwork for new construction shall be blast-cleaned to the visual standard of Sa 2
in accordance with ISO 8501-1, and shall retain this standard of cleanliness at the time
of coating.
Abrasive material Shall be approved By LINDE using GAM-QCR-QAC-GTL-051

7.4.

SURFACE PREPARATION ( SHOP AND FIELD ) ABOVE GROUND


Prior to start blasting, the GAMA shall demonstrate to the satisfaction of LINDE and
SHELL/PMC that the selected abrasive provides the specified anchor profile and
surface cleanliness. This shall be done by blasting representative piece of steel and
measuring the anchor profile, in accordance with ISO 8504-3 and/or comparing the
surface cleanliness to the appropriate visual standard. Any changes in the abrasives or
mesh size shall qualify in the same way prior to be used.

T-4.250.916 Rev. B

Page 7 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

Visible oil, grease and soil shall be removed by solvent cleaning, area shall be washed in
clean fresh water and allowed to dry before conventional (air blast) cleaning, automatic
(wheel blast) or hand/power cleaning. GAMA Qatar Quality Department shall perform
surveillance to ensure cleaning is performed adequately, where applicable.
The surface shall be prepared prior to application of primer or paint by abrasive blasting
(paint shop application) or by hand tool/abrasive blasting (field application).The
method of surface preparation shall be recorded on form GAM-QCR-QAC-GTL-055.
Only blasting material that is approved and that conforms to the requirements of project
specification may be used for surface preparation. Test results shall be obtained by the
Painting Supervisor and handed over to GAMA Qatar Quality Department.
The type of abrasive is determined in compliance with the Project Specification
requirements by the profile required and the type of material to be blasted. The use of
steel shot or steel grit is not permitted for blasting of stainless steel. The type of
blasting abrasive used, and the required profile shall be recorded on GAM-QCR-QACGTL-055 by the Painting Supervisor for the Paint Shop and field application.
All blasting materials shall be kept dry. With the exception of expendable abrasives,
blasting abrasives may be reclaimed and used as per the manufacturer procedure.
The GAMA Qatar Quality Department shall perform surveillance of pre-blast blasting
operations. Once the blasting is complete for one batch QCI, shall use testex tape and
measure the profile and shall be witness by LINDE and SHELL/PMC. The result and
testex tape shall be recorded and taped to form GAM-QCR-QAC-GTL-055.
After cleaning, the surfaces shall be kept free from oil, grease, dirt, etc. until the coating
has been applied. Surfaces shall be coated within 4 hours or before any visible
deterioration of the blasted surface has occurred and this will be recorded in GAMQCR-QAC-GTL-055. Surfaces not meeting the blasting profile shall be re-blasted prior
to coating.
Used abrasive shall be removed from external surfaces using a dry brush and blowing
down with clean dry compressed air.
Steel defects revealed during abrasive blasting (silvers, laminations, cracks, pitting etc.,)
shall be reported to the LINDE /SHELL/PMC for evaluation. Defects will be
repaired as directed by the LINDE /SHELL/PMC Representative.

7.5.

SURFACE PREPARATION ( SHOP AND FIELD ) UNDERGROUND


Identification Marking shall be transferred to inside the pipes before commencing the
blasting and painting operation. Transfer of markings shall be witness by the LINDE

T-4.250.916 Rev. B

Page 8 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

authorized inspectors as per T-13.377.437-specification for certification and marking

of materials.

Proper surface preparation shall be maintained and checked prior to applying any primer in
accordance with the applicable sections of this procedure and Project specifications.
Pipe ends and fitting ends shall be left uncoated for a distance of 50mm at shop
.

Field welds and damaged coating shall be made ready for painting application using
hand or power tools and then fully coated as applicable.
All blast cleaned surfaces shall be inspected for proper cleaning and anchor profile in
accordance with SSPC Specification and as per Project specification.

7.6.

PAINT STORAGE
The date of manufacture shall be clearly marked on each paint container, and paints that
have exceeded their shelf life shall be discarded. The same will be monitored on a
regular basis by GAMA Qatar, in conjunction with the paint manufacturer.
Paints and thinners shall be stored in areas that are well ventilated, and as specified by
the paint manufacturer (or) MSDS.
Coating materials shall be used on "First in-First out Basis"; no coating materials shall be
used beyond shelf life of 12 months. The maximum shelf life for zinc silicates shall be

6 months

Paints that show signs of leakage or have gelled shall be discarded and any skins that
have formed shall be cut and removed prior to application
Each batch of paint or thinner used shall be accompanied by a MDS from the respective
manufacturer. Any paint or thinner arriving on site without MDS shall not be used until
such time certification has been obtained.

