Documente Academic
Documente Profesional
Documente Cultură
Construction site inspections on work by other utilities, such as gas lines, power lines and
telephone lines:
Exposed pipeline protection inspections;
Water pipeline leak and damage inspections;
Leak repairs.
Line patrols:
Pipelines, pipe bridges, easements.
Public notification:
Water shutoff, turbid water occurrences, noise due to construction, construction
schedule plans.
j) Pipe flushing:
Draining turbid water;
Systematically flushing sediment deposits and scale deposits in the distribution
pipes.
Office manager
Assistant manager
Executive engineers
12
Executive officers
Engineers
15
13
14
16
58
Clerical personnel
11
12
12
11
46
Pipe fitters
58
57
56
56
227
Drivers
15
Warehouse personnel
10
Delivery personnel
Trucks
12
Jeeps
1;
Small vans
17
16
16
16
65
Flowmeter
10
15
11
11
47
Transceiver
27
Submergible pump
11
Drain pump
13
Generator
15
15
14
44
27
20
37
15
99
25
70
19
38
152
Pipe cutters
3
Name of Material
Straight pipe
Fitting bend 45
22.5
Collar
Flanged socket
Flanged spigot
Double flanged pipe
Gate valve
Fire hydrant Single-type
Double-type
Flange packing
Rubber gasket
Retainer gland
Bolt and nut
Leak clamp
Split repair sleeve
075mm0350mm
1 each
4 each
4 each
2 each
1 each
1 each
2 each
1 each
1 each
I each
2 each
8 each
8 each
8 sets each
6 each
3 each
0400mm01000mm
2 each
4 each
4 each
4 sets each
2 each
l each
Differences in the mechanical properties of ductile iron pipes and grey cast-iron pipes are
shown in Table 3.1.
Table 3-1 Mechanical properties
min. 420
min. 590
min. 10
Grey cast-iron
pipe
150 - 260
200 - 360
Negligible
15-17 x 104
10-12 x 104
Approx. 20 x 104
max. 230
max. 230
Approx. 140
Steel pipe
min. 400
min. 400
min. 18
Underground pipelines;
Patrols should pay particular attention to trunk pipelines, pipelines where leaks
frequently occur, and pipelines buried along main roads;
Pipe bridges;
Pipeline easements;
Construction sites for other utilities.
10
11
12
Superstructures:
Check water leakage from pipes, air valves and expansion joints.
Check that the structures are not rusted.
Substructures:
Check for settling, sloping, and cracks in the concrete.
Survey whether every anchor bolt is fastened tightly against every concrete base
(whether there is no loose anchor nut).
Survey whether any excessive scouring/corrosion by river water flowing around
abutments and/or piers.
4.2 Handling
Pipe bridges are the only pipeline installations clearly visible to the outside world.
13
Inspection month/day/year
14
15
5 Pipeline easements
Table 3.4 shows the details of tasks for pipeline easements.
Table 3.4 Details of tasks for pipeline easements
Details of tasks
Check whether boundary posts are
damaged, missing, sunken or moved.
Handling
Restore posts to their original condition.
16
Check whether the contractor is confirming the pipe position by excavating to expose
the top of pipes before installing piles or sheet piles.
Check whether there is sufficient distance between the pipes and the piles or sheet
piles (50cm or more as a rule).
Check whether to use manual labourers for excavation when pipe will be exposed.
Check, whether gushing water or sand will flow out from gaps between the sheet piles.
Check whether the road surface behind the sheet pile is not settling.
350mm max.
2.0m max.
400mm min.
1.5m max.
Are steel support beams installed under heavy appurtenances, such as gate and
butterfly valves?
17
Check the spacing between water pipes and other underground pipes:
Locations where water pipes run parallel to other underground pipes.
Nominal diameter
450mm max.
30cm min.
500mm min.
50cm min.
450mm max.
30cm min.
30cm min.
50cm min.
18
19
20
Authorized
water use
3
521,125,829m
(92.04%)
Accounted
water volume
3
491,298,393m
(86.77%)
Unaccounted
water volume
29,827,436m3
(5.27%)
Unauthorized
water use
3
45,085,371m
(7.96%)
Unmetered consumption
3
26,328,821m (4.65%)
Utility water use
3,498,615m3(0.62%)
Selected reduced price
water volume
3
3,788,512m (0.67%)
Amount of leakage,
unexplained water volume
3
41,296,859m (7.29%)
Distributed water: This refers to the total volume of water flow (transit volume) at
the starting point of distributed pipelines. The starting point of distributed pipelines
refers to the point at which distributed pipelines branch off from the outlet of a
distribution reservoir, a distribution pump station, or from transmission pipelines. In
order to measure distributed water volume, a flowmeter must be installed at the
starting point.
