Sunteți pe pagina 1din 8

A-PDF Split DEMO : Purchase from www.A-PDF.

com to remove the watermark

W A T E R

A N D

E N E R G Y

I N T E R N A T I O N A L

ROCK MASS CHARACTERISTICS


OF UNDERGROUND CAVERNS
H.C. KHANDURI
Sr. Geologist

HARISH BAHUGUNA
Geologist

P.C. NAWANI
Director

Geological Survey of India, Dehradun

Abstract
Construction of underground powerhouse at Tehri was inevitable
because of non-availability of the space on the surface and the huge
excavation (required to accommodate the powerhouse) of the steep
back slopes. Excavation of the two huge cavities of the powerhouse
complex i.e., machine hall and transformer hall was tackled carefully.
Geotechnical assessment made earlier revealed that both these
cavities are located in the most competent rock mass at Tehri dam
site i.e. phyllitic quartzite massive (PQM) and phyllitic quartzite thinly
bedded (PQT) GradeI. Considering the geotechnical parameters
including the in-situ stress measurements, the alignment of these
cavities was preferred in N0209 direction. As the alignment was
also against the dip direction, the excavation in these cavities was
free from any major failure. These gigantic caverns were stabilized
by means of rock bolting and shotcreting barring a patch in the
crown of machine hall where a 5m band of deformed rock mass,
associated with a major longitudinal shear, was encountered. The rock
cover between the two cavities was insufficient (i.e. less than 2D),
because of which problem of convergence was recorded during the
excavation of the bus ducts in the common wall. Multiple bore hole
extensometers (MPBAX) and load cells were installed to monitor the
rate and extent of convergence, and a number of deep cable anchors
(blind and through) were installed to stabilize the area.

1. Introduction
Tehri project is to be developed
in two stages of 1000 MW each.
The stage I, known as HPP, has
been completed and it consists
of an underground Powerhouse
of 1000 MW (4 x 250 MW). The
three main cavities in stage I viz.,
machine hall, transformer hall, and
Special Issue on Tehri Dam Project

CK

expansion chambers of the complex


are located in the available most
competent rocks (PQM). These
cavities run parallel to each other
and are aligned normal to the
strike of rocks. Other cavities in
the complex are draft tubes, bus
ducts, ventilation tunnels, cable
tunnel, drainage galleries, adits
and tail race tunnels etc., beside
water conductor system comprising
84

CK

head race tunnels, pressure


shafts, butterfly valve chamber,
penstock assembly chamber and
penstocks.
The intakes for drawing the water
from the reservoir into the headrace
tunnels (HRTs) have invert at EL
720m. Out of the four HRTs, the
two of 8.5m dia are meant for
serving the machines of HPP
while the other two will carry the
water into four machines of PSP
(Stage-II). The transformer hall
cavity is common for both stages
HPP and PSP. Two TRTs of 9.0m
dia each will take the water back
to the river.
The surface powerhouse was
not viable because of the huge
excavation that was required to
create space on the existing steep
(450-550) rocky slopes in order
to accommodate the proposed
powerhouse complex (Stage I &
II). Such excavation would have
endangered the stability of the
steep slopes. The choice of an
underground powerhouse thus
became imperative.

2. Geology at the Site


2.1 At the Tehri dam site the
folded metasedimentary rocks
of Chandpur phyllites (Pt 3
Proterozoic-III) having variable
proportions of argillaceous and
arenaceous constituents (Nawani,
1994) are exposed. Considering
the rhythmicity of intercalated band
of arenaceous and argillaceous
materials and varied degree of
tectonisation effects in them, the
phyllites at the dam site have
been classified into mainly four
lithological variants.
Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

E N E R G Y

CK

I N T E R N A T I O N A L

Fig. 1 : Perspective View of Tehri Hydro Power Plant, Tehri Dam Project

Phyllitic quar tzite massive


(PQM)
Phyllitic quartzite thinly bedded
(PQT)
Quartzitic phyllite (QP)
Sheared/schistose
(SP)

phyllite

2.2 The primary bedding and


foliation planes are dipping 45-650
towards N195-2400 and 30-420
towards N160-1800 respectively.
Local variations in the dip direction
associated with general warping
have also been noticed. Different
discontinuities identified at the site
were grouped in different orders,
Special Issue on Tehri Dam Project

CK

depending on their continuity.