7.7.

PAINTING MIXING
Paint shall be mixed thoroughly immediately prior to application.
Paint shall be properly mixed with recommended mixers such as, mechanical stirrers,
paddle mixers and can vibrators or shakers.

T-4.250.916 Rev. B

Page 9 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

Metallic zinc or other dense pigment filled coatings shall be mechanically mixed
thoroughly prior to and during paint application. In field application, applicators must
constantly agitate the paint to obtain homogeneous mix.
Multi-component material shall be mixed in the volumes pro vided by the coating
manufacturer as "kits". Kits will not be "broken or split" without the written approval of
LINDE and SHELL/PMC.
Approved coating thinners shall be used as directed by the paint manufacturer.
Mixing shall be performed using mechanical mixers, designed to mix paint materials, in
clean containers. Containers shall be kept covered at all times except during
opening/closing and mixing operations.
Manufacturer's pot life, as stated in product data sheets, shall not be exceeded. When
the pot life limit is reached, the equipment must be emptied, material properly disposed of
and new material mixed.
If the paint cannot be mixed uniformly (thick sediments at the bottom etc.), it shall not be
used.

7.8.

WEATHER CONDITIONS
The Painting Supervisor shall monitor the weather conditions and take measurements
for wet bulb temperature, surface temperature, dew point temperature (For Dew Point
Calculation Chart). These, including weather conditions (windy, wet, dry, and cloudy)
shall be recorded on form GAM-QCR-QAC-GTL-055 by the Painting Supervisor at the
start, during and at end of work. Where applicable, all measuring devices shall be
calibrated and shall bear valid calibration stickers.
Any significant changes to weather conditions which may adversely affect the quality of
the paint warrants additional readings as per above.
Blasting operations shall not take place when the metal surface temperature is less
than 3C above the ambient dew point temperature (or) the Relative humidity is
greater than 85%. Priming / Painting shall not be applied when the surface
temperature is greater than 40C (unless higher temperature is agreed by the paint
manufacturer). An ELCOMETER disc type calculator or equivalent means should be used
to determine the relative humidity and dew point.
The GAMA Qatar Quality Department shall perform surveillance inspection to ensure the
data is collected and recorded and to ensure blasting and painting operations are
only performed within the requirements of the project specifications.

T-4.250.916 Rev. B

Page 10 of 22

Q A T A R

7.9.

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

MASKING
The bevel of each spool shall be masked to a distance of 50 mm from the bevel prior to
painting. This also applies to bevels in the field where the piping is painted prior to
completion of the welding. The masking of stainless steel requires special chloride free
tape which will be approved by Linde/PMC.
The Painting Supervisor shall also ensure that the piping identification is maintained
prior to and after painting. This also applies to the straight run pipes.
The Painting Supervisor shall ensure that there is no overspray onto previously painted
surfaces or beyond the application area. If there is danger of inorganic zinc primer
overspray contaminating stainless steel then the stainless steel shall be protected
by suitable means i.e. masking, covering with polythene etc.
After completion of painting all masking shall be removed and any overspray, dry spray
etc.
The GAMA Qatar Quality department shall perform surveillance inspection to ensure
proper masking protection is applied.
Masking shall be applied before blasting and coating operations to protect the gasket
surfaces (except plain face) and the pipe or nozzle interior. Surfaces that will be
inaccessible after assembly including the surfaces of lap joint, flanges, nozzle necks,
bolt holes shall receive the complete painting system before being assembled, steel
structure bolted connections shall be primed only unless otherwise noted.
The outer edge of ring groove flanges and raised face flanges will be blasted and coated
to the upper (outer) edge of the ring groove or the outside edge of the raised portion of
the flange. The entire groove area shall be protected.
In addition to the above, areas to be masked not blasted and painted are nameplates, valve spindles, level gauge glasses, small instruments, etc.

7.10. PRE COATING CLEANING


After the surface has been blasted and prior to application of any coating, the surface shall
be cleaned either by brushing or by air blowing. Used blasting material shall be removed
from external surfaces using a dry brush or by air blowing. Under no circumstances shall
surfaces that have been contaminated be coated before the surface has been adequately
cleaned.

