East

Side
Access

QuarterlyProgress
Monthly
Progress Report
Report
January,2014
February,
January
March 2014

Capital Construction

table of

CONTENTS

Quarterly Progress Report


1st Quarter 2014

1ST QUARTER HIGHLIGHTS WITH A LOOK AHEAD TO NEXT QUARTER................................................................................................... 1


ENTERPRISE LEVEL PROJECT EXECUTION PLAN (ELPEP)....................................................................................................................... 2
TOP RISKS AND OPPORTUNITIES.................................................................................................................................................................. 2
SUMMARY OF SCHEDULE............................................................................................................................................................................... 3
SUMMARY OF COST........................................................................................................................................................................................ 4
ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ in Millions)................................................................................................................ 6
44th St. Demolition and Construct Fan Plant Structure and 245 Park Ave. Entrance (CM004)..................................................................... 9
Manhattan South Structures (CM005)............................................................................................................................................................ 12
50th Street Ventilation Facility (CM013)......................................................................................................................................................... 15
55th Street Ventilation Facility (CM013A)....................................................................................................................................................... 18
GCT Concourse and Facilities Fit-Out Early Work (CM014A)........................................................................................................................ 21
Vertical Circulation - Escalators and Elevators (VM014)................................................................................................................................ 24
Manhattan Force Account (FMM19)............................................................................................................................................................... 26
Plaza Substation and Queens Structures (CQ032)........................................................................................................................................ 28
Harold Structures Part 1 and GO2 Substation (CH053)................................................................................................................................. 31
Harold Structures Part 2A (CH054A).............................................................................................................................................................. 34
Harold Stage 1 - Amtrak Force Account (FHA01)........................................................................................................................................... 37
Harold Stage 2 - Amtrak Force Account (FHA02) .......................................................................................................................................... 39
Harold Stage 1 - LIRR Force Account (FHL01) ............................................................................................................................................. 41
Harold Stage 2 - LIRR Force Account (FHL02) ............................................................................................................................................. 43
Procure Harold Material Stage 2 (VHA/L02).................................................................................................................................................. 46
Harold and Point CILs (VH051 Part 1) .......................................................................................................................................................... 48
Harold Tower Supervisory Control System (VH051 Part 2)............................................................................................................................ 50
SUMMARY OF COMPLETED CONTRACTS..................................................................................................................................................... 52
PROJECT SCHEDULE...................................................................................................................................................................................... 56
CONTRACT PACKAGING PLAN Rev.10.0..................................................................................................................................................... 58
MARCH BUDGET STATUS................................................................................................................................................................................ 59
PROJECT FUNDING STATUS (AS OF March 31, 2014) ($ in millions)............................................................................................................ 60
STATUS OF PROJECT CONTINGENCY........................................................................................................................................................... 61
CONSTRUCTION SAFETY................................................................................................................................................................................ 62
SYSTEM SAFETY AND SECURITY.................................................................................................................................................................. 62
QUALITY ASSURANCE..................................................................................................................................................................................... 62
12 MONTH CUMULATIVE RUNNING TOTAL OF LTA AND BLS RATES.......................................................................................................... 63
GRAND CENTRAL TERMINAL.......................................................................................................................................................................... 63
RAILROAD SYSTEMS....................................................................................................................................................................................... 63
OPERATIONAL READINESS/LIRR START UP................................................................................................................................................. 64
ENVIRONMENTAL MITIGATION....................................................................................................................................................................... 65

table
of
TABLE

CONTENTS

Quarterly Progress Report


1st Quarter 2014

PUBLIC OUTREACH......................................................................................................................................................................................... 65
REAL ESTATE.................................................................................................................................................................................................... 65
HISTORIC AND PRESERVATION ISSUES....................................................................................................................................................... 66
FEDERAL RAILROAD ADMINISTRATION HIGH SPEED INTERCITY PASSENGER RAIL GRANT................................................................ 67
1ST QUARTER HIGHLIGHTS WITH A LOOK AHEAD TO NEXT QUARTER............................................................................................... 68
DESIGN MILESTONES.................................................................................................................................................................................. 69
SUMMARY OF BUDGET AND FUNDING...................................................................................................................................................... 70
STATUS OF SUBMISSIONS AND APPROVALS........................................................................................................................................... 70
PROPOSED BUDGET................................................................................................................................................................................... 72
PROCUREMENT MILESTONES................................................................................................................................................................... 74
ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ in Millions)............................................................................................................ 75
Harold Stage 3 - Amtrak Force Account (FHA03)........................................................................................................................................... 76
Harold Stage 3 - LIRR Force Account (FHL03).............................................................................................................................................. 78
Loop Interlocking CIL - Amtrak (FQA65)......................................................................................................................................................... 80
Harold Structures - Part 3 Westbound Bypass (CH057A) ............................................................................................................................. 82

1st Quarter Jan, Feb, Mar 14

1ST QUARTER HIGHLIGHTS WITH A LOOK AHEAD TO NEXT QUARTER


ORGANIZATION
In March, MTACC announced a reorganization of the senior
management structure including the appointment of William
Goodrich as the new MTACC Executive Vice President, ESA
Senior Program Executive. The reorganization also included
the creation of three new Program Executives for Project
Controls, Heavy Construction and Harold/Systems.
In addition, a new Executive Change Review Committee has
been established for consultation and direction on major proposed construction contract modifications and major changes
to future construction contract packaging decisions
CONSTRUCTION SAFETY
The overall project safety rate improved slightly from 2.23 in
January and February to 2.22 incidents per 200,000 workhours in March. In comparison, the revised national industry
rate is now 1.70.
CONSTRUCTION MILESTONES
The following key milestones were reached in the 1st quarter:
The 50th Street Vent Plant Facility (CM013) contract
reached its Substantial Completion milestone in March
All major blasting and excavation was completed under the
site of the new 55th Street Vent Plant Facility (CM013A).
Construction has shifted to waterproofing installations
and concrete work in the plenum and cavern areas of the
facility.
MANHATTAN CONSTRUCTION
The Manhattan South Structures (CM005) contractor continues waterproofing, rebar and drainage installations and concrete work in areas of the GCT Caverns, Wyes and Tunnels
Completion of the GCT Concourse and Facilities Fit-Out Early
Work (CM014A) contract has been shifted to the 4th quarter
of 2014 due to a substantial redesign of the SCADA equipment. The equipment is now being fabricated and it will be
delivered on-site in the 2nd quarter. A contract modification for
the additional work and time is expected to be approved by
the MTA Board in the 2nd quarter, as well.
QUEENS CONSTRUCTION
The Plaza Substation and Queens Structures (CQ032) contractor continues the waterproofing, concrete work and rebar
installations at the yard lead trench, revenue track, and sump
pit. Concrete repairs and conduit installations also continue in
the existing 63rd Street tunnel.

MTA/LIRR East Side Access

The B10 Substation and facilities at Roosevelt Island, Vernon


Boulevard and 12th and 29th Streets were completed in
March. The facilities will be ready to be turned over to the
follow-on Systems Package 1 Facilities Systems (CS179)
contractor in May.
HAROLD CONSTRUCTION AND AMTRAK/
LIRR COORDINATION
Construction of Microtunnel Runs 1-4 started on the Harold
Structure Part 1 and GO2 Substation (CH053) contract. The
construction of the new 12KV ductbank and storm sewer continued on the Harold Structures Part 2A (CH054A) contract.
The 12KV Commissioning Plan was finalized with Amtrak in
February. Testing of the cable feeders prior to cutover commenced in March. Cutover of the C3 feeder is expected to
begin in April. Cutover of the remaining C1and C2 feeders will
follow in May. This is critical as it enables the Project to deenergize and remove the existing 12KV ductbank.
The Harold Structures Part 3 Westbound Bypass (CH057A)
contractor started site mobilization and initiated surveys for
future demolition work in the next quarter
PROCUREMENT
The Manhattan North Structures (CM006) contract was
awarded to Frontier Kemper Constructors Inc. on March 28,
2014. The total amount of the contract is $294,201,750. Kickoff meetings will commence in April.
System Package 1 Facilities Systems (CS179) contract
was awarded to Tutor Perini Corporation on March 31, 2014.
The total amount of the contract is $550,388,000 comprised
of a base amount of $333,588,000; plus 7 options totaling
$216,800,000. Kickoff meetings will commence in April.
The Harold Structures Relocated Mainline 2/4 Tracks at
48th Street (CH057B) and System Package 3 Signal Equipment Procurement (VS086) contracts are expected to be
awarded in the next quarter
The GCT Concourse and Facilities Fit-Out (CM014B), Harold
Track Work, On-Call (CH057C) and System Package 4
Traction Power Systems (CS084) contracts are expected to
be advertised in the next quarter
An Industry Outreach was conducted for the Manhattan Cavern Structure and Facilities Fit-Out (CM007) contract in Febru-

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14

1ST QUARTER HIGHLIGHTS WITH A LOOK AHEAD TO NEXT QUARTER (CONT)


ary. The results from this outreach are being evaluated and
incorporated into the bid package. This contract is expected to
be advertised in the 4th quarter.

COST
3rd Party contract modifications totaling $6,056,656 and
Consultant contract modifications totaling $119,374,949 were
executed in the 1st quarter

ENTERPRISE LEVEL PROJECT EXECUTION PLAN (ELPEP)


The PMOC provided comments to Project Management Plan
Revision 9.0. ESA is reviewing the comments and making
revisions where necessary.

An overall update to the Cost Management Plan and Schedule Management Plan is in progress

TOP RISKS AND OPPORTUNITIES


MANHATTAN
(Manhattan/Systems/IST Program Risk Assessment Stage
1) The project team and stakeholders concluded the Manhattan/Systems/IST program risk assessment in January 2014.
The workshop took into account all Systems and Manhattan
re-packaging since the 2012 program-wide risk assessment,
inter-contract interfaces, procurement actions and construction progress to date. Preliminary results were shared with all
stakeholders. The top cost and schedule risks identified from
the risk analysis were access delays affecting productivity of
civil packages, delays to IST and pre-revenue testing, agency
extended overheads due to schedule delay, and general
construction risks (design issues, owner directed changes,
labor/material shortages, general production and contractor
performance). This workshop was the first stage of a total
program review.
(Opportunity Study - Trackwork Transfer to Manhattan Civil
Contract(s)) The PMT is doing a study to ascertain the advantages of transferring trackwork from the Systems Package
2 - Tunnel Systems (CS284) contract package to Manhattan
civil packages. The objective is to determine if there are cost
effective transfers of scope that reduce risks to interfaces between contracts and schedule delay risks. The study is looking
at all track installation from the Queens tunnels down to the
tail tracks south of GCT. The study will include the means by
which transfers will be made, whether it is by a modification to
an existing civil contract or inclusion in the future Manhattan
Cavern Structure and Facilities Fit-Out (CM007) bid package.
Initial briefs have been made to the Executive Change Review

MTA/LIRR East Side Access

Committee.
(Opportunity Study - Cavern North Back of House (BOH)
Transfer to an Existing Manhattan Civil Contract) The PMT is
doing a study to ascertain the advantages of transferring the
future GCT Cavern North (BOH) scope to an existing Manhattan contract. As identified in presentations provided by the
PMT, the north BOH is a critical early component of cavern
construction that has early turnover milestones to the Systems
Package 1 - Facilities Systems (CS179) contract. The CM007
RFEI sessions with potential contractors also indicated this to
be an early critical build initiative. The objective is to determine
if there is a schedule and cost benefit advancing the scope
to an existing contract that reduces risk and provides earlier
turnover access to the CS179 start of BOH communications
work. Initial briefs have been made to the Executive Change
Review Committee.
(CM007 RFEI) The ESA RFEI team met individually with 10
potential bidders to discuss the design and build out ideas for
the future CM007 Cavern package. General themes discussed included hybrid designs for the structure, track, access
points, architectural finishes, schedule and the BOH ends
of the cavern. The project team will now consider the ideas
offered and will provide a recommendation for final design
direction. This package will follow an RFP procurement model
for a design/bid/build approach. Ideas collected from the
contracting community will be strongly considered to provide
the best risk reduction and cost effective solutions. Design
direction will incorporate ideas with merit into the final design
and bid package.

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14

TOP RISKS AND OPPORTUNITIES (CONT)


(Risk Workshop and Assessment - CM014B) The PMT is
preparing materials to perform a risk workshop for the GCT
Concourse and Facilities Fit-Out (CM014B) package. This
pre-award workshop will be independently facilitated and will
discuss the cost, schedule and risk complexion of the contract.
The workshop will be a joint collaboration with project stakeholders, the project management team and oversight partners. This contract package is responsible for the future GCT
Concourse construction and architectural fit out and will be
working in conjunction with the Vertical Circulation - Escalators
and Elevators (VM014) contract.

Systems workshop in January, the project team developed a


summarized schedule model and shared it with all participants
prior to the workshop. The collaborative workshop has been
completed and the independent Harold preliminary results
have been shared with participants. Now, the collected data
from both the Manhattan/Systems risk analysis and Harold will
be combined to complete a total program-wide risk review. The
schedule models will be merged, and a Monte Carlo analysis
will be performed on the integrated model and the top program
risks identified.

HAROLD
(Harold Risk Assessment Stage 2) A Harold risk assessment
was held in March as part of a two-stage program-wide risk
review. The four-day Harold workshop took into account all of
the re-packaging since the 2012 program-wide risk assessment, procurement actions, awards and active construction
progress to date. The revised Harold program Integrated
Project Schedule (IPS), cost estimates and risk register were
the starting basis to all discussions. Similar to the Manhattan/
SUMMARY OF SCHEDULE
The IPS continues to be a dynamic tool that is updated and modified
to account for changing conditions and additional information as it
becomes available. The current working IPS reflects a plan with a
target Revenue Service Date (RSD) of September 10, 2021. This
RSD is inclusive of one-year of program-level contingency.
The following contracts are on the East Side Access Program Critical Path: Manhattan South Structures (CM005), Manhattan Cavern
Structure and Facilities Fit-Out (CM007), and Systems Package
1 - Facilities Systems (CS179). In addition to the Program Critical
Path, the following contracts are near critical: Systems Package 2 Tunnel Systems (CS284) and System Package 4 Traction Power
Systems (CS084).
The completion of Harold contracts has approximately one year of
programmatic float in addition to the year of program level schedule
contingency; however, work within and around the Harold Interlocking is subject to influences outside of the control of ESA such as
Force Account and Railroad support. Therefore, significant attention is paid to the work in Harold to ensure the dynamic nature of
the availability of resources does not have a negative impact on
the overall program. Active Harold contracts Harold Structures Part
1 and GO2 Substation (CH053) and Harold Structures Part 2A

MTA/LIRR East Side Access

(CH054A) are both forecasting Substantial Completion by the end of


2014, and Harold Structures - Part 3 Westbound Bypass (CH057A)
is forecasting Substantial Completion by the end of February 2016.
GCT Concourse and Facilities Fit-Out (CM014B) has over one
year of programmatic float on the completion of construction work
in the concourse, but certain key interfaces with CS179 must be
monitored closely to ensure interim milestones are met, and that
critical Systems work can proceed without overwhelming available
Systems resources. The CM014B schedule has been revised to
include additional detail and provide better defined interfaces with
follow on contractors, as well as MNR outages required where work
penetrates the Revenue Service level of GCT.
The negotiated Manhattan North Structures (CM006) contract
was awarded March 28, 2014. The CM006 Access Restraints and
Milestones shown in the IPS represent the dates from the awarded
contract and have been validated against predecessor contracts in
the IPS.
The negotiated CS179 contract was awarded March 31, 2014. The
CS179 Access Restraints and Milestones shown in the IPS represent the dates in the awarded contract and have been validated
against predecessor contracts in the IPS.

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14

SUMMARY OF SCHEDULE (CONT)


The East Side Access IPS contains programmatic float. The Critical
Path of an individual contract or the float for an individual contract
can be obtained by isolating (filtering) it from the IPS.
The IPS will constantly evolve to incorporate opportunities,
mitigate risk, and document progress. After it was decided not to
Month
Contingency

Sept 2009 (ELPEP


Baseline)
131 Cal Days

award CM012R due to undesirable bid results, the IPS has been
re-planned and risk informed. The IPS is being utilized as a tool
to track, monitor, and forecast progress as the program moves
forward.

January 2014

February 2014

March 2014

TBD

365 Cal Days

365 Cal Days

Revised target RSD of September 10, 2021

SUMMARY OF COST
In January, MTACC presented to the MTA Capital Program Oversight Committee of the Board the preliminary results of the cost
and schedule review jointly undertaken by MTACC, MTAOCO,
Independent Engineer, a Supplemental Independent Engineer, and
the Federal Transit Administration. The presentation included a cost
range of $9.693B to $10.309B and a Revenue Service Date range
of September 2021 to September 2023. Since January, the MTACC
has been refining estimates. All budgets in this report reflect the
February 2014 Preliminary Project Estimates. MTACC will continue

MTA/LIRR East Side Access

to refine estimates, meet with MTAOCO and the Independent


Engineer to evaluate cost and schedule. Until this effort is complete
(targeted for 2nd quarter 2014), the project will monitor and report
progress against the low end of the cost and schedule ranges.
The budgets for Manhattan North Structures (CM006) and Systems
Package 1 - Facilities Systems (CS179) both received favorable
bids this quarter.

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14


ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ IN MILLIONS)

Current Value

Project
Description/
Contractor

Status

Budget
at Award

Cost
Expenditure %
Complete****

Original
Current Remaining
Total
Contract Approved
Budget Budget
Award Contract
****
****

Estimate at
Completion*

Plan Actual

Substantial Completion****

Invoiced

NTP

Plan

Forecast

Orig. Revised

Manhattan/Bronx
CM004 44th St. Demolition & Construct
Fan Plan Structure
& 245 Park Ave.
Entrance
Yonkers Contracting
Company, Inc. (YCC)

NO

42.8

40.8

55.3

0.2

55.5

55.2

100.0%

96.8%

53.5

09/16/09

09/11

12/13

05/14

CM005 - Manhattan
South Structures
Michels Corporation

NO

220.7

200.6

200.8

18.5

219.3

222.6

15.1%

20.2%

40.5

09/09/13

02/16

02/16

02/16

CM013 50th St.


Vent Facility
CCA Civil-Halmar
International (CCA)

NO

99.1

94.4

97.4

0.2

97.6

96.4

100.0%

97.4%

95.1

01/04/10

06/12

03/14

03/14

CM013A 55th
Street Vent Facility
SCC-JPP, JV
(Schiavone and
Picone, JV)

NO

58.8

56.0

56.4

3.7

60.1

57.1

30.6%

34.3%

19.3

09/04/12

04/15

04/15

04/15

CM014A - GCT Concourse & Facilities


Fit-Out Early Work
Yonkers Contracting
Company, Inc.

NO

46.5

44.7

51.9

6.0

57.9

55.9

91.8%

57.4%

29.8

11/07/11

04/13

02/14

12/14

VM014 - Vertical Circulation (Escalators &


Elevators)**
Schindler Elevator
Corp.

NO

51.4

24.4

24.6

29.7

54.3

46.0

2.0%

2.0%

4.0

09/27/10

09/18

09/18

07/19

MTA/LIRR East Side Access

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14


ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ IN MILLIONS)

Current Value

Budget
at Award

Cost
Expenditure %
Complete****

Original
Current Remaining
Total
Contract Approved
Budget Budget
Award Contract
****
****

Estimate at
Completion*

Plan Actual

Substantial Completion****

Project
Description/
Contractor

Status

Invoiced

NTP

Plan

Forecast

FMM19 - Manhattan
Force Account Support MNR***

NO

33.1

31.1

31.1

35.2

66.3

63.1

N/A

55.0%

28.3

04/01/08

03/12

07/13

01/21

NO

162.1

147.4

207.7

26.5

234.2

227.8

82.5%

53.0%

109.7

08/10/11

08/14

08/14

12/15

144.4

139.3

236.9

99.2

336.1

303.5

100.0%

87.6%

207.6

01/01/08

05/10

01/12

12/14

Orig. Revised

Queens
CQ032 - Plaza Substation and Queens
Structures
Tutor Perini

Harold Interlocking
CH053 - Harold
Structures Part 1 and
GO2 Substation
Perini Corp.

