Documente Academic
Documente Profesional
Documente Cultură
REVETMENT
Introduction:
For the first five (5) years of its existence, the Project Management Office - Flood
Control and Sabo Engineering Center (PMO-FCSEC) conducted several site survey
and investigation of the different flood control structures of the Regional and District
Engineering Offices of DPWH. The team analyzed both the good and damaged
structures. These structures were compiled in the database together with the plans
and typical designs (if available).
Based from the available data and information gathered from the RO/DEO, manuals
were formulated and hoping in the near future DPWH can come up with a more
effective and efficient structures for flood control and river works.
Revetment, by definition, it is a flood control structure built to protect the riverbank
from collapsing due to erosion, scouring and/or riverbed degradation. But why
revetment structures always damage? If these structures that we planned and
designed are always damaged why we always stick on the same plan and design?
This lecture material will be used to enhance the capability of DPWH in flood control
structures and river works system.
Problem Analysis
Revetment is frequently damaged. First we have to understand the different
phenomena acting on the river and the possible (based on the analysis of damaged
structures) source of damage:
Scouring
Revetment has insufficient depth of foundation
There were no countermeasures against scouring
Poor quality of construction
Direct water attack
Inconsistency in the design of adjoining (extension) revetment
Improper alignment
Did not consider additional countermeasures (i.e. spur dikes)
No provision of end protection works
Residual Hydraulic Pressure or Water table
No provision of weep holes
No provision of gravel or filter cloth in the weep holes
Improper use of weep holes
Degradation/Aggradation
Collapse due to dredging or quarrying activities
Foundation depth was not based on the natural riverbed (before
aggradation)
Based on our statistics on the published Damaged Structures Profile (December
2002) we have the following breakdown as shown below, but this does not represent
the whole DPWH, only selected good samples of bad sites (note: we intend not to
humiliate DPWH Engineers, for we are also part of DPWH but we intend to remedy
the problem):
Statistics on Damaged Structures
Statistics on Damaged Structures
Revetment
Bridge
groundsill
spurdike
Scouring at
foundation
Slope erosion
Passive Force
Others
Identify the target area the length of the project and the degree of
importance.
Establish the whole stretch of the river improvement
Conduct cross-section, topo and establish the control point for stake out.
Observe and study the present situation (Riverbed gradient,
Representative Grain Size Diameter, Surveyed Scouring Depth and
tendency of the riverbed variation).
Delineate and calculate the catchment area and calculate the discharge
capacity using the cross-section survey
The discharge corresponding to the experienced maximum flood
generally recommended as the design discharge, in order to avoid
similar disaster.
In case where the elevation of the beneficiary is quite high, the
bigger design discharge as compared with the experienced
maximum flood shall be considered.
For cases other than bank erosion, such as scouring or riverbed degradation and/or
damages of revetment, a thorough study is needed. The appropriate river
improvement plan shall be established.
Designing for Revetment Structures
Revetment structures shall consist of the following:
Slope covering works
Foundation Works
Foot protection works
The following should be considered in the designing of the revetment
The alignment shall be as smooth as possible
Structural type of the revetment shall be determined based on the
estimated external forces (velocity of flood flow) and the characteristics
of the river.
Foot protection works shall be considered based on the external forces
Transition structure (end-protection works) of the revetment to the
original bank shall be provided.
Flow Direction
Slope Covering
Partition
Foot Protection
(Apron)
Foundation Work
(Cut-off Walls)
End Protection
Shoulder Beam
(Head Wall)
Slope Covering
Filter Cloth
Lean Concrete
Foot Protection
Backfill Materials
Foundation
Crest Protection
Crest
Key
Definition
a.
b.
c.
d.
e.
f.
g.
h.
i.
j.
k.
l.
Slope Covering = Directly covers and protect the bank slope from erosion,
direct attack from boulders and floating debris.
Foundation = Constructed at the toe of the slope that supports the slope
covering.
