Sunteți pe pagina 1din 108

TOP DRIVE INSTALLATION &

REMOVAL
FS 231

CANDOC_FS 231
TD INSTALLATION & REMOVAL_01

Information in this document is subject to change without notice. No part of this document may be reproduced or transmitted in any form
or by any means, electronic or mechanical, for any purpose, without the express written permission of Canrig Drilling Technology Ltd.
Printed in the United States of America.

Training Department
FS 231
Top Drive Installation and Removal

CANRIG DRILLING TECHNOLOGY LTD

GENERAL
Job Preparation
Commissioning Binder
Review job scope and ask questions. Prepare.

INSTALLATION
Pre Rig-up
Conduct Safety Meetings before each Operation
Advise Rig:
Standpipe has to be extended
Ensure hook is removable
Racking board modifications
Extra drilling line on Drawworks Drum
Block has to come down to floor level

Check:
Do an inventory of parts
Rotary hose on location; unions installed/match
What size elevator links to be used; clamps on hand
Accessories
Drillers Console
Mount in a location that allows a view of the TD when operating
the console

BUW Saver kit


UWCV Auto kit
Floor Stabilizer
Portable
Safety
Initial Installation
Crown Hanger
Standard 2 piece
Clamp
Do NOT weld to Crown

Harpoon
Torque Reaction Beam
Clamp
Turnbuckle

Feeder Breaker
Location SCR preferred

Training Department
FS 231
Top Drive Installation and Removal

CANRIG DRILLING TECHNOLOGY LTD

Top Drive Support Unit (TDSU)


Locate
Make sure it is within reach of cables

Power up
Ensure AC power in is proper phase.

Test: HPU, CIP


Install Grasshopper mount
Raise Grasshopper
HPU bypass procedure

Route cables and hoses


Block Interface
Types
Becket/Bail
Specific to Block Size (350, 500, 650,750)
Use Upper Links to cross over

Shank
Custom

Torque Guide
Preparation to pick up
Racking board
Remove catwalk & ramp
Align & back in truck
Ensure Weight Indicator is installed and working

Attach winch and raise TG to floor


Attach block to raising interface
Pick up torque guide
Latch
Attach torque reaction beam
Tension
Remove raising interface
Swing out service support
Top Drive
Attach Travelling Block
Hoist TD and remove transport pins
Align Top Drive
Hook up blower inlet
Connect Rotary Hose
4 Fig. 1002

Install Bails and Clamps


Hoist Top Drive to check clearances
Run full length of travel

Training Department
FS 231
Top Drive Installation and Removal

CANRIG DRILLING TECHNOLOGY LTD

Check clearance at racking board & crown


Set Crown Saver for top drive interference (as required)

Function test
Install LWCVs and torque properly
Quill connections:
6027: NC50
8035: 6 5/8 REG
1050: 6 5/8 REG
1165: NC61 (3 bore)
1275: 7 5/8 REG (4 bore)

Hurricane Style
Torque Guide
Installation
Install track
Pick up & install skid/TD

Top Drive
Attach Travelling Block
Hoist TD and remove transport pins
Align Top Drive
Hook up blower inlet
Connect Rotary Hose
Hoist TD to check mast clearances
Install Bails and Clamps
Check clearances
Run full length of travel
Check clearance at racking board & crown

Function test
Install LWCVs and torque properly
Rig Down Storm Condition
Install headache rack
Lower top drive to floor and stab
Disconnect blocks
Install Rig-up assembly
Lay down torque guide
Fixed
Crown Attachment
Mast girt attachment
Pads
Turnbuckles

Training Department
FS 231
Top Drive Installation and Removal

CANRIG DRILLING TECHNOLOGY LTD

Alignment
Horizontal
Vertical
Top Drive Installation
Pick up and attach
Alignment
Hook up blower inlet
Connect Rotary Hose
Hoist TD to check mast clearances
Install Bails and Clamps
Check clearances
Run full length of travel
Check clearance at racking board & crown

Function test
Install LWCVs and torque properly

REMOVAL
Portable
Safety
Preparation for Removal
Remove Elevator Links
Remove LWCVs
Top Drive Positioning
Disconnect Travelling Block
Erection Rigging
Installing
Securing
Disconnect from Torque Reaction
Unlatching the Harpoon
Removal from Mast
Lowering
Securing on truck
Offloading from truck
Do NOT use lifting sling when offloading from trailer

NOTES
CANRIG DRILLING TECHNOLOGY LTD

Engineering
Bill of Material

CANRIG DRILLING TECHNOLOGY LTD.

With Mfg Details


877-01-1
Part:
Description: BUW SAVER INTERLOCK KIT
0
Eng ID:
Drawing ID: 877-01-1
Item