A total of eight joint sets were
delineated at the site. The shear
zones were graded according to the
thick ness of clay gouge and their
relation with the bedding/foliation
joints. The shear zones with their
attitude parallel/sub parallel to
bedding/foliation were identified
as longitudinal (L shears) and
those having attitude diagonal to
bedding/foliation were termed as
diagonal (D shears) shears.
2.3 At the site eleven major L
shears and six major D shears
were delineated. A block tectonic
model was evolved for the Tehri
dam with an aim to understand the
85

bearing of the major L and D shears


on the state of geomechanical
behavior of the rock mass at the
dam site. The geometry, orientation,
frequency and interplay of major
(IV order) L and D shears
have considerably affected the
geomechanical characteristics of
the rock mass and it provided a
scope of dividing different sites
into different tectonic blocks.
Four different blocks were then
identified and the boundaries of
these tectonic blocks are defined
by major diagonal shears. The
underground power house is
mainly confined to block number
3.This paper aims at discussing
the rock mass characters of the
Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

two main cavities i.e. machine hall


and transformer hall.

3. Machine Hall
Cavity
The machine hall cavern (197m x
67m x 24m) is aligned in N0200
direction he rock cover available
above the roof of the machine hall
cavity is about 350 m (Photo-1).
The excavation of the machine
hall was started, along its axis
at the crown level, by driving
the approach adit 4 (with it is
crown El 628.75m). The crown
of the cavity is at El 630.2m and
the bottom most portion is at El
563m. The transformer hall and
expansion chambers are located in
the upstream are aligned parallel
to the machine hall.
3.1 The Roof Section
The arch portion was widened
to the required width with the

E N E R G Y

CK

I N T E R N A T I O N A L

crown at El 630.2m and SPL


at El 624.0m, from RD 0.0 to
188.0m. The roof of the cavity
exposed interbedded sequence
of phyllitic quartzite massive
(PQM) and phyllitic quartzite thinly
bedded (PQT) and occasional
bands of quartzitic phyllite (QP).
The sheared/shattered phyllite
(SP) occupies the affected zones/
tectonised zones along the major
shear planes (Fig. 1). The primary
bedding joints were dipping at 4255/N195-235 and were cut across
by the foliation planes dipping at
38-44/N160-210. The variation in
the attitudes of the beds is due
to folding pattern, which is very
conspicuous between RDs 51.0m
and 95.0m, on the left half of the
cavity (facing the heading).
The rocks are traversed by two
prominent joint sets, dipping
towards 52-78/N315-350 and
38-80/N020-060 and one random
joint set dipping at 78/N140.
Intersections of northwesterly and

northeasterly dipping joints with S0


and S1 joints, which are sometimes
transformed to L-shears, have
caused prominent wedge failures.
Over breaks of maximum 1.5m or
so, due to wedge failures have
been observed between RDs 69
and 75.0m and RDs 82.0 and
86.0m. The characteristics of the
prominent joint sets are described
in Table 1.
Numerous minor and major
longitudinal (L) shears have been
intercepted at different locations.
Minor shears (clay gouge 2-10cm
thick) dipping at 42-600 /N150-190,
50/N180, 51/N160 and 50/N200
have been encountered at the
crown level at RD 81.0m, 94.0m,
114.0m and 156.0m respectively.
Major shear zones (clay gouge
more than 10cm thick) dipping
at 38/N180, 58/N220 and 62/
N230 were exposed at the crown
level at RD 29.0m, RD 45.0m
and RD 120.0m respectively. A
highly deformed zone existed at
the crown at RD 115.0m-120.0m
confined between a minor shear
dipping at 50/N210 and the major
shear dipping of 62/N230. The
geological map of machine hall
is given in Fig. 2.
3.2 Wall Sections

