Documente Academic
Documente Profesional
Documente Cultură
Previous Document
WARNING
This document is the property of United
Technologies Corporation (UTC). You may not
possess, use, copy, or disclose this document or
any other information in it, for any purpose
including
without
limitation
to
design,
manufacture, or repair parts, or to obtain FAA or
other government approval to do so, without
UTCs express written permission. Neither receipt
nor possession of this document alone, from any
source, constitutes such permission. Possession,
use, copying, or disclosure by anyone without
UTCs express written permission is not
authorized and may result in criminal and/or civil
liability.
15 January 2002
Rev. 2
Homepage
PROPRIETARY WARNING - 1
Previous Document
Revision Number
Date of Issue
Issued By
Original Manual
September, 1999
Ken Nagy
Rev 1
September, 2000
Ken Nagy
Rev 2
Mike Cowan
REV-2
15 January 2002
Homepage
REVISION RECORD-1
Previous Document
INTRO-1
15 January 2002
Homepage
Previous Document
If submitting the completed form via standard mail, please address to:
Pratt and Whitney Power Systems
80 Lamberton Road
Windsor, CT 06095
Attn: Customer Technical Services
Publications Supervisor
If submitting the manual change recommendation via facsimile transmission please
forward to: (860) 565-8500. Address the facsimile cover sheet to the attention of the
Publications Supervisor, PWPS Customer Technical Services.
4.0 Change Symbols
The FT8 Construction manual is subject to amplification and revision as additional
information becomes available. Revised text is indicated by a black vertical line in either
margin of the page, adjacent to the affected text, like the one printed next to this
paragraph. The change symbol identifies the addition of either new information, a
changed procedure, the correction of an error, or a rephrasing of the previous material.
5.0 Warnings, Cautions and Notes
The following definitions apply to WARNINGS, CAUTIONS and NOTES found
throughout this manual.
WARNING
A procedure, practice or condition, etc. which may result in
injury or death if not carefully observed or followed.
CAUTION
A procedure, practice, or condition, etc. which may result in
damage to equipment if not carefully observed or followed.
NOTE
A procedure or condition, etc. which is essential to
emphasize or expand upon.
REV- 2
INTRO-2
15 January 2002
Homepage
Previous Document
REV- 2
INTRO-3
15 January 2002
Homepage
Previous Document
Company:
PWPS Customer Technical Support
80 Lamberton Road
Windsor, CT 06095
Signature:
REV- 2
Title:
INTRO-4
15 January 2002
Homepage
Previous Document
Title
Page
1.1
Introduction
1-1
1.2
1-1
1.3
General Requirements
1-1
1.4
Electrical Safety
1-3
1.5
Construction Safety
1-10
1.6
1-24
1.7
First Aid
1-35
1.8
1-35
1-1
Strength of Plank
1-36
1-2
1-36
1-3
1-37
1-4
1-38
1-5
1-39
1-6
1-40
1-7
Bridling of Spreaders
1-41
1-8
1-42
1-9
1-43
Tables
REV-2
15 January 2002
Homepage
TOC-1
Previous Document
1-10
Strength of Turnbuckles
1-43
1-11
Strength of Chains
1-44
1-12
1-44
1-13
Strength of Shackles
1-45
1-14
1-46
1-1
Accident Procedures
1-34
1-2
1-47
Charts
Title
Page
2.1
Site Layout
2-1
2.2
Excavations
2-1
2.3
2-2
2.4
2-2
2.5
Piles
2-3
2.6
Foundation Forming
2-5
2.7
Embedded Hardware
2-5
SECTION 3 CONCRETE
Paragraph
Title
Page
3.1
Introduction
3-1
3.2
Composition of Concrete
3-1
REV-1
15 January 2002
Homepage
TOC-2
Previous Document
3.2.1
Cement
3-2
3.2.1.1
Types of Cement
3-2
3.2.2
Aggregates
3-4
3.2.3
Water
3-4
3.3
3-6
3.4
3-11
3.5
Weather Conditions
3-12
3.6
3-13
3.7
3-13
Title
Page
4.1
Introduction
4-1
4.2
Sources of Information
4-1
4.3
4-2
4.4
Equipment Arrivals
4-2
4.5
4-2
4.6
Freight Collect
4.7
Handling Paperwork
4-3
4.8
Storage of Equipment
4-3
4.9
Material Issue
4-4
REV-1
15 January 2002
Homepage
4-3
TOC-3
Previous Document
Figure
4-1
4-5
Title
Page
5.1
Introduction
5-1
5.2
5-1
5.3
Vendor-designed Equipment
5-14
5.4
5-14
5.5
5-15
5.6
5-20
5.7
5-20
5.8
5-23
5.9
5-29
5.10
5-31
5.11
5-32
5.12
5-40
5.13
5-41
5-1
5-4
5-2
5-34
Tables
REV-1
15 January 2002
Homepage
TOC-4
Previous Document
Title
Page
6.1
Scope
6-1
6.2
Inventory
6-1
6.3
Tools
6-1
6.4
Standard Practices
6-1
6.5
6-2
6.6
6-2
6.7
6-2
6.8
6-3
6.9
Control House
6-4
6.10
6-5
6.11
Testing
6-5
Table
6-1
Battery Report
6-6
Title
Page
7.1
7-1
7.2
7-6
7-1
7-11
Tables
REV-1
15 January 2002
Homepage
TOC-5
Previous Document
7-2
Valve Symbols
7-3
7-12
7-1
7-15
7-2
7-16
7-3
7-17
7-4
7-18
7-5
7-19
7-6
7-20
7-7
7-21
7-8
7-22
7-9
7-23
7-10
7-24
Figures
Title
Page
8.1
Introduction
8-1
8.2
Sequence (abbreviated)
8-1
8.3
Procedures
8-2
REV-1
15 January 2002
Homepage
TOC-6
Previous Document
Title
Page
9.1
Introduction
9-1
9.2
9-1
9.3
Checkout
9-3
9.4
Startup
9-4
9.5
Commissioning
9-5
9.6
Sequence
9-5
REV-1
15 January 2002
Homepage
TOC-7
Previous Document
Title
TPM-AR-1
TPM-AR-2
FR-1
FR-2
TPM124
TPM126
TPM129
TPM130
TPM132
TPM139
Title
REV-1
15 January 2002
Homepage
TOC-8
Previous Document
REV-2
PAGE: 1-1
15 January 2002
Homepage
Previous Document
The Prime Contractor and the PWPS Site Supervisor shall have the responsibility to
ensure that all work is performed in accordance with the safety and health regulations.
All visitors must check in with the Site Supervisor or his designate before entering the
site. The Site Supervisor should know who is on the site, and be able to caution visitors
about possible dangers.
1.3.3 Site Trailer
The Prime Contractor trailer and PWPS office trailer shall be placed as close to the
installation as practical. The trailer should be kept clean; shelves shall not be overloaded;
materials and drawings shall be stored or stacked neatly and all doorways and traffic areas
must be kept clear for safe movement and accessibility.
1.3.4 First Aid Kits
An OSHA-approved emergency first aid kit and emergency first aid instructions shall be
placed within the trailers so that they shall be easily accessible when required. The
contents of the first aid kit shall be checked at least weekly to ensure that the expended
items are replaced.
Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart D, Section 1926.50
Medical Services and First Aid.
1.3.5
Medical Attention
Hazard Communication
In recent years OSHA has placed increased emphasis on the reduction of chemical source
illness and injuries. OSHA has issued rules for a Hazard Communication Program to
increase employer and employee awareness of chemical hazards. This program ensures
that all employers receive the information they need to inform and train their employees
properly and to design and put in place employee protection programs. It also provides
necessary hazard information to employees, so they can participate in and support the
protective measures in place at their workplace.
REV-2
PAGE: 1-2
15 January 2002
Homepage
Previous Document
Paragraph 1.5.22 of this chapter outlines the requirements of the OSHA Hazard
Communication Standard, and provides the information on which steps must be taken to
comply with this Standard.
Refer to OSHA Regulations, Standards 29 CFR, Part 1910, Subpart Z, Section
1910.1200 Hazard Communication.
1.3.7
Safety Equipment
Nonmetal hard hats for site personnel and visitors shall be kept on hand and used in all
site construction areas. Ear protectors, safety glasses, welding goggles, face shields,
aprons, and rubber gloves shall be available as required under the regulations.
The trailer and areas where fire hazards exist shall be equipped with at least one fire
extinguisher of the type required for Class A, B, and C fires.
Refer to OSHA Regulations, Standards 29 CFR, Part 1910, Subpart I, Sections
1910.133 Eye and Face Protection, 1910.135 Head Protection and 1910.138 Hand
Protection
1.3.8 State Operated OSHA Programs
Under the provisions of Section 18 of the William-Steiger Act, several States operate
their own OSHA programs, as further explained in paragraph 1.6.1 of this chapter.
However, Section 18 (c) of the William-Steiger Act requires that individual state
standards and the enforcement of such standards must be at least as effective in providing
safe and healthful employment and places of employment as the Federal standards
promulgated by OSHA under the William-Steiger Act.
Therefore, the rules cited herein are to be considered the minimum standards. Further
state requirements that amend or supersede the Federal standards may be in force.
1.4
Electrical Safety
REV-2
PAGE: 1-3
15 January 2002
Homepage
Previous Document
Electrical current diffuses through the body from one contact area, usually on a hand, to
another area at a different voltage potential, such as a hand on another conductor or feet
on a wet floor with high voltage. Contact locations may exhibit burns due to the
resistance of the skin to the passage of electric current when the electrical energy is
converted into heat. If contact areas are large, such as that provided by water or good
grounding, no marks or burns may be evident.
Body organs must be in the path of the electric current if they are to experience harmful
effects. Once the skin is penetrated, the human body offers little resistance to current
flow. The path taken by the current flow determines an individuals ability to survive.
Paths through the heart or brain system may cause death from ventricular fibrillation
current passing through the heart and interrupting its proper rhythmic beat, or from
respiratory failure. Applying cardiopulmonary resuscitation (CPR) techniques may be the
only means to prevent death in such cases.
It is important to note that brief contact with a 1000 volt source with dry hands may be
less dangerous that contact with 120 volts when wet or grounded.
Investigations have demonstrated that muscular contractions increase with an increasing
current. A let-go current is defined as that which an individual can tolerate and still be
able to release his or her grip on the electrified object. If the current exceeds this value,
the victim is frozen onto the conductor.
Techniques used in the prevention of electrical shock accidents are usually limited to
isolation, insulation, and grounding.
Isolation refers to the placing of high voltage lines or equipment so as to be out of reach
of, or have adequate clearance to, workers and their equipment.
Insulation is a term which is largely self-explanatory. It is important to note however,
that the condition of the insulation determines its ability to protect against electrical
shock. Moreover, hard usage, age, and exposure can render a conductor unsafe, so that
the permanent covering or insulation on a wire or other electrical conductors should not
necessarily be considered as protection against electrical shock.
Grounding an electrical system or device is accomplished by connecting the non-current
carrying metal portion to earth ground with a conductor. Its purpose is to carry leakage
current to ground in the event of failure of the insulation. If ungrounded metal parts of a
device come into contact with the body and such leakage or fault current exists, the
body becomes the conductor to ground, resulting in possible shock, severe burning, or
death.
From an understanding of the factors involved in the use and application of electrical
energy, safe practices can be developed to prevent or minimize electrical shock accidents.
REV-2
PAGE: 1-4
15 January 2002
Homepage
Previous Document
PAGE: 1-5
15 January 2002
Homepage
Previous Document
In most cases high voltage equipment is more carefully guarded than low voltage
equipment due to the greater hazard. Some exceptions, such as the exposed high voltage
bus on switchyard equipment, require greater precautions. For example, safety barriers
may be required with exposed overhead bus leads. Also, construction activity near
switchyards, substations, or overhead power lines should not be allowed unless adequate
safety precautions have been taken.
Rubber gloves should be worn as a supplementary safety measure, never as a substitute
for safety devices or procedures. For an on-the-job test the cuffs on double-walled
electricians gloves should be rolled down toward the hand to trap and forced air into the
palms and fingers. They should not be used if they are wet or not in good condition.
Gloves should be worn, and personnel should be kept clear during the test.
1.4.4
FT8 Power Pac, Twin Pac and Swift Pac generating systems will be used with state-ofthe-art technology, vacuum circuit breakers or circuit breakers that use sulfurREV-2
PAGE: 1-6
15 January 2002
Homepage
Previous Document
hexaflouride (SF6) bottle for 13.8 kV (10.5 kV) and higher voltage applications. Rules as
given below must be observed for safe operation and maintenance of this equipment.
If air circuit breakers are to be used, such as in re-powering applications using FT8
engines to replace older engine models, personnel must observe additional safeguards for
air circuit breakers as also indicated below.
Vacuum and sulfur-hexaflouride bottle breakers are operated by high energy, high speed
mechanisms, interlocked to provide safe operating sequences. To ensure the safety of
personnel, the following rules must be observed:
1. Only qualified personnel trained in the installation, operation, and
maintenance of power circuit breakers should be allowed to work on these
breakers.
2. Do not work on an energized breaker.
3. Consult the manufacturers service instructions before any adjustment,
servicing, parts replacement, or other acts requiring physical contact with the
electrical working components or wiring of the breaker.
4. Do not work on a closed breaker.
5. Do not work on a breaker with closing springs charged.
6. Do not attempt to close the breaker by hand on a live circuit.
7. When working on equipment on the generator side of the electrical system, do
not use an open circuit breaker by itself as the sole means of isolating a high
voltage circuit. For complete isolation the circuit should be in the disconnect
position, or should be withdrawn completely.
8. For the safety of personnel performing maintenance operations on the breaker
or connected equipment, all components should be disconnected by means of
a visible break and securely grounded.
9. The circuit breaker must be either fully open or fully closed when making high
potential tests. Do not test with contact partially open.
10. During high voltage testing the operator must safeguard against X-radiation,
as explained below. Breakers must not be subject to direct current (DC) highpotential tests.
REV-2
PAGE: 1-7
15 January 2002
Homepage
Previous Document
11. The circuit breaker will display warning and caution labels. Whenever the
circuit breaker is handled or maintained, these warnings and cautions must be
followed.
When voltage is applied across the contacts of a vacuum breaker, there is the possibility
of generating X-rays. The radiation levels at normal operating voltage are negligible. At
the voltages specified for testing, it is recommended that the test operator observe
additional precautions of distance and shielding, as given in the vendors maintenance
manual.
WARNING
The breaker must not be subjected to the high voltage DC
tests since dangerous radiation may be produced.
When received and during installation, the breaker should be handled as instructed in the
vendors service manual. If it is not possible to put the breaker into service immediately,
it should be carefully protected against condensation and other forms of water. It should
be stored in a clean location, free from corrosive gases or fumes. Particular care should
be taken to protect the equipment from moisture and cement dust, as this combination has
a very corrosive effect on many parts.
In addition to the above general precautions that are also applicable to air circuit breakers,
handling main air circuit breakers requires additional care in moving because of their
size. Main breakers must never be lifted with a cable or strap in the form of a single
noose, nor should they be rolled down an incline without some means of preventing
tipping. Large breakers tend to be top heavy, and subject to rolling out of a single sling or
tipping over, endangering the equipment and personnel.
During inspection, especially if the arc chutes are lifted, personnel should stay clear of
moving parts. The arc chutes of an air circuit breaker can weigh up to approximately 400
pounds each.
Putting a wet air circuit breaker into operation could result in dangerous arcing, fire or
even explosive destruction. It is therefore very important that it be protected against
moisture and condensation during storage and handling
Before preliminary operation of the unit, the breaker should be tagged out in the test or
disconnect position and never racked in until ready to make power, except for possible
alignment checks of the primary disconnect.
REV-2
PAGE: 1-8
15 January 2002
Homepage
Previous Document
1.4.5 Motors
Before any work is performed on motors, such as coupling alignment, the operating
switch or breaker should be opened and tagged.
Motor winding should be protected against exposure to oil or water to guard against
shorting, grounding, and possible fire.
The location of the motor is important. For example, fuel forwarding equipment is not
mounted inside fuel tank dikes, as it would be a fire hazard in the event of a tank rupture.
Drive couplings should always be protected with a suitable guard.
1.4.6 Space Heaters
The generator space heaters, and exciter and switchgear cubicle strip heaters are normally
energized in the early phases of erection. The power supply is 480 VAC, with 240 VAC
across each heater. Construction personnel should be informed of the potential hazard,
since much activity is carried on in close proximity to the energized heaters, especially
those in the switchgear cubicles and the exciter housing.
During the replacement of generator shipping bearings (if used) with running bearings,
the power to the exciter heaters and any ground fault relay circuit should be de-energized.
Switchgear cubicles should be kept free from combustible material and tools to avoid a
fire or shock hazard.
Steps should be taken to keep debris from accumulating around or inside the generator,
especially during the period when the generator exhaust and lead compartment openings
are uncovered. The surface temperature of the generator space heaters or strip heaters is
high enough to ignite combustible material or burn the skin.
1.4.7
Equipment in the various enclosures and on the ancillary skids generally will be
connected to the control house via direct burial cables with terminal connections at both
ends. Connections at the load end will normally be at the driven equipment. Cables will
enter the control house through multi-cable transits in the floor under the two master
terminal board (MTB) cabinets. One is located on the control side of the control house
for the control wiring, and another one is located on the motor control center (MCC) side
for the power wiring. All connections will be made using terminal strips on the MTBs
for ease of assembly and checkout, except where connected directly to the motor starters
for some of the larger motors.
REV-2
PAGE: 1-9
15 January 2002
Homepage
Previous Document
Before removing any terminals, the applicable circuits must be de-energized and tagged
out. Also, it must be remembered that equipment must be inactive before tagging out.
For example, some equipment, such as the generator lube oil pumps, must remain
energized during coastdown.
1.4.8 Igniter Plugs
The gas turbine uses a 28 VDC ignition system, which produces a very high voltage
across an igniter plug gap. This results in a trigger spark. During functional checkout of
the ignition system, the igniter plugs should be removed from the engines, unless it can be
determined that no residual combustible mixtures could exist, such as before the fuel
lines have been connected. Personnel should be kept clear and all inflammables should
be removed from the area during testing. This is because the igniter plugs have a much
higher energy level than an automotive spark plug.
The igniter or exciter boxes must not be touched when the ignition is on or for a short
duration thereafter, because of the hazards of high voltages and high temperatures.
1.4.9
Current Transformers
REV-2
PAGE: 1-10
15 January 2002
Homepage
Previous Document
1.5
Construction Safety
1.5.1
Nonmetal hard hats shall be worn by employees working in areas where there is a danger
of head injury from impact, or from falling or flying objects, or from electrical shock and
burns. Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart E, Section
1926.100 Head Protection.
Ear protective devices shall be provided and used where the noise levels or duration of
exposures exceed those shown in Table D-2 contained in OSHA Regulations, Standards
29 CFR, Part 1926, Subpart D, Section 1926.52 Occupational Noise Exposure. In
addition, refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart E, Section
1926.101 - Hearing Protection.
Eye and face protection equipment shall be provided where machines or operations
present potential eye or face injury. Refer to OSHA Regulations, Standards 29 CFR,
Part 1926, Subpart E, Section 1926.102 Eye and Face Protection.
1.5.2
All hand and power tools and similar equipment, whether furnished by the employer or
the employee, shall be maintained in safe condition. Electric power operated tools shall
be of the approved double insulation type, or grounded in accordance with the
regulations. Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart I,
Section 301 Hand Tools and Section 302 Power Operated Hand Tools.
1.5.3 Fire Protection
The employer shall be responsible for the development of a fire protection program to be
followed throughout all phases of construction. He shall provide for the fire fighting
equipment, as specified in the regulations. As fire hazards occur, there shall be no delay
in providing the equipment necessary.
Fire fighting equipment shall be placed at potential hazard areas. It shall be readily
accessible from any point on the site. Fire fighting equipment must be periodically
inspected and maintained in an operating condition.
An asbestos blanket or fire retardant canvas shall be used when welding or burning
operations are conducted on or near the unit or related equipment to minimize the
possibility of damaging hardware, wiring or igniting flammable materials.
Availability of hydrants or other water supplies should be noted for possible use as
backup fire protection.
REV-2
PAGE: 1-11
15 January 2002
Homepage
Previous Document
Fire Prevention
Particular attention should be paid to ignition hazards and the storage of combustible
materials in any active fire prevention program. Refer to OSHA Regulations, Standards
29 CFR, Part 1926, Subpart F, Section 1926.151 Fire Prevention.
1.5.4.1 Ignition Hazards
Electrical wiring and equipment for light, heat or power purposes shall be installed in
compliance with the requirements of the regulations. Internal combustion engine
powered equipment shall be located so that the exhausts are well away from combustible
materials. Smoking shall be prohibited at or in the vicinity of operations, which
constitute a fire hazard, and shall be conspicuously posted No Smoking or Open Flame.
1.5.4.1.1
Storage
Combustible materials in open yard storage shall be piled with due regard to the stability
of piles and in no case higher than twenty (20) feet. The entire storage site shall be kept
free from accumulation of unnecessary combustible materials. Weeds and grass should
be kept down and a regular procedure provided for the periodic cleanup of the entire area.
All indoor storage shall not obstruct or adversely affect means of exit.
1.5.5
Only approved containers and portable tanks shall be used for storage and handling of
flammable and combustible liquids. Approved metal safety cans shall be used for the
handling and use of the flammable liquids in quantities greater than one gallon, except
that this shall not apply to those flammable liquid materials which are extremely hard to
pour, which may be used and handled in original shipping containers. For quantities of
one gallon or less of flammable liquids, only the original container or approved metal
safety cans shall be used for storage, use and handling. Flammable liquids shall not be
stored in areas used for exits or stairways, or normally used for safe passage of people.
Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart F, Section
1926.152 Flammable and Combustible Liquids .
REV-2
PAGE: 1-12
15 January 2002
Homepage
Previous Document
PAGE: 1-13
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-14
15 January 2002
Homepage
Previous Document
When welding near an industrial gas turbine or on or near an electric generator, the
grounding lead must be no more than 18 inches from the weld. This is to prevent any
potential of arcing through the bearings of these machines.
Welding operations are covered under OSHA Regulations, Standards 29 CFR, Part
1926, Subpart J. The following sections of Subpart J pertain:
Section 1926.350 Gas Welding and Cutting
Section 1926.351 - Arc Welding and Cutting
Section 1926.352 Fire Prevent
Section 1926.353 - Ventilation and Protection in Welding, Cutting, and Heating
1.5.9 Batteries
The sulfuric acid electrolyte solution in battery cells can burn the skin and be very
dangerous if allowed to contact the eyes. Face shield, aprons, and rubber gloves shall be
provided for workmen handling acids and batteries. Facilities for quick drenching of the
eyes and body shall be provided within twenty-five (25) feet of battery handling areas.
Facilities shall be provided for flushing and neutralizing spilled electrolyte and for fire
protection. When batteries are being charged, the vent caps shall be kept in place to
avoid electrolyte spray.
1.5.10 Accident Prevention Signs and Tags
Warning signs shall be visible at all times when work is being performed and shall be
removed or covered promptly when the hazards no longer exist.
Danger signs shall be used only when an immediate hazard exists. Caution signs shall be
used only to warn against potential hazards or to caution against unsafe practices.
Color code requirements for danger, caution, exit, safety instructions, and traffic signs are
given in OSHA Regulations, Standards 29 CFR, Part 1926, Subpart G, Section
1926.200 Accident Prevention Signs and Tags.
1.5.11 Excavations
Prior to opening an excavation, effort shall be made to determine whether underground
installations, i.e., sewer, water, fuel, electric lines, etc., will be encountered and, if so,
where such underground installations are located. Utility companies shall be contacted
and advised of proposed work prior to the start of actual excavation. Refer to OSHA
Regulations, Standards 29 CFR, Part 1926, Subpart P, Section 1926.651 Specific
Excavation Requirements.
REV-2
PAGE: 1-15
15 January 2002
Homepage
Previous Document
Daily inspections of excavations and inspections after every rainstorm shall be made by a
competent person. If evidence of possible cave-ins or slides is apparent, all work in the
excavation shall cease until the necessary precautions have been taken to safeguard
employees. Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart P,
Section 1926.651 Specific Excavation Requirements.
In excavations where employees shall be required to enter, excavated material shall be
effectively stored and retained at least 2 feet or more from the edge of the excavation.
Further specific requirements for excavations are given in OSHA Regulations, Standards
29 CFR, Part 1926, Subpart P, Section 1926.651 Specific Excavation Requirements.
Banks more than 5 feet high shall be shored or sloped to the angle or repose where a
danger of slides or cave-ins exists as a result of excavation. Sides of trenches in unstable
or soft material 5 feet or more in depth shall be shored, sheeted, braced, sloped, or
otherwise supported by means of sufficient strength to protect the employees working
within them. Further specific requirements for trenching are given in Refer to OSHA
Regulations, Standards 29 CFR, Part 1926, Subpart P, Section 1926.652
Requirements for Protective Systems.
Barriers shall be placed around all excavation, or at least in exposed areas adjacent to
personnel and equipment traffic.
1.5.12 Ladders and Scaffolding
Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart L, Section
1926.450 Scope, Application and Definitions Applicable to This Subpart and Section
1926.454 Training Requirements.
The use of ladders with broken or missing rungs or steps, broken or split side rails, or
other faulty or defective construction is prohibited. When ladders with such defects are
discovered, they shall be withdrawn immediately from service. Inspection of metal
ladders shall include checking for corrosion of interiors of open end hollow rungs.
Ladders shall not be placed in passageways, doorways, driveways, or any location where
they may be displaced by activities being conducted in any other work, unless protected
by barriers or guards. The side rails shall extend not less than 36 inches above the
landing. When this is not practical, grab rails shall be installed.
Portable ladders in use shall be tied, blocked, or otherwise secured to prevent their being
displaced. Portable metal ladders shall not be used for electrical work or where they may
contact electrical conductors. Refer to OSHA Regulations, Standards 29 CFR, Part
1910, Subpart D, Section 1910.25 Portable Wood Ladders.
REV-2
PAGE: 1-16
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-17
15 January 2002
Homepage
Previous Document
The PWPS Site Supervisor shall maintain a tagging log that will list the equipment
tagged, when it was tagged, reason for tagging, when it was released, and by whom.
Also, space shall be provided for the signature of the person who releases the equipment
for return to service. Each release must be co-signed by the PWPS Site Supervisor or his
designate. A suggested Tagging Log Format is provided in Chart 1 2 at the end of this
chapter.
1.5.14.1 Responsibilities of the PWPS Site Supervisor
1. Determines whether or not site equipment can be taken out of service, and
when.
2. Reviews with the supervisors in charge of the work the safest method of
lockout of the equipment to be worked on.
3. Verifies the tagging at the correct lockout points.
4. Determines that no voltage, pressure, toxic fumes, or any unsafe condition
exists as a result of lockout of the equipment.
5. Issues indexed tag(s) as required, upon request, for tagging equipment.
6. Confirms with the supervisor in charge of the work that the equipment to be
worked on has been correctly locked out.
7. Obtains release from the supervisor in charge of the work that it is complete
and that the equipment can be returned to normal service.
8. Removes the lockout tags and verifies that all equipment is in normal status.
9. Informs any and all on-site personnel, directly or through PWPS
representatives, that tag out procedures are in effect, and that only the person
tagging the equipment can clear tag(s) to release equipment.
1.5.14.2 Responsibilities of the Work Supervisor
1. Determines area or work affected and requests lockout of the equipment
through the PWPS Site Supervisor.
2. Together with PWPS Site Supervisor determines the lockout points required
to allow safe working conditions on the equipment.
3. Upon completion of the tagging verifies that all points have been correctly
locked out and the equipment is safe to work on.
REV-2
PAGE: 1-18
15 January 2002
Homepage
Previous Document
4. Informs the PWPS Site Supervisor upon completion of his work that the
equipment is available for return to normal status.
1.5.14.3 General Rules for Tagging
1. The supervisor in charge of work on the equipment requiring tags must have
the equipment tagged in his name.
2. The person named on the tag or his one-time designate is the only person who
may initiate the removal of the tag.
3. No equipment tagged with a lockout tag or tags shall be operated by anyone
until all tags have been properly released and removed. In no case shall any
equipment be restored to service until all tags have been removed as
authorized.
4. Equipment shall be tagged as follows:
A. Remotely controlled equipment - Tags shall be attached to the control
switch handles and to the device itself.
B. Manually operated equipment - Tags shall be hung on the manually
operated handle.
C. Draw out type circuit breakers - Tags shall be hung on the levering-in
device when practical, or on the cubicle door for all other cases.
D. When equipment is locked out and tagged, the control circuits of that
equipment shall be locked out and tagged also. An example would be to
remove control circuit fuses for a gas generator lube oil cooling fan.
E. Entire mechanical systems or parts of systems controlling the flow of air,
water, or oil may be tagged as unit systems with lockout tags placed at the
isolating points. Any drains, vents, relief devices, or other devices, which
could, under certain conditions, allow energy in any form to accumulate,
must be tagged open with a lockout tag.
F. When installation or construction work has progressed to the point where
electrical equipment could be energized or mechanical equipment operated
from any other source, then the PWPS Site Supervisor or the customer or
their designates shall lock open and tag all switches, control apparatus,
valves, etc., that could endanger anyone working of the equipment.
REV-2
PAGE: 1-19
15 January 2002
Homepage
Previous Document
NOTE
All equipment under the customers jurisdiction shall
follow the lockout, tagging, and release procedures as
outlined above when no customer tag out procedure is in
effect. Where a customers procedure is available and in
force, it will be followed on a mutual responsibility basis
with PWPS, so as to provide maximum safety to all
personnel working on the site. The customer shall
coordinate all tagging of equipment under the customers
jurisdiction with the PWPS Site Supervisor.
1.5.15 Gas Turbine Safety Enclosure
WARNING
No person shall enter the gas turbine or exhaust enclosures
during startup or above idle speed. Equipment failure
during normal operation may expose personnel within the
enclosure to hazards that may result in serious injury or
death.
All personnel must be at least twenty (20) feet away from
the gas turbine enclosure during start cycles. The start
cycle is defined as from when the start horn activates and
until the gas turbine, including both sides of a Twin Pac if
both gas turbines are to be started, reach gas generator idle
and/or sync idle. Suitable high visibility tape or lines on
the ground shall be used to define the twenty (20) foot
boundary lines.
The Site Supervisor shall take all necessary steps to ensure that the following procedures
are adhered to:
1. Personnel shall not enter the gas turbine or exhaust enclosures during startup or
during operation above idle speed.
2. No person shall enter the gas turbine or exhaust enclosures with the gas turbine
running until he is fully instructed with regard to the following:
A. Ear and eye protection and nonmetal hats must always be worn in the
enclosure, or when standing near an open door.
REV-2
PAGE: 1-20
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-21
15 January 2002
Homepage
Previous Document
site of the person entering the enclosure, must be ready to lend assistance if
needed.
4. For personnel safety reasons, as well as to minimize the risk of equipment
damage, whenever possible, all adjustments, such as tightening leaking fittings,
jacking mounts, etc., shall be accomplished with the unit shut down.
5. Good judgment demands that as many other factors as possible be considered in
addition to those mentioned above before permitting anyone to enter the enclosure
with the equipment running. These factors range from the nature of the
equipment distress to such considerations as that the additional heat and noise in
the enclosures on hot summer days may exceed some individuals tolerance
levels.
6. The customers operating personnel should receive training and instruction in the
above.
1.5.16 Generator Enclosure Safety
The following items must be kept in mind when in the generator enclosure when the unit
is spinning, particularly under load:
1. When making adjustments to the lubrication oil system, be careful of hot metal
surfaces, and keep hands, tools, and clothing clear of the cooler fan and pump
couplings.
2. The exciter area should be avoided or precautions, such as eye and head
protection, used when the cover is removed for any reason, such as inspecting the
exciter fuses with a stroboscope. If a thermometer is used to take temperature
measurements at the exciter, care should be exercised to avoid rotating parts.
3. Care should be exercised when checking exciter fuses with a strobe light to avoid
dropping objects from pockets into rotating parts or getting hands or loose
clothing near them.
1.5.17 Pressurized Air, Gas, or Liquid System Safety
Before opening any valves or disconnecting piping in pressurized air, gas, or liquid
systems, and especially before removing pipe caps or plugs, ensure that they system has
been depressurized. A high velocity stream of air or flying particles could cause serious
eye injury. In addition, high pressure hoses or tubing, under pressure, can be extremely
hazardous due to the whipping action, which results when disconnected.
REV-2
PAGE: 1-22
15 January 2002
Homepage
Previous Document
Relief valves must be checked for proper setting and functionally checked prior to initial
operation.
Purging and leak checking of liquid and gas systems use high pressure air and liquids.
Particular caution should be exercised during these operations to avoid the above dangers.
During hydrostatic testing the system has not yet been proven to withstand either the
operating pressures or the over pressures used in testing.
1.5.18 Gaseous Fuel Compressor Safety
The danger of explosion is an additional and serious safety hazard associated with the
operation of gaseous fuel compressors. This hazard exists during pressure checking and
initial startup or gassing in as well as during normal operation. The following
precautions should be observed:
1. No smoking or open flame is allowed in the gas compressor area. Signs should be
displayed to this effect.
2. Prior to initial charging of the unit with natural gas, all air must be purged from
the system.
3. All vent and seal drain lines must be routed to a point well above ground level,
and have flame arresters installed.
4. Buildings used to house gaseous fuel compressors must be well ventilated and
have combustible gas detector units installed.
5. Relief valves should be set no higher than the maximum allowable working
pressure and functionally tested if possible. When compressors are housed in
buildings, relief valves and vent lines should be routed out of the building and
above roof level.
1.5.19 Air Compressor Safety
Before any work is performed on the Air Pac or related systems, the unit should be locked
out to protect against inadvertent starting, since the rotating compressor components
could cause injury. It is also well to remember the dangers associated with high pressure
systems, and that a high pressure stream of air, from a leak for example, can be
hazardous. Leak checking should always be done with caution.
1.5.20 Fuel System Safety
Field installed fuel piping, whether gas or liquid, must be properly pressure checked,
usually to one and one-half times the working pressure.
REV-2
PAGE: 1-23
15 January 2002
Homepage
Previous Document
Liquid fuel storage tanks must be surrounded by a dike capable of containing an amount
of fuel equal to the tank capacity. Forwarding equipment should be installed outside of
the dike area.
Liquid fuels, such as those used by gas turbines, are irritating to the skin and eyes; care
should be exercised during flushing, fueling, or filter changing operations.
1.5.21 Fire Protection Systems
The area must be cleared of all personnel prior to any functional test of a fire protection
system, and all site personnel must be informed that such a test is imminent. This
includes areas outside of the fire protection zone, such as on enclosure roofs, and
especially near fire damper doors. After the test is concluded, the fire zone shall be well
ventilated prior to entry.
1.5.21.1 Halon 1301
Halon 1301 fire protection systems use a colorless, odorless, non-conductive gas
(Bromotrifluoro-methane - CBrF3) with an exceptionally low toxicity. Exposure to this
agent in enclosed areas is, therefore, relatively safe. However, if a storage container
should discharge close to personnel, serious injury could result from the high pressure,
high velocity gas stream.
Environmental or operating conditions, which may short or ground the fire protection
systems logic components can result in malfunction or actual discharge of the system.
Therefore, when checking or servicing the components, the system should always be
disarmed.
All types of storage cylinders should have safety caps in place when handling or storing
to protect the cylinder valve. If the cylinder valve is damaged or broken off and safety
caps are not in place, the thrust from the escaping gas in capable of propelling the
cylinder and endangering personnel.
1.5.21.2 Carbon Dioxide
Carbon dioxide extinguishes a fire by diluting the amount of available oxygen. The
hazard to personnel is obvious, since the amount of available oxygen may be quickly
reduced to a level below that required to sustain life if the system is discharged.
When checking or servicing the system, or when work requiring extended periods of time
is done in fire protection zones, the system must be disarmed.
1.5.22 Hazard Communication
REV-2
PAGE: 1-24
15 January 2002
Homepage
Previous Document
Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart C, Section 1926.59
Hazard Communications.
1.5.22.1 Hazard Communication Standard
Refer to OSHA Regulations, Standards 29 CFR, Part 1910, Subpart Z, Section
1910.1200 Hazard Communication.
The OSHA Hazard Communication Standard was adopted August 24, 1987 to ensure that
the hazards of all chemicals produced or imported are evaluated, and that information
concerning their hazards is transmitted to employers and employees. The standard
requires employers to develop and maintain a written hazard communication program for
the workplace, and conform to other Hazard Communication requirements as listed in
paragraph 1.5.22.2.
An employer is defined by OSHA, in OSHA Regulations, Standards 29 CFR, Part
1926, Subpart D, Section 1926.59 Hazard Communication as a company engaged in a
business where chemicals are either used, distributed, or are produced for use or
distribution, including a contractor or subcontractor.