01B

Qty

Units

1.00 EA

Rev No: A
Part ID

Description

P01-1003-010

44VALVE, SHUTTLE, 1/4in, PNEU

Mfg Name / Part ID: WABCO / P54350-2

01C

2.00 EA

H15-070123-08-04

REDUCER, MALE 1/2 JIC, FEM 1/4 JIC

Mfg Name / Part ID: PARKER / 8-4 TRTX-S

01D

2.00 EA

H15-070110-08

NUT, 1/2 JIC

Mfg Name / Part ID: PARKER / 8 BTX-S

01E

2.00 EA

H15-070123-06-04

REDUCER, MALE 3/8 JIC, FEM 1/4 JIC

Mfg Name / Part ID: PARKER / 6-4 TRTX-S

01F

2.00 EA

H15-070110-06

NUT, 3/8 JIC

Mfg Name / Part ID: PARKER / 6 BTX-S

01G

2.00 EA

H15-070432-04-04

TEE, SWV NUT RUN, 1/4 JIC

Mfg Name / Part ID: PARKER / 4 R6X-S

01H

2.00 EA

H15-070432-06-06

TEE, SWV NUT RUN, 3/8 JIC

Mfg Name / Part ID: PARKER / 6 R6X-S

01I

2.00 EA

H15-070432-08-08

TEE, SWV NUT RUN, 1/2 JIC

Mfg Name / Part ID: PARKER / 8 R6X-S

01J

8.00 EA

H15-070102-04-04

ADAPTER, MALE 1/4 JIC, MALE 1/4 NPT

Mfg Name / Part ID: PARKER / 4-4 FTX-S

01K

4.00 EA

H15-070202-04-04

ELL 90, MALE 1/4 JIC, MALE 1/4 NPT

Mfg Name / Part ID: PARKER / 4-4 CTX-S

01L

70.00 FT

H16-1301-04

HOSE, HP SAE 100R2, 1/4, 5000 psi

Mfg Name / Part ID: PARKER / 301-4

01M

8.00 EA

H15-3201-04-04

HOSE FTG, STR, 1/4, FEM SWV 1/4 JIC

Mfg Name / Part ID: PARKER / 20630-4-4

01N

2.00 EA

H15-3202-04-04

HOSE FTG, ELL 90, 1/4, FEM SWV 1/4 JIC

Mfg Name / Part ID: PARKER / 23930-4-4

01O

4.00 EA

H15-3101-04-04

HOSE FTG, 1/4, MALE 1/4 NPT

Mfg Name / Part ID: PARKER / 20130-4-4

01P

1.00 EA

H15-070601-04-04

UNION, BULKHEAD, MALE 1/4 JIC

Mfg Name / Part ID: PARKER / 4 WTX-S

01R

1.00 EA

H15-1010-010

QUICK DISC-CPLER, 1/4 BDY, 1/4 NPTF

Mfg Name / Part ID: PARKER / H2-62

Printed: 1/19/2001

Page 1 of 1

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

CANRIG DRILLING TECHNOLOGY LTD

Installation Instructions
Portable Torque Guide (Typical)
MAST APPLICATION
Pre Rig-Up ................................................... ...................................................................3-52
Mast Preparation .........................................Drawing Number: M-7-108-01 (A) ...............3-53
Grasshopper Installation .............................Drawing Number: M-7-110-01 (0) ...............3-54
Torque Guide Erection ................................Drawing Number: M-7-109-01 (C)...............3-56
Harpoon ......................................................Drawing Number: M-7-108-08 (0) ...............3-63
Torque Reaction .........................................Drawing Number: M-7-108-09 (0) ...............3-64
Erecting Assembly Removal .......................Drawing Number: M-7-108-10 (A) ...............3-65
Traveling Block ...........................................Drawing Number: M-7-108-11 (0) ...............3-66
Torque Guide Tensioning ............................Drawing Number: M-7-108-12 (A) ...............3-67
Service Support Assembly Positioning ........Drawing Number: M-7-108-16 (A) ...............3-68
Top Drive Alignment and Final Rig-Up ........Drawing Number: M-7-108-14 (0) ...............3-69

The drawings in this Subsection are provided to represent a


TYPICAL PORTABLE TORQUE GUIDE MAST APPLICATION.
As applications tend to differ from one rig to the next, the user should refer to the
drawings in Section 6 of this Manual for specifications and instructions for the
specific application.

Canrig Portable Torque Guide - Mast Application

Pre Rig-Up
Before beginning to rig up the Top Drive unit, several steps should be taken to ensure that
the operation goes as safely as possible.
1. Perform a thorough inventory of equipment on site. Make sure that all equipment needed
for the rig-up is present and is in good condition. Check lifting assembly for damage and any
lifting cables or lifting/snubbing cables for general damage or broken wires.
2. Conduct a safety meeting before beginning to rig up. Review this procedure with rig and
company personnel. Confirm that all personnel involved understand the operation, their
positions during rig-up and their duties during rig-up.
3. Assign personnel to act as observers to watch for interference in the mast as the Torque
Guide is being lifted up through it. The minimum recommended spotters are:

One person should be stationed ODS on the drill floor.


One person should be stationed DS on the drill floor.
One person should be stationed on the ground to watch the Torque Guide as it unfolds from the
bed truck.
One person should be in the crown to watch the Torque Guide as it reaches the crown and to
guide the harpoon into the Torque Guide pocket.
One additional person may be required at the monkey board in tight mast applications.
Personnel not involved in the rig-up should not be on the drill floor during the rig-up.

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

Top Drive and Torque Guide Installation

Mast Preparation
Drawing Number: M-7-108-01 (A)
1. With the mast in the down position (preferably), remove the diving board hinged section from
the racking board. Alternately, adjust the board forward.
2. Remove the hook and install the block adapter bail or interface.
3. Clamp the Torque Reaction Beam to girt #1 on the mast. Refer to the Torque Reaction Beam
Assembly drawing in Subsection 6A of this Manual. The beam should be positioned so that it is
centered about well center. All fasteners must be properly torqued (see Capscrew Torque
Values in Subsection 4D of this Manual. The Torque Guide clamp plates should not be installed
at this time.
4. Install the Crown Hanger Plates and Harpoon Assembly at the
crown. Refer to the Crown Hanger Assembly drawing in
Subsection 6A in Volume 2. Attach one end of each safety sling
to the Hanger Plates. The free ends of the slings will be pinned to
the Torque Guide once it is latched to the Harpoon. Ensure that
all safety pins and keeper bolts are securely in place and check
that the Harpoon is installed with the correct orientation. The
sloped side of the Harpoon should be facing towards the
drawworks.
5. Install the bridle line equalizer (see View A A) or insert equalizer
directly into block becket.
6. Raise the mast (and drawworks) if applicable.

Canrig Portable Torque Guide - Mast Application

Grasshopper Installation
Drawing Number: M-7-110-01 (0)
NOTE: Place TDSU as per the rig JSA. Connect the TDSU power cables to the AC power
source.
DANGER:

Ensure that the feeder breaker is OFF while connecting the power cables to it.
Be aware that the line side of the feeder breaker may still be live even if it is in
the OFF position. Use extreme caution while working in the feeder breaker
junction box.

The following method for handling the Grasshopper during installation should be followed to prevent
damage to equipment or injury to workers. The safest method of rigging the Grasshopper is with
the use of a crane. The crane is generally able to lift from directly above the point of attachment of
the cable to the Grasshopper, allowing the operator to control the movement of the Grasshopper.

1. With the Grasshopper still laid down, elevate the pole as required and rotate the entire
assembly until section 1 (the inboard section) is in the required position. Use the HPU override
pushbutton on the Grasshopper pedestal to start HPU 1 while the console is not connected.
2. Anchor section 1 so that it will not rotate while raising section 2. Failure to do so may allow
this section to swing uncontrollably during the rest of the rig-up.
3. Attach the line to be used for raising section 2.
4. To control the swinging of the Grasshopper, a tag line must be attached from the outboard end
of section 2 to a forklift, loader or similar vehicle. The tag line must be attached prior to
attempting to raise section 2 of the Grasshopper.
5. Attach the line in a manner that will not allow it to slide along the Grasshopper section.
6. Position the vehicle so that it can provide the greatest resisting force to oppose the lifting force
as much as possible.
7. The operator of the vehicle will keep the line between the vehicle and the Grasshopper taut at
all times in order to provide a resisting force to control the swing of the Grasshopper.
8. Section 2 will have a tendency to swing once it is lifted from its cradled position in
section 1. If the pull from the lifting winch is coming from one side of the Grasshopper, that is
the direction in which it will swing. If the pull is from directly above, it could swing in either
direction. Ensure that the person controlling the tag line is prepared and all personnel are
standing clear.
9. The operator of the vehicle attached to the tag line will be required to coordinate with the
crane/winch operator to control the swing of the Grasshopper.
10. After section 2 has been raised to a vertical height that will allow it to clear section 1, it can be
allowed to swing to a stable position by slowly and carefully slacking off the tag line while
keeping section 2 raised above section 1 (i.e., do not allow section 2 to rest on section 1). Once
section 2 has swung to its extreme, continue lifting to be absolutely sure that there is no more
tendency for it to swing. If the Grasshopper is stable, the tag line can be removed. The
structure will remain stable for the rest of the installation.
11. Pin the swivel mount to the mounting bracket installed on the substructure.

Revision 00.03

Top Drive and Torque Guide Installation

Grasshopper Installation
Drawing Number: M-7-110-02 (A)
NOTE: Portable Torque Guide must be installed before continuing.
12. Connect the hydraulic supply and return lines from the end of the Grasshopper to the Torque
Guide skid.
13. Connect the two control cables from the Grasshopper to the Control Console.
14. Connect the Electric Service cables from the Grasshopper to the Torque Guide J box.
15. Turn on the power at the TDSU and perform a function test.
16. If the Upper Well Control Valve AUTO feature is to be used:
Connect the pressure switch to the mud pump pressure line at the drilling recorder.
Connect the cable to the Top Drive Console.
Connect the interface cable from the TDSU to the rig for the mud pump running status
signal.