CP

CH054A - Harold
Structures Part 2A
Perini Corp.
FHA01 - Harold Stage
1 Amtrak
Amtrak Force
Account***, ****
FHA02 - Harold Early
Stage 2 Amtrak
Amtrak Force
Account***, ****
FHL01 - Harold Stage
1 LIRR
LIRR Force Account***,
****
FHL02 - Harold Early
Stage 2 LIRR
LIRR Force Account***,
****

NO

27.1

21.8

44.8

25.2

70.0

64.3

100.0%

76.1%

33.9

08/24/08

12/10

12/10

11/14

CP

9.5

18.8

18.8

0.0

18.8

18.8

95.5%

95.5%

18.2

06/30/07

09/10

02/16

02/16

CP

27.3

38.6

38.6

3.1

41.7

41.7

79.4%

78.3%

36.9

12/15/08

09/13

08/17

09/17

NO

28.8

20.8

20.8

0.0

20.8

20.8

77.4%

77.4%

18.1

06/29/07

09/10

04/15

01/15

NO

54.1

48.2

48.2

23.0

71.2

71.2

37.6%

33.4%

30.7

08/17/09

11/15

11/16

11/16

MTA/LIRR East Side Access

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14


ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ IN MILLIONS)

Current Value

Budget
at Award

Original
Current
Contract Approved
Award Contract
****
****

Cost
Expenditure %
Complete****

Remaining
Total Estimate at
Budget Budget Completion*

Substantial Completion****

Project
Description/
Contractor

Status

Plan Actual Invoiced

VHA02 - Procure
Harold Material
Stage 2 Amtrak
Amtrak Force Account

NO

12.7

11.2

11.2

0.1

11.3

11.3

N/A

80.1%

6.6

VHL02 - Procure
Harold Material
Stage 2 LIRR
LIRR Procurement

NO

25.0

23.2

23.2

0.8

24.0

24.0

N/A

89.3%

VH051 (Part 1) Harold and Point


CILs
Ansaldo STS USA,
Inc. (ASTS)

NO

30.9

25.5

26.8

7.0

33.8

29.0

82.0%

VH051 (Part 2)
- Harold Tower Supervisory Control
System
ARINC, Inc.

NO

7.1

7.2

7.2

1.4

8.6

7.6

93.0%

Total Award Value

$1,201.7

NTP

Plan

Forecast

Orig.

Revised

01/09

01/12

05/12

08/14

22.4

01/09

08/13

08/13

11/15

78.0%

19.4

05/11/09

06/12

07/15

07/15

88.0%

7.0

02/03/09

08/10

08/10

07/15

*EACs do not include possible contract mods and future claims. **Current approved contract does not include full scope. ***Actual Cumulative % Complete
is based on Current Contract Value. ****Contract Awards for Force Account work (FHA01, FHA02, FHL01, FHL02) are made on an annual basis.
For more information, please refer to the individual contract summaries.
Status

Critical Path (CP)

MTA/LIRR East Side Access

Near Critical (NC)

Not Critical (NO)

(PM 3.5.108757)

1st Quarter Jan, Feb, Mar 14

44th St. Demolition & Construct Fan Plant Structure & 245
Park Ave. Entrance (CM004) 47 E. 44th Street: Demolish existing building,
perform soil and rock excavation. Construct shell of new building. 245 Park Avenue
Entrance: Conduct environmental abatement and demolition; construct new
foundations, walls and supports, furnish and install escalator. Install architectural
finishes, plumbing, fire protection, HVAC, lighting, power, fire alarm, and communication systems.
Manhattan South Structures (CM005) The Manhattan South Structures
work provides the fabrication and construction of permanent structural concrete
lining, interior structures, and fit-out for caverns and tunnels previously excavated
by others beneath Grand Central Terminal located in Manhattan.
Manhattan North Structures (CM006) Work on the Manhattan North
Structures consists of the installation of the permanent lining, duct bench and
embedded MEP in all running tunnels and structures north of the GCT station
caverns, construction of the 50th Street air plenum cavern and the underground
55th Street ventilation facility as well as rehabilitation to the existing 63rd Street
tunnel.
50th St. Ventilation Facility (CM013) Construction of new ventilation building structure and vertical utility shaft form building foundation at 50th
St.
55th St. Ventilation Facility (CM013A) Work includes excavation from
the street level to an existing cavern below. Upon completion of excavation, a
subsurface concrete vent building is erected from the cavern invert to the sidewalk
elevation.
GCT Concourse & Facilities Fit-Out Early Work (CM014A)
Fit-out of lower portion of new LIRR concourse located in the lower level of GCT,
Construction of south sub-station facility, fit-out of shaft 2, procurement of electrical
equipment for north substation & unit substations, Construction & fit-out of terminal
management system & Construction of certain rooms adjacent to south substation
& TMC.
Vertical Circulation - Escalators & Elevators (VM014) The base
scope includes the fabrication and installation of 17 elevators and 45 escalators for
the Concourse, Caverns, 44th and 50th St. Ventilation Facilities, and MNR facilities. Options exist for an additional five elevators and two escalators.
Manhattan Structures Part 1 MNR (FMM19) MNR Railroad resources in support of the contracts CM019, CM004, CM013, CM014A and General
Conditions contracts in the vicinity of GCT. These resources include both direct
and indirect labor, worktrain support, and track outages.

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
44th St. Demolition and Construct Fan Plant Structure and 245 Park Ave. Entrance
(CM004)
Contractor: Yonkers Contracting Company, Inc.
(YCC)
Construction Manager: Bill Madden
FTA Grant: NY-03-0344, ARRA Stimulus Funds
NY-36-0002
SCHEDULE PROGRESS

44th Street Vent Plant


The forecast Substantial Completion is May 15; six
week delay due to lack of Contractor coordination. YCC
is waiting on resolution of underground interferences
impacting the utility work
Above ground intumescent painting completion has been
delayed to early April due to lack of Contractor coordination and weather issues
Completed staircases, handrails, insulation and sheetrock as planned
CRITICAL ISSUES

The critical path goes through the utility work on the north
side of the street which is forecast to complete in May on
schedule. DEP approval of water service is required.
Terrazzo rework is required at 245 Park Avenue; it will be

Description: 47 E. 44th Street: Remove hazardous

material, demolish existing building, perform soil and rock


excavation. Construct shell of new building. Frame and
partially fit-out new building. 245 Park Avenue Entrance:
Conduct environmental abatement and demolition; construct
new foundations, walls and supports, furnish and install
escalator. Install architectural finishes, plumbing, fire protection, HVAC, lighting, power, fire alarm, and communication
systems.

Completed CMU and concrete encasement as planned


Continued utility work at 44th Street; expected completion May 15, a two month delay due to slow progress to
obtain DEP approvals
Completed Shaft 1 and AT-1 punch-list
245 Park Avenue Entrance
Punch list is ongoing and is expected to be complete August 15; three months later than forecasted last quarter
due to Contractor delays
handled as a punch list item
44th Street Sewer connection is being removed from the
contract. Sewer connection will be redesigned into Madison Yard under CM014A and reflected in revised schedule.

MITIGATION

The south side street utility work and sewer connection is being removed from the contract and transferred to CM014B.

COST

79 modifications have been executed, which is the same as


last month. 96.8% of the total CM004 current contract value
was invoiced as of March 2014, up from 95.2% last month.
95.0% of the current contract value has been paid, up from
LOOK AHEAD

44th Street Vent Plant: Complete all work in the building by


mid-April. Complete utility work in the street by May 15.
SAFETY

Continued emphasizing importance of safety with


the contractor to minimize safety issues and correct any issues immediately
Management walkthroughs conducted on a
weekly basis, to assure that CMs office and contractors management get together and address
MTA/LIRR East Side Access

93.2% last month. The EAC has decreased slightly from


$55,281,648 reported last month. The EAC includes two
pending contract credits totaling $92,000.

245 Park Avenue Entrance: Complete punch list items by


August 15

any and all concerns with the project


The FDNY conducts bi-weekly tours
1st quarter safety assessment performed
Safety StatisticsLTIR 2.61, B.L.S. (Bureau of
Labor Standards) 1.70
(PM 3.5.108757)

LTIR represents incidents that


occurred for
every 200,000
manhours
worked.
9

CM004 PROGRESS CURVE


100%

Original Baseline

50

Current Baseline

80%

Actuals/Forecast

40
60%
30

1st Quarter
Current
Period
Plan:
Plan:
0.2%1.0%

20

0
Sep-09

Jan-10

May-10

Sep-10

Jan-11

May-11

Sep-11

Jan-12

May-12

Sep-12

20%

Actual: 96.8%

Actual:
Actual:
0.6%3.7%

10

40%

Cumulative
Plan: 100.0%

Jan-13

May-13

Sep-13

0%
May-14

Jan-14

MILESTONES
2008

2009

2010

2011

2012

2013

Current

Actual/

Baseline

Forecast

Notice to Proceed

9/16/09

9/16/09

Complete South End of Platform E

5/28/10

10/05/11

Complete Rock Excavation &


Shaft Construction, 44th

1/28/13

6/28/13

Beneficial Use of 245 Park

10/4/12

10/21/13

Substantial Completion of 44th St.


Vent Plant

12/31/13

5/15/14

(+135 days)

Final Completion - 44th St.

3/30/14

8/1/14

(+124 days)

Q3 Q4 Q1

Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1

2014

Q2 Q3 Q4 Q1

Q2 Q3 Q4

(0 days)

(+495 days)

Current Baseline

Actual/Forecast

(+151 days)

(+382 days)

FINANCIAL SUMMARY
Budget
$55,541,413

Contract
(Award/Mods)
$55,281,647

$55,541,413

$40,765,000

Invoiced
$53,503,137

$14,516,647

$53,503,137

Paid to Date
$52,507,921

$52,507,921

EAC
$55,189,648

$55,189,648

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

10

SITE MAP

44th Street Vent Plant Facility


Park Avenue
245 Park Avenue Entrance

MTA/LIRR East Side Access

(PM 3.5.108757)

11

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
Manhattan South Structures (CM005)
Description: The Manhattan South Structures work

Contractor: Michels Corporation

provides the fabrication and construction of permanent


structural concrete lining, interior structures, and fit-out
for caverns and tunnels previously excavated by others
beneath the existing Grand Central Terminal located in
Manhattan.

Construction Manager: Vincent Monaco


FTA Grant: NY-03-0344

SCHEDULE PROGRESS
East Cavern: Completed rebar installation in pits #1, 2, 4 & 6 and
continued installation in pits #3, 5, 7, 8 & 9. Completed invert
pours in pits #1, 2, 3, 4, 5 & 6. The rebar & concrete installation
progress in the pits is 40% complete vs. 31% planned. Michels
started rebar installation for the EB Cavern structural slab and is
5.6% complete. The rebar installation is expected to be complete
by July 30.
West Cavern: Completed smoothing shotcrete operation on the
wall of west bound cavern. Continued waterproofing installation
on the West & East wall and waterproofing installation in the pits.
The waterproofing is ahead as compared to the approved plan
and is 73.7% complete.
GCT 1 & 2 EB: Continued waterproofing in GCT 1 & 2 walls
ahead of baseline schedule. Waterproofing installation is 74%
CRITICAL ISSUES
Milestone #2 - Complete North Half of EB Cavern Slab - MS 2
July 6. This milestone is independent of the SC in the schedule
therefore, no impact to the SC.

complete vs. 50% planned. (Michels changed the plan in the last
update to install WP from the upper slab to the invert which was
different from the original plan in which installation was only from
the Mezzanine level to the Invert). Michels started installation of
invert rebar.
Tail Tunnel L402: Completed concrete pours for invert ahead of
the planned baseline date. The L402 concrete invert installation
work is 100% complete vs. 0% planned. The waterproofing installation for the arch also started ahead of the baseline plan and is
currently 49% complete vs. 0% planned. The waterproofing installation is expected to be complete by April 11.
Tail Tunnel L403: Started rebar & concrete installation of structural slab ahead of the planned start date and is currently 97%
complete vs. 0% planned.
WB Cavern - MS 3 - January 12 is trending behind original plan.
Michels and CM team are working to mitigate the delay caused
by slow progress and design issues. This MS is independent of
SC work and shows no impact to the SC.

Milestone #3 - Complete South Half of EB Cavern and Entire


MITIGATION
As part of the mitigation of MS #2 and 3, the contractor started
crew will move from EB pit to WB pit. Currently the schedule
invert rebar installation on April 2 in the EB Cavern, which is
reflects one rebar crew moving from EB cavern pits to EB cavern
earlier than the planned start of May 13 to recover the schedule.
invert to westbound cavern pits.
Contractor informed the CM team that the EB Cavern pit rebar
COST
Two contract modifications have been executed, up one from last
The EAC increased from the $200,092,743 reported last month.
month. 20.2% of the CM005 current contract value has been inThe EAC includes eight pending and potential modifications totalvoiced as of March 2014, up from 14.2% last month. 10.5% of the
ing $21,800,000, which includes a new potential modification of
current contract value has been paid up from 8.0% last month.
approximately $12M.
LOOK AHEAD
Continue rebar installation in EB Cavern structural slab
Complete invert concrete pouring in L403 Tunnel
Complete waterproofing in the WB Cavern walls and pits
Continue Rebar installation in GCT 1&2 EB Invert
Continue arch waterproofing in L402 Tunnel
SAFETY
The CM conducts weekly safety walks
Safety audits will be conducted on a
reau of Labor
LTIR represents
which Michels will attend to address all
quarterly basis
Standards)
incidents that ocon-site safety related issues
1.70
curred for every
1st quarter safety assessment performed
The FDNY conducts bi-weekly tours
MTA/LIRR East Side Access

Safety StatisticsLTIR 3.05, B.L.S. (Bu(PM 3.5.108757)

200,000 manhours
worked.

12

CM005 PROGRESS CURVE


200
190
180
170
160
150
140
130
120
110
100
90
80
70
60
50
40
30
20
10
0

100%
Current Baseline Early

90%

Contractor Baseline

80%

Actual

70%
60%
50%

1st Quarter
Plan: 9.6%

40%

Cumulative
Plan: 15.1%

Actual: 11.8%

30%
20%

Actual: 20.2%

10%
0%

MILESTONES
Current
Baseline

Actual/
Forecast

Notice to Proceed

9/9/13

9/9/13

Escalator/Cavern Connections

9/9/14

7/9/14

North End of East Cavern

7/6/14

8/6/14

North End of West Cavern

1/12/15

2/11/15

Substantial Completion

2/6/16

2/6/16

Final Completion

5/6/16

5/6/16

2012
Q1

2013

Q2 Q3 Q4 Q1

2014

Q2 Q3 Q4 Q1

2015

Q2 Q3 Q4 Q1

2016

Q2 Q3 Q4 Q1

Q3 Q4

(-62 days)
(+31 days)

(+30 days)

(0 days)

Q2

(0 days)

Current Baseline

2017

Q2 Q3 Q4 Q1

Actual/Forecast

(0 days)

FINANCIAL SUMMARY
Budget
$219,311,991

$219,311,991

Contract
(Award/Mods)
$200,766,277

$200,602,743
$163,534

Mods
Invoiced
$40,547,882

$40,547,882

Paid to Date
$21,100,816
$21,100,816

EAC
$222,566,277

$222,566,277

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

13

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

14

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
50th Street Ventilation Facility (CM013)
Description: Construct 50th St. Ventilation Facility.

Contractor: CCA Civil-Halmar International


Construction Manager: Vincent Monaco
FTA Grant: NY-03-0344

SCHEDULE PROGRESS

Vent Building: Completed roof railing installation at the ventbuilding. Flood tested mid-roof gravel placement.
Public Open Space: Wiring to permanent power panel
pending Con-Edison account application. Stone paver inCRITICAL ISSUES

Based on Time Impact Analysis (TIA) for the renegotiation


of mod 32, Milestone 3 Substantial Completion was moved
from December 31, 2013 to March 3, 2014, with the conditions that the mod will be executed by January 22. However, the mod was not finalized and delivered until February
6. NOC 23 is requesting 17 days delay. Letter ESA-CH-403
Response to Letter CH-MTA-263 Time Impact Adjustment

Work includes: building demolition including environmental abatement, termination of utility connections; foundation excavation and lining; shaft and tunnel excavation
and lining; and construction of new ventilation building
structure and vertical utility shaft.

stallation is ongoing (only pavers at fountain basin remain).


Green screen installation is in progress. Plantings and
irrigation to be done in Spring.
Vent Shaft: Punch list work is in progress
to Mod 32 was sent to the Contractor on February 26
with the response that the NOC should have merit with 17
excusable non-compensable days.
Milestone 3 to be moved from March 3 to March 20. CPR
43 sent to the CM on March 10. MTA approved TIA-0050
and Project Estimate-0063 on March 28. These are required for Mod 37.

MITIGATION

MTA is monitoring the completion of remaining contract work and punch list completion. Substantial Completion will be retroactively issued, effective March 20.
COST

26 modifications have been executed, which is the same


as last month. 97.6% of the CM013 current contract value
has been invoiced as of March 2014, which is the same as
last month. 91.3% of the current contract value has been

paid, up from 90.1% last month. The EAC decreased from


the $97,660,279 reported last month. The EAC includes
two pending and potential modifications totaling a credit of
$992,776.

LOOK AHEAD

Punch list and demobilization


SAFETY

Continued to maintain emphasis on safety with


contractor and their trades through daily walkthroughs and developing daily hazard logs
Continue with CM Management/OCIP walks on a
weekly basis

MTA/LIRR East Side Access

Performing monthly Safe Work Plan audits


The FDNY conducts bi-weekly tours
1st quarter safety assessment performed
Safety StatisticsLTIR 2.14, B.L.S. (Bureau of
Labor Standards) 1.70

(PM 3.5.108757)

LTIR represents
incidents that
occurred for
every 200,000
manhours
worked.

15

CM013 PROGRESS CURVE


100

100%
Original Baseline

90

90%

Rebaseline Late Mod25


Rebaseline Late (Global Mod)

80
70

80%

Mod 32 Rebaseline
Actual

70%

60

60%

50

50%

40

40%

1st Quarter
Plan: 3.1%

30
20

Cumulative
Plan: 100.0%

Actual: 2.6%

10

30%
20%

Actual: 97.4%

10%

0%

MILESTONES
2009

Notice to Proceed
Installation of Street Decking
300 Park Wall & Site Access
New Milestone for Shaft Access
Complete 280 Park Ave.
Substantial Completion
Final Completion - 44th St.

Current
Baseline

Actual/
Forecast

1/4/10
11/19/10
2/6/11
8/27/12
3/3/14
4/1/14

1/4/10
11/6/10
4/29/11
8/1/13
11/30/13
3/20/14
4/18/14

Q1

2010

Q2 Q3 Q4 Q1

Q2

Current Baseline

2011

Q3 Q4 Q1

2012

Q2 Q3 Q4 Q1

2013

Q2 Q3 Q4 Q1

2014

Q2 Q3 Q4 Q1

Q2 Q3 Q4

(0 days)

(-13 days)

(+82 days)

(+339 days)

(+17 days)

(+17 days)

Actual/Forecast

FINANCIAL SUMMARY
Budget
$97,581,387

$96,740,304

Contract
(Award/Mods)
$97,417,038

$841,083

$94,355,000

$2,220,955
$841,083

Invoiced
$95,125,744

Paid to Date
$88,987,053

$94,284,661

$88,145,970

$841,083

$841,083

EAC
$96,437,930

$95,596,847

ESA

$841,083

Regional Investment

Other

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

16

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

17

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
55th Street Ventilation Facility (CM013A)
Contractor: SCC-JPP, JV (Schiavone and Picone,
JV)
Construction Manager: Caroline Purcell
FTA Grant: NY-03-0344

Description: Work includes excavation from


the street level to an existing cavern below. Upon
completion of excavation, a subsurface concrete
vent building is erected from the cavern invert to the
sidewalk elevation.

SCHEDULE PROGRESS

The waterproofing installation in the Cavern walls up to


spring-line started as planned on March 7. The overall
waterproofing installation is 38% complete. The remaining waterproofing in the cavern wall is expected to be
complete by April 15 which includes water barriers and
inspection on the west wall.

In the plenum, the waterproofing on the east side below


the bench level is complete. Contractor commenced the
installation of rebar for the invert and completed the rebar
installation and concrete pour for the first 60 feet of invert
section in the Cavern. The invert concrete is 45% complete.