An employee is defined as a worker who may be exposed to hazardous chemicals
under normal operating conditions or in foreseeable emergencies. Workers such as office
workers or bank tellers who encounter hazardous chemicals only in non-routine, isolated
instances are not covered.
A list of toxic and hazardous air contaminants and the limits of employee exposure to
these substances are provided in OSHA Regulations, Standards 29 CFR, Part 1910,
Subpart Z, Section 1910.1000 Air Contaminants, Table Z1. The limits of exposure,
precautions, and requirements of communication of hazards to employees for asbestos,
tremolite, anthophyllite, and actinolite are given in OSHA Regulations, Standards 29
CFR, Part 1926, Subpart D for the construction industry.
The Standard requires that chemical manufacturers and importers must convey the hazard
information they learn from their evaluations to downstream employers by means of
labels on containers and Material Safety Data Sheets (MSDSs). The information to be
contained in these data sheets in described in OSHA Regulations, Standards 29 CFR,
Part 1926, Subpart D, Section 1926.59 Hazard Communication, paragraph (g). A copy
of these data sheets must be kept in a file on the construction site.
REV-2
PAGE: 1-25
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-26
15 January 2002
Homepage
Previous Document
Broad based lobbying led to the enactment of the Williams-Steiger Occupational Safety
and Health Act on December 29, 1970. This law applies to all industries affecting
commerce, including the construction industry. The law became effective on April 28,
1971.
Section 5 of the Act establishes that each employer:1
1. Shall furnish to each of his employees employment and a place of employment
that are free from recognized hazards that are causing or are likely to cause death
or serious physical harm to his employees.
2. Shall comply with occupational safety and health standards promulgated under
this act.
Each employee shall comply with occupational safety and health standards and all rules,
regulations, and orders issued pursuant to this Act that are applicable to his own actions
and conduct.
The regulations promulgated from this Act for the construction industry were first
published in April 17, 1971 Federal Register, Volume 36, Number 75, Part II. They were
originally called Part 1518, but were reissued for OSHA as Code of Federal Regulations,
Title 29, Part 1926 on December 30, 1971.
To interpret Section 5 of the Act, Part 1926 requires as a condition of each contract for
construction, alteration, and/or repair, including painting and redecorating, that no
contractor or subcontractor contracting for any part of the contract work shall require any
laborer or mechanic employed in the performance of the contract to work in surroundings
or under working conditions which are unsanitary, hazardous, or dangerous to his health
or safety, as determined under construction safety and health standards promulgated by
the regulations. Refer to OSHA Regulations, Standards 29 CFR, Part 1926, Subpart C,
Section 1926.20 General Safety and Health Provisions.
Section 18 (b) of the Act provides that any State which desires to assume responsibility
for the development and enforcement therein of occupational safety and health standards
relating to issues covered by corresponding standards promulgated (by the Act) shall
submit a plan for doing so to the Assistant Secretary. Section 18 (c) of the Act sets out
certain criteria that a plan which is submitted under section 18 (b) of the Act must meet.
Foremost among these criteria is the requirement that the plan must provide for the
development of State standards and the enforcement of such standards which are or will
be at least as effective in providing safe and healthful employment and places of
employment as the standards promulgated under the Act.
Laws of the 91st Congress - Second Session - Public Law 91-596, 84 Stat. 1590
Occupational Safety and Health Act of 1970
1
REV-2
PAGE: 1-27
15 January 2002
Homepage
Previous Document
The following States and territories currently operate their own OSHA programs under
Section 18 (b): Alaska, Arizona, California, Hawaii, Indiana, Iowa, Kentucky, Maryland,
Michigan, Minnesota, Nevada, New Mexico, North Carolina, Oregon, Puerto Rico, South
Carolina, Tennessee, Utah, Vermont, Virginia, the Virgin Islands, Washington, and
Wyoming. In addition, Connecticut and New York have OSHA approved plans that
cover public employees only. Therefore the rules cited herein are to be considered the
minimum standards. Further state requirements that amend or supersede the Federal
Standards may be in force.
Each volume of the Code of Federal Regulations is revised at least once each calendar
year and issued on a quarterly basis. OSHA Code of Federal Regulations, Title 29, Part
1926, covering the construction industry, is issued approximately July 1. The information
in this Construction Manual is based on the July 1, 1988 revision of Part 1926, which is
the latest revision that is currently available.
1.6.2 Inspections, Citations, and Proposed Penalties
The purpose of OSHA as Code of Federal Regulations, Title 29, Part 1903 is to prescribe
rules and set forth general policies for enforcement of the inspection, citation, and
proposed penalty provisions of the OSH Act of 1970.
Inspections take place at such times and in such places of employment as the Area
Director or the Compliance Safety and Health Officer (CSHO) may direct. At the
beginning of an inspection, the CSHO shall present their credentials, explain the nature
and the purpose of their inspection, and indicate generally the scope of the inspection and
the records that they wish to review. Refer to OSHA Regulations, Standards 29 CFR,
Part 1903, Section 1903.7 Conduct of Inspections.
Inspections are usually originated by:
1. Situations creating an imminent danger that can be expected to cause death or
serious physical harm.
2. Fatalities and accidents resulting in the hospitalization of five or more
employees.
3. Employee complaints of alleged violations of standards or of unsafe or
unhealthful working conditions.
4. Programmed inspections aimed at specific high hazard industries, occupations,
or health substances.
REV-2
PAGE: 1-28
15 January 2002
Homepage
Previous Document
When the OSHA inspector arrives on site, it is PWPSs policy that the OSHA inspector
be permitted entry. He has the right to talk to anyone on the site and he can require
testimony and evidence under oath.
When an inspection reveals a violation of the OSHA regulations which could reasonably
be expected to cause death or serious harm immediately, the CSHO shall inform the
affected employees and employer of the danger. The Area Director will review the
inspection report of the CSHO, and will issue either a citation or notice of de minimis
violation within six months if he believes that the employer has violated an OSHA
requirement. A de minimis violation is one which has no direct or immediate relationship
to safety or health.
If the citation is sent to the Site Supervisor, he must immediately post a copy in the
manner and location(s) as required in OSHA Regulations, Standards 29 CFR, Part
1903, Section 1903.16 Posting of Citations. The citation must be posted for a minimum
of three (3) working days and until the violation has been abated. He shall also send a
copy or facsimile of the citation immediately after its receipt to the Construction Office
Support Group at the PWPS Home Office.
The Area Director determines the amount of any proposed penalty, giving due
consideration to the appropriateness of the penalty with respect to the size of the business,
the gravity of the violation, the good faith of the employer, and the history of previous
violations. Penalties are not proposed for de minimis violations. The Area Director will
notify the employer of the proposed penalty, or that no penalty is being proposed.
NOTE
The Area Director will not notify the employer following
an inspection if the site is in compliance.
1.6.3 Records
The regulations require that certain records be accurately maintained and/or posted.
These records are:
1. OSHA No. 101, Supplementary Record of Occupational Injuries and
Illnesses
Occupational injuries and/or illnesses to be logged on this form within six
working days from the time the employer learns of the work-related injury or
illness.
REV-2
PAGE: 1-29
15 January 2002
Homepage
Previous Document
NOTE
A substitute for OSHA No. 101, such as insurance or
workers compensation forms, may be used it contains all
required information.
2. OSHA No. 200, Log and Summary of Occupational Injuries and Illnesses
Occupational injuries and/or illnesses to be logged on this form within six
working days from the time the employer learns of each recordable
occupational injury or illness. This log may be prepared and maintained at an
off-site location, but a copy updated within 45 calendar days must be present
at all times on site.
NOTE
A copy of the OSHA 200 log must be posted at the site
from February 1 to March 1 each year for the preceding
year, even though there were no injuries or illnesses during
the year.
Record keeping forms are not to be sent to OSHA or any other agency. They are TO BE
maintained for five years at the workplace and must be available for inspection by
representatives of OSHA, HHS (Health and Human Services), BLS (Bureau of Labor
Statistics), or the designated state agency.
It shall be the Site Managers responsibility to complete and file the Supplementary
Record of Occupational Injuries and Illnesses, OSHA Form 101, whenever an
occupational accident or injury occurs. A copy shall be maintained in a permanent file in
the Construction Office Support Group at the PWPS Home Office.
The Site Manager has the further responsibility to obtain and display the Safety and
Health Poster in the PWPS site trailer(s) and in the Contractors trailer(s). These posters
are obtainable from he Construction Office Support Group.
1.6.4 Accident Procedures
Should an accident occur on a job site for which you are responsible, follow the
procedures indicated in Chart 1-1 shown on page 1- 37. It is important of note that
OSHA Form 101 and a complete accident report must be filed with the Construction
Office Support Group within six days of the accident or occupational illness. Fatalities
and catastrophes injuring five or more employees must be reported to OSHA within fortyeight (48) hours of their occurrence.
REV-2
PAGE: 1-30
15 January 2002
Homepage
Previous Document
Fatalities resulting from heart attacks or like causes should be reported. The report can be
cancelled or withdrawn later if it is determined that the case was not occupational in
origin.
1.6.5 Procedures and What to Expect from an OSHA Inspection
Should an OSHA inspector, officially titled Compliance Safety Health Officer (CSHO),
come onto your job site with the intention of making an inspection, he is first required to
show his credentials. Once the CSHO has established his identity, he will ask for an
opening conference.
An authorized employee representative should be given the opportunity to attend the
opening conference and accompany the CSHO during the inspection. If the employees
are represented by a recognized bargaining representative, the union will ordinarily
designate the employee representative. If there is no authorized employee representative,
the CSHO will consult with a reasonable number of employees concerning safety and
health matters in the workplace. The Site Supervisor should also invite the
superintendent of each subcontractor.
At the opening conference the CSHO will:
1. Inform the employer that the purpose of his visit is to make an investigation to
ascertain whether the employer is in compliance with the requirements of the
Act.
2. Outline in general terms the scope of inspection, including records he may
desire to review, employee interviews, physical inspection of the worksite or
workplaces, and the closing conference with the employer or his designated
representative to discuss the inspection findings.
3. Give the employer copies of the laws, standards, regulations, and promotional
materials, as applicable.
4. Finish a copy of complaint(s) if appropriate.
5. Inform the employer how he may obtain additional copies of other applicable
materials.
6. At an appropriate time during the opening conference, the CSHO shall discuss
the all-round provisions under the Act. The employer should be asked to
designate his representative for walk around purposes. In addition, the CSHO
should determine if there is a certified or recognized union or unions in the
plant, or any other authorized employee representative and they should be
contacted. Where any authorized employee representative is designated at the
REV-2
PAGE: 1-31
15 January 2002
Homepage
Previous Document
beginning of the inspection, the CSHO should discuss with them the scope of
the walk around. To the extent possible, all issues relating to walk around
should be settled at the beginning of the inspection.
The Site Supervisor shall make a complete set of notes, including names and time, during
the CSHOs meetings and inspection, and send a report to the Construction Office
Support Group.
After this meeting is completed, the CSHO will conduct the walk around inspection. The
CSHO can deny the right of accompaniment to any person whose conduct interferes with
a full and orderly inspection.
During the inspection, the compliance officer usually takes photographs of specific
hazardous situations, as well as the overall site. If so, it is recommended that am
employer representative also take photographs to duplicate the compliance officers
photographs for record purposes.
During the inspection, the CSHO may note apparent violations of OSHA regulations. He
will indicate these apparent violations to the Site Supervisor and the other employee
representatives. Citations will not be issued during this visit. If the OSHA Area
Administrator decides that the violations warrant a citation, the citation will be mailed to
the employer. The CSHO is not allowed to discuss the possibility of a citation with the
Site Supervisor or others. However, he can inquire about estimates of corrective
measures, extenuating circumstances, and the period required for abatement.
After the walk around inspection is completed, the CSHO will conduct another meeting
with the employer representatives. The CSHO shall at that time disclose all conditions
and practices which constitute safety and health violations.
A complete report of the inspection should be written immediately and sent to the
Construction Office Support Group.
At no time during the inspection should the PWPS Site Supervisor argue with the
inspector over the interpretation of the OSHA regulations. If the site inspection reveals
violations for which a citation is issued, the citation should be mailed to the Site
Supervisor, unless the citation is issued to our contractor or his subcontractors only.
REV-2
PAGE: 1-32
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-33
15 January 2002
Homepage
Previous Document
2. If an employer does not agree, he has fifteen (15) working days from the date the
citation is received to contest in writing (1) the citation, (2) the proposed penalty,
and/or (3) the abatement date.
NOTE
If the employer does not contest within 15 working days,
the citation becomes a final order.
For violations not contested, the employer must:
1. Promptly notify the OSHA Area Director, by letter, that he has taken the
appropriate corrective action within the time set forth in the citation,
and
2. Pay the penalty within fifteen (15) working days of receipt of the penalty notice.
Before deciding whether to file a Notice of Intent to Contest, the employer may request an
informal conference with the OSHA Area Director to discuss the Citation and
Notification of Penalty. This is recommended if there is any difficulty in complying with
any part of the citation. However, the informal conference will not extend the 15 working
day Notice of Intent to Contest period, nor take the place of filing a written notice of
context.
The Notice of Intent to Contest must clearly state what is being contested. A proper
contest of any item suspends the legal obligation to abate and pay until the item contested
has been judicially resolved. If only the penalty is contested, the employer must still
correct all violation by the dates indicated on the citations.
1.6.7 The Site Supervisors, PWPSs Contractor(s), and OSHA
The General Conditions of the specifications to which the contractor is building the site
states, All material and services furnished (by the Contractor) shall be in compliance
with the provisions of the Occupational Safety and Health Act. It is the Site
Managers responsibility to ensure contractor compliance with OSHA regulations.
Following the below listed steps can help the Site Supervisor ensure compliance by
PWPS contractors:
1. Make certain that you, other PWPS personnel, and the contractors supervisory
personnel are knowledgeable in depth about the Act and its administration.
REV-2
PAGE: 1-34
15 January 2002
Homepage
Previous Document
Take
3. Make sure that MSDSs are filed and made available to contractors where
necessary.
4. Prior to commencement of work, determine with the contractors representative,
who is responsible for each of the mutual requirements of the regulations.
5. Ensure that cross training concerning hazardous materials occurs between
subcontractors, since employees of one subcontractor may be exposed to
hazardous materials used by another.
1.6.8 Summary
The Occupational Health and Safety Act require all employers to provide healthy and
safe employment and place of employment. OSHA provides for the promulgation of
regulations and for civil and criminal penalties for violation of these regulations.
The responsibility for compliance to all OSHA regulations rests on the prime contractor.
The Site Supervisor shall ensure that all contractors, their subcontractors and employees
comply with OSHA regulations.
Each of PWPSs construction personnel should become familiar with the regulations and
administration of OSHA.
Certain records must be maintained to comply with OSHA. The most important to the
Site Supervisor are the Supplementary Record of Occupational Injuries and Illnesses,
OSHA Form 101, and the Log and Summary of Occupational Injuries and Illnesses,
OSHA Form 200. The Site Supervisor shall have the OSHA Safety and Health poster
displayed in the PWPS office trailer, the Contractors trailers, and any other location
where all workers on the site are most likely to read them.
Accident procedures are outlined in Chart 1-1.
Should an OSHA inspection take place at one of our sites, the Site Supervisor shall:
1. Ensure that an employer representative from each contractor and each trade on site
is at the pre-inspection meeting, inspection, and post-inspection meeting.
2. Keep accurate and complete notes of all activities involved with the inspection.
3. Write an inspection report and submit it to the Construction Support Group at the
PWPS Home Office.
REV-2
PAGE: 1-35
15 January 2002
Homepage
Previous Document
4. If a violation receives a citation, the Site Supervisor shall post the citation in
accordance with OSHA requirements and will send a copy or facsimile of the
citation to the PWPS Home Office.
REV-2
PAGE: 1-36
15 January 2002
Homepage
Previous Document
1. Determine accident severity and take the appropriate action shown under that
heading.
MINOR
SERIOUS
SEND VICTIM TO
PHYSICIAN (IF
REQUIRED)
CALL AMBULANCE
TRANSPORT VICTIM TO
HOSPITAL
FATALITY
IF 5 OR MORE
HOSPITALIZED, OR ONE
OR MORE DEATHS,
REPORT ACCIDENT TO
OSHA OFFICE CLOSEST
TO JOB SITE WITHIN 48
HOURS.
OSHA INSPECTION OF
JOB SITE.
WRITE A COMPLETE
ACCIDENT REPORT.
SEND TO THE PWPS
HOME OFFICE WITHIN 6
DAYS.
REV-2
PAGE: 1-37
15 January 2002
Homepage
Previous Document
REV-2
Strength of Plank
Safe Loads on Timber used as Beams
Safe Loads on Timber Columns, Posts, or Braces
Strength of Wire Rope
Strength of Wire Rope Connections
Wire Rope Clips
Bridling of Spreaders
Strength of Manila Rope Blocks
Strength of Standard Hooks
Strength of Turnbuckles
Strength of Chains
Safe Hitches and Knots
Strength of Shackles
Crane or Swinging Boom Hand Signals
PAGE: 1-38
15 January 2002
Homepage
Previous Document
10
12
14
16
18
305
370
430
300
350
290
54
72
90
33
43
55
2x8
2 x 10
2 x 12
400
500
600
260
325
390
190
235
285
180
220
165
3 x 10
3 x 12
3 x 14
1245
1495
1740
820
980
1145
600
720
840
465
555
650
370
445
520
The loads given are in pounds concentrated at the center of the span.
The above loads are for fir or spruce planks in first class condition. For yellow pine planks in first class
condition add 10% to the above allowable loads.
Safe loads given are based on planks surfaced under sizes shown.
Positio
n
10
12
14
16
18
20
24
260
400
930
1270
1760
2400
5730
7940
10500
4930
7260
10050
8790
12170
16090
14290
220
340
800
1090
1520
2070
4970
6890
9130
4270
6300
8730
7630
10570
14000
12410
690
950
1330
1810
4370
6070
8040
3740
5540
7690
6710
9310
12330
10930
610
830
1170
1600
3890
5410
7180
3320
4930
6860
5970
8300
11020
9750
940
1280
3160
4410
5870
2680
4000
5590
4840
6760
9000
7940
Hor.
Hor.
Hor.
Vert.
Vert.
Vert.
Vert.
Vert.
Vert.
Vert.
Vert.
200
990
1530
3440
4700
6430
6690
10250
12050
13820
10740
12960
15220
15690
18430
21170
21630
130
650
1010
2290
3120
4260
6660
10200
12000
13760
10690
12900
15150
15620
18340
21070
21520
90
480
750
1700
2320
3180
4330
10160
11940
13690
10640
12840
15080
15550
18260
20970
21420
380
590
1340
1830
2520
3440
8150
11260
13630
7020
10320
14280
12490
17240
20880
21320
310
480
1110
1510
2080
2840
6740
9320
12310
5800
8540
11810
10340
14300
18870
16780
The loads given are in pounds concentrated at the center of the span.
The above allowable loads are for fir or spruce in first class condition.
For yellow pine beams in first class condition add 10% to the above allowable loads.
Most yellow pine timber now available is short-leaf. Inspect carefully for cross-grain. If badly crossgrained, reduce above safe loads accordingly.
All loads given are based on surfaced timber.
REV-2
PAGE: 1-39
15 January 2002
Homepage
Previous Document
10
12
14
16
18
20
25
30
35
40
45
50
60
13.5
28.5
48.3
72.9
9.4
23.4
42.1
65.5
18.2
35.9
58.3
13.1
29.7
51.1
23.4
43.7
17.2
36.5
21.9
...
4.7
4.0
13.4
27.3
45.9
69.4
97.7
11.0
24.0
41.9
64.5
91.8
A
6x6
8x8
10 x 10
12 x 12
14 x 14
12.2
25.6
43.9
67.0
94.8
9.8
22.4
39.8
61.9
89.0
8.6
20.8
37.7
59.4
86.0
7.5
19.2
35.7
57.0
83.1
6.3
17.5
33.6
54.5
80.2
The above loads are based on yellow pine or fir timber in first class condition.
Safe load on wood column is frequently limited by bearing cap or sill.
Loads below line A can only be permitted if the end grain of the post rests on steel beam or slab.
Loads between line A & B can only be permitted if the load is transferred in and out of post by bearing on
oak or similar pedestal or corbel, to distribute the load over a greater area of yellow pine cap or sill.
Permissible pressure across the grain of yellow pine is 400 lbs. Per square inch and for oak is 750 lbs. per
square inch.
Most yellow pine now available is short-leaf. Inspect carefully for cross-grain. If badly cross-grained,
reduced above safe loads accordingly.
REV-2
PAGE: 1-40
15 January 2002
Homepage
Previous Document
Minimum Size of
Sheave
(Inches)
Safe Working
Load Running
Cable
(Lbs.)
Safe Working
Load-Eye and Eye
Chokers
(Tons)
Approximate
Weight per Foot of
Cable
(Lbs.)
3/8
1/2
5/8
3/4
7/8
9
12
14
16
18
4200
7200
11100
15800
21500
1.3
2.2
3.3
4.8
6.5
0.23
0.40
0.63
0.90
1.23
1
1-1/8
1-1/4
1-3/8
1-1/2
20
24
28
32
36
28000
35300
43300
52300
61700
8.4
10.6
13.0
15.7
18.5
1.6
2.03
2.50
3.03
3.60
1-5/8
1-3/4
1-7/8
2
40
44
48
52
72000
82700
94700
107300
21.6
24.8
28.9
32.2
4.23
4.90
5.63
6.40
3
3
5
3/8
1/2
1/2
3.7
6.4
10.7
REV-2
PAGE: 1-41
15 January 2002
Homepage
Previous Document
100% of cable
85%
80%
80%
85%
1
2
3
4
8300
16100
23450
30350
9120
18000
26550
34900
5
6
7
8
36850
42950
48650
54050
43000
50800
58400
65800
9
10
11
12
59100
63850
68350
72550
72950
79900
86600
93150
The above values are based on two snatches between the engines and the falls. For each additional snatch
block or sheave; add 6% to the lead line pull for bronze bushed sheaves; add 3% to the lead line pull for
ball-bearing sheaves.
REV-2
PAGE: 1-42
15 January 2002
Homepage
Previous Document
Diameter of Wire
Rope
(Inches)
Number of Clips
for Improved Plow
Steel
Minimum Spacing
D Between Clips
(Inches)
Number of Clips
for Improved Plow
Steel
Minimum Spacing
D Between Clips
(Inches)
3/8
1/2
5/8
3/4
7/8
1
1-1/8
1-1/4
1-3/8
1-1/2
3
4
4
5
5
6
6
7
7
8
3
3-1/2
4-1/4
5
5-3/4
6-1/2
7-1/4
8
8-3/4
9-1/2
3
3
3
4
4
5
5
6
6
6
3
3-1/2
4-1/4
5
5-3/4
6-1/2
7-1/4
8
8-3/4
9-1/2
The above are the minimum requirements to develop 85% of the full strength of the wire rope when using
U-Bolt Clips, and 90% of the full strength of the wire rope when using First Grip Clips.
REV-2
PAGE: 1-43
15 January 2002
Homepage
Previous Document
S
(Ins.)
1/2
5/8
3/4
7/8
1
3 Parts 3/8 Braided
3 Parts 1/2 Braided
5 Parts 1/2 Braided
22
33
48
65
84
37
64
107
Procedure:
1. Lay off length S as shown in sketch
2. Measure Distance R in inches.
3. R / 10 = Safe load in tons on one leg due to bridling
Example: Using 7/8 0 spreaders. Find allowable load.
1. Lay off S = 65 inches on one leg.
2. Distance R measures 64 inches.
3. Safe load on one leg = .46 / 10 = 4.6 tons
4. Total allowable safe load = 2 x 4.6 = 9.2 tons
Notes:
1.
2.
REV-2
PAGE: 1-44
15 January 2002
Homepage
Previous Document
Two Singles
(Pounds)
Two Doubles
(Pounds)
Two Triples
(Pounds)
3
4
5
6
600
750
1500
2250
825
1125
2250
3000
1050
1500
3000
3750
7
8
9
10
2550
3300
3900
4500
3675
4350
5100
5625
4800
5400
6300
6750
12
14
16
5400
6600
9000
7200
8550
11250
9000
10500
13500
Two Singles
(Pounds)
Two Doubles
(Pounds)
Two Triples
(Pounds)
3
4
5
6
750
1200
1650
2400
1350
2250
3300
4500
1950
3000
4200
6000
7
8
9
10
3000
3600
4050
6000
5700
7050
7500
10500
7200
10050
10500
13500
12
14
16
7500
9750
12000
13500
16500
21000
18000
22500
27000
REV-2
PAGE: 1-45
15 January 2002
Homepage
Previous Document
Throat Opening
(Inches) B
22
23
24
25
7/8
1
1-1/8
1
1-1/16
1-1/8
1-1/4
0.5
0.6
0.7
1.2
26
27
28
29
30
1-1/4
1-3/8
1-1/2
1-5/8
1-3/4
1-3/8
1-1/2
1-3/4
1-7/8
2-1/16
1.7
2.1
2.5
3.0
4.0
31
32
33
34
34a
35
2
2-3/8
2-3/4
3-1/8
3-1/4
3-1/2
2-1/4
2-1/2
3
3-3/8
3-5/8
4
4.7
5.5
6.8
8.0
10.0
11.0
36
38
4
4-1/2
4-1/2
5
20.0
30.0
The above values are for Vulcan and similarly designed standard hooks.
The capacity can be found by the diameter of the hole in the eye of the hook. If the throat opening of any
hook exceeds the dimensions given above for the corresponding diameter of the eye, the hook has been
overstrained and must not be used.
3/4
7/8
2.2
3.2
3/8
1/2
1
1-1/4
4.1
6.6
5/8
3/4
1-1/2
1-3/4
9.7
13.1
7/8
1
2
2-1/4
17.2
22.5
1-1/8
1-3/8
2-1/2
2-3/4
28.0
36.7
1-1/2
1-3/4
REV-2
PAGE: 1-46
15 January 2002
Homepage
Previous Document
3/8
1/2
5/8
3/4
7/8
1.5
2.5
4.1
6.2
8.4
2300
4000
6300
9000
12300
1
1-1/8
1-1/4
1-3/8
1-1/2
10.5
13.6
16.0
19.3
23.0
16300
19600
24300
29300
35000
REV-2
PAGE: 1-47
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-48
15 January 2002
Homepage
Previous Document
Diameter of Shank B
(Inches)
Maximum Width
between Eyes C
(Inches)
3/4
7/8
1
1-1/8
1-1/4
5/8
3/4
7/8
1
1-1/8
1-1/16
1-1/4
1-1/2
1-5/8
1-7/8
2.2
3.2
4.3
5.7
6.7
1-3/8
1-1/2
1-5/8
1-3/4
2
1-1/4
1-3/8
1-1/2
1-5/8
1-3/4
2
2-1/8
2-1/4
2-3/4
2-3/4
8.3
10.0
12.0
14.0
16.0
2-1/4
2-1/2
2-3/4
3
3-1/4
2
2-1/4
2-1/2
2-3/4
3
3-1/4
4
4-1/8
4-1/2
5
21.0
27.0
34.0
40.0
46.0
REV-2
PAGE: 1-49
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 1-50
15 January 2002
Homepage
Previous Document
Chart 1-2
Tagging Log Format
Equipment
No.
When Tagged
Date
Time
REV-2
15 January 2002
Reason
Requested
By
Tagged
By
When Released
Date
Time
PAGE: 1-51
Released
By
REV-2
15 January 2002
Homepage
PAGE: 2-1
Previous Document
All excavations shall be large enough to permit working space for subsequent operations
within them. Excavations shall be maintained in a dry condition, free of standing water
to permit progress of work. Grading in the vicinity of the work shall be controlled to
prevent water from running into the excavated area. If any water should accumulate
therein, the water shall be removed by pumping, draining, or other approved methods.
The Contractor shall be responsible for providing a dewatering system to lower the water
table where excavations are at an elevation below the water table. The excavations shall
be provided with barricades, signs, sheeting, and shoring per OSHA regulations for the
safety of personnel and the protection of the work.
All excavations shall be maintained free of frost and thoroughly cleaned immediately
before granular fill, concrete, piping, cable, backfill or other materials of construction are
placed therein.
A nominal amount of excavations for trenches will be necessary for the proper laying of
piping, insulated, and non-insulated cable, conduit or tubing. The bottom of the trenches
shall be cleaned of all stones and organic material, and accurately graded to provide
uniform bearing on washed sand compacted to 95 percent ASTM D1557.
Where required, the Contractor shall install and support the excavation shoring with
material and members dimensioned per OSHA shoring requirements. Shoring
requirements concerning excavations are given in section 1.5 (K). Refer to OSHA
Regulations, Standards 29 CFR, Part 1926, Subpart P- Excavations.
2.3 Fill and Backfill
All filling and backfilling necessary to complete the work shall be accomplished using
suitable excavated material or approved selected fill material.
Fill materials required for raising the subgrade for concrete foundation pads and slabs to
the elevations shown on the drawings and for backfilling around foundation walls shall be
selected and approved material placed and compacted as specified. Crushed stone,
granular fill, and backfill material shall not be placed until the subgrade or other below
grade work has been completed, inspected, and approved. However, when the subgrade
excavation is approved, the granular fill shall be placed immediately after the excavation
of the unsuitable material, debris, and organic matter.
The granular fill and backfill shall be deposited in layers not to exceed six inches, loose
measure, thoroughly compacting each layer as specified herein. Crushed stone layers for
the foundation and pads shall measure 18 inches, loose measure.
Granular fill and backfill shall not be placed on soil that is disturbed, muddy, contains
frost pockets, or is frozen. Fill placement and compaction operations shall be suspended
REV-2
PAGE: 2-2
15 January 2002
Homepage
Previous Document
during periods of rainfall. Compacted areas that have settled or have softened due to rain
or some other cause shall be restored and thoroughly recompacted.
Backfill around foundations and pads shall raise the grade to final rough grade. Backfill
shall be placed and compacted as specified herein. Redress and recompact any areas that
settle from traffic, precipitation, or storage loading.
After the piping, cables, conduit, and tubing are laid, inspected, tested, and approved, the
periphery of each shall be filled and compacted with approved, washed sand and gravel to
a minimum radius of six inches around the piping, etc., unless otherwise indicated on the
drawings or by the PWPS Site Supervisor in writing. Special care shall be taken in
backfilling around and over non-metal piping to prevent damage to the piping.
Backfilling around cables shall be completed per PWPS specifications.
2.4 Compaction and Tests
Each layer of fill or backfill material shall be thoroughly compacted throughout to the
requirements given below at optimum moisture content for the material using appropriate
methods and equipment for the conditions involved. The addition or removal of water, as
required, shall control moisture content.
All areas under new construction shall be compacted throughout to a density of at least 95
percent of the maximum value as determined by an ASTM D1557 designation (AASHOT-180) compaction test. Compaction densities specified on the drawing are minimum
limits to be achieved by maintaining soil moisture within +/- 2 percent of the optimum
moisture content determined by ASTM D1557 or D698. Compaction requirements for
the crushed stone are usually not specified, since it is anticipated that grading equipment
used to level the crushed rock will compact it sufficiently.
All other areas shall be compacted throughout to a density of at least 90 percent of the
maximum value, as determined by the same compaction test.
PWPS may arrange for an approved independent laboratory to obtain and examine test
specimens from the completed work to certify contract compliance in writing. Test
specimens shall be taken from the work at the locations and depths prescribed by PWPS.
The Contractor shall cooperate with the testing laboratory personnel.
NOTE
Arrange for this service early, before compaction must be
checked.
REV-2
PAGE: 2-3
15 January 2002
Homepage
Previous Document
If the fill does not meet the stated compaction requirements, the Contractor shall
recompact the fill and pay for all retesting until it is determined that the fill has been
constructed in accordance with this specification.
2.5 Piles
Normally, the piling area will be graded prior to driving the piles.
Logs of soil borings in the vicinity of the foundation are taken to indicate the general
nature and depth of soil formation.
In general, a technical specification covering all specific pile design requirements will be
written for each project. The following are typical driving and test requirements. Driving
requirements for different applications may vary.
2.5.1 Driving
All piles shall be driven from the ground surface existing after general nature and depth
of soil formation.
Piles shall be driven without interruption from the first hammer blow until final resistance
is developed in the bearing stratum, insofar as possible. In any event the last five feet of
pile length shall be driven without interruption.
The piles shall be driven as nearly as possible in the exact position shown on the plans.
Deviation of the location of the top of the pile from that shown on the plans shall not
exceed three inches.
Piles shall be driven with a maximum permissible deviation of two (2) inches in ten (10)
feet from the vertical.
A suitable cap shall be provided to prevent undue damage to the top of the pile and to
hold the pile centered under the hammer.
After each pile has been driven to the required depth and resistance, the top elevation of
the pile shall be recorded. Such levels shall be checked from time to time as adjacent
piles are driven to determine whether any heaving of piles has taken place. Where there
is a reason to believe, in the opinion of PWPS, that a pile has heaved, it shall be redriven
to specified final resistance.
Jetting is prohibited.
Piles shall not be driven within twenty (20) feet of concrete that is less than seven (7)
days old.
REV-2
PAGE: 2-4
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 2-5
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 2-6
15 January 2002
Homepage
Previous Document
Homepage
Previous Document
The jacking plates shall be placed and grouted after the concrete formwork has been
removed. The grout to use is as specified in paragraph 2.7.6.
Grout consistency shall be stiff enough to support jacking plates as they are leveled.
When placing the grout for the jacking plates, the grout must not be allowed to enter the
anchor bolt sleeves or to restrict the movement of the anchor bolt within the sleeve.
Jackscrews should be coated with paste wax, putty, or wrapped with electrical tape. All
jackscrews must be removed before operation of equipment and after the grout cures.
2.7.5 Laitance
Laitance is the weaker mixture of cement, fine sand, and water that accumulates on the
surface of concrete. When an area of concrete is being prepared to receive grout, the
laitance is usually chipped away using a jackhammer to expose the aggregate beneath to
improve the bond between the epoxy grout and the concrete.
2.7.6 Grout
The Contractor shall provide and place a modified epoxy resin based grout mixture of
648CP Grout, produced by:
The Ceilcoate Co., Inc.
140 Sheldon Road
Berea, Ohio 44017.
Preparation of foundation, equipment, and grout mixture, and placing of grout shall be
per Ceilcotes installation instructions.
Shade the foundation from strong sunlight at least twenty-four (24) hours before and
forty-eight (48) hours after grouting; and, prevent any water or moisture from
accumulating on the foundation or in the anchor bolt sleeves. Proper curing of the grout
is important.
REV-2
PAGE: 2-8
15 January 2002
Homepage
Previous Document
3.0 CONCRETE
3.1 Introduction
It is the purpose of this section to provide a general understanding of the components
used in making concrete, as well as the approved methods of placement, finishing and
curing to give the required qualities in the finished product.
For further information on the specific materials and procedures used in making concrete,
refer to the 13th edition on the Portland Cement Associations Design and Control of
Concrete Mixtures. The Portland Cement Associations publication also references
appropriate American Concrete Institute reports for each of its topics.
The American Concrete Institute publishes the ACI Manual of Concrete Practice, a threepart series giving committee reports on concrete technology, as follows:
Part 1 Materials and Properties of Concrete
Construction and Practices and Inspection
Pavements and Slabs
Part 2 Notation
Structural Design
Structural Specifications
Structural Analysis
Part 3 Products and Processes
This manual should be used also as a reference for information on current practices in
concrete construction.
CAUTION
Prolonged contact with freshly mixed concrete will cause
skin irritation or chemical burns. Cement is alkaline and
therefore caustic. Cement is hygroscopic it absorbs
moisture from the skin.
3.2 Composition of Concrete
In general, the ready-mix supplier is responsible for the quality of all materials that go
into the concrete mix. Proportions of components and selection of materials are based on
the most economical used of available materials that will produce a concrete of required
workability, placeability, durability and strength. The A&E contractor responsible for
REV-2
15 January 2002
Homepage
PAGE: 3-1
Previous Document
this phase of the construction process will usually develop specifications for the materials
and their proportions.
Concrete is composed essentially of three materials: cement, water and aggregates.
Sometimes a fourth material, an admixture, is added for a variety of specific purposes,
such as entrainment of air, acceleration or retardation of setting and hardening, etc. A
brief discussion of each of these materials follows:
3.2.1
Cement
Type II
REV-2
15 January 2002
Homepage
PAGE: 3-2
Previous Document
Type III
Type IV
Type V
Air-entrained Types I, II and III Portland cements are covered by ASTM specifications in
air-entrained types. The letter A following the type number identifies these types of
cement. In these cements, very small quantities of air-entrained agents are inter-ground
with the cement clinker during manufacturing. Air-entrained produces resistance to sever
frost action and the harmful effects of de-icing salts used for ice and snow removal. A
sufficient quantity of entrained air in concrete greatly improves durability properties with
respect to freezing, thawing or frost action. Types IA, IIA or IIIA cements are used for
the same type of construction and purposes as their counterpart Type I, II and III cements.