Revision 00.03

Canrig Portable Torque Guide - Mast Application

Torque Guide Erection


Drawing Number: M-7-109-01 (C)
1. Remove the catwalk and V-door ramp.
2. Pin the Lifting/Snubbing Assembly to the Live Roll End on the Torque
Guide/Top Drive (TG/TD) skid.
3. Load the TG/TD skid onto a bed truck as shown below so that the top
end of the skid overhangs approximately 21 feet behind the truck roll.
4. Position the bed truck so that the top end of the skid is approximately
2 to 3 feet from the rig substructure.
NOTE: Ensure that the torque guide is in line with well center.

Revision 00.03

Top Drive and Torque Guide Installation

Torque Guide Erection


Drawing Number: M-7-109-02 (A)
5. Attach the Lifting/Snubbing Assembly to the truck winch.
6. Tie one tugger through the Harpoon hole.
7. Install the runner frame stop pins into the holes in the angles on the top section of
the Torque Guide. (See Detail B.)
8. Ensure that either:
both the slide plates and clamp plates are installed on the torque reaction
beam assembly, or
both the slide plates and clamp plates are removed.
9. Ensure that the safety pin (1/2 by 6 cotter pin) is installed in the safety block
below the Whale Hook. This pin prevents the safety block from releasing and the
whale hook from coming out of its pocket in the Torque Guide.

CAUTION: Ensure that the shipping pins (qty 4) are in place and are
secure prior to hoisting. (See Detail A)

Revision 00.03

Canrig Portable Torque Guide - Mast Application

Torque Guide Erection


Drawing Number: M-7-109-04 (B)
10. Lift with the tugger to extend section 4 and section 5 until the blocks
can slide onto section 5. Wrap a chain around section 5 and through
the block becket if required for stability.
NOTE: The hinge between section 4 & 5 should be even with
or above the rig floor and section 3 may be partially
unfolded, depending on the floor elevation.
11. Block section 3 in its partially unfolded
position if required.
12. Rotate the Service Support Frame (Upper
and Lower) until they are as close as
possible to section 3. This step should
only be required on very narrow masts.
(See END VIEW.)
CAUTION: Do not disconnect the Load Binder ratchets to lay
the Service Support Frames toward section 3. The
frames will swing out of control during erection of
the Torque Guide if the binders are left
disconnected.
13. Slide the blocks on section 5 until the block adapter bail can be
pinned to the rigging yoke.
NOTE: Ensure that section 5 is stable and secure before
pinning.
14. Raise the blocks to tension the erection sling and remove the runner
frame stop pin from section 5.

Revision 00.03

Top Drive and Torque Guide Installation

Torque Guide Erection


Drawing Number: M-7-109-05 (A)
15. Begin lifting the Torque Guide with the blocks. Leave the
tugger connected to the Harpoon hole until sections 4 and 5
are straight.
NOTE: Ensure that the Service Loops are not pinched.
16. Continue lifting until all sections are unfolded and the skid
section is on the bed truck as shown below. Move truck back
and forth as required to assist in unfolding guide sections.
17. Release load binder on local blower and remove.
18. Swing blower into working position and bolt into place.

Canrig Portable Torque Guide - Mast Application

Torque Guide Erection


Drawing Number: M-7-109-06 (A)

19. Continue lifting, backing up the truck as required.


20. Monitor clearance at the racking board area during the lifting
process.

Top Drive and Torque Guide Installation

Torque Guide Erection


Drawing Number: M-7-109-07 (A)
21. Continue lifting the Torque Guide, letting-off on the truck winch as
required.
22. Continue to hoist the assembly, with the skid sliding on the front
corner of the substructure, if possible. If there are obstacles on
the substructure, be sure to maintain a safe distance between skid
and substructure while hoisting.

Canrig Portable Torque Guide - Mast Application

Torque Guide Erection


Drawing Number: M-7-109-08 (A)
23. Once the end of the skid reaches floor level, continue to let-off
cable from the truck winch until the Torque Guide is vertical
and completely inside the mast.
CAUTION: For stability and safety, the Live Roll End of
the skid should be kept as close to the floor as
possible during erection.
24. Continue lifting the Torque Guide until the Harpoon begins to
stab into the Torque Guide.
CAUTION: Do not pull more than 20 000 lb (9 000 daN)
over the free weight of the assembly.

Top Drive and Torque Guide Installation

Harpoon
Drawing Number: M-7-108-08 (0)
1. Once the Torque Guide is fully extended and has been raised into the mast, continue to slowly
hoist until the Harpoon enters the opening at the top of the Torque Guide (Stage 1, below). As
the Harpoon enters the opening, the Harpoon latches will pivot inward allowing the Torque
Guide to pass over them (Stage 2). Once past, the latches will pivot outward to their original
position (Stage 3).
2. Slowly lower the Traveling Block to set the Torque Guide onto the Harpoon latches.
3. Pin the free ends of the safety cables to the lugs on the Torque Guide. Refer to the Crown
Hanger Assembly drawing in Subsection 6A of this Manual. While installing the cables, visually
confirm that the Harpoon latches are fully latched.
CAUTION: The latches are supporting the total weight of the Top Drive and Torque
Guide. It is critical that they are fully latched.

4. Remove the Lifting/Snubbing Assembly from the Torque Guide/Top Drive skid.
5. Remove the Live Roll Assembly.

STAGE 1

STAGE 2

STAGE 3

STAGE 4

Canrig Portable Torque Guide - Mast Application

Torque Reaction
Drawing Number: M-7-108-09 (0)
1. If the clamp plates and slide plates are already in place from a previous installation, remove
the clamp plates and allow the Torque Guide skid to rest against the slide plates of the Torque
Reaction Beam. Otherwise, first install the slide plates and place the Torque Guide clamp
plates on the top of the bottom flange of the Torque Guide skid and then bolt them to the slide
plates. The skid flange should be sandwiched between the slide plate and the clamp plate.
Refer to the Torque Reaction Beam Assembly drawing in Subsection 6A of the Drawings and
Parts List book.
2. Measure the distance between the mast girt flange and the Torque Reaction Beam. Add or
remove shim plates until the nominal distance indicated on the Torque Reaction Beam
Assembly drawing is achieved to within 1/2 inch.
3. Ensure that all fasteners are properly torqued. Refer to Capscrew Torque Values in
Subsection 4D of this Manual.

Top Drive and Torque Guide Installation

Erecting Assembly Removal


Drawing Number: M-7-108-10 (A)
1. Climb the mast to the position of the lifting hook in the Torque Guide. Raise the Traveling Block
until the lifting hook is in its uppermost position in the lifting pocket.
2. Remove the cotter pin in the latch lock.
3. Insert the latch release rod into the lifting hook latch and turn until the latch is in the unlocked
position as shown below.
4. Lower the Traveling Block to allow the lifting hook to move down and out of the lifting groove.
Continue lowering the block until the erection apparatus is just above the Top Drive at the
bottom of the Torque Guide.
5. Remove the drillers side pin on the lifting frame and slide the runner to its extended position.
Replace the pin. Tilt the lifting frame and push sideways to remove it from the Torque Guide.
Repeat for the runner frame.
CAUTION: The lifting frame may tend to swing toward the V-door. Use care to avoid
pinching fingers.
6. Connect a tugger to the yoke and lift slightly in order to remove the two yoke pins. Lower the
entire apparatus to the floor.

