Sunteți pe pagina 1din 31

May 2015

EKONS

TAGURU
FOOT BRIDGE L=43m

FOOT BRIDGE

TABLE OF CONTENTS
1.1

INTRODUCTION

1.2

GEOMETRY

1.3

LOAD ANALYSIS

1.3.1

CONSTANT LOAD (DL)

1.3.2

LIVE LOAD (LL)

1.3.3

WIND LOAD (WL)

1.3.4

LOAD COMBINATIONS

1.4

STRUCTURAL DESIGN

1.4.1

DECKING

1.4.2

CROSS BEAMS

1.4.3

SUSPENDERS

1.4.4

MAIN CABLES

1.5

MATERIALS

1.5.1

LIST OF POSITIONS

1.5.2

CONNECTIONS

1.5.3

CONCRETE

1.6

INSTALLATION

10

1.6.1

PHASES

10

1.6.2

FOUNDATION

11

2.

BILL OF QUANTITY

14

3.

DRAWINGS

22

Foot Suspension Bridge L=43m

1.1

INTRODUCTION

The pedestrian suspension bridge is located in Papua New Guinea, Southern Highlands Province, Taguru
Village across Polu River1. The span for pedestrian suspended cable bridge is 43m, divided in 22 parts.
Bridge walkable width is 150 cm.
This project tasks are:
1. To design safe and eyes pleasant foot bridge
2. To adapt (and optimize) installation technology on remote site
3. To estimate material, works and other costs for construction
Type of bridge is suspension bridge, with adjustable cables for tightening.
Bridge is made by timber, strengthen with steel profiles in constructive joints.
Main cables (4 x wire ropes 40mm) are positioned bellow cross beams (240x290mm) and by suspenders
(wire ropes 14mm) are attached to upper cables. Cables are anchored in both river banks into concrete
blocks. Reccomendations is to use the both side adjustable ends, secured and ready for tensioning during
and after bridge assembling.
Structural calculation shown that vertical deformation of bridge, caused by constant load, will be 5 cm.
Recommendation is to tension main cables in positon reduced for above mentioned value.
All positions of key points must be referenced, followed and controlled by surveyor, appropriate equipped
for remote sites.
For measuring of cable strain and for tightening, it must to be ensure appropriate equipment for remote
sites.
Workers safety is the managements critical path activity.
General Contractor or Investor can check, review and improve methodology only if all stakeholders are
agreed before.
Designers recommendations for safe bridge installation are:
1. The Site Specific Safety Plan (SSSP) must be submitted and approved before bridge installation
2. Specialized workers during bridge assembling must be constantly attached to cables with appropriate equipment
3. During first phase (placing cross beams on 2m interval) only 1 worker can be on bridge.
4. Bridge will be constructed from both side, 1 field-left, 1 field-right
5. Prefabricated Floor End Beams (180x200mm) are connecting with Cross beams by bolts, through
earlier prepared holes
6. Diagonals are placing after Floor End Beams. In this phase, to install just 1diagonal and second
one after first tensioning
7. Final position of bridges referenced points, must be synchronized by surveyor and site engineers
during tensioning2
8. Next phase is placing screw through steel profiles and connection Floor End Beams longitudinally
9. In that phase 2 workers can be on bridge on same side.
10. Construction takt is also 1 field left side- 1 field right side
11. Important next phase is placing central floor beams
12. After that phase 4 person can be on bridge3
13. Concrete works must be done 21 days before installation and concrete must be curred by cold
watter. Frequency is depending by temperature and humidity. First 3 day must be more frequently to
avoid the occurence of small cracks4.
14. Into concrete to place flexibe pipe diameter 50mm. After through hardened pipe, pull through cables.
15. Bridge Pylons are made by steel, anchored into concrete bellow.
16. Concrete anchor block overturning check indicate that

Site data about location, geological investigations, contours, water streams, winds velocity was not available during this phase. Factor of safety was multiplied by 2.
2 Deformations are related with cable type and manufacturer specification and certificates
3 Must be recalculated by Designer or Site Engineer
4 If site conditions are extreme, site engineer can adapt concrete technology by adding admixtures. Concrete strength before timber parts installation must be at least 18MPa.
.

Foot Suspension Bridge L=43m

1.2

GEOMETRY

Where:

L = span in meters (43m)


Lb = Backstay length (3m)
hsag = cable sag in meters (2m)
ho.b. = height overburden (3m)

Foot Suspension Bridge L=43m

1.3

LOAD ANALYSIS
Bridges structural model was checked manually in first iteration, later was made 3D model
by software Autodesk Robot Structural.

