Documente Academic
Documente Profesional
Documente Cultură
Bayarbat .S,
Director-General,
Finance and Investment Department
CONTENT
key Mines
Nariin Sulhait
Tavan tolgoi
Renewable energy
Rich resources of Solar, Wind and Hydro in Mongolia:
Solar: 270-300 sunny days in a year, 4.3-4.7 kWh/meter or higher per day
Wind: 10 % of the total land area can be classified as excellent for utility scale
applications, Power density 400-600 W/m2, the resource could potentially supply
over 1100 GW of installed capacity.
Hydro: Theoretical potential 6.2 GW, more than 1 GW of these ahs been identified
Energy Statistics
Primary Energy Supply and Economic Indicators
2000
Total Primary Energy Supply (1,000 TOE)
2005
2010
2012
00-05
05-10
10-12
2,564
2,800
3,545
8,526
1.8%
4.8%
55.1%
1.06
1.09
1.27
2.97
0.5%
3.1%
52.7%
Population (thousand)
2,408
2,562
2,781
2,868
1.3%
1.6%
1.6%
2,100
2,780
4,154
5,438
5.8%
8.4%
14.4%
1.22
1.01
0.85
1.57
-3.8%
-3.3%
35.5%
19.4%
21.4%
25.6%
15.5%
1.9%
3.7%
-22.2%
2005
2010
2012
00-05
05-10
10-12
Indigenous Production
2,019
3,592
11,591
14,038
12.2%
26.4%
10%
Import
497.1
597.9
908.9
1321.7
3.8%
8.7%
20.6%
Export
1,405
9,028
6,227
236%
45.1%
-16.9%
2,564
2,800
3,545
8,526
1.8%
4.8%
55.1%
Energy Statistics
Structure of Primary Energy Supply by Source
2000
Coal
Oil
Hydro
Traditional Fuels & Others
Total
2010
2012
1,798
1,895
2,324
6,884
70.2%
67.7%
65.6%
80.7%
472
584
879
1,284
18.4%
20.9%
24.8%
15.1%
0.25
0.28
4.73
8.96
0.01%
0.01%
0.13%
0.11%
293
321
337
348
11.4%
11.5%
9.5%
4.1%
2,564
2,800
3,545
8,526
100.0%
100.0%
100.0%
100.0%
05-10
10-12
1.0%
4.2%
72.1%
4.3%
8.5%
20.9%
2.1%
76.0%
37.6%
1.8%
1.0%
1.6%
1.8%
4.8%
55.1%
10 000
8 000
6 000
4 000
2 000
0
1990
Coal
Oil
1995
2000
Hydro
2005
2010
2012
Ulaanbaatar
Current state
Energy sector
10
11
Recent challenges
Energy sector
1) Capacity shortage on Domestic Power Generation due to:
6 000
1600
1400
5 000
1200
4 000
1000
3 000
800
2 000
600
400
1 000
200
0
2006 2007 2008 2009 2010 2011 2012 2013 2014
Domestic Production
0
2008
Import
2009
Central
17,0%
2010
Western
2011
Eastern
2012
2013
2014
Oyutolgoi mine
12,0%
7,0%
2,0%
-3,0%
GDP Growth rate
12
Recent challenges
Energy sector
2) Lower Efficiency of Existing Power Plants due to:
Aging of main equipments
Insufficient financial capacity for Rehabilitations
Tariff
Lack of investment
60
47
44
43
Lenght km
51
50
40
29
30
20
26
12
10
1400
700
1200
600
1000
500
800
400
600
300
400
200
200
100
0
5-10 years
0
CHP2
CHP3
CHP4
Number of transformers
15-30 years
35-50 years
6, 10 kV cabel lines
above 55
13
STRUCTURE
Current
State
Challenges
Vision,
Fundamental
Principles and Priority
Areas
and
Implementation Stage,
Criteria and Indicator
and Expected Results
TIME FRAME
Privatization
Restructuring
Medium-term National
Energy Program 8
years
Human Resource
Tariff
and
14
STATE POLICY
ON ENERGY
EFFICIENCY
ENVIRONMENT
Expected Results
In the 1st stage 2015-2023: The stage to develop energy safety resources and
backup capacity, establish a foundation for the development of renewable,
enhance normal documents and improve legal environment.
The installed power capacity will be doubled, and start using critical
technology with high parameters. Hydro will be taken place at least 10% of the
total installed power capacity and it will increase packup capacity to 10%, and
create fundament for renewable sector to development intensively, enhance
tariff system.
In the 2nd stage 2024-2030: The stage to export secondary energy and
develop sustainably the renewable sector.