CRITICAL ISSUES

The approval of cable support design by Con Edison is


required to commence installation of rebar/formwork for
the facility level floor slab. The slab work is on the contract
critical path and may impact the current completion date.

Based on current approved CPM schedule UD#14, the


rebar installation for the slab is expected to commence on
May 28.

MITIGATION

MTACC is working with the GEC to come up with an alternate design in case Con Edison does not approve the contractual
design
COST

Five contract modifications have been executed, up four


from last month. 34.3% of the CM013A current contract value has been invoiced as of March 2014, up from 30.6% last
month. 27.7% of the current contract value has been paid,

up from 25.7% last month. The EAC has increased from the
$56,409,275 reported last month. The EAC includes seven
pending and potential modifications totaling $698,467.

LOOK AHEAD

Complete waterproofing installation in the Cavern walls


Complete invert concrete pour and commence wall rebars
Commence invert rebar and concrete pour in the east

plenum
Continue waterproofing in the plenum
Get Con Edison approval of cable support design

SAFETY

Continued to maintain emphasis on safety and


public protection around the site with contractor
and their workers
Conducted daily safety walks and documented
them in the daily hazard logs
Performing monthly Safe Work Plan audits
MTA/LIRR East Side Access

The FDNY conducts bi-weekly tours


1st quarter safety assessment performed
Safety StatisticsLTIR 1.68, B.L.S. (Bureau of
Labor Standards) 1.70

(PM 3.5.108757)

LTIR represents
incidents that
occurred for
every 200,000
manhours
worked.

18

CM013A PROGRESS CURVE


100%

Current Baseline Early


50

90%

Contractor Baseline

80%

Actual

40

70%
60%

30

50%
40%

20

Cumulative
Plan: 30.6%

1st Quarter
Plan: 7.5%

10

Actual: 34.3%

Actual: 7.2%
0
Sep-12

Nov-12

Jan-13

Mar-13

May-13

Jul-13

Sep-13

Nov-13

Jan-14

Mar-14

May-14

Jul-14

Sep-14

Nov-14

Jan-15

Mar-15

May-15

30%
20%
10%
0%
Jul-15

MILESTONES
Current
Baseline

Actual/
Forecast

Substantial Completion

9/4/12
2/21/14
10/1/14
4/5/15

9/4/12
2/21/14
10/1/14
4/5/15

Final Completion

7/4/15

7/4/15

Notice to Proceed
Access Restraint #1
Milestone #1

2012
Q1

2013

Q2 Q3 Q4 Q1

Current Baseline

2014

Q2 Q3 Q4 Q1

2015

Q2 Q3 Q4 Q1

2016

Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1

2017
Q2 Q3 Q4

(0 days)

Actual/Forecast

(0 days)

(0 days)

(0 days)

(0 days)

FINANCIAL SUMMARY
Budget
$60,058,213

$60,058,213

Contract
(Award/Mods)
$56,396,275

Invoiced
$19,338,179

Paid to Date
$15,625,806

$56,044,000

$352,275

$19,338,179

$15,625,806

EAC
$57,094,742

$57,094,742

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

19

SITE MAP

55th Street Vent Plant

MTA/LIRR East Side Access

(PM 3.5.108757)

20

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
GCT Concourse and Facilities Fit-Out Early Work (CM014A)
Description: Fit-out of lower portion of new LIRR con-

Contractor: Yonkers Contracting Company, Inc.


(YCC)
Construction Manager: Bill Madden
FTA Grant: NY-03-0344
SCHEDULE PROGRESS
Slab on grade concrete placement is 99% complete, with some
change order work to complete
Continued CMU wall, door frame and concrete header construction. It had a three-month delay this quarter due to slow Contractor performance, existing utility interferences and design refinements which are the subject of NOCs and CPRs.
Unit substation conduit and wiring were installed this quarter, a
two month delay due to slow Contractor performance
CRITICAL ISSUES
The Contractor issued a CPM with a projected Substantial Completion date of December 3, a three month delay which is driven
by change order issues. The CM believes that even though the
projection is more reasonable than recent submittals, based on
past performance, YCC will be on the job until December. This is
almost 10 months later than the unilateral modification. They are
less than 65% complete, 28 months into the job.
MITIGATION
SCADA unilateral modification to capture time related portion of
SCADA delay has been issued to the Contractor, and caps the
impact due to SCADA at 308 calendar days. Meetings to finalize
compensable delay costs are on-going.
COST
21 contract modifications have been executed, up 19 from last
month. 57.4% of the CM014A current contract value has been
invoiced as of March 2014, down from 58.6% which was reported
in error last month. 54.1% of the current contract value has been
paid, down from 55.8% which was also reported incorrectly last
LOOK AHEAD
Complete CMU work and unit substation conduit and wiring by
the end of June
Continue HVAC and plumbing installation and SCADA equipment
SAFETY
Continue to stress the importance of safety with field
staff. Addressed safety issues and documented what
was corrected through hazard logs.
Conducting workshops for contractor when reviewing
plans for upcoming work
MTA/LIRR East Side Access

course located in the lower level of GCT, construction of


south sub-station facility, fit-out of shaft #2, procurement
of electrical equipment for north substation and US-3/
US-4 unit substations, construction and fit-out of Terminal
Management Center (TMC), and construction of certain
rooms adjacent to south substation and TMC.

Seismic clip installation began this quarter, a two month delay


due to slow Contractor performance and execution of a Contract
Modification for the seismic clips
Continued CM014B scope transfer work. This is an additional
work item and is forecast to complete in May, a two month loss in
the quarter due to slow Contractor progress.
Work continued in Shaft 2. This is forecast to complete in May, a
two month delay due to slow Contractor progress.
SCADA delay costs are expected to be finalized in April, a three
month delay this quarter
Switchgear delivery is expected in May. The Con Edison approval
process may impact the delivery date further.
Scheduling and coordination of Con Edison energization of substations could impact Substantial Completion
Slow Contractor performance
ESA management and the CM are meeting on a regular basis
with the Contractor to address critical issues
The CM team is coordinating with Con Edison on required approvals
month. Non-ESA budget was mistakenly not factored in last
month. The EAC decreased from the $55,760,143 reported last
month. The EAC includes nine pending and potential modifications totaling $2,750,338.
fabrication
Switchgear delivery and installation and completion of work in
Shaft 2 is expected by the end of May

Performing monthly Safe Work Plan audits


The FDNY conducts bi-weekly tours
1st quarter safety assessment performed
Safety StatisticsLTIR 2.59, B.L.S. (Bureau of Labor
Standards) 1.70
(PM 3.5.108757)

LTIR represents incidents that


occurred for
every 200,000
manhours
worked.
21

CM014A PROGRESS CURVE


50

100%
Current Baseline

45

Original Baseline

40

80%

Actual/Forecast

35
30

60%

25
20

40%

15

1st Quarter
Plan: 15.9%

20%

1-Jan-15

1-Dec-14

1-Oct-14

1-Nov-14

1-Sep-14

1-Jul-14

1-Apr-14

1-May-14

1-Mar-14

Actual: 57.4%*
1-Feb-14

1-Jan-14

1-Dec-13

1-Oct-13

1-Nov-13

1-Sep-13

1-Jul-13

1-Aug-13

1-Jun-13

1-Apr-13

1-May-13

1-Mar-13

1-Feb-13

1-Jan-13

1-Dec-12

1-Oct-12

1-Nov-12

1-Sep-12

1-Jul-12

1-Aug-12

1-Jun-12

1-Apr-12

1-May-12

1-Mar-12

1-Feb-12

1-Jan-12

1-Dec-11

1-Oct-11

Actual: 5.4%
1-Nov-11

1-Aug-14

Cumulative
Plan: 91.8%

1-Jun-14

10

0%

*Cumulative Actual % Complete decreased this month due to an increase in the Current Contract Value

MILESTONES
2011
Current
Baseline

2012

2013

Actual/Forecast Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Notice to Proceed

11/7/11

11/7/11

Substantial Completion

2/26/14

12/15/14

Final Completion

5/27/14

3/15/15

2014

2015

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Q2 Q3 Q4

(0 days)

Current Baseline

2016

Actual/Forecast

(+292 days)

(+292 days)

FINANCIAL SUMMARY
Budget
$57,873,104

$56,684,834
$1,188,270

Contract
(Award/Mods)
$51,942,273

$43,502,000

$7,225,541

$1,214,732
Invoiced
$29,808,453

Paid to Date
$28,085,692

$29,808,453

$28,085,692

EAC
$55,903,097

$54,714,827

ESA

Regional Investment

$1,188,270

Other

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

22

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

23

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
Vertical Circulation - Escalators and Elevators (VM014)
Contractor: Schindler Elevator Corp.
Construction Manager: Doug Tilden
FTA Grant: NY-03-0344/Freedom Grant NY57-X018-00

Description: The base scope includes the fabrication

and installation of 17 elevators and 45 escalators for the


Concourse, Caverns, 44th and 50th St. Ventilation Facilities, and MNR facilities. Options exist for an additional five
elevators and two escalators.

SCHEDULE PROGRESS

The contractor continues Phase II Fabrication work which currently involves the submittal of shop drawings

CRITICAL ISSUES

The contractor is preparing a change proposal for increased labor and material costs resulting from the adjustments to the
GCT Concourse and Facilities Fit-Out (CM014B) schedule as initially set forth in the VM014 contract awarded in September 2010
MITIGATION

The ESA team is completing the negotiations and contract modification to the contract

COST

One contract modification has been executed. 16.4% of the current contract value has been invoiced and paid as of March
2014. The EAC includes one pending modification of $340,775. All of these measures are the same as last month. The EAC
did not change from last month.

LOOK AHEAD

Finalizing shop drawing reviews and authorizing commencement of fabrication for the 22 escalators and 14 elevators within
the VM014 contract to be installed as part of the GCT Concourse and Facilities Fit-Out (CM014B) contract

MTA/LIRR East Side Access

(PM 3.5.108757)

24

PERCENT COMPLETE
Schedule Progress

Current Period

Cumulative

Cost Expenditure

Plan

Actual

Plan

Actual

Phase 1Engineering

100%

100%

1%

1%

Phase IIFabrication

10%

10%

2%

2%

Phase IIIInstallation

0%

0%

N/A

N/A

Phase IVInterim Maint.

0%

0%

N/A

N/A

MILESTONES

Notice of Award
Notice to Proceed
Substantial Completion
Final Completion

Current

Actual/

Baseline

Forecast

9/23/10
9/27/10
9/20/18
12/20/18

9/23/10
9/27/10
7/24/19
10/24/19
Current Baseline

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4

(0 days)
(0 days)

(+307 days)
(+308 days)

Actual/Forecast

FINANCIAL SUMMARY

Budget
$54,282,562

$2,731,406

$51,112,592

$438,564
Contract
$24,620,341

Invoiced
$4,043,700

Paid to Date
$4,043,700

$24,374,558

$937,840

$245,784

RI

RI

RI

$3,105,860

$937,840

RI

$3,105,860
$438,564

EAC
$45,973,993

$2,731,406

$42,804,023

ESA

RI

Regional Investment

Other

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

25

1st Quarter Jan, Feb, Mar 14

Manhattan Construction
Manhattan Force Account (FMM19)
Description: MNR Railroad resources in support of

Contractor: Metro-North Railroad

the Manhattan active and future contracts. These resources include both direct and indirect labor, flagging, project
management, work train support, load inspection, rail cars
inspection and repair, and track outages.

Construction Manager: Fred Atiles


FTA Grant: NY-03-0344

SCHEDULE PROGRESS

MNR continued to provide flagman protection outside of


Madison Yard envelope during the day time
MNR continued to provide flagman support and track outages to Yonkers Contracting for contract CM014A

MNR continued to provide flagman support and track outages to Yonkers Contracting for contract CM004 so they
can complete their punch list work

CRITICAL ISSUES

None

MITIGATION

N/A

COST

91.1% of the FMM19 current contract value has been invoiced and paid as of March 2014, up from 90.8% last month. The
EAC did not change from last month.
LOOK AHEAD

Continue to provide flagman protection outside of Madison Yard envelope during the day time shift
FINANCIAL SUMMARY
Budget
$66,274,222

$61,745,148
$4,529,074

Contract
$31,094,340

$31,094,340

Invoiced
$28,313,629

$28,313,629

Paid to Date
$28,313,629

$28,313,629
$4,529,074

EAC
$63,143,325

$58,614,251

ESA

Regional Investment

Other

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

26

1st Quarter Jan, Feb, Mar 14

Queens/Harold Construction

Plaza Substation and Queens Structures (CQ032) Structural and architectural rehabilitation to
existing facilities along existing 63rd St. Tunnel. Construction of Plaza Interlocking below grade facilities for
Mainline Traction Power Substation C06, Facility Power Substation B11, ventilation, signal, emergency power,
mechanical and communication rooms.
Harold Structures 1 and GO2 Substation (CH053) Construct various civil infrastructure elements at Harold Interlocking and expand the existing LIRR Amtrak Right of Way for the future TBM tunnels
and Mainline track diversions including the design, and installation of a pre-fabricated substation.
Harold Structures 2 (CH054A) Construct various civil infrastructure elements at Harold Interlocking
and expand the existing LIRR and Amtrak Right of Way for the future TBM tunnels and Main-line track diversions.

Harold Stage 1-2 Amtrak/LIRR Force Account (FHA/L01-2) Installation of track/switches by


LIRR and Amtrak. Installation of new microprocessor based signal system. Construction of traction power
substation. Modified catenary system.
Procure Harold Materials Stage 2 (VHA/L02) Procure LIRR and Amtrak Force Account material in support of Stage 2 construction.
Harold & Point CILs (VH051 Part 1) This is the procurement of seven Harold Interlocking Central
Instrument Locations (CILs) and one Point Interlocking Central Instrument Location and the purchase of
a fully operational Vital Microprocessor-Based Interlocking Control System for the referenced interlockings.
Harold Tower Supervisory (VH051 Part 2) This contract includes the purchase of a fully operational Supervisory Control System for control of signals at Harold and Point Interlocks.

1st Quarter Jan, Feb, Mar 14

Queens Construction
Plaza Substation and Queens Structures (CQ032)
Contractor: Tutor Perini
Construction Manager: Alvaro Buendia
FTA Grant: NY-03-0344

SCHEDULE PROGRESS
Roosevelt Facility: Completing pending work items for turnover
Vernon Facility: The final completion of the facility is on hold
pending resolution between the GEC and LIRR. Interior signage
and Red Key (1 door) resolution between the GEC and LIRR is
still pending.
12th Street Facility: The final completion of the facility is pending
a revision to interior signage and key re-design

Description: Structural and architectural rehabilitation to

existing facilities along existing 63rd St. Tunnel. Construction


of Plaza Interlocking below grade facilities for Mainline Traction
Power Substation C06, Facility Power Substation B11, ventilation, signal, emergency power, mechanical and communication
rooms. Construction of Mid-Day Storage Yard Traction Power
Substation. Construction of above grade Plaza Bulk Facility
Power Substation (B10) and Yard Lead Service Building. Installation of ConEd Manholes and conduits for permanence power
services. Construction of miscellaneous site work in preparation
for Mid-Day Storage Yard.

hold pending resolution between the GEC and LIRR. This issue
is not critical but impedes the final completion and turnover of the
facility.
29th Street Facility: P3 equipment room and water room ready to
be painted
Plaza Interlocking Substation: Continued installation of waterproofing membrane for the revenue track invert slab. Continued
installation of waterproofing membrane on the sump pit walls.

23rd Street Facility: Interior signage and Red Key (1 Door) on


CRITICAL ISSUES
The schedule for the Early Access Chamber and re-bracing impacts the schedule. Stage 3 & 4 construction sequencing has been approved and is awaiting negotiations. The EAC stages 1 through 4 are crucial to the completion of the foundation structure of the Plaza
Building. Stages 3 & 4 have yet to be approved by the MTA/Contractor. In addition, the Contractor has not submitted a Change Order
Proposal or a TIA for said work in order to move towards negotiations.
MITIGATION
A re-baseline schedule accounting for the access restraint delays In addition, the Early Access Chamber Stage 2 is scheduled to
and changes in the scope of work was negotiated on March 26
be negotiated
and is being finalized by both parties
COST
38 contract modifications have been executed, which is the
modification of $8M added this month.
same as last month. 52.8% of the CQ032 current contract value
43.7% of the CQ032 FA current contract value has been invoiced
has been invoiced as of March 2014, up from 49.6% last month.
as of March 2014, which is the same as last month. CQ032 Force
44.2% of the current contract value has been paid, up from
Account is paid out FQL99 and FQA99, which are accounts that
42.0% last month. The EAC increased from the $213,066,634
LIRR and Amtrak force account packages are paid from. $26M
reported last month. The EAC includes 17 pending and potential
has been paid out of FQL 99 to date. $52.M has been paid out of
modifications totaling $20,112,500, which includes a time impact
FQA99 to date.
LOOK AHEAD
Continue Tunnel B/C track invert work

Continue work at Bulk Power Station (B10). Roofing, louvers,


fireproofing are progressing.

Continue rehabilitation of existing 63rd Street Tunnel (scope


transfer)
The 63rd Street Tunnel on track for a 4th quarter completion
SAFETY
Continued daily safety walkthroughs of the site with
actions as well as the actions of the workers
LTIR reprecontractor safety and MTACC safety, and weekly
sents incidents
Performing monthly Safe Work Plan audits
that occurred
safety walks with the CM team and OCIP
1st quarter safety assessment performed
for every
Continued to emphasize safety to the contractors
Safety StatisticsLTIR 0.55, B.L.S. (Bureau of Labor 200,000 manmanagement and that they are accountable for their
hours worked.
Standards) 1.70
MTA/LIRR East Side Access

(PM 3.5.108757)

28

CQ032 PROGRESS CURVE


100%

Current Baseline
193

Actual

90%

Original Baseline

178

Forecast
80%

164
149

70%

134

60%

119
104

50%

89

Cumulative
1st Quarter
Plan: 82.5%
Plan: 10.2%

74
59
45

30%

Actual: 53.0%

Actual: 8.7%

30

40%

20%

10%

Jul-15

Jun-15

Apr-15

May-15

Mar-15

Jan-15

Feb-15

Dec-14

Oct-14

Nov-14

Sep-14

Jul-14

Aug-14

Jun-14

Apr-14

May-14

Mar-14

Jan-14

Feb-14

Dec-13

Oct-13

Nov-13

Sep-13

Jul-13

Aug-13

Jun-13

Apr-13

May-13

Mar-13

Jan-13

Feb-13

Dec-12

Oct-12

Nov-12

Sep-12

Jul-12

Aug-12

Jun-12

Apr-12

May-12

Mar-12

Jan-12

Feb-12

Dec-11

Oct-11

Nov-11

Sep-11

Jul-11

Aug-11

15

0%

MILESTONES
Current

Actual/

Baseline

Forecast

Notice to Proceed

8/10/11

8/10/11

Turnover YL Track

6/10/13

4/21/15

C06 Substation Area

9/8/13

7/21/15

C07 Substation

6/5/14

9/21/15

Substantial Completion

8/14/14

12/24/15

Final Completion

11/12/14

3/24/16

2011

2012

2013

2014

2015

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2016

Q2 Q3 Q4 Q1 Q2 Q3 Q4

(0 days)

Actual/Forecas

(+681 days)
(+473 days)

Current Baseline

(+680 days)

(+497 days)

(+498 days)

FINANCIAL SUMMARY 3RD PARTY


Budget
$234,177,227

$234,177,227

Contract
(Award/Mods)
$207,663,570

Invoiced
$109,679,559

Paid to Date
$91,726,937

$147,377,000

$60,286,570

$109,679,559

$91,726,937

EAC
$227,776,070

$227,776,070

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

29

FINANCIAL SUMMARY FORCE ACCOUNT


Budget
$571,473

Contract
$75,000

$571,473

$75,000

Invoiced
$32,757
$32,757

Paid to Date
n/a

EAC
$571,473

$571,473

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

30

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Structures Part 1 and GO2 Substation (CH053)
Contractor: Perini Corp.
Construction Manager: James Pagano
FTA Grant: NY-03-0344/NY-95-X025

Description: Construct various civil infrastructure ele-

ments at Harold Interlocking and expand the existing LIRR


Amtrak Right of Way for the future TBM tunnels and Mainline track diversions including the design, and installation
of a pre-fabricated substation and installation of new signal
towers and catenary structures by replacing the existing
structures.

