Page 1 of 9
December 1, 2011
1. Regulating reserve plant. NorthWestern Energys Dave Gates Generating Station consists of three Pratt & Whitney
Power Systems 50-MW Swiftpacs. Also shown is the 500,000-gallon raw water storage tank on the right and the 500,000gallon demineralized water storage tank on the left. Courtesy: NorthWestern Energy
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 2 of 9
contracted power purchases from outside its service territory. By 2005, quickly rising power prices caught the
attention of the Montana Public Service Commission and state legislators.
The Montana legislature passed House Bill 25 (HB 25) in May 2007, which allowed NWE to build and add new
generation to its rate base as part of the states move back toward the regulated utility model. Also in 2007, NWE
was faced with two problems that threatened its grid-balancing authority responsibilities: Purchased ancillary
services were becoming more costly, and renewal of those contracts was just a few years away.
A self-assessment found that NWEs most important generation need was not baseload or peaking power, but
regulating reserve power. The Shaw Group was retained to perform an independent engineering assessment of
technology and plant siting options for a plant designed to provide regulating services to NWEs Montana grid.
Shaw completed site and technology recommendations in December 2007. The generation technology options were
quickly narrowed to fast-acting natural gasfired, simple cycle combustion turbines (CTs). The turbine selection
process began in January 2008 and ended in July 2008 when an agreement was reached with Pratt & Whitney
Power Systems (PWPS) for three Swiftpacs, based on the FT8 combustion turbine (Figure 2). In addition, Shaw was
retained as the owners engineer for the project in the fall of 2008.
2. The race goes to the swift. A close-up of the Pratt & Whitney Power Systems FT8 combustion turbine inside the
enclosure shows how the output shaft on the right connects with a double-ended generator. Another FT8 is attached to the
other side of the generator. The entire package is a 50-MW Swiftpac. Courtesy: Pratt & Whitney Power Systems
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 3 of 9
contracts for balancing power, also called ancillary services, to balance on a moment-to-moment basis the
differences between scheduled electric supply and demand within its assigned region.
The instantaneous measure of this balance is known as the Area Control Error (ACE), which is calculated every 4
seconds. The Control Performance Standards are a measure of how well NWE manages its ACE. Generally, NWEs
main focus is to manage the magnitude of the ACE within prescribed limits.
Design requirements for grid regulation are stringent because grid balancing requires a plant to rapidly and
continuously change load, usually within seconds to minutes. Demands on ancillary service providers in areas, like
Montana, with growing amounts of nondispatchable generation are expected to grow.
Nondispatchable resources for NWE include about 150 MW of wind plus small roof-top photovoltaic systems that are
net metered. Because wind is very difficult to accurately schedule and can be highly volatile on a moment-to-moment
basis, it is difficult to integrate into the transmission grid. For example, generation from the Judith Gap Wind Farm in
south central Montana frequently ramps up from 0 MW to 131 MW in 10 minutes and ramps back down to 0 MW in
the same length of time. DGGS was sized and designed to accommodate load changes of this magnitude and
speed.
Regulatory Details
As part of the original project assessment, NWE identified a dozen potential sites in Montana where the plant could
be located. Shaw developed a matrix of important siting parameters, such as availability of natural gas, transmission
congestion, land use, and other similar factors. A first cut reduced the dozen sites to a final four. A more definitive list
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 4 of 9
of 35 selection criteria was then developed to assess the four sites. The final analysis indicated that the best site was
at Mill Creek in southwestern Montana outside of Anaconda. This site had minimal electrical congestion and was
near an existing substation and a main natural gas trunk line. The site was an existing brown fieldspecifically, a
Superfund siteso permitting and land use issues were minimized as long as the site was properly remediated prior
to construction.