Foot Protection = Constructed to prevent scouring in front of the
foundation work and escape of material from the bank of the slope
covering work.
Crest work = For revetment that frequently overtopped during flood, it
protects the crest or top of the slope covering works.
Key = Installed at the end portion of the crest work to protect it against
erosion at the back of the revetment.
Crest protection = Installed at the end portion of the key to join the crest
and the original ground for protection against erosion at the back of the
revetment.
Shoulder beam = A headwall that is installed at the shoulder of the
revetment to prevent damage.
Partition = Installed between regular construction sections, to prevent the
damage of the revetment from spreading.
End protection = installed at the upstream and downstream end of the
slope covering to prevent undermining of materials behind the structure.
Transition Work = Installed between the natural bank and the end
protection for a smooth transition. It can be constructed at the upstream or
downstream.
Backfill Materials = Composed of suitable materials which are backfilled to
the slope.
Filter Material/Cloth = Installed behind the slope covering for prevention of
underneath materials from escaping due to residual hydraulic pressure.
b)
c)
Structures
A structure located in the path of flowing water increases the velocity of
flow around the structure and cause local scouring.
d)
The manual focuses on the scouring depth due to the meandering river (bend) and
sand bar
b
10 or d r 0.2mm
Hd
In case that the riverbed is formed by fine sands (around 0.2mm or less)
b
is 10 or less, the
and the ratio of river width and average water depth
Hd
sand bar is not developed. Therefore, the surveyed maximum scouring
depth (Zs) is the maximum scouring depth (Z).
Case 1:
Cross-section Survey
b
DFL
Hd
Average Riverbed
Zs = Z
Case 2:
b
10 or d r 2cm
Hd
b
exceeds 10 and the riverbeds composition is
When the ratio of
H
d
gravel, sand bar is generally formed. In this case, maximum scouring
depth (Zc) should be determined. Afterwards, compare with the surveyed
maximum scouring depth (Zs). The maximum scouring depth (Z) will be
the larger value.
Cross-section Survey
b
DFL
Hd
Average Riverbed
Surveyed maximum
scouring depth (Zs)
Height of Sand
bar (Hs)
Computed maximum
scouring depth (Zc)
b
Hd
H d /d R - 5~20
move to sand bar of plural rows
H d /d R = 25
H S/H d
H d /d R = 50
3.0
8.7
2.0
H d /d R < 100
sand bar of plural rows
8
7
6
5.7
H d /d R > 500
1.0
0
0
10
H d/d R = 200
H d/d R = 100
H d /d R = 300
20 30 40 50 60 70 80
90
100
b/H d
Hd
dr
4) Calculate the water depth at the maximum scoured portion (Hmax) using the
formula
H
H max 1 0.8( s )( H d )
Hd
5) Calculate the maximum scouring depth (Zc)
Zc H max H d
Case 3:
b
10 and 0.2mm dr 2cm
Hd
b
exceeds 10 and the riverbed is formed by coarse
When the ratio of
Hd
sand and medium sand, fish scale sand bars are generally developed. In
this case, height of bar becomes higher due to integration of sand bars.
b
Hd
Hs
Hd
H d /d R - 5~20
move to sand bar of plural rows
H d /d R = 25
H S/H d
H d /d R = 50
3.0
8.7
2.0
H d /d R < 100
sand bar of plural rows
8
7
6
5.7
H d /d R > 500
1.0
0
0
10
H d/d R = 200
H d/d R = 100
H d /d R = 300
20 30 40 50 60 70 80
90
100
b/H d
Hd
dr
4) Calculate the water depth at the maximum scoured portion (Hmax) using the
formula
H
H max 1 0.8( s )( H d )
Hd
5) Calculate the maximum scouring depth (Zc)
Zc 1.5( H max H d )
6) Compare the resulting (calculated) maximum scouring depth (Zc) to the
cross sections (surveyed) maximum scouring depth (Zs). Use the larger
value.
