Documente Academic
Documente Profesional
Documente Cultură
W A T E R
A N D
E N E R G Y
I N T E R N A T I O N A L
HARISH BAHUGUNA
Geologist
P.C. NAWANI
Director
Abstract
Construction of underground powerhouse at Tehri was inevitable
because of non-availability of the space on the surface and the huge
excavation (required to accommodate the powerhouse) of the steep
back slopes. Excavation of the two huge cavities of the powerhouse
complex i.e., machine hall and transformer hall was tackled carefully.
Geotechnical assessment made earlier revealed that both these
cavities are located in the most competent rock mass at Tehri dam
site i.e. phyllitic quartzite massive (PQM) and phyllitic quartzite thinly
bedded (PQT) GradeI. Considering the geotechnical parameters
including the in-situ stress measurements, the alignment of these
cavities was preferred in N0209 direction. As the alignment was
also against the dip direction, the excavation in these cavities was
free from any major failure. These gigantic caverns were stabilized
by means of rock bolting and shotcreting barring a patch in the
crown of machine hall where a 5m band of deformed rock mass,
associated with a major longitudinal shear, was encountered. The rock
cover between the two cavities was insufficient (i.e. less than 2D),
because of which problem of convergence was recorded during the
excavation of the bus ducts in the common wall. Multiple bore hole
extensometers (MPBAX) and load cells were installed to monitor the
rate and extent of convergence, and a number of deep cable anchors
(blind and through) were installed to stabilize the area.
1. Introduction
Tehri project is to be developed
in two stages of 1000 MW each.
The stage I, known as HPP, has
been completed and it consists
of an underground Powerhouse
of 1000 MW (4 x 250 MW). The
three main cavities in stage I viz.,
machine hall, transformer hall, and
Special Issue on Tehri Dam Project
CK
CK
W A T E R
A N D
E N E R G Y
CK
I N T E R N A T I O N A L
Fig. 1 : Perspective View of Tehri Hydro Power Plant, Tehri Dam Project
phyllite
CK
W A T E R
A N D
3. Machine Hall
Cavity
The machine hall cavern (197m x
67m x 24m) is aligned in N0200
direction he rock cover available
above the roof of the machine hall
cavity is about 350 m (Photo-1).
The excavation of the machine
hall was started, along its axis
at the crown level, by driving
the approach adit 4 (with it is
crown El 628.75m). The crown
of the cavity is at El 630.2m and
the bottom most portion is at El
563m. The transformer hall and
expansion chambers are located in
the upstream are aligned parallel
to the machine hall.
3.1 The Roof Section
The arch portion was widened
to the required width with the
E N E R G Y
CK
I N T E R N A T I O N A L
CK
86
W A T E R
A N D
E N E R G Y
CK
I N T E R N A T I O N A L
Fig. 2 : 3-D Geological Map of Machine Hall Cavity (Crown Portion), Tehri Dam Project (From R.D. 0.0 m to R.D. 188.0 m
Orientation
(Dip amount/direction)
Spacing
(cm)
1.
2.
3.
20-50
5-20
20-200
4.
5.
38-80/N020-060
78/N140 (random)
1.5-100
7-10
Insitu Stress
Measurements
CK
Roughness
Smooth
Smooth
Rough to
moderately smooth
Quartz veins
Smooth
Maximum
continuity
(strike wise) (m)
5-20
5-20
0.5-4.0
0.3-8.0
1.0-3.0
W A T E R
A N D
E N E R G Y
I N T E R N A T I O N A L
LSZ1
LSZ2
LSZ3
Orientation
Dip
Dip
amount
azimuth
58
N195
55
N215
48
N170
4
7-11
7-15
10
20-25
20-25
LSZ4
46-50
N180-205
3-4
8-12
LSZ5
48-57
N195-200
3-15
5-35
LSZ6
43-50
N180-205
3-12
15-30
LSZ7
LSZ8
LSZ9
LSZ10
LSZ11
50-55
54
50
55
40
N195-200
N205
N190
N205
N215
<2-9
2-3
<2
5-7
3-5
LSZ13
LSZ14
52
57
N215
N215
<2
8-12
20-25
8-10
4-5
15-20
10-hed
rock
3-4
20-30
LSZ15
LSZ16
LSZ17
LSZ18
54
52
58
48
N215
N195
N195
N200
2-3
<2
<2
15-20
5-7
5-10
2-3
40-50
CK
Table 3 : The strength characteristics of the rock mass and major discontinuities determined in the
longitudinal direction of Power House Cavern.
