STATEMENT
For
ERECTION OF
STEEL PLATFORM
UHV PLANT
PROJECT
: 18 March 2015
Page
: 1 of 57
METHOD STATEMENT
FOR
ERECTION OF STEEL PLATFORM
(CHRISTIANI & NIELSEN (THAI) PCL.)
(Doc. No. : 130087-MS-C-330)
Contract No.
Project Title
Location
Owner
Contractor
:
:
:
:
:
130087
UHV Plant Project
Rayong in Thailand
IRPC Public Company Limited
Consortium of GS E&C and SK E&C
26 May 2015
CNT
REV
DATE
DESCRIPTION
PRPD
B.S. Lee
REVD
REVD
(QC)
(HSE)
K.S. Song
APPD(SM)
NOTES:
a)
b)
c)
Revision bar (vertical line) would be placed in the left or right hand margin to indicate where the
change has been made.
PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPD = Approved by
In case of conflict between any requirements stipulated in this document with the contractual
requirements, the contractual requirements shall prevail.
UHV PLANT
PROJECT
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
TABLE OF CONTENTS
1.0
SCOPE
2.0
REFERENCES
3.0
RESPONSIBILITIES
4.0
5.0
WORKING PROCEDURE
6.0
HSC PLAN
7.0
INSPECTION PROCEDURE
8.0
ATTACHMENT
#1: JSA
#2: Catalog
: 18 March 2015
Page
: 2 of 57
UHV PLANT
PROJECT
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
: 18 March 2015
Page
: 3 of 57
1.0 SCOPE
This document describes the detailed method of Erection of Steel Platform to be installed at
78T002 API Pond in IRPC UHV Project to ensure that the work is done in line with HSE and
good engineering practices and is compliance with project specification engineering standard
practices, nation & local codes. The details of the procedures may be modified base upon
actual site requirement
2.0 REFERENCES
UHV- SP- C - 001
UHV- SP- C - 009
3.0 RESPONSIBILITIES
3.1 Project Engineer
3.1.1 Assisting site manager to prepare construction plan and performing construction
works.
3.1.2 Supervising the execution of civil construction activities to meet the safety and
quality requirement of the contract and project specification.
3.1.3 Preparation and mobilization of construction facilities and construction
equipment / tools for civil construction works.
3.1.4 Planning and assignment to manpower for civil construction works.
3.1.5 Supervising Civil Construction Engineers.
3.2 Site Engineer
3.2.1 Monitors the daily operations involved with work planned safety, quality and
progress control for the civil construction works as directed by the site
Construction Manager and Civil Construction Superintendent.
3.2.2 Assisting to the development of civil construction procedures.
3.2.3 Distribution and control of all civil construction drawings for assigned his
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
UHV PLANT
PROJECT
: 18 March 2015
Page
: 4 of 57
charges subcontractors.
3.2.5 Supervising construction inspection and test reports to perform during the
construction period.
3.2.6 Providing solutions and suggestions to resolve discrepancy items between
engineering drawings and field conditions.
3.2.7 To prepare shop drawings and verify quantities of any construction materials
modified.
3.3 QA/QC Engineer
3.3.1 To perform quality inspection as per inspection and testing plan of civil
construction works and summarization / collection of relevant inspection
reports.
3.3.2 Responsible for inspecting construction equipment / tools of civil construction
works for proper working order and calibration.
3.3.3 Verification of all inspection / test reports and measurement records.
3.3.4 Supervision and identification of all construction equipment / tools / products
during construction period.
3.4 Safety officer
3.4.1 Have full familiarity with the Works at all stages to enable advice to be given,
where necessary, to ensure safe work condition and the subsequent prevention
of injury to personnel.
3.4.2 Supervise the training in and correct use of protective clothing and safety
equipment.
3.4.3 Advise management on changes in legislation.
3.4.4 Investigate accidents and dangerous occurrences and recommend means of
preventing repetition.
3.4.5 Carry out frequent site inspections to determine that all Notifications are being
observed.
3.4.6 Check that Welfare facilities are properly provided and maintained.
3.4.7 Ensure that all reports of accidents are made on the prescribed forms and
forwarded to Head Office without delay.
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
UHV PLANT
PROJECT
: 18 March 2015
Page
: 5 of 57
3.4.8 Advise on and assist in the training of employees to promote and maintain
awareness of injury prevention.
3.4.9
2
3
2
2
15
Protective overalls
Good quality gloves, goggles and face mask.
Ventilator fan
UHV PLANT
PROJECT
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
: 18 March 2015
Page
: 6 of 57
UHV PLANT
PROJECT
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
: 18 March 2015
Page
: 7 of 57
METHOD
STATEMENT
For
ERECTION OF
STEEL PLATFORM
UHV PLANT
PROJECT
: 18 March 2015
Page
: 8 of 57
7.2
7.3
Contractor shall notify in writing by using FIN to the O/C for inspection
Subcontractor shall request the daily inspection 24 hours before it starts work.
Maintain close liaison with the Safety Manager.
8.0 ATTACHMENT
#1
#2
JSA
Catalog