1.3.1

CONSTANT LOAD (DL)


POSITION

POSITION

ASSUMPTIONS/CONVERSIONS

LOADING

No.

NAME

1.

DECKING

TIMBER BEAM: LxBxH = 3m x 0.18m x 0.1m

CL1=WxBxH

Width 1.5m

Width: 8pcs x 0.18m = 1.44m

=9.5x0.18x0.1

WEIGHT (W): 9.5KN/m


2.

CROSS BEAMS
Length 2.0m

TIMBER BEAM: LxBxH = 2m x 0.2m x 0.2m


WEIGHT (W): 9.5KN/m

=0.17 KN/m
CL2= WxBxH
=9.5x0.2x0.2
=0.38 KN/m

Tributary area (decking): L=3m, H=0.1m

CL21= WxLxH
=9.5x3.0x0.1
=2.85 KN/m

3.

SUSPENDERS

Cable: 7/19 Wire Rope

insignificant

Cable: 6/19 seale IWRC Wire Rope

0.64 KN/m

(WIRE ROPE)
4.

MAIN CABLE

W = 6.4kg/m = 0.64 KN/m

1.3.2

LIVE LOAD (LL)


Pedestrian bridge live load: LL1=4KN/m2 (Case Symmetric)
Pedestrian bridge live load: LL2=4KN/m2 (Case Asymmetric on longitudinal direction)

1.3.3
1.3.4

WIND LOAD (WL)


WL= 1.5 KN/m
LOAD COMBINATIONS

Comb1: 1,4DL + 1,6 LL (manual calculation)


Software calculation

Foot Suspension Bridge L=43m

1.4

STRUCTURAL DESIGN

1.4.1

DECKING

L=2m, Plank (beam): L x B x H = 2m x 18 cm x 10cm


Constant Load (self weight): CL1=WxBxH = 9.5x0.18x0.1 = 0.17 KN/m
Live Load: LL=4KN/m2 * 0.18m = 0.72K/m
Total load: 1.4*CL + 1.6*LL = 1.4*0.17 + 1.6*0.72 = 0.24 + 1.15 = 1.39 KN/m
Moments: Mmax=(q*L2)/8=1,39*22/8=0,69 KNm

Section modulus: W=18x102/6 =300cm3


= Mmax/W=0,69*105 / 300=231 N/cm3 allowable=1000 N/cm3
1.4.2

CROSS BEAMS

Constant Load (selfweight): CL1 = WxBxH = 9.5x0.24x0.28 = 0.64 KN/m


Constant Load (decking):
CL2 = WxLxH = 9.5x2.0x0.1 = 1.90 KN/m
Live Load: LL=4KN/m2:
LL1 = LxLL1 = 2.0x4.0= 8.00KN/m
Total load: 1.4*CL + 1.6*LL = 1.4*(0.64+1.90) + 1.6*8.0 = 3.55 + 12.8 = 16.35 KN/m
Reaction in beam supports: A = B = 16.35 KN
Moment in middle: Mmax=(q*L2)/8=16,35*22/8=8,18 KNm
Section modulus: W=24x282/6 =3136cm3

= Mmax/W=8.18*105 / 3136 = 260.78 N/cm3 allowable=1000 N/cm3


1.4.3

SUSPENDERS
Vertical suspenders transfer the loads from the deck to upper main cables at 2 meter intervals..
Each suspender must be able to carry 16.35 KN5.

Manufacturer6

As suspender P/N 2637 WR SS 7x19 G304 5.5MM (7/32) is recommended.

5
6

See 1.4.2 beam reactions


http://wirerope.net.au/products/stainless-steel-wire-rope/7x19-g304-wire/

Foot Suspension Bridge L=43m

1.4.4

MAIN CABLES

Calculation of strains in cables was calculated by Autodesk Robot Structural Professional.


Combination of load is described in 1.3.4
Extreme possible tension force in cable is 405.79KN

As main cable7 P/N TBA WR GALV 6x36 IWRC 28MM is recommended.

http://wirerope.net.au/products/galvanized-wire-rope/wire-rope-6x36-iwrc/

1.5

MATERIALS

1.5.1

LIST OF POSITIONS

1. Cables
1.1. Main Cables (MC) (4pcs * 53m)
1.2. Suspenders (S) (42pcs * 1.3m)
2. Cross Beams (CB) (23 pcs * 2m)
3. Floor End Beams (FEB) (40pcs * 2m)
4. Floor Beam (FB) (154pcs x 2m)
5. Diagonals (D) (44pcs * 2.5m)
6. Wire fence 2pcs * 1.2m * 45m