T-4.250.916 Rev. B

Page 11 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

All visible oil, grease and soil shall be removed with an approved solvent prior to
coating. Solvent, cleaning solutions, acid washes, inhibitors must be approved by
Material Approval Request (MAR) prior to use. The cleaned area shall then be washed in
clean, potable water and allowed to dry.
The compressed air supply shall be checked by the Painting Supervisor to ensure the air
is moisture and oil free. These checks are to be carried out at the start of each shift and
again after lunch. If necessary, a cooler shall be installed in the compressed air line to
ensure that compressed air is supplied at a temperature less than 110C. A Digital
thermometer also may be used to check the air temperature at the hose tip and will be
recorded in GAM-QCR-QAC-GTL-055.

7.11.

PRIMING (SHOP AND FIELD)

Primers, Intermediate coats and Topcoats shall be as per Project specification and
manufacturers product recommendation /MDS
Prior to application of primer, all difficult to coat areas such as corners edges, and welds
shall be stripe coated with the specified primer.
When inorganic zinc primer is used, checks for surface zinc oxide formation shall be
made immediately prior to applying an epoxy topcoat. Any oxide formation shall be
removed either by high pressure cleaning with potable water, or hosing with potable water
and then scrubbing with a soft brush to remove all the zinc salts. The surface shall be
thoroughly dried before applying the top coat.
Dry film thickness readings will be taken and calculated as per Project specification,
T-13.376.799 and ISO 2808 shall be recorded on GAM-QCR-QAC-GTL-055 by the
Painting inspector. This applies to each individual coat .DFT gauges Shall be calibrated in
accordance with section 2 of SSPC-PA-2
To control the final thickness of the coats the painting Inspector may use WFT (Wet Film
Thickness) measurements as an indicator for final thickness.

7.12. PAINTING
The representative of the paint manufacturer shall visit the site at regular intervals to
provide technical support and he shall submit a periodic report to GAMA Qatar and
LINDE confirming that painting is being carried out in accordance with the requirements
and quality of work is acceptable.
The specific paint systems to be used are identified in Project
Specifications T-4.096.672/0100 W-SP 2301, T.13.376.799-Painting & coating of New
Equipment (Amendments) and DEP 30.48.00.31-Painting & coating of New Equipment.
T-4.250.916 Rev. B

Page 12 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

The paint coats shall be applied in the limits specified by Project specification
T-4.096.672/0100 W-SP 2301, DEP 30.48.00.31-Painting & coating of New Equipment
and MDS.
Each coat shall be checked for correct average DFT by GAMA Qatar QCI or Painting
Subcontractor QCI prior to application of subsequent coat.
The Painting Supervisor shall apply all coats in the paint shop or in the field including
final coat as specified in Project specification,
DEP 30.48.00.31-Painting & coating of New Equipment
All paint shall be applied either by air spray or airless spray as specified by paint
manufacturers. The use of brushes is only allowed in the case of repairs or in difficult
areas where spray technique is not practical.
After the completion of painting in the shop, all spools shall be cleaned to ensure that
spent abrasives are not present inside the pipe. Both ends shall be covered to avoid
ingress of sand after cleaning.
All welds, edges, etc. shall be stripe coated to ensure full DFT in those areas. This
includes nuts and bolts heads.

7.13. REPAIR OF DAMAGE COATING


The damaged area shall be re-cleaned as originally specified for that item and the full
coating system re-applied in accordance with the manufacturers application datas.
Any repair of damaged coating shall be cleaned by hand tools or power tools in
accordance with ISO 8501-1 grade st 3 and documented on form GAM-QCR-QAC-GTL056
Any repair areas shall be feathered into the undamaged coating a minimum of 50 mm.
Repair shall be performed prior to the subsequent coat.
Any damage or repair shall be performed prior to the next coat application. Coating of
weld joints shall be in accordance with original paint application as specified in Project
specification.
For item such as equipment already painted by a supplier, GAMA Qatar shall use the
same paint or an equivalent and compatible paint approved by the supplier.
Repair of damaged surfaces of zinc silicate primer shall be performed as detailed in the
Project specification.
T-4.250.916 Rev. B

Page 13 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

Any holidays, defects and unacceptable work shall be repaired in accordance with
manufacturer's recommendations. Holidays should be generally ground to bare metal
feathering the adjacent sound coating back a minimum of 25mm.

