Introduction
Project Salient
Principle of Function
Comparison with Gravity System
Integrated Layout
Individual Component
Site Photograph/Activities
Conclusion
INTRODUCTION
PROJECT SALIENT
The Projects Includes Vacuum Sewerage
system
Pipe Length to be relocated : 5.9 km
Approx
Diameter Used : 90/125/180/200mm
Types of pipes : HDPE(SDR 13.6 &11)
Peak Flow : 13.2 lit/sec
Types of Flow : Negative Pressure(-0.64
to -0.75)
PROJECT SALIENT
DEVELOPER : ALDAR
CONSULTANTS :
- Consultant (Design) : M/s Dar Al Handasah
- Consultant (Supervision) : M/s Dar Al Handasah
- Consultant(Overseeing) : M/s Mott MacDonald
CONTRACTOR
- M/s Six Co.
Specialized Contractor
- METCO
Estimated Project Cost : AED 8.65 MILLIONS
Start Date
: Jan 2010
Completion Date
: Sep 2010
Project Status
: Completed
PRINCIPLE OF FUNCTION
Gravity
Vacuum
Pipe Diameter
Large (>160)
Small (80-250)
Trenches
Deep
Shallow
Excavation
Leakage
Possible
Impossible
Manholes
Required
No manholes, inspection
pipes only
Machinery required
Heavy machinery
Simple machinery
Cost
High Cost
Low(compare to gravity)
Storm Water
Can Collect
Cannot Collect
Distance
Long Distance
Short Distance
Biofilter
Not Required
Required
INTEGRATED LAYOUT
INDIVIDUAL COMPONENT
Interface Valve
Isolation valve
Vacuum Pump
Vacuum Vessel
Discharge Pump
Interface Valve
Division Valve
Vacuum Pump
SITE ACTIVITIES
SITE ACTIVITIES
SITE ACTIVITIES
SITE ACTIVITIES
SITE ACTIVITIES
SITE ACTIVITIES
CONCLUSION.
For the planning and layout of a sewerage
system both systems should be
considered.
There is the use for conventional gravity
systems in the presence of sufficient slope
and in densely populated areas
But in rural communities and town
extremities, the VSS should be regarded as
an appropriate solution for the installation
of a sewer network.
CONCLUSION