Sunteți pe pagina 1din 19

Technical issues on the integration of long

distance AC cables in HV and EHV networks


C - Cable Systems

Luig COLLA

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Cable line with line-connected shunt


compensation at both terminals

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Cable length reduces maximum transmissible active power


DC offset of no-load energization current in highly shunt
compensated cables
Risk of low order harmonic resonance
Uneven loading when cables are paralleled with overhead lines
Short circuit level increases in the network
Temporary overvoltages
Self-excitation of synchronous generators
Capacitive switching
Lightning protection
Blue: specific issues of long cable lines
Black: issues that are normally dealt with by ordinary grid planning analyses
Green: issues that can be mitigated by proper shunt compensation design
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Cable length reduces maximum transmissible


active power
Ampacity is still the fundamental limiting factor for
the length of HV cable between compensating stations.
Active and charging current load the cable;
maximum active power transmission is attained when
the same reactive power is evacuated at both ends of
the CL.
Neglecting losses, this corresponds to having equal
terminal voltages.
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Short cable

Too long cable


IQ
ITL
ITL

IQ
IP

IP

ITL = Maximum current at thermal limit


IQ = Capacitive current
IP = Active current
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Optimal operation of a long cable line


VMX
US

UR=US

Voltage
-QS

QR

PS

PR

Reactive power
Active power

Sending

Receiving

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Maximum length of AC cables


PMax vs. L plots
Maximum active power transfer, 230 and 400 kV-50 Hz cables (lossless)

1500

2500 sqmm, U=380 kV


2500 sqmm, U=400 kV
2500 sqmm, U=420 kV
1200 sqmm, U=220 kV
1200 sqmm, U=230 kV
1200 sqmm, U=240 kV

1350
1200

1440
1280
1120
Active power (MW)

Active power (MW)

1050
900
750
600

960
800
640

450

480

300

320

150

160

25

50

75

100

125

150

Cable length ( km)

175

200

225

Maximum active power transfer, 345 kV and 525 kV-60 Hz cables (lossless)

1600

250

2500 sqmm, U=500 kV


2500 sqmm, U=525 kV
2500 sqmm, U=550 kV
1520 sqmm, U=330 kV
1520 sqmm, U=345 kV
1520 sqmm, U=360 kV
0

25

50

75

100

125

150

175

200

225

Cable length ( km)

Approximately:
Cable lines long 0.75LMax retain PMax0.75SZ
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

250

Shunt compensation
Shunt compensation design was based on openended operation. Typical figures for 400kV-50 Hz
CLs are:
Energizing bus voltage variation: US3%

Receiving (open) end overvoltage: UR10%


For slow reclosure it should be U1.2UM

Cable-charging current: Ic 400 A (U=1.4UM)


Rated cable-charging breaking capacity of standard
400 kV CBs is 400 A (IEC 62271-100)

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Shunt compensation
Examples of shunt compensation degree of n.2
400kV cable lines vs. short circuit power
645

95

80

128

90

581

70

112

85

549

60

96

80

517

50

80

75

485

40

64

70

453

30

48

65

421

20

32

60

389

10

16

55

357

10

12

14

16

Short-circuit power Psc (GVA)

18

20

22

0
24

Shunt compensation degree Ksh (%)

144

Sending end 3%
Receiving end 10%
Icap 400A (@1.4 Um)

SR rated power Qsr (Mvar)

100

90

Shunt compensation degree Ksh (%)

400 kV-50 Hz, 2500 sqmm cable - 100 km long

160

50

Sending end 3%
Receiving end 10%
Icap 400A (@1.4 Um)

10

12

14

16

18

20

Short-circuit power Psc (GVA)

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

22

613

325
24

SR rated power Qsr (Mvar)

400 kV-50 Hz, 2500 sqmm cable - 25 km long

100

Shunt compensation
Examples of shunt compensation degree vs. 400kV
cable line length. 2 short circuit power values
400 kV-50 Hz, XLPE underground cable, 2500 mm2 Cu (P sc=4000 MVA)

87.5

87.5

75

75

62.5
50
37.5
25
Sending end 3%
Receiving end 10%
Icap 400A (@1.4 Um)

12.5
0

400 kV-50 Hz, XLPE underground cable, 2500 mm2 Cu (P sc=12000 MVA)

100

Shunt compensation degree Ksh (%)

Shunt compensation degree Ksh (%)

100

15

30

45

60

75

90

Length of cable line (km)

105

120

135

62.5
50
37.5
25
Sending end 3%
Receiving end 10%
Icap 400A (@1.4 Um)

12.5

150

15

30

45

60

75

90

105

120

Length of cable line (km)

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

135

150

Shunt compensation
Examples of shunt compensation degree vs. 230kV
cable line length. 2 short circuit power values
230 kV-50 Hz, XLPE underground cable, 1200 mm2 Cu (P sc=4000 MVA)