3.2.2 Aggregates
Aggregates normally represent 66 to 78 per cent of the volume of concrete. This bulk and
the relatively inexpensive unit cost are responsible for making concrete an economical,
competitive building material. For most concrete, the selection of aggregates is limited to
the types available locally. Aggregates also must meet specific specification
requirements, which is the responsibility of the ready mix dealer. Particle shape,
gradation and maximum size have a significant influence of both the proportions and
economy of the concrete, as well as ultimate quality. Aggregates must consist of clean,
hard, strong and durable particles, free of chemicals or coatings of clay of other fine
materials. Weak, friable particles are undesirable.
Two classifications of aggregates are utilized in the production of concrete. These are
designated fine aggregate and coarse aggregate, which are defined as follows:
1. Fine Aggregate - Consists of natural sand, manufactured sand, or a
combination thereof, graded in size from " (6.3 mm) maximum diameter
to near dust size.
REV-2
15 January 2002
Homepage
PAGE: 3-3
Previous Document
2.
For most construction, coarse aggregate is all below 2 inches (51 mm) in size. For
economy and quality, specify the largest size coarse aggregate practical to use for the
conditions of the job. The larger the maximum size of the coarse aggregate, the less
water and cement will be required to produce quality concrete. Maximum size will
depend on the size and shape of the concrete members and amount and distribution of
reinforcing steel, if any. This should not exceed 1/5 of the minimum dimension of the
member, nor of the clear spacing between reinforcement bars.
Shape of the aggregate particles also has significance. Very sharp, rough particles or flat
elongated pieces require more fine material (sand) to produce workable concrete than
aggregates rounded or cubical in shape.
The ready-mix dealer is qualified to advise on specifications, quality, ratio or fine to
coarse aggregate, and other matters relating to aggregates in concrete.
3.2.3 Water
Mixing water is perhaps the least costly of the ingredients in concrete, but nevertheless
one of the most important. The amount of water used largely determines the ultimate
strength of concrete. There is a definite relation between the amount of water used and
the quality of the resulting concrete; increasing amounts of water sacrifice quality.
Additional water dilutes the paste, reducing its cementing action. It is necessary to limit
mixing water to that which will just permit proper handling and placement.
Water in concrete serves a dual function. It first converts dry cement and aggregates into
a plastic, workable mass and secondly, reacts with cement chemically to hydrate and
harden the plastic mass into a solid strong unit.
The all-important relationship of water to cement is known as the water cement ratio.
This is expressed as a ratio of pounds of water to pounds of cement per unit of concrete.
REV-2
15 January 2002
Homepage
PAGE: 3-4
Previous Document
In general, the lower the ratio, the denser and stronger the paste. This ratio is established
either by the ready-mix producer or by the requirement of the consumer when specified.
Water used in concrete must be free of acids, alkalis and oils. Particularly avoid water
containing decayed vegetable matter or other organic materials. Generally, water that is
suitable for drinking purposes is usually satisfactory for concrete.
The importance of water content in providing compressive strength in concrete is shown
below in Figure 3-1.
6000
6000
5000
5000
4000
4000
3200
3000
2500
2000
2000
1000
3
10
W A T E R C E M E N T R A T IO - G A L S . O F W A T E R P E R B A G O F C E M E N T
REV-2
15 January 2002
Homepage
PAGE: 3-5
Previous Document
DONT
REV-2
15 January 2002
Homepage
for
drainage
if
PAGE: 3-6
Previous Document
3.3.2 Forms
DO
DONT
REV-2
15 January 2002
Homepage
PAGE: 3-7
Previous Document
DONT
REV-2
15 January 2002
Homepage
PAGE: 3-8
Previous Document
3.3.4 Finishing
DO
Plan to grade slabs for water runoff. Slope
should be a minimum of 1/8 inch in 10 feet
(3.2 mm in 3050 mm).
Permit wet spots to disappear before final
finish troweling.
Finish steel troweling twice first lightly
enough to remove surface defects; second
for final smoothing. Do second troweling
only after the concrete has hardened
sufficiently so that mortar adheres to the
edge of the trowel.
DONT
Dont overwork freshly placed
concrete. Excessive finishing brings
an excessive amount of water and
fines to the surface, resulting in a low
strength surface skin. Dont spread
dry cement on a finished surface to
absorb water. This reduces wear
resistance and durability of the surface
and induces crazing.
REV-2
15 January 2002
Homepage
PAGE: 3-9
Previous Document
3.3.5 Curing
DO
Cure by temperature and moisture control:
1. Keep concrete around 70F (21C) for
a minimum of 3 days after placement.
[The
hydration
process
ceases
altogether below 40F (4.5C)]
2. Keep concrete moist for at least 7 days
after pouring by (a) flooding the
surface to a depth of at least 1 inch (25
mm), or (b) covering with soaked
straw, burlap or waterproof paper, (c)
frequent sprinkling with water, or (d)
spraying the surface with a special
curing compound.
If possible, let concrete cure a full month
before putting it to full use. The first 3
days are very important in the life of
concrete. During this early period, when
the cement and water are combining
rapidly, the concrete is most susceptible to
permanent injury. At the age of 7 days, the
concrete has attained approximately 70
percent strength; at the end of 14 days,
approximately 85 percent; in 28 days,
almost full strength. Concrete actually
continues to gain strength for years.
REV-2
15 January 2002
Homepage
DONT
Dont permit concrete to lose water
rapidly. Cracking and loss of strength
occur when water evaporates too
rapidly. If concrete is kept moist for at
least 3 days after placement, it will
reach its peak strength with a
minimum of cracking.
Dont under any circumstances permit
freshly placed concrete to freeze. At
32F (0C) and below, expansion
changes within the mix will cause
permanent damage and drastic loss of
strength.
Dont let direct rays of the sun hit
freshly finished concrete. Direct heat
of the sun promotes too rapid drying.
Do shade the finished job and keep the
surface moist during the curing period.
PAGE: 3-10
Previous Document
PAGE: 3-11
Previous Document
in gauging the thickness of the application. Black compounds are both tough
and waterproof. When plans call for floor slabs to be covered with tile or
linoleum, a black curing compound provides an excellent base for those
materials. Black compounds should not be used in hot weather because black
pigments absorb heat.
C. White compounds White compounds are especially effective in hot weather
concreting. By reflecting a high percentage of heat rays, white compounds
help reduce the concrete temperature. If glare from white compounds is a
problem, a gray colored compound, which blends with the natural color of the
concrete can be used. Some of these compounds can inhibit the bonding of
paint to the concrete, so care should be exercised in the selection of a
compound.
4. Waterproof paper Waterproof paper is a widely used curing material, usually
available in widths of 18 inches (450 mm) to 96 inches (2,400 mm). This low
cost and efficient curing material is spread on the concrete surface with the edges
anchored with sand or planks. Waterproof paper provides an effective moisture
barrier, is easy to apply, offering some protection against damage from frost,
direct sun, traffic, mortar staining and debris. Cleanup is fast and easy. Often
waterproof paper can be reused, thereby offering still more economy. Some
waterproof curing papers are reinforced with a pattern of glass fibers to reduce
likelihood of tearing.
5. Plastic sheeting Plastic sheeting is a lightweight, flexible curing material.
Although higher in cost than most waterproof curing papers, plastic sheeting is
easy to fit over even the most complex shapes. Plastic sheeting is non-absorptive,
and therefore resists mildew and rotting. In addition, the weight of plastic
sheeting is constant, wet or dry. Plastic sheeting can be rolled up for reuse after
the curing process is completed. Plastic sheeting need not be idle between curing
applications it can be used for such jobs as protecting lumber and other job-site
materials from the weather.
Plastic sheeting is available in widths up to 32 feet. Because of the lightweight of
this material, little manpower is needed to handle the largest sizes. Durability
depends to a great extent upon the thickness of the material. Most plastic sheeting
used in the concrete industry is milky or white in appearance. This white pigment,
which has been added to an otherwise clear material, helps reflect heat rays, and
therefore helps keep concrete temperatures at the desired curing level. It can also
be welded, permitting airtight joints, thus aiding in preventing moisture
evaporation.
REV-2
15 January 2002
Homepage
PAGE: 3-12
Previous Document
NOTE
Wet earth, sand, straw, sawdust, cotton mats and similar
improvised materials commonly employed in the past have,
for the most part, fallen into disuse in the construction
industry. These materials are either inefficient or present
costly labor, material or cleanup problems. They may also
create a serious staining problem.
3.5 Weather Conditions
Applying a curing material to freshly placed concrete alone does not insure a properly
cured, finished product. Atmospheric conditions at the time of the pour and during the
curing period are very important in determining the final strength and surface perfection
of the concrete structure or slab. Problems must be anticipated, and provisions for
combating adverse conditions must be made in advance.
3.6 Hot Weather Curing
Hot weather can create excessive evaporation and excessive heat in freshly placed
concrete. If neglected during the curing period, these can cause permanent injury to
concrete.
Hot weather curing must be started as soon as possible after concrete is in place. If the
surface is hard enough to resist marring, the concrete is ready for protection against
evaporation loss and heat damage. If concrete is exposed to hot winds, windbreaks will
aid the curing process. Shading fresh concrete from direct rays of the sun will also help.
Water curing is very effective. Often, in very hot weather, it is advisable to cover the
concrete with standing water or to spray the concrete for 12 hours before employing other
curing mediums.
NOTE
Alternate wetting and drying must be avoided.
In hot weather, maximum strength and surface perfection will be attained if the curing
period is prolonged as long as possible at least 7 days. During the balance of the first
month, the green concrete should be subjected to limited use.
3.7 Cold Weather Curing
A basic rule for winter concreting is that the concrete must be prevented from freezing
during curing. It takes twice as long for concrete to set up and gain the strength needed
when the temperature is 50F (10C) as when it is 80F (27C). Strength gain of concrete
REV-2
15 January 2002
Homepage
PAGE: 3-13
Previous Document
PAGE: 3-14
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 3-15
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 4-1
Previous Document
4.4.1
Purpose
The purpose of this procedure is to provide standardized guidelines for the delivery of
project equipment and material. All project equipment and/or material will ship in
accordance with the guidelines contained within this procedure.
NOTE
No material will be transported to the job site without strict
adherence to the requirements established by this
procedure.
4.4.2
Areas of Responsibility
Material Planner
The Material Planner is responsible for shipping authorization compliance and work
order closeout.
4.4.2.3
Transportation Coordinator
Project Manager
The Project Manager is responsible for providing direction to PWPS personnel, the
Project Requirements in accordance with PWPS Contract.
REV-3
March 10, 2003
Homepage
PAGE: 4-2
Previous Document
4.4.2.5
The customer and/or the customers contractor are responsible for equipment off-loading
from all incoming trucks.
4.4.2.2 Quality Assurance
Quality Assurance is responsible for the inspection of all equipment, coordination of
Quality Inspection subcontractors and final sign-off of direct ship paperwork.
4.4.2.7 Site Inventory Advisor
The Site Inventory Advisor is responsible for all site inventory receipts, completion of
required paperwork, assisting and witnessing the customers physical inventory of cargo,
and obtaining customer written acceptance of the cargo.
4.4.3
Shipping Processes
PAGE: 4-3
Previous Document
1. Ship-to address
2. Shipping marks/labels (to be provided by Transportation/Logistics
NOTE
Each individual pallet or crate containing items shipped for
Project must be marked with this information.
A cargo manifest will be utilized in the event that one shipment is divided between two or
more trucks. The cargo manifest will describe exactly what is shipped on each truck.
Unit designators are required for each shipping authorization, for example Unit 1, Unit 2,
Unit 3, etc. These designators need to be communicated to the vendors/suppliers so that
they can properly mark their equipment, which will help to ensure that an accurate
inventory can be maintained at the site.
4.4.4
Shipment Tracking
A shipment tracking report will be available on PWPSs Website. This report will
contain all shipments that are currently moving to each site.
There will also be an inventory report, by warehouse location, on the internal PWPS Odrive server, which contains all equipment currently in storage.
Both of the shipment tracking report and the inventory report will be maintained and
updated daily by Transportation/Logistics.
4.4.5
Upon shipment of material to a job site and/or from the PWPS warehouse, the
Transportation Coordinator will notify the customer and PWPS site representative via a
pre-alert e-mail and/or Fax to the below listed locations:
1. PWPS site trailer
REV-3
March 10, 2003
Homepage
PAGE: 4-4
Previous Document
Shipment Pre-Alert
Upon receipt of the pre-alert notice, the PWPS Site Inventory Advisor will be ready to
receive the cargo. Once the cargo arrives at the site the PWPS Site Inventory Advisor
will complete the actions listed below. In the event material is damaged, the PWPS
representative(s) is to sign the B/L and state that material was received damaged. A copy
of the B/L will be transmitted back to the Transportation Coordinator, who will file claim
with the carrier and coordinate with the PWPS Purchasing Agent for inspection and/or
repair of the material.
Each Twin Pac/Power Pac will have its own folder listing a description of the item, part
number, top level assembly, shipping authorization, pre-alert notification and contain all
packing slips, bills of lading and bill of materials. The PWPS Site Inventory Advisor will:
REV-3
March 10, 2003
Homepage
PAGE: 4-5
Previous Document
PAGE: 4-6
Previous Document
PAGE: 4-7
Previous Document
Documentation
PAGE: 4-8
Previous Document
REV-3
March 10, 2003
Homepage
PAGE: 4-9
Previous Document
CARGO MANIFEST
TBOL/AWB #:
Load Manifest:
Ship Via:
Shipping Authorization:
Description:
Ship From:
Ship To;
ETD:
ETA:
Notes/Status:
Cargo Dimensions:
REV-3
March 10, 2003
Homepage
PAGE: 4-10
Previous Document
FROM:
COPY:
NUMBER OF PAGES:
P _________________
This document must be completed for each Straight Bill of Lading. When parts are
missing, please fax this document along with copies of the Bill of Lading and SA to
the phone number shown above. Mark the cover sheet Attn: Jeff Snelling
Attached are copies of the following Shipping Authorizations (SA) which have
missing parts:
SA Number
SA Number
REV-3
March 10, 2003
Homepage
Remarks
Top Assembly
Part
Inventoried
Yes/No
Parts Missing
From SA
Yes/No
SA Accepted
and Signed By
PAGE: 4-11
Previous Document
There is a standardized drawing tree numbering system that will be used for
all site-specific drawings. The drawing number consists of a four (4)-digit
project number assigned to a given site followed by a dash and the
standardized drawing tree number. The standardized drawing tree number is
broken down into two parts. The first part is typically a three-digit number,
which is the top-level drawing number. The second part is the specific
drawing number, which is made up of five characters.
For example: 9612-138-M000D
9612-
-138-
-M000D
Note that the five (5) digit specific drawing number always starts and ends
with a letter. The number will start with one of the following three (3) letters:
E, M or S. These letters indicate which Engineering group is responsible for
generating the drawing. The letter E is for electrical, M is for mechanical and
S is for structural.
REV-2
PAGE: 5-1
15 January 2002
Homepage
Previous Document
The five- (5) digit specific drawing number will end with one of the following
letters: B, D, J, and L. The letter B denotes that this is the detached bill of
material for the drawing with the same number while the letter D indicates
that it is a drawing or blue print, for example drawing number 9612-123E400B is the detached bill of material for drawing 9612-123-E400D. The
letter J indicates that this is a job specification, typically vendor equipment,
while the letter L is for listings, such as Load Lists or Cable Lists etc. e.g.
9612-189-E007L.
The standardized drawing tree numbers of interest to construction personnel
for FT8 systems are given in Table 5-1. This list leaves out some of the lower
tiers of numbers in the complete drawing tree and also many drawings that
normally would not be required for construction. A complete drawing tree
will be available for each installation.
2.
Drawings that usually are the same from site to site are given an IPX prefix,
where X denotes the drawing size, A through E. These generic drawings will
be listed on the overall drawing tree for a given site and will be crossreferenced to the corresponding standardized drawing number described in
paragraph (1) above, for reference. When an IPX (generic) drawing number is
used for a project, the standardized/site specific drawing number for that
drawing will not exist.
For example:
IPE-22180
NOTE
Some of the IP drawing numbers will be followed by a GR1, or a
GR2, or GR. designator. This designator indicates that the
drawing has multiple bills of materials. GR1 indicates to use the
quantities listed under the number 1 bill of material on the IP
drawing; GR2 indicates to use the number 2 bill of material, etc.
5.2.2 Specifications
The bulk of the PWPS parts provided for a particular project will not be made up of
drawing numbers as noted above. They will be CT part numbers. The CT is the PWPS
Specification for common materials such as pipe, wire, nuts and bolts etc., as well as
more specialized equipment like pressure transducers, flow meters, protective relays, etc.
The CT part number starts with the two letters CT followed by six numbers. For example
the PWPS Specification for Mobil Jet 254 Gas Turbine Oil is CT116675.
REV-2
PAGE: 5-2
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-3
15 January 2002
Homepage
Previous Document
as MS, AN, AS, ST, etc. In addition to these numbering systems, PWPS will use a
different numbering system for identification of gas turbine and power turbine parts.
REV-2
PAGE: 5-4
15 January 2002
Homepage
Previous Document
XXXX-112
XXXX-112-S000D
XXXX-112-S000B
XXXX-113
XXXX-113-S000D
XXXX-113-S000B
XXXX-113-S100D
XXXX-113-M200D
XXXX-114
XXXX-114-S100D
XXXX-114-E100D
XXXX-114-S200D
XXXX-114-E200D
XXXX-114-S300D
XXXX-114-E300D
This is a master drawing tree listing. A project will use some of these drawings, as required.
REV-2
PAGE: 5-5
15 January 2002
Homepage
Previous Document
ASSY, FOUNDATION
ASSY, FOUNDATION
ASSY, FOUNDATION, BILL OF MATERIAL
FOUNDATION INTERFACE, MAIN
FOUNDATION, INTERFACE, TRENCH
FOUNDATION, FUEL SYSTEM FILTER
FOUNDATION, FUEL SYSTEM FORWARDING
FOUNDATION, INTERFACE, MAIN BREAKER
FOUNDATION, INTERFACE, LUBE OIL SKID
FOUNDATION, INTERFACE, CONTROL ENCLOSURE
FOUNDATION, INTERFACE, DIESEL GENERATOR
FOUNDATION, INTERFACE, GAS SCRUBBER
FOUNDATION, INTERFACE, HYDRAULIC START
SYSTEM
FOUNDATION, INTERFACE, AIR START SYSTEM
FOUNDATION, INTERFACE, LIQUID FUEL SYSTEM
XXXX-121-E303D
XXXX-121-E303B
XXXX-121-E305J
XXXX-121-E306D
XXXX-121-E400D
XXXX-121-E401D
XXXX-121-E500D
XXXX-121-E500B
XXXX-122
XXXX-122-E000D
XXXX-122-E100D
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-6
15 January 2002
Homepage
Previous Document
XXXX-123-E300D
XXXX-123-E300B
XXXX-123-E400D
XXXX-123-E400B
XXXX-123-E500D
XXXX-13
XXXX-131
ANCILLARY SYSTEMS
SKID, STARTING
XXXX-132
XXXX-132-M00J
FIRE SYSTEM
SPEC, FIRE/GAS DETECTION & SUPPRESSION
XXXX-133
XXXX-133-M100J
XXXX-133-M200J
XXXX-133-M300J
XXXX-133-M400J
GAS FUEL
SPEC, SKID, GAS METERING
SPEC, SKID, GAS FILTERING
SPEC, SKID, GAS FUEL COMPRESSOR
SPEC, SKID, GAS PRESSURE REDUCING
XXXX-134
XXXX-134-M100D
XXXX-134-M100B
XXXX-123-E150D
XXXX-123-E200D
XXXX-123-E200B
XXXX-134-M100J
XXXX-134-M200J
XXXX-134-M300J
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-7
15 January 2002
Homepage
Previous Document
XXXX-136
XXXX-136-M100J
XXXX-137
EQUIPMENT, MISCELLANEOUS
XXXX-138
XXXX-138-M000D
XXXX-138-M000B
XXXX-138-M400D
XXXX-138-M400B
FIELD PIPING
ASSY, PWPS FIELD PIPING
ASSY, PWPS FIELD PIPING, BILL OF MATERIAL
ASSY, FIELD, COLD AIR BUFFER
ASSY, FIELD, COLD AIR BUFFER, BILL OF MATERIAL
XXXX-14
XXXX-141
XXXX-141-S100J
XXXX-141-S200J
XXXX-141-S300J
XXXX-141-S400J
XXXX-141-S401J
XXXX-141-S402J
BALANCE OF PLANT
WASTE HEAT BOILER
SPEC, BOILER
SPEC, SYSTEM, BOILER FEED WATER
SPEC, SYSTEM, BYPASS
SPEC, CONDENSER
SPEC, CONDENSER INLET DUCT
SPEC, SKID, CONDENSATE PUMP
XXXX-142
XXXX-142-S100J
XXXX-142-S200J
XXXX-142-S300J
WATER TREATMENT
SPEC, SYSTEM ,WATER DEMINERALIZATION
SPEC, SYSTEM, WASTE WATER TREATMENT
SPEC, SKID, MAKEUP WATER
XXXX-143
XXXX-143-S100J
XXXX-143-S200J
XXXX-143-S300J
XXXX-143-S400J
EMISSIONS MONITORING
SPEC, SCR
SPEC, CO CONVERTER
SPEC, SYSTEM, CHEMICAL INJECTION
SPEC, SYSTEM, CONTINUOUS EMISSIONS
MONITORING
SPEC, MONITOR, OPACITY
XXXX-143-S500J
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-8
15 January 2002
Homepage
Previous Document
PLANT COOLING
ASSY, SYSTEM, PLANT COOLING
ASSY, SYSTEM, PLANT COOLING
XXXX-145
XXXX-145-S100J
XXXX-145-S200J
XXXX-145-S300J
XXXX-145-S400J
XXXX-145-S500J
XXXX-145-S600J
TANKS
SPEC, TANK, LIQUID FUEL OIL STORAGE
SPEC, TANK, RAW WATER STORAGE
SPEC, TANK, DEMINERALIZED WATER STORAGE
SPEC, TANK, CAUSTIC SODA STORAGE
SPEC, TANK, ACID STORAGE
SPEC, TANK CONDENSATE STORAGE
XXXX-146
XXXX-146-S100J
COMPRESSOR, MARINE
SPEC, COMPRESSOR/MARINE SYSTEM
XXXX-147
XXXX-147-S100J
XXXX-147-S200J
XXXX-151
XXXX-151-E100J
XXXX-151-E101J
XXXX-151-S102J
XXXX-151-E103J
ELECTRIC GENERATOR
SPEC, ELECTRIC GENERATOR
SPEC, DIESEL GENERATOR SET
SPEC, STEAM TURBINE GENERATOR
SPEC, AUTOMATIC VOLTAGE REGULATOR
XXXX-152
XXXX-152-E000D
XXXX-152-E100J
XXXX-152-E101J
XXXX-152-E102J
XXXX-152-E103J
XXXX-152-E105J
XXXX-152-E200J
XXXX-152-E300J
XXXX-152-E301J
XXXX-152-E302D
XXXX-152-E400J
* This is a master drawing tree listing. A project will use some of these drawings, as required.
REV-2
PAGE: 5-9
15 January 2002
Homepage
Previous Document
HIGH VOLTAGE
SPEC, ASSY, SYSTEM, STEP UP TRANSFORMER
XXXX-16
OPEN CATEGORY
XXXX-17
XXXX-171-S000B
XXXX-172-S000B
START UP SPARES
XXXX-181
XXXX-181-M100D
XXXX-181-M200D
XXXX-181-M201D
XXXX-181-M202D
XXXX-181-M203D
XXXX-181-M204D
XXXX-181-M300D
XXXX-181-M301D
XXXX-181-M302D
XXXX-181-M303D
XXXX-181-M304D
XXXX-181-M305D
XXXX-181-M306D
XXXX-181-M307D
XXXX-181-M400D
XXXX-181-M401D
XXXX-181-M402D
XXXX-181-M403D
XXXX-181-M404D
XXXX-181-M405D
XXXX-181-M500D
XXXX-181-M501D
XXXX-181-M502D
XXXX-181-M505D
XXXX-181-M506D
XXXX-181-M507D
P & IDS
DIAGRAM, P&I, GAS TURBINE SYSTEMS
DIAGRAM, P&I, FUEL AND INJECTION SYSTEMS
DIAGRAM, P&I, LIQUID FUEL SYSTEM
DIAGRAM, P&I, GAS FUEL SYSTEM
DIAGRAM, P&I, WATER INJECTION SYSTEM
DIAGRAM, P&I, STEAM INJECTION SYSTEM
FUEL CONDITIONING SYSTEMS
DIAGRAM, P&I, GAS FUEL CONDITIONING SYSTEM
DIAGRAM, P&I, GAS METERING SYSTEM
DIAGRAM, P&I, GAS FILTERING SYSTEM
DIAGRAM, P&I, LIQUID FUEL CONDITIONING SYSTEM
DIAGRAM, P&I, LIQUID FUEL METERING SYSTEM
DIAGRAM, P&I, LIQUID FUEL FILTERING SYSTEM
DIAGRAM, P&I, LIQUID FUEL FORWARDING SYSTEM
AUXILIARY SYSTEMS
DIAGRAM, P&I, HYDRAULIC OIL SYSTEM
DIAGRAM, P&I, LUBRICATION SYSTEM
DIAGRAM, P&I, START SYSTEM
DIAGRAM, P&I, MUSCLE AIR SYSTEM
DIAGRAM, P&I, ENGINE HEAT SYSTEM
DIAGRAM, P&I, SUPPORT SYSTEMS
DIAGRAM, P&I, FIRE SYSTEM
DIAGRAM, P&I, ENGINE COOLING SYSTEM
DIAGRAM, P&I, ANTI-ICE SYSTEM
DIAGRAM, P&I, WATER WASH SYSTEM
DIAGRAM, P&I, VENT & DRAIN SYSTEM
* This is a master drawing tree listing. A project will use some of these drawings, as required.
REV-2
PAGE: 5-10
15 January 2002
Homepage
Previous Document
XXXX-182
OPEN CATEGORY
XXXX-183
XXXX-183-S100D
XXXX-183-S101D
XXXX-183-S102D
XXXX-183-E102D
XXXX-183-S103D
XXXX-183-S104D
XXXX-183-M200D
XXXX-183-M300D
XXXX-183-M301D
XXXX-183-M400D
XXXX-183-M401D
XXXX-183-E500D
XXXX-183-E501D
XXXX-183-E506D
XXXX-183-E507D
XXXX-183-E508D
XXXX-183-E509D
XXXX-183-E510D
XXXX-183-E511D
XXXX-183-E512D
XXXX-183-E513D
XXXX-183-E514D
XXXX-183-E600D
XXXX-183-E601D
OUTLINE, DRAWINGS
ENCLOSURE/TURBINE OUTLINES
OUTLINE, ISLAND, GAS TURBINE
OUTLINE, GAS TURBINE & BASE
OUTLINE, A BOX
OUTLINE, ENCLOSURE, MECHANICAL PACKAGE
OUTLINE, COLLECTOR BOX, INTERFACE
PRIMARY SKID OUTLINES
MISC SKID OUTLINES
OUTLINE, LUBE OIL SKID
FUEL FILTERING/METERING SYSTEM OUTLINES
OUTLINE, LIQUID FUEL METERING
OUTLINE, CONTROL CENTER
OUTLINE, MCC
OUTLINE, CABINETS INSTRUMENT & CONTROL
OUTLINE, CABINET, REMOTE TERMINAL UNIT (RTU)
OUTLINE, CABINET, AUXILIARY EQUIPMENT
OUTLINE, CABINET, GAS TURBINE INSTRUMENT
OUTLINE, CABINET, OPERATOR CONTROL
OUTLINE, CABINET, GENERATOR INSTRUMENT
OUTLINE, CABINET, PROTECTIVE RELAY
OUTLINE, CABINET, MASTER TERMINAL BOARD (MTB)
OUTLINE, CABINET, REMOTE CONTROL
OUTLINE, ENCL. REMOTE I/O
OUTLINE, ENCL. EM35, DIGITAL DRIVER, GAS FUEL
XXXX-184
XXXX-184-S100D
FOUNDATION LOADING
LOADING, FOUNDATION, GAS TURBINE ISLAND
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-11
15 January 2002
Homepage
Previous Document
ONE-LINE/BLOCK/FLOW DIAGRAMS
DIAGRAM, ONE LINE
DIAGRAM, FLOW, WASTE HEAT RECOVERY SYSTEM
DIAGRAM, BLOCK, POWER ISLAND
DIAGRAM, BLOCK, CONTROL SYSTEM
DIAGRAM, INTERCONNECT, FIRE SYSTEM
DIAGRAM, ONE LINE, MCC
PLANT INTERCONNECT
DIAGRAM, CABLE, ENGINE & ENCLOSURE
XXXX-186
XXXX-186-C110D
XXXX-186-C140D
XXXX-186-C150D
XXXX-186-C160D
XXXX-186-C170D
XXXX-186-C180D
XXXX-186-C190D
XXXX-186-C210D
XXXX-186-C230D
XXXX-186-C240D
XXXX-186-C260D
XXXX-186-C280D
XXXX-186-C290D
XXXX-186-C360D
XXXX-186-C370D
XXXX-186-C380D
XXXX-186-C600D
XXXX-186-C601D
LOGIC DIAGRAMS
DIAGRAM, LOGIC, LUBE OIL
DIAGRAM, LOGIC, LIQUID FUEL SYSTEM
DIAGRAM, LOGIC, LIQUID FUEL CONDITIONING
DIAGRAM, LOGIC, PANEL INSTRUMENTATION & CONTR
DIAGRAM, LOGIC, WATER INJECTION
DIAGRAM, LOGIC, STEAM INJECTION
DIAGRAM, LOGIC, GAS TURBINE CONTROL INTERFACE
DIAGRAM, LOGIC, FIRE SYSTEM
DIAGRAM, LOGIC, GENERATOR LUBE OIL
DIAGRAM, LOGIC, GENERATOR INSTRUMENTATION
DIAGRAM, LOGIC, DIAGNOSTICS, UNIT CONTROL
DIAGRAM, LOGIC, ANCILLARY SYSTEMS
DIAGRAM, LOGIC, WATER WASH
DIAGRAM, LOGIC, BALANCE OF PLANT
DIAGRAM, LOGIC, START UP
DIAGRAM, LOGIC, SHUTDOWN
DIAGRAM, LOGIC, GAS TURBINE CONTROL (SIMPLIFIED)
DIAGRAM, LOGIC, GT CONTROL
XXXX-187
XXXX-187-E100D
XXXX-187-E101D
XXXX-187-E102D
XXXX-187-E103D
XXXX-187-E104D
SCHEMATICS
SCHEMATIC, CONTROLLERS
SCHEMATIC, UNIT CONTROL
SCHEMATIC, GAS TURBINE CONTROL
SCHEMATIC, PLANT CONTROL
SCHEMATIC, PHOENIX RELAY BLOCK
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-12
15 January 2002
Homepage
Previous Document
XXXX-188
OPEN CATEGORY
XXXX-189
XXXX-189-E000L
XXXX-189-C001L
XXXX-189-C002L
XXXX-189-C003L
XXXX-189-C004L
XXXX-189-C005L
XXXX-189-E006L
XXXX-189-E007L
XXXX-189-E008L
XXXX-189-E011L
XXXX-189-E102L
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-13
15 January 2002
Homepage
Previous Document
MANUALS
SPECIFIC OPERATING INSTRUCTIONS
FT8 SYSTEMS MAINTENANCE
GAS GENERATOR MAINTENANCE
POWER TURBINE MAINTENANCE
GG8 ILLUSTRATED PARTS CATALOG (IPC)
PT8 ILLUSTRATED PARTS CATALOG
* This is a master drawing tree listing. A project will use some of these drawings as required.
REV-2
PAGE: 5-14
15 January 2002
Homepage
Previous Document
2.
3.
Reference to the above drawing and documentation system should be adequate to provide
installation information for the Site Supervisor and/or Construction Engineers.
REV-2
PAGE: 5-15
15 January 2002
Homepage
Previous Document
5.4
The following sections provide general information to assist and guide the Site
Supervisor and/or Construction Engineers during installation of FT8 Power Pac, Twin
Pac and Swift Pac systems. The following sections cover sub-systems, such as the
electric generator and the gas turbine base assembly, for which additional information
might be helpful. Information is given in tabular form in Table 5-2 at the end of Section
5 for the remainder of the FT8 sub-systems.
5.4.1 Installation of Electric Generator
5.4.1.1 Prior to Placement
The following section outlines general procedures to prepare for placement and grouting
of the electric generator.
NOTE
Prior to setting the generator it is recommended that
accurate lateral and axial reference lines be established on
the foundation, preferably scribed on the metal plates under
the coupling(s) and at Engine Station 218.50 (reference
drawings XXXX-113-S000D, sheet 2 and XXXX-115S100D). This would allow precise axial and lateral
placement of the generator when initially set, possibly
eliminating the necessity for lateral and axial jacking of the
generator for precise location. This does not imply that
axial and lateral location need not be checked during and
after lateral and axial leveling.
Before any machinery is placed, the concrete areas that are grouted must be chipped back
and swept or air blown clean. A rough as-cast surface will not suffice.
Remove the protective water stops from the anchor bolt sleeves to inspect and remove
any water. The anchor bolt sleeves must be free of debris and water.
Wire brush the anchor bolts and threads if necessary. Lubricate with grease and spin on
the anchor bolts mating nuts to be certain the threads are clean. Then re-install the
protective water stops or back fill with clean, dry sand.
Verify the location of the generator guide pin and locating block embedments. If these
embedments are scheduled to be installed after the placement and grouting of the
electrical generator, insure that a large enough pocket is left in the foundation so that they
can properly installed after the installation of the generator.
REV-2
PAGE: 5-16
15 January 2002
Homepage
Previous Document
The electric generator will be shipped to site in a wooden create and bolted to two steel
shipping beams. Inside the create the generator will be wrapped in a protective vapor
barrier. The generator may be set over the foundation in the shipping create or removed
from the create and then sent on the foundation.
The removal of the wooden crate from around the electric generator requires some effort.
The crate will need to be cut around its entire perimeter near the bottom of the box. This
can be done by cutting through the protective sheeting and wood framing or by pulling off
the lower section of sheeting followed by cutting the wood framing. Once the wooded
crate is completely cut through at the perimeter then the top half of the box can be
removed with a crane. Use two safety lines when lifting the crate; and, use caution not to
damage any of the instrumentation or hardware on the generator. To remove the bottom
half of the crate, four of the generator access covers will need to be opened so that the
shipping beams can be unbolted from the generator frame. Once the shipping beams are
unbolted then the generator can be lifted by crane and the floor can be pulled out from
underneath the generator.
5.4.1.2 Installation
Electric generator installation procedures will vary depending upon the type,
manufacturer and model of generator to be installed. Specific instructions for a given site
will be given in the drawing system described above, and by the manufacturers
Installation Instruction Manual.
In general, these precautions must be observed:
1. Always use extreme care in handling of the equipment to prevent personal injury
and/or damage to the equipment.
2. Make certain that lifting devices (cranes, hoists, lift trucks, etc.) are of adequate
capacity.
3. Make certain that straps, chains, slings, etc. are of adequate capacity and in good
condition.
4. When lifting and handling the equipment, do not disturb or bend the piping on the
exterior of the frame.
5. If the rotor is shipped separate from the stator, check inside the stator for bolts,
rags, small tools, packing material, etc. Check the rotor surface to see that pieces
of steel are not clinging to it due to residual magnetism.
6. The generator is located as required in the mechanical field assembly drawing by
manipulating the jacking screws and grouted.
REV-2
PAGE: 5-17
15 January 2002
Homepage
Previous Document
Since much of the expertise in heavy equipment installation is gained through experience,
generator manufacturers normally recommend that the user should benefit from the
services of their representative during installation.
The contract with the generator manufacturer will normally include a requirement to have
a service representative assist during the test and checkout phase of installation and not
with installation.
Although a crane is desirable for moving the generator to its foundation, the generator
may be skidded or rolled into place with winches. If a crane is used, use spreader beams
to keep lifting cables vertical. If the generator is to be skidded or rolled, use two winches,
whether the ground is level or slopedone winch to pull, the other on the opposite side
to play out slack. This prevents the generator from having a surging movement that could
cause loss of control. Greased plates, rails and cribbing should always be arranged so that
tipping the generator more than 15 degrees from the vertical is unnecessary. Experienced
riggers can best determine the amount of plates, planks, rails, or rollers, the size of cranes,
etc..
Axial and lateral positioning should be established using the vendors instructions and
drawing for the specific generator being installed. Also, the design elevation of the
generator rotor axis above foundation elevation 0.000 must be maintained within limits so
that proper mating of gas turbine/generator enclosure components can be achieved,
because the gas turbine enclosure is located by placing it on a 1-inch gasket. This gasket,
compressed to one half inch (), precludes any elevation adjustment of the enclosure.