Canrig Portable Torque Guide - Mast Application

Traveling Block
Drawing Number: M-7-108-11 (0)
1. Position the Traveling Block so that the bail can be pinned to the upper connecting links of the
Top Drive. Ensure that all pin keepers are securely fastened.

Top Drive and Torque Guide Installation

Torque Guide Tensioning


Drawing Number: M-7-108-12 (A)
NOTE: TDSU and Grasshopper must be installed prior to this step.
1. Connect the hydraulic supply and return lines from the end of the Grasshopper to the Torque
Guide skid.
2. Start the HPU.
3. Shift the hydraulic valve to retract the two hydraulic cylinders that will tighten the Torque Guide
tensioning cables. The valve is located on the lower skid section as shown below.
4. Shut off the HPU.
CAUTION: Valve pressure is pre-set by Canrig. Do not exceed the recommended
pressure setting as described in the hydraulic schematics in Subsection 6G
of this Manual.

Canrig Portable Torque Guide - Mast Application

Service Support Assembly Positioning


Drawing Number: M-7-108-16 (A)
1. Adjust the angle of the upper and lower frame using the load binders shown. The angle should
be adjusted so that the Top Drive and the Traveling Block can clear the frames as they travel up
and down on the Torque Guide.
2. Ensure that while adjusting the angle of the service support frames, no structural members of
the mast will interfere with the service support frame. Should this happen, the upper and lower
frames can be moved vertically by connecting a tugger line to the appropriate frame and
removing the frame pin. Carefully move the frame into a clear location and replace the frame
pin.
NOTE: In most cases, only the upper frame may require relocation.
3. If required, trim the connecting hose to suit the location of the frames.

Top Drive and Torque Guide Installation

Top Drive Alignment and Final Rig-Up


Drawing Number: M-7-108-14 (0)

1. Place a level on the skid section of the Torque


Guide and add/remove shims until Torque Guide
is level.
2. Remove top transport pins.
3. Hoist Top Drive several inches.
4. Remove bottom transport pins.
5. Position the Top Drive at a height where the
guide rails are fully engaged on the Torque Guide
Track.
6. Adjust the Top Drive Guide Rails so they are all
contacting the Torque Guide angle. A gap of up
to 1/8 is acceptable between rail and Torque
Guide angle. Do not over-tighten the Guide Rails
to the Torque Guide as this may cause premature
wear of the rails.
7. Adjust the Top Drive alignment until the Quill is
level. This adjustment is done using the center
position adjustment bolts, top vs. bottom.
8. Adjust the Top Drive over Well Center
maintaining level at the Quill. This adjustment is
done using the center position adjustment bolts,
adjusting top and bottom together side vs. side.
9. Lock down all adjustment bolts.
10. Install lower Links and Elevators. Position Link Tilt clamps so Elevators do not extend past Top
Drive cage.
11. Slowly hoist the Top Drive over its entire travel range and verify clearances. Use caution when
approaching the Service Support Frame and the top of the mast.
12. Install Lower Well Control Valves.
13. Install Rotary Hose. Secure safety cables to Top Drive Upper Links.

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

CANRIG DRILLING TECHNOLOGY LTD

Portable Torque Guide


Platform Application
Pre Rig-Up..........................................................................................................................3-106
Mast Preparation.Drawing Number: M-7-115-01 (0) ...3-107
Initial Installation..Drawing Number: M-7-115-02 (0)...3-108
Initial Installation..Drawing Number: M-7-115-03 (0)...3-109
Initial Installation..Drawing Number: M-7-115-04 (0)...3-110
HarpoonDrawing Number: M-7-108-08 (0) ...3-111
Erecting Assembly Removal .Drawing Number: M-7-108-10 (A) ..3-112
Traveling Block ... .Drawing Number: M-7-108-11 (0) ...3-113
Torque Reaction ...Drawing Number: M-7-108-09 (0) ...3-114
Torque Guide Tensioning .Drawing Number: M-7-108-12 (A)...3-115
Service Support Assembly Positioning .Drawing Number: M-7-108-16 (A) ...3-116
Top Drive Alignment and Final Rig-UpDrawing Number: M-7-108-14 (0) ...3-117
Portable Torque Guide Rig-Down Storm Condition..Drawing Number: M-7-115-12 (0) ...3-118

The drawings in this Subsection are provided to represent a


TYPICAL PLATFORM PORTABLE TORQUE GUIDE APPLICATION.
As applications tend to differ from one rig to the next, the user should refer to the drawings in
Section 6 of this Manual for specifications and instructions for the specific application.

Canrig Portable Torque Guide - Platform Application

Pre Rig-Up
Before beginning to rig up the Top Drive unit, several steps should be taken to ensure that the
operation goes as safely as possible.
1. Perform a thorough inventory of equipment on site. Make sure that all equipment needed for the
rig-up is present and is in good condition. Check lifting assembly for damage and any lifting cables
or lifting/snubbing cables for general damage or broken wires.
2. Conduct a safety meeting before beginning to rig up. Review this procedure with rig and company
personnel. Confirm that all personnel involved understand the operation, their positions during rig-up
and their duties during rig-up.
3. Assign personnel to act as observers to watch for interference in the mast as the Torque Guide is
being lifted up through it. The minimum recommended spotters are:

One person should be stationed ODS on the drill floor.


One person should be stationed DS on the drill floor.

One person should be in the crown to watch the Torque Guide as it reaches the crown and to guide
the harpoon into the Torque Guide pocket.
One additional person may be required at the monkey board in tight mast applications.

Personnel not involved in the rig-up should not be on the drill floor during the rig-up.

Top Drive and Torque Guide Installation

Mast Preparation
Drawing Number: M-7-115-01 (0)
1.

With the mast in the down position (preferably), remove the diving
board hinged section from the racking board. Alternately, adjust the
board away from well center.

2.

Remove the hook and install the block adapter bail or interface.

3.

Clamp the Torque Reaction Beam to girt #1 on the mast. Refer to


the Torque Reaction Beam Assembly drawing in Subsection 6A of
this Manual. The beam should be positioned so that it is centered
about well center. All fasteners must be properly torqued (see
Capscrew Torque Values in Subsection 4D of this Manual. The
Torque Guide clamp plates should not be installed at this time.

4.

Install the Crown Hanger Plates and Harpoon Assembly at the


crown. Refer to the Crown Hanger Assembly drawing in
Subsection 6A in Volume 2. Attach one end of each safety sling to
the Hanger Plates. The free ends of the slings will be pinned to the
Torque Guide once it is latched to the Harpoon. Ensure that all
safety pins and keeper bolts are securely in place and check that
the Harpoon is installed with the correct orientation. The sloped
side of the Harpoon should be facing towards the drawworks.

5.

Install the bridle line equalizer (see below) or insert equalizer


directly into block becket.

6.

Raise the mast if applicable.

