Cost estimate of Oil & gas facilities

Welcome to this presentation.


It explains how the investment cost for an Oil & Gas facility is
estimated.
After a short introduction, the 3 common methods of cost
estimate are shown.
Common ratios, such as $/kg for equipment, pipe etc. are given.

2013 Herv Baron

Please download this file so that you can see my trainers notes in
the top left corner latest Acrobat Pro feature.
Herv

HERVE
BARON

Cost estimate of Oil & gas facilities

Please download this file to access my notes in the top left corner
Place your
mouse over
here

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Please download this file to access my notes in the top left corner
Place your
mouse over
here

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Agenda
Introduction

2013 Herv Baron

The different estimation methods:


Capacity factored
Equipment factored
Analytical

HERVE
BARON

Cost estimate of Oil & gas facilities

2013 Herv Baron

What will be the


overall cost of
this facility?

HERVE
BARON

Cost estimate of Oil & gas facilities


Cost = Quantities * item costs
All items

How would you determine quantities?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Quantities estimates:
Ratio from past projects
Material Take-Off

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


Cost = Quantities * item costs
All items

How would you determine quantities?


What is an item cost made of?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


Item cost = Supply cost + installation cost
How would you each one?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Item cost estimates:


Supply + installation
In-house data from
past projects
Inquiries

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Item cost estimates:


Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Item cost estimates:


Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron

Steel, alloy steel, copper,


cement, iron

HERVE
BARON

Cost estimate of Oil & gas facilities

Item cost estimates:


Supply + installation
In-house data from
past projects
Inquiries
Sensitivity to:
Raw materials
2013 Herv Baron

Construction market

HERVE
BARON

Cost estimate of Oil & gas facilities

Sensitivity to:

Construction market

2013 Herv Baron

Raw materials

HERVE
BARON

Cost estimate of Oil & gas facilities

2013 Herv Baron

Purpose of estimate:
Concept screening
Study of feasibility
Decision to invest
Estimate type:
Capacity factored
Equipment factored
Analytical

HERVE
BARON

Cost estimate of Oil & gas facilities

2013 Herv Baron

Purpose of estimate:
Concept screening
Study of feasibility
Decision to invest
Estimate type:
Capacity factored
Equipment factored
Analytical

HERVE
BARON

Cost estimate of Oil & gas facilities

Capacity factored
e
C1/C2 = (P1/P2)
e ~ 0.6
Ci: Cost of facility with production
capacity Pi

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Capacity factored
e
C1/C2 = (P1/P2)
e ~ 0.6
Ci: Cost of facility with production
capacity Pi

2013 Herv Baron

Exercise: what is the increase in cost for +50% capacity increase?

HERVE
BARON

Cost estimate of Oil & gas facilities

Capacity factored
e
C1/C2 = (P1/P2)
e ~ 0.6
Ci: Cost of facility with production
capacity Pi

2013 Herv Baron

Exercise: what is the increase in cost for +50% capacity increase?


In your opinion, what is the limit of such estimate?

HERVE
BARON

Cost estimate of Oil & gas facilities

Capacity factored
e
C1/C2 = (P1/P2)
e ~ 0.6
Ci: Cost of facility with production
capacity Pi

2013 Herv Baron

Exercise: what is the increase in cost for +50% capacity increase?


In your opinion, what is the limit of such estimate? It takes into
account neither market conditions nor plant location (labour cost)

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor

2013 Herv Baron

Note: Typical figures for Petrochemical Plant

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C=fM
C: total installed cost of facility
M: cost of main equipment
f: factor

2013 Herv Baron

Whats the main equipment?

HERVE
BARON

Cost estimate of Oil & gas facilities

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

2013 Herv Baron

How is the cost of main


equipment evaluated?

HERVE
BARON

Cost estimate of Oil & gas facilities


Process design
PFDs
H&M balance

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C=fM
f: factor
f depends on
type of facility (petrochemical, refining, LNG, off-shore)
Size

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C=fM
f: factor
f depends on
type of facility (petrochemical, refining, LNG, off-shore)
Size

In your opinion, how can we refine the estimate?

