3) Electrical:
The protective relay, metering, and control settings must be
supplied by the customers engineer or from a Power System
Study performed prior to commissioning.
Apply Control Power to Switchgear
Verify Electrical Breaker Operation
_ Open and close each breaker with breaker control switch
_ Open and close each breaker from remote terminals (if
applicable)
_ Close breaker, trip circuit breaker utilizing protective relay
(if applicable)
_ Ensure 86 LOR operates (if applicable)
_ Ensure breaker a and b contacts operate
Verify Metering
_ Functionally test metering devices by energizing circuits to
rated values
4) Operational Controls
_ Test Automatic Transfer System (if applicable)
_ Other Operational Test
5) Final details after Witness Test are complete.
_ Complete mimic bus.
_ All remaining nameplates installed.
_ Drawers and doors aligned.
_ Danger labels and other warning stickers.
_ Vacuum and perform final cleaning of gear.
_ Touch up painting.
_ Check Shutter alignment.