Authorized water use: This refers to the water volume which provides income and
the water volume authorized for use in the water supply business.
Account water volume: This refers to the water volume that provides income from
water rates or from other public accounts.
Water volume charged for water rates: This refers to the water volume based on
water rate collection. Where a meter is installed on the service line (meterage
connection), it refers to the actual metered volume of water used, but where no meter
is installed on the service line (flat rate connection), it refers to the volume obtained by
multiplying the basic water consumption by the number of taps or users.
Others: This refers to the water volume that provides income from other public
accounts, such as water for public parks, water for public restrooms and fire-fighting
water.
The water volumes described above must be accurately obtained from reports received from
affiliated companies.
Unaccounted water: This refers to water volumes that do not provide income for
21
consumption.
Meters in general use have an appropriate or proper flow rate range, depending on the type of
meter, because of their mechanisms. Outside that range we cannot expect an accurate flow
rate and the difference grows between the actual flow rate through the meter and the measured
flow rate. In such circumstances, the measured flow rate is usually lower than the actual flow
rate. This difference is the unmetered consumption, and is characteristic of each meter, so it
differs according to the type of meter, the pipe diameter, and the age of the meter.
Selecting the proper meter diameter according to actual flow rate is crucial, and the meter
must be installed according to standard installation procedures. Use of meters where either of
the above was not done correctly aggravates unmetered consumption.
Since it is impossible to actually measure unmetered consumption for every meter installed,
generally some meters are selected at random and their unmetered consumption is measured.
Utility water use: This refers to the water volume used in the maintenance activities
required for distribution facilities, such as water for leakage control work as well as
water for flushing distribution and service lines.
Unauthorized water volume: This refers to any water volume not authorized for use.
Selected reduced price water volume: This refers to the amount of water released
because of turbidity, repairs or other reasons, and targeted for reduced pricing by an
adjustment in water rate charging.
Leakage: This refers to the amount of water that leaks from service lines upstream
from the meter and from distribution pipelines downstream from the flowmeter.
Unexplained water volume: This refers to the remainder after subtracting the sum of
the above items from the distributed water volume. When the ratio of individual water
volume types to the distributed water volume is expressed as a percentage (%), we get
the following:
Authorized rate (%) = authorized water volume/distributed water volume x 100
Unauthorized rate (%) = unauthorized water volume/distributed water volume x 100
Account rate (%) = account water volume/distributed water volume x 100
Leak rate (%) = leakage/distributed water volume x 100
reservoir to the value measured by the flowmeter in order to compensate for the
flowmeter error.
Calculation error for the water volume for flat rate connection: It is desirable to
shift flat rate connections to meterage connections by installing a meter. In Osaka City,
all service connections are meterage connections.
Recognized error in water volume for public use: Meters should be installed for
water used in public facilities, such as public parks and public restrooms. It is also
important to set a calculated standard to get a precise understanding of the amount of
water used for fire fighting. In Osaka City, flowmeters are being installed in all firefighting vehicles, and in all public parks and public restrooms.
Recognized error in utility water use: With water used for business, such as flushing
turbid water and cleaning pipes, closely following water pipeline construction,
standards must be prepared for the calculation method as well as the confirmation
method for on-site water use volumes in order to obtain accurate data.
Recognized error in settled reduced price water volume: When damage or other
problems with a water meter make it impossible to measure the consumption, the use
conditions must be surveyed, and as accurate a water volume as possible must be
estimated.
Unexplained water volume: During meter inspections, bill collections and leakage
control work, every effort must be made to find and prevent illegal service
connections, such as service lines that are connected without permission as well as
unlawfully laid service lines that do not run through a meter.
2 Leakage control
2.1 Proposing implementation plans
2.1.1 Selecting work or implementation areas
The first step in an implementation plan is to select work or implementation areas on a
priority basis. In urbanized areas, underground leaks generally tend to occur most often in the
following locations:
Paved roadways;
Areas with sewer lines installed;
Places where the underground water level is high;
Places where the ground is mostly sand or gravel.
23
Areas with frequent above-ground leaks also tend to have frequent underground leaks.