Type

Number

Length
(m)

Unit weight
(kG/m)

Bar weight
(kG)

Painting
area
(m2)

Total weight
(kG)

TIMBER
Cross Beam 24x29

1.52

20.18

30.68

123

6.44

Cross Beam 24x29

23

20.18

40.37

928

48.76

Diagonals 10x18

2.15

8.35

17.96

72

5.85

Diagonals 10x18

24

2.52

8.35

21.05

505

41.13

Diagonals 10x18

16

2.53

8.35

21.13

338

27.53

Floor Beams 18x10

14

1.52

5.22

7.93

111

11.92

Floor Beams 18x10

84

2.01

5.22

10.49

881

94.55

Floor Beams 18x10

56

2.02

5.22

10.54

590

63.35

Floor Beams 18x20

24

2.01

13.57

27.28

655

42.45

Floor Beams 18x20

16

2.02

13.57

27.42

439

28.44

Total per sections


Cross Beam 24x29

27

52.08

20.18

1051.18

1051

55.2

Diagonals 10x18

44

109.56

8.35

915.05

915

74.5

Floor Beams 18x10

154

303.24

5.22

1582.91

1583

169.81

Floor Beams 18x20

40

80.56

13.57

1093.36

1093

70.89

4643

370.41

Total
Steel

Total length (m)

Cable

1.52

12.16

15

120

1.53

Cable

1.85

1.85

18.26

18

0.23

Cable

1.87

1.87

18.45

18

0.23

Cable

48

2.01

96.48

19.84

952

12.12

Cable

30

2.02

60.6

19.93

598

7.62

Cable

2.03

4.06

20.03

40

0.51

Cable

2.81

2.81

27.73

28

0.35

Cable

2.82

2.82

27.83

28

0.35

0.89

1.04

0.09

Total Cable

182.65

Suspender

Suspender

40

1.2

0.89

1.07

43

1.81

Cable

92

182.65

9.87

1802.42

1802

22.95

Suspender

42

50.34

0.89

44.71

45

1.9

1847

24.85

Total per sections

Total

Foot Suspension Bridge L=43m

1.5.2

CONNECTIONS

Typical assembly connection types:


1. Cable Suspender (C-S) (42pcs)
2. Cable Cross Beam (C CB) (46pcs)
3. Cross Beam Suspenders (CB S) (42pcs)
4. Cross Beam Diagonals (CB D) (88pcs)
5. Cross Beam Floor End Beam (CB FEB)
6. Cross Beam - Floor Beam (CB FB) (308pcs)
7. Diagonals Diagonals Floor Beam (D-D-FB) (22pcs)
8. Anchor Blocks Cables (AB C) (4pcs)
9. Column Cables ( C-C) (4pcs)

Foot Suspension Bridge L=43m

1.5.3

CONCRETE

1. Continuous footing bellow pylons1 T120/50x130x60cm, A=1.05m2, L=4m


(2pcs).V=4.2x2=8.4m3
2. Concrete block, Th=3m, L=3m, B=4m (2pcs)..V=36x2=72 m3
3. Access slab, Th=1.05m, L=3m, B=0.9m (2pcs)...V=2.84x2=5.68 m3
4. Foundation will be detail designed after site inspection
Total volume of concrete: 86.08 m3.
Reinforcement quantity2: assumption 40 kg per 1 m3 of concrete..3.4 tones

Refer to 1.6.2
Since this is massive anchor block for, acting as counterweight reinforcement is necessary in continuous footing
and in some places within concrete block.
2

1.6

INSTALLATION

1.6.1

PHASES

10

1.6.2

FOUNDATION

Dead Load

Combinations envelope

Live Load
Each of 4 fictive points (foundation) must accept following maximum forces:
1. Pylons
a. FmaxX = 310.50KN
b. FmaxZ = 247.73KN
2. Anchor Blocks
a. FmaxX = 250.53KN
b. FmaxZ = 133.60KN
Horizontal forces, bellow pylons, will be accepted by
horizontal ground beam connected to anchor blocks.
Thus, foundation bellow pylons will be dimensioned
according vertical forces and anchor blocks loaded
with additional horizontal forces.

Dimensioning of footing bellow pylon1


FmaxZ = 247.73KN
Allowable bearing capacity: 150 KN/m2
Area of footing: 247.73/150 = 1.65m2
BxL= 1.2 x 1.5m
Since distance between pylons is 2m, for foundation type is recommended to use continuous footing L=3m, width
B=1.2m.