2013 Herv Baron

Typical figures for a chemical plant

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor
Why do you think justifies such an approach?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C = fi Mi
Mi Cost of all type i Main equipment
fi: factor
Why do you think justifies such an approach?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Equipment factored
C = fi Mi
Mi Cost of all type I Main equipment
fi: factor

2013 Herv Baron

In your opinion, what is the limit of such estimate?

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical

Western Europe, labour cost $100/hr yields $20k/ton


Middle East, labour cost $18/hr, productivity 2.5 yeilds $16k/ton

2013 Herv Baron

Establish the bill of quantities (BOQ) in each trade: equipment,


civil, piping, structural steel etc.
BOQ = Material Take-Off (what is measured from available
drawings at this stage) + allowances for design development +
allowances for what is not yet on drawings + contingencies
Apply ratios to get supply + installation cost
Installation cost = qty * manhours/ton ratio * labour cost
Labour cost is all in, i.e., includes construction equipment (crane,
scaffolding)
The ratio is based on standard manhours, i.e., home country,
Localization factor (productivity) to be applied, i.e., actual
installation manhours = ratio * productivity
Example: piping installation cost, ratio: 250 std h / ton

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply: eqt list (dimensions) => weight
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


Process design
PFDs
H&M balance

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply: eqt list (dimensions) => weight
Rate?
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply: eqt list (dimensions) => weight
Rate:

Important note: the above ratios and the following ones - are the ones obtained by large EPC
Contractors ordering large quantities (USD 1bln jobs). Higher ratios must be used on smaller jobs!

2013 Herv Baron

USD 4/kg for CS depends on eqt size: 4 (large) 10 (small)


USD12/kg for SS
USD 300-500 /m2 for Shell&Tube / Air-coolers
USD 1000/kW for pumps

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply: eqt list, dimensions/capacity/weight
Installation
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Supply: eqt list, dimensions/capacity/weight
Installation ratios: % supply cost, typ. 8%
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install

2013 Herv Baron

Supply: eqt list, dimensions/capacity/weight


Installation ratios: % supply cost, typ. 8%
30 std manhours/ton (includes labour
and equipment)

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

ratio (eqt weight), typ. 40%

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty: ratio

f (eqt number)

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty: ratio

f (eqt number)

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty: ratio

f (eqt number)
Remark: Unit vs Interconnection

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

ratio (eqt number, eqt weight)


MTO
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


Process design
PFDs

P&IDs

H&M balance

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


Process design

PFDs

P&IDs

H&M balance

Equipment list

2013 Herv Baron

Plot Plan

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping Layout
P&IDs

Plot Plan

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


For more information on Engineering, refer to:

A unique synthesis for the


busy Project professional
270 pages
300 illustrations

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


For more information on Engineering, refer to:
Table of Contents

2013 Herv Baron

HERVE
BARON

The Oil & Gas Engineering Guide


2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalo
gue-detail/1111/oil-gas-engineering-guidethe.html

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines, Fire water

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines, Fire water
Allowances added for:

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:

MTO
Item count: P&IDs
Lengths:
Piping Layout
Both Process & Utility lines
Both Above Ground & Underground lines
Allowances added for:
what is not taken-off, e.g., small diameter and design
development (P&ID completion) to obtain quantities
to erect
2013 Herv Baron

cut and losses to obtain quantities to be supplied

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:
Rate

ratio (eqt number, eqt weight)


MTO
Supply

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:
Rate

ratio (eqt number, eqt weight)


MTO
Supply
$ /kg, typ. USD 3 /kg for CS

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:
Rate

ratio (eqt number, eqt weight)


MTO
Supply
$ /kg, typ. USD 3 /kg for CS
Install
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Piping supply + install


Qty:
Rate

2013 Herv Baron

ratio (eqt number, eqt weight)


MTO
Supply
$ /kg, typ. USD 3 /kg for CS
Install
std mhrs/ton, typ. 200-250 in unit,
100 on interconnecting pipe-racks,
applied to the total piping weight,
including fittings & valves.