SCHEDULE PROGRESS
12KV Ductbank: Installed Current Transformer (CT) cabinet at Substation 44 and control cable between CT cabinet and C3 control panel and
riser for extension to existing manhole MH-3
Catenary Structures: Completed construction of foundation and guy
anchor for B-921W structure
43rd St. Bridges: Completed welding of utility bridge at 43rd St. WBY
bridge between west abutment and center pier and installed walkway
grating along north span of bridge
48th St. Bridge: Installed rebar and poured concrete for east abutment
back wall at 48th St. ML 2&4 Bridge

CRITICAL ISSUES

12KV Ductbank continues to be the most critical scope of work in the


CH053 contract. The critical path of CH053 is driven by cutover of the
new 12KV ductbank leading to completion of manholes for Microtunnel
Runs 1-4 and G02 Substation. Construction of the manholes is impacted by the existing 12KV system which cannot be demolished until
the new 12KV ductbank is cutover. The manholes will convey LIRR
traction power from G02 Substation, also constructed under CH053,
to the third rail reactors in the interlocking and are essential to perform
the final load test and handover of the G02 Substation to LIRR. The
existing 12KV ductbank also obstructs excavation and concrete work at
Tunnel A Reception Pit & Approach Structure which can be considered
the secondary critical path of CH053. The 12KV cutover is dependent
on completion of additional work at Substation 44 and commissioning

MITIGATION
Development of the 12KV C3 feeder testing and commissioning plan
was completed. The testing and commissioning is expected to require
12 outages at Substation 44. The CM has authorized an emergency/
retroactive NTP which will allow the Contractor to commence work as
soon as negotiations conclude in May. Typically, the Contractor cannot
commence work until the negotiated price and scope is ratified by the
MTA Board as a contract modification. The retroactive/emergency NTP
authorizes the release of limited funds for the Contractor to commence

COST

120 contract modifications have been executed, up one from last month.
88.4% of the CH053 current contract value has been invoiced as of
March 2014, up from 86.7%. 81.8% of the current contract value has
been paid, up from 79.3% last month. The EAC increased from the
$245,445,678 reported last month. The EAC includes 27 pending and
potential modifications totaling $66,236,394. This amount includes a
schedule re-baseline claim that was negotiated for $55M and is now a

MTA/LIRR East Side Access

Microtunnel Runs 1-4: Completed mining of Run 4 and 3, approximately


100 LF
Microtunnel Run 12: Cored manhole EMH-2B for future conduit installation
MG Signal Power Separation: Completed installation of conduits on
HP1 tower
LIRR Signal Bridges: Erect Signal Bridge 20 and Signal Bridge 21
Relocation OF 27KV Feed: Completed track foundation at Amtrak Substation S-1 to restore primary 27KV backup feed (10Q37 Feed)

of the new feeder system. Change orders for the additional Substation 44 work were issued to the contractor in January and February.
Resolution of the change orders have been delayed as the CM and
Contractor continue to develop a commissioning and testing plan to
meet the requirements set by the GEC and Amtrak.
MG Signal Power Separation: MG Signal Power Separation continues
to drive cutover of LIRR H3 and H4 Interlockings and is critical to the
overall Harold Interlocking Program. CH053 is contracted to construct
concrete ductbanks, equipment pads and install signal towers for H3
and H4 Interlocking cutover performed by LIRR. Delays to H3 and H4
Interlocking cutover can disrupt future third party contracts and railroad
work. Completion of the CH053 portion of MG Signal Power Separation
has been hampered by design changes and addition of scope.
work before the contract modification can be executed by the MTA
Board. Final payment for the change order work will be made only
after receiving the fully executed contract modification from the MTA. A
change order was issued to commence construction of G02 Substation
manholes.

pending modification.
94.5% of the CH053 FA current contract value has been invoiced as of
March 2014, which is up from 92.1% last month. CH053 Force Account is paid out FQL99 and FQA99, which are accounts that LIRR and
Amtrak force account packages are paid from. $26M has been paid out
of FQL 99 to date. $52.M has been paid out of FQA99 to date.
(PM 3.5.108757)

31

LOOK AHEAD
Catenary Structures: Erect Structure B-924WA south and K-frame

Negative Return Ductbank: Complete relocation of DC negative return


ductbank

12KV Ductbank: Negotiate change orders and issue emergency/retroactive NTP for additional Substation 44 work and commissioning of the C3
feeder

Mictrotunnel 1-4: Complete installation of positive and negative manholes at Runs 3 & 4 reception pits and conduits in Run 2

Retaining Walls: Complete construction of 43-S2 retaining wall. Approximately 100 LF remain and is scheduled to be completed in April.

Tunnel A Reception Pit and Approach Structure: Complete remaining


soldier piles at Tunnel A Reception Pit

SAFETY
Continued ongoing weekly safety walkthroughs of the site
with management and documentation in daily hazard logs
Coordination with the railroads, toning of the ground, and
hand digging procedures are still being followed to prevent
buried utility strikes at excavation sites
Continue weekly OCIP walks

Continue safety tool box talks for CM staff


Performing monthly Safe Work Plan audits
1st quarter safety assessment performed
Safety StatisticsLTIR 0.85, B.L.S. (Bureau of Labor
Standards) 1.70

LTIR represents
incidents that
occurred for
every 200,000
manhours
worked.

CH053 PROGRESS CURVE


100%
Original Baseline
Actual

220

Forecast

90%

Current Baseline
200
80%
180
70%

160

140

60%

120

50%

100

80

60

Current Period
Plan: N/A

Cumulative
Plan: 100.0%

Actual: 3.2%

Actual: 87.6%

40%

30%

20%
40

10%

Oct-14

Dec-14

Nov-14

Jul-14

Sep-14

Aug-14

Apr-14

Jun-14

Mar-14

May-14

Jan-14

Feb-14

Oct-13

Dec-13

Nov-13

Jul-13

Sep-13

Aug-13

Apr-13

Jun-13

Mar-13

May-13

Jan-13

Feb-13

Oct-12

Dec-12

Nov-12

Jul-12

Sep-12

Aug-12

Apr-12

Jun-12

May-12

Jan-12

Mar-12

Feb-12

Dec-11

Oct-11

Nov-11

Jul-11

Sep-11

Aug-11

Apr-11

Jun-11

May-11

Jan-11

Mar-11

Feb-11

Dec-10

Oct-10

Nov-10

Jul-10

Sep-10

Aug-10

Apr-10

Jun-10

May-10

Jan-10

Mar-10

Feb-10

Oct-09

Dec-09

Nov-09

Jul-09

Sep-09

Aug-09

Apr-09

Jun-09

May-09

Jan-09

Mar-09

Feb-09

Oct-08

Dec-08

Nov-08

Sep-08

Jul-08

Aug-08

Apr-08

Jun-08

May-08

Jan-08

Mar-08

Feb-08

20

0%

MILESTONES
2008

2009

2010

2011

2012

Current
Baseline

Actual/
Forecast

Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1/2 Q3/4 Q1

1/1/08

1/1/08

2014

Q2 Q3 Q4 Q1

2015

Q2 Q3 Q4 Q1

Q2 Q3 Q4

(0 days)

Notice to Proceed
Beneficial Occupancy
Harold Access Bridge
New GO2 Substation
Completion

1/1/11

11/18/13

4/15/11

12/23/14

Substantial Completion

1/16/12

12/23/14

Final Completion

4/15/12

3/23/15

Actual/Forecast

(PM 3.5.108757)

(+1,052 days)

Current Baseline

MTA/LIRR East Side Access

2013

(+1,348 days)
(+1,072days)

(+1,072 days)

32

FINANCIAL SUMMARY 3RD PARTY


Budget
$336,070,307

Contract
(Award/Mods)
$236,876,958

Invoiced
$207,561,072

Paid to Date
$192,077,655

$335,701,307

$138,911,000

$369,000

$97,596,958

$207,225,072

$336,000

$191,758,455

EAC
$303,482,354

$369,000

$319,200

$303,113,354

ESA

Regional Investment

RI

RI

RI

$369,000

Other

RI

RI

Executed Modifications

EACs do not include possible contract mods and future claims.

FINANCIAL SUMMARY FORCE ACCOUNT


Budget
$47,647,631

$47,647,631

Contract
$47,647,631

$47,647,631

Invoiced
$45,024,208

Paid to Date
n/a

$45,024,208

$0

EAC
$47,647,631

$47,647,631

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

33

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Structures Part 2A (CH054A)
Contractor: Perini Corp.
Construction Manager: Garth Lawrence
FTA Grant: NY-03-0344/ARRA Stimulus Funds
NY-36-0002

SCHEDULE PROGRESS
12KV Ductbank: Completed 430 LF of open cut concrete ductbank. Completed ductbank tie-ins at jacked shield tunnel jacking
and receiving pits. Completed installation of conduits and grouting of jacked shield tunnel Runs 14, 15 and 16 and the installation of two precast manholes EMH-27 A & B.
43-S1 Retaining Wall: Installed two cap beams for retaining wall
43-S1. Continued installing precast panels between pile 120 and
CRITICAL ISSUES
The CH054A critical path continues to be driven by the Storm
Sewer. The change order process was expected to be completed
in March. Resolution was delayed due to the revision to the
jet grout soil stabilization scope. The change order process is
expected to be complete by mid-April. Delayed completion of the
storm sewer impacts the construction of Access Road AR 4 and
the Loop 1A track bed which impacts follow-on work by Amtrak
Force Account. The storm sewer also impacts the installation of
MITIGATION
The change order process is expected to be resolved by midApril. Scoping meetings have concluded between the CM, GEC
and Contractor and the CM is currently waiting on final proposals
from the Contractor to begin negotiations.
The majority of the civil work for the 12KV ductbank has been
COST
34 contract modifications have been executed, which is the
same as last month. 75.8% of the CH054A current contract
value has been invoiced as of March 2014, up from 71.2% last
month. 64.0% of the current contract value has been paid, up
from 59.6% last month. The EAC increased from the 52,474,628
reported last month due to the addition of a negotiated claim.
The EAC includes 15 pending and potential modifications totaling
LOOK AHEAD
12KV Ductbank: Complete construction of open cut sections of
12KV ductbank between existing manhole EMH-1560 and EMH20. Approximately 75 LF remains. Complete receiving pit and
mine Microtunnel Run 13. Complete roof slab of caisson manhole
EMH-22D.
Storm Sewer: Execute contract modification for trenchless excavation of sewer. Install jet grout blocks for soil stability at Queens
MTA/LIRR East Side Access

Description: Construct various civil infrastructure

elements at Harold Interlocking and expand the existing


LIRR and Amtrak Right-of-Way for the future TBM tunnels
and Main-line track diversions including: 1) the construction of retaining walls 2) Track D TBM reception pit 3) AC
traction power duct bank 4) access road work 5) demolition of existing Catenary Foundations 6) procurement
of two signal bridges and 7) other utility relocations and
adjustments.

121.
F2/F2E CIH: Drilled three 6-inch holes in previously installed
manhole MH-F3 and pulled additional cable for F1, F2 and F2E
CIH. Performed megger tests on the cables.
Demolition of Signal Bridge 11: Completed demolition of existing
Signal Bridge 11
trough and pull boxes for the Snow Melter Units (SMU) and Relay
Transmission Unit (RTU) which are to be constructed in conjunction with the Access Road and track bed.
The 12KV ductbank is the secondary critical path of CH054A.
The construction of Access Road AR4, Loop 1A track bed and
SMU/RTU troughs are also dependent on completion of the new
12KV ductbank and demolition of the existing ductbank.
completed with the exception of Microtunnel Run 13 and manhole EMH-22E. Construction of the jacking pit and launch block
was completed in March and the tunneling subcontractor has
commenced setup for tunnel mining which is forecast to commence in May.
$11,310,000, which is the same as last month.
98.7% of the CH054 FA current contract value has been invoiced
as of March 2014, up from 92.1% last month. CH054A Force
Account is paid out FQL99 and FQA99, which are accounts that
LIRR and Amtrak force account packages are paid from. $26M
has been paid out of FQL99 to date. $52M has been paid out of
FQA99 to date.
Blvd bridge abutment.
Snow Melter Units and Relay Transmission Units: Commence
procurement of Relay Transmission Unit. Complete procurement
of Snow Melter Units.
MG Signal Power Separation: Complete construction of H4 CIL
crib wall extension
(PM 3.5.108757)

34

SAFETY
Continued ongoing weekly walkthrough of site with management and daily safety site visits which are documented in the daily hazard logs

LTIR represents
incidents that
occurred for
every 200,000
manhours
worked.

Coordination with the railroads, toning of the ground, and hand digging procedures are still being followed to
prevent buried utility strikes at excavation sites
Continued to have safety talks with the CM construction team on a weekly basis
Continue OCIP walkthroughs on a weekly basis
Performing monthly Safe Work Plan audits
1st quarter safety assessment performed
Safety StatisticsLTIR 1.28, B.L.S. (Bureau of Labor Standards) 1.70
CH054A PROGRESS CURVE

100%

44
Original Baseline

42

90%

Actual

39

Forecast

36

80%

Current Baseline

34

70%

31
29

60%

26
23

50%

21
18

40%

16
30%

13

Oct-14

Sep-14

Jul-14

Aug-14

Jun-14

Apr-14

May-14

Mar-14

Jan-14

Feb-14

Dec-13

Oct-13

Nov-13

Sep-13

Jul-13

Aug-13

Jun-13

Apr-13

May-13

Mar-13

Jan-13

Feb-13

Dec-12

Oct-12

Nov-12

Sep-12

Jul-12

Aug-12

Jun-12

10%

Apr-12

Actual: 76.1%

May-12

Actual: 10.2%
Mar-12

Oct-11

20%

Nov-11

Sep-11

Jul-11

Aug-11

Jun-11

Apr-11

May-11

Mar-11

Jan-11

Feb-11

Dec-10

Oct-10

Nov-10

Sep-10

Jul-10

Aug-10

Jun-10

Apr-10

May-10

Mar-10

Jan-10

Feb-10

Dec-09

Oct-09

Nov-09

Sep-09

Aug-09

Cumulative
Plan: 100.0%

Jan-12

Current Period
Plan: 0.0%

Feb-12

Dec-11

10

0%

MILESTONES
Current

Actual/

Baseline

Forecast

Notice to Proceed

8/24/09

8/24/09

Retaining Wall THOM S1/S2

5/26/10

12/21/10

Complete 12KV Relocation

12/7/10

6/19/14

Substantial Completion

12/21/10

11/26/14

Final Completion

3/21/11

2/26/15

2009

2010

2012

2013

2014

2015

Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4 Q1/Q2 Q3/Q4

(0 days)

(+209 days)

(+1,290 days)

Current Baseline

MTA/LIRR East Side Access

2011

(PM 3.5.108757)

(+1,438 days)
Actual/Forecast

(+1,436 days)

35

FINANCIAL SUMMARY 3RD PARTY


Budget
$70,030,689

$70,030,689

Contract
(Award/Mods)
$44,771,105

$21,777,777

Invoiced
$33,946,161

$22,993,328

$33,946,161

Paid to Date
$28,637,365

$28,637,365

EAC
$64,306,105

$64,306,105

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

FINANCIAL SUMMARY FORCE ACOUNT


Budget
$6,748,182

$6,748,182

Contract
$6,748,182

$6,748,182

Invoiced
$6,657,874

Paid to Date
n/a

$6,657,874

$0

EAC
$6,748,182

$6,748,182

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

36

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Stage 1 - Amtrak Force Account (FHA01)
Description: Install one track crossover (723), relocate catena-

Contractor: Amtrak

ry and signal power at several locations, perform modifications and


removal of poles, third-rail installation, signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of the 723 crossover
incorporating changes to F Interlocking and software and hardware modification for the Penn Station Central Control (PSCC).
Clear debris and other incidentals from the Amtrak Maintenanceof-Way Yard, electrical traction relocations in support of the CH053,
CH054A and CQ031 civil work.

Construction Manager: Peter Malvese


FTA Grant: N/A

SCHEDULE PROGRESS

Removed old B-908E structures and poles

44

Continued relocating signal line (#123, #124, #135) and


feeder (#4301, #4303, #441, #442) at south of Substation

The overall work of Catenary and Signal power relocation is


87% completed

CRITICAL ISSUES

The track and signal power outages are required in order


to complete catenary wire transfers and signal power relocations on schedule

Low production rate in the first quarter due to the weather


(snow) and sending the team to support the Contractor on
another project

MITIGATION

ESA continued to work with Amtrak and LIRR to lockdown


track and power outages for signal power relocation on the
south and north sides. Priority areas have been identified.
ESA and Amtrak are working on resequencing the catenary

schedule to coordinate with the weekend outage. The


weekend work plan will mitigate the duration that was lost in
the first quarter.

COST

96.5% of the FHA01 current contract value has been invoiced as of March 2014, up from 96.4% last month. 89.1% of the
current contract value has been paid, up from 89.0% last month. The EAC has not changed since last month.
LOOK AHEAD

Remove 27KV feeder (10Q36) from B-931W north pole


Commence wire transfer for 823 and 821 switches on north side
Continue hardware installation, catenary wire transfer, signal power (#124 and #123), and feeder (#4301 and #4303) relocations between Thomson Avenue and Substation 44
FHA01 PROGRESS CURVE

100%

18

Original Baseline

90%

Current Baseline

16

80%

Actual

14
70%

12

60%

10

50%

20%

MTA/LIRR East Side Access

Jan-16

Nov-15

Jul-15

Sep-15

May-15

Jan-15

Mar-15

Nov-14

Jul-14

Sep-14

May-14

Jan-14

Mar-14

Nov-13

Jul-13

Sep-13

May-13

Jan-13

(PM 3.5.108757)

Mar-13

Nov-12

Jul-12

Sep-12

May-12

Jan-12

Mar-12

Nov-11

Jul-11

Sep-11

May-11

Jan-11

Mar-11

Nov-10

Jul-10

Sep-10

May-10

Jan-10

Mar-10

Nov-09

Jul-09

Sep-09

May-09

Jan-09

Mar-09

Nov-08

Jul-08

Sep-08

May-08

Jan-08

Mar-08

Nov-07

Jul-07

Sep-07

10%

May-07

30%

Actual: 95.5%

Actual: 1.4%

40%

Cumulative
Plan: 95.5%

1st Quarter
Plan: 1.3%

0%

37

MILESTONES
Current
Baseline

Actual/
Forecast

11/19/07
6/30/07
8/10/08

11/19/07
6/30/07
10/5/08

Compl. 68 Spur Track

5/1/10

9/6/10

Compl. Signal Power

9/20/10

4/23/12

Substantial Completion

2/4/16

2/25/16

100% Design
Commence Stage 1
Cutover Stage 1

2007

2008

2009

2010

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2011

2012

2013

2014

2015

2016

Q2

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

(0 days)
(0 days)

(+56 days)
(+128 days)

(+581 days)
(+21 days)

Current Baseline

Actual/Forecast

FINANCIAL SUMMARY
Budget
$18,824,861

$18,824,861

Contract
$18,824,861

$18,824,861

Invoiced
$18,170,661

Paid to Date
$16,773,440

$18,170,661

$16,773,440

EAC
$18,824,861

$18,824,861

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

38

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Stage 2 - Amtrak Force Account (FHA02)
Description: Install seven switches and LP1A Track

Contractor: Amtrak

(app. 2,400lf). Relocate catenary and signal power at


several locations, perform modifications and removal of
poles. Third-rail installation, signal infrastructure installation, cable pulls, tie-ins, testing and cut-over of F1 CIH, F2
CIH and FHACS (F Interlocking and Harold Interlocking
Alternate Control System).