The application for approval to construct the plant was filed with the Montana Public Service Commision (MPSC) in
August 2008. A provision of HB 25 allowed the MPSC up to 270 days after receipt of an adequate application to
issue a decision, with the option of an additional 90 days. If an air quality permit is required, MPSC is required to hold
a public hearing on the application at least 30 days following the issuance of an air permit. These published
regulatory lead times did not match well with the practical need to have the plant in service by the time contracts with
third-party ancillary service providers expired. The first MPSC hearings were held in February 2009 and, despite
several interveners, the MPSC granted project approval in May 2009.
In addition, an application for an air quality permit was filed with the Montana Department of Environmental Quality
(MDEQ) in August 2008. The MDEQ required additional air dispersion modeling that was completed three months
later. The final, complete application was submitted on Dec. 1, 2008. The MDEQ approved the permit in January
2009. The air quality permit includes the future, fourth unit.
Construction Plan
While the regulatory process continued, the selection of the engineer, procure, and construct (EPC) contractor
continued. Fifteen pre-bid qualification inquiries were sent out in October 2008. Seven bidders were invited for a
formal presentation, and four bidders were then selected to submit proposals. Those proposals were received on
February 20, 2009, concurrently with the MPSC hearings. NewMech, a Corval Group company, was selected as the
project EPC contractor. NewMech subcontracted the engineering work to Zachry. A full project release was
contingent on the MPSC approval. MPSC issued a final order on May 19, 2009, allowing the project to go forward.
The form of the EPC contract was a guaranteed maximum price (GMP), excluding change orders. As part of its
owners engineer responsibilities, Shaw instituted a robust change order review process to ensure that added project
costs were closely managed. On the upside, if NewMech brought the project in for less than the GMP, then the
contractor shared in 50% of the difference between actual cost and the GMP. The project was brought in under
budget, which resulted in a split in the savings.
DGGS was designed to be constructed in two stages. The first phase entailed installation of the three Swiftpacs by
the end of 2010 (Figure 3). The second and future phase is the addition of a fourth Swiftpac, which could occur
between 2012 and 2015, depending upon NWEs need for additional regulation service in Montana.
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 5 of 9
3. New Year, new start. This photograph was taken on January 1, 2011, the day that DGGS entered commercial service.
The louvered boxes on the package are the air inlet filters, one for each of the two combustion turbines that constitute a
Swiftpac. Courtesy: NorthWestern Energy
Resource Sourcing
Natural gas to fire the CTs was obtained from an existing NWE pipeline running between Morel, which is about a
mile north of Warm Springs, and Anaconda. A new 24-inch natural gas pipeline, approximately 2.5 miles long,
connected the plant with the pipeline. To control pressure in the pipeline, a compressor station, using three, 1,100horsepower compressors, was located about 2.5 miles from the facility near State Highway 48.
The fuel gas line to the plant also has an important second use: It is designed to provide instantaneous storage (line
packing) in order to respond to rapid changes in gas demand caused by the CTs responding to grid regulation
needs.
Water for DGGS is sourced from the Silver Lake pipeline, a 34-inch-diameter line that carries water from areas west
of Anaconda to Butte. The pipeline crosses the southern end of NWEs property. Only 600 feet of small-diameter
pipeline was needed to bring water into the plant, where it is stored in a 500,000-gallon raw water storage tank.
From that storage tank, water is filtered in multimedia filters and then sent through cartridge filters before entering the
reverse osmosis unit to remove dissolved minerals. The reverse osmosis effluent is further processed through an
electro-deionization skid to meet the water injection purity requirements of the combustion turbine manufacturer and
then stored in a second 500,000-gallon demineralized water storage tank. The water injection flow rate to each CT
for NOx control is approximately 26 gpm. Wastewater produced at the plant is primarily reverse osmosis reject water
that is transported to the City of Anacondas wastewater treatment plant via a 2-mile-long sewer line (Figure 4).