Photo 1 : Panoramic View of Machine Hall


Special Issue on Tehri Dam Project

CK

86

The mapping revealed different


bands of PQM, interbedded PQM &
PQT, PQT and deformed/tectonised
PQT and sheared phyllite. The
primary bedding and foliation,
which are the most prominent joints
as well, dip at 48o-65o/N195-220
and 35o-46o/N165-175 respectively.
On the left wall, structural wedge
induced, over break has been
observed at number of places.
Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

E N E R G Y

CK

I N T E R N A T I O N A L

Fig. 2 : 3-D Geological Map of Machine Hall Cavity (Crown Portion), Tehri Dam Project (From R.D. 0.0 m to R.D. 188.0 m

Table 1 : Characteristics of the prominent joint sets in the Machine


hall cavern.
Sl.
No.

Orientation
(Dip amount/direction)

Spacing
(cm)

1.
2.
3.

42-58/N165-235 (S0 joints)


38-44/N160-210 (S1 joints)
52-78/N315-350

20-50
5-20
20-200

4.
5.

38-80/N020-060
78/N140 (random)

1.5-100
7-10

The rock mass parameters


estimated are Q=10-13, RMR=6568, GSI=60-63.
3.3

Insitu Stress
Measurements

Insitu stress measurements were


made at a number of locations,
in the underground openings,
Special Issue on Tehri Dam Project

CK

Roughness
Smooth
Smooth
Rough to
moderately smooth
Quartz veins
Smooth

Maximum
continuity
(strike wise) (m)
5-20
5-20
0.5-4.0
0.3-8.0
1.0-3.0

in the powerhouse complex


by flat jack tests, geophysical
method (by Russian Experts),
and by hydrodynamic fracturing
(by CSMRS).
The analysis of flat jack tests
data, demonstrates that average
values of stresses equal to
87

Maximum Horizontal Stress (H) (1)


= 8.5MPa (in northerly direction)
Minimum Horizontal Stress (h) (3) =
2.65 MPa (in southerly direction)
Vertical Stress (V) (2) = 5.2MPa
The natural stresses computed in
the powerhouse cavity (machine
hall) by geophysical methods were
found to be
Maximum Horizontal Stress (H) (1) =
10-11MPa (in northerly direction)
Minimum Horizontal Stress (h) (3)
= 6 MPa (in southerly direction)
Vertical Stress (V) (2) = 9MPa
Based on hydraulic fracturing tests
conducted at a depth of 370m, i.e.
at the roof level (El 632m) of the
transformer hall cavity, the following
Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

E N E R G Y

I N T E R N A T I O N A L

Table 2 : Details of the shears exposed in the Machine hall cavity


(right wall)

LSZ1
LSZ2
LSZ3

Orientation
Dip
Dip
amount
azimuth
58
N195
55
N215
48
N170

4
7-11
7-15

10
20-25
20-25

LSZ4

46-50

N180-205

3-4

8-12

LSZ5

48-57

N195-200

3-15

5-35

LSZ6

43-50

N180-205

3-12

15-30

LSZ7
LSZ8
LSZ9
LSZ10
LSZ11

50-55
54
50
55
40

N195-200
N205
N190
N205
N215

<2-9
2-3
<2
5-7
3-5

LSZ13
LSZ14

52
57

N215
N215

<2
8-12

20-25
8-10
4-5
15-20
10-hed
rock
3-4
20-30

LSZ15
LSZ16
LSZ17
LSZ18

54
52
58
48

N215
N195
N195
N200

2-3
<2
<2
15-20

5-7
5-10
2-3
40-50

CK

stresses have been worked out.