Construction Manager: Peter Malvese


Federal Grant: N/A

SCHEDULE PROGRESS

Supported LIRR signal department pulling cables and testing for new Point CIL
Completed fiber cables from portal tunnels to F1 and F2CIHs to Harold Communication Hut via Substation 44
Continued pulling copper cables from portal tunnel Line 4 to
F1B signal case
Commenced catenary relocation for 747 switch cutover

Commenced trough installation at south of LIRR-FRT track


to F1GW/GE location (E35 Signal Bridge)

CRITICAL ISSUES

None

MITIGATION

N/A

COST

95.7% of the FHA02 current contract value has been invoiced as of March 2014 up from 94.1% last month. 95.2% of the current contract value has been paid up from 94.1% last month. The EAC has not changed from last month.
LOOK AHEAD

Complete communication cable (copper) portal Line 4 to


F1B signal case
Erect Signal Bridge E34 (Line 1 Track)
Continue remaining signal work (conduits, cables) at E35

location (F1GW and F1GE) for H-3CIL cutover


Continue catenary work for 747 Switch cutover
Support LIRR for New Point CIL cutover, expected completion on April 26

FHA02 PROGRESS CURVE


100%

40

Current Baseline

38

90%

Original Baseline

36
34

Actual

80%

32
30

70%

28
26

60%

24
22

50%

20
18

40%

16

1st Quarter
Plan: 2.9%

14
12
10
8

Cumulative
Plan: 79.4%

Actual: 1.8%

6
4

30%
20%

Actual: 78.3%

10%

MTA/LIRR East Side Access

(PM 3.5.108757)

Aug-17

Apr-17

Jun-17

Feb-17

Oct-16

Dec-16

Aug-16

Apr-16

Jun-16

Feb-16

Oct-15

Dec-15

Aug-15

Apr-15

Jun-15

Feb-15

Oct-14

Dec-14

Aug-14

Apr-14

Jun-14

Feb-14

Oct-13

Dec-13

Aug-13

Apr-13

Jun-13

Feb-13

Oct-12

Dec-12

Aug-12

Apr-12

Jun-12

Feb-12

Oct-11

Dec-11

Aug-11

Apr-11

Jun-11

Feb-11

Oct-10

Dec-10

Aug-10

Apr-10

Jun-10

Feb-10

Oct-09

Dec-09

Aug-09

Apr-09

Jun-09

Feb-09

Dec-08

2
0%

39

MILESTONES

Commence Stage 2
Install F2 CIH

08 09 10

Current

Actual/

Baseline

Forecast

Q4

12/15/08

12/15/08

4/2/11

4/2/11

Install F1 CIH

8/1/11

8/1/11

Install 747A Switch

2/12/12

2/12/12

Install 771A Switch

4/21/12

4/28/12

Install 771B Switch

4/28/12

5/5/12

Install 747B Switch

5/5/12

6/16/12

FHACS Cutover

7/15/12

7/16/13

F2-CIH Cutover

11/17/12

5/18/13

F1-CIH Cutover

3/2/12

11/2/13

Complete Stage 2

8/15/17

9/6/17

2011
Q1

2012

Q2 Q3 Q4 Q1

2013

2014

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2015

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2016

2017

Q2 Q3 Q4 Q1 Q2 Q3

(0 days)

(0 days)

(0 days)

(0 days)

(+7 days)
(+7 days)
(+42 days)

(+366 days)
(+182 days)

(+610 days)
(+22 days)

Current Baseline

Actual/Forecast

FINANCIAL SUMMARY
Budget
$41,683,606

$41,683,606

Contract
$38,585,122

Invoiced
$36,918,530

Paid to Date
$36,735,681

$38,585,122

$36,918,530

$36,735,681

EAC
$41,683,606

EACs do not include possible contract mods and future claims.

$41,683,606

ESA

Regional Investment

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

40

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Stage 1 - LIRR Force Account (FHL01)
Description: Install eight track switches into the exist-

Contractor: Long Island Rail Road

ing signal system and remove two switches. Install signal


infrastructure in preparation of Stage 2 (Harold and Point
CILs). Reroute signal power cables. Install third rail for
new switches and track. Pull traction power cables from
G02 Substation final manholes to Harold Main Line tracks.
Energize and commission the relocated G02 Substation
installed by CH053. Install and relocate signal and communications cables. Cut and throw Main Line 4 and relocated
Main Line 2 upon CH053 expanding the South ROW East
of 43rd Street.

Construction Manager: Peter Malvese


FTA Grant: NY-03-0344

SCHEDULE PROGRESS

No work performed during this period


CRITICAL ISSUES

The substantial completion date is driven by the new G02 Substation construction that is impacted by the delay of Micro
Tunneling construction (CH053)
MITIGATION

Working with Perini and LIRR to re-schedule the construction plan of the new G02 Substation
COST

87.3% of the FHL01 current contract value has been invoiced as of March 2014, which is the same as last month. 85.7% of
the current contract value has been paid, up from 85.3% last month. The EAC has not changed from last month.
LOOK AHEAD

Schedule work for energizing new G02 Substation


FHL01 PROGRESS CURVE
100%

20

Original Baseline

90%

Current Baseline

18

80%

Actual

16

70%

14

60%

12

50%

10

Cumulative
Plan: 77.4%

1st Quarter
Plan: 0.0%

8
6

30%

Actual: 77.4%

Actual: 0.0%

40%

20%

MTA/LIRR East Side Access

Apr-15

Feb-15

Oct-14

Dec-14

Aug-14

Apr-14

Jun-14

Feb-14

Oct-13

Dec-13

Aug-13

Apr-13

Jun-13

Feb-13

Oct-12

Dec-12

Aug-12

Apr-12

(PM 3.5.108757)

Jun-12

Feb-12

Oct-11

Dec-11

Aug-11

Apr-11

Jun-11

Feb-11

Oct-10

Dec-10

Aug-10

Apr-10

Jun-10

Feb-10

Oct-09

Dec-09

Aug-09

Apr-09

Jun-09

Feb-09

Oct-08

Dec-08

Aug-08

Apr-08

Jun-08

Feb-08

Oct-07

0%

Dec-07

Jun-07

10%

Aug-07

41

MILESTONES
Current

Actual/

Baseline

Forecast

2007

2008

2009

2010

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2011

2012

2013

2014

2015

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

(+30 days)

100% Design

6/7/07

7/7/07

Begin Stage 1

6/29/07

6/29/07

Install 823 Switches

3/20/10

8/21/10

Cutover 865 Switch

10/16/10

10/16/10

Compl. Signal Power


Operate 821 & 823
Switch

9/20/10

11/6/13

5/10/14

8/2/14

Substantial Completion

4/9/15

1/30/15

(-69 days)

(0 days)

(+154 days)

(0 days)

Current Baseline

Actual/Forecast

(+1,143 days)
(+84 days)

FINANCIAL SUMMARY
Budget
$20,804,621

$20,804,621

Contract
$20,782,146

$20,782,146

Invoiced
$18,139,911

Paid to Date
$17,809,427

$18,139,911

$17,809,427

EAC
$20,804,621

$20,804,621

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

42

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Stage 2 - LIRR Force Account (FHL02)
Description: Install 15 track switches, new Mainline

Contractor: Long Island Rail Road

4 tracks (app. 2,800lf) and remove two switches; Install


signal infrastructure, cable, testing and circuit revision for
Harold (6 CILs) Loc 30, Point CILs and HTSCS; Install
third rail for new switches & track. Install new MG set for
LIRR Signal Power Separation from Amtrak. Renovate
Harold Tower. Install and remove signal bridges.

Construction Manager: Peter Malvese


FTA Grant: NY-03-0344

SCHEDULE PROGRESS

Performed pre-testing and circuit revisions for new Point


CIL Cutover (~98.5% Complete)

Signal Bridge 35 and pulled cables to signals

Preformed pre-testing from new Point CIL to PSCC Theater


(~ 15% Complete)

Assembled, installed and wired pedestal signals 25EC and


45WC by Signal Bridge 16

Performed pre-testing inside H4-CIL (~20% Complete)

Installed foundation legs, trough and pull boxes around H3CIL location

Completed test 1 break down testing on H3-CIL

Installed H3-CIL and Battery Hut

Performed test 1 break down testing on H5-CIL (~60%)

Installed power distribution panels for H1, H2, H3, and H6


CILs.

Installed conduit for Signal Bridge 15 and 20


Built and installed signals 44W, M13, 13-4 and E35-2 on
CRITICAL ISSUES

Signal Power Separation is required to begin track circuit testing for new CILs except Point CIL. Point CIL is being powered
by the existing Amtrak power (91.6 Hz). If the signal power separation cutover is delayed (current target date is in July
2014), the current H4 and H3 CIL cutovers could potentially slip.
MITIGATION

ESA and LIRR continue to hold weekly meetings to lockdown the cutover date of the MG set. The re-design and
coordinating schedule have been in process in order to
mitigate the schedule impact.

Signal Power (91.6Hz) to mitigate the schedule impact due


to the delay of LIRR Signal Power Separation
ESA and LIRR are working with Amtrak to get a permit for
Temporary Signal Power for testing track circuit H3-CIL

Track circuit testing for H4 CIL will begin with Temporary


COST

63.8% of the FHL02 current contract value has been invoiced as of March 2014, up from 62.2% last month. 55.7% of the current contract value has been paid, up from 52.7% last month. The EAC has not changed from last month.
LOOK AHEAD

Continue pulling/terminating cables from H4-CIL to various


locations and perform testing at H4-CIL and new Point-CIL

Continue Point-CIL and H4-CIL pre-Testing

Continue installing conduit cross tracks for future signals


and switches in Harold Interlocking

Pull power cables between HP1 and HP2 poles for Signal
Power Separation

Continue test 1 break down testing on H5-CIL

Install trough west of H3-CIL and commence pulling cables


Complete communication work for Point, H4, and H3
cutovers
MTA/LIRR East Side Access

Complete structural repairs on Tower 62 to Tower 69

(PM 3.5.108757)

43

FHL02 PROGRESS CURVE


100%

70
Current Baseline

90%

Original Baseline

60

80%

Actual

50

70%
60%

40

50%
30

40%

Cumulative
1st Quarter
Plan: 37.6%
Plan: 6.6%

30%
20%
10%

Nov-16

Jul-16

Sep-16

May-16

Jan-16

Mar-16

Actual: 33.4%
Nov-15

Jul-15

May-15

Jan-15

Mar-15

Nov-14

Jul-14

May-14

Jan-14

Mar-14

Nov-13

Jul-13

Sep-13

May-13

Jan-13

Mar-13

Nov-12

Jul-12

Sep-12

Mar-12

May-12

Jan-12

Nov-11

Jul-11

Sep-11

May-11

Jan-11

Mar-11

Nov-10

Jul-10

Sep-10

May-10

Jan-10

Mar-10

Nov-09

Jul-09

Sep-09

Sep-14

Actual: 2.4%

10

Sep-15

20

0%

MILESTONES
2011

2012

2013

2014

2015

2016

Current
Baseline

Actual/
Forecast

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

EWD LI Passenger Track West

3/12/11

3/12/11

EWD LI Passenger Track East

9/24/11

9/24/11

PW2 Track Installation

12/3/11

12/3/11

Point CIL Installation

9/24/11

9/24/11

HTSCS Cutover

10/13/13

10/13/13

Point CIL Cutover

4/12/14

4/26/14

Complete Stage 2

11/25/16

11/25/16

(0 days)

(0 days)

(0 days)
(0 days)

(0 days)

(+14 days)
(0 days)

Current Baseline

Actual/Forecas

FINANCIAL SUMMARY
Budget
$71,189,359

$71,189,359

Contract
$48,179,882

$48,179,882

Invoiced
$30,715,868

Paid to Date
$26,829,202

$30,715,868

$26,829,202

EAC
$71,189,359

$71,189,359

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

44

SITE MAP

Early Stage 2 Trough Line

MTA/LIRR East Side Access

(PM 3.5.108757)

45

1st Quarter Jan, Feb, Mar 14

Harold Construction
Procure Harold Material Stage 2 (VHA/L02)
Contractor: Various

Description: Procure LIRR and Amtrak Force Ac-

Construction Manager: Peter Malvese

count material in support of Stage 2 construction. LIRR


will manage and operate the project warehouse with ESA
oversight. Example of materials include: Track - switches,
rail, concrete ties and ballast; Third-Rail & Power rail,
cables, boards, brackets, wire, power connectors, bus
bar; Signal Equipment switch machines, cables, signals,
relays, motor generators, heaters, troughs, impedance
bonds; and Structures signal bridges, retaining walls
etc.; Communications equipment, wire, cables, and
poles.

Federal Grant: ARRA Stimulus Funds NY-360002 (Only VHL02)

SCHEDULE PROGRESS

LIRR procured all 17 switches and they are to be delivered


from May 2013 to April 2014. Reviewing alternate locations
with expanded facilities for delivery, building and storage.

average of Amtrak and LIRR combined. Deliveries continue


in coordination with the construction schedule.

Bill of materials for VHA/L02 is an average of 84.7%


procured. This percentage was recalculated based on the
MATERIAL STATUS FOR VHA02

95% of the remaining materials required on Bill of Materials (BOMs) have been sent to Procurement for requisition
processing
Procured third rail has been delivered

95% of procured DC traction miscellaneous material has


been delivered
Communication material inner duct and cable have been
delivered

MATERIAL STATUS FOR VHL02

The majority of procured materials have been delivered including long lead items
CRITICAL ISSUES

None

MITIGATION

N/A

COST

An overall VHL02 savings is expected due to large scale


advance procurement for Stage 2 materials
The budget of VHL02 was increased to purchase two motor generators for Harold signal power separation. Meetings are being held regarding contract purchase and award
of the motor generators.

MTA/LIRR East Side Access

58.7% of the VHA02 current contract value has been


invoiced and paid as of March 2014, which is the same as
last month. The EAC has not changed from last month.
96.7% of the VHL02 current contract value has been
invoiced and paid as of March 2014, up from 95.2% last
month. The EAC has not changed from last month.

(PM 3.5.108757)

46

FINANCIAL SUMMARY VHA02


Budget
$11,317,452

$11,317,452

Contract
$11,165,322

$11,165,322

Invoiced
$6,552,539

$6,552,539

Paid to Date
$6,552,539

$6,552,539

EAC
$11,317,452

$11,317,452

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

FINANCIAL SUMMARY VHL02


Budget
$23,964,861

$23,964,861

Contract
$23,183,118

$23,183,118

Invoiced
$22,410,168

$22,410,168

Paid to Date
$22,410,168

$22,410,168

EAC
$23,964,861

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

$23,964,861

ESA

Regional Investment
(PM 3.5.108757)

47

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold and Point CILs (VH051 Part 1)
Description: This includes the procurement of seven

Contractor: Ansaldo STS USA, Inc. (ASTS)

Harold Interlocking Central Instrument Locations (CILs)


and one Point Interlocking CIL and the purchase of a fully
operational Vital Microprocessor-Based Interlocking Control System for the referenced interlockings. This system
will operate the new Harold Interlocking configuration and
eventually connect to the new GCT tunnels.

Construction Manager: Chuck Miller


FTA Grant: NY-03-0344

SCHEDULE PROGRESS

Four of the six delivered CILs have been set on site. H2 and H1 CILs will be delivered by Ansaldo in the next three months.
CRITICAL ISSUES

Implementation of Civil Speed Restrictions on the LIRR will have an impact on the CIL cutover schedules
Constant changes to the Harold footprint in order to mitigate/improve construction sequencing and/or operational issues
are resulting in additional cost and schedule impacts to both the vital signal system and non-vital supervisory control system. Scope changes are absorbing limited signal design resources.
MITIGATION

Will be assessed upon LIRRs direction


Issue no additional changes to Harold Interlocking
COST

Two contract modifications have been executed, which is the same as last month. 72.3% of the VH051 Part 1 current contract
value has been invoiced and paid as of March 2014, down from 73.0% that was mistakenly reported last month. The financials have been corrected to include Non-ESA budget, invoices, and expenditures. The EAC decreased from the $30,243,343
reported last month because a potential modification was disputed, so it was removed and may become a claim. The EAC
includes three pending and potential modifications totaling $2,119,000, which is the same as last month.
LOOK AHEAD

Complete delivery of the last two CILs


VH051 PART 1 PROGRESS CURVE
100%

24
21

Original Baseline

90%

Current Baseline

80%

Actual

70%

18

60%

15

50%

12

40%

1st Quarter
Plan: 7.0%

9
6

Actual: 6.0%

3
0
Mar-09

Cumulative
Plan: 82.0%

Jul-09

Nov-09

Mar-10

Jul-10

MTA/LIRR East Side Access

Nov-10

Mar-11

Jul-11

Nov-11

Mar-12

Jul-12

Nov-12

Mar-13

(PM 3.5.108757)

Jul-13

Nov-13

30%

Actual: 78.0%
Mar-14

Jul-14

Nov-14

Mar-15

Jul-15

20%
10%
0%

48

MILESTONES
Current

Actual/

2009

2010

2011

2012

2013

2014

2015

Baseline

Forecast Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Notice to Proceed

5/11/09

5/11/09

Complete POINT CIL set

11/6/11

11/6/11

Complete H4 CIL

7/27/12

7/27/12

Q2 Q3 Q4

(0 days)

(0 days)

(0 days)

Complete H5 CIL

6/20/13

6/20/13

Complete H6 CIL

10/31/13

10/31/13

Complete 30 Loc Hut

10/31/13

10/31/13

Complete H1 CIL

2/5/14

6/5/14

Complete H2 CIL

3/31/14

4/30/14

Complete H3 CIL

2/8/13

2/8/13

Substantial Completion

7/1/15

7/31/15

(+30 days)

Final Completion

8/28/15

8/28/15

(0 days)

(0 days)

(0 days)
(0 days)

Current Baseline

Actual/Forecast

(+120 days)
(+30 days)

(0 days)

FINANCIAL SUMMARY
Budget
$33,784,654

$33,402,120

Contract (Award/Mods)
$26,839,810

$382,534

$25,475,497
$1,364,313

Invoiced
$19,395,434

$19,395,434

Paid to Date
$19,395,434

$19,395,434

EAC
$28,958,809

$28,576,275

ESA

Regional Investment

$382,534

Other

Modifications

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

49

1st Quarter Jan, Feb, Mar 14

Harold Construction
Harold Tower Supervisory Control System (VH051 Part 2)
Description: This procurement contract requires

Contractor: ARINC, Inc.

purchase of a fully operational Harold Tower Supervisory


Control System (HTSCS) for control of signals at Harold
and Point Interlocking.

Construction Manager: Chuck Miller


FTA Grant: NY-03-0344

SCHEDULE PROGRESS

PSCC and HTSCS systems are on-site. HTSCS testing is on-going in anticipation of the POINT cutover.
CRITICAL ISSUES

Graphics changes need to be confirmed for all future cutovers to support schedule
MITIGATION

Work with ARINC and Ansaldo to insure all updates to the Interlocking footprint have been incorporated. Amtrak resources
are critical to insure changes are made to PSCC.
COST

Six contract modifications have been executed, which is the same as last month. 96.9% of the VH051 Part 2 current contract
value has been invoiced as of March 2014, up from 92.4% last month. 88.5% of the current contract value has been paid,
which is the same as last month. The EAC decreased from the $7,921,474 reported last month because an option that was
reported in the EAC last month was not included this month. The EAC includes two pending and potential modifications totaling $400,000, which is also the same as last month.
LOOK AHEAD

POINT cutover

VH051 PART 2 PROGRESS CURVE


100%

7
Current Baseline

90%

Original Baseline
Actual

80%

70%
60%

50%
3

40%

1st Quarter
Plan: 0.0%

0
Feb-09

Actual: 0.0%
Aug-09

Feb-10

MTA/LIRR East Side Access

Aug-10

Feb-11

Aug-11

Feb-12

Aug-12

Feb-13

(PM 3.5.108757)

Aug-13

Jan-14

30%

Cumulative
Plan: 93.0%

20%

Actual: 88.0%
Jul-14

Jan-15

Jul-15

10%
0%

50

MILESTONES
2009

Current

Actual/

Baseline

Forecast

Q1

Notice to Proceed

2/3/09

2/3/09

Delivery of HTSCS Control


Systems

3/16/10

10/8/10

5/9/12

Substantial Completion

8/24/10

7/31/15

Final Completion

5/3/12

8/28/15

Delivery of FHACS

2010

2011

2012

2013

2014

2015

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
(0 days)

(+206 days)

(+1,802 days)

Current Baseline

Actual/Forecast

(+1,212 days)

FINANCIAL SUMMARY
Budget
$8,581,222

Contract
$7,221,475

Invoiced
$6,995,244

Paid to Date
$6,393,602

$8,581,222

$7,221,475

$6,995,244

$6,393,602

EAC
$7,621,475

$7,621,475

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757

51

1st Quarter Jan, Feb, Mar 14


SUMMARY OF COMPLETED CONTRACTS ($ IN MILLIONS)
Substantial Completion
Project Description/ Contractor

NTP

Plan

Actual

Original
Budget at
Award

Orig. Revised

Final Total
Budget Scope
Completed

Value of Status
Scope
Transferred

Remarks

Manhattan/Bronx
CM001 Highbridge Yard
Highbridge Yard Contractors

09/05/01

04/15/03 04/15/03

12/04/03

$ 80.1

$ 75.6 Y

CM002- GCT Expansion Joint


Replacement and Structural Closures
J-Track LLC

05/09/11

07/02/12 07/02/12

07/02/12

4.8

4.8 Y

Open

Final invoice to be
processed

CM008 - Madison Yard Site Clearance


Gramercy Group, Inc.