Allowable bearing capacity must be checked by geomechanical surveyer


11

Dimensioning of anchor block1


FmaxX = 250.53KN+247.73KN=498.26KN
FmaxZ = -133.60KN
Assumptions:
Weight of anchor block (Wb): 2*2*2=8m3 * 25KN/m3 = 200KN
Uplift check: Wb/FmaxZ = 200/133.6=1.49OK
Overturning check: Wb/FmaxX = 200/498.26KN = 0.4..NOT OK
Iteration 2: Weight of anchor block (Wb): 2*4*3=24m3 * 25KN/m3 = 675KN
Overturning check: Wb/FmaxX = 675/498.26KN = 1.35..OK2
Gravity anchor block must provide counterweight safety and must ensure stability against overturning of structure, caused by large horizontal forces. Therefore, dimension of concrete block 2*4*3m is recommended as anchor block. Since, this foot bridge has 2 anchor block, total weight must be doubled and concrete block is
4*4*3m.

Horizontal forces are changing depend on footings elevation and before construction must be recalculated after
on-site Survey
2 Neglected passive soil pressure, upplift force, active soil pressure, underground water, pylons unfavorable
moment
12

13

2.

BILL OF QUANTITY

14

Bill of Quantities: Foot Bridge, Length 43m


1

General

Pos.
I

I.2
I.3
I.4
I.5

I.6
I.7

I.8

I.9

I.10

I.11
I.12
I.13
I.14

Unit

Qty.

lumpsum

1.00

lumpsum

1.00

lumpsum

1.00

lumpsum

1.00

month

1.00

lumpsum

1.00

month

1.00

lumpsum

1.00

month

1.00

lumpsum

1.00

lumpsum

1.00

month

1.00

month

1.00

The Contractor shall enter against each of the following


items the amount he requires, if any. If no rate is set
against an item, then it will be understood that
compliance with such an item is included in the priced
rates in the subsequent bills.
Provision of two (2) sets of all technical documentation
and standards as per specification
Costs for Permits and Licenses as per specification
Costs for Design Activities and Changes by the
Contractor as per specification
Contractor's mobilization at site and demobilization from
the site, comprising all installations, offices, stores,
procurement and housing of labour
Provide maintenance of the site, including supply of
portable electricity, water, telephone and security as per
specification
Provide, erect and maintain project sign boards (2) as
per specification
Provision and maintenance of Temporary Installations
and Services (temporary buildings, fencing, barricades,
traffic diversions, signboards, electricity, lighting, water
supply, sanitation, temp. access roads, drainage of
sites, deviation of existing services, as per specification
Establish on Site the temporary office/ hut for the
Engineer and Employer (incl, equipment) during
mobilization and remove from Site on demobilization,as
per specification
Provide maintenance of the Engineer's office as
specified, including supply of electricity, water,
telephone and guarding
Provision and maintenance of Surveying Equipment,
Tools and Safety Equipment for the Engineer as per
specification
Provision of Supporting Staff for the Engineer as per
specification
Provision for site tests (testing of concrete, materials
and soil), as per specification
Arrange for Site safety, personal protective equipment
for workers and complete with all adequate first aid
equipment as per specification
Provisions for activities related to controll points, survey
and setting out of the works, as per sepcification

lumpsum

1.00

I.16

Preparation and provision of Working Drawings as


specified.

lumpsum

1.00

I.17

Start up of operation and commissioning of all systems

lumpsum

1.00

lumpsum

1.00

lumpsum

1.00

lumpsum

1.00

lumpsum

1.00

I.19
I.20
I.21

Unit price
$

Total
$

GENERAL ITEMS

I.15

I.18

Taguru Bridge 43m

Description

Preparation and provision of As Built Drawings and AsBuilt Design documents as specified.
Provision of Reports and Records (photographic
records, site records, progress reports) as per
specification
Clearance of site, including payments for any
environmental demage and project closeout
Provision of four (4) sets of O&M manuals (1x English
and 3x Tok Pisin as per specification
Subtotal GENERAL ITEMS

page 1 of 11

II

OTHER
The Contractor shall insert below all other items which
he considers that costs shall be incurred under the
Contract and for which separate payment should be
made, insertion of costs against these items is not
obligatory and any costs not covered shall be deemed
included elsewhere:

II.1
II.2
II.3
II.4
II.5
II.6
II.7
II.8
II.9
II.10
Subtotal OTHER

I
II

RECAPITULATION
GENERAL ITEMS
OTHER

Total General

2
Pos.
I
I.1
I.2

Provisional
Description
PROVISIONAL ITEMS
Additional tests and samples ordered by the Engineer
Overheads and profit on provisional sum, % as per
Appendix to Tender
Subtotal PROVISIONAL ITEMS:

Unit

Qtty.

lumpsum

10.00

10.00

Unit price
$

Total
$

RECAPITULATION

Total Provisional

Taguru Bridge 43m

page 2 of 11

BRIDGE 43, Taguru


Pos.