Therefore, the following points must be considered by individual areas when selecting a work
or implementation site.
24
Figure 3.7 Cost of leakage control and the cost of leak losses
The following is a calculation method for determining the most economical work cycle.
First, the relationship between the work cycle and the cost of leakage control is expressed as
follows:
X:
L:
n:
A:
A1:
A2:
a:
Cost of leakage control (yen) in one year when the work cycle is n (years).
Length of distribution pipes (km) targeted in the leakage control.
Work cycle (years).
Cost of leakage control per kilometre of pipe (yen/km).
Cost of leak surveys per kilometre of pipe (yen/km).
Cost of leak repairs per kilometre of pipe (yen/km).
Cost of repairs for the number of new leak locations generated in one year per
kilometre of pipe (yen/km).
Next, the relationship between the work cycle and the cost of leak losses is expressed as
follows:
Q:
S:
Cost of leak losses (yen) in one year when the work cycle is n.
Unit cost of leakage (yen/m3).
25
q:
r:
Leakage per kilometre of pipe that remains even after leak prevention work
(m3/day/km).
Newly generated leakage in one year per kilometre of pipe (m3/day/km).
The work cycle obtained from the above calculations comprises a full round to each
successive work area, but the use of the equations is strictly limited to leakage control work
targeting naturally increasing leakage.
Individual figures used in the equations may vary tremendously depending on conditions, so it
is difficult to rely on the accuracy of the calculated results. Because of this, setting the
average work cycle within four to five years, or two years particularly in critical districts, is
highly recommended.
Leaks cause costs (required expenditures) and effects (economic effects).
2.2 Work procedure for leakage control
The work procedures for leakage control are as follows:
27
29
Figure 3.10 Opening and closing the curb stops of large-volume users
2.2.3.3 Leakage conversion for water pressure
The results obtained by measuring leakage are actually leakage in terms of water pressure at
the time of measurement. Since water pressure varies with the season and time of day,
estimating the actual leakage involves surveying the average water pressure in the area being
measured, and then converting the leakage corresponding to that pressure. Normally measured
leakage is collected, and is treated as a statistical volume, so if an appropriate standard water
pressure is set, the leakage is converted in terms of the standard water pressure, and is written
down with the leakage at the time of measurement. This information can then serve as data
that is both reproducible and universal.
In Osaka City, the standard water pressure is set at 2.0kg/cm2. The following equation is used
to convert leakage for water pressure:
Q0:
Q:
P0:
P:
The current status of the leak determines which of these two figures will be used.
2.2.4 Detecting leak locations
The detection of leak locations involves primarily placing a sound-listening stick in direct
contact with objects, such as sluice valves, fire hydrants, air valves, curb stops and meters.
Check for leaks by touching the other side of the listening stick to your ear to discern leak
noise from the complex range of noises generated above and under the ground. This basic
method has not changed in the years since leak detections were first instituted, and it is still
used today to detect leak locations. The detection does require a certain amount of training.
As far as actual leak noise is concerned, outflowing noise that scrapes against pipe walls when
water is flowing out from pipes, or impact noise that occurs when water strikes various soils
surrounding the pipe, are intricately formed and reach the ground level by propagating
through a medium, such as earth and sand. The frequency of the noise varies widely
depending on the conditions, such as peripheral soil, pavement types, piping materials and the
ground's ability to cut off water. Non-metallic pipes in particular are not as good at
propagating leak noise as metallic pipes, so such pipes do not facilitate detection of leak
locations with an acoustic leak detector.
In addition to the noises above, flowing water noise in pipes, traffic noise and other noises,
such as vibrations, that are similar to leak noise are constantly present and often hinder
listening. Depending on the circumstances, conducting detection at night may be more
effective in areas where traffic and urban noise hinder acoustic detection.
The detection of leaking water entails attentiveness and a desire to succeed.
31
Figure 3.12 Acoustic detection for leak locating with the listening stick
32
Acoustic characteristics of leak noise: Table 3.8 shows the general relationship of
leak noise categories that can be heard.