5.4.1.3 Running Bearing Installation
The following instructions are given for replacement of shipping bearings, if used, with
running bearings. Alternatively, the generator may be shipped with a sheet of Mylar
between the shaft journal and the running bearings, for protection during transit. In this
case, only step (1) below would be necessary to remove the Mylar.
NOTE
The instructions given herein are intended for an Electric
Machinery generator. For a generator from another
vendor, installation instructions may vary. Refer to the
vendors installation manual for the necessary tooling and
further instructions.
To remove the shipping bearing, if a shipping bearing is
used, removal of the upper end bell or sliding back of the
exciter housing may be required. The exciter end-bearing
cap can then be removed. A block and tackle will be
REV-2
PAGE: 5-18
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-19
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-20
15 January 2002
Homepage
Previous Document
PAGE: 5-21
15 January 2002
Homepage
Previous Document
XXXX-111
XXXX-112
XXXX-113
The XXXX in these numbers will be the project number for the specific site.
Once the gas turbine assembly enclosure is installed, insure the maintenance trolley
assembly is installed prior to accomplishing any maintenance actions on the gas turbine
assembly. PWPS drawing IPE 21779, sheets 1 and 2 provide details of the maintenance
trolley assembly.
CAUTION
The guide tabs installed on the maintenance trolley
assembly are installed as safety devices. Do not use the
maintenance trolley without these tabs installed.
When not is use, secure the trolley to the end wall of the
enclosure using a cable to secure the maintenance trolley to
the wall.
5.6 Gas Turbine to Generator Alignment
The following section outlines the objectives and procedures involved in the alignment of
the gas turbine, coupling spacer shaft and generator packages.
NOTE
If the ambient temperature is less than 60F, provisions
should be made for gas turbine and generator enclosure
space heating during grouting and before engine alignment
begins.
Prior to the alignment procedures, it is presumed that the following procedures have been
completed as part of the gas turbine and generator installation:
1. Generator and exciter heaters have been energized for several days prior to the
start of engine-to-generator alignment. These heaters should remain energized
during the alignment and recording of final readings, or considerable
misalignment may occur.
2. Anchor bolt locations have been carefully checked before and after pouring of
foundations, and the jacking pads are on their design elevations. This is critical,
especially if this elevation is to be used for reference when establishing generator
elevation.
REV-2
PAGE: 5-22
15 January 2002
Homepage
Previous Document
3. Elevations of the top of all anchor bolts have been checked to insure sufficient
anchor bolt penetration through the bottom plates of the machinery.
5.6.1 Alignment Tools and Equipment
The following tools and equipment are required and are to be provided by the installing
contractor or owner:
Special Tools:
Tool No.
Tool Name
TC350-115
TC350-116
Cradle (1)
Rail (2 pieces)
or
PWA 77582
TC350-117
Cradle Support
Compressor (Lucas) (5)
or
TC350-118
TC350-165
Additional Tools:
Tool Name
Magnetic Base (2)
Dial Indicator, 0 to 1inch (2)
ID Micrometer, 0-4
inch or equivalent
Center Head
Consumables:
Spec No.
PWA 521
PWA 586
Name
Engine Oil
Anti-seize Compound
PAGE: 5-23
15 January 2002
Homepage
Previous Document
PAGE: 5-24
15 January 2002
Homepage
Previous Document
1.
Distillate fuel
TPM FR-1
2.
Gaseous fuel
TPM FR-2
REV-2
PAGE: 5-25
15 January 2002
Homepage
Previous Document
3.
Injection Water
TPM AR-1
PAGE: 5-26
15 January 2002
Homepage
Previous Document
Specifications
American Petroleum Institute Specifications Code 650
National Fire Protection Association Code 30
Underground
U.L. 58
The tank will be of butt welded construction, normally with adapters to receive the
equipment listed below, furnished and installed by the tank fabricator:
1. Outside ladders or stairs
2. Shell manhole
3. Automatic level gage with high low level contacts
4. Emergency vent and manway cover
5. A vent with bird screen
6. Non-freezing drain valve
7. Fill line connections
8. Discharge line connections
9. Floating suction assembly
REV-2
PAGE: 5-27
15 January 2002
Homepage
Previous Document
Whether horizontal or vertical, fuel tanks must have provisions for water draw-off.
Horizontal tanks should have a pitch of 1 to 3percent with a water draw line provided at
the lowest point of the tank. Vertical tank bottoms must have a sump near the outer
periphery of the tank. A bottom water draw-off line should pass through the shell and
terminate in the center of the sump below the lowest point of the tank bottom. Tank
bottom pump-out provision is required for underground tanks. Each storage tank must be
equipped with floating suction assembly.
At the lowest traverse, the suction bell shall be clear of the tank bottom in conformance
with the following:
Floating Suction Line
Diameter
Clearance to Bottom
3 inch
4 inch
6 inch
0-150 gpm
150-350 gpm
above 350 gpm
7 inch
9inch
12 inch
The tank fill line must terminate within six (6) inches of the bottom of the tank to avoid
splash loading. The fill line termination must be located in a place as remote as possible
from the floating suction inlet.
5.7.1.2.1 Tank Exterior
All exterior surfaces are to be cleaned, primed and finish painted as required in tank
specifications.
5.7.1.2.2 Testing
After tank fabrication is completed, filling the tank with water shall test the welded
seams. Before inspecting the tank, the temperature of the water should be allowed to
equalize with the ambient temperature, so that sweating of the tank skin will not be
mistaken for leakage.
5.7.1.2.3 Grounding
The tank should be grounded to the site grounding grid.
5.7.1.3 Fuel Forwarding Skid
The purpose of the fuel forwarding skid is to deliver fuel oil from the fuel oil storage tank
to the engine fuel oil pump, passing through the fuel strainer, meter, fire valve and filter
at a pressure of 50 psi to the inlet of the engine fuel oil pump.
The skid consists of the following equipment:
REV-2
PAGE: 5-28
15 January 2002
Homepage
Previous Document
1. Strainer - Installed on the suction line of the pumps in order to prevent damage to
the pump impeller by foreign material.
2. Check Valve - Installed on each pump discharge line to prevent one pump from
motoring the other pump during the non-operating period of the inoperative pump.
3. Pressure Switch - Connected at the output of each AC pump in systems with two
AC pumps to indicate which pump is operating and if it is operating above the
minimum required pressure.
4. Orifice Plate - Installed in the line between pump discharge header and pump
suction header to bypass fuel during no flow conditions, thereby protecting the
pumps.
5. Main Pump and Motor Assembly - A 50 GPM, 50 psig, centrifugal pump, driven
by a 380/480 volt, 3-phase, 50-60 Hz motor on Power Pacs. Twin Pacs use a 100
GPM pump and motor.
6. Auxiliary Pump and Motor Assembly - A 5 GPM, 50 psig, centrifugal pump,
driven by a 125 VDC motor on Power Pacs and a 10 GPM pump on Twin Pacs.
7. Base Frame - A channel frame provides for complete component mounting and
support. Also, the skid should be grounded to the site grid system.
8. Pressure Gages - Installed with block and bleed valves to read pump input and
output pressures.
5.7.1.4 Main Fuel Filter
The main fuel filter is basically an unfired pressure vessel constructed of steel in
accordance with ASME code with its respective depth type filters. A depth type filter is
designed to filter out large particles at the O. D. of the element and small particles toward
the center, as well as remove moisture.
5.7.1.5 Flow Meter
If a liquid fuel flow meter is incorporated in the system, it should be installed according
to manufacturers recommendations. Also, the meter body should be checked to assure
that the direction of flow is correct.
5.7.1.6 Fire Valve
The fire valve, a trip release shutoff valve, is installed downstream of the final filter. The
valve is designed to close automatically when de-energized and is used to shut the unit
down in case of fire in the engine enclosure. It must be manually reset after closing to
restart the engine. Whenever possible, it is preferred that the valve be installed in a
horizontal pipeline with its top assembly upright. This is especially true whenever it is to
be located out-of-doors exposed to the weather.
REV-2
PAGE: 5-29
15 January 2002
Homepage
Previous Document
The trip valve must be mounted in the pipeline so that flow through it will be in the same
direction as that indicated by the arrow cast on the valve body. If the valve is located in a
long run of piping, supports must be provided to avoid placing the valve body in a bind.
To check valve operation, energize the circuit to the valve. Open the manual reset valve
to fully open, then break the current so that the valve closes. Repeat this operation
several times to provide a positive check on the valves performance and permit the seat
and disc to be wiped free of any foreign matter which may have accumulated in the line
during installation. Note that the valve must be functionally tested in conjunction with
the Fire Protection System.
5.7.1.7 Final Filter
A final filter is installed upstream of #1 and #2 shutoff valves, and is used to remove
particles between the main fuel filter and the fuel pump. In the installation of the filter,
the arrow on the body should be checked for direction of flow. Piping supports should be
installed within 12 of the inlet and outlet connections.
5.7.2 Installation
5.7.2.1 Skids
Prior to setting the individual skids on their foundation, the anchor bolt location should
be checked for proper alignment. The anchor bolt threads should be lubricated and
chased with a mating nut. The foundation surface should also be checked for levelness.
After the skid has been set, again check for levelness and, if necessary, add shims and
tighten down on the anchor bolts. After the anchor bolts have been tightened, the skid
should be grouted to its foundation. Even though the alignment between the skid pump
and motors is set at the factory prior to shipment, make a final check before operating.
5.7.2.2 Piping
All piping after the main filter must be schedule 40 seamless, stainless steel pipe, meeting
the required ASME specifications. Fuel forwarding piping is usually schedule 40 carbon
steel pipe. All pipe should be pickled, coated with non-additive SAE 20 mineral oil, and
the pipe ends capped before leaving the pipe manufacturers shop.
If pipe is to be stored outside for a considerable length of time at the construction site, it
should be supported on blocks every five (5) feet.
All welding on fuel oil pipe should meet the requirements of the American Welding
Society and the ASME Boiler and Pressure Vessel Code and Power Piping Code 31.1.
All fuel oil piping to be installed underground should have a protective covering, using
procedures as specified by the contractor.
REV-2
PAGE: 5-30
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-31
15 January 2002
Homepage
Previous Document
4. Do not use natural rubber hose, lamp cords, etc., with oil or oil handling
equipment.
5. Do not pull oil into a transformer unless it has been tested for dielectric strength.
Oil should test 30 KV or more. (Take a sample from the bottom of the oil
container)
6. Do not compress nitride gaskets more than 30 percent.
7. Do not test insulation with a megohmmeter or make electrical tests while the
transformer is under vacuum; it could cause insulation failure.
8. Do not enter a transformer until analysis of air in tank shows at least 19.5 percent
oxygen. Station a man near the manhole outside the tank when someone is inside
the transformer.
9. Do not stand on a transformer cover under vacuum.
10. Do not smoke on top of the transformer when the manhole covers are open, or in
the vicinity of oil handling equipment. When the transformer is open, no one
should be on the cover unless he has removed all loose items from his pockets,
cuffs, etc. All tools taken into the transformer must be accounted for before a
transformer is buttoned up.
11. Do not stand on any electrical insulation inside the transformer.
12. Do no make pressure or vacuum tests before checking the nameplate notes. Some
transformers require that pressure between the main tank and other compartments
be equalized.
13. Do not pull a vacuum on a transformer tank when it is raining, to avoid pulling
moisture into the unit. Likewise, do not let a vacuum pump run overnight
unattended.
14. Do not shut down the vacuum pump before closing the vacuum valve.
15. Do not attempt to take oil samples with a vacuum in the air space above the
transformer. (Air may enter into the oil and lodge in the core and coils).
16. Do not drill holes in the transformer tank braces before checking whether the
braces are air compartments.
17. Do not permit a three-phase transformer to soak without checking the output
voltages to insure that all three phases are applied to the transformer input. An
REV-2
PAGE: 5-32
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-33
15 January 2002
Homepage
Previous Document
2. Level unit with jack screws using dial indicators on coupling halves and bubble
level on flat of compressor crankcase surface. This operation will be done with a
vendors serviceman present.
3. Grout per instructions.
4. After grout has cured, back off on jack bolts.
5. Pull down on foundation bolts.
6. Recheck coupling alignment and, if correct, dowel motor as required per prints.
5.10 Installation of Other FT8 Sub-Systems (Refer to Table 5-2)
Table 5-2 presents PWPS drawing tree numbers and installation instructions for
additional FT8 sub-systems. The PWPS drawing tree system is described in paragraph
5.2.
5.10.1 FT8 Sub-Systems
Table 5-2 gives information on the following FT8 sub-systems:
1. Gas Turbine and Base
2. Enclosure Assembly
4. Exhaust Enclosure
6. Secondary Air
7. Engine Heater
9. Exhaust System
23. Generator
24. Switchgear
REV-2
PAGE: 5-34
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
XXXX-XXX
SPECIAL INSTRUCTIONS
Anchor bolts must be located within
tolerances (typically +/-1/8 inch) to avoid
poor assemblies.
Lubricate thread bolts and chase with a
mating nut.
Check conduit and piping stub-up
lengths, material, size, and locations
against the drawings.
Check incoming wiring against the
drawings.
When placing skid, avoid twisting the
frame, which can misalign motors and
driven loads.
Shim and grout per applicable drawing.
Make sure connecting pipes are clean.
Torque hold down bolts, making sure that
piping connections are stress-free.
Check location and method of attaching
ground cable.
Test system per specifications.
Paint assembly per specifications, if
applicable.
Lifting fixtures and spreader beams for
bottom lift skids.
REV-2
XXXX-111-
PAGE: 5-35
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
SPECIAL INSTRUCTIONS
ENCLOSURE
ASSEMBLY
XXXX-112-
GAS TURBINE
ENCLOSURE
XXXX-112-
XXXX-112-
DRIVEN EQUIPMENT
ENCLOSURE
XXXX-112-
SECONDARY AIR
XXXX-112-
ENGINE HEATER
XXXX-112-
XXXX-112-
EXHAUST SYSTEM
REV-2
XXXX-112-
None
PAGE: 5-36
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
XXXX-113-
SPECIAL INSTRUCTIONS
See Section 5.7 for alignment of
coupling between gas turbine and driven
load.
See drawing XXXX-113 for field
installation of bleed ducts, collector box,
and diffuser assembly. Align collector
box per requirement on drawing XXXX113.
ANCILLARY
ENCLOSURES
XXXX-114-
CONTROL HOUSE
XXXX-121-
Confirm foundation
locations.
and
anchor
bolt
REV-2
PAGE: 5-37
15 January 2002
Homepage
Previous Document
XXXX-131-
FIRE PROTECTION
SYSTEM
(See Sheet 5 for continued
information on the Fire
Protection System)
XXXX 132 -
REV-2
PAGE: 5-38
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
SPECIAL INSTRUCTIONS
Unused conduit openings must be
sealed with plugs. For the devices, a
shipping plug is installed when
shipped.
If one of the conduit
openings is not used, then the shipping
plug must be removed and a
permanent plug installed to insure no
moisture can enter the device.
For all outdoor connectors and fittings,
insure a proper rain-tight and/or rainproof seal is provided. In the past, fire
protection system installers have
found many of the fittings were
installed with the gasket on the fitting
not sealing against the body of the
device boxes.
For the manual pull stations, the
mounting box is supplied with spacers
attached at the screw locations and a
gasket is attached to the rear of the
pull station. See Figure 5 1. The
spacers must remain to insure a good
gasket seal with the pull station.
NOTE
Detailed spacers are not available from
the vendor. If spacers have already
been removed and/or lost, then the
only option is to install the manual
pull station without them.
REV-2
PAGE: 5-39
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
XXXX 133 -
SPECIAL INSTRUCTIONS
See instructions in Section 5.10 for
installation of gas compressor.
Check alignment between compressor
and motor before operating.
Hydrostatic test and blow down field
installed piping per instructions in
Chapter 7.
Check operation of compressor and
protection system per test instructions.
LIQUID FUEL
CONDITIONING
XXXX 134 -
WATER INJECTION
SYSTEM
XXXX 135 -
XXXX 133 -
XXXX 134 -
REV-2
PAGE: 5-40
15 January 2002
Homepage
Previous Document
DRAWING TREE
DRAWING NO.
SPECIAL INSTRUCTIONS
HYDRAULIC OIL
SYSTEM
XXXX 137 -
WATER WASH
SYSTEM
XXXX 137 -
NOTE
Customer connection is under the
foundation, and must be made prior to
pouring the main foundation.
Hydrostatic test and flush field
installed piping per instructions in
Section 6.
DRAIN SYSTEM
XXXX 137 -
GENERATOR
XXXX - 151 -
SWITCHGEAR
XXXX 152 -
STEP-UP
TRANSFORMER
XXXX 153 -
REV-2
PAGE: 5-41
15 January 2002
Homepage
Previous Document
REV-2
PAGE: 5-42
15 January 2002
Homepage
Previous Document
REV-2
15 January 2002
PAGE: 5-43
REV-2
15 January 2002
PAGE: 5-44
PAGE: 6-1
Previous Document
3. Cable assemblies, junction boxes, and equipment shall be protected from the
weather and stored properly to prevent damage.
6.5 Prepping Before Final Placement
6.5.1 Engine Heat
Install control and power cables on engine heat unit junction box before placement on
roof of engine enclosure.
NOTE
The engine heat junction box that these cables plug to will
be located on the outside wall of the engine enclosure.
Power Pac Right Hand Side and Twin Pac, Unit A
Right Hand Side, Unit B Left Hand Side.
6.5.2 Cold Buffer Air
Check cold buffer skid for control box connected to motor. If supplied, remove and
notify PWPS site manager.
6.5.3 Generator Enclosure
To ease installation of conduit at the generator to cable tray, it will be acceptable to
eliminate conduits and replace with vertical pieces of tray.
NOTE
Use cable ties as required to secure cables.
6.5.4 Wire Markers
Wire labels must be installed on each terminated wire. A BRADY type marker system is
recommended. Wiring list will have the information for labels.
NOTE
Some labels include 1s and Is. Use care not to mix-up.
Proper identification of the wiring and cabling is a critical
task that must be accomplished by the installing electrician.
REV-2
15 January 2002
Homepage
PAGE: 6-2
Previous Document
PAGE: 6-3
Previous Document
5. All junction boxes, ancillary equipment, lube enclosure, engine enclosure, exhaust
enclosure, exhaust stack and generator enclosure require ground connections.
6. All ground grid connection shall be cad welded. Refer to TPM Specification 130
Grounding, General Requirements & Practices contained in Appendix A in this
manual.
6.8 Motor Wiring, AC and DC
Reference the National Electrical Code Article 430 and TPM Specification 132 Wiring,
General Requirements & Practices contained in Appendix A in this manual.
All 3 phase and DC motors shall use a split bolt type power connector. Size to be
determined at installation. Make electrical connection inside motor housing and tape
with approved rubber tape. It is essential that connections are tight and there are no
exposed conductive surfaces.
When connecting motors, it is required to establish the correct working voltage for proper
wiring.
6.8.1 Gas Generator DC Lube Motor
Make sure DC motor labels are well defined to insure proper
connection. Only 3 wires connect from the MCC to DC motor in the
GG Lube Oil enclosure. The supplied PWPS cable has numerals
printed on each conductor. NOTE: The motor is a 6 LEAD
COMPENSATED COMPOUND WOUND MOTOR and leads marked
J are not used (optional thermostat). Rotation is clockwise (CW) facing
the commutator end opposite of drive end (see fig 6.8.a). If the motor is
running backward reverse armature leads. DO NOT reverse all three
sets of leads. WARNING, Never start a DC motor without it being
connected to the pump and never run the motor with the pump dry.
CW
figure 6.8.a
NOTE
Generator lube oil motor turns CCW.
6.8.2 Generator Lube Oil DC Motor
Make sure DC motor labels are well defined to ensure proper connection. Only three (3)
wires connect from the motor control center (MCC) to the DC motor on the generator
lube oil skid. The supplied PWPS cable has numerals printed on each conductor.
REV-2
15 January 2002
Homepage
PAGE: 6-4
Previous Document
WARNING
Never start the DC motor without it being connected to the
pump and never run the motor with the pump dry.
NOTE
This motor is wired to a junction box on the rear side of
lube skid. Wire to terminal box per field wiring list. For
reference purposes, the compound wound motor uses a
different code system (BRITISH).
The only way to check rotation is to look for proper oil pressure.
WIRE
#1
F1
F1(E1)
13
F2(E2)
GP
15
GP
SHUNT
(MCC)
A1
WIRE
#3
14
A2(B1)
S1(D1)
L2
(MCC)
S2(D2)
GP
(MCC)
WIRE
#2
A1(A2)
SERIES
REV-2
15 January 2002
Homepage
RED
WHITE
BLACK
PHASE
ATS
A
RED
WHITE
BLACK
PAGE: 6-5
Previous Document
NOTE
Final power connections must keep the same phasing or
equipment could be damaged.
6.9.1 AUX Transformer
The AUX transformer located near switchgear must also be checked for proper phasing.
It also connects to above automatic transfer switch. The electrician must check the AUX
transformer tap settings to make sure they agree with required 3-phase voltage.
NOTE
AUX transformer feeds the automatic transfer switch Aux
power/Normal.
6.9.2 Battery Systems
Use caution not to short terminals to each other or to ground when installing battery cells.
CAUTION
The negative and positive of each battery must be isolated
from ground. For safety the electrician should use insulated
tools.
After installing batteries check each battery for proper electrolyte level. If the level is too
low, use only distilled water to fill the low cells. Record each battery cell voltage level
and specific gravity and temperature, before and after charging on Table 6-1 Battery
Report, and submit to PWPS site manager. Each battery should have a numeral assigned
to it.
Adjust battery chargers float, equalize, and current limit per PWPS Checkout Manual
and charger/battery manufacture instructions. Refer to Table 6-1.
6.9.3 Electro-Static Discharge (ESD)
Use wristband straps that are properly connected to earth before handling PC boards or
cards. The most common cause of electrostatic damage is the direct transfer of
electrostatic charge from the human body or a charged material to the electrostatic
discharge sensitive (ESDS) device. The Woodward Governor NetCon or MicroNet cards
are ESD sensitive. Never touch the pin of the connector unless ESD protected.
Motor overloads, breaker settings, electrical checks, and rotation to be performed by field
personnel. Refer to NEC Article 430.
REV-2
15 January 2002
Homepage
PAGE: 6-6
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 6-7
Previous Document
Sp.Gr.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
REV-2
15 January 2002
Homepage
VOLTS
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
VOLTS
24 DCV BANK
BATTERY P/N _________
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
PAGE: 6-8
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-1
Previous Document
7.1.3 Flushing
All field installed piping shall be flushed with the type of fluid used in the system to
assure that no dirt or other foreign materials have been introduced into the system. The
following guidelines describe methods to flush the system so that components not
requiring flushing are bypassed. Component identification (tag) numbers and field
connection numbers given are as referenced on their respective Piping and
Instrumentation Diagram (P&ID) drawings.
Flow diagrams, Figure 7-1 through 7-6, located at the end of this section, illustrate the
flushing paths recommended in the following procedures. These flow diagrams are
essentially overlays on the generic P&ID drawings for these sections. The P&ID drawing
numbers are referenced on the diagrams.
All P&ID symbols are diagrammed and defined in Table 7-1, located at the end of
Section 7.
7.1.3.1 Special Equipment Required for Flushing
1. Lube Oil Pump stainless steel body and impeller, 30-50 GPM flow, 50-75 psig
delivery pressure, 3-5 hp drive motor, 240/480 VAC
2. Lube Oil Heater 8-10 kW, 20 watts/square inch maximum, 195 to 210F range,
240/480 VAC
3. Lube Oil Pressure Gage 0-100 psig
4. Valves stainless steel, quantity and sizes as required
5. Screen 100 mesh, stainless steel
6. Flex hose 1, 1-1/2, and 2, as required
7. NPT to Swagelok and NPT to 37 degree AN fittings, as required
8. Lube Oil Filters 10 micron filters for F601 and F602, to remain in place
throughout flushing and initial startup
9. Liquid Fuel Filter 36 GPM, 5-50 psig
10. Other fittings, tees, caps, and plugs, as required
REV-2
15 January 2002
Homepage
PAGE: 7-2
Previous Document
Homepage
PAGE: 7-3
Previous Document
piping where the flushing hose was attached, and proceed with the final field
flushing.
7.1.4.2 Final Field flushing (Refer to Figure 7-2)
1. Connect the flushing hose at F3 before the fire valve FV1001, and route it
back through a filter to the storage tank or an empty tank truck. Cap the open
fitting to the fire valve at F3.
2. Install the main fuel filter elements removed in A.1 above.
3. Remove the filter element from the final filter F-1001.
4. Resume the flushing operation as described in steps A.5 through A.7, except
including the piping up to F3. Check the differential pressure gage reading on
the main filter periodically to determine the effectiveness of the initial flush.
5. When the samples indicate clean fuel, terminate the flush, install the final
filter elements, install the hose between the final filter and the engine, and
install the flow meter, if applicable. Install any orifices that have been
removed, and bleed air from the system by opening the appropriate valves,
such as those on top of the final filter and heating tank and the fuel pump
pressure sense line.
6. Remove the Y strainer between the forwarding skid and the storage tank.
Check for cleanliness, clean and replace, taking care not to introduce any
contaminates into the openings.
7.1.5 Flushing the Gas Turbine Lube Oil System (Refer to Figure 7-3)
The lube oil skid supplies filtered, cooled, de-aerated oil to both the gas generator and
power turbine. Lube oil system components are skid mounted and located outside of the
engine enclosure. Prior to shipment, this unit has been flushed and sealed per PWPS
specifications.
Flushing is to begin after installation of all the tubing and hose assemblies. (Inspection of
the system is required at this time.) Figure 7-3 shows the flushing paths used in the
following procedure.
The procedure for field flushing the FT8 lube oil system is detailed in TPM Specification
141.
REV-2
15 January 2002
Homepage
PAGE: 7-4
Previous Document
Homepage
PAGE: 7-5
Previous Document
installed piping for a particular installation; no additional cleaning and flushing should be
required for the hydraulic system. However, if no additional flushing is used, it is
particularly important to keep the interference of these three flex hoses clean during
handling and assembly.
7.1.8
The hydraulic start system consists of a factory-assembled skid with electric motor driven
pump(s), interconnection piping and tubing and an engine mounted hydraulic starter
motor.
CAUTION
The hydraulic system will be pressure tested to 1.5 times normal
pressure before initial operation. Because of this increased
pressure test requirement, the use of proper tooling is critical when
fabricating and installing the piping and tubing for the hydraulic
start system.
Use of the appropriate tooling will prevent
unnecessary leaks and damage to the equipment and eliminate the
added costs of having to replace equipment damaged through the
use of improper tooling.
When fabricating and installing hydraulic start system piping using
Swagelok fittings, the appropriate commercial Swagelok tools and
installation procedures shall be used to install all Swagelok fittings.
When fabricating and installing hydraulic start system piping using
Parker Instrumentation fittings, the Parker ICD Ferrule Presetting
Tool Kit and the tool kit assembly procedures shall be used to
install all Parker fittings.
The piping and tubing between the skid and the engine(s) is field fabricated and
assembled. The return and drain lines are fabricated from stainless steel tubing and must
be field flushed prior to operation. The high-pressure (5000 PSI) supply piping is double
strength stainless steel and is field welded. It must be cleaned and flushed prior to
operation.
7.1.8.1 Parker Instrumentation Fittings Remake Instructions. The instructions
contained in the next paragraph have been extracted from the Parker ICD Ferrule
Presetting Tool Kit Assembly Instructions, Bulletin 4290-B1, revised May 1997.
A disassembled joint can be remade simply by retightening the nut to the position of the
original make-up. For maximum number of remakes, mark the fitting and nut before
REV-2
15 January 2002
Homepage
PAGE: 7-6
Previous Document
disassembly. Before retightening, make sure the assembly has been inserted into the
fitting until the ferrule(s) seats in the fitting. Retighten the nut by hand. Rotate the nut
with a wrench to the original position as indicated by the previous marks lining up. (A
noticeable increase in mechanical resistance will be felt indicating the ferrule is being resprung into sealing position.) Then snug the nut 1/12 turn (1/2 hex flat) as shown from A
to B, past the original position.
REV-2
15 January 2002
Homepage
PAGE: 7-7
Previous Document
7.2.2 Blowdown
Prior to putting any of the systems in service, all piping must be purged with inert gas or
air to clean any moisture or loose material from the line.
Flow diagrams Figure 7-7 through 7-10 below illustrate the blowdown paths
recommended in the following procedures. These flow diagrams are essentially overlays
on the generic P&ID drawings for these sections. The P&ID drawing numbers are
referenced on the diagrams.
All P&ID symbols are diagrammed and defined in Table 7-1, located at the end of this
section.
CAUTION
During the blowdown procedure the exhaust gases must be
directed toward a safe area, and the hose or pipe positively
secured to prevent the end from whipping.
7.2.3 Gaseous Fuel Supply System (Refer to Figure 7-7)
7.2.3.1 Hydrostatic Test
1. Pressure test the lines before connecting the flange to the engine base fuel plate
input at G2, or disconnect this flange before performing the test to isolate the gas
generator. Cap the gas inlet flange at G2 to keep out the contamination, and seal
the terminations as necessary to conduct this test. Isolate other system
components as directed by PWPS personnel.
2. Hold the test pressure as required in the specification without depletion of
pressure.
3. Proceed with the blowdown procedure before reconnecting flange G2.
7.2.3.2 Blowdown
1. Blow the lines down to remove moisture and loose material following the
hydrostatic test. The blowdown path is show in Figure 7-7.
2. Control the air in short bursts until there is no evidence of foreign material in the
purge air.
REV-2
15 January 2002
Homepage
PAGE: 7-8
Previous Document
3. Reconnect the fuel inlet line at G2, taking care to avoid introducing contamination
into the openings.
7.2.4 Air Start Pac (Refer to Figure 7-8)
7.2.4.1 Hydrostatic Test
1. Pressure test the lines before connecting the 3 inch flex hose to the engine
starter at AS5, or disconnect this flex hose before performing the test. Plug the
starter inlet to keep out contamination, and seal terminations as necessary to
conduct this test. Isolate other system components as directed by PWPS
personnel.
2. Hold the test pressure as required in the specification without depletion of
pressure.
3. Proceed with the blowdown procedure before reconnecting the 3 inch flex hose
at AS5.
7.2.4.2 Blowdown
1. Blow the lines down to remove moisture and loose material following the
hydrostatic test, as shown in Figure 7-8.
2. Control the air in short bursts until there is no evidence of foreign material in the
purge air.
3. Reconnect the air start inlet line at AS5, taking care to avoid introducing
contamination into the openings.
7.2.5 CO2 Fire Protection System (Refer to Figure 7-9)
7.2.5.1 Hydrostatic Test
1. Pressure test the lines from the CO2 cylinder before connecting them to the
nozzles and secondary air dampers, or disconnect these terminations before
performing the test. Cap the lines from the cylinders to keep out contamination,
and seal terminations as necessary to conduct this test. Isolate other system
components as directed by PWPS personnel.
2. Hold the test pressure as required in the specification without depletion of
pressure.
REV-2
15 January 2002
Homepage
PAGE: 7-9
Previous Document
3. Proceed with the blowdown procedure before reconnecting the CO2 lines.
7.2.5.2 Blowdown
1. Blow the lines down to remove moisture and loose material following the
hydrostatic test, as shown in Figure 7-9. Each exit should be blown down
sequentially, starting with the closest exit (nozzle X-201) and progressing to the
most remote exit (secondary air damper pneumatic release R-202).
2. Control the air in short bursts until there is no evidence of foreign material in the
purge air.
3. Reconnect the CO2 lines, taking care to avoid introducing contamination into the
openings.
7.2.6 Halon Fire Protection System (Refer to Figure 7-10)
7.2.6.1 Hydrostatic Test
1. Pressure test the lines from the Halon cylinders as given above for the CO2
system, except two sets of lines must be tested, as shown in Figure 7-10.
7.2.6.2 Blowdown
1. Blow the lines down as given above for the CO2 system. For each of the two sets
of lines, each exit should be blown down sequentially, also, starting with the
closest exit and progressing to the most remote exit.
2. Reconnect the Halon lines, taking care to avoid introducing contamination into the
openings.
7.2.7 Cold Air Buffer System
7.2.7.1 Hydrostatic Test
1. Pressure test the three lines before connecting the flanges to the engine base input
at HX1, HX3 and HX4. Cap the flanges at HX9, HX10, HX11 and HX12 to keep
out the contamination, and seal the terminations as necessary to conduct this test.
Isolate other system components as directed by PWPS personnel.
2. Hold the test pressure as required in the specification without depletion of
pressure.
REV-2
15 January 2002
Homepage
PAGE: 7-10
Previous Document
3. Proceed with the blowdown procedure before connecting flanges HX1, HX3 and
HX4.
7.2.7.2 Blowdown
1. Blow the lines down to remove moisture and loose material following the
hydrostatic test.
2. Control the air in short bursts until there is no evidence of foreign material in the
purge air. Approximately 100 psi air or nitrogen will be required along with a
quick opening ball valve at the discharge end. The air supply line needs to be
firmly attached at on end and soft metal target needs to be placed at the discharge
end of the ball valve.
3. Continue the air blows in short, full-flow bursts until three consecutive shots
yields no visible marks on the target. The final three successful shots must be
witnessed and accepted by the PWPS site representative
4. Reconnect the ends of the three cold air buffer lines, taking care to avoid
introducing contamination into the openings.
5. Install the two nominal size orifice plates as shown on the XXXX-138-M400D
drawing.
REV-2
15 January 2002
Homepage
PAGE: 7-11
Previous Document
AIR COOLER
ACCUMULATOR
AIR STARTER
BALL VALVE
BREATHER VALVE
BUTTERFLY VALVE
COMPRESSOR
CHECK VALVE
DEAERATOR
DUMP VALVE
EXPANSION JOINT
FILTER
FLOW CONTROL VALVE
FLOW ELEMENT
FLOW ORIFICE
FEMALE PIPE THREAD
FLUID STOP VALVE
FIRE VALVE
GATE VALVE
GEAR BOX PUMP
HEATER
HAND SWITCH
HEAT EXCHANGER
LEVEL ALARM HIGH
LEVEL ALARM HIGH HIGH
LEVEL ELEMENT
LEVEL GAGE
LEVEL SWITCH HIGH
LEVEL SWITCH HIGH HIGH
LEVEL SWITCH LOW
LEVEL SWITCH LOW-LOW
LEVEL TRANSDUCER
MAIN OIL PUMP
MAIN OPERATED VALVE
MALL PIPE THREAD
OIL MIST ELIMINATOR
PUMP
PRESSURE ALARM LOW
PRESSURE ALARM LOW-LOW
PRESSURE CONTROL VALVE
PRESSURE DIFFERENTIAL INDICATOR
PRESSURE DIFFERENTIAL ALARM HIGH
PRESSURE DIFFERENTIAL CONTROL VALVE
PRESSURE INDICATOR
PRESSURE REGULATING VALVE
PRESSURE SWITCH HIGH
PRESSURE SWITCH HIGH-HIGH
REV-2
15 January 2002
Homepage
PSL
PSLL
PSV
PT
RCV
RO
SAL
SAH
SI
SOP
SOV
SP
ST
SV
TAH
TAHH
TAL
TCV
TK
TE
TI
TRV
TS
VAH
VAHH
VI
VP
VT
XA
X
XS
ZA
ZS
ZT
PAGE: 7-12
Previous Document
VACUUM BREAKER
BUTTERFLY VALVE
ELECTRO HYDRAULIC
METERING VALVE
REGULATING VALVE
NOTE
The NORMALLY OPEN (unshaded symbol) designation
means that the valve is open in normal system operation, and
does not indicate the de-energized condition of a solenoid valve.
The abbreviation FO and FC are added to the valve symbol
to indicate FAIL OPEN or FAIL CLOSED. As a rule, the
valve will fail to the de-energized state. Therefore, for instance,
a shaded solenoid valve symbol with FO will be normally
closed in system operation and energized to closethat is, the
solenoid will hold the valve closed in normal system operation.
REV-2
15 January 2002
Homepage
PAGE: 7-13
Previous Document
CONTRACTOR
SUPPLY
PWPS
SUPPLY
RESTRICTING
ORIFACE
BATTERY
LIMIT
HEATER
FILTER
DRIP LEG
NOZZLE
OIL MIST
ELIMINATOR
COMPONENT
(AS SPECIFIED)
SEPARATOR
SCREEN
FILTER Y-TYPE
AIR STARTER
ACCUMULATOR
MOTOR
REV-2
15 January 2002
Homepage
BREATHER
VALVE
PAGE: 7-14
Previous Document
PROCESS LINE
PNEUMATIC LINE
ELECTRIC LINE
FLOW ELEMENT VENTURI TYPE
HYDRAULIC LINE
MISCELLANEOUS SYMBOLS
REDUCER
INSTRUMENT BLOCK AND BLEED VALVE
FLEXHOSE
EXPANSION JOINT
PLUG
PUMP SYMBOLS
TRAP
RESET
CENTRIFUGAL
POSITIVE
DISPLACEMENT
CONNECTION POINT
VACUUM
PUMP
REV-2
15 January 2002
Homepage
PAGE: 7-15
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-16
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-17
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-18
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-19
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-20
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-21
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-22
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-23
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-24
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 7-25
Previous Document
8.0
8.1 Introduction
The installation sequence for the FT8 Power Pac and the FT8 Twin Pac starts with
installing the power island, the main foundation equipment in parallel with the control
house and ancillary skids. The power island is then interconnected to the control house
and ancillary skids with the installation of the major field assemblies like the field
electrical, piping and mechanical assemblies.
