Module 4

Pipe laying

Oil & Gas introduction Course for NonEngineers SEC

1. Pre-lay Survey
Inspecting the seabed along the intended pipe line route before construction
Consisting of:
- Desktop study
- Bathymetry profile (side scan)
- Geotechnical sampling
- Visual inspection

Oil & Gas introduction Course for NonEngineers SEC

2. Sand Waves (or Dunes)


Ridges on the seabed formed by current

San Francisco Bay

Dubai Coast

Oil & Gas introduction Course for NonEngineers SEC

3. Span Correction
Measure to prevent free span of pipe line

Free Span

Oil & Gas introduction Course for NonEngineers SEC

4. Landfall
Location where pipe line comes onshore

Land fall Ca Mau


Trenching

Oil & Gas introduction Course for NonEngineers SEC

5. J-Lay
Pipes have J-shape when in laying process

Lay direction

Application: Water depth more than 200m

Oil & Gas introduction Course for NonEngineers SEC

J-lay Tower
6

6. S-Lay
Pipes have S-shape when in laying process

Lay direction

Application: Shallow water (Vietnam)

Oil & Gas introduction Course for NonEngineers SEC

Monitoring

7. Stinger
Support frame to guide pipe line overboard during S-laying

To prevent small bending radius

Oil & Gas introduction Course for NonEngineers SEC

8. Pipe Laying Ship (or Vessel)


Mono hull vessels to lay pipe lines offshore

Application: Small diameter pipe with small bending radius

Oil & Gas introduction Course for NonEngineers SEC

9. Pipe Laying Barge


Flat barge or Semi used to lay offshore pipe lines

Application: Larger diameter pipe


Drivers for choice?;
- Water depth
- Diameter pipe line
Oil & Gas introduction Course for NonEngineers SEC

10

10. Pipe Tensioner


Gripper on the vessel that holds the string during the laying process

Oil & Gas introduction Course for NonEngineers SEC

11

11. Beveling
Machining a sloped surface on the pipe end for welding purposes

Oil & Gas introduction Course for NonEngineers SEC

12

12. Line up Tools


Tool to align two joints of pipe before welding

IPEC Canada

Oil & Gas introduction Course for NonEngineers SEC

13

13. Field Weld


Welding two joints of pipe together offshore

Oil & Gas introduction Course for NonEngineers SEC

14

14. Field Joint


Completed connection between two joints done offshore

Oil & Gas introduction Course for NonEngineers SEC

15

15. Welded Pipe


Steel pipe made of plate steel

Longitudinal
pipe

Spiral welded Pipe


Use: Construction purposes/small
Wall thickness

Use: Big
diameter/Wall
thickness
Pipe lines

Oil & Gas introduction Course for NonEngineers SEC

16

16. Seamless pipe


Hot rolled steel pipe with no weld

Use: Petrochemical industry, small


diameters/big wall thickness
Drivers for choice?;
- Wall thickness
- Diameter pipe
- Mechanical properties
Oil & Gas introduction Course for NonEngineers SEC

17

17. Weight coat


Concrete jacket around the pipe line to weigh it down and protect it

Use: Offshore Pipelines

Length of one Joint: 12 m

Oil & Gas introduction Course for NonEngineers SEC

18

18. PLEM
Pipe Line End Manifold = Protecting structure housing valves and T-pieces

Purpose: Fix position of


pipe line end and protect
valves/actuators from
fishing nets and anchors

Oil & Gas introduction Course for NonEngineers SEC

19

19. Spool Piece


Small pipe piece made to order to connect two flanged pipe ends

Measurement by Divers: Geometrics

Can also be used as expansion piece

Oil & Gas introduction Course for NonEngineers SEC

20

20. Pressure testing


Testing the pipeline for leaks by pressurizing it and monitoring the pressure

Important moment for pipe laying


contractor

Test pressure depends on design


pressure and safety factor

Oil & Gas introduction Course for NonEngineers SEC

21

21. Testable Gasket


Sealing between two flanges that can be tested without pressurizing the line

Connection
test kit

Flange connection

Oil & Gas introduction Course for NonEngineers SEC

22

22. Pigs
Plugs that are send trough the pipe line by compressed air or water to perform duties
Duties:
Cleaning
Measuring
Inspection

ROSEN
Malaysia

Pig Launch

Oil & Gas introduction Course for NonEngineers SEC

23

23. Cleaning (Pre commissioning)


Remove all debris and particles from the pipe line

Oil & Gas introduction Course for NonEngineers SEC

24

24. Drying (Pre commissioning)


Remove all water residue and vapor before commissioning of the pipe line

Pig train

Techniques used:
1. Glycol/Methanol
2. Air drying
3. Vacuum drying

Purpose:
To avoid corrosion (Hydrate) and
contamination of product

Oil & Gas introduction Course for NonEngineers SEC

25