Canrig Portable Torque Guide - Platform Application

Initial Installation
Drawing Number: M-7-115-02 (0)
1. Lift the Torque Guide Assembly onto the rig floor using the supplied handling
slings. Ensure that the slings are pinned to the handling beams with the correct
orientation. Refer to the Torque Guide Handling Sling Assembly in the manual.
Place the Torque Guide as close to the drawworks as possible then remove the
handling slings.
NOTE: ENSURE THAT THE CRANE HAS ENOUGH CAPACITY TO LIFT APPROX.
15,000 LBS.
2. With the Travelling Block Interface installed onto the block, lower the block until
the lifting yoke on top of the Torque Guide can be pinned to the Travelling Block
Interface. Refer to the Rig-up Assembly drawing in the manual.
NOTE: A TUGGER MAY BE NEEDED TO PULL THE TRAVELLING BLOCK OVER
TO THE LIFTING YOKE FOR PINNING.
3. Install the runner frame stop pins into the holes in the angles on the top section of
the Torque Guide.
4. If using a headache rack to support Torque Guide: Install the Rig up platforms
onto section 3 of the Torque Guide by sliding the drillers side platform thru the
holes provided on that section. Slide the Off-drillers side platform onto the pipes
and insert the two pins to lock that assembly onto the section.

Top Drive and Torque Guide Installation

Initial Installation
Drawing Number: M-7-115-03 (0)
5. Hoist the travelling block to lift and unfold the Torque Guide into a vertical position.
Continue lifting the Torque Guide until it is completely unfolded and the bottom of the
Torque Guide is approx. 24 inches above the rig floor.

Canrig Portable Torque Guide - Platform Application

Initial Installation
Drawing Number: M-7-115-04 (0)
6. Lift the Top Drive/Transport Skid onto the rig floor using a crane with enough
capacity to lift 23,000 lbs. Place the skid so that the top roll end is as close
as possible to the drawworks.
NOTE: 1. ENSURE THAT THE SHIPPING PINS ARE SECURELY IN PLACE
AT THE TOP AND BOTTOM ENDS OF THE TOP DRIVE GUIDE
RAILS.
2. IF THE CRANE DOES NOT HAVE ENOUGH CAPACITY, THEN
THE SKID SHOULD BE LIFTED FIRST AND PLACED ON THE
FLOOR FOLLOWED BY THE TOP DRIVE.
TOP DRIVE = 18,000 LBS. Approx.
SKID = 5,000 LBS. Approx.
7. Slowly lower the Torque Guide with the Travelling Block until the Torque
Guide can be pinned to the top of the skid torque tube.
8. Securely attach a cable from a crane to the bottom end of the skid.
NOTE: IF THE BOTTOM END OF THE SKID HANGS OVER THE EDGE OF
THE PLATFORM, THEN THIS CABLE SHOULD BE USED TO
CARRY SOME OF THE LOAD UNTIL THE END OF THE SKID IS
OVER TOP THE RIG FLOOR.
9. Continue lifting the skid and the Torque Guide with the travelling block. As
the skid becomes more vertical keep the bottom end of the skid as close as
possible or touching the rig floor at all times.
10. Continue hoisting until the skid is off of the floor and the top end of the
Torque Guide is about to stab into the Crown Hanger Harpoon.

Top Drive and Torque Guide Installation

Harpoon
Drawing Number: M-7-108-08 (0)
1. Once the Torque Guide is fully extended and has been raised into the mast, continue to slowly hoist
until the Harpoon enters the opening at the top of the Torque Guide (Stage 1, below). As the
Harpoon enters the opening, the Harpoon latches will pivot inward allowing the Torque Guide to
pass over them (Stage 2). Once past, the latches will pivot outward to their original position (Stage
3).
2. Slowly lower the Traveling Block to set the Torque Guide onto the Harpoon latches.
3. Pin the free ends of the safety cables to the lugs on the Torque Guide. Refer to the Crown Hanger
Assembly drawing in Subsection 6A of this Manual. While installing the cables, visually confirm that
the Harpoon latches are fully latched.
CAUTION: The latches are supporting the total weight of the Top Drive and Torque Guide. It
is critical that they are fully latched.

STAGE 1

STAGE 2

STAGE 3

STAGE 4

Canrig Portable Torque Guide - Platform Application

Erecting Assembly Removal


Drawing Number: M-7-108-10 (A)
1. Climb the mast to the position of the lifting hook in the Torque Guide. Raise the Traveling Block until
the lifting hook is in its uppermost position in the lifting pocket.
2. Remove the cotter pin in the latch lock.
3. Insert the latch release rod into the lifting hook latch and turn until the latch is in the unlocked
position as shown below.
4. Lower the Traveling Block to allow the lifting hook to move down and out of the lifting groove.
Continue lowering the block until the erection apparatus is just above the Top Drive at the bottom of
the Torque Guide.
5. Remove the drillers side pin on the lifting frame and slide the runner to its extended position.
Replace the pin. Tilt the lifting frame and push sideways to remove it from the Torque Guide.
Repeat for the runner frame.
CAUTION: The lifting frame may tend to swing toward the V-door. Use care to avoid
pinching fingers.
Connect a tugger to the yoke and lift slightly in order to remove the two yoke pins. Lower the entire
apparatus to the floor.

Canrig Portable Torque Guide - Platform Application

Torque Reaction
Drawing Number: M-7-108-09 (0)
1. If the clamp plates and slide plates are already in place from a previous installation, remove the
clamp plates and allow the Torque Guide skid to rest against the slide plates of the Torque
Reaction Beam. Otherwise, first install the slide plates and place the Torque Guide clamp plates on
the top of the bottom flange of the Torque Guide skid and then bolt them to the slide plates. The
skid flange should be sandwiched between the slide plate and the clamp plate. Refer to the Torque
Reaction Beam Assembly drawing in Subsection 6A of the Drawings and Parts List book.

2. Measure the distance between the mast girt flange and the Torque Reaction Beam. Add or
remove shim plates until the nominal distance indicated on the Torque Reaction Beam
Assembly drawing is achieved to within 1/2 inch.
3. Ensure that all fasteners are properly torqued. Refer to Capscrew Torque Values in
Subsection 4D of this Manual.

Top Drive and Torque Guide Installation

Torque Guide Tensioning


Drawing Number: M-7-108-12 (A)
1. Pin the tensioning cables on the Torque Guide to the cylinder rod clevis on each side of the skid.
2. Connect the hydraulic supply and return lines from the end of the HPU to the Torque Guide
skid.
3. Start the HPU.
4. Shift the hydraulic valve to retract the two hydraulic cylinders that will tighten the Torque Guide
tensioning cables. The valve is located on the lower skid section as shown below.
5. Shut off the HPU.
CAUTION: Valve pressure is pre-set by Canrig. Do not exceed the recommended pressure
setting as described in the hydraulic schematics in Subsection 6E of this Manual.

Canrig Portable Torque Guide - Platform Application

Service Support Assembly Positioning


Drawing Number: M-7-108-16 (A)
1. Adjust the angle of the upper and lower frame using the load binders shown. The angle should be
adjusted so that the Top Drive and the Traveling Block can clear the frames as they travel up and
down on the Torque Guide.
2. Ensure that while adjusting the angle of the service support frames, no structural members of the
mast will interfere with the service support frame. Should this happen, the upper and lower frames
can be moved vertically by connecting a tugger line to the appropriate frame and removing the frame
pin. Carefully move the frame into a clear location and replace the frame pin.
NOTE: In most cases, only the upper frame may require relocation.
3. If required, trim the connecting hose to suit the location of the frames.