(H max / H d)
b)
4
3
R
1
0
0
0.1
0.2 0.3
0.4
0.5
0.6
0.7
0.8 0.9
r = R - b/2
( b/r )
II)
III)
IV)
Height of Revetment
The height of revetment is based on the longitudinal profile and cross sectional
profiles, and shall be determine as follows:
1)
Scouring depth
Height of Revetment
DFL
d>1.0 m
2)
In case there is difficulty in identifying the top of foundation due to extreme scouring
or riverbed degradation, use steel sheet pile as foundation or toe protection works.
The following can be considered for the identification and setting of elevation of the
foundation.
i)
Existing Riverbed
Top of Foundation
Foundation
Bed elevation at maximum scouring
Foot Protection
ii)
Existing Riverbed
Top of Foundation
Foot Protection
0.5 1.5 m
iii)
Existing Riverbed
0.5 1.5 m
Top of Foundation
Foot Protection
Sheet Pile
iv)
Top of Foundation
Overflow Water Level Tide Level
Sheet Pile
Bed elevation at maximum scouring
Slope
a) The slope of the protection work shall be gentle as much as possible
for stability purposes and shall be based on the natural slope of the
adjacent bank.
b) The slope shall be 2:1 (H:V) or milder.
c) In case of rapid flow stretches wherein floodwater includes a large
quantity of boulders or gravels, the slope shall not necessarily gentle
and shall be determined considering safety against the flood frequency.
d) In case of joint portion with rock-strewn slope, the slope of revetment
shall be gradually changed to smoothly connect with the latter.
e) For the retaining wall type revetment, a maximum slope of 0.3:1 shall
be observed in consideration to stability and the resulting residual
hydraulic pressure.
(2)
Berm Arrangement
a) If the height of revetment is more than 5.0 meters, berm (banquette)
must be provided and is so designed in order to separate the
revetment into segments, and in consideration of site condition
(geography and geology).
b) Berm shall be at least 1.0 meter in width for maintenance, stability and
patrol of the river purposes.
c) For a single berm revetment, the berm location shall be just above the
ordinary water level whenever possible.
Berm
(banquette)
H
Alignment
The alignment of the revetment should be as smooth as possible considering the
direction of flow, natural bank alignment nearby, condition of bend, scouring portion,
etc. In case of the joint portion with the rock-strewn slope, however, the alignment
shall not be unnaturally smooth.
Cross-section profiles
In accordance with the above dimensions, the cross-section profiles at the sites shall
be prepared and evaluated considering the river conditions.
If there are any difficulties in the profiles, the slope, the berm arrangement and the
alignment of the revetment shall be revised to cope with the difficulties.
Condition of Stretch
Straight and almost uniform
Non-uniform
stretch
including
meandering
Representative Cross-section
One (1) section with the smallest capacity
At least three (3) sections with the smallest
discharge capacities.
b)
For water level calculation at the design flood for each representative
cross section using uniform flow calculation.
c)
d)
e)
Velocity
The velocity of flow is an indispensable factor in the selection of the types of
revetment. The mean velocity derived in the uniform flow calculations is not equal to
the velocity of flow in front of the revetment. The velocity is actually influenced by the
effects of sand wave, bend and foot protection work. For designing the revetment, it
is recommended to correct the mean velocity to the design velocity of the revetment.
It is necessary to apply the correction to the mean velocity derived from the uniform
flow calculation. In cases there will be no correction, it is recommended that the
maximum value in the mean velocities of the representative cross-sections at the
design flood is adopted as the design velocity of the revetment at the proposed site
VD Vmave
Where:
VD
Vmave
:
:
Z
2H d
Equation 1
ii.
B
2r
Equation 2
B
Z
2r 2 H d
Equation 3
Where:
Correction Coefficient
(Segment 1: 2 and
Segment 2 and 3: 1.6
B River width (m)
r Radius of the bend (m)
Z Maximum scouring depth (m)
H d Average design water depth (m)
iii.