7.14. IDENTIFICATION MARKING JOB STENCIL


All spools and straight run pipe shall be identified clearly as per T-4.250.928 Material
Traceability & Marking.
A job stencil shall be applied in the field in letters in a color which is in accordance with
Project specification, T-.13.377.437-certification ad marking of materials. This shall only be
applied on the final coat.
The job stencil shall contain information as per T-4.250.928 Material Traceability &
Marking. and Project specification T-.13.377.437-certification ad marking of materials

8. QUALITY CONTROL
The GAMA Qatar QCI shall perform inspection as per DEP -30.48.00.31 and relevant ITP
on all painting activities, in addition to profile measurements and DFT checks carried out
by the Painting Subcontractor's QCI as perform GAM-QCR-QAC-GTL-055.The Painting
subcontractor's QCI shall perform inspections on each batch and each coat and the
checks shall include but not limited to the following:
Pinholes
Blisters
Bubbling
Fisheyes
Unmatched colors
Uniformity
Curing properties

Dry Film Thickness


Orange peel
Mud cracking
Dry Spray
Runs and sags
Mechanical damage
Holidays, missed areas

The inspection shall be witnessed and signed off by the GAMA Qatar QC Inspector,
LINDE and SHELL/PMC as per relevant ITP on the painting activity on form GAM-QCRQAC-GTL-055
When a painting manufacturer is different between shop coating and field coating,
adhesion testing shall be done at randomly selected areas by grinding (Crosshatch),
following the procedures of ASTM D4541 & ISO 2409. Adhesion testing shall be carried
out at least once per equipment item or 100 m of coated surface, and on properly cured
coating.

T-4.250.916 Rev. B

Page 14 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

Adhesion of inorganic zinc coatings shall be tested by firmly scraping the coated surfaces
with the edge of a coin. A zinc film, which is properly dried and hard, will polish to bright
metal without powdering or loss of material.
For underground piping, the inspection on site shall be done by Holiday detector in
accordance with 30.48.00.31-Painting & coating of New Equipment and Project
Specification ASTM D 5162. Form No. GAM-QCR-QAC-GTL-053 shall be used for the
Inspection of underground piping.

9. INSPECTION RECORD
9.1.

SHOP BLASTING AND PRIMING


The shop blasting and priming shall be documented on form GAM-QCR-QAC-GTL-055.
This form shall be completed by the Painting Supervisor and QCI as indicated. The form
shall list all the items which were blasted and primed in one batch. If one batch contains
more than one priming system then separate forms shall be generated for each primer
type.
Should there be items that are not released for further painting these items shall be listed in
the section on the form specified as "Items on hold and release after repair". These items
shall be signed off by GAMA Qatar QCI upon repair. The final signature on this form,
releases all items for next coat application with the exceptions as listed.

9.2.

SHOP PAINTING

The shop painting shall be documented on form GAM-QCR-QAC-GTL-055 this form shall
be completed by the Painting Supervisor and QCI as indicated. This form shall list all the
items which were painted in one batch and these shall reference the report numbers for the
blasting and priming. If one batch contains more than one painting system then separate
forms shall be generated for each paint type.
Should there be items that are not released for further painting these items shall be listed in
the section on the form specified as "Items on hold and release after repair. These items
shall be signed off by GAMA Qatar QCI upon repair. The final signature on this form,
releases all items for next coat application with the exceptions as listed. Signature by GAMA
Qatar QCI / LINDE on form GAM-QCR-QAC-GTL-055 signifies that the painting is complete
and the items are released for transport or storage.
LINDE or SHELL/PMC acceptance of the shop painting work shall be obtained on the
30.48.00.31-Painting & coating of New Equipment .The main function of this Procedure to
compile and handover the completed and signed-off forms GAM-QCR-QAC-GTL-055
pertaining to a certain period of shop production specified under ITP scope. Consequently,
T-4.250.916 Rev. B

Page 15 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

this ITP shall include in-process Inspection activities. The acceptance of work shall be the
relevant section of the form GAM-QCR-QAC-GTL-055

9.3.