The power island sequence starts with first placing, leveling and grouting the electric
generator. The electric generator enclosure is built around the electric generator followed
by the exhaust enclosure system. Then the gas turbine and its enclosure system are
installed followed by the installation of the inlet air silencers and inlet filter house. For
the FT8 Twin Pac, two of each of these assemblies are installed for a single electric
generator. The gas turbine(s) is then aligned to the grouted electric generator some time
after the installation of the gas turbine enclosure.
The control house, the start pac(s), the lube oil skid(s) and the other ancillary skid(s) are
placed on their respective foundations some time during the installation of the power
island equipment. Generally the control house is set in place after the installation of its
cable tray system. The first placement of the control house is only temporary. After the
installation of the electric generator and its enclosure, the high voltage bus duct is
erected from the electric generator to the control house. To make the final bus duct
connection, the control house is typically moved to line up with the bus duct.
8.2 Installation Sequence (Abbreviated)
Foundations
Completed
FT8 Equip
Received
Inventory
FT8 Equip.
Install
Exhaust Sys.
Install Elec.
Generator
Install Elec.
Gen. Enclosure
Install
Cable Tray
Set Gas
Turbine
Install GT
Enclosure
Align Gas
Turbine
*
Startup
Commissioning
Checkout
REV-2
15 January 2002
Homepage
*
*
* Requires two of these items
for a FT8 Twin Pac
PAGE: 8-1
Previous Document
8.3 Procedures
The following procedures apply to the abbreviated sequence shown above in section 8.2.
These procedures are in a simplified checklist format.
8.3.1 Foundations
1. Prior to installing any FT8 equipment, foundation installations must be completed
(by others), cured and ready for equipment placement.
2. Clean foundation surfaces for equipment placement.
3. Check size, depth and quality of gas turbine and electric generator chip back
areas.
4. Check the 4-inch square datum pad locations and elevations and scribe
centerlines.
5. Check anchor bolts location and elevation.
6. Check jacking pad location and elevation.
7. Remove all water from all anchor bolt sleeves.
8. Grease entire length of all anchor bolts.
9. Seal all anchor bolts sleeves and/or back fill sleeves with dry sand.
8.3.2 Receiving FT8 Equipment
1. Inspect all equipment for shipping damage.
2. Inventory equipment against all shipping documents.
3. Report any damages in writing to PWPS.
4. Mark, sign and fax a copy of the packing list (shipping authorization) to PWPS
project management.
5. Maintain copies on site of all shipping documents.
6. Properly locate and/or store equipment on site.
7. Weather protect all equipment as necessary.
REV-2
15 January 2002
Homepage
PAGE: 8-2
Previous Document
8. Energize electric generator(s) three phase space heaters when generator arrives
(prior to placement if there are any delays).
8.3.3 Inventorying FT8 Equipment
1. Inventory in detail all FT8 equipment, parts and tools received on site.
2. Cross check received equipment with released project bill of material noting all
shortages with respect to bill of material.
3. Mark each inventoried item with the appropriate drawing number and item
number (quantities and part number are to be previously provided by PWPS and
its vendors).
4. Recheck all material for shipping or storage damage.
5. Where possible store or kiddy equipment by assemblies and/or by field
assemblies.
8.3.4 Electric Generator
1. Complete Foundations checklist items paragraph 8.3.1 above.
2. Remove packaging and check for shipping and/or storage damage.
3. Assemble, clean and set electric generator sole plate assemblies on foundation
over anchor bolts with equal quantities of shims as per PWPS field drawings; bolt
to electric generator when placing generator.
4. Mark foundation with centerline from one end of unit to the other.
5. Place electric generator on foundation by skidding or crane. Connect temporary
power to generator heaters. Refer to Brush drawing. A03176257 Terminal box
#2. Refer to Section 3 of Brush manual for complete information.
6. Remove transportation bump meter(s) and return to PWPS.
7. Reconnect three phase power to space heaters.
8. Remove rotor-blocking fixture.
9. Align to centerlines, level and grout per PWPS field drawings. Verify that rotor is
on design pin gage dimension. If rotor is not on pin gage adjust the axial position
from 'A' datum station 218.5 by the required amount.
REV-2
15 January 2002
Homepage
PAGE: 8-3
Previous Document
10. There are two methods of placing generator: Sole plates mounted to the generator
plates, or, sole plates grouted to foundation prior to setting generator.
11. Tighten the generator anchor nuts on sole after grout has cured.
12. Install electric generator neutral cubicle onto the left side of the generator (with
your back to exciter end) (DO NOT MAKE HIGH VOLTAGE CONNECTION
UNTIL AFTER PI TESTING). See Brush drawing 9625696.
13. Install cable tray along generator wall on lube module side of generator prior to
placing module. Refer to PWPS drawing XXXX-123-E110D Sheet 2.
14. Install electric generator lube oil skid onto right side of generator (with your back
to exciter end). See Brush foundation drawing 3175823 for location on base. Do
not anchor at this time. Wait until piping is installed. Install required field
electrical assemblies.
15. When ready for the electric generator enclosure system, remove top mounted steel
plate and install generator exhaust damper assembly, two inlet grills, and install
transition duct provided with electric generator enclosure assembly.
16. Install electric generator enclosure system.
17. PI (polarity index) test electric generator stator windings. When successful make
neutral cubicle connections and start high voltage bus duct installation.
18. Start checkout, tank inspection, oil fill (Mobil DTE Lite, CT116676), flushing,
etc.
8.3.5 Electric Generator Enclosure System
1. Install per PWPS generator enclosure drawing (e.g. Power Pac: STND-112S300D-02, Twin Pac: STND-112-S300D-01).
2. Unpack and check for shipping and/or storage damage.
3. Before placing walls, mount sidewall inlet louvers (Power Pac); mount sidewall
silencer panels (Twin Pac).
4. Lift right side wall first and install gasket at bottom with contact cement (punch
holes in gasket).
5. Set right sidewall at dimension shown on drawing noted above.
REV-2
15 January 2002
Homepage
PAGE: 8-4
Previous Document
6. Install closure panel (open wall section at generator coupling end) with gaskets
and adhesive; install one for power pac and two for twin pac.
7. Install left wall section with gaskets.
8. Install enclosure end wall (Power Pac only).
9. Install roof panels with gaskets and adhesive.
10. Install the exhaust silencer (REMOVE ALL DRAIN PLUGS).
11. Install generator lube oil vent line to bottom of exhaust silencer.
12. Install field electrical assembly (e.g. XXXX-123-E110D).
13. Install fire system piping (if option purchased by customer).
8.3.6 Exhaust System
1. Assemble diffuser assembly. Degrease as necessary.
2. Un-crate, degrease and insulate collector box.
3. Place and block collector box in its proper position on foundation.
4. Lift and temporarily set diffuser assembly inside collector box.
5. Lift exhaust enclosure. Check that the enclosure is centered over the shaft center
line and install gaskets and set in place over collector box assembly (clearance left
and right is +/- 1inch (25 mm)).
6. Install high temperature gaskets and set exhaust transition duct on top of exhaust
enclosure.
7. Install next set of high temperature gaskets and set first exhaust duct on top of
transition duct; repeat above for remaining exhaust duct(s).
8. Install generator enclosure bulkhead/fire wall (one for Power Pac and two for
Twin Pac).
9. Repeat above procedures for second exhaust system (Twin Pac only).
REV-2
15 January 2002
Homepage
PAGE: 8-5
Previous Document
PAGE: 8-6
Previous Document
correct diffuser location is to have a smaller bolt head located equal distance
between two larger tie rod bolts. This allows for correct position of N3 cable
channel and position of alignment tooling rear support bracket.
14. Install horizontal thrust rods and use special thrust washers.
15. Install shaft support tooling in diffuser tunnel and place shaft on rails and align to
the coupling piece installed in above step above.
16. Install shaft per Lucas print and PWPS drawing. Torque per instructions on
drawing.
17. Remove the front drive shaft support cradle. (now ready for alignment)
18. Repeat above procedures for second gas turbine (Twin Pac only).
8.3.8 Gas Turbine Enclosure System
1. Unpack and check for shipping and/or storage damage.
2. On the GT enclosure, remove rubber seals on inlet plenum opening so they do not
interfere with GT bell mouth when setting enclosure.
3. Set GT enclosure using gasket between enclosure and concrete. Align front of
enclosure so that centerline of enclosure is on centerline of GT base.
4. Install electrical junction box A and other external electrical hardware.
5. Install gas turbine enclosure trolley.
penetration for overhead lifting.
NOTE
If trolley was installed by the manufacturer prior to delivery, insure
the alignment tabs are in place.
If trolley is to be installed at the site, mount the trolley on the
tracks within the enclosure and weld on the alignment tabs to
prevent the trolley from falling from the tracks. Refer to PWPS
drawings IPE 21778 and XXXX-112-S000D.
6. Install roof top engine heat unit.
REV-2
15 January 2002
Homepage
PAGE: 8-7
Previous Document
7. Attach gaskets to gas turbine enclosure and mount secondary air fire damper
assembly followed by secondary air inlet louver.
8. Install CO2 bottle and fire system.
9. Install external field electrical, mechanical, piping, cold air buffer systems, etc.
10. After gas turbine alignment & grouting, install nose cone and balance of field
electrical, mechanical, piping and cold air buffer systems.
11. Repeat above procedures for second GT enclosure (Twin Pac only).
8.3.9
1. Tools required:
NOTE
All measuring equipment needs to be accurate to within .001-inch.
A. Two (2) precision levels --Two 6-inch levels or one 6-inch level and one 12 inch level.
B. One (1) bar - machined true over entire length to .001 inch. Dimensions - 24
inches long, 1/2 inch X 1.5 inch to 1 X 2 inch.
C. One (1) dial indicator - 1 inch travel.
D. Three (3) dial indicators 0.25-inch travel, with magnetic base.
E. One (1) set inside micrometers capable of measuring 1.5-inch to 3.0 inches or
Parallel bars and micrometer.
F. Specialized shaft support tooling:
TC350-115
TC350-116
Cradle
Rail
2 each
1 each
or
PWA 77582
Cradle Support
1 each
TC350-117
Compressor
5 each
REV-2
15 January 2002
Homepage
PAGE: 8-8
Previous Document
2.
3. Install generator adapter flange, torque bolts, measure and record electrical
resistance down to Mega ohms.
4. Install output shaft with special PWPS alignment tooling (i.e. (2) TC350-115
cradles and (1) TC350-116 rail).
5. Torque all coupling bolts per TPM-124 specification.
6. Remove front cradle and install customers dial indicators.
7. Rotate shaft and zero output shaft to power turbine shaft. Zero shaft run out so
shaft centerline is in line with that of GT centerline. To do this place magnetic
base of indicator on shaft and locate stylus of dial indicator on coupling rear face
between two bolts on the OD mounting flange. Adjust rear PT shaft support to
have indicator read <. 001 FIR. Leave indicator installed and check occasionally
that is hasnt changed.
NOTE
Rotate the output shaft in only one direction; NEVER
ROTATE IN THE OPPOSITE DIRECTION WHILE
TAKING READINGS!
8. Verify that the GT two cross members are level. Check at the support legs
using machinist levels. Flat service located directly under PT is one and
the other is under GG just forward of gearbox. Maintain level orientation
while readings are being taken.
9. Install a second set of dial indicators at electric generator side of output
shaft.
10. Move gas turbine base assembly with jack screws as follows to satisfy
requirements on XXXX-113-S000D drawing:
A. Jack pads should have been grouted into place at top of concrete elevation. If
that has been done then screw-jack bolts through base until they protrude 1.5
inch. This should set GT vertical center line to that of generator but slightly
high. (It is easier to lower base than to raise on jackscrews.)
REV-2
15 January 2002
Homepage
PAGE: 8-9
Previous Document
B. Use the jack bolts at 4 locations (3 bolts at each location) to obtain the design
specifications for the ambient temperature. Keep all jack bolts snug when
making move.
C. For instance if required to go .050 aft loosen the bolts used to push forward.
Move the turbine aft with proper bolts and then snug the first bolts that were
loosened.
11. Determine generator rotor axial position. Normally a generator from the factory is
at design pin gage but this should be verified. If different than design position a
correction value equal to the amount of offset must be determined. Determine
ambient temperature. Correction values for temp and rotor offset must be applied
to the GT gap design value to give the required coupling gap. It is not necessary
to jack rotor into design pin gage position.
12. Mark Generator output coupling (install if not already installed) at 12, 3, 6, & 9
using carpenter level.
CAUTION
Never use a lead pencil anywhere on the GT.
13. Attach 24-inch parallel bar (true to .001 inch) on end of GT output shaft.
14. Take a set of readings and begin making the required moves at jack points to
obtain the corrected gap, design slope, and rotor centerline offset (peripheral).
NOTE
All clock positions are taken facing the PT toward the front
of the engine. It is easy to confuse the 3 and 9 readings so
assure that the reading orientation is correct before making
corrective moves.
15. Take face of bar reading to generator adapter piece at the 12,3,6,9 position at the
OD of generator coupling hub. Rotate PT to do this. Add width of parallel bar to
readings. Average of 3 and 9 readings should equal average of 12 and 6 readings.
The average of the four readings is the gap. The difference between 12 and 6 is
the slope.
NOTE
Constantly check that the shaft run out to the GT is less than
.001 inch
REV-2
15 January 2002
Homepage
PAGE: 8-10
Previous Document
16. Attach the base of a dial indicator to the attached parallel bar. Place the stylus of
indicator on the OD flange of generator adapter. Set indicator to zero at the 12
position. Rotate the GT shaft until stylus is at the 3 o'clock position. Record
reading. Rotate to 6 and record reading, Rotate to 9 and record. Rotate to 12 and
reading should return to zero. If indicator reading does not return to zero at the 12
position, repeat the above process. The sum of the 3 and 9 readings should equal
the 6 reading.
17. As you get closer to the alignment (maintaining level on GT cross members) you
can use the dial indicators at the front and rear cross members of the GT base to
verify effect at coupling. As you get closer make half the calculated move and
verify that the calculation was correct.
18. Repeat above procedures for second gas turbine (Twin Pac only).
8.3.9.1 A Typical Example
Design slope is .016
Design gap is 2.958 at 59 degrees F
Temperature is 80 degrees F. This means gap is reduced.
Rotor pin gage design is 125mm
Rotor is actually 2 mm away from design and is towards B (.078 inch)
This means gap is increased for A end and reduced for B end
Doing the A side of a TP, calculate required coupling gap
Design gap - (.0009 X 21) + Gen rotor offset
2.958 - .019 + .078 = 3.017 inch
8.3.9.2 Additional Information and Recommendations
1. Always rotate the PT shaft in the same direction
2. The PT thrust bearing has .050 inch of axial travel. Axial position should be
addressed after the GT is sloped in the proper direction (Back -PT is lower than
front - GG)
3. Do alignment when the temperature is fairly steady to get stable readings
REV-2
15 January 2002
Homepage
PAGE: 8-11
Previous Document
4. PWPS computerized alignment program can be used and the moves will be close
to what are required.
5. Pre-grout accuracy is essential to preclude the necessity of realignment and
shimming the GG and PT after grouting.
6. It is easy to reverse the 3 and 9 positions so it is best to find a convenient place
and note the 3 and 9 position prior to starting (Never use lead pencil)
7. After the final move check that shaft is still zeroed and that base cross members
are level
8. After final alignment install anchor nuts and snug to prevent movement when
grouting. This may move the GT base when tightening. Verify unit is still
aligned just before grouting.
8.3.9.2.1 Peripheral
1. The ratio between front jack bolts and effect at coupling is about 1 to 1.
2. The ratio between rear jack bolts and effect at coupling is about 2 to 1
8.3.9.2.2 Design Slope
1. 10 to 1 ratio for changing slope at front jack point
2. 5 to 1 at the rear mount
An example:
Slope is .014 and 0.16 is required. All other readings are within specification.
Raise front jack .020 and raise rear jack .010 Raise each in 50 percent
increments.
8.3.9.2.3 Temperature Correction
1. Design gap is at 59 degrees F.
REV-2
15 January 2002
Homepage
PAGE: 8-12
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 8-13
Previous Document
5. Using hydraulic jacks, scissors jacks, chain falls, etc., move the collector box to
its proper position. A tape measure or go/no-go gages should be used to verify
position. If the go/no-go gages are used, two sizes will be required to
accommodate the front and rear of the collector box.
NOTE
After each move, check for inadvertent counter-moves that
may be caused by thermal distortion of the collector box or
blueprint tolerances. The collector box may not stay
positioned after adjustments.
A. Equalize the side-to-side (3:00 and 9:00) measurements on both front and rear
of the collector box.
B. Align the vertical position, both front and rear, so that the gap at 12:00 is
approximately 0.400 inch larger than the gap at 6:00.
C. Axially position the collector box so that the front side of the box (seal
mounting area) is no more that 0.125 to the rear of the diffuser front flange
(seal mounting area toward the engine).
1) In some cases, per the NOTE above, the best possible placement may be
to split the difference. Refer to the numbers recorded on the drawings in
the sign-off section for the as found position.
2) Record all final measurements in the as left blanks of the sign-off
section.
Include horizontal dimensions (3:00 and 9:00), vertical
dimensions (12:00 and 6:00) and axial dimensions (front and rear).
3) Tighten all the self-locking nuts on the four vertical support rods located at
the corners of the collector box, the nuts securing the two thrust rods on
either side of the collector box and the hardware (located on the front side
of the collector box) securing the bottom of the collector box to the
triangular support plate.
NOTE
The upper self-locking nuts should be snugged, not
tightened. This is to account for thermal expansion to
prevent the support rods from breaking.
D. Recheck all measurements for movement. Re-adjust as necessary.
REV-2
15 January 2002
Homepage
PAGE: 8-14
Previous Document
E. After all hardware has been secured, remove the hydraulic jacks, scissors
jacks, chain falls, etc.
F. Ensure that there is a minimum gap between the edge of the collector box
seals and the bottom of the mating groove per Table below.
NOTE
All seals must be checked.
FRONT SEALS
12:00
3:00
6:00
9:00
REAR SEALS
.55 - .75 inch
.40 - .60 inch
.25 - .45 inch
.40 - .60 inch
12:00
3:00
6:00
9:00
1) Proceed as follows:
a. Insert the seals, one at a time, in their proper locations and
bottom them out in the mounting groove.
b. With a suitable marker, trace edge of the mounting groove onto
the seal.
c. Move the seal out to its mounting position, secure with at least
two bolts, and trace the edge of the mounting groove again.
Remove the seal and note the distance between the lines.
d. If the distance is too small, remove the seal and grind off the
excess material. If the distance is too large, notify PWPS
engineering.
1) Install all front and rear collector box seals after
ensuring dimensional compliance. Installation must be
in the same location as removed.
2) Reconnect the bleed valve exhaust duct flex lines and
6th stage spent-air line(s) coming from the engine to
either side of the collector box, inside the engine
enclosure. Also, reconnect the No. 8 & 9 oil scavenge
and pressure sense lines at the rear side of the collector
box.
REV-2
15 January 2002
Homepage
PAGE: 8-15
Previous Document
PAGE: 8-16
Previous Document
1) In some cases, per the NOTE above, the best possible placement may be to
split the difference. Refer to the numbers recorded on the drawings in
the sign-off section for the as found position.
2) Record all final measurements in the as left blanks of the sign-off
section.
Include horizontal dimensions (3:00 and 9:00), vertical
dimensions (12:00 and 6:00) and axial dimensions (front and rear).
3) Tighten all the self-locking nuts on the four vertical support rods located at
the corners of the collector box. Also tighten the nuts securing the two
thrust rods on either side of the collector box and the hardware (located on
the front side of the collector box) securing the bottom of the collector box
to the triangle support plate.
REV-2
15 January 2002
Homepage
PAGE: 8-17
Previous Document
SEAL GAP
.12 + .12
AVERAGE ALL
AROUND
M + .40 + .10
X + .10
REV-2
15 January 2002
Homepage
PAGE: 8-18
Previous Document
EXHAUST
LOCATOR PLATE
HORIZINTAL RETRAINT
REV-2
15 January 2002
Homepage
PAGE: 8-19
Previous Document
ENCLOSURE WALL
EXHAUST
HORIZONTAL TIE-RODS
(2 FRONT 2 REAR)
LOCATOR PLATE
HORIZONTAL RESTRAINT
PAGE: 8-20
Previous Document
PAGE: 8-21
Previous Document
PAGE: 8-22
Previous Document
PAGE: 8-23
Previous Document
Confirm fuel(s) and water comply with the latest revision of PWPS Spec. (i.e.
FR-1, FR-2, AR-1 and AR-2).
PAGE: 8-24
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 8-25
Previous Document
1. Function Generator,
2. TC Meter
3. Infrared Thermometer
4. Multimeter
REV-2
15 January 2002
Homepage
Instek FG-8-1G
Fluke 51
Wahl DHS-26X, or
Raytek Raynger ST-4
Fluke 8060A
PAGE: 9-1
Previous Document
Tektronix THS720P
Tektronix A621
Multi-Volt PSI-700
Amprobe ACDC-620T
Transcat Checkmate 1000
Vaisala HM-34
TEGAM 8012 Type K
Transcat 23300P
Dynalco F-16
Davis Inst. Model G-03316-80
AEMC 5100
HP3560A
TrigTek 401B
Druck DP1610
Triplett- Fox, and
Triplett-Hound2
I.D.ProPlus
CAL-D438
Master Appliance HG301J
Ametek T-620
Ametek T-740
Dial Gauge
Dial Gauge
Omega COH-80
Hammer
Screwdrivers (flat, phillips, torx, and square heads)
Open/Box end 12pt wrenches, (5/16 to 1-3/4)
Adjustable wrenches, (4 to 24)
Socket Set, 12pt (5/16 to 1)
Pliers (various styles)
Lockwire Pliers
Flashlights
Special Equipment: (Not Inclusive)
Homepage
PAGE: 9-2
Previous Document
9.3 Checkout
Checkout is accomplished by following and completing the procedures listed in the FT8
Checkout Manual. A typical FT8 checkout manual will consist of 35 procedures or
sections. Procedures 1 through 25 will be for items needed to complete the checkout
phase.
The following is a list of these 22 procedures:
1. Air Conditioner
2. Battery Banks & Chargers
3. Purge/Blow down and Leak Check Piping
Clean and Inspect Reservoir or Tanks
Strainers and Filters
Gas Turbine Lube Oil System Flushing
Hydraulic Start system Flushing
Generator Lube System Flushing
Thrust Balance System Flushing
4. Fuel, Water, and Lube Oil Sampling
5. Systems Inspection
6. Inspection Gas Turbine and Auxiliary System Junction Boxes
7. Ground Grid Visual Inspection
8. Inlet Filter, Inlet Plenum, and Engine Inlet Inspection
9. MCC & Motor Rotation
10. NL and NH Rotation
11. Vibration Monitor
12. Manual Transfer Switch
13. Gas Turbine Engine Heat System
14. Initial Software Loading
15. Engine & Unit Control
A. Discrete Inputs--Pressure Switches
B. Discrete Inputs--Temperature Switches
C. Other Contact Closures
D. T5.0 Thermocouples Cr Al type K
E. RTDs 100 Ohm Analog Inputs
F. NL, NH, NP Speed Transducers
G. Pressure Transducers
H. Clutch, Igniters and SOVs
I. I/O Check, MCC
J. Liquid, Gas and Water Mod Valve Calibration
K. IGV & VSV Static Calibration
L. Generator RTD Calibration
16. Fire Protection System
17. Hydraulic Start System
REV-2
15 January 2002
Homepage
PAGE: 9-3
Previous Document
18.
19.
20.
21.
22.
23.
24.
Chip Detectors
Airpax Tach-Pak 3
Alignment Verification
Starter Speed Hydraulic
Lube Oil Systems Functional Test
Cold Air Buffer System
Thrust Balance
Once the above procedures are completed, the gas turbine can be safely rotated on its
starter and fuel should be made available for the startup phase of checkout.
9.4 Startup
After successful completion of the required checkout procedures fuel can be introduced
to the gas turbine and the startup activities can be completed.
Startup of the FT8 always begins with a series of incomplete start sequences. The
incomplete sequences are start attempts that are designed to result in failure to light off
while double checking the start and shut down logic of the control and safety systems.
Fuel will be introduced into the engine, however the igniters will be disabled.
The following is a list of the startup procedures found in a typical FT8 Checkout Manual:
25.
26.
27.
28.
29.
30.
It is important to note that no one should consider an operating FT8 power station to be
safe until the gas turbine overspeeds have been set and demonstrated to be operating
properly.
9.5 Commissioning
The actual commissioning of an FT8 power plant will be defined by the requirements set
forth in the contract documents. The following five procedures are set-aside in the
typical FT8 checkout to record the commissioning phase of checkout:
31.
32.
33.
34.
REV-2
15 January 2002
Homepage
PAGE: 9-4
Previous Document
REV-2
15 January 2002
Homepage
PAGE: 9-5
Previous Document
CONSTRUCTION MANUAL
APPENDIX A - SELECTED SPECIFICATIONS
(For Reference Purposes Only)
Appendix A contains copies of TPM/PWPS Specifications and Service Bulletins, which are
being provided for informational purposes only. The referenced specification and/or service
bulletin may not contain the latest technical information available from PWPS. Please contact
PWPS for copies of the latest revisions of these documents when installing, operating or
maintaining any FT8 equipment.
The following TPM/PWPS specifications are provided in this section:
TPM-AR-1
TPM-AR-2
FR-1
FR-2
TPM124
TPM126
TPM129
TPM130
TPM132
TPM139
REV-2
APPENDIX: A-1
15 January 2002
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
TPM-AR-1
SHEET
REV C
OF
1
3
ISSUED BY : R. Sklenar
DATE: 11-14-72
DATE: 7/23/01
REFERENCE :
REV:
Natural water comes from rivers, streams, lakes or wells. This water tends to be high in particulate matter and
chemical content. It is highly unlikely that natural water could be used in gas turbine engines on a continuous
basis without treatment. The ordinary levels of minerals and metals found in even good well water are sufficient
to cause deposit buildup and corrosion in the gas turbine hot section.
2.
Treated water includes facility prepared or municipal potable water, softened or demineralized boiler makeup
water and processed natural water. The quality level of treated water will depend on the amount and type of
treatment used. Analyses should be performed to determine whether the water is acceptable for continuous gas
turbine usage without further treatment.
3.
Condensate quality is achieved by properly vaporizing either natural or treated water. This vapor may then be
condensed, depending on whether steam or water injection is to be used. Water of this quality can be obtained
by using a gas turbine waste heat boiler or by extracting steam or condenser water from a steam power plant. In
either case, care must be exercised so that impurity carryover is held to acceptable levels. Condensate quality
water will ordinarily be acceptable for continuous gas turbine usage.
When the nature and quantity of the water impurities have been determined, a system design can be established. Undissolved
solids are normally removed with filters or separators. Ion exchange resins may be used for removal of many of the dissolved
solids. However, in some cases, it may be necessary to include chemical treatment of the water. The trade-offs between removal of impurities and chemical treatment to minimize adverse effects would have to be made for each installation. Chemicals may also be used to control other properties such as pH and to inhibit the formation of boiler scale. Individual assessment can be made by PWPS to judge the suitability of various chemical additives.
Handling and storage should also be considered as part of any water management system. Storage tanks, pumps,
vaporizors and plumbing should be such that they do not add significantly to water contamination.
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV C
TPM-AR-1
OF
2
3
ISSUED BY : R. Sklenar
DATE: 11-14-72
DATE: 7/23/01
REFERENCE :
REV:
Continuous Usage
The requirements below are for either 1) liquid treated water or 2)condensate of the steam delivered to the gas turbine
for continuous usage:
Limit
Test Method
(See Note 1 & 2)
1.00
ASTM D1888
Grab
Sodium (ppm)
0.10
ASTM D2791
In-Line
Silica (ppm)
0.02
ASTM D859
Grab
10 max.
ASTM F312
Grab
3. Conductivity (micromho/cm)
1.5 max
ASTM D5391
Grab
Property
1. Total Solids
1.0 max.
Test Location
(See Note 3)
In-Line
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
TPM-AR-1
SHEET
REV C
OF
3
3
ISSUED BY : R. Sklenar
DATE: 11-14-72
DATE: 7/23/01
REFERENCE :
REV:
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
TPM-AR-1
SHEET
REV C
OF
1A
1
ISSUED BY : R. Sklenar
DATE: 11-14-72
DATE: 7/23/01
REFERENCE :
REV:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
1, 2, 3
All
2,3
P. Lavendier
12/19/96
EC#8757
EC#9925
L. DiSalvo
J. Kennedy
7/23/01
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
TPM-AR-2
PWPS
SPECIFICATION
RELEASED
SHEET
REV A
OF
1
1
ISSUED BY : P. Olyarchik
DATE: 9/22/00
REVISE BY : J. Kennedy
DATE: 7/25/01
REFERENCE :
REV:
INORGANIC
Arsenic
Barium
Cadmium
Chlorides
Chromium
Copper
Cyanide
Fluoride
Iron
Lead
Magnesium
Maganese
Mercury
Nitrite Nitrogen
Nitrite plus Nitrite Nitrogen
Selenium
Silver
Sodium
Sulfate
Zinc
MILLIGRAMS/LITER
0.05
1
0.01
250
0.05
1.0
0.2
2.0
0.3
0.05
125
0.05
0.002
1.0 (as N)
10.0 (as N)
0.01
0.05
20
250
5.0
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
TPM-AR-2
SHEET
REV A
OF
1A
1
ISSUED BY : P. Olyarchik
DATE: 9/22/00
REVISE BY : J. Kennedy
DATE: 7/25/01
REFERENCE :
REV:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
1
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
2
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
3
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
Distillates of the No. 2 diesel fuel (ASTM D975) No. 2 fuel oil (ASTM
D 396), No. 2 GT gas turbine, and marine diesel (MIL-F-16884) types.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV C
FR-1
OF
4
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
Limit
NOTE(S)
Test Method
(Note 1)
ASTM D445
ASTM D445
ASTM D445
0.025 max.
10.0 max.(2.7)
20 max
ASTM D1744
ASTM D2276
ASTM D2002
Hydrogen - % by weight
12.4 min
ASTM D1018
0.2 max.
0.2 max.
2.0 max.
0.1 max.
0.02 max.
6&7
6&7
6&7
6&7
6&7
Copper corrosion
No.1 max.
ASTM D130
To be reported
12.5 max.
ASTM D93
ASTM D323
12.5 max.
10
1.3
11, 12
To be reported
Specific Gravity
To be reported
Homepage
ASTM D5191
0.005 max.
IP288, ASTM
D3605
ASTM D93
ASTM D2500
ASTM D524
ASTM D4294
ASTM 482
ASTM D1298
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
5
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
Homepage
Af
Lf
Cair
Cwater
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
6
6
ISSUED BY : P. Lavendier
DATE: 8/18/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
NOTE 8
Copper corrosion test conditions are 2 hours at 212 deg F (100 deg C).
NOTE 9
No flash point limitation is specified; however, local regulatory limits and safety regulations must be met.
NOTE 10
The cloud point shall be at least 25 degrees F below the anticipated gas turbine fuel inlet temperature. To meet
this requirement, additional fuel heating, to a maximum of 160 degrees F (71C), may be needed.
NOTE 11
Sulfur content limits Below 1.3% WT. are imposed when:
a) The local regulatory limits of sulfur oxides exhaust emissions are exceeded; then the fuel sulfur content
must be reduced until the local regulatory limits are satisfied. For instance, the USA EPA limits fuel
Sulphur content to 0.8% for S02 emissions control, but local codes vary widely.
b) If exhaust heat recovery equipment is employed; then the equipment manufacturer's limit may apply.
NOTE 12
High sulfer fuels will impact hot section repair interval dependent on the amount of alkalai metals present. The
combination of high sulfur and high alkalais must be avoided.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-1
SHEET
REV C
OF
1A
1
ISSUED BY : P. Lavendier
DATE: 8/28/95
REVISE BY : L. DiSalvo
DATE: 7/23/01
REFERENCE :
REV:
REV SHEETS
LET AFFECTED
1-4
All
Homepage
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
P. Lavendier
8/18/95
EC#8352
EC#9025
T. Fox/D. Dalal
2/11/98
EC#9925
L. DiSalvo
7/23/01
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-2
SHEET
REV D
OF
1
6
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-2
SHEET
REV D
OF
2
6
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
To protect the power plant equipment, a fuel testing program to periodically measure contaminant removal
from the fuel and perform maintenance on the fuel filtration system is recommended. This is an important step
in ensuring that the proper quality fuel is provided to the gas turbine.
PWPS/P&W fuel requirements of Table 1 are the allowable limits of fuel properties. The operators of the
PWPS/P&W equipment must comply with all aspects of this specification, and confirm compliance through
analysis of gas fuel samples taken regularly. Additional detailed guidance can be obtained through a PWPS/
P&W representative.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV D
FR-2
OF
3
6
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
COMBUSTOR TYPE
NOTE(S)
Test Method
(Note 1)
800-1200
(30 - 45)
ASTM D3588
1040-1350
(39 - 50)
1040-1350
(39 - 50)
2, 3
ASTM D3588
Note 4
1.0
ASTM D1945
Note 6
Note 6
ASTM D1946
30
30
5, 7, 10
ASTM D2009
10
10
ASTM D2009
300
(149)
300
(149)
32
(0)
32
(0)
+28
(+16)
+50
(+28)
Note 13
+28
(+16)
+50
(+28)
Note 8
Note 8
5, 10, 8
ASTM D1072
or
ASTM D3246
0.2
0.2
5, 10
ASTM D3605
Note 10
Note 10
5, 11
ASTM D1142
Not Applicable
2.2
12
Property
Conventional
DLN
800-1200
(30 - 45)
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-2
SHEET
REV D
OF
4
6
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
Where:
Tgc = inlet gas temperature, C
S.G = specific gravity relative to air
LHV in MJ/m3 (note 2)
NOTE 4
Hydrogen content up to 4% vol. may be used. Higher amounts of hydrogen content can be used but should
be approved by PWPS/P&W and must satisfy all applicable safety codes for the fuel system.
NOTE 5
At the inlet to the gas turbine fuel plate or at gas turbine enclosure interface, if the enclosure is provided
by PWPS.
NOTE 6
Fuel CO content will increase CO output, thus CO fuel content may require control to meet guarantee
exhaust emissions levels.
NOTE 7
Particulates are composed of any solids in the gas fuel stream, including sand, rust, clay, coke, tar, iron
sulfide, etc.
NOTE 8
Total sulfur includes hydrogen sulfide (H2S), mercaptans, carbon disulfide(CS2), carbonyl sulfide(COS),
thiopene, sulfur oxides, etc.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-2
SHEET
REV D
OF
5
6
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
NOTE 9
Limits on fuel sulfur are imposed when:
a) The local regulatory limits of sulfur oxides exhaust emissions are exceeded, then the fuel sulfur content
must be reduced until the local regulatory limits are satisfied.
b) When exhaust heat recovery equipment is employed, the equipment manufacturer's limits will apply.
NOTE 10
The allowable gas fuel contaminants shall be debited by the amounts of that contaminants entering with
the inlet airflow (type A&B combustor) and water injection flow (type A combustor):
Allowable fuel limit = Overall limit - (Air/Fuel x Inlet Air Level) -(Water/Fuel x Water Level)
NOTE 11
Gas Hydrates are not allowed, therefore water content should be below the concentration which would
allow gas hydrates to form at the operating temperature and pressure. Fuel heating is allowed to bring gas
fuel temperature above the moisture saturation (dew) point.
NOTE 12
Flammability limits at 1 atm (101.3 KPa) and 77 Deg. F (25 Deg. C).
NOTE 13
FOR DRY LOW NOx (DLN) COMBUSTORS ONLY:
Hydrocarbon dew points are to be evaluated from ambient pressure up to the maximum gas turbine
inlet pressure
Dew points will be based on extended analysis to C14 level according to method of GPA 2286-95.
Gas samples shall be taken per method of GPA 2166-86.
Concentrations should be determined to an accuracy of 10 PPM or less.