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 6 of 9
4. High plains plant. The three Swiftpacs are located in the center of the plant site, each with a single, 90-foot-tall stack,
approximately 15 feet in diameter. The gas compression building is in the center, and the back-up diesel storage tanks, the
ammonia storage system, and the fuel transfer building are on the right. The water treatment building and water storage
tanks are on the left. Courtesy: NorthWestern Energy
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 7 of 9
NWE proposed BACT emission rates at the peak values found during operating simulations, irrespective of
maximum generation capacity. NWE requested as long an averaging period as possible, to account for periodic non
steady state operations. As emissions vary greatly between fuels, BACT emission rates are fuel dependent.
Originally, NWE proposed a concentration-based BACT rate, as PWPS could guarantee a fairly constant emission
rate across most operational loads, down to approximately 6% of maximum turbine load. In order to provide the
emissions guarantees at the low turbine loads, the turbine vendor provided a slight derate in emissions reduction at
maximum generation. This derate provided predictable water injection control and flame stability at the low loads the
turbines would typically experience at DGGS.
The application for the air quality permit was submitted in August of 2008 with emission rates approximately two to
four times higher than current BACT levels for aeroderivative turbines operating at steady state. NOx and CO were
proposed as concentrations (ppm) as a reasonable assurance that the plant was meeting BACT at all operational
loads, including low turbine loads. Thirty-day averages were proposed on all pollutants; PWPS was also willing to
guarantee the emissions on an hourly basis.
The MDEQ requested that modeling of PM2.5 be expanded to include additional sources, most of which had never
been modeled or fully inventoried before. The models, which included nine years of meteorological data, were
modified to include more than 300 additional sources. The new models were then run several dozen times, each run
requiring more than 400 computing hours. Several months were required to develop the inventories, rerun all
modeling, and modify the application.
The revised application was resubmitted in December 2008 and was determined administratively complete. The final
air quality permit was issued on Jan. 22, 2009, in support of the MPSC hearings in February 2009.
Third-Party Operator
When its plants were sold to PPL Montana in 1999, most of NWEs expertise in plant operation was lost. Because
the May 2009 MPSC order approving DGGS required NWE to operate the plant with its own personnel after three
years, in early 2009, NWE solicited bids from three third-party operators. NAES was selected in June 2009, and the
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 8 of 9
plant operations contract was in place by the end of 2010. Having the plant operator on board early was helpful
during discussions with the potential CT and other major equipment suppliers regarding plant operations and spare
parts inventory needs.
5. Follow the leader. This figure shows the automatic generation control (AGC) signal requested from NorthWestern
Energys System Operations Control Center (pale blue line) and the output from Dave Gates Generating Station following
that signal (green line) over a typical 24-hour weekday. Engines are started and stopped as required to follow the AGC
signal. The vertical scale is 100 MW, maximum. Wind power capacity of 150 MW is connected to this system. Courtesy:
NorthWestern Energy
As of September 30, 2011, the six engines at the DGGS have operated 16,488 hours, producing approximately
251,000 MWh net. Two-unit availability has been 99.38%, which provides sufficient regulation capacity except in
extreme temperature conditions when three units are needed. An impressive 5,465 engine starts have occurred
since commercial operation. The plant has served as a reliable replacement for third-party contracts for regulation
service by consistently meeting a monthly control performance standard (CPS2) greater than 90%, the required
reliability standard (Figure 5, p. 60).
William T. Rhoads, PE (william.rhoads@northwestern.com) is general manager, generation; Dr. John S.
Fitzpatrick (john.fitzpatrick@northwestern.com) is executive director, state and local community relations; and
Richard P. Walsh (richard.walsh@northwestern.com) is environmental manager, large projects for NorthWestern
Energy. Gary T. Wiseman, PE (gary.wiseman@shawgrp.com) is a project manager for The Shaw Group.
Close Window
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013
Page 9 of 9
http://www.powermag.com/print/issues/features/NorthWestern-Energy-Builds-a-Regulatin... 1/30/2013