FIELD PAINTING OF ABOVE GROUND PIPING

Date to date production and QC inspections for field painting shall be documented by GAMQCR-QAC-GTL-055. This form shall be generated for each type of paint, and may include
more than one isometric. The completed GAM-QCR-QAC-GTL-055 shall be filed per unit or
area
LINDE or SHELL/PMC acceptance of the field painting work shall be obtained on the
30.48.00.31-Painting & coating of New Equipment. The main function of this procedure to
compile and handover the completed and signed-off form GAM-QCR-QAC-GTL-055
pertaining to the individual ITP scope. Consequently, this ITP shall include in-process
Inspection activities and there are no sign-off acceptances of the painting works. The
acceptance of work shall be the relevant section of the form GAM-QCR-QAC-GTL-055, as
applicable.

9.4.

FIELD PAINTING OF UNDERGROUND PIPING

Field painting of underground piping inspection shall be carried after tape wrapping of
welded joints by Holiday detection in accordance with 30.48.00.31-Painting & coating of
New Equipment and ASTM D 5162. The inspection report # GAM-QCR-QAC-GTL-056
should be filled and signed by GAMA Qatar, LINDE, and SHELL/PMC before backfilling
operations start.

10. STORAGE AND TRANSPORTATION OF PAINTED PIPES / SPOOLS


All painted pipes/spools should be properly stored, dunned and clear from the ground.
Pipes with end caps are supplied, end caps should be reinstated and wherever end caps
were not provided, pipes shall be protected both ends.
Method of storage shall protect coated pipes/spools from standing water, direct soil
contact, and sharp or hard objects.
Coated / Painted pipes and spools shall be transferred by lifting and placement without
the use of hooks, ropes, cables, or other sharp handling devices.
If coated/painted underground pipes
Handling Procedure.

T-4.250.916 Rev. B

are to

be stored, it should

follow the Material

Page 16 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

11. ATTACHMENTS
Dew Point Calculation Chart
GAM-QCR-QAC-GTL-051
GAM-QCR-QAC-GTL-053
GAM-QCR-QAC-GTL-055
GAM-QCR-QAC-GTL-056

T-4.250.916 Rev. B

Page 17 of 22

Q A T A R

Doc. Title

PROCEDURE FOR SHOP AND FIELD PAINTING WORK ON SITE

Doc No

GAM-QCP-QAC-GTL-032, REV-E

DATE:

06.10.08

DEW POINT CALCULATION CHART

Q A T A R

AMBIENT AIR TEMPERATURE


(DEGREES CENTIGRADE)

%
Relative

Temperature
-7 C

-1 C

4 C

10 C

16 C

21 C

27 C

32

38 C 43 C 49 C

90

-8

-2

14

19

25

31

36

42

47

85

-8

-3

13

18

24

29

35

40

45

80

-9

-4

12

17

23

28

34

39

43

75

-9

-4

11

17

22

27

33

38

42

70

-11

-6

-1

10

16

20

26

31

36

41

65

-11

-7

-2

14

19

24

29

34

39

60

-12

-7

-3

13

18

23

28

33

38

55

-13

-8

-4

12

16

21

27

32

37

50

-14

-9

-5

-1

10

15

19

25

30

34

45

-16

-11

-6

-2

13

18

23

28

33

40

-17

-12

-8

-3

11

16

21

26

31

38

-19

-13

-9

-5

-1

14

18

23

28

30

-21

-16

-11

-7

-2

11

16

21

25

humidity

Example: If the air temperature is 21 C and the relative humidity is 70%, the dew point is 16.

T-4.250.916 Rev. B

Page 18 of 22

C2 ASU PEARL GTL PROJECT


RAS LAFFAN INUSTRIAL CITY
MAR
(Material Acceptance Report)
Project: QSGTL PEARL GTL PROJECT

MAR No.:

Date:

Manufacturer:
PO/Subcontract
Number :
Description of the Proposed Material:
QTY:

Nos:

Note:

Civil / Buildings

Mech. / Piping

Civil

Involved
Discipline:

Mechanical

Electrical

Instrumental

Welding

Others

..

Location & Usage of the Delivered Material:

Applicable Specifications & Technical Details:

Proposed material complies with applicable project specification


Attachments:

Inspection Report
Release Note

Yes

Mill Certificates

Data Sheets

No

Others

Comments:

Accepted By

Carried out By
GAMA REP.
VENDOR REP.
LINDE REP.
QSGTL REP.

GAM-QCR-QAC-GTL-051

DATE

NAME

SIGNATURE

Q A T A R

C2 ASU PEARL GTL PROJECT


RAS LAFFAN INDUSTRIAL CITY

PINHOLE & HOLIDAY TESTING REPORT

Subcontract Ref.:

Report No.