The maximum expected dew point line during the operating period, must be used to establish the
minimum required fuel temperature at the gas turbine inlet
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
FR-2
SHEET
REV D
OF
1A
1
ISSUED BY : P. Lavendier
DATE: 7/1/85
DATE: 7/23/01
REFERENCE :
REV:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
All
3&4
EC#8975
D. J. Dalal
10/28/97
All
EC#9012
D.J. Dalal/T. Fox
12/22/97
3
5
EC#9077
T. Fox
8/20/98
All
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
1
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
PURPOSE
This specification establishes acceptable torque values for various sizes and types of threaded members
assembled under specified conditions.
2.0
APPLICATION
Torque limits in this specification apply to threaded assemblies when this specification is referenced on
the drawing or in a document referenced on the drawing. Torque limits specifically shown on the drawing
or in a document referenced on the drawing shall take precedence over the torques listed in this specification.
2.1
Torquing procedure
It is preferred that the nut be turned rather than the bolt wherever possible. If the bolt is to be turned,
observe the following to assure proper tension can be achieved and that there will be no scoring of
bolt, hole or bearing surface.
3.0
(a)
The bolt (including close tolerance shank bolts) must pass freely through aligned holes.
(b)
Where the flange material is soft (e.g., Al, Mg) an Engineering specified washer must be
present under the bolt head.
(c)
3.1.2
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
2
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
4.0
3.2.2
FREE-SPINNING FASTENERS
For free-spinning nuts, bolts, and screws (including free-spinning self-locking nuts; see para. 5.2) use the
torque values listed in Table I.
4.1
General
Torque values for nuts, bolts, and screws have been established to provide sufficient preload without over-stressing the parts and are based on materials having minimum ultimate tensile strengths
of 125,000 PSI, equivalent to a hardness of 26HRC for steel parts.
4.2
4.3
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
3
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
SELF-LOCKING NUTS
For self-locking bolts or screws, bolts or screws used in self-locking inserts, or prevailing torque type selflocking nuts (see para. 5.1), except if used on a stud, use the torque values listed in Table II. For prevailing
torque self-locking nuts used on studs and free-spinning self-locking nuts (see para. 5.2) use values listed
in Table I.
5.1
5.2
6.0
7.0
8.0
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
4
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
9.2
37 Cone seat connectors with nickel gaskets (E.G., AS3074 and AS3075)
Use torque values in Table VII.
10.0
11.0
a.
b.
Tighten inner nut at each end of tube assembly to torque given in Table VIII while holding inner
nut at opposite end with wrench.
c.
d.
If inner nut maintains torque, proceed with step e. If inner nut does not maintain torque, repeat step
c. If inner nut does not maintain torque after repeating step c four times, replace tube assembly.
e.
Tighten outer nut at each end of tube assembly to torque given in Table VIII.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
5
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
13.0
13.1
13.2
13.3
13.4
13.5
13.6
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
6
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
STUDS
The torque limits given in para. 14.1 and 14.2 for driving studs are based on stud materials having a minimum ultimate tensile strength of 125,000 psi, equivalent to a minimum hardness of 26 HRC. For studs
having a minimum hardness of 34 HRC, the maximum torque values may be increased by 25%.
14.1
14.2
14.3
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
7
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
15.0
15.2
16.0
17.0
Standard Equipment
Approximately one and one half turns beyond normal hand engagement is considered sufficient to
effect a seal. Table XIX can be used as an approximate guide. In the case of elbows, if excessive
force is required for proper alignment, then the elbow should be replaced by another part with different thread orientation.
17.2
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
8
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
2)
3)
4)
Multiply the Nm value by the factor that appears to the left of the row from which the original ftlb torque came.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
9
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
.190-24
.190-32
.250-20
.250-28
30
36
70
85
23**
24**
50**
65**
27**
32**
65**
75**
21.5
26
50
60
16
19.5
37**
45**
19.5
23**
45**
54**
.3125-18
.3125-24
.375-16
.375-24
150
170
270
300
110**
125**
200**
225**
135**
150**
250**
275**
105
120
185
215
80**
90**
140**
160**
95
110**
170**
190**
.4375-14
.4375-20
.500-13
.500-20
425
475
650
750
325
350
500
550
375
425
600
675
300
340
450
515
225
255
340
390
270
310
400
460
.5625-12
.5625-18
.625-11
.625-18
950
1050
1300
1500
700
800
1000
1150
850
950
1200
1350
675
750
900
1025
500
550
675
775
600
675
800
925
.750-10
.750-16
.875-9
.875-14
2300
2600
3700
4200
1700
2000
2800
3200
2100
2400
3400
3800
1600
1800
2600
2900
1200
1350
1950
2200
1450
1600
2350
2600
1.000-8
1.000-12
1.125-7
1.125-8
5600
6400
7900
8400
4700
4800
5900
6300
5100
5800
7200
7600
3900
4300
5400
5700
2900
3200
4100
4300
3500
3850
4900
5100
1.250-7
1.250-8
1.375-6
1.375-8
11200
11700
14700
15900
8400
8800
11000
11900
10100
10600
13300
14400
7700
7900
10100
10600
5800
5900
7600
8000
6900
7100
9100
9500
1.500-6
1.500-8
1.750-5
1.750-8
19600
21100
30900
34500
14700
15800
23200
25900
17700
19000
27900
31100
13300
14000
21100
22700
10000
10500
15800
17000
12000
12600
19000
20400
2.000-4.5
2.000-8
46600
52600
35000
39500
42000
47400
31700
34400
23800
25800
28500
31000
* Use Type I minimum values only where alignment of locking holes for cotterpins or safety wire is required at assembly.
Use Type II minimum values where alignment of locking holes is not required at assembly.
**
For screws having screwdriver slots only (no external wrenching provisions) 22 lb in. minimum is permissible.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
10
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Thread
size
Thread
size
.112-40
.138-32
.164-32
.164-36
6-7
12-14
23-26
25-28
5-6
9-11
18-20
20-22
.750-10
.750-16
.875-9
.875-14
2200-2450
2500-2750
3600-4000
4000-4450
1600-1750
1750-1950
2500-2850
2800-3100
.190-24
.190-32
.250-20
.250-28
32-35
36-40
74*-82
85*-95
24-27
27-30
55*-62
62*-72
1.000-8
1.000-12
1.125-7
1.125-8
5400-6000
6000-6700
7600-8200
8000-8700
3800-4200
4000-4500
4300-5700
5500-6000
.3125-18
.3125-24
.375-16
.375-24
160*-175
180*-200
270*-300
290*-325
115*-130
125*-140
200*-220
225*-250
1.250-7
1.250-8
1.375-6
1.375-8
10500-11600
11000-12100
13800-15100
14900-16300
7300-8100
7500-8300
9600-10500
10000-11000
.4375-14
.4375-20
.500-13
.500-20
420-465
450-500
630-700
720-800
315-350
340-380
450-500
515-575
1.500-6
1.500-8
1.750-5
1.750-8
18200-20100
19500-21600
28500-31500
31700-35100
12500-13800
13100-14500
19600-21700
21000-23300
.5624-12
.5625-18
.625-11
.625-18
950-1050
1050-1150
1250-1400
1450-1600
675-750
750-825
900-1000
1030-1150
2.000-4.5
2.000-8
42800-47400
48200-53400
29300-32500
31800-35200
For screws having screwdriver slots only (no external wrench provisions), the minimum permissible torque is 22 lbin, plus the torque necessary to turn the screw thru the nut or self-locking helical coil insert.
TABLE III
Assembly Torques for pipe plugs, ANPT or NPT, oil lubricated* (See para. 6)
Homepage
Thread Size
Torque, lb-in
Thread Size
Torque, lb-in
.062
.125
.250
.375
30-40
30-40
70-85
95-110
.500
.750
1.000
1.250
140-160
210-230
285-315
355-385
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
11
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Thread Size
.250-28
.3125-24
.375-24
15-20
35-40
40-50
10-13
23-26
26-33
--40-45
80-90
--25-30
50-60
.4375-20
.500-20
.5625-18
65-75
90-100
110-120
42-49
58-65
70-80
100-115
120-135
150-170
65-75
80-90
95-110
.625-18
.750-16
.8125-16
150-170
200-225
225-250
95-110
130-145
145-160
--270-300
---
--175-195
---
.875-14
1.000-12
1.0625-12
250-275
275-300
375-425
160-175
175-190
240-270
505-555
--625-675
330-360
--405-440
1.1875-12
1.250-12
1.3125-12
450-550
500-600
525-625
285-350
315-380
330-395
835-915
--920-1000
545-595
--600-650
1.500-12
1.625-12
1.750-12
600-700
650-750
650-750
375-440
400-470
400-470
--1275-1425
---
--830-925
---
1.875-12
2.250-12
2.500-12
650-750
650-750
650-750
400-470
400-470
400-470
1425-1575
--1850-2050
925-1025
--1200-1330
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
12
22
DATE: 11/17/92
RELEASED
OF
DATE: 6/14/90
S. Leavitt
ISSUED BY:
SHEET
REFERENCE:
Thread
size
Thread
size
.125
.1875
.250
.4375-24
.500-20
.625-18
25-30
25-30
25-30
55-60
55-60
55-60
.3125
.375
.4375
.6875-16
.750-16
.8125-16
30-35
30-35
45-50
65-70
65-70
90-100
.500
.5625
.625
.875-14
1.000-12
1.0625-12
55-60
60-65
65-70
110-120
120-130
130-140
.750
.875
1.000
1.1875-12
1.375-12
1.500-12
70-80
75-85
100-110
140-160
150-170
200-220
1.125
1.250
1.500
1.625-12
1.750-12
2.125-12
100-110
100-110
100-110
200-220
200-220
200-220
Figure 1
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV B
TPM124
TPM
SPECIFICATION
ISSUED BY:
OF
13
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
Tubing
OD
Thread
size
Aluminum Fittings
Steel
All lubricants
Oil lubricated
Anti-gallant coated
-3
-4
-5
.1875
.250
.3125
.375-24
.4375-20
.500-20
30-50
40-65
60-80
70-80
90-100
135-150
50-60
65-75
100-110
-6
--8
--10
.375
.4375
.500
.5625
.625
.5625-18
.625-18
.750-16
.8125-16
.875-14
75-125
100-175
150-250
175-300
200-350
270-300
320-350
450-500
550-600
650-700
200-225
225-250
340-375
400-450
475-525
----
-.6875
--
.875-16
1.000-12
1.000-14
200-350
275-450
275-450
650-700
800-900
800-900
475-525
600-675
600-675
-12
---
.750
.875
--
1.0625-12
1.1875-12
1.250-12
300-500
400-600
400-650
900-1000
1100-1200
1150-1300
675-750
825-900
900-1000
-16
--20
1.000
1.125
1.250
1.3125-12
1.500-12
1.625-12
500-700
600-900
600-900
1300-1400
1500-1600
1700-1800
950-1050
1050-1200
1150-1300
-24
1.500
1.875-12
600-900
2100-2200
1500-1600
*If the nut or either of the mating sealing surfaces is aluminum, the required torque limits for aluminum fittings apply.
Figure 3
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
14
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Tubing
OD
Thread
size
Steel Fittings
Oil lubricated
Anti-gallant coated
-3
-4
-5
.1875
.250
.3125
.375-24
.4375-20
.500-20
50-60
90-100
135-150
40-45
65-75
100-110
-6
--8
.375
.4375
.500
.5625-18
.625-18
.750-16
200-220
250-270
350-400
150-165
185-200
270-300
--10
--
.5625
.625
.6875
.8125-16
.875-14
1.000-12
400-450
500-550
600-700
300-350
360-400
480-530
-12
--16
.750
.875
1.000
1.0625-12
1.1875
1.3125-12
700-800
800-900
1000-1100
540-600
600-675
750-825
--20
-24
1.125
1.250
1.500
1.500-12
1.625-12
1.875-12
1300-1400
1400-1500
1600-1700
900-1000
1000-1100
1200-1300
Figure 2
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
15
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Inner Nut
Outer Nut
Thd size
Torque, lb-in
Thd size
Torque. lb in
.750-16
.8125-16
.9375-12
1.750-12
340-375
400-450
525-600
1325-1450
1.1875-12
1.1875-12
1.375-8
2.375-8
290-340
290-340
370-420
1055-1130
TABLE IX
Assembly Torques for jam nuts for bulkhead or positioning fittings, oil lubricated (see para. 11)
Thread
size
.250-28
.3125-24
.375-24
.4375-20
.500-20
.5625-18
.625-18
.750-16
.8125-16
.875-14
1.000-12
1.0625-12
1.1875-12
1.250-12
1.3125-12
1.500-12
1.625-12
1.875-12
2.250-12
2.500-12
--30-35
60-70
90-100
120-135
150-170
--270-295
--345-375
--455-505
835-910
--920-1000
--1275-1425
1425-1575
--1850-2050
Figure 4
Homepage
Previous Document
TPM
SPECIFICATION
OF
16
22
DATE: 6/14/90
S. Leavitt
ISSUED BY:
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Aluminum asbestos
Copper asbestos
Nickel asbestos
Steel asbestos
135
135
135
180
180
180
180
270
270
270
360
360
67
67
67
90
90
90
90
135
135
135
180
180
TABLE XI
TABLE XII
Torque, lb-in
Thread size
Torque, lb-in
8-10
8-12
10-15
30-35
35-40
.164-32
.190-32
20-25
25-30
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV B
TPM124
TPM
SPECIFICATION
ISSUED BY:
OF
17
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
Torque, lb-in
.164-32
.190-32
15-20
24-40
TABLE XIV
Installation Torques for standard interference fit studs (See para. 14)
Torque limits, lb-in (See para. 3.2)
Thread
(Stud end)
Maximum
Minimum
Necked-down*
Plain**
.164-32
.190-24
10
15
30
40
30
45
.250-20
.3125-18
.375-16
40
85
160
95
210
375
105
230
425
.4375-14
.500-13
.5625-12
200
250
425
600
950
1400
675
1050
1500
.625-11
.750-10
625
1100
1900
3500
2100
3800
These limits apply where the unthreaded diameter of the stud is less than the
minimum minor diameter of the coarse pitch thread (stud end).
**
These limits apply where the unthreaded diameter of the stud is equal to or greater
than the minimum minor diameter of the coarse pitch thread (stud end).
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV B
TPM124
TPM
SPECIFICATION
ISSUED BY:
OF
18
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
Maximum
Minimum
Necked-down*
Plain*
.164-36
.190-32
10
15
30
45
30
50
.250-28
.3125-24
.375-24
40
85
160
115
240
450
125
260
500
.4375-20
.500-20
.5625-18
200
250
425
700
1150
1600
800
1300
1800
.625-18
.750-20
625
1100
2400
4200
2600
4600
These limits apply where the unthreaded diameter of the stud is less than the
minimum minor diameter of the fine pitch thread (nut end).
**
These limits apply where the unthreaded diameter of the stud is equal to or greater
than the minimum minor diameter of the fine pitch thread (nut end).
TABLE XVI
Installation Torques for standard and stepped studs installed in self-locking
helical coil inserts (See para.14)
Torque Limits, lb-in.**
Thread size
(Nut end)
Minimum
Maximum
.190-32*
.250-28
.3125-24
23
52
105
45*
90
180
.375-24
.4375-20
.500-20
140
175
260
240
300
450
.5625-18
.625-18
350
525
640
900
*
**
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
19
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Thread
size
Torque, lb-in.
Min
Max
breakaway
locking
Thread
size
Torque, lb-in
Min
Max
breakaway
locking
.112-40
.112-48
.138-32
.138-40
0.5
0.5
1.0
1.0
3
3
6
6
.500-14
.500-20
.5625-12
.5625-18
24.0
18.0
30.0
24.0
150
150
200
200
.164-32
.164-36
.190-24
.190-32
1.5
1.5
2.0
2.0
9
9
13
13
.625-11
.625-18
.750-10
.750-16
40.0
32.0
60.0
50.0
300
300
400
400
.250-20
.250-28
.3125-18
.3125-24
4.5
3.5
7.5
6.5
30
30
60
60
.875-9
.875-14
1.000-8
1.000-14
82.0
70.0
110.0
92.0
600
600
800
800
.375-16
.375-24
.4375-14
.4375-20
12.0
9.5
16.5
14.0
80
80
100
100
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV B
TPM124
TPM
ISSUED BY:
SPECIFICATION
OF
20
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
1/2-13
5/8-11
3/4-10
7/8-9
1-8
1 1/8-8
1 1/4-8
35-40
70-80
120-135
195-220
290-330
420-480
595-675
Notes:
* Applicable only for high strength bolting materials:
Bolts- ASTM A193, Grade B7 or Grade B8M
Nuts- ASTM A194, Grade 2H or Grade 8M
**
For spiral wound gasket applications, the flange faces should bottom out on gasket inner/outer rings prior to reaching the final assembly torque (A feeler gauge can be used for purposes of checking this).
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
21
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REV B
TPM124
REFERENCE:
Normal
hand
engagement
L
Pitch
P
.062-27
.125-27
.250-18
.1600
.1615
.2278
.375-18
.500-14
.750-14
X basic
(Nominal)
tight
engagement
L + 1.5 p
X minimum
(X basic-2p)
X maximum
(X basic + 2p)
X maximum + p
.03704
.03704
.05556
.2156
.2171
.3111
.1415
.1430
.2000
.2897
.2912
.4222
.3267
.3282
.4778
.2400
.3200
.3390
.05556
.07143
.07143
.3233
.4271
.4461
.2122
.2843
.3033
.4344
.5700
.5890
.4900
.6414
.6604
1.000-11.5
1.250-11.5
1.500-11.5
.4000
.4200
.4200
.08696
.08696
.08696
.5304
.5504
.5504
.3565
.3765
.3765
.7043
.7243
.7243
.7913
.8113
.8113
2.000-11.5
2.500-8
3.000-8
.4360
.6820
.7660
.08696
.12500
.12500
.5664
.8695
.9535
.3925
.6195
.7035
.7403
1.1195
1.2035
.8273
1.2445
1.3285
Thread
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV B
TPM124
ISSUED BY:
OF
22
22
DATE: 6/14/90
S. Leavitt
DATE: 11/17/92
RELEASED
SHEET
REFERENCE:
Figure 7
Homepage
Previous Document
TPM
SPECIFICATION
RELEASED
REV
TPM124
ISSUED BY:
S. Leavitt
SHEET
OF
1A
1
DATE: 6/14/90
DATE: 11/17/92
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
--
1
3
---
--
--
8
-All Tables -11
--
13
--
15
--
18
--
S. Leavitt
10/22/90
EC#3462
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
RELEASED
REV
TPM124
ISSUED BY:
S. Leavitt
SHEET
OF
2A
2
DATE: 6/14/90
DATE: 11/17/92
REFERENCE:
REV SHEETS
LET AFFECTED
20
SHEETS
DESCRIPTION
ADDED
--
REV BY
APPVD
& DATE
& DATE
Torque lb-ft
1/4-20
5/16-18
3/8-16
7/16-14
1/2-13
9/16-12
5/8-11
3/4-10
7/8-9
1-8
1 1/8-8
1 1/4-8
1 3/8-8
1 1/2-8
1 5/8-8
1 3/4-8
1 7/8-8
2-8
2 1/4-8
2 1/2-8
2 3/4-8
3
6
12
18
30
45
68
90
150
240
368
533
750
1020
1200
1650
2250
3000
3300
4770
6600
8880
11580
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV C
TPM126
ISSUED BY:
OF
1
3
DATE: 1/21/91
S. Leavitt
DATE: 3/20/92
RELEASED
SHEET
REFERENCE:
SCOPE
This specification establishes the requirements for field connection identification, component identification, ancillary assembly (skid) identification and federally mandated warning tags.
2.0
3.0
Identification tags are intended to provide a readily visible means to correlate the assembly P&I diagram with the actual physical components.
2.2
One and one-half inch diameter stainless steel (Ref. CT115508-1200) or blue anodized aluminum
tags (Ref. CT112872-2400) shall be utilized as specified on the skid assembly drawing or purchase
order.
2.3
As shown on the applicable assembly drawing, identification shall be legibly marked on each tag in
letters 1/4 inch high to a minimum depth of .010.
2.4
Tags shall be secured to each field connection and component in a visible location so as to not interfere with the physical installation and operation of the skid. Tags shall be attached by annealed stainless steel wire of .025 to .035 diameter (Ref. CT112940 or as otherwise specified).
2.5
If tags are attached prior to final skid painting, they shall be suitably protected from the painting process.
ASSEMBLY (SKID)
3.1
Each major system assembly or skid delivered by TPM shall carry a nameplate.
3.1.1
3.2
In addition to the specific information required in paragraphs 3.3 thru 3.6, name plates shall
carry the corporate logo, engine logo, etc., as required by company policy (Ref. IPD21140).
"TYPE OF SKID" shall be as indicated on the specific assembly and test specification.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV C
TPM126
TPM
SPECIFICATION
ISSUED BY:
OF
2
3
DATE: 1/21/91
S. Leavitt
DATE: 3/20/92
RELEASED
SHEET
REFERENCE:
01
02
03
04
Project Number
05
06
07
08
09
10
11
12
13
14
16
17
18
Starting Skid
Fire Skid
Gas Fuel Conditioning Skid(s)
Liquid Fuel Conditioning Skid(s)
(Fuel forwarding, fuel filtering)
Hydraulic Skid
Lubrication Skid(s)
Water Wash Skid
Water Injection Skid
Steam Injection Skid
Liquid Fuel Skid (Fuel Plate for FT8)
Gas Fuel Skid
Engine Drying
Muscle Air Skid
Drain Skid
Turbine Cooling Air Skid
Water Purge Skid
Ignition Gas Skid
3.4
"Assembly Number" shall be the assembly number or part number each skid is built to.
i.e. - IPE20685GR1
3.5
3.6
3.7
Required information shall be legibly marked on the plates in 1/8 inch high letters to a minimum
depth of .010.
3.8
Nameplates shall be permanently attached to the skids by CT112921-0500 drive screws or as otherwise specified on the applicable assembly drawing.
3.9
If plates are attached prior to final skid painting, they shall be suitably protected from the painting
process.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
REV C
TPM126
ISSUED BY:
OF
3
3
DATE: 1/21/91
S. Leavitt
DATE: 3/20/92
RELEASED
SHEET
REFERENCE:
HAZARD LABELS
4.1
Hazard warning tags or labels shall be provided as determined by the responsible engineer or corporate legal staff and as indicated on the assembly drawings. Such tags shall be in accordance with the
governing regulating specification.
4.2
Particular attention should be given to locations which include elevated temperatures (over 140F),
electrical conductors and potentially explosive environments. (Ref. CT114063 for high temperature
warning).
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
RELEASED
REV
TPM126
ISSUED BY:
SHEET
OF
S. Leavitt
1A
1
DATE: 1/21/91
DATE: 3/20/92
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
1, 2
--
SLL
4/3/91
--
SLL
1/13/92
EC#5274
--
B. Jelen
3/3/92
EC#5484
--
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
1
3
DATE: 5/11/91
B. Staib
RELEASED
SHEET
REV A
TPM129
DATE:
12/14/92
REFERENCE:
2.0
SCOPE
1.1
This specification establishes the minimum requirements for preparation and painting of steel surfaces
of equipment for Turbo Power and Marine Systems, Inc. (TPM).
1.2
Where alternate requirements are presented, the document which references this specification will
identify those sections which are applicable.
1.3
Where this document and referenced documents are in conflict, this document shall have precedence.
SURFACE PREPARATION
2.1
All steel shall be thoroughly cleaned. Loose rust, rust scale, mill scale, and other foreign material
including dust, dirt, oil, grease, chemical contamination, or any previously applied paint shall be
removed so as to produce a clean surface satisfactory for the application of paint.
2.2
Welded joints and areas in the vicinity of welded joints shall have splatter, slag, and flux deposits
removed. Break all sharp edges.
2.3
Cleaned steel shall be prime painted within eight hours after cleaning.
2.4
All galvanized steel shall be chemically etched prior to painting, using "Galvaprep" by Amchem
Products, or equal.
2.5
Surface preparation shall be in accordance with one of the following Steel Structures Painting Council
(4400 Fifth Avenue, Pittsburgh, Pennsylvania) specifications.
2.5.1
2.5.2
2.5.3
2.6
Note that power tool or blast cleaning must be preceded by solvent cleaning to remove heavy deposits
of oil or grease.
2.7
On galvanized steel the specification of Section 2.5.2 or 2.5.3 may be relaxed to 2.5.1.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
2
3
DATE: 5/11/91
B. Staib
RELEASED
SHEET
REV A
TPM129
DATE:
12/14/92
REFERENCE:
COATINGS
All paint shall be applied in accordance with Steel Structures Painting Council SSPC-PA1-82, and with paint
manufacturers instructions with particular attention given to limits on humidity, surface temperature, and
time between coatings. Paint shall be applied thoroughly and evenly and shall be worked well into pores,
joints, and other openings. Workmanship shall be of the highest quality with no running paint or other
unsightly blemishes. The TPM inspector may check the dry film thickness measurements in accordance with
Steel Structures Painting Council SSPC-PA2-82. Measurements will be made at random at the judgement
of the TPM inspector. The specified film thicknesses are stated in mils where one mil = 0.001 inch = 25
microns. Maximum dry film thickness shall not exceed twice the stated minimum thickness. Surface
coatings shall be per one of the following, as specified in the referring document.
3.1
Protective Oil
3.1.1
3.2
4.0
Machine finished surfaces which are not to be painted shall be protected against corrosion by
coating with E. F. Houghton "Rust Veto" #76-HF. Coating shall not be harmful to adjoining
painted areas. Application shall be preceded by solvent cleaning.
3.2.2
Apply one coat Ameron Dimetcote #21-5 Inorganic Zinc Silicate, 3 mils minimum dry film
thickness. Color to be light gray.
Acrylic
4.1.1
Use only over surfaces previously coated per Section 3.2 (or 2.5.1 if galvanized).
4.1.2
4.1.3
Apply one coat of Ameron Amerguard #220 Acrylic, 2 mils minimum dry film thickness for a
total of 5 mils minimum dry film thickness including primer. Color to be Pearl Gray (GR-3).
An intermediate mist coat is required, using Ameron #856 wetting agent additive and thinned
with clean water.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
3
3
DATE: 5/11/91
B. Staib
RELEASED
SHEET
REV A
TPM129
DATE:
12/14/92
REFERENCE:
4.3
4.4
4.5
5.0
4.2.2
4.2.3
Apply one coat of Ameron Amerlock #400 High Build Epoxy, 3 mils dry film thickness for a
total of 6 mils minimum dry film thickness including primer. Color to be Pearl Gray (GR-3).
An intermediate mist coat is required.
Polyurethane
4.3.1
4.3.2
Clean and touch up damaged areas per Section 3.2 and 4.2.
4.3.3
Apply one coat of Ameron Amercoat #450 HS Polyurethane, 2 mils dry film thickness for a
total of 8 mils minimum dry film thickness including primer. Color will be specified in
referring document.
Inorganic Topcoat
4.4.1
4.4.2
4.4.3
Apply one coat of Ameron Amercoat #741 Inorganic Topcoat, 3 mils dry film thickness for a
total of 6 mils minimum dry film thickness including primer. Color to be Pearl Gray (GR-3).
Epoxy, Self-Prime
4.5.1
Prepare surfaces per Section 2.5.1 if existing coating is tightly adhering and in good condition,
or 2.5.2 if not. See referring document for masking requirements, if any.
4.5.2
Apply one coat of Ameron Amerlock #400 Epoxy, 5 mils minimum dry film thickness. Color
to be Pearl Gray (GR-3).
COATING MANUFACTURERS
E.F. Houghton, Valley Forge, Pennsylvania
Ameron Protective Coatings, Brea, California
Amchem Products, Ambler, Pennsylvania
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
RELEASED
REV
TPM129
ISSUED BY:
B. Staib
SHEET
OF
1A
1
DATE: 5/11/91
DATE: 12/14/92
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
EC#6693
E. K.
12/14/92
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
1
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
12.0
13.0
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
2
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
2.2
2.3
2.4
2.5
2.6
IEEE 142; IEEE Recommended Practice for Grounding of Industrial and Commercial Power
Systems
2.7
IEEE 837; IEEE Standard for Qualifying Permanent Connections Used in Substation Grounding
2.8
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
3
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
FIGURE
GENERATOR GROUND
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
4
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
FIGURE 2A
EMERGENCY GENERATOR GROUNDING
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
5
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
FIGURE 2B
Ups Solid State Neutral Intertie To Premises System Neutral Busbar
5.0
6.0
General
6.1.1
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
6
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
6.1.3
FIGURE 3
CONTROL CABINET GROUNDING
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
7
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
6.2
The cabinet main ground bus shall be secured at the bottom of the cabinet, as shown in
Figure 4 of this specification. It shall be located towards the rear of the cabinet so that it
will not be in the way of regular maintenance activities but it shall be forward of the
wireways mounted on the rear panel.
6.2.2
Two methods of securing the cabinet main ground bus are given in Figures 4A & 4B.
Figure 4A mounts the ground bus on angle brackets mounted on bottom side rails. Figure
4B mounts the ground bus directly on the bottom side rails. Choice can be made between
the two, based on available space and accessibility to the ground bus. The ground bus may
be spliced using 1" x 1/4" copper bus, if necessary.
6.2.3
When more than one cabinet is mechanically attached to form a lineup of cabinets as an
assembly, the ground bus shall traverse all cabinets, and be equipped on each end for
connection to the grounding electrode system. The conductor between the ground bus and
the grounding electrode is installed by the constructor and shall be sized and attached as
shown in Figure 4A & 4B.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
8
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
6.3
FIGURE 5
INSTRUMENT/SHIELD COMMON BUS
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
9
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
6.5
6.6
FIGURE 6
CABINET DOOR GROUNDING STRAP
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
10
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
7.0
Equipment Grounding
The NEC (Article 250-92) requires that one of the following three methods be used for
grounding ac equipment enclosures:
1. By the raceway, cable tray, cable armor, or cable sheath (The term "raceway" is defined to
include rigid metal conduit, plus a variety of other "enclosed channels".)
2.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
11
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
8.0
FIGURE 7
INTRINSICALLY SAFE BARRIER GROUND
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
12
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
9.2
10.0
12"
18"
100
BD12
BD18
125-200
BE12
BE18
Note: The Part Numbers on the above table are available from Burndy Corp.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
13
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
Bonding Jumper
Install a bonding jumper from the equipment enclosure (e.g., motor frame or motor terminal box)
to the conduit supplying the power, using an approved bonding jumper and conduit ground
clamp. The conduit must be continuous from the equipment to the power source. If a flexible
conduit is used for vibration damping, the bonding jumper shall be installed according to Article
250-91(b) and Article 350-5 of the NEC.
11.2
Discontinuity of Raceway
If the conduit is interrupted in any way (e. g., by a trench or cableway) additional provisions must
be made to continue the ground back to the service ground. Bonding jumpers shall connect the
conduit to the cableway, or a separate bare or green (or green with yellow stripes) insulated
conductor shall be clamped to the conduit and terminated at the service ground at the power
source cabinet (MCC). The separate conductor shall be routed in close proximity (parallel) to the
power cable or conductors.
1. The motor branch circuit is routed from the MCC via various wiring methods (i.e. direct burial, trenches, cable tray) and the
continuity of the raceway system can not be assured
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
14
14
DATE: 8/2/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
Inspection
Inspection and resistance measurements to ground shall be made after installation in accordance
with Section 12.0
12.0
13.0
13.2
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
R. Darveau
OF
1A
1
DATE: 8/2/93
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM130
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
1
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Scope
2.0
Reference Documents
3.0
Quality Assurance
4.0
5.0
6.0
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
2
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Scope
This specification establishes the minimum requirements for the wiring and interconnecting cables for
control systems, electrical equipment, cabinets, panels, devices, switches, relays, etc. manufactured for
United Technologies, Turbo Power and Marine Systems, Inc. (Hereafter referred to as TPM). This
specification is applicable to both internal control cabinet wiring and field installed wiring. Project specific
criteria as detailed or project specific drawings override this specification.
2.0
Reference Documents
2.1 NFPA 70; National Electrical Code (NEC)
2.2 Project Schematics and Wiring Diagrams
2.3
IEEE 422; IEEE Guide for the Design and Installation of Cable Systems in Power Generating
Stations
2.4
2.5
Quality Control
3.1
The vendor shall have a Quality Control System which complies with TPM-QA-200A.
3.2
The vendor shall furnish a complete written inspection and test procedure for review and approval
by TPM prior to commencement of manufacturing. TPM will select designated witness points and
notify the vendor by Purchase Order supplement and/or written communication by Engineering.
3.3
Unless otherwise specified, the vendor is responsible for the planning, performance and cost of all
inspections and tests.
3.4
TPM reserves the right to witness all inspections and tests including source inspections, in-process
tests and final acceptance tests. The vendor shall notify TPM prior to the inspection and test date(s).
3.5
The vendor shall submit to TPM, via written communication, any and all exceptions taken to the
requirements specified by either this specification or TPM Purchase Order.
3.6
Acceptance after inspection does not relieve the vendor from the responsibility of complying with
the performance requirements specified herein.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
3
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Ampacity
The following table defines the maximum ampacity allowed for the different sizes of
conductor: (1)
Conductor Size AWG
20
18
16
14
12
10
8
Ampacity
5
7
10
15
20
30
40
4.2
4.1.2
4.1.3
Control wiring not associated with the Woodward Governor is protected by fusing,
matching the ampacity table as given in section 4.1.1. a minimum of #16AWG is to be used.
4.1.4
Current transformer circuits having 5 Amps secondary current shall all be #12AWG.
4.1.5
Fire Protective Circuits - The minimum wire size for Fire Protective Circuits is #14 AWG.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
4
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Lugs
Either ring or fork tongue lugs can be used to terminate suppressor
4.3.1
4.3.2
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
5
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Tools
Only ratchet type crimping tools shall be used when installing pins, lugs, splices and coaxial connectors.
All crimping tools shall be checked according to manufacturers recommended procedure at
least once a month.
Tool manufacturer shall be the same as lug manufacturer, unless tool and lug compatibility
is controlled by recognized industry standards.
4.4
Conductors
4.4.1
Color
NEC Type
SIS
24 Vdc (All)
Blue
Ground (GND)
Green
Stranding
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
6
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
4.4.2
No. Strands/Gauge
16
19/29
7134
14
19/27
7135
12
19/25
7136
Multiconductor Cables
Multiconductor cables and miscellaneous cables are to be as specified on assembly
drawings and associated bill of material.
4.4.3
Shielded Cables
Multi-conductor cables and miscellaneous cables are to be as specified on assembly
drawings and associated bill of material. Shielded cable shall be braided or foil with drain
wire type. Multi-conductors shall be twisted. Shielded wire shall be Alpha type
5610B1601E (or equal). Wire size #16 AWG unless otherwise specified. Rated 300V, -20C
to +105C.
Shield terminations - Braided tinned copper. See attached (Figure 1).
1. Remove outside jacket back three (3) inches from the end.
2. Unwrap and prepare per standard practice.
3. To prepared shield, add ground pigtail per Fig. 1A.
4. Put one inch shrink tubing over exposed shield or HYRING and pigtail per Fig. 1A.
5. Lug wire ends for attachment to grounding studs and bus.
Shields shall be continuous from signal source to monitoring and control equipment. When
it is necessary to pass through a terminal block a separate terminal shall be utilized for the
shield. Shielded leads shall be grounded to the monitoring or control device at the monitor
or control device end only. The unsaddled portion of the conductor shall be kept as short as
practical. If the monitor or control device is not provided with a terminal for shield
termination, a short pigtail splice (See Fig 1A) green #16 AWG, shall be added to facilitate
grounding the shield to the instrument shield common bus. Locate a point as close as
practical to the conductors being shielded to ground (or bond) the pigtail splice. Alternate
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
7
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Coaxial Cable
Coaxial cables are used for PLC intercommunication drops. Cables shall be 75 ohm RG-6
quad shield (foil-braid, foil-braid) type. Temperature Rating -40 to +80C. Polyethylene or
polypropylene core with PVC or polyethylene outer jacket. Copper covered steel conductor.
Connectors shall be single piece type F-56QS (for foil-braid, foil braid type cable)
manufactured by Augat, LRC series. Cable to be dressed using proper stripping tool.
Connectors to be installed using proper crimping tool. See Figure 1B for recommended and
acceptable lead dressing.
4.4.5
Thermocouple Cable
Thermocouple extension wire shall be solid, duplex, (thermocouple pair) #16AWG, of an
ANSI Type matching the thermocouple Type (Type K is the usual choice). The wire shall
meet ANSI MC96.1 specifications for thermocouple type wire and color coding. Polyvinyl
insulation 0 to 105 C insulation. Omega part number EXPP-x-16 or equivalent.
5.0
Ampacity
Cables as detailed in this specification are the TPM recommended cables to be used for the
interconnection wiring between the control cabinets and the field located skid assemblies, junction
boxes, etc. Cables are as specified in the project specific Cable List, xxxx-189-E006L. In this
document, wire size is selected from the 60 C Insulation Column of Table 310-16 of the NEC. No
corrections have been made for derating due to direct burial, covered, or unventilated cable trays
located within cable troughs, or for cables located within the high ambient temperature environment
of the gas turbine enclosure. Minimum wire sizes for control circuits and fire protective circuits are
as noted in Section 4.1.