If
bw
1.0
Hl
0.91
Equation 4
If
bw
1.0
Hl
1.01
Equation 5
Hl
Hd
Average Riverbed
Foot Protection
bw
Sodded Riverbank
with Pile Fence
Allowable
Design
Velocity
(m/s)
Slope
(H:V)
4.0
Milder
than
2:1
Remarks
3.0
Milder
than
2:1
Grouted Riprap
(Spread Type)
5.0
Grouted Riprap
(Wall Type)
Gabion
(Piled-up Type)
6.5
Gabion
(Spread Type)
5.0
Rubble Concrete
(spread Type)
Rubble Concrete
(Wall Type)
Milder
than
2:1
1.5:1
to
0.5:1
1.5:1
to
0.5:1
Milder
than
1.5:1
Milder
than
1.5:1
Milder
than
1:1
Reinforced Concrete
Sheet Pile
N.A.
A minimum thickness of 20 cm
In cases where ordinary water level is very high.
Design procedure and sample design computation for steel
sheet pile is provided in Annex A of the Manual on Design of
Flood control Structures January 2005 Publication (Light
Green Book)
Water Depth
1.0
2.0
3.0
4.0
5.0
1.0
2.0
3.0
4.0
5.0
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
60
30
30
20
20
70
50
40
40
Appurtenance Works
The appurtenance works of the revetment are installed in order to protect the crest,
the upstream and downstream end of the slope covering from erosion and to prevent
the outflow or sucking out of materials or soils of the banks.
The following shall be considered in the design:
1)
Backfill materials
For the rigid type revetment, backfilling materials shall be installed in
order to reduce the force of the residual hydraulic pressure to the
covering works and to make the structure stable.
For the permeable type revetment such as wooden fence type and
gabion mattress type, the backfill materials is not necessary.
The backfilling materials shall be with high permeability, such as
crushed gravel, etc. Thickness of the backfill materials shall be 30 40
cm for wall type and 15 20 cm for pitching or lining type.
For the residual water pressure, weep holes are provided to let water
from the land side pass through the structure, however these weep
holes should have filter cloth or equivalent materials to prevent backfill
materials from escaping.
2)
3)
1,500 2,000 mm
1,000 mm (min)
Crest Armouring
Crest
Shoulder Beam
Key
Crest Armouring
Crest
500
(min)
4)
5)
Partition Works
In case the length of the rigid type revetment is more than 50 m, a
partition shall be installed in order to prevent the damage of the
revetment from spreading.
The structure of the partition works shall be the same as the end
protection works.
6)
Transition Works
A transition work to the natural bank is installed in order to connect the
revetment and the natural bank smoothly and to prevent erosion at the
upstream and downstream sides of the revetment from spreading
behind the revetment.
A transition work shall be flexible type like gabion mattress and the like.
The fitting angle to the natural bank shall be 30 degrees or less at the
upstream side and 45 degrees or less at the downstream side.
However the fitting angle shall be determined based on the present
condition of the bank.
45
30
Diameter (cm)
30
50
80
120
Gabion Type
Gabion Box
Design Velocities
3.0
4.0
5-15
10-20
5-15
5-15
5-15
5-15
5-15
5-15
5-15
5-15
5-15
5-15
5.0
15-20
15-20
5-15
5-15
5-15
6.0
15-20
15-20
15-20
15-20
Design Velocities
3.0
4.0
10
30
10
15
10
15
5
15
5
10
5
10
5.0
35
25
25
20
20
6.0
65
45
40
35
30
Wooden Stockade
Water
Depth
1.0
2.0
3.0
4.0
5.0
6.0
1.0
5
5
5
5
5
5
2.0
5
5
5
5
5
5
100.0
Single unit
Disorder pile up
10.0
Order pile up
1.0
0.1
10
100
2)
3)
Z
sin
Where:
B
Ln at least 2.0 meters
References:
Manual on Planning and Design
Manual on Design of Flood Control Structures
Technical Standards and Guidelines on Planning and Design of Flood Control
Volume 1