Item Description:

Inspection Date:

Item Location / Area:

Test Code No.:

System:

ITP No.:

Subsystem:

Ref.Drg./Doc.

Used Measuring and test equipment ref. (if applicable):


HOLIDAY DETECTOR
DETAILS
Make: _________
Date

Identification No.:
Pipe
T.D.F.T
Ident. No.
Dia (inch) Microns

K.V.Range:
KV
Settings

H.D Result
Damages
Pinholes

Remarks:

Accepted By

ORGANIZATIONS
THIRD PARTY
REP.
GAMA REP.
LINDE REP.

QSGTL or its PMC


REP.
GAM-QCR-QAC-GTL-053

DATE

NAME

SIGNATURE

Remarks

C2 ASU PEARL GT PROJECT


RAS LAFFAN INDUSTRIAL CITY
PAINTING INSPECTION REPORT

QATAR

Report No.:
Item Description:
System:
Item Location / Area:
Ref. DWG / Documents:
Used Measuring and test equipment ref. (if applicable):
Working Conditions
Internal / External

Inspection Date:
Test Code No.:
Subsystem:
ITP No.:
Paint Spec:

Compr. Air Temp.


Time (hrs.)
Air
WB
O
Temp
( C)
DB
Dew Point (O C)
Relative Humidity %
Metal Temp. (O C)

1. Hygrometer

Insp. Equipment Used

Identification #

2. DP / RH Calculator
3. Temperature Gauge
4. Hypodermic Needle
Gauge
5. Surface Profile Gauge
6. WFT Gauge
7. DFT Gauge

Surface Cleaning with fresh water


SURFACE PREPARATION

PROFILE MEASUREMENT TAPE

From: ________________hrs.
To: ________________hrs.

Grit Blasting
Machine Sl.No.
Nozzle Pressure
Grit Type

Wire Brushing
Manual / Power
Grade
mm
PSIG
Surface Finish
Surface Profile
Microns
*PAINT APPLICATION
From: ______________ hrs. To: _______________ hrs.
Manual / Auto

Coating Manufacturer:

Paint:

Product/Coat

Batch No.

Mix
Ratio

A.
B.
Intermediate A.
Coat
B.
A.
Top Coat
B.
Further Inspection Required:
Conducted :
Corrective action if necessary:

Application
Methods

Airless Spray Machine Sl. No.


Total
Colour
WFT DFT
DFT

Overcoat
Time

Primer

Accepted By

ORGANIZATIONS

DATE

NAME

THIRD PARTY REP.


GAMA REP.
LINDE REP.
QSGTL or its PMC REP.

*Priming application will be done within 4 hrs after surface preparation.


GAM-QCR-QAC-GTL-055, Rev-1

SIGNATURE

Q A T A R

C2 ASU PEARL GT PROJECT


RAS LAFFAN INDUSTRIAL CITY
REPAIR & TOUCHUP PAINTING
INSPECTION REPORT

System:
Item Description:
Item Location / Area:
Subsystem:
Ref. DWG / Documents:
Used Measuring and test equipment ref. (if applicable):
Working Conditions
Internal / External

Report No.:
Inspection Date:
Test Code No.:
ITP No.:
Paint Spec:
Insp. Equipment Used

Identification #

1. Whirling Hygrometer

Time (hrs.)
Air
WB
O
Temp
( C)
DB
Dew Point (O C)
Relative Humidity
%
Metal Temp. (O C)

2. DP / RH Calculator
3. Temperature Gauge
4. WFT Gauge
5. DFT Gauge

SURFACE PREPARATION
From: ________________
To: ________________

Method of
Cleaning

PAINT APPLICATION
From: ______________ hrs. To: _______________ hrs.
Application
Methods

Airless Spray Machine Sl. No.


Total
Colour WFT DFT
DFT

DATE

NAME

Coating Manufacturer:

Paint:

Product/Coat

Batch No.

A.
B.
A.
Intermediate
B.
A.
Top coat
B.
Remarks:

Mix
Ratio

Overcoat
Time

Primer

Accepted By

ORGANIZATIONS
THIRD PARTY REP.
GAMA REP.
LINDE REP.
QSGTL or its PMC REP.

GAM-QCR-QAC-GTL-056, Rev-1

SIGNATURE

S-ar putea să vă placă și