HERVE
BARON

Cost estimate of Oil & gas facilities

Electrical supply + install


Price ratio

% Main equipment, typ. 15-20%


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Electrical supply + install


2013 Herv Baron

Price ratio
% Main equipment, typ. 15-20%
Quantities:
Consumers list
Rate (supply+install):
USD 50k / consumer (w/o
generation)
USD 520 / installed kW

HERVE
BARON

Cost estimate of Oil & gas facilities

Consumers list

Single Line Diagram

Plot Plan

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Consumers list

Single Line Diagram

Plot Plan

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


Price ratio

% Main equipment, range: 40-120%


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


Price ratio
Qties

% Main equipment, range: 40-120%


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


Price ratio
Qties

% Main equipment, range: 40-120%


nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


% Main equipment, range: 40-120%
nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
2013 Herv Baron

Price ratio
Qties
Rate

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


% Main equipment, range: 40-120%
nb equiv. loops (CV, 0.5 ON/OFF, Analyser)
supply: $ /equivalent control loops, typ. 90k
install: hrs / equivalent control loops, typ. 750

2013 Herv Baron

Price ratio
Qties
Rate

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


Price ratio
Qties

% Main equipment, range: 40-120%


Instrument list
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Instrumentation & Control system supply + install


% Main equipment, range: 40-120%
Instrument list
Supply+install: $ / I/O, typ. 1000

2013 Herv Baron

Price ratio
Qties
Rate

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio

% Main equipment cost, typ. 15-20%

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty
Dimensions/Weight of equipment &
structure => size of foundations (m3)
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty
Dimensions/Weight of equipment &
structure => size of foundations (m3)
Rate
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio % Main equipment cost, typ. 15-20%
Qty
Dimensions/Weight of equipment &
structure => size of foundations (m3)
Rate
all-in (materials & labour) rate $/m3, typ. 1000
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio
Qty

% Main equipment cost, typ. 15-20%


MTO: excavation, formwork, rebar, etc.

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Civil Works
Price Ratio
Qty
Rate

% Main equipment cost, typ. 15-20%


MTO: excavation, formwork, rebar, etc.
Mhrs/operation + labour cost
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Steel structures
Price Ratio

% Main equipment cost, typ. 10-30%


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Steel structures
% Main equipment cost, typ. 10-30%
2013 Herv Baron

Price Ratio
Qty Ratio

HERVE
BARON

Cost estimate of Oil & gas facilities

Steel structures
% Main equipment cost, typ. 10-30%
pipe-racks: 90% of piping weight
platforms: 10% of equipment weight

2013 Herv Baron

Price Ratio
Qty Ratio

HERVE
BARON

Cost estimate of Oil & gas facilities

Steel structures

Rate

% Main equipment cost, typ. 10-30%


pipe-racks: 90% of piping weight
platforms: 10% of equipment weight

2013 Herv Baron

Price Ratio
Qty Ratio

HERVE
BARON

Cost estimate of Oil & gas facilities

Steel structures

Rate

% Main equipment cost, typ. 10-30%


pipe-racks: 90% of piping weight
platforms: 10% of equipment weight
Supply USD 2/kg
Erection 20 std manhours/t

2013 Herv Baron

Price Ratio
Qty Ratio

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical

Main equipment supply + install


Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Painting, Insulation
Price ratio

% eqt, piping, str cost, typ. 5% each


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Painting, Insulation
Price ratio
Qty

% eqt, piping, str cost, typ. 5% each


MTO
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Painting, Insulation
% eqt, piping, str cost, typ. 5% each
MTO
supply + install h / m2
typ. 0,5 for painting 1,5 for (hot) insul.