I
I.A

I.A.1

Description

Unit

Qtty.

Unit price
$

Total $

PREPARATORY WORKS
SETTING UP CONSTRUCTION SITE
Preparation of site: clearing/grabbing up terrain
(removal of bushes and low plants incl. levelling of
terrain), removal of harvest, fruit or forest trees with
compensation to the owners. Relocation of underground
and above-ground installations (if required). Lump sum.

lumpsum
1.00

I.B
I.B.1

I.B.2
I.C
I.C.1

II
II.A

II.A.1

II.A.2

II.A.3

II.A.4

II.B

II.B.1

II.B.2

Taguru Bridge 43m

GEODETIC SETTING OUT


Surveying/marking of fixed points, terrain, alignment,
frontage line, construction parcel and size of facility with
setting securing with stakes. Calculation per m1 of
bridge.
Surveying/marking of all alignments, incl. required
staking out and securing marked points. Calculation per
m1.
SITE TRAFFIC/TRANSPORT LINES
Construction of temporary access crossing or bridge.
Calculation per m.
Subtotal PREPARATORY WORKS

m1

43.00

m1

43.00

200.00

m3

196.00

m2

52.00

m3

13.00

m3

13.00

m3

31.20

m3

5.20

EARTH WORKS
FOUNDATIONS
Removing humus layer of 25cm with placing removed
material outside foundation pit; humus will be used for
resoiling of storage tank embankment slopes. Removed
humus/overburden will be transported up to 50 m from
foundation pit. Calculation per m3. 28*3.5=98m3 x 2pcs
Levelling of foundation pit bottom with rolling up to the
compactness MS 25. Calculation per m2. 4*6.5=26m2
x 2pcs
Procurement and spreading gravel below foundaments.
Tipping of gravel sub-base is to be done in layers;
compacting and fine levelling with height tolerance +/- 1
cm, up to compactness MS 45. Calculation per m3 of
compacted gravel. 26*0.25=6.5m3 x 2pcs
Tipping in layers of 20cm each and compacting of
naturally wet fine soil around facility and retaining walls.
Soil from excavation (IV category) is transported from
temporary site depony or from borrow area up to 10km
away. Compacting is to be carried out using
corresponding vibro-devices (vibro-plates and
hammers). Calculation per m3 of made and compacted
soil measured at cross-section.
SURFACE AND GROUND WATER DRAINAGE
SYSTEM
Mechanical excavation of trench for laying drainage
pipeline DN100 in the soil of I to V category; trench
width 60cm, average depth 100cm. Calculation per m3
of excavated natural ground. 0.6*1.0*26=15.6m3
Procurement, spreading and levelling sand bedding for
pipe ( 10cm below pipe). Calculation per m3 of built in
sand. 26*0.1=2.6m3

page 3 of 11

II.B.3

II.B.4

II.B.5

III
III.A

III.A.1

III.B
III.B.1

III.B.2

III.B.3
III.C
III.C.1

Taguru Bridge 43m

Backfilling of concrete pipes up to 15 cm above pipe


crown using fine material from excavation with both side
compacting. Calculation per m3.
226*(1*0.5-0.096)=91.3m4
Procurement and building in drainage gravel size 1632mm around drainage PVC piping DN 110mm to be
used for drainage around foundation. Complete filter fill
is to be covered with "geotextil", fully according to the
detail from graphical attachment. Calculation per m3 of
built in drainage material.
26*0.5=13m3
Backfilling of remaining trench part using soil from
excavation; backfilling is done in layers of h=30cm with
compacting. Calculation per m3.
26*0.6=15.6m3
Subtotal EARTH WORKS

m3

91.30

m3

26.00

m3

15.60

m2

56.00

m3

8.40

m3

5.68

m3

72.00

kg
kg

2400.00
1200.00

CONCRETE AND REINFORCED-CONCRETE WORKS


CONCRETE WORKS
Making of equalizing bed at foundation pit bottom using
plain concrete grade C 16/20, thickness d=8cm and with
drop of 1%. Calculation per m2 of equalizing bed.
28m2
REINFORCED-CONCRETE WORKS
Concreting of continuous foundation
(T120/50x130x60cm), concrete grade C30/37.
Calculation per m3. A=1.05m2, L=4m
(2pcs).V=4.2x2=8.4m3
Concreting of slab for access to bridge. Calculation per
m3. Th=1.05m, L=3m, B=0.9m
(2pcs)...V=2.84x2=5.68 m3
Concreting of counterweight block using concrete
gradeC30/37. Calculation per m3.
Th=3m, L=3m, B=4m (2pcs)..V=36x2=72 m3
REINFORCING WORKS
Procurement, bending and placing reinforcement
ribbed reinforcement: kg 2400
reinforcement mesh: kg 1200
Subtotal CONCRETE AND REINFORCEDCONCRETE WORKS