Top Drive and Torque Guide Installation

Top Drive Alignment and Final Rig-Up


Drawing Number: M-7-108-14 (0)

1. Place a level on the skid section of the Torque


Guide and add/remove shims until Torque Guide
is level.
2. Remove top transport pins.
3. Hoist Top Drive several inches.
4. Remove bottom transport pins.
5. Position the Top Drive at a height where the
guide rails are fully engaged on the Torque Guide
Track.
6. Adjust the Top Drive Guide Rails so they are all
contacting the Torque Guide angle. A gap of up
to 1/8 is acceptable between rail and Torque
Guide angle. Do not over-tighten the Guide Rails
to the Torque Guide as this may cause premature
wear of the rails.
7. Adjust the Top Drive alignment until the Quill is
level. This adjustment is done using the center
position adjustment bolts, top vs. bottom.
8. Adjust the Top Drive over Well Center
maintaining level at the Quill. This adjustment is
done using the center position adjustment bolts,
adjusting top and bottom together side vs. side.
9. Lock down all adjustment bolts.
10. Install lower Links and Elevators. Position Link Tilt clamps so Elevators do not extend past Top
Drive cage.
11. Slowly hoist the Top Drive over its entire travel range and verify clearances. Use caution when
approaching the Service Support Frame and the top of the mast.
12. Install Lower Well Control Valves.
13. Install Rotary Hose. Secure safety cables to Top Drive Upper Links.

Canrig Portable Torque Guide - Platform Application

Portable Torque Guide Rig-Down


Storm Condition
Drawing Number: M-7-115-12 (0)
1. Swing all hinged or adjustable sections out of the way
on the racking board and belly board (if applicable).
2. Install headache rack (if applicable) to support Torque
Guide.
3. Using the load binders, swing the Service Support Frames
inwards toward the Torque Guide.
4. Unpin and remove the Bottom End Section from the Skid.
5. Lower the Top Drive to the floor and stab the drill stem into
the rotary table and set the slips.
6. Unpin the Top Drive upper connecting links from the Block
Interface Assembly.
7. Place the Rig-up Assembly onto the Torque Guide and pin
the lifting yoke to the Block Interface Assembly.
8. Raise Rig-up Assembly to lifting pocket location on Torque
Guide. Slide hook into pocket and lock into place.
9. Unpin the crown hanger safety slings from the Torque
Guide.
10. Hoist travelling block to lift Torque Guide off of the crown
hanger latches. Pull latch release cable to retract latches
so that the Torque Guide can be lowered over top of them.
11. Slowly lower the Torque Guide until the bottom of the skid
rests on the floor.
12. Continue lowering the Torque Guide, folding the sections
onto the headache rack.
13. Once all sections of the Torque Guide are resting on the
rack, continue lowering the travelling block until it lays flat
on top of the Torque Guide.
14. Secure the Torque Guide, travelling block and skid as
required for the approaching storm.

NOTES
CANRIG DRILLING TECHNOLOGY LTD

CANRIG DRILLING TECHNOLOGY LTD

Installation Instructions
Fixed Torque Guide (Typical)
Initial Installation .........................................Drawing Number: M-7-117-01 (0) ...............3-42
Top Drive Installation (Method 1) ................Drawing Number: M-7-117-03 (0) ...............3-44
Top Drive Installation (Method 2) ................Drawing Number: M-7-117-05 (0) ...............3-46
Traveling Block Connection .........................Drawing Number: M-7-108-11 (0) ...............3-47
Top Drive Alignment and Final Rig-Up ........Drawing Number: M-7-108-14 (0) ...............3-48
Lowering Mast .............................................Drawing Number: M-7-117-04 (0) ...............3-49

The drawings in this Subsection are provided to represent a


TYPICAL FIXED TORQUE GUIDE APPLICATION.
As applications tend to differ from one rig to the next, the user should refer to the
drawings in Section 6 of this Manual for specifications and instructions for the
specific application.

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

NOTES
CANRIG DRILLING TECHNOLOGY LTD

Canrig Fixed Torque Guide

Initial Installation
Drawing Number: M-7-117-01 (0)
1. After the mast is assembled and prior to raising, position the Torque Guide sections as shown
below. Also refer to the Torque Guide Installation drawing in Subsection 6C of this Manual.
Preset the turnbuckle lengths as indicated on the Torque Guide Installation drawing.
2. Lift each Torque Guide section into place and pin into the turnbuckles.
Install locking pins or bolts at each end of the turnbuckle pins. Refer to the Torque Guide
Installation drawing.
3. Bolt the sections together using the hardware specified on the Torque Guide Installation
drawing.
4. Center the Torque Guide with respect to the mast by taking measurements to each side of the
mast from the Torque Guide. Measurements should be equal 1/2 inch. Adjust the
turnbuckles equal amounts in opposite directions to correct any centering errors. For example if
the Torque Guide is too close to the drillers side at a particular mounting point, then extend the
drillers side turnbuckle and retract the off-drillers side turnbuckle equal amounts.
5. Check the fore-aft position by measuring at each side of the Torque Guide and take the
average. The tolerance for the fore-aft position is 1/2 inch. Correct the fore-aft position by
adjusting the two turnbuckles equally and in the same direction. Refer to the Torque Guide
Installation drawing for theoretical fore-aft positions (Dim x) of the Torque Guide. Some fine
tuning may be required and is usually done at the time commissioning. Measure, record and
return the actual fore-aft positions to Canrig. A formal drawing with as-built dimensions will be
issued which can be used to verify the correct Torque Guide position on subsequent rig-ups.
NOTE: Ignore the torsional positional of the Torque Guide at this stage since it is not
controlled by the turnbuckles.
6. Visually check the straightness of the Torque Guide in both the side and fore-aft planes and
make any adjustments as required. The turnbuckles should never need to be readjusted and it
is recommended that they be wired to prevent accidental movement due to drilling.

Top Drive and Torque Guide Installation

Initial Installation
Drawing Number: M-7-117-02 (0)
7. Install the Crown Hanger plates into the crown and pin the crown turnbuckles to the top of the
Torque Guide and to the Crown Hanger plates as shown in the Crown Hanger Assembly
drawing in Subsection 6A of this Manual. Pay particular attention to preset length of
turnbuckles.
NOTE: The crown turnbuckles will support the entire weight of the Torque Guide in
the working position (approximately 20,000 lb) and will support the weight of
both the Torque Guide and the Top Drive (approximately 50,000 lb) during rigup and rig-down. Ensure that all pins and keepers are secure.
8. Ensure that safety cables are installed.
9. Install the Torque Reaction Beam as shown on the Torque Reaction Beam Assembly Drawing
in Subsection 6A of this Manual.
10. Install the Traveling Block and string the drill line.
11. Attach the Traveling Block to the bridle line equalizer in preparation for raising the mast. Refer
to the Mast Raising Interface drawing in Subsection 6A of this Manual.