Table 3.8 The relationship of high- and low-pitch leak noise to various conditions
High-pitched noise
Low-pitched noise
Short distance
Long distance
False leak noise: The problem with detecting leaks using the acoustic detection
method is that there are false sounds, such as noise and extraneous sounds that closely
resemble leak noise. In terms of how noise is generated, false leak noise is
continuously generated by a variety of noise sources, such as water flowing through
pipes, tap water use, circuit noise inducted from power cables, exciter frequency noise
constantly generated by electric transformers and fluorescent lights, motor noise and
wind noise if the wind speed is 4 metres per second or faster. When these types of
noises are propagated through the air and ground, there is a real danger that they will
be mistaken for leak noise. This is why it is so important to get a good understanding
beforehand of the characteristics of the noises that closely resemble leak noise:
The sound of flowing water in pipes. The scraping sound generated when
flowing water passes through pipes or passes around obstacles in the gate valve
is propagated through water and pipe walls as a vibrational sound. When a gate
valve is not fully opened, the scraping sound of flowing water can in no way
be distinguished from leak noise. These scraping sounds are a hindrance to
acoustic leak detection.
Circuit noise, such as power cables. Power cables laid underground,
transformers on poles, street lights and other such equipment generate low33
frequency noise through inductive current and exciter vibrations, which mean
that special care must be taken when listening anywhere near such facilities.
Water tap noise. Water tap noise is generated when large volumes of water
are in use. Special care must be taken here because it is quite easy to
mistake this sound for leak noise when acoustic leak detection is
conducted on pipelines. The sound of water tap use can be distinguished
by closing and opening the curb stop.
Flowing sewage and dripping noise in manholes. Flowing sewage and dripping
noise in manholes sound very much like leak noise, but the dripping sound
characteristic of surface water as well as a heavy reverberating noise can be
faintly heard. Special care must be taken here when conducting acoustic leak
detection.
Traffic noise. Traffic noise is transitory and the volume of the noise varies
irregularly, so this type of noise is quite easy to distinguish. However, the
scraping sound of tyres at least 60 metres away can easily be mistaken for leak
noise, so special care should be taken here in acoustic leak detection.
Wind shear noise. A low-frequency wind shear noise is generated if the wind is
blowing during acoustic leak detection, and this may well be mistaken for leak
noise. If the wind speed is 46 metres per second (can be felt on the skin),
wind shear noise becomes continuous, and sounds most like leak noise, so it is
the most difficult to distinguish. At wind speeds higher than those listed above,
leak noise cannot be heard at all.
Urban noise. Urban noise is a combination of various noises, such as wind,
building cooling and heating equipment as well as traffic, which forms in the
valleys created by tall buildings. The frequency components of this noise cover
a broad spectrum, and may hinder listening surveys because they include a
frequency component very close to that of leak noise.
Tremendous time and effort are required to detect leaks, so let's try to repair them as
quickly as possible.
34
10
30
50
70
100
150
200
Leakage (ml/min)
1.3
2.3
7.0
11
16
23
31
43
2.2.6 Measuring zone leakage after repair work has been completed
Zone leakage is measured again after detection and repairs on leak locations have been
completed in order to determine the effectiveness of work that has been done.
Here every effort should be made to prevent leaks, but setting zero as the goal for leakage in
actual works requires significant expenditures and labour, and so is not very economical.
There are times when a certain amount of leakage is unavoidable in terms of economics and
technology. Here we will talk about the concept of unavoidable leakage as a work target. It is
impossible to set a uniform figure for unavoidable leakage, but generally a standard is set for
the average leak density for all supply areas.
The work procedure is the same as the one for the zone leakage measurements prior to
starting work, and a zone passes if leakage is below the unavoidable leak level. If leakage
exceeds unavoidable leakage, then detect and repair operations are instituted again.
2.2.7 Organization after work has been completed
Work reports are prepared and pipeline drawings as well as appurtenance ledgers are revised
once the leakage control work has been completed. An example of the form used for work
reports is shown in Table 3.10.
35
36
ANNEX III
CHANGE IN LEAKAGE CONTROL MEASURES IN OSAKA
MUNICIPAL WATER WORKS BUREAU
A Leakage control measures taken by Osaka Municipal Water Works Bureau
Figure 3.13 shows the change in leak rate in Osaka City. Before 1944, there was no correct
statistical data concerning leak rate, but the waste-water volume was 25% to 29% of supplied
water volume, meaning that no special measures were taken to control leakage. In 1945,
leakage control measures were taken for the first time because the estimated leak rate had
reached 70% due to war damage. In the early stages, the leak rate dropped rapidly with the
implementation of leakage control measures, but after that it decreased only gradually. At
present, the leak rate is about 7%. In this period, leakage control measures were changed
several times, thereby affecting the leak rate.
Table 3.11 shows the changes in leakage control measures. From 1945 to 1946, temporary
leakage control measures were taken for urgent pipe repairs in heavily damaged areas.