These results were found to be
more realistic.
Maximum Horizontal Stress (H) (1)
= 5.26Mpa (orientation N16.20E,
i.e. parallel to cavern

Clay crushed rock


Clay and crushed rock
Clay and crushed rock and
crushed rock
Clay and crushed rock and
crushed quartz vein
Clay, crushed rock and
crushed quartz vein
Clay and crushed rock and
crushed quartz vein
Clay and crushed rock
Clay and crushed rock
Clay, crushed rock
Clay, crushed rock

Minimum Horizontal Stress (h) (3)


= 3.14 MPa (normal to the major
principal stress)
Vertical Stress (V) (2) = 10Mpa
(corresponding to 370m rock
cover)
The following horizontal stress
ratios have been used in
analysis
Major horizontal stress ratio H/V
= 0.52

Clay, crushed rock


Clay, crushed rock and
quartz vein
Clay, crushed rock
Clay and crushed rock
Clay
Clay, crushed rock and
crushed quartz vein

Minor horizontal stress ratio h/V


= 0.31

Table 3 : The strength characteristics of the rock mass and major discontinuities determined in the
longitudinal direction of Power House Cavern.
Sl. Engineering geological Specific Modulus of Poissons
Strength
Orientation Parameters of sets of fractures
ratio
characteristics of fractures
No. element of rock mass gravity deformation
gm/cc E (kg.cm2)

C
Strike
Spacing
(kg.cm2 azimuth
(m)
of dip
Phyllitic Quartzite Massive
2.76
75000
0.22
45
8
_
_
Phyllitic Quartzite
(PQM)
Massive (PQM)
Phyllitic Quartzite thinly
2.77
75000
0.22
45
8
_
_ Phyllitic Quartzite thinly
bedded (PQT)
bedded (PQT)
Sets of fractures
Sets of fractures
1. Faults/shears of order-IV
_
_
_
22
0.2
N190 1. Faults/shears of order-IV
____
2.

Tectonic fractures and


joints of order V and VI
3.
Tectonic fractures and
joints of order V and VI

24

0.4

N220

24

0.4

N190

4.

Joints of order VII

35

1.0

N200

Tectonic fractures and


joints of order V and VI
3.
Tectonic fractures and
joints of order V
and VI
Tectonic fractures and
joints of order V
and VI
4.
Joints of order VII

24

0.4

N310

5.

Joints of order VII

35

1.0

N020

5.

Tectonic fractures and


joints of order V and VI

Special Issue on Tehri Dam Project

CK

88

2.

Joints of order VII

35
20
____

2
2

Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

E N E R G Y

3.4 Geotechnical Assessment


and the Critical Zones

A highly deformed/shattered/
p u cke r e d zo n e c o n f i n e d
between two minor bedding
shears has been encountered
at RD115-120m (crown
level) where frequent failures
of wedges formed due to
intersecting S0/S1 and NE/NW
joints were observed. This
critical shear zone has been
traced downwards on the right
wall (RD102-108, El 616m) and
left wall (RD 96m 101m, El
616m) where it is characterized
by multiplicity of minor shear
seams confined between two
important L shears. Q 1-2,
RMR 17 and support load P
3.5 kg/cm2 (35 tonnes/m2) were
estimated for the reach.
Intersection of the bedding
shears with the NE/ NW
dipping joints led to formation
of wedges, which caused over
breaks at several locations at
the crown, at RD 12-17m, RD
66-94m and RD156-165m.

Similar tectonised rock


mass marked by puckering,
silicification multiple shears
and frequent water dripping,
has been recorded on the
left wall (at El 624m) at RD
46-48m, 61-66m, 86-88m and
151-163m. These bands are
downward extension of their
crown counterparts.

NE dipping joints are very


critical for the left wall whereas
NW dipping joints control the
right wall configuration. Frequent
failures along them have
jeopardized the stability of 1m
wide berm for the crane beam
all along the cavern length,
particularly between RD 150
and 170m.

PQM rocks on the zero wall


resulted in block toppling due
to wedge formation between
S0/S1 and NE dipping joints.