Canrig Fixed Torque Guide

Top Drive Installation (Method 1)


Drawing Number: M-7-117-03 (0)
NOTE: This method is typically used on high floor substructures.
1. Prepare Traveling Block and mast for raising as per manufacturers specifications and
procedures.
2. Raise the mast as per the mast manufacturers specifications and procedures. Complete the
assembly of the substructure, if applicable.
3. Lift the Top Drive and Transport Skid assembly to the drill floor using a crane with enough
capacity to lift 30,000 lb.
NOTES:
Ensure that the shipping pins are securely in place at
the top and bottom ends of the Top Drive guide rails.

If the Top Drive skid is not directly below the traveling


block, do not install the Block Guide Assembly at this
time.

4. Secure the upper connecting links to the skid (with a chain


and load binder, for example) to help minimize the bending
forces in the upper connecting links.

5. Assemble the Block Interface. Refer to the Block Interface


Assembly drawing in Subsection 6A of this Manual.
6. Lower the Traveling Block as low as possible to the rig floor.
Attach the Block Guide Assembly to the Traveling Block,
then slide the assembly onto the Torque Guide. Refer to
the Block Guide Assembly drawing in Subsection 6A.
7. With the bail in the block becket, attach the block to the
upper connecting link pins using cable slings of sufficient
length. BOP slings are acceptable. One 1 1/16 dia cable
or two 3/4 dia cables are the minimum recommended.
8. Hoist the Traveling Block to pull the Top Drive and skid up
to a vertical position. Continue lifting until the skid makes
contact with the bottom of the Torque Guide.

Top Drive and Torque Guide Installation

Top Drive Installation (Method 1)


Drawing Number: M-7-117-03 (0)
9.

Align the skid with the Torque Guide and bolt together.

10.

Pin the skid to the Torque Reaction Beam using the turnbuckles provided. Refer to the
Torque Reaction Beam Assembly drawing in Subsection 6B in Volume 2. Adjust the
turnbuckles to align the Torque Guide. Refer to the Torque Reaction Turnbuckle
Adjustment drawing.
NOTE: The entire weight of the Torque Guide should be on the crown turnbuckles
when in operation, and the bottom of the skid should be approximately
7 6 above the rig floor.

11.

Lower the Traveling Block and remove the slings.

12.

Remove the upper shipping pins. Raise the Traveling Block to take the load off the lower
Top Drive shipping pins and then remove the pins.

13.

Lower the Top Drive to the floor and attach the Service Loop connections and the Kelly
hose.

Canrig Fixed Torque Guide

Top Drive Installation (Method 2)


Drawing Number: M-7-117-05 (0)
NOTE: This method is typically used on barge rigs.
1. Prepare the Traveling Block and mast for raising as per manufacturers specifications and
procedures.
NOTE: The mast should be raised with the Block Guides installed ONLY if the sling
line geometry does not pull the Traveling Block excessively behind well center,
which could damage the Block Guide and the Torque Guide.
THIS SHOULD ONLY BE DONE WITH APPROVAL FROM CANRIG.
2. Raise the mast as per the mast manufacturers specifications and procedures.
3. Remove the Traveling Block from the bridle line equalizer.
4. Attach slings similar to those used in Top Drive Installation - Method 1 (see preceding pages)
between the Traveling Block and the lugs on the outside of the skid.
5. Hoist the Traveling Block to pull the skid up until it makes contact with the bottom of the Torque
Guide. Align the skid with the Torque Guide and bolt together.
6. Remove the shipping pins.
7. Attach the Block Interface to the Top Drive upper connecting links. Refer to the Block Interface
Assembly drawing in Subsection 6A of this Manual.
8. If a Local Blower is installed, it may have rotated back to the working position.
9. Re-pin the Block Guide to the Traveling Block only if it was removed for lowering the mast.
Refer to the Block Guide Assembly drawing in Subsection 6A and to the instructions above.
10. Remove the slips from the rotary table.

Top Drive and Torque Guide Installation

Traveling Block Connection


Drawing Number: M-7-108-11 (0)
1. Position the Traveling Block so that the bail can be pinned to the upper connecting links of the
Top Drive. Ensure that all pin keepers are securely fastened.

Canrig Fixed Torque Guide

Top Drive Alignment and Final Rig-Up


Drawing Number: M-7-108-14 (0)

1. Remove the top transport pins.


2. Hoist the Top Drive several inches.
3. Remove the bottom transport pins.
4. Position the Top Drive at a height where the
guide rails are fully engaged on the Torque
Guide Track.
5. Adjust the guide rails so that they are all
contacting the Torque Guide angle. A gap of
up to 1/8 is acceptable between the rail and
Torque Guide angle. Do not over-tighten the
Guide rails to the Torque Guide as this may
cause premature wear of the rails.
6. Adjust the Top Drive alignment until the Quill is
level. This adjustment is done using the center
position adjustment bolts, top vs. bottom.
7. Adjust the Top Drive over Well Center
maintaining level at the Quill. This adjustment
is done using the center position adjustment
bolts, adjusting top and bottom together side
vs. side.
8. Lock down all adjustment bolts.
9. Install lower Links and Elevators. Position Link Tilt clamps so Elevators do not extend past
Top Drive cage.
10. Slowly hoist the Top Drive over its entire travel range and verify clearances. Use caution
when approaching the Service Support Frame and the top of the mast.
11. Install Lower Well Control Valves.
12. Install Rotary Hose. Secure safety cables to Top Drive Upper Links.

Top Drive and Torque Guide Installation

Lowering Mast
Drawing Number: M-7-117-04 (0)
1. Lower the Top Drive to the drill floor and stab into rotary table.
2. Unpin the Block Guide from the Traveling Block, then remove the Block Guide from the Torque
Guide.
ALTERNATELY, leave the Traveling Block and Block Guide Assembly on the Torque Guide,
even with the mast laid down.
NOTE: This may only be possible if the sling line geometry does not pull the Traveling
Block excessively behind well center, which could damage the Block Guide
and the Torque Guide.
THIS SHOULD ONLY BE DONE WITH APPROVAL FROM CANRIG.
3. Detach the Block Interface (and local Blower hose, if applicable) from the Top Drive connecting
links and then raise the block up clear of the Top Drive.
4. Install shipping pins into the pinning holes on the skid rails and install keeper bolts.
5. Attach slings similar to those used for the Top Drive Installation (Method 1 or 2) between the
Traveling Block and the lugs on the outside of the skid.
6. Keeping the slings tight, unbolt the skid section from the rest of the Torque Guide and lower it
until it rests on the Top Drive rails. Remove the slings from the Traveling Block and the skid.
7. Attach the Traveling Block to the Bridle Line equalizer in preparation for lowering the mast.
Refer to the Mast Raising Interface drawing in Subsection 6A of this Manual.
8. Prepare Traveling Block and mast for lowering as per manufacturers specifications and
procedures.
9. Lower the mast.

NOTES
CANRIG DRILLING TECHNOLOGY LTD

CANRIG DRILLING TECHNOLOGY LTD

Removal Instructions
Portable Torque Guide (Typical)
MAST APPLICATION
Preparation for Removal .............................Drawing Number: M-7-126-01 (A) ...............3-72
Top Drive Positioning ..................................Drawing Number: M-7-126-02 (0) ...............3-73
Traveling Block Removal ............................Drawing Number: M-7-108-11 (0) ...............3-74
Erection Rigging ..........................................Drawing Number: M-7-108-10 (A) ...............3-75
Traveling Block Untensioning ......................Drawing Number: M-7-108-12 (A) ...............3-76
Torque Reaction .........................................Drawing Number: M-7-108-09 (0) ...............3-77
Harpoon ......................................................Drawing Number: M-7-108-08 (0) ...............3-78
Torque Guide Removal ...............................Drawing Number: M-7-109-08 (A) ...............3-79

The drawings in this Subsection are provided to represent a


TYPICAL PORTABLE TORQUE GUIDE MAST APPLICATION.
As applications tend to differ from one rig to the next, the user should refer to the
drawings in Section 6 of this Manual for specifications and instructions for the
specific application.