However, from 1947 the focus switched to systematic leakage control. From 1952, the work
area of systematic leakage control was expanded to the entire city and the work began to be
implemented cyclically.
Time
1945
1947
1952
1960
1965
1991
On the other hand, service line improvements were commenced in 1960 and distribution main
improvements were commenced in 19.65, as other preventative measures against leakage. The
combination of systematic leakage control measures and facility improvements were able to
reduce the leak rate to less than 10%. However the low leak rate caused low cost efficiency in
systematic leakage control. Accordingly, systematic leakage control was discontinued in 1991.
B Details of each control measure
1 Temporary leakage control
Table 3.12 shows the temporary measures for leakage control taken from 1945 to 1946. A
special unit was organized and exclusively charged with implementing these measures that
were effective when the leak rate was high. Immediately after the Hanshin Earthquake in
January 1995, temporary leakage control measures were taken in the early stages of the
restoration work. However, as the leak rate decreased to a certain level, the measures became
insufficient and other measures were employed.
3
4
Service line improvements have been implemented since 1960 with the aim of reducing
leakage and maintaining sufficient flow capacity. Service installations are installed at
customers expense and customers are responsible for maintaining service installations.
However, in many cases leaks on service lines leading to meters are left as they are.
Accordingly, Osaka Municipal Waterworks Bureau is improving service lines leading to
meters at the bureau's expense in order to provide comprehensive maintenance of water
supply facilities.
To increase the effects of facility improvements, when a distribution main is improved,
service lines connecting to that distribution main are replaced at the same time. Figure 3.15
shows the change in distribution main length by joint type. Unlined grey cast-iron pipes with
lead joints were used until 1955 in Osaka City. To improve distribution mains, these unlined
lead-joint pipes are being actively replaced or permanently repaired because they corrode
easily and leak more than mechanical joint pipes with internal lining. As a result, the
proportion of lead-joint pipes declined from 63% in 1965 to 13% in 1994.
Figure 3.16 shows the change in service line length by piping materials. The lengths shown in
Figure 3.16 are only the under road section. Lead pipes were the main piping material up to
1956, but the length of lead piping decreased by 39% by 1994. Conversely, the length of PVC
pipes increased to 56% by 1994 with the progress of service line improvements. In addition to
replacement of aged pipes, the following measures were also taken as service line
improvements to facilitate the maintenance of service lines:
Changing service line locations from private land to public roads;
Simplification of complicated multi-parallel service lines;
Changing meter locations from the inside of houses to the outside;
C Discontinuance of systematic leakage control
As a result of the systematic leakage control measures and facility improvements, the leak rate
dropped steadily. However, when the leak rate fell below about 10%, the low leak rate
reduced the efficiency of systematic leakage control. The cost of leakage control has also
exceeded the cost of leak losses prevented by leakage control since 1988.
To make matters worse, decreases in the leak rate and increases in the cost of leakage control
resulted in a longer work cycle for systematic leakage control. If the work cycle gets longer,
some underground leaks appear on the ground surface and are repaired immediately before
the next leakage control work is implemented. This situation reduces the necessity and lowers
the efficiency of systematic leakage control measures. For these reasons, systematic leakage
control measures were discontinued in 1991.
D Future prospects for leakage control
The future prospects for leakage control by Osaka Municipal Waterworks Bureau are as
follows.
1 Distribution main and service line improvements
The first measure is to promote distribution main improvements and service line
improvements as preventative measures for leakage control. Unlined lead-joint pipes and lead
pipes still remain in the city, thus pipe improvements will continue to be implemented in the
future.
39
40
41
42
43
44
Slide1
Slide2
Slide3
Slide4
Slide5
Slide6
45
Slide7
Slide8
1947- 49
1950- 51
1952- 64
1965- 91
Paved Road
Unpaved Road
80
40
20
1
50
20
5
--------
Slide9
Slide10
Slide11
Slide12
46
U n its:m 3 / day/ km
Slide13
Slide14
Slide15
Slide16
Slide17
Slide18
47
Slide19
Slide20
Slide21
Slide22
Slide23
Slide24
48
Slide25
Slide26
Slide27
Slide28
Slide29
Slide30
49
Slide31
Slide32
Slide33
Slide34
Slide35
Slide36
50
Slide37
Slide38
Slide39
Slide40
Slide41
Slide42
51
Slide43
Slide44
Slide45
52