The backup capacity of power system will be reach at 20% and share of
renewables will be reach at 30%. Integrated smart energy system will be
created by connecting regions with high capacity transmission lines. State
owned Power companies will be become a public company. Distribution and
supply service will be privatized and energy sector will be worked as a
competitive marked with regulation. Secondary energy will be exported by
connecting with North east Asian countries with high capacity DC lines.
2014
/Base year/
-10%
3%
-16.22 %
14.4 %
1st stage
/by 2023 /
10 %
10 %
0%
11.2%
2nd stage
/by 2030/
20%
15 %
5%
9.14 %
13.7%
10.8%
7.8%
7.62%
20%
30%
0.52 ton 2
equivalent
0.49 ton 2
equivalent
0.47 ton 2
equivalent
0%
20%
40%
CFB
Sub Critical
Coal Bed
Methane,
Battery Energy
Storage,
Pumped Storage
Super Critical,
Ultra S/Critical,
Hydrogen,
Concentrated
Solar Plant
20
Coal Based
Renewable based
21
PLANNED PROJECTS
100 MW Capacity Extention
of Darkhan and Erdenet
Telmen PP 100 MW
Ulaanbaatar:
CHP 5 450 MW
Tuul-Songino Pumped Storage 100
W
Baganuur PP 600 MW
Western
region PP
MW, Hovd
Hydro PP
EG HPP 315 MW
Shuren HPP 300 MW
Capacity Expansion of
Dornod CHP
100 MW
Bayanteeg PP 60 MW
PROJECT
PROJCT COST
ESTIMATION
/Million US.D/
BIDDING
PROCESS
DEVELOP ELECTRIC
POWER LINE AND Finance-build-trasfer
SUBSTATION
39.1
BIDDING
DEVELOP ELECTRIC
Develop drawingPOWER LINE AND
Finance-build-transfer
SUBSTATION
87.7
BIDDING
Develop drawingFinance-build-transfer
53.3
BIDDING
Develop drawingFinance-build-transfer
72.1
BIDDING
43.1
BIDDING
DEVELOP ELECTRIC
Develop drawingPOWER LINE AND
Finance-build-transfer
SUBSTATION
54.5
BIDDING
DEFINITION
DEVELOP ELECTRIC
POWER LINE AND
SUBSTATION
DEVELOP ELECTRIC
Undurkhaan-Choibalsan 220kV transmission
POWER LINE AND
line, substation project
SUBSTATION
DEVELOP ELECTRIC
Baganuur-Ulaanbaatar transmission line,
POWER LINE AND
substation project
SUBSTATION
Baganuur-Undurkhaan 220kV transmission
line, substation
DEVELOP
Oyutolgoi-Tsagaan suvraga transmission ELECTRIC POWER
line, substation project
LINE AND
SUBSTATION
DEVELOP
Mandalgovi-Arvaikheer 220kV
ELECTRIC POWER
transmission line, substation project
LINE AND
SUBSTATION
DEVELOP
Nariin sukhait-Tavantolgoi 220kV
ELECTRIC POWER
transmission
LINE AND
6/18/2015 line, substation project
SUBSTATION
CONCESSION
TYPE
BRIEF INTRODUCTION
Build-transfer
45.9
Oyutolgoi-Tsagaansuvraga 220 kV 2
circuit 160 km transmission line,
BIDDING
Oyutolgoi substation expansion, 220/22
kV Tsagaan suvraga substation project
Build-transfer
66.3
BIDDING
Build-transfer
82.9
BIDDING
Power plant
PROJECT NAME
DEFINITION
CONCESSION
TYPE
CAPACITY
PROJECT
BIDDING
COST /USD PROCESS
PROJECT STATUS
AWARDED PROJECTS
ULAANBAATAR
FITH COMBINED
1
HEAT POWER
PLANT
TELMEN POWER
PLANT PROJECT
DEVELOP COMBINED
HEAT POWER PLANT
FOR ULAANBAATAR
CITY
TUUL-SONGINO
WATER
3
RESOURCE
PROJET
DEVELOP WATER
PURIFY PLANT & 100
MWT WATER LOAD
POWER PLANT
BAGANUUR