03/09/09

06/02/10

04/10/11

04/10/11

40.9

42.7 Y

Open

In close out phase

CM009 - Manhattan Tunnels Excavation


Dragados/Judlau (DJ)

07/10/06

03/31/12 09/30/13

09/30/13

449.4

431.9 N

(17.5) Open

CM014MP - Early Work for GCT and


Facilities Fit-Out
The Urban Group, Ltd.

03/27/13

10/13

12/13

2.0

2.0 Y

Open

CM016 Manhattan Approach Tunnels


Excavation
Kiewit Constructors, Inc.

02/23/04

08/20/04 08/20/04

08/18/04

11.8

11.1 Y

Closed

CM017 GCT East Yard Remediation


Tully Environmental Inc.

01/06/03

10/03/03 10/03/03

09/26/03

2.2

1.8 Y

Closed

MTA/LIRR East Side Access

10/13

(PM 3.5.108757)

Closed

Multiple scope moves


were made during the
life of this contract both
into and out of CM009.
The main movement
out of CM009 occurred
as a result of a settlement between MTACC
and DJ to move $42.8
million out of CM009
to CM012 and CS179.
This is offset by the
$25.3 million that was
transferred into CM009.

52

1st Quarter Jan, Feb, Mar 14


SUMMARY OF COMPLETED CONTRACTS ($ IN MILLIONS)
Substantial Completion
Project Description/ Contractor

NTP

Plan

Actual

Original
Budget at
Award

05/31/13

756.0

794.7 Y

12/09

12/08

58.7

24.6 Y

Closed

06/30/10 06/30/10

06/30/10

14.5

17.0 Y

Closed

Orig. Revised
03/31/12 06/01/13

Final Total
Budget Scope
Completed

Value of Status
Scope
Transferred

CM019 Manhattan Structures Part 1


Dragados-Judlau (DJ)

04/01/08

FMM02 GCT East Yard Track & Signal


Modifications
MNR F/A

12/01/02

FM216 MNR Traction Power MODs &


13.2kV Loop
TC Electric

09/25/08

CS770 GCT Flat Cars Procurement


J-Track, LLC

11/17/08

02/09

03/09

03/09

2.4

2.3 Y

Closed

CS780 Madison Yard Preparation


T. Moriarty and Sons, Inc.

05/14/08

12/08

04/09

09/09

4.4

4.9 Y

Closed

CS790 GCT Protection Works


Ad-Tech Enterprises

10/23/08

10/09

09/10

10/08/10

12.8

13.0 Y

Closed

CS800 GCT Instrumentation


Wang Technology, LLC.

06/28/08

06/09

09/09

09/09

7.1

7.5 Y

Closed

VM022 MNR Locomotives


Brookville Equipment Corp.

12/01/02

01/09

01/09

05/11/09

5.8

5.5 Y

Closed

12/09

34.4 Open

Remarks

In close out phase. Additional scope was completed and transferred


from various contracts
into CM019: CM012,
CS078, CM004,
CM013A, CM009, and
CS179
All scope completed,
savings realized

Queens
CQ025 Demolition of Superior Reed
Bldg and Preparation of Yard A
Tully Environmental, Inc.

11/05/02

07/02/03 09/15/03

09/15/03

5.3

5.6 Y

Closed

CQ026 Open Cut Excavation at


Bellmouth
Kiewit Construction, Inc.

10/07/02

09/07/03

11/25/03

11/25/03

16.8

18.7 Y

Closed

CQ027 Arch St Yard and Shop Facility


Slattery Skanska/Edwards & Kelcey

07/09/02

06/28/04

11/30/04

12/31/04

77.1

77.1 Y

Closed

MTA/LIRR East Side Access

(PM 3.5.108575)

53

1st Quarter Jan, Feb, Mar 14


SUMMARY OF COMPLETED CONTRACTS ($ IN MILLIONS)
Substantial Completion
Project Description/ Contractor

NTP

Plan

Actual

Original
Budget at
Award

06/08

121.5

62.8 N

(59.8) Closed

Orig. Revised
CQ028 Queens Open-Cut Excavation
Pile Foundation Construction Co., Inc.

CQE28-01 Emergency Work Civil/


Structural
Railroad Construction Co., Inc.

04/27/06

04/15/08 10/22/08

Final Total
Budget Scope
Completed

Value of Status
Scope
Transferred

Remarks

Contractor was defaulted. Scope was not completed and transferred


to various contracts:
CQ039, CQE28-01,
CQE28-02, CQ031

06/08

10/09

10/09

12/09

6.5

8.0 Y

2.0 Closed

CQE28-02 Queens Emergency Work


Environmental
Impact Environmental Consulting, Inc.

07/14/08

08/09

01/10

02/10

8.8

2.9 N

(5.2) Closed

CQ031 - Queens Bored Tunnels and


Structures
Granite-Traylor-Frontier Joint Venture
(GTF)

09/28/09

09/12

09/12

11/13

756.8

786.6 Y

Open

Close out is in progress

CQ039 - Northern Boulevard Crossing


Schiavone/Kiewit, a Joint Venture (SK)

02/03/10

10/05/11 08/01/12

09/30/13

89.2

102.1 Y

2.6 Open

Close out is in progress

CS810 Queens Instrumentation


Wang Technology

05/06/09

05/11

09/11

3.0

3.1 Y

Open

FQA36 Arch Street Yard Access


Amtrak
Amtrak F/A

11/14/04

09/01/05 06/23/06

06/23/06

3.8

3.4 Y

Closed

FQL36 Arch Street Yard Access LIRR


LIRR F/A

11/14/04

09/01/05 06/23/06

06/23/06

8.3

4.9 Y

Closed

10/08

11/08

26.9

27.1 Y

Closed

Closed

FQL35 Wood Interlocking LIRR


LIRR F/A

07/05

05/10

10/08

Scope transferred from


defaulted contract
CQ028
Scope was not completed and transferred
to CQ031

In close out phase

Harold
VH055 Switch Exchange System
(Procurement) Plasser American Corp.

12/20/02

06/27/04 05/29/05

09/30/05

17.7

17.2 Y

VHA01 Procure Harold Materials


Stage 1
Amtrak Various

06/06/06

07/08 09/29/10

09/09

5.1

5.1 Y

MTA/LIRR East Side Access

(PM 3.5.108757)

Open

Processing final invoice

54

1st Quarter Jan, Feb, Mar 14


SUMMARY OF COMPLETED CONTRACTS ($ IN MILLIONS)
Substantial Completion
Project Description/ Contractor

NTP

Plan

Actual

Original
Budget at
Award

Orig. Revised
VHL01 Procure Harold Materials
Stage 1
LIRR Various

Final Total
Budget Scope
Completed

Value of Status
Scope
Transferred

06/26/07

01/09

03/10

09/09

8.3

8.3 Y

03/10

03/11

03/11

03/11

37.9

16.6 N

FHA62 F Interlocking CIH


Amtrak Force Account

09/11/08

08/10

07/11

08/11

8.2

8.2 Y

Open

Processing final invoice

VQ065 - Loop Interlocking CILs


Amtrak

09/12/12

03/14

03/14

10/13

2.7

2.7 Y

Open

Awaiting final invoices


from Amtrak

Subtotal

$ 2,656.8

CS099 Advanced Procurement of Third


Party Materials
Various

MTA/LIRR East Side Access

Open

Remarks

(20.7) Closed

Processing final invoice

Scope was not completed and was transferred


to CS179, CS284, and
VS086

$ 2,599.8

Value of scope transferred

($ 66.2)

Total

$ 2,590.6

$ 2,599.8

(PM 3.5.108757)

55

1st Quarter Jan, Feb, Mar 14

PROJECT SCHEDULE

MTA/LIRR East Side Access

(PM 3.5.108757)

56

1st Quarter Jan, Feb, Mar 14

PROJECT SCHEDULE

MTA/LIRR East Side Access

(PM 3.5.108757)

57

1st Quarter Jan, Feb, Mar 14


CONTRACT PACKAGING PLAN REV.10.0

Contract Packaging Plan Rev 10.0 was updated and distributed in March 2014
MTA/LIRR East Side Access

(PM 3.5.108757)

58

1st Quarter Jan, Feb, Mar 14


MARCH BUDGET STATUS

Engineering
Construction
OCIP
Management
Real Estate
Rolling Stock
Projectwide
Reserve
Total
Change from 4th
quarter 2013

Feb 2014
Preliminary
Project Budget
$706,910,398
7,230,916,480
288,913,620
925,930,891
166,318,314
7,500,000

Current Budget

Awarded Value

Invoiced

Paid to Date

Forecast

$706,910,398
7,230,916,480
288,913,620
925,930,891
166,318,314
7,500,000

$621,126,661
4,663,767,896
187,960,159
644,933,079
110,793,747
0

$620,578,360
3,563,736,548
156,904,955
562,003,049
108,761,571
0

$599,802,206
3,454,281,012
156,904,955
557,690,462
108,761,571
0

$706,910,398
7,230,916,480
288,913,620
925,930,891
166,318,314
7,500,000

367,000,000

367,000,000

367,000,000

$9,693,489,703

$9,693,489,703

$6,228,581,542

$5,011,984,483

$4,877,440,206

$9,693,489,703

$1,448,489,703

$1,448,489,703

$789,779,774

$123,616,005

$95,324,315

N/A

The Budget has been revised to reflect the February 2014 Preliminary Project Budget. In the 1st quarter of 2014, the following contracts have been
awarded: Manhattan North Structures (CM006) and Systems Package 1 - Facilities Systems (CS179).

MTA/LIRR East Side Access

(PM 3.5.108757)

59

1st Quarter Jan, Feb, Mar 14

PROJECT FUNDING STATUS (AS OF MARCH 31, 2014) ($ IN MILLIONS)


Total Budget (exclusive of financing costs) $9,693.4
Total Commitments to Date $6,540.6
MTA Capital
Programs

Budget

Fund Source
Federal

Local

New Starts

Other

New Starts

ARRA

1995-1999

$158

$64.0

$93.7

2000-2004

1,534

754.0

31.0

775.5

2005-2009

2,683

1618.6

195.4

31.0

810.8

2010-2014

3,154

5.0

3,149.0

2015-2019

2,165

717.0

Total

$9,693

$2,436.6

$195.4

$67.0

$5,546.0

Totals may not add due to rounding. Does not include rolling stock reserve.
Value of Contract Awards

$5,438.8

Federal Share of Contract Awards

2,030.0

37.3%

Local Share of Contract Awards

3,408.8

62.7%

Value of finance charges incurred (based on prorated share from $665.6 million*
This is being reevalauted and will be updated in the next quarterly report.

Summary of Federal Grants Received ($ in millions)


Grant No.
NY-03-0344-01-12 + ARRA
NY-03-0344-13

FTA Award Date

FFY

Obligation Amount

Disbursement

N/A

1998-2010

$1,748.3

$1,748.3

22-Jun-12

2011

215.0

131.6

Subtotal ESA New Starts Grants

$1,963.3

$1,879.9

NY-90-X467 (MNR&LIRR)

29-Mar-02

2002

15.2

15.2

NY-03-0395 (LIRR)

20-Feb-02

2002

7.5

7.5

NY-03-0406 (MNR)

12-May-03

2003

5.0

5.0

NY-90-X489 (MNR)

08-Aug-03

2003

1.1

1.1

NY-03-0427 (LIRR)

01-Mar-05

2005

2.0

2.0

NY-05-0108 (LIRR)

27-Jun-06

2006

2.7

2.7

NY-05-0109 (LIRR)

24 Jul -07

2007

5.8

5.8

NY-95-X002 ESA (CMAQ)

14-Sep-07

2007

6.6

6.6

NY-95-X009 ESA (CMAQ)

13-Jan-09

2008

2.3

2.3

NY-95-X015 ESA (CMAQ)

22-Sep-09

2009

2.3

2.3

NY-95-X025 ESA (CMAQ)

23-Sep-10

2010

11.6

11.6

NY-95-X037 ESA (CMAQ)

01-Jan-13

2012

4.6

Subtotal Non-New Starts Grants

$66.7

$62.1

Total All Grants

$2,029.9

$1,942.0

MTA/LIRR East Side Access

(PM 3.5.108757)

60

1st Quarter Jan, Feb, Mar 14

STATUS OF PROJECT CONTINGENCY


ESA Contingency Balance
Feb 14 Preliminary
Project Budget

February
Contingency

1st Quarter
Drawdown

Contingency
Balance

Pre Award Contingency (AFI)

$92,855,208

$92,855,208

$92,855,208

Post Award Contingency (AWO)

278,800,412

278,800,412

13,446,498

265,353,914

Sub-Total

371,655,620

371,655,620

13,446,498

358,209,122

Risk Contingency

367,000,000

367,000,000

367,000,000

$738,655,620

$738,655,620

$13,446,498

$725,209,122

Total Contingency
Drawdown

Budget Mod #

AFI

AWO

($12,153,326)

$0

($12,153,326)

Harold Structures Part 2A CH054A

$3,031,477

$0

$3,031,477

44th St Vent Plant/245 Park Ave CM004

($132,000)

$0

($132,000)

$0

($1,222,349)

Total

Contingency Drawdown in 1st Quarter


Executed Modifications/New Exposures
Harold Structures Part I CH053

Manhattan South Structures - CM005

$14,883,834

50th Street Vent Plant Facility - CM013

($1,222,349)

55th Street Vent Plant Facility - CM013A

$625,467

GCT Concourse Facilities Ph I CM014A

($401,778)

Plaza Substation and Queens Structures


CQ032

$9,297,436

Northern Boulevard Crossing CQ039

($482,263)

Total Executed Modifications

$14,883,834
$625,467
($401,778)
$0

$9,297,436
($482,263)

$13,446,498

$0

$13,446,498

$0

$0

$0

Budget Mod #s are not assigned to executed contract Mods

Scope Transfers
None
Total Scope Transfers

Other Adjustments
None

$0

Total Other Adjustments

$0

Total 1st Quarter Drawdown

$0

MTA/LIRR East Side Access

(PM 3.5.108757)

$13,446,498

61

1st Quarter Jan, Feb, Mar 14

CONSTRUCTION
SAFETY
OPERATIONAL READINESS/LIRR
START UP
CURRENT WORK EFFORT
Continued to perform bi-weekly walkthroughs with the FDNY
and MTACC
Started to provide safety oversight to new contract Manhattan
South Structures (CM005)
Reviewed Safe Work Plan for Harold Structures - Part 3 Westbound Bypass (CH057A)
1st quarter safety assessments performed and finalization in
process

2ND QUARTER 14 LOOK AHEAD


Continue maintaining a safety culture with the contracts
Revisit and update all contractor Emergency Action Plans/Safe
Work Plans/logistic maps
Reviewing and tracking trends on daily hazard logs
Kick-off meetings for Manhattan North Structures (CM006) and
Systems Package 1 - Facilities Systems (CS179) scheduled
for April

SYSTEM SAFETY AND SECURITY


CURRENT WORK EFFORT
Coordinated presentation and preparation of three certification packages (Harold Early Stage 3 - Amtrak Force Account
(FHA03), Manhattan Tunnels Excavation (CM009), and Northern Boulevard Crossing (CQ039)) for approval by the System
Safety Certification Committee
Prepared the white paper on incident command and response
and presented it to the senior level management group consisting of Vice Presidents from LIRR, MNR, and MTACC
Continued development of processes and organization of
working groups consisting of design, construction management and quality representatives to support safety certification

of contract packages in construction


2ND QUARTER 14 LOOK AHEAD
Ongoing coordination and preparation of certification packages for design and construction for presentation to the System
Safety Certification Committee in future months
Continue support for development of processes and procedures for safety certification
Continue facilitating technical working groups for contracts
in construction, identifying documentation requirements for
certifiable elements
Finalize the white paper on incident command and response

QUALITY ASSURANCE
CURRENT WORK EFFORT
Completed 2013 Q4 quality audits for all active contracts and
issued results
Continued monitoring of all third party construction contractors quality programs
Continued oversight of the General Engineering Consultant
(GEC) construction phase services quality assurance process
Conducted quality assurance kickoff meetings with new
contracts
Performed additional 3D laser scans to verify as-built conditions and provide quality check to contractor submitted
information
Began review of active contracts Site System Safety Certification process and checklists along with instituting monthly
checks of their progress
Tracking of active contracts close-out binder and status

Engineering (SUE) services for location of buried utilities and


structures
Checked project control network from Queens to Manhattan
and set additional primary control for all contracts to use
2ND QUARTER 14 LOOK AHEAD
Perform 2014 Q1 quality audit on all active contracts
Complete 3D laser scans of all remaining tunnels and caverns
Perform process audits on selected work items and specification requirements for active contracts
Conduct quality assurance training for new contracts
Perform SUE investigation for various new design packages
and continue review and monitoring of the SUE services for
location of buried utilities and structures
Provide training and workshops on the ESA quality program to
active contracts

Continued review and monitoring of the Subsurface Utility


MTA/LIRR East Side Access

(PM 3.5.108757)

62

1st Quarter Jan, Feb, Mar 14

12
MONTH SYSTEMS
CUMULATIVE RUNNING TOTAL OF LTA AND BLS RATES
RAILROAD
CH053, CH054A, CH057A, CM004, CM013, CM013A, CM014A, CQ031, CQ032, CQ039
2.50
2.30

2.27

2.25

2.23

2.23

2.22

2.23

2.22

2.23

2.23

2.23

2.22

2.00
1.7
1.50

1.00

0.50

0.00

Apr-13

May-13

Jun-13

Jul-13

Aug-13

Sep-13

Oct-13

LTA

Nov-13

Dec-13

Jan-14

Feb-14

Mar-14

BLS

1) Chart shows available rates at the time this Quarterly Report is published
2) Lost Time Accident (LTA) rates represent incidents per 200,000 work-hours
3) Bureau of Labor Statistics (BLS) / National Industry Average Rates published in 2013

GRAND CENTRAL TERMINAL


CURRENT WORK EFFORT
GCT Concourse and Facilities Fit-Out (CM014B) Continuedfinalizing and preparing the contract for bid
48th Street Entrance (CM015) Continued working with the
building owner of 415 Madison Ave. regarding a modified
approach to the entrances construction in which significantly
more of the work inside the building would be constructed by
the building owner

2ND QUARTER 14 LOOK AHEAD


Negotiate the change order to the Vertical Circulation Escalators and Elevators (VM014) contract
Advertise the GCT Concourse & Facilities Fit-Out (CM014B)
contract for bid
Work with the 415 Madison Ave. building owner to establish a
Work Agreement for the structural design work to be undertaken by the building owner

RAILROAD SYSTEMS
CURRENT WORK EFFORT
Systems Package 1 - Facilities Systems (CS179) - CS179
was approved by the MTA Board for award at the January
2014 Board meeting. The Notice of Award and Notice to Proceed was signed on March 31, 2014.
Systems Package 3 - Signal Equipment Procurement (VS086)
- VS086 was approved by the MTA Board for award at the
January 2014 Board meeting. Prepared contract execution
documents.
MTA/LIRR East Side Access

2ND QUARTER 14 LOOK AHEAD


Systems Package 2 - Tunnel Systems (CS284) Reviewing
contract packaging opportunities
Systems Package 4 - Traction Power System (CS084) Issue
documents for procurement

(PM 3.5.108757)