5.2
Cable Trays
When cabling is run in a cable tray installation where the power and signal cables form a multi-tier
assembly as detailed in Figure 3, separation of cable types shall be observed with regard to the
following sections of the NEC:
318
Cable Trays
430
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
8
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
725
760
As shown in Figure 3, the Remote-Control, Signalling and Power-Limited Circuits, as well as the
intrinsically safe and fire signalling circuitry is installed in a cable tray separate from the power
wiring. A minimum vertical separation of 18 inches between the top of the bottom tray and the
bottom of the top tray is required. When this separation can not be maintained (such as installation
in a wiring trough), then a tray cover is to be installed over the lower tray as shown in Figure 3. This
is as recommended in Reference 2.3 to eliminate EMI / RFI. The fire protective signal wiring and
the intrinsically safe wiring is to be physically separated from the rest of the wiring by either
raceways or tray barriers. Intrinsically Safe Wiring signs are to be applied to the intrinsically safe
wiring per Section 504 of the NEC. Medium voltage cable is to be installed in cable tray or raceway
separate from low voltage signal and power wiring. In the signal circuit cable tray, analog signals
are to be physically and electrically isolated from the discrete control signals by means of a cable
tray barrier as shown in Figure 3.
5.3
5.4
Testing
The vendor shall ring out all wiring Ring out means to use an audible or visual electrical device to
check continuity from one point to all other points in a circuit. Low voltage devices shall be used,
i.e., ohmmeter, check out buzzer. Power shall be applied to panels, cabinets, devices, etc., only
under the supervision of TPM Test Engineer/Inspector. A two week notice shall be given to TPM
for inspection and checkout of equipment at the vendor's facility. All repairs to faulty wiring or
damaged equipment shall be at the vendor's expense, unless it can be proven the equipment was
damaged prior to assembly. Incoming inspection of all equipment is advised.
5.5
Cable Types
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
SHEET
REV
TPM132
ISSUED BY:
OF
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
9
16
REFERENCE:
Base
Hash Marks
or Stripes
Cond
No.
Base
Hash Marks
or Stripes
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Black
Red
Blue
Orange
Yellow
Brown
Red
Blue
Orange
Yellow
Brown
Black
Blue
Orange
Yellow
Brown
Black
Red
Black
Black
Black
Black
Black
Red
Red
Red
Red
Red
Blue
Blue
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
Orange
Yellow
Brown
Black
Red
Blue
Yellow
Brown
Black
Red
Blue
Orange
Brown
Black
Red
Blue
Orange
Yellow
Blue
Blue
Blue
Orange
Orange
Orange
Orange
Orange
Yellow
Yellow
Yellow
Yellow
Yellow
Brown
Brown
Brown
Brown
Brown
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
10
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
6.0
Wire Numbers:
6.1.1
The wire number consists of 6 alpha numeric characters with a dash (-) separating the first
three characters from the last three. The separation allows easy location of the wire number
on the schematic and for service purposes.
6.1.2
The first character is a letter that is chosen to define the schematic group (system), followed
by two numbers representing the schematic sheet number. The next two numbers represent
the line number (LN) on the schematic sheet and the last number is the position of the wire
in the line.
6.1.3
Wire numbers will be consecutive from top left to lower right on the schematic diagram. All
conductors or cables of the same potential will carry the same wire number, resulting in all
conductors on the same device terminal having the same wire number. Conductors passing
thru a terminal block will have the same wire number on both sides (i.e., entering and
leaving the terminal block).
6.1.4
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
11
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
U10-120
POSITION ON LINE
LINE ON SHEET
SHEET NO.
UNIT SCHEMATIC
(Earlier Designs are S for Station Control)
L2
L1
Line #
10
100
100
CR1
101
102
CR3
100
11
12
LS1
4/117
102 10 101 103
A
PLC
102
CR2
120
4/118
120 11
A
111 121
6.1.5
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
12
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
Wire Labels
All wire labels shall be of the heat shrinkable type, sized for the conductor or cable. The label shall
be installed so that the wire number is visible for service purposes. Label markings shall be
permanent, not easily rubbed off during normal usage. The marking shall be typed, hot stamped or
neatly hand printed. The hand printing is preferred for repair or emergency usage and is not
acceptable on original supplied equipment from vendor.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
13
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
14
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
15
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
FIGURE 3
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
16
16
DATE: 7/27/93
R. Darveau
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM132
REFERENCE:
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
SHEET
REV
TPM132
OF
R. Darveau
DATE: 7/27/93
DATE:
REVISED BY:
RELEASED
1A
1
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
1
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
SCOPE
1.1
2.0
This specification establishes the minimum requirements for the interconnecting cable
termination for TPM installed equipment. This specification is applicable to all field installed
low voltage (less than 600V) wiring. In such a case where project specific documents are in
conflict with this specification, the information depicted in the project specific documents shall
take precedence.
PREPARATION OF CABLES
2.1
GENERAL
2.1.1
Prior to making any terminations, all cables must be inspected for continuity, shield
isolation, and proper installation of trays. (See paragraph 4.2 and Figure 1).
2.1.1.1
All power cables must be megger checked line to line and line to ground
before termination. Use 500V megger for this check.
2.1.2
All cables shall be dressed as neatly as possible. Wire ties shall be used in the junction
boxes, cabinets and wire trays as required. Provide slack in cables for bend radius and
at terminations for at least two (2) future repairs. Tight bend radius and crossing of
cables must be avoided. Workmanship must be approved by the site manager.
2.1.3
Cable segregation shall be maintained between signal, control and power cables. No
signal cable shall occupy the same tray with power cables or control cables without a
metal grounded barrier isolating (shielding) them. See Figure 1.
2.1.4
When and if signal cables cross power or control cables they must cross at right
angles. If it is impractical to separate control and power cables, they may occupy the
same wireway but the control cables should be grouped away from the power cables.
2.1.5
Cable shields are terminated at one end only, usually at Control Enclosure end. The
shield is brought through terminal blocks and is isolated from ground.
NOTE: On some cables, an overall shield may be supplied that is not required in the
design. In this case, no direction is given in the terminal list regarding the
termination of the shield. This shield must be grounded at the Control Enclosure end
only. The shield is to be brought to power ground (copper ground bar) through an
unused terminal in the Motor Control Center (MCC) or Instrument Cabinets, using a
#14 AWG green conductor. The unused terminal selected must be approved by the site
manager and shall be clearly marked on the site drawing set. The other end of the
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
2
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
2.3
The outer jacket shall be removed to a minimum length required for proper installation
purposes. In no case shall unjacketed cable be exposed in trenches or uncovered
wireways. Cable jacket may be removed to facilitate installation in conduit, covered
wireways, junction boxes or cabinets.
2.3.2
If an outer (overall) shield is provided on the cable, the outer shield shall be terminated
with a green ground conductor (not smaller than the largest conductor in the cable) and
brought to the closest equipment ground stud or grounding bar at the Control
Enclosure end only (See Figure 2). The other end shall remain under the outer jacket
or shall be protected under shrink tubing (See Figure 3). The overall shield shall be
terminated at one point only. Care must be taken to insure shield does not come in
contact with ground except through the green ground conductor.
2.3.3
The shielded conductors (TSP, Twisted Shielded Pair or TST, Twisted Shielded
Triplex) shall be terminated per the Cable Termination List applicable to the project.
The TSP/TST shield must not contact ground or any other shield, and is to remain
isolated except as noted on the termination list. The jacket may be removed from the
TSP/TST as necessary to facilitate termination. The shield must be brought as close as
practical to the terminating point (3" maximum). The drain wire is to be brought to the
applicable terminal as noted on the termination list. A sleeve shall be installed over the
exposed drain wire to prevent it from coming in contact with any other shield or
conductor.
2.3.4
The TSP/TST cables are supplied with a foil shield and outer mylar wrap. Care must
be taken when removing the overall jacket to insure that the foil and mylar wrap does
not come lose destroying the shielding capability. A two (2) inch long shrink sleeve or
equivalent method shall be used to insure the integrity of the foil shield with its outer
mylar wrap at the terminating point. Electrical tape can be used until the shrink tubing
is installed. Shrink tubing can be installed over the electrical tape if desired (See
Figure 2).
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
3
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
2.4
THERMOCOUPLE CABLES
2.4.1
2.5
Thermocouple cables must be terminated properly. That is, conductor jacket must
match the color on both sides of the terminal block. Thermocouples are type K
cromel (+) yellow and alumel (-) red. The cromel must be connected to cromel and
alumel must be connected to alumel at the terminal blocks.
3.0
Fiber optic cables can be checked by exposing one end to a bright light source and
observing the light emitted at the other end. The light should not be diminished in any
way. Broken fibers will diminish the optical capability. Inspect mating connectors on
equipment to insure good quality connections and optical capability.
All conductors are to be permanently identified with the Wire Number as specified on the
applicable termination list. A heat shrinkable sleeve containing wire number shall be used. The
wire number shall by typed, hot stamped or neatly hand printed on the sleeve. The sleeve is to
be attached to the conductor so that the number can be viewed without disturbing the
installation.
3.2
The wire number is made up of six (6) characters, (3) and (3) separated by a dash. The first (1)
character identifies the system schematic i.e. U Unit Control schematic (see Symbology
Drawing for complete list). The next two (2&3) characters identify the applicable sheet of the
schematic. The next two (4&5) characters identify the line number on the applicable sheet. The
last character (6) identifies the location on the line of the applicable schematic sheet.
3.3
A permanent cable ID shall be placed at both ends of all cables (See Figures 2&3). A heat
shrinkable sleeve shall be used. The cable ID is called out on the Cable List and the
Termination List (External Wiring List).
3.3.1
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
4
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
TESTING
4.1
After all wiring is completed for a system, a point to point wiring check shall be made to
confirm all wiring is complete and continuity is established between point to point. The system
schematic diagram shall be used to confirm this wiring. Recognizing that the termination list
is developed from the schematic diagram, the schematic diagram must be used as the governing
document.
4.1.1
4.2
After the installation is completed, the work shall be inspected for good workmanship by a
person skilled in this type of installation and a written report of the completion shall be given to
the site manager.
4.3
Motor power circuits are to be Megger checked before any motor is energized. Use a 500V
megger for this purpose. Be sure circuit breakers are open at the motor source. Check between
each conductor and ground. Record all readings and supply site manager with report prior to
activating any circuits.
4.4
NOTE: Care must be taken when using any test equipment on circuits that have been terminated
to avoid any possible damage to equipment.
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
5
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
FIGURE 1
SUGGESTED CABLE TRAY INSTALLATION
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
6
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
FIGURE 2
TYPICAL DRESSING OF SHIELDED CABLES
(TERMINATED SHIELDS)
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
OF
7
7
DATE: 1/23/95
C. Spencer
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
FIGURE 3
TYPICAL DRESSING OF SHIELDED CABLES
(UN-TERMINATED SHIELDS)
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
TPM
SPECIFICATION
ISSUED BY:
C. Spencer
OF
1A
1
DATE: 1/23/95
DATE:
REVISED BY:
RELEASED
SHEET
REV
TPM139
REFERENCE:
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
This document is the property of Turbo Power and Marine Systems, Inc. and is delivered on the express condition
that it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any
purpose without the express written consent of Turbo Power and Marine Systems, Inc.; and that no right is granted
to disclose or so use any information contained in said document. These restrictions do not limit the right to use information obtained from another source.
Homepage
Previous Document
REV-2
15 January 2002
Homepage
APPENDIX: B-1
Previous Document
REV-2
15 January 2002
APPENDIX: B-2
REV-2
15 January 2002
APPENDIX: B-3
REV-2
15 January 2002
APPENDIX: B-4
REV-2
15 January 2002
APPENDIX: B-5
REV-2
15 January 2002
APPENDIX: B-6
REV-2
15 January 2002
APPENDIX: B-7
REV-2
15 January 2002
APPENDIX: B-8
REV-2
15 January 2002
Homepage
APPENDIX: B-1
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV A
CT118001
1
3
DATE:
12/17/04
REVISE BY : M. Etre
DATE:
1/13/05
REFERENCE :
REV:
ISSUED BY :
P. Maiorana
OF
MATERIAL:
PWPS P/N
HILTI P/N
SIZE
DIA. x LENGTH
CT118001-03041Z
00068657
3/8" X 5 1/8"
CT118001-04052Z
00068658
1/2" X 6 1/2"
CT118001-04072H
1/2" x 9"
CT118001-05061Z
00068659
5/8" X 7 5/8"
CT118001-05084H
5/8" x 10 1/2"
CT118001-06077Z
00068660
3/4" X 9 5/8"
CT118001-06104H
3/4" x 13"
CT118001-07080H
00068661
7/8" X 10"
CT118001-07128H
00045259
7/8" X 16"
CT118001-08096H
Special Order
Hot Dipped Galvanized
1" x 12"
CT118001-08096Z
00068662
1" X 12"
CT118001-08144H
1" x 18"
CT118001-10128Z
00068663
1 1/4" X 16"
CT118001-10168H
1 1/4" x 21"
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV A
CT118001
2
3
DATE:
12/17/04
REVISE BY : M. Etre
DATE:
1/13/05
REFERENCE :
REV:
ISSUED BY :
P. Maiorana
OF
Notes:
1.
The first two digits of the PWPS dash number represent the anchor diameter in eights of an inch. The second
three digits represent the anchor length in eights of an inch.
H = Hot Dipped Galvanized
Z = Zinc plated.
2.
3.
Nuts and washers shall be furnished to meet the requirements of the above material specification.
DISPENSERS:
PWPS P/N
DESCRIPTION
HILTI P/N
CT118001-10
00229154
CT118001-11
00256889
PWPS P/N
DESCRIPTION
HILTI P/N
QUANTITY/PKG
CT118001-20
Mixer, HIT M
00089912
CT118001-21
00068156
100
CT118001-22
Mixer, HIT HY
00256082
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
SHEET
REV A
CT118001
3
3
DATE:
12/17/04
REVISE BY : M. Etre
DATE:
1/13/05
REFERENCE :
REV:
ISSUED BY :
P. Maiorana
OF
PWPS P/N
DESCRIPTION
HILTI P/N
CONTENTS
INCL IN PKG.
USABLE VOL.
CT118001-30
HY150/330/1
00246650
1 Mixer HIT M
16.5 In3
(270 ml)
CT118001-31
HY 150 Large
(32. oz)
00256480
1 Mixer HIT HY
61.0 In3
(1000 ml)
Rod Diameter
(in.)
Drill Bit
Diameter
(in.)
1/4
5/16
0.055
3/8
7/16
0.095
1/2
9/16
0.133
5/8
11/16
0.184
3/4
13/16
0.232
7/8
24mm
0.272
1 1/16
0.366
1 1/4
1 1/2
0.918
MANUFACTURER:
Hilti
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
PWPS
SPECIFICATION
RELEASED
ISSUED BY :
REVISE BY :
P. Maiorana
M. Etre
1A
1
SHEET
REV A
CT118001
OF
DATE:
12/17/04
DATE:
1/13/05
REV:
REFERENCE :
REV SHEETS
LET AFFECTED
SHEETS
ADDED
DESCRIPTION
REV BY
APPVD
& DATE
& DATE
EC#11262
M. Etre
1/13/05
This document is the property of Pratt & Whitney Power Systems, Inc. and is delivered on the express condition that
it and the information contained in it are not to be used, disclosed, or reproduced in whole or in part, for any purpose
without the express written consent of Pratt & Whitney Power Systems, Inc.; and that no right is granted to disclose
or so use any information contained in said document. These restrictions do not limit the right to use information
obtained from another source.
Homepage
Previous Document
Anchoring Systems
4.2.2
8. Unlock dispenser.
2
1
ROD
INSERT
REBAR
10
10
10
11
11
11
11. Do not disturb anchor between
specified gel time and cure time.
12
12
12
TTmax
inst
TTmax
inst
HIT HY 150/
HIT-ICE
96
HIT HY 150/
HIT-ICE
HIT HY 150/
HIT-ICE
US: 1-800-879-8000 / www.us.hilti.com Hilti Product Technical Guide 2002 Canada: 1-800-363-4458 / www.ca.hilti.com
Homepage
Previous Document
4.2.4
Adhesive Anchoring Systems
HIT-ICE Dispenser
HIT-ICE Mixer
HIT-ICE Cartridge
4.2.4
HIT HY 150/HIT-ICE
or
4.2.4.4
Installation Instructions
4.2.4.5
Ordering Information
Listings/Approvals
4.2.4.1 Product Description
Hilti HIT HY 150 is a hybrid adhesive consisting of a
methacrylate resin, hardener, cement and water. It is
formulated for fast curing and installation in a wide range
of solid base material temperatures from 104F (40C)
down to 23F (5C). For colder environmental
installations, HIT-ICE adhesive is a winter formulation of
HIT HY 150 for base material temperatures down to
10F (23C). HIT-ICE consists of a methacrylate resin
and hardener.
The systems consist of adhesive refill packs, a mixing
nozzle, a HIT dispenser and either a threaded rod, rebar,
HIS internally threaded insert or eyebolts. HY 150/HIT-ICE
is specifically designed for fastening into solid base
materials such as concrete, grout, stone or grout filled
block.
The Hilti HIT-TZ is an innovative threaded rod installed
with HIT HY 150/HIT-ICE hybrid adhesive. Please refer to
section 4.2.3 for details on HIT-TZ. With the combination
of HIT HY 150/HIT-ICE and the innovative design of the
HIT-TZ rod, anchoring into uncleaned holes, wet holes
(including standing water) and/or Hilti matched tolerance
diamond-cored holes does not adversely affect tensile
capacity. Use HIT-ICE in base material temperatures
40 F (5 C).
Product Features of HIT HY 150/HIT-ICE
Seismic qualified per ICC-ES AC58
Small edge distance and anchor spacing allowance
Mixing tube provides proper mixing and accurate
dispensing of mixed resin
Contains no styrene; virtually odorless
Cures quickly over a large range of base
material temperatures
Excellent weathering resistance; high temperature
resistance
High load capacities
Guide Specifications
Master Format Section:03250 (Concrete accessories)
Related Sections:
03200 (Concrete Reinforcing
Reinforcing Accessories)
05050 (Metal Fabrication)
05120 (Structural Steel;
Masonry Accessories)
Injectable adhesive shall be used for installation of all
reinforcing steel dowels or threaded anchor rods and
inserts into new or existing concrete. Adhesive shall be
furnished in containers which keep component A and
component B separate. Containers shall be designed to
accept static mixing nozzle which thoroughly blends
component A and component B and allows injection
directly into drilled hole. Only injection tools and static
mixing nozzles as recommended by manufacturer shall
be used. Manufacturers instructions shall be followed.
Injection adhesive shall be formulated to include resin
and hardener to provide optimal curing speed as well as
high strength and stiffness. Typical curing time at 68F
shall be 50 minutes for HIT HY 150 and 1 hour for
HIT-ICE. Injection adhesive shall be HIT HY 150 or
HIT-ICE, as furnished by Hilti.
Anchor Rods: Shall be furnished with chamfered ends
so that either end will accept a nut and washer.
Alternatively, anchor rods shall be furnished with a 45
degree chisel point on one end to allow for easy insertion
into the adhesive-filled hole. Anchor rods shall be
manufactured to meet the following requirements: 1. ISO
898 Class 5.8 2. ASTM A 193, Grade B7 (high strength
carbon steel anchor); 3. AISI 304 or AISI 316 stainless
steel, meeting the requirements of ASTM F 593
(condition CW).
Fastener Components
HAS Threaded Rod
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
95
4.2.4
HY 150
HIT-ICE
71.8 MPa
10,420 psi
72 MPa
10,440 psi
15.9 MPa
2310 psi
12 MPa
1740 psi
29.3 MPa
4250 psi
7032 MPa
0.12%
0.12%
2.4%
2.4%
2x1011 OHM/cm
5.1x1011 OHM/in.
2x1011OHM/in.
5.1x1011OHM/in.
Standard HAS-E rod material meets the requirements of ISO 898 Class 5.8
Mechanical Properties
fy
min. fu
ksi (MPa)
ksi (MPa)
58 (400)
72.5 (500)
High Strength or Super HAS rod material meets the requirements of ASTM A 193, Grade B7
105 (724)
125 (862)
Stainless HAS rod material meets the requirements of ASTM F 593 (AISI 304/316) Condition CW 3/8" to 5/8"
65 (448)
100 (689)
Stainless HAS rod material meets the requirements of ASTM F 593 (AISI 304/316) Condition CW 3/4" to 1-1/4"
45 (310)
85 (586)
Material
54.4 (375)
66.7 (460)
50.8 (350)
101.5 (700)
HAS Super & HAS-E Standard Nut material meets the requirements of ASTM A 563, Grade DH
HAS Stainless Steel Nut material meets the requirements of ASTM F 594
HAS Standard and Stainless Steel Washers meet dimensional requirements of ANSI B18.22.1 Type A Plain
HAS Stainless Steel Washers meet the requirements of AISI 304 or AISI 316 conforming to ASTM A 240
HAS Super & HAS-E Standard Washers meet the requirements of ASTM F 436
All HAS Super Rods (except 7/8") & HAS-E Standard, HIS inserts, nuts & washers are zinc plated to ASTM B 633 SC 1
7/8" HAS Super rods hot-dip galvanized in accordance with ASTM A 153
Note: Special Order threaded rods may vary from standard materials.
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
7/8
(22.2)
1
(25.4)
1-1/4
(31.8)
in.
7/16
9/16
11/16
13/16
15/16
1-1/16
1-1/2
in.
(mm)
3-1/2
(90)
4-1/4
(110)
5
(125)
6-5/8
(170)
7-1/2
(190)
8-1/4
(210)
12
(305)
hef hnom
ft lb
(Nm)
18
(24)
30
(41)
75
(102)
150
(203)
175
(237)
235
(319)
400
(540)
ft lb
(Nm)
15
(20)
20
(27)
50
(68)
105
(142)
125
(169)
165
(224)
280
(375)
hef = hnom
minimum
base material
thickness4
in.
(mm)
5-1/2
(140)
6-1/4
(160)
7
(180)
8-1/2
(220)
9-1/2
(240)
10-1/2
(270)
15
(380)
hef hnom
in.
(mm)
Details
dbit
bit diameter1, 2
hef = hnom
std. depth of embed.3
Tmax
max.
tighening
torque
All
Hilti
1.0 hef+ 1.0 hef+ 1.0 hef+ 1.0 hef+ 1.0 hef+ 1.0 hef+ 1.0 hef+
2
2
2
2
2
2-1/4
3
(51)
(51)
(51)
(51)
(51)
(57)
(76)
50/45
31/28
18/16
10/9
8/7
6/5
2/2
236
145
85
45
38
29
dbit
Tmax
t
hef
h
www.us.hilti.com US
www.ca.hilti.com Canada
96
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
in.
(mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
in.
11/16
7/8
1-1/8
1-1/4
dbit
bit diameter1
hnom
std. depth
of embed.
in.
(mm)
4-1/4
(110)
5
(125)
6-5/8
(170)
8-1/4
(210)
th
useable thread
length
in.
(mm)
1
(25)
1-3/16
(30)
1-1/2
(40)
2
(50)
Tmax
Max. tightening
torque
ft lb
(Nm)
18
(24)
35
(47)
80
(108)
160
(217)
in.
(mm)
6-3/8
(162)
7-1/2
(191)
10
(254)
12-3/8
(314)
Recommended Hilti
Rotary Hammer Drill
TE 5, 15, TE 18-M,
18-M, 25 25, 55, 76
dbit
Tmax
hhef
nom
TE-55, 76
1 For Hilti matched tolerance carbide tipped drill bits, see section 8.4.1.
No. 3
No. 4
No. 5
No. 6
No. 7
No. 8
No. 9
No. 10
No. 11
1/2
5/8
3/4
7/8
1-1/8
1-3/8
1-1/2
1-9/16
Details
bit diameter1, 2
dbit:
in.
1 Rebar diameters may vary. Use smallest drill bit which will accommodate rebar.
2 Use Hilti matched tolerance carbide tipped drill bits, see section 8.4.1.
10M
15M
20M
25M
30M
35M
14 mm
3/4"
24mm
1-1/8"
37mm
1-9/16"
1 Rebar diameters may vary. Use smallest drill bit which will accommodate rebar.
2 For Hilti matched tolerance carbide tipped drill bits, see section 8.4.1.
( NN )
d
rec
5/3
( VV )
d
rec
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
97
4.2.4
HIT HY 150/HIT-ICE Allowable and Ultimate Bond/Concrete Capacity for HAS Rods in Normal Weight Concrete1,2,3
HIT HY-150/HIT-ICE Allowable Bond/Concrete Capacity
Tensile
Shear
Anchor Embedment
Diameter
Depth
in (mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
7/8
(22.2)
1
(25.4)
1-1/4
(31.8)
in (mm)
fc = 2000 psi
(13.8 MPa)
lb (kN)
fc = 4000 psi
(27.6 MPa)
lb (kN)
fc = 2000 psi
(13.8 MPa)
lb (kN)
fc = 4000 psi
(27.6 MPa)
lb (kN)
fc = 2000 psi
(13.8 MPa)
lb (kN)
fc = 4000 psi
(27.6 MPa)
lb (kN)
fc = 2000 psi
(13.8 MPa)
lb (kN)
fc = 4000 psi
(27.6 MPa)
lb (kN)
1-3/4
(44)
3-1/2
(89)
5-1/4
(133)
2-1/8
(54)
4-1/4
(108)
6-3/8
(162)
2-1/2
(64)
5
(127)
7-1/2
(191)
3-3/8
(86)
6-5/8
(168)
10
(254)
3-3/4
(95)
7-1/2
(191)
11-1/4
(286)
4-1/8
(105)
8-1/4
(210)
12-3/8
(314)
6
(152)
12
(305)
15
(381)
720
(3.2)
1895
(8.4)
2635
(11.7)
1220
(5.4)
2725
(12.1)
4300
(19.1)
1620
(7.2)
4395
(19.6)
6025
(26.8)
2365
(10.5)
4655
(20.7)
9515
(42.3)
3080
(13.7)
7845
(34.9)
13330
(59.3)
3445
(15.3)
8330
(37.1)
15540
(69.1)
4645
(20.7)
15490
(68.9)
19210
(85.5)
1265
(5.6)
2705
(12.0)
2800
(12.5)
1575
(7.0)
3935
(17.5)
5295
(23.6)
1985
(8.8)
5250
(23.4)
8225
(36.6)
3925
(17.5)
8885
(39.5)
12140
(54.0)
4800
(21.4)
11020
(49.0)
16645
(74.0)
4865
(21.6)
11635
(51.8)
19525
(86.85)
7000
(31.1)
20770
(92.4)
26815
(119.3)
1390
(6.2)
3435
(15.3)
6485
(30.4)
1980
(8.8)
5210
(23.2)
10380
(46.2)
2460
(10.9)
7345
(32.7)
14630
(65.1)
5430
(24.2)
12515
(55.7)
25200
(112.1)
6700
(29.8)
16185
(72.0)
32245
(143.4)
8260
(36.7)
19810
(88.1)
39465
(175.5)
14760
(65.7)
40045
(178.1)
58520
(260.3)
1965
(8.7)
4860
(21.6)
9680
(43.1)
2800
(12.5)
7370
(32.8)
14680
(65.3)
3480
(15.5)
10385
(46.2)
20690
(92.0)
7680
(34.2)
17700
(78.7)
35640
(158.5)
9475
(42.1)
22890
(101.8)
45600
(202.8)
11680
(52.0)
28015
(124.6)
55810
(248.3)
20870
(92.8)
56635
(251.9)
82760
(368.1)
2710
(12.1)
7120
(31.7)
9880
(44.0)
4580
(20.4)
10220
(44.5)
16140
(71.8)
6090
(27.1)
16480
(73.3)
22595
(100.5)
8870
(39.5)
17460
(77.7)
35695
(158.8)
11555
(51.4)
29430
(130.9)
49990
(222.4)
12920
(57.5)
31250
(139.0)
58280
(259.3)
17430
(77.5)
58085
(258.4)
72040
(320.5)
4750
(21.1)
10160
(45.2)
10510
(46.8)
5910
(26.3)
14760
(65.7)
19860
(88.3)
7460
(33.2)
19690
(87.6)
30850
(137.2)
14720
(65.5)
33330
(148.3)
45530
(202.5)
18000
(80.1)
41000
(182.3)
62425
(277.7)
18250
(81.2)
43640
(194.1)
73220
(325.7)
26265
(116.8)
77900
(346.5)
100560
(447.3)
4175
(18.6)
10305
(45.8)
20535
(91.3)
5940
(26.4)
15630
(69.5)
31140
(138.5)
7380
(32.8)
22030
(98.0)
43890
(195.2)
16295
(72.5)
37545
(167.0)
75600
(336.3)
20105
(89.4)
48550
(216.0)
96730
(430.3)
24790
(110.3)
59425
(264.3)
118395
(526.6)
44280
(197.0)
120140
(534.4)
175560
(780.9)
5900
(26.2)
14575
(64.8)
29040
(129.2)
8400
(37.4)
22105
(98.3)
44040
(195.9)
10440
(46.4)
31155
(138.6)
62070
(276.1)
23040
(102.5)
53095
(236.2)
106915
(475.6)
28430
(126.5)
68665
(305.4)
136800
(608.5)
35050
(155.9)
84040
(373.8)
167435
(744.8)
62610
(278.5)
169900
(755.8)
248285
(1104.4)
2 For hef hnom average ultimate concrete shear capacity based on Concrete Capacity Design (CCD) method.
For hef < hnom average ultimate concrete shear values
based on testing.
www.us.hilti.com US
www.ca.hilti.com Canada
98
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
HAS Super
ASTM A 193 B7
HAS SS
AISI 304/316 SS
Rod
Diameter
in. (mm)
Tensile
lb (kN)
Shear
lb (kN)
Tensile
lb (kN)
Shear
lb (kN)
Tensile
lb (kN)
Shear
lb (kN)
3/8
(9.5)
2640
(11.7)
1360
(6.0)
4555
(20.3)
2345
(10.4)
3645
(16.2)
1875
(8.3)
1/2
(12.7)
4700
(20.9)
2420
(10.8)
8100
(36.0)
4170
(18.5)
6480
(28.8)
3335
(14.8)
5/8
(15.9)
7340
(32.7)
3780
(16.8)
12655
(56.3)
6520
(29.0)
10125
(45.0)
5215
(23.2)
3/4
(19.1)
10570
(47.0)
5445
(24.2)
18225
(81.1)
9390
(41.8)
12390
(55.1)
6385
(28.4)
7/8
(22.2)
14385
(64.0)
7410
(33.0)
24805
(110.3)
12780
(56.9)
16865
(75.0)
8690
(38.6)
1
(25.4)
18790
(83.6)
9680
(43.0)
32400
(144.1)
16690
(74.2)
22030
(98.0)
11350
(50.5)
1-1/4
(31.8)
29360
(130.6)
15125
(67.3)
50620
(225.2)
26080
(116.0)
34425
(153.1)
17735
(78.9)
HAS Super
ASTM A 193 B7
Yield
Tensile
lb (kN)
lb (kN)
Shear
lb (kN)
HAS SS
AISI 304/316 SS
Yield
Tensile
Shear
lb (kN)
lb (kN)
lb (kN)
3/8
(9.5)
4495
(20.0)
6005
(26.7)
3605
(16.0)
8135
(36.2)
10350
(43.4)
6210
(27.6)
5035
(22.4)
8280
(36.8)
4970
(22.1)
1/2
(12.7)
8230
(36.6)
10675
(47.5)
6405
(28.5)
14900
(66.3)
18405
(79.0)
11040
(49.1)
9225
(41.0)
14720
(65.5)
8835
(39.3)
5/8
(15.9)
13110
(58.3)
16680
(74.2)
10010
(44.2)
23730
(105.6)
28760
(125.7)
17260
(76.8)
14690
(65.3)
23010
(102.4)
13805
(61.4)
3/4
(19.1)
19400
(86.3)
24020
(106.9)
14415
(64.1)
35120
(156.2)
41420
(185.7)
24850
(110.5)
15050
(66.9)
28165
(125.3)
16800
(75.2)
7/8
(22.2)
26780
(119.1)
32695
(145.4)
19620
(87.3)
48480
(215.7)
56370
(256.9)
33825
(150.5)
20775
(92.4)
38335
(170.5)
23000
(102.3)
1
(25.4)
35130
(156.3)
42705
(190.0)
25625
(114.0)
63600
(282.9)
73630
(337.0)
44180
(196.5)
27255
(121.2)
50070
(222.7)
30040
(133.6)
1-1/4
(31.8)
56210
(250.0)
66730
(296.8)
40035
(178.1)
101755
(452.6)
115050
(511.8)
69030
(307.1)
43610
(194.0)
78235
(348.0)
46940
(208.8)
Rod
Diameter
in. (mm)
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
99
4.2.4
Anchor
Diameter
in. (mm)
Embedment
Depth
in. (mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
4-1/4
(108)
5
(127)
6-5/8
(168)
8-1/4
(210)
2750
(12.2)
4195
(18.7)
6700
(29.8)
7855
(34.9)
1605
(7.1)
3040
(13.5)
4575
(20.4)
6305
(28.0)
ASTM F 593
Stainless Steel
Tensile1
Shear1
lb (kN)
lb (kN)
4370
(19.4)
7775
(34.6)
12150
(54.0)
17495
(77.8)
3645
(16.2)
6480
(28.8)
10125
(45.0)
12395
(55.1)
2250
(10.0)
4005
(17.8)
6260
(27.8)
9010
(40.1)
1875
(8.3)
3335
(14.8)
5215
(23.2)
6385
(28.4)
Anchor
Diameter
in. (mm)
Embedment
Depth
in. (mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
4-1/4
(108)
5
(127)
6-5/8
(168)
8-1/4
(210)
11000
(48.9)
16790
(74.7)
26795
(119.2)
31430
(139.8)
6425
(28.6)
12170
(54.1)
18310
(81.5)
25215
(112.2)
ASTM F 593
Stainless Steel
Tensile1
Shear1
lb (kN)
lb (kN)
9935
(44.2)
17665
(78.6)
27610
(122.8)
39760
(176.9)
8280
(36.8)
14720
(65.5)
23010
(102.4)
28165
(125.3)
5960
(26.5)
10600
(47.2)
16565
(73.7)
23855
(106.1)
4970
(22.1)
8835
(39.3)
13805
(61.4)
16900
(75.1)
www.us.hilti.com US
www.ca.hilti.com Canada
100
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
HIT HY 150/HIT-ICE Allowable and Ultimate Bond/Concrete Capacity for HAS Rods
Installed in Lightweight Concrete 3000 psi (207 MPa)
Anchor
Diameter
in. (mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.9)
3/4
(19.1)
Embedment
Depth
in. (mm)
1-3/4
(44)
3-1/2
(89)
2-1/8
(54)
4-1/4
(108)
2-1/2
(63)
3-3/8
(86)
1 Influence factors for spacing and/or edge distance are applied to allowable
concrete/bond values above, and then compared to the allowable steel value (See
page 99). The lesser of these values is to be used for design.
2 All values based on holes drilled with matched tolerance carbide tipped bit (see section 8.4.1) and cleaned with a wire brush.
Embedment
Depth
in. (mm)
1/2 (12.7)
4-1/4 (108.0)
5/8 (15.9)
5 (127.0)
Edge
Distance
in. (mm)
1-3/4 (44.5)
2-3/4 (69.9)
1-3/4 (44.5)
2-3/4 (69.9)
Shear lb (kN)
Tension
lb (kN)
1280 (5.3)
1800 (8.1)
1700 (7.6)
2725 (12.1)
Load II to Edge
1445 (6.4)
2100 (9.5)
1445 (6.4)
2455 (10.9)
Load to Edge
400 (1.8)
845 (3.8)
400 (1.8)
960 (4.3)
Allowable Loads for Attachment of Sill Plates to top of grout filled block wall with HIT HY 150/HIT-ICE1
Anchor
Diameter
in. (mm)
Embedment
Depth
in. (mm)
1/2 (12.7)
4-1/4 (108.0)
5/8 (15.9)
5 (127.0)
Edge
Distance
in. (mm)
1-3/4 (44.5)
2-3/4 (69.9)
1-3/4 (44.5)
2-3/4 (69.9)
Shear lb (kN)
Tension
lb (kN)
1395 (6.2)
1795 (8.0)
1840 (8.2)
1965 (8.7)
Load II to Edge
1425 (6.3)
2085 (9.3)
1800 (8.0)
3070 (13.7)
Load to Edge
560 (2.5)
1110 (4.9)
680 (3.0)
1110 (4.9)
1 Loads are based on concrete or masonry failure. Steel strength must be checked separately. Values based on safety factor of 4.0
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
101
4.2.4
HIT HY 150/HIT-ICE Allowable Loads for Threaded Rods in Grout-Filled Concrete Masonry Units
(ASTM C 90 Block)1, 2, 3, 4
Anchor Diameter
in.