4 COMBINED HEAT
POWER PLANT
DEVELOP POWER
PLANT BASED ON
BAGANUUR DISTRICT
AND COAL ORE
CONCESSION AGREEMENT
PPA
SIGNED ON JUNE, 2014
BUILD-OPERATE- 450 MW CAPACITY 1.5 Billion
NEGOTIATIO PPA & OTHER REGUERED
TRANSFER
POWER PLANT
USD
N
AGREEMENTS ARE UNDER
NEGOTIATION
CONCESSION AGREEMENT
ABOUT
BUILD-OPERATE285.0 Million
SIGNED ON JUNE 2013
100 MW CHP PLANT
FINANCIAL
TRANSFER
USD
CONCESSIONAIRE IS WORKING
CLOSE
FOR REACHING FINANCIAL CLOSE
CONCESSION AGREEMENT
ABOUT
BUILD-OWN100 MW POWER 183.0 Million
SIGNED ON APRIL, 2014
FINANCIAL
OPERATE
PLANT
USD
CONCESSIONAIRE IS WORKING
CLOSE
FOR REACHING FINANCIAL CLOSE
CONCESSION AGREEMENT
PPA
SIGNED ON APRIL, 2015
BUILD-OPERATE- 700 MW CAPACITY 950.0 Million
NEGOTIATIO PPA & OTHER REQUERED
TRANSFER
POWER PLANT
USD
N
AGREEMENTS ARE UNDER
NEGOTIATION
24
Power plant
BIDDING PROJECTS
BIDDING
PROJECT STATUS
PROCESS
DORNOD
DEVELOP CHP POWER
CONTRACT
BUILD-OPERATE- 100 MW CAPACITY 160.0 Million
CONCESSION AGREEMENT IS
COMBINED HEAT PLANT FOR DORNOD
NEGOTIATIO
TRANSFER
POWER PLANT
USD
UNDER NEGOTIATION
POWER PLANT
PROVINCE
N
DEVELOP POWER
CHANDGANA
PLANT BASED ON
POWER PLANT,
600 MW CAPACITY
CHANDGANA COAL
BUILD-OWNPOWER LINE
POWER PLANT AND
ORE AND POWER LINE OPERATE FOR
CONCESSION AGREEMENT
FROM BAGANUUR
POWER LINE FROM 1.6 Billion BIDDING IN
FROM BAGANUUR
POWER PLANT,
NEGOTIATION IS UNDER
TO UNDURKHAAN
BAGANUUR TO
USD
PROGRESS
PROVINECE TO
BUILD TRANSFER
PREPARATON
AND UNDURKHAAN
UNDURKHAAN AND
UNDURKHAAN &
FOR POWER LINE
TO CHOIBALSAN &
SUBSTATION
UNDURKHAAN TO
SUBSTATION
CHOIBALSAN
DEVELOP POWER
CONCESSION AGREEMENT
TEVSHIIN GOVI
PLANT BASED ON
BUILD-OWN600 MW CAPACITY 900.0 Million BIDDING IN
NEGOTIATION IS UNDER
POWER PLANT
TEVSHIIN GOBI COAL
OPERATE
POWER PLANT
USD
PROGRESS
PREPARATON
ORE
EXPANSION ON
"CHOIR"
SUBSTATION
EXPANSION ON
EXISTING CAPACITY
"CHOIR"
"CHOIR" SUBSTATION
OF '220/110/35/6 kV
CONCESSION AGREEMENT
19.0 Million BIDDING IN
SUBSTATION
AND
BUILD-TRANSFER
TO 200 MW,
NEGOTIATION IS UNDER
USD
PROGRESS
EXPANSION
DIFFERENTIATION
EXPANSION ON
PREPARATON.
STATION
EXISTING CAPACITY
OF 220/110/35/6 kV
DIFFERENTIATION
STATION
PROJECT NAME
DEFINITION
CONCESSION
TYPE
CAPACITY
25
Power plant
PROJECT NAME
DEFINITION
CONCESSION
TYPE
CAPACITY
BIDDING
PROCESS
PROJECT STATUS
DEVELOP HYDRO
POWER PLANT ON BUILD-OPERATEKHOVD RIVER, BAYANTRANSFER
ULGII AIMAG
NO BIDDING
KHOVD IRVER
2 HYDRO POWER
PLANT PROJECT
DEVELOP HYDRO
POWER PLANT ON BUILD-OPERATEKHOVD RIVER, KHOVD
TRANSFER
AIMAG
64 MWT HYDRO
POWER PLANT
NO BIDDING
TOTAL REQUIRED INVESTMENT IN ENERGY SECTOR /Including: Transmission line and power plants/
Total transmission line estimated costs:
-Awarded projects:
-Bidding projects:
26
For planned and potential projects of power plant and transmission lines:
As a financier, Contractor, Equipment supplier, Consulting service
Concession agreement: Built-Operate-Transfer, Built-Transfer,
Independent Power Producer
PPP
27
THANK YOU
FOR YOUR ATTENTION