page 4 of 11

IV
IV.A

IV.A.1

IV.A.2

IV.A.3

IV.A.4

PREFABRICATION OF PARTS
CARPENTERY WORKS
Prefabrication of cross beams L=2m, BxH=24x29cm.
Volume per beam is 0.14m3 (40.37kg). Price include
only beam preparation. Steel parts, protective painting
and assembling steel and timber in fabric are included
as other BoQ item
psc.

23.00

pcs

40.00

pcs

154.00

pcs

44.00

psc.

92.00

psc.

46.00

psc.

46.00

pcs

4.00

pcs

42.00

pcs

42.00

pcs

42.00

lumpsum

1.00

Prefabrication of floor end beams L=2m, BxH=18x20cm.


Volume per beam is 0.072m3 (27.28kg). Price include
only beam preparation. Steel parts, protective painting
and assembling steel and timber in fabric, are included
as other BoQ item
Prefabrication of floor beams L=2m, BxH=18x10cm.
Volume per beam is 0.036m3 (13.64kg). Price include
only beam preparation. Steel parts, protective painting
and assembling steel and timber in fabric, are included
as other BoQ item
Prefabrication of diagonal beams L=2.5m,
BxH=18x10cm. Volume per beam is 0.045m3
(21.64kg). Price include only beam preparation. Steel
parts, protective painting and assembling steel and
timber in fabric, are included as other BoQ item

IV.B

STEEL WORKS
Prefabrication steel parts and attachment to Cross
Beam
EAP 150x150x10mm, L=450mm, W=9.86kg, side
position 4 pcs per CB
IV.B.1
EAP 150x150x10mm, L=550mm, W=12.07kg, top
position, internal side 2 pcs per CB
EAP 150x150x10mm, L=300mm, W=7.47kg, top
position, external side 2 pcs per CB
Procurement and installation of main cables (type P/N
TBA WR GALV 6x36 IWRC 28MM or equivalent).
Length of cable is 53m. There is foreseen 4 wire rope
IV.B.2
Calculation per piece of mounted cable.

IV.B.3

IV.B.4

Procurement and installation of suspender cables (type


P/N 2637 WR SS 7x19 G304 5.5MM (7/32) or
equivalent). Length of cable is 1.3m. There is foreseen
42 wire ropes. Calculation per piece of mounted cable.
Procurement and installation of connections between
upper cables and susspenders. Detail is per
manufacturer specification. There is foreseen 42 pcs.
Calculation per piece of mounted connection.

IV.B.5

Procurement and installation of connections between


lower cables and susspenders. Detail is per
manufacturer specification. There is foreseen 42 pcs.
Calculation per piece of mounted connection.

IV.B.8

Other connecting material: bolts, screws, nails and


miscellaneous materials for connecting per
specifications

Taguru Bridge 43m

page 5 of 11

IV.C
IV.C.1

IV.C.2

IV.C.3

IV.C.3

IV.C.2

PAINTING WORKS
Coating of Cross Beam's surfaces in two layers using
protective colors. Calculation per m2 of coated surface.
Area 55.2 m2
Coating of Floor End Beam's surfaces in two layers
using protective colors. Calculation per m2 of coated
surface. Area 70.9 m2
Coating of Floor Beam's surfaces in two layers using
protective colors. Calculation per m2 of coated surface.
Area 169.81 m2
Coating of Diagonal Beam's surfaces in two layers using
protective colors. Calculation per m2 of coated surface.
Area 74.5 m2
Corrosion protection using primer and finishing coatings
or plastic coat (as may be required by the Employer) of
all metal parts of steel structure. Lump sum.

m2

55.20

m2

70.90

m2

169.81

m2

74.50

lumpsum
1.00

Subtotal PREFABRICATION OF PARTS


V
V.A

V.A.2

Taguru Bridge 43m

INSTALLATION WORKS
Cable installation
Transportation and tightening of wire ropes. Work
includes 3 tightening and securing ends for jointing.
Minor fittings are included in price. Machines and tools
are also within this item. Include all temporarily cranes
and wire ropes. Calculation per properly placed cable.
Main cable 4 x 53m
Suspenders 42x1.3m
Procurement, transport and installation of stainless steel
fence. Height of fence is 1.2m. Length is 49m x 2pcs
Calculation per mounted fence length in meters.

pcs
pcs

4.00
42.00

m1

78.00

page 6 of 11

V.B

V.B.1

V.C.