63

1st Quarter Jan, Feb, Mar 14

OPERATIONAL READINESS/LIRR START UP


CURRENT WORK EFFORT
Began development of a revised outline and draft of Volume
3 (Monitoring) of the Rail Activation Plan jointly with LIRR and
MNR
Provided ongoing technical support for the Rail Activation
quarterly review process and other reporting and documentation activities in partnership with LIRR and other participants
Provided ongoing technical support for the safety certification
process, including support for continuing development of certification processes and procedures and support for a System
Safety Certification Committee meeting held in February
Began development of the operational readiness component
of the East Side Access Integrated Project Schedule

2ND QUARTER 14 LOOK AHEAD


Conduct multiple joint workshops with LIRR and MNR to define the core business processes for monitoring the execution
of the Rail Activation Plan
Continue testing initial application uploads in Maximo
Continue ongoing technical support for the Rail Activation
quarterly review process and other reporting and documentation activities in partnership with LIRR and other participants
Continue ongoing technical support for the safety certification
process, including working group and future System Safety
Certification Committee meetings

Continued review of asset listings and training of contractors


to support populating the asset templates by contractors
Continue collaboration with LIRR ESA and Special Projects
on development of service codes that will be used during the
interim maintenance process

MTA/LIRR East Side Access

(PM 3.5.108757)

64

1st Quarter Jan, Feb, Mar 14

ENVIRONMENTAL
MITIGATION START UP
OPERATIONAL READINESS/LIRR
The quarterly environmental field audit of Queens and Manhattan contractors is scheduled for April 9 and 11, 2014
Bi-weekly environmental walkthroughs with contractors and
environmental coordinators are being held regularly by project
environmental engineers. Environmental deficiencies are

reported to construction managers via bi-weekly walkthrough


reports.
Conducted weekly visits to Manhattan vent plant sites to
address community concerns and ensure that appropriate
mitigation remained in place

PUBLIC OUTREACH
CURRENT WORK EFFORT
Sent contract award notifications for Harold Structures - Part 3
Westbound Bypass (CH057A) to Queens elected officials
Convened 4th quarter 2013 Construction Advisory Committee
meeting for 55th Street
Sent 4th quarter ESA Community Newsletters to Manhattan
and Queens constituencies
Performed site visits to all Queens and Manhattan project
sites to view ongoing work and to identify and address any
potential negative community impacts
Monitored and logged snow removal efforts by ESA construction management
Provided notifications and addressed community inquiries and
concerns regarding activities and schedules of work on 37th
Street by Manhattan South Structures (CM005)
Implemented a Unifier business process for project related
complaints, inquiries and requests for community outreach
Began outreach to Community Board 5 and 6 in Manhattan
and elected officials in Queens to provide updates on ESA
activities
Met with Arts for Transit & Urban Design to discuss additional

plans for the artwork installation at Roosevelt Island and budgeting needs for future installations elsewhere on the project
Convened monthly construction progress meetings with
representatives of the Yale Club to discuss ongoing impacts
from work by 44th Street Demolition and Construct Fan Plant
Structure and 245 Park Ave. Entrance (CM004)
Distributed flyers and sent email notification regarding
planned overnight work by Harold Structures Part 1 and GO2
Substation (CH053) in proximity to the Sunnyside Garden
community
Developed landscaping improvement plan for the 37th Street
and Park Avenue site
Continued to address inquiries and issues regarding the blasting and excavation activites at 55th Street
2ND QUARTER 14 LOOK AHEAD:
Continue providing property owners and other area stakeholders timely notifications regarding construction activities
Send contract award notifications and begin outreach planning for future contracts
Perform regular site visits to evaluate and address conditions
and community impacts

REAL ESTATE
CURRENT WORK EFFORT
Continued working with the expeditor, Gillman Consulting
Inc., who is assisting the project in filing the NYC Department
of Buildings application required to make repairs to privately
owned columns that extend into the lower train shed (GCT
Concourse and Facilities Fit-Out Early Work (CM014A))
Worked with 335 Madison Avenues building manager and
other property representatives to obtain access for GEC personnel to observe existing conditions and for the environmental consultant to inspect and collect samples from those areas
where the Station Masters Office/Terminal Management
Center and the Biltmore Elevators will impact that building
MTA/LIRR East Side Access

(GCT Concourse and Facilities Fit-Out (CM014B))


Met with a representative of 200 Park Avenues consulting engineer, Severud Associates, to explain ESAs need to extend
two existing elevator shafts down, which will result in interference with the existing footings for two columns that support
200 Park Avenue. The work on those elevator shafts will be
done under Manhattan Cavern Structure and Facilities Fit-Out
(CM007).
Visited Madison Yard with representatives of 250 Park Avenue
to discuss and see the buildings strut (horizontal structural
steel member) that needs to be lowered to facilitate the construction of the 47th Street Cross Passageway Connection
(PM 3.5.108757)

65

1st Quarter Jan, Feb, Mar 14

REAL ESTATE (CONT)


2ND QUARTER 14 LOOK AHEAD:
Meet with the MTA Real Estate Department to discuss the
easements required from the property located at 41-02 Northern Boulevard in the Borough of Queens (Block 0183, Lot
0040). Existing catenary poles are in the way of future tracks
to train yard, so new catenary poles need to be erected on an
adjacent privately owned property (Harold Structures - Part 3,
EBRR Structure, D Phase 2 & B/C Approach (CH058))

Continue working with the 300 Park Avenues representative


with respect to having their authorized signatory sign and
return the Department of Buildings application that will allow
ESAs contractor to make repairs to their buildings deteriorated structural members (GCT Concourse and Facilities Fit-Out
Early Work (CM014A))

Continue discussions with the MTA Real Estate and Legal


Departments regarding the temporary easement required
from the Gaseteria property to reconstruct a retaining wall
on railroad property under the Mid-Day Storage Yard Facility
(CQ033), and an access agreement needed to maintain the
rail or fence installed on top of that retaining wall
HISTORIC AND PRESERVATION ISSUES
CURRENT WORK EFFORT
There wasnt any archaeological monitoring conducted in
the past three months. Harold Structures - Part 3 Westbound
Bypass (CH057A), which will construct westbound bypass
structures may disturb archeological sensitive area #6B next
quarter. The project Archaeologist will be notified prior to any
disturbance of sensitive areas and excavation will take place
under his/her direction as per approved Construction Protection Plan.

MTA/LIRR East Side Access

2ND QUARTER 14 LOOK AHEAD


MTACC will continue to consult with the New York State Historic Preservation Office (SHPO) and the FTA, when necessary,
on issues related to the preservation and protection of cultural
resources in the Area of Potential Effect, in accordance with
the ESA Programmatic Agreement

(PM 3.5.108757)

66

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant

Harold Structures Part 3 Westbound Bypass Structures (CH057, CH057A, CH053,


CQ031)
The Westbound Bypass tunnel enables Amtrak trains entering Harold Interlocking from the Hell Gate Line
to be routed into Penn Station East River Tunnel (ERT) Line 2 conflict free, thereby decreasing the number
of potential service delays which will be caused by current service levels. Construction of the grade separated Westbound Bypass will reduce travel times through Harold Interlocking and allow Amtrak to increase
service.
Harold Structures Part 3 Eastbound Reroute (CH058)
Eastbound Reroute tunnel enables Amtrak trains entering Harold Interlocking from Penn Station to be routed
into the Hell Gate Line Track 2 decreasing the number of conflicts and thereby reducing the number of service
delays which will be caused by current service levels. Construction of the Eastbound Reroute will reduce
travel times through Harold Interlocking and allow Amtrak to increase service.

Loop & T Interlocking - Direct F/A & Procurement (FQA65, VQ065)


Modification of the existing Loop Track interlocking (installation of Central Instrument Locations (CILs) and
crossovers) provides additional routing east of the Amtrak car washer. This routing permits efficient access by
Amtrak from the Amtrak Bypass track to the southern existing Sunnyside Yard storage tracks.
Harold Stage 3 and 4 Force Account (FHA/L03, FHA/L04, VHA/L03, VHA/L04)
Includes railroad agency force account direct labor, equipment and procurement of materials for construction of the Westbound Bypass and Eastbound Reroute. Construction includes the modification/relocation of
catenary and installation of new signals.
Building Demolition (CQ033)
Demolition of Amtrak Buildings 7 & 8

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


1ST QUARTER HIGHLIGHTS WITH A LOOK AHEAD TO NEXT QUARTER
CURRENT WORK EFFORT
FRA is drafting an amendment to MTAs High-Speed Intercity
Passenger Rail (HSIPR) Grant to allow for the spending of
all federal funds prior to using local match funds (tapered
match). ESA will provide a Harold Interlocking status update,
including revised schedule and HSR budget in the 2nd quarter of 2014 before the grant amendment is finalized.
The amendment to the Service Outcome Agreement (SOA)
was signed by the MTA and Amtrak
On November 21, 2013, MTACC issued a Notice of Award
and Limited Notice to Proceed to Harold Structures Joint Venture for the Task 2: Westbound Bypass (CH057A) contract.
Following the SOA signoff, the FRA granted approval to issue
a full Notice to Proceed for CH057A on March 7, 2014 and
MTACC issued the full NTP to the contractor on March 10,
2014. The contract value is $104.3M, of which $103.3M is
expected to be funded under the HSIPR grant. The contractors initial work scope consists of engineering and submittals,
survey and mobilization, well point design and installation,
procurement of material for soldier and secant piles, and
procurement of jacked tunneling equipment and other related
equipment. Amtrak and LIRR issued permits needed to
advance these initial work stages.

completed its research and is drafting a Buy America Waiver


letter.
PLANNED WORK EFFORT
Finalize FRA Grant Amendment to include tapered match language and the proposed Harold Repackaging Plan, including
the corresponding schedule and budget updates
Complete review and submission to FRA of Amtrak PI for
FQA65 Part 2 (Track)
Submit the 100% design for:
Task 2 - Westbound Bypass: CH057 Harold Structures
Part 3, reflecting re-sequencing of contract scope items
Task 3 - Eastbound Re-route: CH058 Harold Structures
EBBR, reflecting re-sequencing of contract scope items
Task 4 - Westbound/Eastbound Force Account: FHA04
Harold Stage 4 Amtrak, FHL04 Harold Stage 4 LIRR,
VHA04 Procure Harold Materials Stage 4 Amtrak, and
VHL04 Procure Harold Materials Stage 4: LIRR
Task 5 - Submit design revisions for Task 5: Loop Interlocking (FQA65)

NYSDOT approved the corresponding Amtrak and LIRR Access and Protection (A&P) agreements required for CH057A:
FHL57A (LIRR A&P) was approved on December 19, 2013
and FHA57A (Amtrak A&P) was approved January 3, 2014
The 100% design drawings for Replacement of Amtrak Car
Washer: CH059 Harold Structures Part 4 (Task 6) were submitted to the FRA on March 3, 2014
The 100% design drawings for Demolition of Amtrak Buildings: CQ033 Mid-Day Storage Yard Facility (Task 7) were
submitted to the FRA on March 27, 2014
NYSDOT approved Part 1 of the Amtrak Project Initiative for
Task 5: Loop Interlocking (FQA65) on January 6, 2014. Part
1 is for signals, Part 2, which is for track, is scheduled to be
submitted by the end of the 2nd quarter 2014.
The MOU with LIRR for FHL03 and the PI with Amtrak for
FHA03 covering Procurement of Stage 3 Harold Materials
were sent to NYSDOT on March 5, 2014
MTA and LIRR have been working collaboratively with the
FRA to compile the necessary information in order to move
forward with the Buy America Waiver request. LIRR is currently contacting potential vendors to determine their interest
in submitting a bid to produce the required material. LIRR has
MTA/LIRR East Side Access

(PM 3.5.108757)

68

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


DESIGN MILESTONES
Area Contract
Number

Queens

CQ033

FQA65

CH057

Harold

CH058

CH059

FHA/L04
VHA/L04

Contract
Name

Forecasted Date

Comments

Design
Submitted

90%

100%

Mid-Day
Storage Yard
Facility

Current
Month

Done

Done

Previous
Month

Done

Done

Loop Interlocking CIL Amtrak F/A

Current
Month

Done

Done

Previous
Month

Done

Done

Harold Structures - Part


3 48th Street
Bridge, D
Approach
Phase 1 &
EBRR East
Approach

Current
Month

Done

06/14

Previous
Month

Done

Done

Harold Structures - Part 3,


Eastbound
Bypass
Structure, D
Phase 2 & B/C
Approach

Current
Month

08/14

10/14

Previous
Month

08/14

10/14

MTA Board approved this


repackaging effort in March.
The mod is in process and
expected to be issued to the
GEC in April.

Harold Structures Part 4, Car


Washer

Current
Month

Done

Done

GEC will sign and seal in April.

Previous
Month

Done

Done

Harold Stage
4 - Force
Account

Current
Month

Done

Done

Previous
Month

Done

Done

GEC submitted the 100% design and LIRR comments are


being addressed. Sign and seal
is expected in the 2nd quarter.
GEC submitted the 100%
design and the change to
concrete ties is being done as
a design mod and is expected
to be completed by April.
100% repackaging is due in
June.

An on-board review meeting


with the railroads will be scheduled for April. 100% drawings
will be sent to FRA in the 2nd
quarter.

Based on 4/1 CSSR

MTA/LIRR East Side Access

(PM 3.5.108757)

69

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


SUMMARY OF BUDGET AND FUNDING
FRA Grant

Federal Disbursements

Total Project Cost

Federal

Local Match

$368,476,974

$294,781,579

$73,695,395

Grant No.

Title

Award Date

Obligated
Amount

Amount
Disbursed

Amount
Remaining

FR-HSR-0065-11-01-00-NY

FRA-NYSDOT

Aug, 2011

$294,781,579

$428,159

$294,353,420

STATUS OF SUBMISSIONS AND APPROVALS


TASK CONTRACT DESCRIPTION

Westbound Bypass
2
CQ031
Harold Structures - Part 3 WBBY Slab
2
CH053
Harold Structures - Part 3 WBBY Structure
Removal
2
CH057A
Harold Structures - Part 3 WBBY
2
FHL57A
Harold Structures - Part 3 WBBY LIRR (A&P)
2
FHA57A
Harold Structures - Part 3 WBBY Amtrak (A&P)
2
CH057
Harold Structures - Part 3
2
FHA057
Harold Structures Part 3 - Amtrak
2
FHL057
Harold Structures Part 3 - LIRR
Eastbound Reroute
2
CH058
Harold Structures - EBRR
2
FHA058
Harold Structures EBRR - Amtrak
2
FHL058
Harold Structures EBRR - LIRR
Westbound/Eastbound Force Account
4
FHA/L03*
Harold Stage 3: Amtrak - Summer Track Outage
4
FHA/L03*
Harold Stage 3: LIRR - Summer Track Outage
4
FHA/L03*
Harold Stage 3: Amtrak (Force Account)
4
FHA03
Harold Stage 3: Amtrak (Catenary)
4
FHA/L03*
Harold Stage 3: LIRR (Force Account)
4
FHA04
Harold Stage 4: Amtrak
4
FHL04
Harold Stage 4: LIRR
4
VHA03
Procure Harold Materials Stage 3 - Amtrak
4
VHL03
Procure Harold Materials Stage 3 - LIRR
4
VHA04
Procure Harold Materials Stage 4 - Amtrak
4
VHL04
Procure Harold Materials Stage 4 - LIRR

MTA/LIRR East Side Access

DESIGN
SUBMITTED TO
FRA

APPROVED
BY FRA

CONTRACT DOCUMENTS
SENT TO APPROVED
NYSDOT BY NYSDOT

PI
APPROVED
(AMTRAK)

AGENCY AGREEMENTS
MOU
PI/MOU
APPROVED APPROVED
(LIRR) BY NYSDOT

NOTICE TO
PROCEED
ISSUED

4/17/12
4/17/12

5/4/12
5/4/12

5/1/13
6/13/13

5/2/13
6/18/13

N/A
N/A

N/A
N/A

N/A
N/A

N/A
N/A

4/17/12
N/A
N/A

5/4/12
N/A
N/A

5/16/13
N/A
N/A

6/20/13
N/A
N/A

N/A
N/A
N/A

N/A
8/29/13
12/19/13

N/A
12/19/13
1/3/14

N/A
N/A
N/A

10/4/12
10/4/12
10/4/12
5/8/13
10/4/12

10/15/12
10/15/12
10/15/12
6/14/13
10/15/12

7/10/13
7/10/13
N/A
N/A
N/A

7/16/13
7/16/13
N/A
N/A
N/A

8/9/13
8/9/13
11/18/13

10/1/13
10/1/13

N/A
N/A

N/A

8/29/13
8/29/13
N/A
N/A
11/21/13

5/8/13
5/8/13

6/14/13
6/14/13

7/26/13
7/26/13

9/26/13
9/26/13

N/A
N/A

N/A
N/A

N/A
N/A

N/A
N/A

(PM 3.5.108757)

70

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


STATUS OF SUBMISSIONS AND APPROVALS (CONT)
TASK CONTRACT DESCRIPTION

Loop Interlocking
5
FQA65
Loop Interlocking CIL: Amtrak (Part 1 Signals)

FQA65

Loop Interlocking CIL: Amtrak (Part 2 Track)

5
VQ065
Loop Interlocking CIH
Replacement of Car Washer
6
CH059
Harold Structures - Part 4
6
FHA59
Harold Structures - Part 4: Amtrak
6
FHL59
Harold Structures - Part 4: LIRR
Demolition of Amtrak Buildings
7
CQ033
Middday Storage Yard Facility - Bldgs #7 & 8
7
FQA33
Midday Storage Yard: Amtrak

DESIGN
SUBMITTED TO
APPROVED
FRA
BY FRA

90% Design
3/15/13
100% Design
5/2/13
90% Design
3/15/13
100% Design
5/2/13
1/11/12

CONTRACT
SENT TO APPROVED
NYSDOT BY NYSDOT

7/13/13

N/A

N/A

7/13/13

N/A

N/A

5/17/12

5/17/12

5/18/12

PI
APPROVED
(AMTRAK)
10/21/13

AGENCY AGREEMENTS
MOU
PI/MOU
APPROVED APPROVED
(LIRR) BY NYSDOT
N/A

1/6/14

N/A

5/10/12

N/A

NOTICE TO
PROCEED
ISSUED
N/A

N/A

5/18/12

9/12/12

3/4/14
N/A
N/A
3/27/14
N/A

Indicates Active Construction


Indicates Completed Construction
*Summer Outage Force Account work was billed to FHA03 and FHL03.