87.5

87.5

75

75

62.5
50
37.5
25
Sending end 3%
Receiving end 10%
Icap 250A (@1.4 Um)

12.5
0

25

50

75

100

125

150

Length of cable line (km)

175

200

225

230 kV-50 Hz, XLPE underground cable, 1200 mm2 Cu (P sc=12000 MVA)

100

Shunt compensation degree Ksh (%)

Shunt compensation degree Ksh (%)

100

Sending end 3%
Receiving end 10%
Icap 250A (@1.4 Um)

62.5
50
37.5
25
12.5

250

15

30

45

60

75

90

105

120

Length of cable line (km)

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

135

150

Route map of the existing and future interconnection


lines between Sicily and the Italian mainland

red: existing 400 kV;

blue: future 400 kV;

green: existing 220 kV

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Single-line diagram of the existing (1000 MVA) and planned (2x1000 MVA)
400kV interconnection lines between Sicily and the Italian Mainland
Sicily
Sorgente
20.6 km

Italy's Mainland
Villafranca

Scilla
38 km

2.2 km
+)

+)

2.5 km

6.5 km

+)

4.9km

34.6 km

0.6 km
14.3 km

21.8 km
400 kV Underground cable
400 kV Land cable in tunnel
400 kV Submarine cable

Red: existing;

29.1 km

2.5 km

+)

*)

Rizziconi

400 kV Single circuit Overhead line

+) 275 Mvar Shunt Reactor

400 kV Double circuit Overhead line

*) 150250 Mvar Shunt Reactor with variable

Mvar output

Blue: Under construction

Shunt compensation degree of new lines ~ 88% of cable charging


power, to be performed by means of a permanently connected shunt
reactors. Busbar reactors used for network reactive power balance
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Need for the operator to limit maximum allowed cable


capacitance in the specification

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

DC offset of no-load energization current

Phase currents in case of no-load energization of a 43 km long


400kV submarine cable line.
a) Synchronized switching not simulated
b) Synchronized switching simulated
Circuit breakers ability to force the current zero crossing has to be
verified/tested
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Risk of low order harmonic resonance


S sc
Qcap

f r = f1

800

P3.0

[kV]
600

[MJ]

400

phase S

2.5

200

2.0

0
-200

phase T

1.5

-400
-600

1.0

-800
0,0

(f il

t 60a 120

0,2
e 0,98
h l4

2b

t)

aTURBC e0,4

0,8

0,6

[s]

1,0

360
[kV]

0.5

0.0

284

phase R
0.0

0.2

0.4

0.6

0.8

208
132
56
-20

10

15
harmonic order

20

25

30

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

[s]

1.0

Risk of low order harmonic resonance


Design and operation countermeasures could include:
- Use of synchronized switching
- Proper specification of shunt reactors saturation
characteristics
- Limit to the specification value of cable capacitance
- Restrictions to the allowed grid configurations (to
be avoided whenever possible)

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Conclusions

Transmitting power over long lengths with HV and EHV cable


lines is feasible
Projects including long cables require an ad hoc system
design
The longer is the cable length the higher is the expected
interaction with the network and therefore the design horizon
has to be extended to the network (f.i. risk of resonances)
To ensure the feasibility of a project including a long cable is
therefore necessary to focus also on the network and on the
expected system operating conditions

IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

Some references

M. Rebolini, L. Colla, F. Iliceto "400 kV AC new submarine cable links between Sicily
and the Italian mainland. Outline of project and special electrical studies" CIGRE
2008 conference
L.Colla et alii HVAC submarine cable links between Italy and Malta. Feasibility of
the project and system electrical design studies CIGRE 2010 conference
L. Colla, F. M. Gatta, F. Iliceto, S. Lauria Design and operation of EHV transmission
lines including long insulated cable and overhead sections IPEC 2005 Singapore,
November 2005
L. Colla, F. M. Gatta, S. Lauria. No-load energization of a long 380 kV cable:
temporary overvoltages. EEUG-Meeting 2006. Dresda, September 2006
S. Lauria, F. M. Gatta, L. Colla. "Shunt compensation of EHV Cables and Mixed
Overhead-Cable Lines" IEEE Power Tech Conference 2007
L. Colla, S. Lauria, F. M. Gatta "Temporary Overvoltages due to Harmonic
Resonance in Long EHV Cables" in Proc. International Conference on Power
System Transients (IPST 2007), Lyon 2007
L. Colla, S. Lauria, F. M. Gatta "Lightning Overvoltages in HV-EHV Mixed
Overhead-Cable Lines" in Proc. International Conference on Power System
Transients (IPST 2007), Lyon 2007
IEEE PES Insulated Conductors Committee Spring 2012 meeting - Seattle, March 25-28, 2012

S-ar putea să vă placă și