Sl. Engineering geological Specific Modulus of Poissons
Strength
Orientation Parameters of sets of fractures
ratio
characteristics of fractures
No. element of rock mass gravity deformation
gm/cc E (kg.cm2)
C
Strike
Spacing
(kg.cm2 azimuth
(m)
of dip
Phyllitic Quartzite Massive
2.76
75000
0.22
45
8
_
_
Phyllitic Quartzite
(PQM)
Massive (PQM)
Phyllitic Quartzite thinly
2.77
75000
0.22
45
8
_
_ Phyllitic Quartzite thinly
bedded (PQT)
bedded (PQT)
Sets of fractures
Sets of fractures
1. Faults/shears of order-IV
_
_
_
22
0.2
N190 1. Faults/shears of order-IV
____
2.
24
0.4
N220
24
0.4
N190
4.
35
1.0
N200
24
0.4
N310
5.
35
1.0
N020
5.
CK
88
2.
35
20
____
2
2
W A T E R
A N D
E N E R G Y
A highly deformed/shattered/
p u cke r e d zo n e c o n f i n e d
between two minor bedding
shears has been encountered
at RD115-120m (crown
level) where frequent failures
of wedges formed due to
intersecting S0/S1 and NE/NW
joints were observed. This
critical shear zone has been
traced downwards on the right
wall (RD102-108, El 616m) and
left wall (RD 96m 101m, El
616m) where it is characterized
by multiplicity of minor shear
seams confined between two
important L shears. Q 1-2,
RMR 17 and support load P
3.5 kg/cm2 (35 tonnes/m2) were
estimated for the reach.
Intersection of the bedding
shears with the NE/ NW
dipping joints led to formation
of wedges, which caused over
breaks at several locations at
the crown, at RD 12-17m, RD
66-94m and RD156-165m.
CK
I N T E R N A T I O N A L
The Roof
CK
W A T E R
A N D
Scooping/removal of sheared
rock mass for 20cm depth
fo l l o w e d b y b a c k f i l l i n g ,
systematic rock bolting and
wire-mesh shotcreting were
recommended as protective
m e a s u r e s fo r t h e w a l l
sections.
CK
E N E R G Y
I N T E R N A T I O N A L
4. Transformer Hall
Cavity
The transformer hall cavity aligned
parallel to the machine hall cavity
in N0200 direction measaures161m
x 34m x18.5m. Exacavation for the
cavity began from the crown at El
634.0m by widening the section of
the exploratory drift driven earlier
along its alignment.
The bedding dips at 56-64/N205220 and foliation at 42-45/N170180. A wide variation in the attitude
of bedding due to complex folding
was recorded between RD 78.0m
and RD 101.0m. A steep and wavy
fault trace (78/N190) recorded at
RD 76.0m-78.0m is marked with
silicification and intense jointing.
4.2 Geotechnical Assessment
The PQM rocks encountered in this
opening belong to fair category
with Q = 5.7 to 13 whereas
highly silicified PQT (Q=7-9) and
the puckered PQT rock mass
have been assessed as poor to
fair type with Q varying from 4
to 6.
90
CK
W A T E R
A N D
E N E R G Y
CK
I N T E R N A T I O N A L
Fig. 3 : 3-D Geological Map of Transformer Hall (Crown Portion), Tehri Dam Project
5. Conclusions
CK
91