(mm)
Embedment Depth
in. (mm)
3/8
( 9.5 )
3-1/2 ( 88.9 )
1/2
(12.7)
4-1/4 ( 108 )
5/8
(15.9)
3/4
(19.1)
( 127 )
6-5/8 (168.3)
4
_>12
4
_>12
4
_>12
4
_>12
Shear lb (kN)5
Tension5
lb
(kN)
HAS-E
HAS Super
HAS SS
1550
( 6.9 )
1360
( 6.0)
2345
(10.4)
1875
( 8.3)
1785
( 7.9 )
2020
2420
( 9.0)
(10.8)
2020
4170
( 9.0)
(18.5)
2020
3335
( 9.0)
(14.8)
2265
(10.1)
3740
(16.6)
2220
3780
2020
5445
( 9.0)
(16.8)
( 9.0)
(24.2)
2020
5625
2020
5625
( 9.0)
(25.0)
( 9.0)
(25.0)
2020
5215
2020
5625
( 9.0)
(23.2)
( 9.0)
(25.0)
HIT HY 150/HIT-ICE Ultimate Loads for Threaded Rods in Grout-Filled Concrete Masonry Units
(ASTM C 90 Block)1, 2, 3, 4
Anchor Diameter
in.
(mm)
Embedment Depth
in. (mm)
Tension lb (kN)5
HAS-E
HAS Super
HAS SS (304SS)
Shear lb (kN)5
HAS-E
HAS Super
HAS SS
3/8
(9.5)
3-1/2
(88.9)
4
_>12
(101.6)
(304.8)
(27.6) 4970
(22.1)
(35.9)
4-1/4
(108)
(101.6)
(304.8)
(35.9) 8075
(12.7)
4
_>12
8075
1/2
5/8
(15.9)
3/4
(19.1)
(127)
6-5/8 (168.3)
4
_>12
(101.6)
(304.8)
4
_>12
(101.6)
(304.8)
(35.9) 8075
(39.3)
(35.9)
1 Values are for lightweight, medium weight or normal weight concrete masonry units
3 Values are for anchors located in the grouted cell, head joint, bed joint, T joint,
cross web or any combination of the above.
(35.9) 8075
(35.9)
4 Values for edge distances between 4 inches and 12 inches can be calculated by
linear interpolation.
5 Loads are based on the lesser of bond strength, steel strength or base material
strength.
www.us.hilti.com US
www.ca.hilti.com Canada
102
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
in.
(mm)
3/8
(9.5)
1/2
(12.7)
5/8
(15.8)
3/4
(19.1)
hnom
in.
(mm)
31/2
(90)
41/4
(110)
5
(125)
65/8
(170)
s
V
c
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
103
4.2.4
HIT HY 150/HIT-ICE Ultimate Bond Strength and Steel Strength for Rebar in Concrete
Concrete Compressive Strength
fc = 2000 psi (13.8 MPa)
Nominal
Rebar
Size
Embed.
Depth
in. (mm)
#3
1-1/2
(38)
3-1/2
(89)
7
(178)
2500
(11.1)
6300
(28.0)
12600
(56.0)
#4
2
(51)
4
(102)
8
(203)
4200
(18.7)
9000
(40.0)
18000
(80.1)
#5
2-1/2
(64)
5
(127)
10
(254)
5600
(24.9)
13500
(60.1)
27000
(120.1)
#6
3-1/2
(90)
7
(178)
14
(356)
10200
(45.4)
22100
(98.3)
44200
(196.6)
#7
3-3/4
(95)
7-1/2
(190)
15
(380)
10700
(47.6)
27100
(120.6)
54200
(241.1)
#8
4
(102)
8
(204)
16
(408)
14100
(62.7)
32500
(144.6)
65000
(289.1)
#9
5
(127)
10
(254)
18
(457)
16700
(74.3)
47400
(210.9)
85300
(379.4)
#10
6
(152)
12
(304)
20
(508)
23300
(103.6)
59600
(265.1)
99300
(441.7)
#11
7
(178)
14
(356)
20
(508)
32000
(142.3)
75800
(337.2)
108400
(482.2)
Ultimate
Bond
Strength
lb (kN)
Embed. to
Embed. to
Develop Yield Develop Tensile
Strength1
Strength1
in. (mm)
in. (mm)
3-3/4
(95.3)
5-1/2
(139.7)
7
(177.8)
8-1/2
(215.9)
10
(254.0)
11-3/4
(298.5)
12-3/4
(323.9)
15-1/2
(393.7)
17-1/4
(438.2)
Grade 60 Rebar
Embed. to
Embed. to
Yield
Develop Yield Develop Tensile Strength
Strength1
Strength1
lb (kN)
in. (mm)
in. (mm)
Tensile
Strength
lb (kN)
5-1/2
(139.7)
3800
(16.9)
8200
(36.5)
16500
(73.4)
2-3/4
(69.9)
4-1/4
(108.0)
6600
(29.4)
9900
(44.0)
8
(203.2)
6000
(26.7)
11800
(52.5)
23600
(105.0)
4-1/4
(108.0)
6-1/4
(158.8)
12000
(53.4)
18000
(80.1)
10-1/4
(260.4)
6900
(30.7)
17700
(78.7)
35300
(157.0)
5-1/4
(133.4)
8
(203.2)
18600
(82.7)
27900
(124.1)
12-3/4
(323.9)
12800
(56.9)
28900
(128.6)
57700
(256.7)
6-1/2
(165.1)
9-3/4
(247.7)
26400
(117.4)
39600
(176.2)
15
(381)
15800
(70.3)
35300
(157.0)
70700
(314.5)
7-3/4
(196.9)
11-1/2
(292.1)
36000
(160.1)
54000
(240.2)
17-1/2
(444.5)
18100
(80.5)
42400
(188.6)
84800
(377.2)
9
(228.6)
13-1/2
(342.9)
47450
(211.1)
71100
(316.3)
19
(482.6)
21800
(97.0)
61800
(274.9)
111300
(495.1)
10
(254.0)
15-3/4
(400.1)
60000
(266.9)
90000
(400.4)
23
(584.2)
32400
(144.1)
77700
(345.6)
129600
(576.5)
12
(304.8)
17-3/4
(450.9)
76200
(339.0)
114300
(508.5)
26
(660.4)
41300
(183.7)
99000
(440.4)
141400
(629.0)
13-1/2
(342.9)
20
(508.0)
93600
(416.4)
140400
(624.6)
1 Based on comparison of average ultimate adhesive bond test values versus minimum yield and ultimate tensile strength of rebar; for more information, contact Hilti.
104
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
HIT HY 150/HIT-ICE Bond Strength and Steel Strength for Metric Rebar in Concrete (Canada Only)1, 4, 5
Strength Properties of Metric Rebar 2, 3
f y = 400 MPa
Embedment
Depth
(mm)
Ultimate
Bond
(kN)
Allowable
Bond
(kN)
Ultimate
Bond
(kN)
Allowable
Bond
(kN)
Yield
Strength
(kN)
Tensile
Strength
(kN)
10M
(#3)
40
90
180
11.1
28.0
56.0
2.8
7.0
14.0
16.9
36.5
73.4
4.2
9.1
18.3
40
60
15M
(#5)
65
130
250
24.9
60.1
120
6.2
15.0
30.0
30.7
78.7
157
7.7
19.7
39.2
80
120
20M
(#6)
90
180
355
45.4
98.3
197
11.3
24.6
49.2
56.9
129
257
14.2
32.2
64.2
120
180
25M
(#8)
100
200
405
62.7
145
289
15.7
36.2
72.2
80.5
189
377
20.1
47.2
94.2
200
300
30M
(#9)
125
250
455
74.3
211
379
18.6
52.8
94.8
97.0
275
495
24.2
68.8
124
280
420
35M
(#11)
180
355
510
142
337
482
35.5
84.2
120
184
440
629
46.0
110
157
400
600
1 For anchoring to grout-filled block or bond beams, please refer to page 102 of this
HIT HY 150/HIT-ICE Injection Adhesive System section.
4 Test data developed for hammer-drilled holes. For diamond cored holes, contact
Hilti Engineering.
2 Use lesser value of bond strength or rebars steel strength for tensile capacity.
5 For anchoring spacing and edge distance guidelines, please refer to page 106 of
this HIT HY 150/HIT-ICE Injection Adhesive Anchor section.
3 Actual tensile bond test data developed for imperial-sized rebar. Yield and ultimate
rebar strengths are for metric sizes.
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
105
4.2.4
Anchor Spacing and Edge Distance Guidelines in Concrete for HIT HY 150/HIT-ICE
s = Actual spacing
s
V
scr
1.5
ccr
2.0
Shear ( to Edge)
Note: Tables apply for listed embedment
depths. Reduction factors for
other embedment depths must be
calculated using equations below.
1.5
1.0
s
hef
smin
0.5
1.0
c
hef
Spacing Tension/Shear
smin = 0.5 hef, scr = 1.5 hef
fA = 0.3(s/hef) + 0.55
for scr>s>smin
ccr
0.5
0
.2
.4
.6
.8
1.0
Tension
cmin
.6
.2
.4
.8
1.0
Edge Distance Adjustment Factor
(fRV, fRN)
7/8
1-1/4
1-3/4
2
2-5/8
3
3-1/2
4
4-1/2
5-1/4
6-1/2
7
7-7/8
9
10-1/2
3/8" diameter
Spacing
Tension/Shear,
fA
Edge Distance
Tension,
fRN
1-3/4 3-1/2 5-1/4 1-3/4 3-1/2 5-1/4 1-3/4 3-1/2 5-1/4 1-3/4
0.70
0.76
0.85 0.70
0.89 0.72
1.00 0.78 0.70
0.81 0.72
0.85 0.75
0.89 0.78
0.94 0.81
1.00 0.85
0.92
0.95
1.00
0.60
0.69
0.80 0.60
0.86 0.63
1.00 0.70 0.60
0.74 0.63
0.80 0.67
0.86 0.70
0.91 0.74
1.00 0.80
0.90
0.93
1.00
0.18
0.30
0.45
0.53
0.72
0.84
1.00
0.46
0.54
0.18
0.64
0.22
0.69
0.32 0.18 0.82
0.37 0.22 0.90
0.45 0.27 1.00
0.53 0.32
0.60 0.37
0.72 0.45
0.91 0.58
1.00 0.63
0.72
0.84
1.00
fRVII
3-1/2 5-1/4
0.46
0.49
0.55
0.59
0.64
0.69
0.74
0.82
0.95
1.00
0.46
0.49
0.52
0.55
0.59
0.64
0.73
0.76
0.82
0.90
1.00
www.us.hilti.com US
www.ca.hilti.com Canada
106
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
Note: Tables apply for listed embedment
depths. Reduction factors for
other embedment depths must be
calculated using equations below.
Embedment
Depth, in.
1-1/16
1-1/2
2
2-1/8
2-3/4
3
3-3/16
4
4-1/4
5
6
6-3/8
7
7-1/2
8-1/2
9
9-9/16
10
11
12-3/4
1/2" diameter
Spacing
Tension/Shear,
fA
Edge Distance
Tension,
fRN
2-1/8 4-1/4 6-3/8 2-1/8 4-1/4 6-3/8 2-1/8 4-1/4 6-3/8 2-1/8
0.70
0.76
0.83
0.85
0.94
0.97
1.00
0.70
0.74
0.76
0.78
0.83
0.85
0.90
0.97
1.00
0.60
0.68
0.78
0.80
0.92
0.96
0.70 1.00
0.74
0.75
0.79
0.83
0.85
0.88
0.90
0.95
0.97
1.00
0.18
0.29
0.42
0.60
0.45
0.66
0.61
0.68
0.67
0.70 0.60 0.72
0.78 0.65 0.93
0.80 0.67 1.00
0.87 0.71
0.96 0.78
1.00 0.80
0.84
0.87
0.93
0.96
1.00
Spacing Tension/Shear
0.46
0.53
0.62
0.18
0.64
0.26
0.75
0.29
0.79
0.32 0.18 0.82
0.42 0.25 0.96
0.45 0.27 1.00
0.55 0.33
0.67 0.42
0.72 0.45
0.80 0.50
0.86 0.55
1.00 0.63
0.67
0.72
0.76
0.84
1.00
4-1/4 6-3/8
0.46
0.51
0.52
0.56
0.62
0.64
0.68
0.70
0.76
0.79
0.82
0.84
0.90
1.00
5/8" diameter
Spacing
Edge Distance
Spacing
Edge Distance
Tension/Shear,
Tension,
( toward edge),
Tension/Shear,
Tension,
( toward edge),
fA
Embedment
Depth, in.
1-1/4
1-11/16
2
2-1/2
3
3-5/16
3-3/4
4
4-1/2
5
5-1/16
5-1/2
6
6-3/4
7-1/2
8
8-1/2
9
9-15/16
10
11-1/4
12
13-1/4
14
15
16
18
20
2-1/2
0.70
0.75
0.79
0.85
0.91
0.95
1.00
3/4" diameter
0.70
0.73
0.75
0.78
0.79
0.82
0.85
0.85
0.88
0.91
0.96
1.00
fRN
7-1/2 2-1/2
0.60
0.67
0.72
0.80
0.88
0.93
0.70 1.00
0.71
0.73
0.75
0.75
0.77
0.79
0.82
0.85
0.87
0.89
0.91
0.95
0.95
1.00
0.60
0.64
0.67
0.70
0.72
0.76
0.80
0.81
0.84
0.88
0.94
1.00
fRV
7-1/2 2-1/2
0.60
0.61
0.64
0.67
0.67
0.69
0.72
0.76
0.80
0.83
0.85
0.88
0.93
0.93
1.00
0.18
0.27
0.34
0.45
0.56
0.63
0.72
0.77
0.88
1.00
0.18
0.23
0.27
0.32
0.34
0.40
0.45
0.46
0.50
0.56
0.64
0.72
0.77
0.83
0.88
0.98
1.00
fRVII
7-1/2 2-1/2
0.18
0.20
0.23
0.27
0.27
0.31
0.34
0.40
0.45
0.49
0.52
0.56
0.63
0.63
0.72
0.77
0.86
0.92
1.00
0.46
0.52
0.57
0.64
0.71
0.76
0.82
0.86
0.93
1.00
0.46
0.50
0.52
0.55
0.57
0.60
0.64
0.64
0.68
0.71
0.77
0.82
0.86
0.89
0.93
1.00
fA
7-1/2 3-3/8 6-5/8
0.46
0.47
0.50
0.52
0.52
0.54
0.57
0.60
0.64
0.66
0.69
0.71
0.76
0.76
0.82
0.86
0.92
0.95
1.00
0.70
0.73
0.77
0.82
0.84
0.88
0.91
0.95
0.99
1.00
fRN
10
3-3/8 6-5/8
0.60
0.64
0.70
0.76
0.70
0.79
0.72
0.84
0.73
0.87
0.75
0.93
0.78 0.70 0.99
0.78 0.70 1.00
0.80 0.72
0.82 0.73
0.86 0.75
0.89 0.78
0.91 0.79
0.93 0.81
0.96 0.82
1.00 0.85
0.85
0.89
0.91
0.95
0.97
1.00
0.60
0.63
0.64
0.67
0.70
0.71
0.73
0.76
0.81
0.85
0.88
0.91
0.94
1.00
fRV
10
0.60
0.60
0.62
0.64
0.67
0.70
0.72
0.74
0.76
0.80
0.80
0.85
0.88
0.93
0.96
1.00
3-3/8 6-5/8
0.18
0.23
0.31
0.39
0.44
0.51
0.55
0.63
0.71
0.72
0.79
0.87
1.00
0.18
0.22
0.24
0.28
0.32
0.32
0.36
0.40
0.46
0.52
0.56
0.60
0.64
0.72
0.73
0.83
0.89
1.00
fRVII
10
0.18
0.18
0.21
0.23
0.27
0.32
0.34
0.37
0.40
0.45
0.45
0.52
0.56
0.63
0.67
0.72
0.77
0.88
1.00
3-3/8 6-5/8
0.46
0.49
0.55
0.60
0.63
0.68
0.71
0.76
0.81
0.82
0.87
0.92
1.00
0.46
0.48
0.50
0.52
0.55
0.56
0.58
0.61
0.65
0.69
0.71
0.74
0.77
0.82
0.82
0.89
0.93
1.00
10
0.46
0.46
0.48
0.50
0.52
0.55
0.57
0.59
0.60
0.64
0.64
0.69
0.71
0.76
0.78
0.82
0.93
1.00
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
107
4.2.4
Embedment
Depth, in.
1-7/8
2-1/2
3
3-3/4
4
4-1/2
5
5-5/8
6
6-1/2
7
7-1/2
8
8-1/2
9
9-15/16
10
11-1/4
12
14
15
16-7/8
18
20
22-1/2
7/8" diameter
Spacing
Tension/Shear,
fA
Edge Distance
Tension,
fRN
fRVII
3-3/4 7-1/2 11-1/4 3-3/4 7-1/2 11-1/4 3-3/4 7-1/2 11-1/4 3-3/4
0.70
0.75
0.79
0.85
0.87
0.91
0.95
1.00
0.70
0.71
0.73
0.75
0.78
0.79
0.81
0.83
0.85
0.87
0.89
0.91
0.95
0.95
1.00
0.60
0.67
0.72
0.80
0.83
0.88
0.93
0.70 1.00
0.71
0.72
0.74
0.75
0.76
0.78
0.79
0.82
0.82
0.85
0.87
0.92
0.95
1.00
0.60
0.61
0.64
0.67
0.70
0.72
0.75
0.77
0.80
0.83
0.85
0.88
0.93
0.93
1.00
0.60
0.61
0.63
0.65
0.67
0.68
0.70
0.72
0.75
0.76
0.80
0.83
0.90
0.93
1.00
0.18
0.27
0.34
0.45
0.49
0.56
0.63
0.72
0.77
0.85
0.92
1.00
0.18
0.20
0.23
0.27
0.32
0.34
0.38
0.41
0.45
0.49
0.52
0.56
0.63
0.63
0.72
0.77
0.92
1.00
0.18
0.20
0.22
0.25
0.27
0.29
0.32
0.34
0.39
0.39
0.45
0.49
0.58
0.63
0.72
0.77
0.87
1.00
0.46
0.52
0.57
0.64
0.66
0.71
0.76
0.82
0.86
0.90
0.95
1.00
Spacing Tension/Shear
7-1/2 11-1/4
0.46
0.47
0.49
0.50
0.52
0.54
0.55
0.57
0.60
0.60
0.64
0.66
0.73
0.76
0.82
0.86
0.92
1.00
Embedment
Depth, in.
108
2-1/16
3
3-1/2
4-1/8
5
5-1/2
6
6-3/16
7-1/2
8-1/4
9
9-1/2
10
10-1/2
12
12-3/8
14
16-1/2
18
18-9/16
20
22-1/2
24
24-3/4
26
28
30
1" diameter
1 1/4" diameter
Spacing
Edge Distance
Spacing
Edge Distance
Tension/Shear,
Tension,
( toward edge),
Tension/Shear,
Tension,
( toward edge),
fA
fRN
fRV
4-1/8 8-1/4 12-3/8 4-1/8 8-1/4 12-3/8 4-1/8 8-1/4 12-3/8 4-1/8
0.70
0.77
0.80
0.85
0.91
0.95
0.99
1.00
0.70
0.73
0.75
0.77
0.78
0.82
0.85
0.88
0.90
0.91
0.93
0.99
1.00
0.60
0.69
0.74
0.80
0.88
0.93
0.98
0.70 1.00
0.73
0.75
0.77
0.78
0.79
0.80
0.84
0.85
0.89
0.95
0.99
1.00
0.18
0.30
0.37
0.60
0.45
0.64
0.56
0.67
0.63
0.69
0.70
0.70 0.60 0.72
0.76 0.64 0.89
0.80 0.67 1.00
0.84 0.69
0.86 0.71
0.88 0.72
0.91 0.74
0.98 0.79
1.00 0.80
0.85
0.93
0.98
1.00
0.46
0.54
0.59
0.18
0.64
0.24
0.72
0.27
0.76
0.30
0.80
0.32 0.18 0.82
0.40 0.24 0.93
0.45 0.27 1.00
0.50 0.30
0.53 0.32
0.56 0.35
0.60 0.37
0.70 0.43
0.72 0.45
0.83 0.52
1.00 0.63
0.70
0.72
0.78
0.89
0.96
1.00
fRVII
fA
8-1/4 12-3/8
0.46
0.50
0.52
0.54
0.55
0.61
0.64
0.67
0.69
0.72
0.74
0.80
0.82
0.89
1.00
0.46
0.50
0.52
0.54
0.56
0.57
0.59
0.63
0.64
0.69
0.76
0.80
0.82
0.86
0.93
0.98
1.00
0.70
0.73
0.76
0.80
0.83
0.85
0.86
0.93
0.96
1.00
12
fRN
15
0.60
0.63
0.68
0.73
0.77
0.70
0.80
0.70
0.81
0.74 0.70 0.90
0.76 0.72 0.95
0.78 0.73 1.00
0.79 0.74
0.80 0.75
0.81 0.76
0.85 0.79
0.86 0.80
0.90 0.83
0.96 0.88
1.00 0.91
0.92
0.95
1.00
12
0.60
0.61
0.65
0.68
0.70
0.72
0.73
0.75
0.80
0.81
0.87
0.95
1.00
fRV
15
0.60
0.62
0.64
0.65
0.67
0.68
0.72
0.73
0.77
0.84
0.88
0.90
0.93
1.00
0.18
0.23
0.28
0.36
0.41
0.45
0.47
0.59
0.65
0.72
0.77
0.81
0.86
1.00
12
0.18
0.19
0.25
0.28
0.32
0.34
0.36
0.38
0.45
0.47
0.54
0.65
0.72
0.75
0.81
0.92
1.00
fRVII
15
0.18
0.21
0.23
0.25
0.27
0.29
0.34
0.36
0.41
0.50
0.56
0.58
0.63
0.72
0.77
0.80
0.85
0.92
1.00
0.46
0.49
0.53
0.58
0.61
0.64
0.65
0.73
0.78
0.82
0.85
0.88
0.91
1.00
12
0.46
0.47
0.51
0.53
0.55
0.57
0.58
0.60
0.64
0.65
0.70
0.78
0.82
0.84
0.88
0.96
1.00
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
15
0.46
0.48
0.50
0.51
0.52
0.53
0.57
0.58
0.62
0.68
0.71
0.73
0.76
0.82
0.86
0.87
0.90
0.95
1.00
4.2.4
Adhesive Anchoring Systems
Behavior
Sulphuric acid
conc.
30%
10%
conc.
10%
conc.
10%
conc.
10%
conc.
10%
conc.
10%
conc.
10%
10%
40%
20%
5%
conc.
5%
10%
10%
10%
2%
10%
10%
Hydrochloric acid
Nitric acid
Phosphoric acid
Acetic acid
Formic acid
Lactic acid
Citric acid
Sodium Hydroxide
(Caustic soda)
Ammonia
Soda solution
Common salt solution
Chlorinated lime solution
Sodium hypochlorite
Hydrogen peroxide
Carbolic acid solution
Ethanol
Sea water
Glycol
Acetone
Carbon tetrachloride
Toluene
Petrol/Gasoline
Machine oil
Diesel oil
Key: non-resistant
1
+
+
+
+
+
+
+
+
+
+
+
+
+
+
+
limited resistance
+ resistant
23F
70F
Note: In actual use, the majority of the resin is encased in the base
material, leaving very little surface area exposed. In some cases, this would
allow the HY 150 to be used where it would be exposed to the
Partially Resistant chemical compounds.
HIT HY 150 2
HIT-ICE
10
0
23
32
41
68
86
104
23
18
5
0
5
20
30
40
25 min
18 min
13 min
5 min
4 min
2 min
1.5 hrs
1.5 hrs
40 min
26 min
11 min
4 min
1.5 min
HIT HY 150 2
HIT-ICE
10
0
23
32
41
68
86
104
23
18
5
0
5
20
30
40
6 hrs
3 hrs
90 min
50 min
40 min
30 min
24 hrs
24 hrs
6 hrs
4 hrs
2 hrs
1 hrs
30 min
HIT HY 150
100F
140F
64% at 212F
HIT-ICE
64% at 155F
120
110
100
90
80
70
60
50
40
30
20
10
0
100% at 100F
180F
Radiation
Exposure2, 3
Detrimental
Effect
< 10 Mrad
Insignificant
10 100 Mrad
> 100 Mrad
Note: Test procedure involves the concrete being held at the elevated temperature for
24 hours them removing it from the controlled environment and testing to failure.
Full Use
Moderate
Restricted Use
Frec. = 0.5 Fperm.
Medium to strong
220F
Recommendation
for Use
No recommendation
for use
Long-term creep test at 176F for HIT HY 150 is also available; contact Hilti
Technical Services.
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
US www.us.hilti.com
Canada www.ca.hilti.com
109
4.2.4
1. Drill anchor hole with a carbide bit. Contact Hilti for use
of Diamond Core bits.
8. Unlock dispenser.
2
1
Rod
10
11
10
11
Insert
2
Tmax
Tmax
2
Tmax
T
max
10
11
12
Rebar
www.us.hilti.com US
www.ca.hilti.com Canada
110
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
5/16
7/16
9/16
11/16
13/16
24mm
1-1/16
1-1/2
0.055
0.095
0.133
0.184
0.232
0.272
0.366
0.918
Rebar Installation
Rod
Diameter
(in.)
#3 or 3/8
#4 or 1/2
#5 or 5/8
#6 or 3/4
#7 or 7/8
#8 or 1
#9 or 1-1/8
#10 or 1-1/4
#11 or 1-3/8
Bar
Drill Bit1
Diameter Diameter
0.110
0.146
0.176
0.218
0.252
0.299
0.601
0.659
0.547
10M
15M
20M
25M
30M
35M
14 mm
3/4"
24 mm
1-1/8"
37 mm
1-9/16"
Adhesive Volume
Required per Inch
of embedment (in3)
0.101
0.176
0.268
0.309
0.644
0.480
1 Rebar diameter may vary. Use smallest drill bit which will accommodate rebar. For Hilti matched tolerance carbide tipped drill bits, see section 8.4.1.
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
111
4.2.4
Description
Contents
00371292
00371957
00305713
1 Cartridge, 1 Mixer
1 Refill Pack, 1 Mixer w/ filler tube
4 Cartridges, 4 Mixers
HIT Dispensers
BD2000
Battery
Dispenser
Description
00335288
MD1000
Dispenser
Manual Dispensers
Item No.
Description
00371291
00229154
00229170
P-3000HY
Pneumatic
Dispenser
HIT-ICE Cartridge
MD2000
Dispenser
P-8000HY
Pneumatic
Dispenser
Pneumatic Dispensers
Item No.
Description
00255032
00373959
00373960
HIT P-3000HY Pneumatic Dispenser, + 1 refill holder for HIT HY refill packs
HIT P-8000 Pneumatic Dispenser (for Jumbo cartridges)
Jumbo pack holder replacement fo HIT P-8000 Dispenser
www.us.hilti.com US
www.ca.hilti.com Canada
112
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
4.2.4
Adhesive Anchoring Systems
HIT-ICE Mixer
Description
00068156
00337111
00371290
00063799
00063994
00063995
Wire Brush
Qty/Pkg
1
1
1
1
1
1
Notes
Air Nozzle
Description
00063964
00255781
00255782
00059893
00255783
00255784
00003206
Qty/Pkg
1
1
1
1
1
1
1
Wire brushes are required for all applications using HY 150/HIT-ICE Adhesive, except HIT-TZ rod fastenings.
US www.us.hilti.com
Canada www.ca.hilti.com
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
113
4.2.4
HAS-E
Description
38-3
38-438
38-518
38-8
38-12
12-318
12-412
12-612
12-8
12-10
12-12
58-8
58-9
58-12
58-17
HAS-E
Description
34-10
34-11
34-12
34-14
34-17
34-19
34-21
34-25
78-10
78-13
1-12
1-14
1-16
1-20
114-16
114-22
Qty/Pkg
10
10
20
10
10
10
10
20
10
10
10
20
10
10
10
HAS-E ISO
898 Class 5.8
Item No.
333201
333198
333202
333203
333204
333205
333206
333207
333208
333209
333210
333211
333212
333213
333214
333215
Qty/Pkg
10
10
10
10
10
10
10
10
10
10
4
2
2
2
4
2
HAS Super, HAS Stainless Steel Rods, HIS and HIS-R Stainless Steel Inserts3
Description
HAS Super 3
Item No.
3/8" x 5-1/8"
1/2" x 6-1/2"
00068657
00068658
5/8" x 7-5/8"
Qty/Box
HIS
Description
HIS Insert
Item No.
Qty/Box
00068675
00068676
10
10
3/8" x 4-1/4"
1/2" x 5"
00258020
00258021
00258029
00258030
10
5
00333783
00333782
10
5/8" x 6-5/8"
00258022
00258031
3/4" x 9-5/8"
00068660
00068678
3/4" x 8-1/4"
00258023
00258032
7/8" x 10"1
000686611
968020064
1" x 12"
00068662
968020074
11/4" x 16"
00333779
1 Hot Dipped Galvanized (3/8" rod only). Coating thickness 2 mils (50.8m)
2 316 Stainless Steel HAS Rods are also available.
3 More HAS rod lengths are available, refer to Hilti Full Line Catalog or contact a Customer Service Representative.
4. Available by the individual piece.
Qty/Box
40
24
16
8
www.us.hilti.com US
www.ca.hilti.com Canada
114
Hilti, Inc. (US) 1-800-879-8000 I Product Technical Guide 2004 I Hilti (Canada) Corporation 1-800-363-4458
PART TWO...
Friction
out in the applicable building codes. Static loads can be tension, shear, or combinations of both. Dynamic loads can be
seismic, fatigue, wind, and shock. The
many types of anchors available have
characteristics that make them suitable
for or unsuitable for use under these various types of loads. Two state-of-the-art
documents, references 1 and 2, give
much more detailed information. Especially good are approval agency evaluation reports such as ICBO ES, BOCA,
and SBCCI or product listings for specific use as issued by listing agencies (e.g.
UL and FM). Manufacturers literature
may specify the applications for which
anchors are qualified and if test reports
are available to document capacities.
The primar y load-transfer mechanisms under tension loading are (in no
particular order of importance): keying
or bearing, friction, and bonding as well
as combinations. For shear loading, it is
keying or direct bearing.
Keying is the direct transfer of load
from the anchor into the concrete by
bearing forces in the same direction of
loading of the anchor. Friction is the
transfer of load through friction between
expansion sleeves of the anchor and the
wall of the drilled hole in the concrete.
Bonding takes place when resins or
grouts are used around the anchor, usually with post-installed anchors. Local
Keying
CAST-IN-PLACE SYSTEMS
Traditionally, design engineers specify
cast-in-place anchors if they know beforehand where anchors are to be installed.
Table 1 provides a brief overview of the
major types of cast-in-place anchors available, all of which use keying as a load
transfer means, in tension, shear, or
both.
Table 1. Cast-in-place Anchors
Standard fasteners
Proprietary shapes
Through bolts
Special shapes
Headed bolts
J and L bolts
Stud-welded plates
Threaded inserts
Proprietary anchors
and shapes
Usually sleeved
Shear lugs
Channel bars
Bonding
Homepage
Previous Document
Traditionally, design
engineers specify
cast-in-place anchors if
they know beforehand
where anchors are to
be installed.
1.5
Headed Bolt
L-Bolt
J-Bolt
Stud-welded Plate
POST-INSTALLED ANCHORS
With the development and improvements of rotary hammer drills and carbide-tipped bits, the user has the
capability to install many different kinds
of post-installed anchors in hardened
concrete virtually anywhere that is accessible to the drills.
Post-installed anchors can be divided
into two major types, depending on the
method of transferring load into the
concrete. They are mechanical systems
and bonded or adhesive systems.
Anchors can also be cross-classified
according to their load carrying capability; heavy-duty, medium-duty and lightduty. Table 2 provides an overview of the
major types of post-installed anchors currently available as well as a generalized
load categorization.
Homepage
HEAVYDUTY
MEDIUMDUTY
LIGHTDUTY
x
x
x
x
x
x
x
x
x
x
MECHANICAL
ANCHORING SYSTEMS
While mechanical anchors have been
available for several decades, there have
been significant advances in the types
and capabilities of these systems. They
cover the range from heavy duty to light
duty capacities. The major concern is to
select the appropriate anchors that will
resist the expected loads for the given
application. Is the anchor expected to
experience seismic or fatigue loads, or
merely static loads? While some anchors
will withstand all of these types of loads,
others may fail abruptly under dynamic
loading at a load level less than the static
capacity.
UNDERCUT ANCHORS
These anchors have been on the market for about 20 years. They are excellent for use under both static and
dynamic loads. They obtain their holding capacity through keying, that is,
direct bearing on the concrete, and,
under proper installation, can withstand
very high loads without slipping out of
the drilled hole. They are the preferred
anchors for use where cracks in tension
zones of the concrete can be expected to
occur.
Previous Document
EXPANSION ANCHORS
Expansion anchors have been available for at least 30 years. There are two
basic types that are distinguished by their
operating principles. The first, torquecontrolled expansion anchors, are
installed by inserting the anchor into the
drilled hole, and applying the prescribed
setting torque to the head or nut. A cone
at the bottom of the anchor is pulled up
into an expansion sleeve that expands
into the concrete with local crushing,
and providing both friction and localized keying as load-transfer mechanisms.
Most have a beneficial follow-up expansion characteristic that under tension
loading, the more the anchor bolt displaces upward out of the hole, the
greater the expansion forces.
There are several types available that
vary significantly in their ability to resist
static and dynamic loads. The heavy-duty
sleeve anchor (not to be confused with
the light duty sleeve anchor composed of
a sheet metal sleeve around a cone) can
resist dynamic loads as well as function
well in expected cracks in concrete.
Wedge anchors are the most common
type of torque-controlled expansion
anchor. Many have been tested for resisting seismic loads and have received
ICBO ES Evaluation Report listings for
such service.
Sleeve anchors are generally considered light duty, and rely more on friction
and less on local crushing and keying of
the concrete. They can be used in hollow masonry.
The second major type of expansion
anchor is the displacement-controlled
expansion anchor. Two primary examples are the drop-in and the self-driller.
Drop-in anchors are installed in the
predrilled hole by use of a setting tool
that drives a plug into the expansion
portion of the anchor. The lower section
of the anchor is expanded into the concrete, which experiences local crushing.
The second type has cutting teeth on the
lower end and drills its own hole. The
anchor is driven onto an expansion plug
that expands the lower portion of the
anchor into the concrete. These anchors
derive their holding capacity from friction and keying. The drawback is that
they do not have any follow-up expansion. Once set, they do not expand further under loading. If the plug is not
Homepage
Sleeve Anchor
Torque-controlled
Expansion Anchor
Heavy-duty
Sleeve Anchor
Undercut
Anchor
Drop-in Anchor
Self-drilling Anchor
Stud Anchor
Previous Document
Predating resin systems are cemetitious grouts. There are a variety of proprietary systems available. Non-shrink or
slightly expansive grouts are preferred to
prevent shrinkage and lack of bonding
to the existing concrete.
Adhesive Capsule
Anchor
IN SUMMARY
A wide variety of anchoring systems
are available. The correct selection
depends on several factors, including
types of loads to be resisted, magnitude
of the load, type of base material (concrete or masonr y), and environment
conditions (damp, wet, dry), among others. The manufacturers literature provides a good starting place, but also look
for evaluation reports and product listings, since they may be required under
many building codes.
REFERENCES
1. State-of-the-Art Report on Anchorage to
Concrete ACI 355.1R-91, American
Concrete Institute, Detroit, 1991.
2. Fastenings to Concrete and Masonr y
Str uctures; State of the Ar t Repor t,
Comit Euro-Intrnational du Bton,
Thomas Telford Services Ltd., London, 1994.
3. ANSI B212.15-1994, American National
Standard for Cutting ToolsCarbideTipped Masonry Drills and Blanks for
Carbide-Tipped Masonry Drills, American National Standards Institute, New
York, N. Y., 10 pp.
Richard Wollmershauser is Director Technical Ser vices for Hilti, Inc. of Tulsa,
Oklahoma. He has been active in the concrete anchor industry for the past 20 years.
He is a registered PE in Ohio and
Oklahoma and a Fellow of the American
Concrete Institute. He currently serves as
Vice-President of CAMA, The Concrete
Anchor Manufactures Association, Chairman of ASTM Subcommittee E06.13,
Performance of Connections in Building
Construction, and just completed 7 years as
Chairman of the American Concrete
Institute Committee 355, Anchorage to
Concrete. He was editor of the ACI State-ofthe-Report on Anchorage to Concrete (ACI
355R1-93). He also serves on the Federation International du Beton Task Group
SAG 4 Fastening to Concrete and Masonry.
He served on three committees of the recent
NEHRP 2000 Seismic Provisions Update
program where he was concerned with the
introduction of anchoring design methods.
Adhesive Cartridge
System
Homepage
Previous Document