Two zones of sheared/shattered


phyllite/deformed rock mass
characterised by Q= >2-2.2,
RMR= 30-35 and GSI= 25-30
were intersected on either wall,
in continuity from the crown
level downwards.

Profuse water dripping was


noticed from the crown at RD
82-85m, RD 113-119m, RD
152-155m, RD 166-169m and
RD 175-177m.
Another critical reach of
deformed /shattered distressed
PQT was recorded at RD 159
166m (crown level) and is
continuing down to RD 141151m (El 609m) on the left wall.
A fault plane dipping 800/N160
(clay 3-5cm) with about 1m
displacement also falls within

Special Issue on Tehri Dam Project

CK

I N T E R N A T I O N A L

this zone. Overbreak of the


order of 2m on both the
sides of centre line is clearly
seen.

The Roof

As the strike of the deformed


rock mass and the bus-duct
alignment are sub parallel,
serious stability problems were
recorded in the crown portion
of these openings (bus ducts)
for a considerable length during
excavations. Longer rock bolts
(+ 15m length) followed by steel
89

CK

rib supports were installed in


these critical zones.

Convergence measured by tape


extensometer is reported as
nil at El 609m. The measures
taken in the crown sections
between El 618m and El 622m
are reported to be only about
7mm between January and
March 1997. Six horizontal
drill holes were drilled from
the middle drainage gallery
into the sidewalls of the
machine hall and transformer
hall and multiple borehole
extensometers have been
installed in these holes to
monitor the convergence. In this
critical reach, steel rib support
was suggested.

3.5 Stabilisation Measures

For the defor med zones


(crown RD 115-120m and 159164m) charged with seepage,
immediate reinforced shotcreting
preferably with steel fibers, and
rock bolting (resin), normal or
oblique (not less than 150-200)
to the bedding planes, was
done at close spacing in a
staggered fashion to stitch the
weak zones properly, with a
provision of drainage holes.

In general, resin type (fully


grouted with cement capsules)
rocks bolt of 10m and 15m
lengths, dia 32mm, @ 2.0m
horizontally and 1.5m vertically,
with wire-mesh shotcreting
of 100mm thickness (in two
layers) and drainage holes
were recommended for the wall
sections.

Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

Longer rock bolts (> 15m length)


followed by steel rib supports
were advised in the deformed
zones.

In the end wall section, spot


bolting was advised in addition
to general pattern of rock
bolting and the negative slopes
were made up by concrete
backfilling.

Controlled blasting was done


to avoid over breaks.

Scooping/removal of sheared
rock mass for 20cm depth
fo l l o w e d b y b a c k f i l l i n g ,
systematic rock bolting and
wire-mesh shotcreting were
recommended as protective
m e a s u r e s fo r t h e w a l l
sections.

3.6 Cable Anchoring on the


Right Wall of Machine Hall
Cavity and Bus Duct
The 40 m wide rock - column
between machine hall and
transformer hall cavities was
considered inadequate and in order
to provide additional strength and
stability to, it was emphasised to
install cable anchors. The cable
anchoring in these cavities had
been done on two patterns i.e.
blind hole cable anchoring and
through hole cable anchoring.
3.7 Power House
Instrumentation
In order to record convergence
taking place during or after the
excavation in the power house
complex, instruments like multiple
bore hole extensometer (MPBX)
and load cells were installed in
Special Issue on Tehri Dam Project

CK

E N E R G Y

I N T E R N A T I O N A L

the machine hall (at ch 45m, 99m


and 155m), transformer hall and
in the bus ducts no. 3 and 4.
The extensometers were installed
from the drainage galleries of the
powerhouse and wall convergence
of different orders was recorded
in them.

4. Transformer Hall
Cavity
The transformer hall cavity aligned
parallel to the machine hall cavity
in N0200 direction measaures161m
x 34m x18.5m. Exacavation for the
cavity began from the crown at El
634.0m by widening the section of
the exploratory drift driven earlier
along its alignment.