V.C.1

Timber parts installation


Transport and installation of timber parts. Calculation
per piece.
Cross beams CB
Floor End Beams FEB
Floor Beam
Diagonal Beam DB
Other installation works
Procurement and installation temperarly supports for
tamperarly wire ropes used for construction site material
transportation.
Calculation lump sum.

pcs
pcs
pcs
pcs

23.00
40.00
154.00
44.00

lumpsum

1.00

lumpsum

1.00

200.00

Subtotal INSTALLATION WORKS


VI
VI.A
VI.A.1
VI.A.2
VI.B
VI.B.1

VII
VII.A
VII.A.
1.a.2.1
VII.A.
1.a.2.2

OTHER WORKS
SITE WORKS
Procurement, transport and installation of safety net.
Calculation lump sum
Making protective site, temporary fence with 190cm
high with wire mesh fill. Calculation per m1 of mounted
fence.
TESTING
Testing of bridge in accordance with the instructions
given within design/technical documentation. Lump
sum.
Subtotal OTHER WORKS

lumpsum

1.00

ELECTRICAL ITEMS
ELECTRICAL INSTALLATIONS
Delivery and installation of lamps complete with
sources rhymes light and accessories for installation:
- 2x36W, FT , 4500oK,
Reflector, 200W, Hal, with IR sensor
movement, IP 65
Subtotal ELECTRICAL WORKS

pcs

20.00

pcs

4.00

RECAPITULATION

Taguru Bridge 43m

I
II

PREPARATORY WORKS
EARTH WORKS

III

CONCRETE AND REINFORCED-CONCRETE WORKS

IV
V
VI
VII

PREFABRICATION WORKS
INSTALLATION WORKS
OTHER WORKS
ELECTRICAL ITEMS

page 7 of 11

3
Pos.
I

I.1
I.2
I.3
I.4
I.5
I.6
I.8
I.9
I.10
I.11
I.12
I.13
I.15
I.17
I.18
I.19
I.20
II

II.1
II.2
II.4
II.5
II.10
II.11
II.12
II.17

Taguru Bridge 43m

Dayworks
Description
LABOR
Rates shall include all taxes, insurance, social costs,
bonus and general allowances
Surveyor
Carpenter
Charge-hand Carpenter
Charge-hand Mason
Civil Engineer
Driver
Electrician
Finishing Mason
Foreman
General Foreman
Labourer (unskilled)
Mason
Plumber
Steel Fixer
Watchman
Welder

PLANT
Rates shall include operator, all operation and
maintenance costs, fuel, oil etc. Only the time the plant
is employed will be paid for.
Compressor (6 m3/min) with 2 breakers
Concrete vibrator engine & poker
Dumper (0.75 m)
Electric welding set including electrodes
Pickup (1 t)
Pickup (5 t)
Plate compactor (3.5 HP)
Tipper lorry (5 t)

Unit

Unit price
$

h
h
h
h
day
h
h
h
h
h
h
h
h
h
h
h

h
h
h
h
h
h
h
h
h

page 8 of 11

III
III.1
III.2
III.3
III.4
III.5
III.6
III.7
III.8
III.9
III.10
III.11

MATERIALS
Aggregate (15 mm)
Aggregate (20 mm)
Aggregate (4 - 8 mm)
Coarse sand for bedding
Concrete blocks 20 x 20 x 40 cm
Concrete C12/15
Concrete C16/20
Concrete C20/25
Concrete C25/30
Concrete C30/37
Demolition, removal and disposal of concrete

m3
m3
m3
m3
m2
m3
m3
m3
m3
m3
m3

III.12

Demolition, removal and disposal of brick / stone work

m3

III.13

Epoxy coating

m2

III.14

Filling of depressions or other places and compaction of


fill material in layers including import of suitable material

m3

III.15
III.16
III.17
III.18
III.19
III.20
III.21
III.22

Taguru Bridge 43m

Geotextile for foundations of pipelines and structures


including laying
Portland cement (50 kg/bag)
Reinforcement bars (10 - 20 mm)
Sand for concrete and mortar
Sandy bricks 24 x 12 x 6 cm
Selected backfill material (stonefree)
Shuttering / Formwork
Sulphate resistant cement (50 kg/bag)