Canrig Portable Torque Guide - Mast Application

Preparation for Removal


Drawing Number: M-7-126-01 (A)
1. Remove Elevators and Lower Links. Disconnect Rotary Hose. Remove Blower Hose.
2. If Lower Well Control Valves or Cross-over Subs require inspection, remove at this time.
3. Raise the Top Drive to allow access to the Torque Guide skid.
4. Raise the Live Roll assembly using the floor winches and insert into the Torque Guide skid.
Install the roll end pins and pin retainers.
5. Remove winch lines.

Top Drive and Torque Guide Installation

Top Drive Positioning


Drawing Number: M-7-126-02 (0)
1. Install the Lower Transport Pins into the Torque Guide.
2. Lower the Top Drive until the full weight of the Top Drive unit is supported by the Transport Skid.
3. Install the Upper Transport Pins into the Torque Guide.

Canrig Portable Torque Guide - Mast Application

Traveling Block Removal


Drawing Number: M-7-108-11 (0)
1. With the full weight of the Top Drive on the Transport Pins, position the Block for removal of the
Upper Link Pins.
2. Remove Pin keepers and Pins.
3. Raise the Traveling Block so the Bail or Block Adapter is free of the Upper Connecting Links.
4. Prepare to install the Erection Rigging.

Top Drive and Torque Guide Installation

Erection Rigging
Drawing Number: M-7-108-10 (A)
1. Raise the Erection apparatus by connecting a tugger line to the Yoke. Raise the apparatus into
position at the Traveling Block and pin the Yoke into the Bail. Install the keepers into the Bail
Pins.
2. Remove the Drillers Side Pin on the runner frame and slide the runner to its extended position.
Tilt the Lifting Frame and hook the ODS runner around the Torque Guide track. Slide the
Drillers side frame to its retracted position around the Torque Guide track and replace the pin.
3. Raise the Traveling Block and repeat Step 2 for the Lifting Frame.
4. Raise the Traveling Block until the Lifting Hook is near the pocket on section 4 of the Torque
Guide. Carefully raise the Block and ensure the Lifting Hook goes into the Lifting Pocket.
5. Insert the Latch Release Rod into the Lifting Hook Latch and turn until the latch is in the locked
position as shown below.
6. Insert the Cotter Pin in the Latch Lock.

Canrig Portable Torque Guide - Mast Application

Traveling Block Untensioning


Drawing Number: M-7-108-12 (A)
1. Shift the Hydraulic Valve to extend the two hydraulic Tensioning Cable cylinders. The Valve is
located on the lower skid section as shown below.
2. Any remaining torque in the Tensioning Cables can be eliminated by rotating the tensioning
cable in the proper direction with a pipe wrench.
NOTE: Do not use a pipe wrench on the cylinder rod.
3. The Tensioning Cables can be unpinned from the Tensioning Cylinder to allow cable movement
during the Rig-down procedure. Remove pins when Tensioning Cylinder rods are fully
extended. Stand clear while retracting the cylinder rods.
CAUTION: The tensioning cables may spin rapidly when they become free from the
tensioning cylinder rod.

Top Drive and Torque Guide Installation

Torque Reaction
Drawing Number: M-7-108-09 (0)
1. Remove the Torque Guide clamp plates to allow the skid section to be free of the Torque
Reaction Beam.
2. The clamp plates can be re-installed on the Torque Reaction Beam for transport purposes.
3. Ensure the main breakers are turned off in the TDSU and no power is going to the Top Drive.
4. Disconnect electrical and hydrualic lines from the Torque Guide.

Canrig Portable Torque Guide - Mast Application

Harpoon
Drawing Number: M-7-108-08 (0)
1. Remove the Safety Cables from the Torque Guide Section 5.
2. Slowly raise the Traveling Block so the Harpoon Latches are free from the top opening on the
Torque Guide.
3. Pull on the Harpoon Latch Cables to pivot them inward. Lower the Torque Guide until the top
opening is below the Harpoon Latches. Release the Harpoon Latch Cables.
4. The Torque Guide and Top Drive are now suspended from the Traveling Block.

STAGE 1

STAGE 2

STAGE 3

STAGE 4

Top Drive and Torque Guide Installation

Torque Guide Removal


Drawing Number: M-7-109-08 (A)

1. Ensure the truck is aligned with Well Center and in position to


accept the Top Drive.
2. Raise the truck winch line to the floor and attach to the
Lifting/Snubbing Assembly.
3. Slowly tension the truck winch until the Torque Guide Skid is clear
of the substructure.

Canrig Portable Torque Guide - Mast Application

Portable Torque Guide Torque Guide Removal


Drawing Number: M-7-109-07 (A)
4. Continue to lower the Traveling Block/Torque Guide while
tensioning the truck winch.
5. If there are obstacles on the substructure be sure to maintain a
safe distance between the skid and substructure while lowering.

Top Drive and Torque Guide Installation

Portable Torque Guide Torque Guide Removal


Drawing Number: M-7-109-05 (A)

6. Lower the Torque Guide while taking in the truck winch as required.

7. Continue until the skid section is secure on the truck bed.

Canrig Portable Torque Guide - Mast Application

Portable Torque Guide Torque Guide Removal


Drawing Number: M-7-126-03 (0)
8. Unbolt the Blower from the working position.
9. Swing the Blower into transport position and install load binder.
10. If extended Upper Links were in use, one or both may have to be removed from the Top Drive to
allow clearance for the Torque Guide to fold into the transport position.

Top Drive and Torque Guide Installation

Portable Torque Guide Torque Guide Removal


Drawing Number: M-7-109-04 (B)

11. Slowly lower the Traveling Block while the Torque Guide folds
onto the truck. Move the truck back and forth to assist in folding
the Torque Guide sections.
12. Ensure the Service Loops are properly folded for transport (side
by side) in the Torque Guide while lowering.
13. Secure the top section of Torque Guide (Section 5) at floor
height.
14. Install the Runner Frame stop Pins.
15. Install a Tugger through the Harpoon hole in Torque Guide
Section 5.

16. Remove the pins in the Rigging Yoke. The Traveling Block is
now free and can be hoisted out of the way.

17. Rotate the Service Support Frame in using the ratchet type load
binder.

Canrig Portable Torque Guide - Mast Application

Portable Torque Guide Torque Guide Removal


Drawing Number: M-7-109-02 (A)
18. Lower the remaining sections of the Torque Guide with the Tugger until all
sections are on the truck.
19. Remove the Tugger Line.
20. Secure Torque Guide to truck for transport.
21. The Lifting/Snubbing Line is not to be used for lowering the Torque Guide to the
ground. Unhook the truck winch from the Lifting/Snubbing assembly and attach
to the Live Roll of the skid.