MTA/LIRR East Side Access

(PM 3.5.108757)

71

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


PROPOSED BUDGET
TASK DESCRIPTION
1
2

Work Plan
Westbound Bypass
CQ031: Harold Structures - Part 3 WBBY Slab
FQA31: Harold Structures - Part 3 WBBY Slab (Access
and Protection)
CH053: Harold Structures - Part 3 WBBY Structure
Removal
CH057A: Harold Structures - Part 3 WBBY**
FHA57A: Harold Structures - Part 3 WBBY Amtrak
(A&P)
FHL57A: Harold Structures - Part 3 WBBY LIRR (A&P)
CH057: Harold Structures - Part 3
FHA57: Harold Structures Part 3 - Amtrak
FHL57: Harold Structures Part 3 - LIRR
Eastbound Reroute
CH058: Harold Structures - EBRR
FHA58: Harold Structures EBRR- Amtrak
FHL58: Harold Structures EBRR- LIRR
Westbound/Eastbound Force Account
FHA03: Harold Stage 3: Amtrak
FHL03: Harold Stage 3: LIRR
FHA04: Harold Stage 4: Amtrak
FHL04: Harold Stage 4: LIRR
VHA03: Procure Harold Materials Stage 3 - Amtrak
VHL03: Procure Harold Materials Stage 3 - LIRR
VHA04: Procure Harold Materials Stage 4 - Amtrak
VHL04: Procure Harold Materials Stage 4 - LIRR
Loop Interlocking
FQA65: Loop Interlocking CIL: Amtrak (Signals Only track to follow)
VQ065: Loop Interlocking CIL
Replacement of Amtrak Car Washer
CH059: Harold Structures - Part 4
FHA59: Harold Structures - Part 4: Amtrak
FHL59: Harold Structures - Part 4: LIRR

MTA/LIRR East Side Access

GRANT
APPROVED
BUDGET*
$171,657,634
-

FEB 2014
PRELIMINARY
BUDGET*
$181,662,430
$4,392,893
$1,245,189

CONTRACT
AWARD

TOTAL

INVOICED
FEDERAL

LOCAL

$125,644,684
$4,025,000
$1,245,190

$5,717,303
$4,025,000
$1,245,190

$4,484,952
$3,220,000
$996,152

$1,121,238
$805,000
$249,038

$369,000

$336,000

$336,000

$268,800

$67,200

$171,657,634
-

$117,920,000
$15,404,570

$103,300,000
$11,077,291

$48,135

$87,827,530
$83,676,159
$2,011,101
$2,140,270
$55,533,194
$46,176,531
$823,950
$7,551,185
$981,528
$31,790,018
$27,184,234

$7,045,602
$31,816,717
$2,351,465
$1,116,995
$106,711,958
$87,641,431
$10,471,087
$8,599,440
$104,012,644
$10,608,828
$26,613,545
$26,465,680
$4,282,632
$19,072,904
$5,703,841
$10,297,876
$967,340
$35,781,021
$33,163,652

$5,661,203
$5,106,100
$2,400,000
$2,706,100
$11,626,226
$9,008,857

$62,978
$5,037,142
$2,331,139
$2,706,003
$1,821,761
$595,977

$4,029,714
$1,864,911
$2,164,802
$1,457,408
$476,782

$1,007,428
$466,228
$541,201
$364,352
$119,195

$4,605,784
$17,759,513
$17,759,513
-

$2,617,369
$58,297,906
$47,822,145
$5,735,096
$4,740,666

$2,617,369
-

$1,225,784
-

$980,627
-

$245,157
-

(PM 3.5.108757)

72

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


PROPOSED BUDGET (CONT)
TASK DESCRIPTION
7

Demolition of Amtrak Buildings


CQ033: Midday Storage Yard Facility- Bldgs # 7,8
FQA33: Midday Storage Yard: Amtrak
Administrative Costs
SC800 - Construction Management by PMC
SP819 - Consultant Const Mgmt Services
Owner Controlled Insurance
CPS - Engineering Support to Construction
Contingency
Total

GRANT
FEB 2014
APPROVED PRELIMINARY
BUDGET*
BUDGET*
$3,909,085
$4,315,499
$3,622,635
$2,662,824
$286,450
$1,652,675
$59,739,036
$15,641,246
$8,540,045
$16,939,198
$8,618,547
$10,000,000
$368,476,974
$550,520,495

CONTRACT
AWARD

TOTAL

INVOICED
FEDERAL

LOCAL

$34,819,668
$11,307,302
$6,573,168
$16,939,198
$177,196,678

$19,904,957
$2,965,759
$16,939,198
$32,481,163

$15,923,966
$2,372,607
$13,551,358
$25,896,040

$3,980,991
$593,152
$3,387,840
$6,474,010

*An updated proposed Grant budget is in development. Grant Approved Budget will be revised upon receipt of concurrence from FRA and NYSDOT.
**A full Notice to Proceed was issued on March 10, 2014.

MTA/LIRR East Side Access

(PM 3.5.108757)

73

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


PROCUREMENT MILESTONES*
Contract
Number

Contract Name

Procurement

Construction

Ready for
Proc. (S&S +
Div1)

Advertise

Advertised
Bid Date

Expected
Bid Date

Notice to
Proceed

Substantial
Completion

Forecasted
Date

Forecasted
Date

Forecasted
Date

Forecasted
Date

Forecasted
Date

Forecasted
Date

11/1/14

12/1/14

3/9/15

4/20/15

7/5/15

10/25/18

7/7/14

7/21/14

9/8/14

9/22/14

11/3/14

7/29/16

CQ033

Mid-Day Storage Yard


Facility

CH057

Loop Box and D Approach, EBRR West


Approach & Tunnel and
B & C Approach

CH058

Harold Structures Part 3, EB Bypass


Structure, D & B/C
Approach

11/3/14

2/24/15

4/6/15

4/20/15

7/2/15

3/31/18

CH059

Harold Structures Part 4

4/30/14

9/2/16

11/28/16

11/28/16

2/1/17

6/22/18

FHA03

Amtrak Harold Stage


3 - Force Account

3/26/13A

n/a

n/a

n/a

5/31/14

8/15/18

Amtrak Harold Stage Catenary

8/30/13 A

n/a

n/a

n/a

5/31/14

8/15/18

LIRR Harold Stage 3 Force Account

3/26/13 A

n/a

n/a

n/a

6/1/14

8/14/17

LIRR Harold Stage 3 Catenary

8/30/13 A

n/a

n/a

n/a

6/1/14

8/14/17

Amtrak Harold Stage


4 - Force Account

5/15/14

n/a

n/a

n/a

3/7/15

12/14/18

Amtrak Harold Stage


4 - Catenary

5/15/14

n/a

n/a

n/a

3/7/15

12/14/18

FHL04

LIRR Harold Stage 4 Force Account

5/15/14

n/a

n/a

n/a

8/23/14

12/14/18

VHA04

Procure Materials for


Harold Stage 4 - Amtrak F/A

5/15/14

n/a

n/a

n/a

9/8/14

12/14/18

VHL04

Procure Materials for


Harold Stage 4 - LIRR
F/A

5/15/14

n/a

n/a

n/a

6/5/14

12/14/18

FHL03

FHA04

*Dates reflect incorporating the preliminary results of the cost and schedule review jointly undertaken by MTACC, MTAOCO,
Independent Engineer, a Supplemental Independent Engineer and the Federal Transit Administration. Based on the 4/1 CSSR.

MTA/LIRR East Side Access

(PM 3.5.108757)

74

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


ACTIVE CONSTRUCTION CONTRACTS SUMMARY ($ IN MILLIONS)
Current Value

Budget
at Award

Original
Current
Contract
Approved
Award*** Contract***

Cost
Expenditure %
Complete***

Remaining
Total Estimate at
Budget Budget Completion*

Plan

Substantial
Completion***

Project
Description/
Contractor**

Status

Actual

Invoiced

FHA03 - Harold
Stage 3
Amtrak Force
Account Line 2
and 4 Tracks
Amtrak

NO

10.6

2.4

2.4

8.2

10.6

10.6

100.0%

100.0%

2.3

FHL03 - Harold
Stage 3 LIRR
Force Account
Line 2 and 4
Tracks

NO

26.6

2.7

2.7

23.8

26.5

26.5

100.0%

100.0%

FQA65 - Amtrak
Loop
Interlocking CIL
Amtrak

NO

33.8

4.5

4.5

28.7

33.2

33.2

8.6%

CH057A - Harold
Structures - Part
3 Westbound
Bypass

NO

113.6

104.3

104.3

25.8

130.1

104.3

NTP

Plan

Forecast

Orig.

Revised

07/19/13

N/A

08/13

08/13

2.7

07/19/13

N/A

08/13

08/13

8.0%

4.5

01/09/14

07/18

08/18

09/18

0.0

12/02/13

01/16

01/16

02/16

*EACs do not include possible contract mods and future claims. **Please refer to the CH053 summary sheet for information regarding the Regional Investment portion.
***Contract Awards for Force Account work (FHA03, FHL03, FQA65) are made on an annual basis.

For more information, please refer to the individual contract summaries.


Status

Critical Path (CP)

MTA/LIRR East Side Access

Near Critical (NC)

Not Critical (NO)

(PM 3.5.108757)

75

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


Harold Stage 3 - Amtrak Force Account (FHA03)
Contractor: Amtrak
Construction Manager: Peter Malvese
FRA Grant: FR-HSR-0065-11-01-00-NY

Description: Demolish and rebuild tracks on Line

2 and 4 for Westbound Bypass Under Track Slab Construction; Reinstall tracks and 3rd rails on Line 2 and 4;
Install new 2,911 feet track panels on Line 2 and Line 4
tracks including 580 feet over the track slab; All of the
work will be performed during the summer long term
Line 2 and Line 4 track out of service, July 19 to Aug 19,
2013.

SCHEDULE PROGRESS

No work this period


CRITICAL ISSUES

None

MITIGATION

N/A

COST

Award amount is for summer outage work only


97.1% of the FHA03 current contract value has been invoiced as of March 2014, which is the same as last month. 92.0% of
the current contract value has been paid, up from 40.9% last month. The EAC has not changed from last month.
LOOK AHEAD

Pending initiation of additional Stage 3 work in June

MTA/LIRR East Side Access

(PM 3.5.108757)

76

MILESTONES
Current

Actual/

Baseline

Forecast

Commence Early Stage 3

7/19/13

7/19/13

Remove & Install Track Line 2

7/19/13

7/19/13

Line 2 Track Back to Service

8/5/13

8/5/13

Remove & Install Track Line 4

8/3/13

8/3/13

Line 4 Track Back to Service

8/19/13

8/19/13

Complete Summer Outage

8/20/13

8/20/13

2013
J

Actual/Forecast

(0 days)
(0 days)

Current Baseline

(0 days)
(0 days)
(0 days)
(0 days)

FINANCIAL SUMMARY
Budget
$10,608,828

$10,608,828

Contract
$2,400,000

$2,400,000

Invoiced
$2,331,139

$2,331,139

Paid to Date
$2,208 ,568

$2,208,568

EAC
$10,608,828

$10,608,828

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

77

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


Harold Stage 3 - LIRR Force Account (FHL03)
Contractor: Long Island Rail Road
Construction Manager: Peter Malvese
FRA Grant: FR-HSR-0065-11-01-00-NY

Description: Install two switches with point protected:


3121W aka ZI1 (Line 4 to Future Westbound Bypass)
and 835 aka AG1 (WWD LI Passenger to WBY). Demolish and rebuild track and third rail on Line 4 (~600 LF) at
east of Honeywell Street. Line 4 work will be performed
during the summer long term Line 2 and Line 4 track out
of service, July 19 to Aug 19, 2013. AG1 will be installed
September 14, 2013.

SCHEDULE PROGRESS

No work this period

CRITICAL ISSUES

None

MITIGATION

N/A

COST

Award amount is for summer outage work only


99.4% of the FHL03 current contract value has been invoiced as of March 2014, which is the same as last month. The EAC
has not changed from last month. FHL03 is paid out FQL99, which is an account several LIRR force account packages are
paid from. $26M has been paid out of FQL99 to date.

LOOK AHEAD

Pending initiation of additional Stage 3 work in June

MTA/LIRR East Side Access

(PM 3.5.108757)

78

MILESTONES
Current Baseline

Actual

Commence Early Stage 3

7/19/13

7/19/13

Install 3132W (ZI1) Switch

8/10/13

8/10/13

Remove & Install Track Line 4

8/3/13

8/3/13

Line 4 Track Back to Service

8/19/13

8/19/13

Complete Summer Outage

8/20/13

8/20/13

Install 835 (AG1) Switch

9/14/13

9/14/13

Actual/Forecast

(0 days)
(0 days)
(0 days)
(0 days)

(0 days)

Current Baseline

(0 days)

FINANCIAL SUMMARY
Budget
$26,465,680

$26,465,680

Contract
$2,722,448

$2,722,448

Invoiced
$2,706,003

$2,706,003

Paid to Date
$0

EAC
$26,465,680

EACs do not include possible contract mods and future claims.

$26,465,680

ESA

Regional Investment

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

79

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


Loop Interlocking CIL - Amtrak (FQA65)
Contractor: Amtrak

Description: Installation and cutover of Loop and T

Construction Manager: Peter Malvese

Central Instrument Houses and all associated huts and


cases. Install all signal troughs and cables. Install new signal apparatus including cutover to new color signal lights.
Demolition of retired signal cable and apparatus. Install
and cutover of fourteen (14) new switches; 19A(HD1),
19B(HD2), 99(HD3), 763(NW2), 91A(NW3), 91B(NW4),
99(NW5), 21A(CH1), 21B(CH2), 12A(CH3), 12B(CH4),
19A(99), 19B(CH5), and DS2.

Federal Grant: FR-HSR-0065-11-01-00-NY

SCHEDULE PROGRESS

Continued the installation of troughs from F2J signal hut to


LOC A signal case (780 LF completed) along Loop 1 track
Commenced the installation of temporary conduits (210 LF)
from LOC A to LOC B signal cases along south of Train-

Washer on Loop track


Material delivery and survey for future trough and conduit
installation are in progress

CRITICAL ISSUES

The Substantial Completion date is tied with Amtrak ET-Catenary resources. There was a low production rate in the first quarter due to the weather (snow) and sending the team to support the Contractor on another project.

MITIGATION

ESA and Amtrak are working on resequencing the catenary schedule to coordinate with the weekend outage. The weekend
work will mitigate a duration lost in the first quarter.

COST

100% of the FQA65 current contract value has been invoiced and paid as of March 2014, which is the same as last month.

LOOK AHEAD

Continue troughs and conduit installation from F2J to LOC


A and LOC B signal cases for new Loop CIH

Continue material delivery and survey for future trough and


track installation

FQA65 PROGRESS CURVE


100%
Current Baseline

90%

Actual

80%

70%

60%

50%

4
40%

30%

Cumulative
Plan: 8.6%

1st Quarter
Plan: 8.6%

MTA/LIRR East Side Access

20%

(PM 3.5.108757)

Jul-18

Aug-18

Jun-18

Apr-18

May-18

Mar-18

Jan-18

Feb-18

Dec-17

Oct-17

Nov-17

Sep-17

Jul-17

Aug-17

Jun-17

Apr-17

May-17

Mar-17

Jan-17

Feb-17

Dec-16

Oct-16

Nov-16

Sep-16

Jul-16

Aug-16

10%

Jun-16

Apr-16

May-16

Mar-16

Jan-16

Feb-16

Dec-15

Oct-15

Sep-15

Jul-15

Actual: 8.0%
Aug-15

Jun-15

Apr-15

May-15

Mar-15

Jan-15

Feb-15

Dec-14

Oct-14

Nov-14

Sep-14

Jul-14

Aug-14

Jun-14

Apr-14

May-14

Mar-14

Jan-14

Feb-14

Dec-13

Actual: 8.0%

Nov-15

0%

80

MILESTONES
2014

Current

Actual/

Baseline

Forecast

Q1

Commence FQA65

1/9/14

1/9/14

T - CIH Cutover

3/8/15

6/14/15

Loop - CIH Cutover

1/10/16

2/28/16

Substantial Completion

8/12/18

9/1/18

2015

Q2 Q3 Q4 Q1

2016

Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1

2017
Q2 Q3 Q4

2018
Q1

2019

Q2 Q3 Q4 Q1

Q2 Q3 Q4

(0 days)

(+98 days)

(+49 days)

Current Baseline

Actual/Forecast

(+20 days)

FINANCIAL SUMMARY
Budget
$33,163,652

$33,163,652

Contract
$4,531,636

$4,531,636

Invoiced
$4,531,636

$4,531,636

Paid to Date
$4,531,636

$4,531,636

EAC
$33,163,652

$33,163,652

ESA

Regional Investment

EACs do not include possible contract mods and future claims.

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

81

1st Quarter Jan, Feb, Mar 14

Federal Railroad Administration High Speed Intercity Passenger Rail Grant


Harold Structures - Part 3 Westbound Bypass (CH057A)
Contractor: Harold Structures Joint Venture
Construction Manager: Stephen Conenna
FRA Grant: FR-HSR-0065-11-01-00-NY

SCHEDULE PROGRESS
Notice to Proceed: Received full Notice to Proceed on March 10
Submittals and Permits: The baseline schedule has been reviewed and comments were provided to the contractor. Received
Long Island Well Permit (LIWP) from NYSDEC. Permit allows
drilling of dewatering wells. Received Lead Abatement Permit
from LIRR. Received Amtrak Temporary Access Permit. Continued submitting subcontractors and vendors for MTA approval.
Submitted Construction Work Plans (CWP) and Safety Work
Plans (SWP) for lead abatement of existing catenary structures
and signal bridges in preparation for demolition.
Mobilization: Commenced coordination with Amtrak to mobilize
to yard and trailers previously occupied by GTF under contract

Description: Construction of jacked shield tunnel, ap-

proach structures, direct fixation track and electrical systems for the Westbound Bypass Structure to be located
along the mainline tracks at F Interlocking and Harold
Interlocking. Contract work also includes the installation of
catenary and signal bridges along the Westbound Bypass
alignment.

CQ031. Established seismic inspection procedures for fire line.


Survey: Commenced locating and survey of as-built areas for
future Westbound Bypass west approach location, monitoring
wells, and piezometers. Surveyed existing catenary structures to
be demolished.
Jacked Tunnel Shield Design: The Contractor elected to pursue
the Jacked Shield Tunnel method as shown in the CH057A contract to construct the Westbound Bypass Tunnel after concluding
the alternate means and methods they investigated were not
feasible. The CM coordinated design review meetings between
Contractors tunnel shield designers and the GEC to expedite
final approval of the shield design.

CRITICAL ISSUES
Differing Site Condition at Signal Bridge 30: Contractors survey found an existing manhole at the location of Signal Bridge 30 north
foundation. The manhole may impact completion of Signal Bridge 30 which is a requirement for Interim Milestone 1.
MITIGATION
Differing Site Condition at Signal Bridge 30: The GEC has issued revised drawings with a solution for the existing manhole interference at Signal Bridge 30 north foundation. In addition, Interim Milestone 1 for Signal Bridge 24 and 30 will be revised as the date
for Signal Bridge 30 from an overall program perspective has been postponed. The new proposed Interim Milestone date for Signal
Bridge 30 is August 1. The previous need date for both signal bridges was July 14.
COST
No contract mods have been executed and none are included in the EAC. 0.0% of the CH057A current contract value has been invoiced
as of March 2014, down from the 2.4% that was erroneously reported last month. The EAC has not changed since last month.
LOOK AHEAD
Submittals and Permits: Finalize Detailed Cost Breakdown and
the baseline schedule. Engineering submittals for critical contract
scope such as Signal Bridges, Signal Tower 14, Westbound
Bypass Jacked Shield Tunnel, Dewatering System and support of
excavation for Westbound Bypass Approach Structures expected.

Amtrak yard near the Q-Tip currently occupied by Perini under


contract CQ032 to setup water treatment facility. Mobilize for
abatement and demolition of existing Signal Bridge 846E (signal
bridge 12) and catenary structures.

Jacked Tunnel Shield Design: Finalize Jacked Tunnel Shield


design and jacking sequence

Demolition of Existing Catenary Structures and Signal Bridges:


Commence abatement of Signal Bridge 12, and existing catenary
structures prior to demolition

Mobilization and Survey: Mobilize to Amtrak yard west of 39th St.


Bridge to be used as a storage yard. Mobilize to a portion of the

Fabrication: Commence fabrication of catenary structures, Signal


Tower 14, Signal Bridge 13

MTA/LIRR East Side Access

(PM 3.5.108757)

82

SAFETY
Reviewed Safe Work Plans

Safety StatisticsLTIR 0.00, B.L.S. (Bureau


of Labor Standards) 1.70

Mobilization continues and prepping for upcoming


work

LTIR represents incidents that occurred for


every 200,000 manhours
worked.

CH057A PROGRESS CURVE


The preliminary schedule is currently under review

MILESTONES

Current

Actual/

Baseline

Forecast

Notice to Proceed

12/2/13

12/2/13

Complete Signal Bridge 24 & 30

7/14/14

8/13/14

Complete Signal Bridge 16

8/15/14

8/10/14

Substantial Completion

1/31/16

2/25/16

Final Completion

4/30/16

5/25/16

2012

2013

2014

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

2015

2016

Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1

Q2 Q3 Q4 Q1 Q2 Q3 Q4

(0 days)

(+30 days)
(-5 days)

(+25 days)

Current Baseline

2017

Actual/Forecast

(+25 days)

FINANCIAL SUMMARY
Budget
$130,130,000

$12,210,000

Contract
(Award/Mods)
$104,300,00

Invoiced
$0

$1,000,000

$117,920,000

$103,300,000

$0

Paid to Date
$0

$0

EAC
$104,300,000

$1,000,000

$103,300,000

ESA

Regional Investment

Modifications

EACs do not include possible contract mods and future claims.

MTA/LIRR East Side Access

(PM 3.5.108757)

83

SITE MAP

MTA/LIRR East Side Access

(PM 3.5.108757)

84