m2
bag
t
m3
m2
m3
m2
bag

page 9 of 11

IV

IV.1

Unit Rates for Items of Work


Rates include for all labor, supervision, material,
equipment and transportation costs. Rates include
overhead and profit.
Filling of depressions or other places and compaction of
fill material in layers including import of suitable material

m3

IV.5
IV.6
IV.7
IV.8
IV.9

General, trench and incidental excavation including


removal of excess material, soil cat. 1 to 5, cart away
surplus material
Backfill of trenches and around structures with
excavated material from site
Backfill of trenches and around structures with imported
graded material
Embankments for road works
Preparation of sub-grade
Preparation of Sub-base, 20 cm thick
Preparation of Road base, 20 cm thick
Preparation of Bituminous sealing, 1.5-2 kg/m

IV.10

Preparation of Bituminous wearing course, 10 cm thick

IV.11
IV.12
IV.13
IV.14

IV.18
IV.19

Preparation of Asphalt tack coat, 0.5 kg/m


m2
Preparation of Asphalt surface course, 5 cm thick
m2
Kerbs, laid straight and in curves
m
Preparation of Gabions
m3
Felling of trees (trunk diameter between 0.15m and
0.5m), uprooting, haulage (< 5 km), filling of holes with kom /(pcs.)
approved material and compaction
Excavating and disposal of rock. Rock, Class 6 and 7 to
m3
DIN 18300 as per Specification
Excavation below invert level in unsuitable material and
m3
backfill with suitable material below invert level.
Excavate trial holes as per Specification
m3
Riprap slope protection as per Specification
m2

IV.20

Stone pitching slope protection as per Specification

IV.2
IV.3
IV.4

IV.15
IV.16
IV.17

m3
m3
m3
m3
m2
m2
m2
m2
m2

m2

Subtotal Dayworks

0.00

Note: Total amount of Series 3 (Daywork) of


this Bill of Quantities shall not exceed 5% into
total offered price of ITEMS 1,2 and 3

Taguru Bridge 43m

page 10 of 11

Bill of Quantities
BRIDGE TAGURU 43m

Summary
Description
1
I
II

Subtotal
$

General
GENERAL ITEMS
OTHER

$0.00
0.00
0.00

Provisional

$0.00

2
I

PROVISIONAL ITEMS

3
I
II

PREPARATORY WORKS
EARTH WORKS

III

CONCRETE AND REINFORCED-CONCRETE WORKS 0.00

IV
V
VI
VII

MASONRY WORKS
INSTALLATION WORKS
OTHER WORKS
ELECTRICAL ITEMS

Total
$

0.00
0.00

Bridge 43m, Taguru

$0.00
0.00
0.00

0.00
0.00
0.00
0.00

Dayworks and Contingencies

$0.00

Total BRIDGE TAGURU 43m

$0.00

+ VAT
+ Custom Duties

Taguru Bridge 43m

page 11 of 11

3.

DRAWINGS

22

Elevation 1

Section A - A
+ 3.50

1
+ 2.00

+ 1.75
+ 1.40
+ 1.10

+ 0.95
+ 0.35

Section B - B

+ 0.85

+ 0.65

+ 0.45

+ 0.30

+ 0.20

+ 0.10

+ 0.05

0.00

Section E - E

DRAWING:

1
SCALE:

1:100, 1:50,

FOOT BRIDGE L=43m


LOCATION: Southern Highlands Province
Pangia District Taguru Village Polu River
SIZE

Signature:

Drawn by:

REV

A2
FOR CONSTRUCTION

PROJECT PHASE: CONSTRUCTION DESIGN

Section D - D
2

Section P - P

Section C - C
Detail 4

Detail 2

DRAWING:

2
SCALE:

1:100, 1:50, 1:20

FOOT BRIDGE L=43m


LOCATION: Southern Highlands Province
Pangia District Taguru Village Polu River
SIZE

Signature:

Drawn by:

REV

A2
FOR CONSTRUCTION

PROJECT PHASE: CONSTRUCTION DESIGN

Foundation plan 1

Section G - G

Section H - H

Section I - I

Section J - J

Section K - K

Section L - L

Section M - M

Section N - N

Section O - O

Detail 1

DRAWING:

3
SCALE:

1:100, 1:50, 1:20

FOOT BRIDGE L=43m


LOCATION: Southern Highlands Province
Pangia District Taguru Village Polu River
SIZE

Signature:

Drawn by:

REV

A2
FOR CONSTRUCTION

PROJECT PHASE: CONSTRUCTION DESIGN

S-ar putea să vă placă și