The bedding dips at 56-64/N205220 and foliation at 42-45/N170180. A wide variation in the attitude
of bedding due to complex folding
was recorded between RD 78.0m
and RD 101.0m. A steep and wavy
fault trace (78/N190) recorded at
RD 76.0m-78.0m is marked with
silicification and intense jointing.
4.2 Geotechnical Assessment
The PQM rocks encountered in this
opening belong to fair category
with Q = 5.7 to 13 whereas
highly silicified PQT (Q=7-9) and
the puckered PQT rock mass
have been assessed as poor to
fair type with Q varying from 4
to 6.

The nor theasterly dipping


joints and bedding/foliation
are forming structural wedges,
causing over breaks at the
crown at RD 6-8m, 24-25m
and 42-45m.

Northwesterly dipping joints,


occasionally, caused sliding of
blocks, particularly on the right
SPL and as such, control the
right wall configuration.

4.1 The Roof


The cavity driven across the
rock strike, exposes interbedded
sequence of phyllitic quartzite
massive (PQM) and phyllitic
quartzite thinly bedded (PQT).
PQM bands are exposed along
the central line of crown at RD
60.0m-62.0m, RD 78.0m-102.0m
and RD 116.0m-129.0m, and
in rest of the area, PQT and
undifferentiated PQT/PQM rocks
were present (Fig. 3). The PQM
band between RD 78.0m and RD
102.0m manifests characteristic
deformation features marked
by folding, crumpling, shearing
tension gashes, silicification and
water dripping. The PQT and its
tectonised variants are mainly
intercepted on the crown at RD
42-46m, 65-72m and 106-117m,
which extend further downwards
on the both walls. (Fig. 2)

90

CK

4.7 Stabilisation Measures

Rock bolts 6-8m long with


spacing 2m c/c followed by
shotcrete layer were provided,
to stabilize the roof.

Steel ribs @ 75cm from RD


81 to 87m and additional rock
bolts @ 1.0m staggered from
RD 87-96m were provided.

Drainage holes, through the


shotcrete layer, in the water
seepage zones were left in order
to check pore pressure.
Vol. 64, No. 1, Jan. - Mar., 2007

A-PDF Split DEMO : Purchase from www.A-PDF.com to remove the watermark

W A T E R

A N D

E N E R G Y

CK

I N T E R N A T I O N A L

Fig. 3 : 3-D Geological Map of Transformer Hall (Crown Portion), Tehri Dam Project

of the machine hall between


RD 115m - RD 120m which
was stabilized by providing
reinforced shotcreting with steel
fibers, and resin type rock
bolts.

5. Conclusions

The geotechnical assessment


done in the earlier stages
helped in locating the machine
hall and transformer hall cavities
in the most competent strata
(Grade-I) available at Tehri
dam site. The orientation of
the cavities was also favorable
(against the dip direction) and
as such no major geotechnical
problem was encountered
during the excavation.
A zone of sheared/deformed
and highly puckered rock mass
was noticed along the crown

Special Issue on Tehri Dam Project

CK

For the wall sections, resin type


rocks bolt of 10m and 15m
lengths, dia 32mm, @ 2.0m
horizontally and 1.5m vertically
and wire-mesh shotcreting of
100mm thickness (in two layers)
along with provision of drainage
holes were recommended as the
main stabilisation measures.

In the crown of transformer


hall cavity steel ribs @ 75cm

91

from RD 81 to 87m and spot


bolts @ 1.0m staggered from
RD 87-96m were provided.
The rock cover between the two
cavities was 42m, which was less
than 2D (considering the width of
machine hall i.e. 24m) because of
this insufficient rock cover, problem
of wall convergence was noticed
during the excavation of bus
ducts. A maximum convergence
of 21.60mm was recorded by the
multiple borehole extensometers. To
stabilize the common wall between
the two cavities, 73 blind and 27
through cable anchors of 77 tonne
capacity were provided.

Vol. 64, No. 1, Jan. - Mar., 2007

S-ar putea să vă placă și