2013 Herv Baron

Price ratio
Qty
Rate

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Temporary Construction facilities


% total cost, typ. 5% for new site

2013 Herv Baron

Ratio
Detailed

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Engineering & Project Management = all Project services


Price ratio

% total cost, typ. 15%


2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Engineering & Project Management = all Project


services
% total cost, typ. 15%

2013 Herv Baron

Price ratio
Qty ratio

HERVE
BARON

Cost estimate of Oil & gas facilities

Engineering & Project Management = all Project


services
2013 Herv Baron

Price ratio
% total cost, typ. 15%
Qty ratio
hrs / eqt item, typ.
1800 for Refining,
2500 for gas, 4000 for LNG

HERVE
BARON

Cost estimate of Oil & gas facilities

Engineering & Project Management = all Project


services
% total cost, typ. 15%

2013 Herv Baron

Price ratio
Qty

HERVE
BARON

Cost estimate of Oil & gas facilities

Engineering & Project Management = all Project


services
% total cost, typ. 15%
home office: tasks list + std manhours
field supervision: ratio to labour, typ. 1/7

2013 Herv Baron

Price ratio
Qty

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous
Contractors cost

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Miscellaneous

Earthworks: always specific


Special foundations
Infrastructures: roads, buildings
Spare parts, typ. 5% main equipment cost
First fill (catalyst, lubes, chemicals)

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Analytical
Main equipment supply + install
Piping supply + install
Electrical supply + install
Instrumentation & Control system supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous
Contractors cost

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Contractors cost
profit,
risks,
sales cost,

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Contractors cost
profit, typ. 7%
risks,
sales cost,
typ. 10-15%

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main equipment supply + install


Piping supply + install
Electrical supply + install
Instrumentation & Control system
supply + install
Civil Works
Steel structures
Painting, Insulation
Temporary construction facilities
Engineering & Project Management
Miscellaneous: catalysts etc.
Contractors cost

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main features:
Different level of Cost estimate accuracy
Feasibility study +/-30% accuracy
Final Investment Decision (FID) +/- 10%
Which of the methods we have seen would you use for
each case?

2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities

Main concepts:
Different level of Cost estimate accuracy
Factored / Detailed
Qty estimate: allowances for design development
Rates:

Direct costs / Indirect costs

2013 Herv Baron

In-house historical data similar Plant


Cost estimate: Contingencies for cost escalation
Inquiries + provisions for cost adders (supplies),
additional works/re-works (construction)

HERVE
BARON

Cost estimate of Oil & gas facilities

Historical evolution:
+ Increased instrumentation & control costs
- Engineering low cost centers
- Low cost sourcing 20% cheaper
- Increase in productivity (3D model)
+ Additional requirements: safety, environment
2013 Herv Baron

HERVE
BARON

Cost estimate of Oil & gas facilities


For more information on Engineering, refer to:

A unique synthesis for the


busy Project professional
270 pages
300 illustrations

2013 Herv Baron

HERVE
BARON

The Oil & Gas Engineering Guide - 2nd edition


Table of Contents

Discipline presentation:
activities and deliverables

The overall process


Methods & tools

HERVE
BARON

The Oil & Gas Engineering Guide - 2nd edition


Table of Contents

Discipline presentation:
activities and deliverables

HERVE
BARON

The work of each


Engineering discipline is
described

HERVE
BARON

Design activities are


explained, e.g., Plant
Equipment layout

HERVE
BARON

Complex activities, such as


QRA, are explained
through a practical
example.

HERVE
BARON

How are materials of


construction selected ?

HERVE
BARON

How and when are Piping


Materials ordered?

HERVE
BARON

A sample of all common


Engineering documents is
included

HERVE
BARON

A sample of all common


Engineering documents is
included

Use this to specify what


you want to your
Engineering supplier !

HERVE
BARON

Verify the contents of


engineering documents
with check lists.

HERVE
BARON

Difference between
Engineering and Shop
drawings

HERVE
BARON

Understand the main


technical aspects, e.g.,
DCS vs ESD

HERVE
BARON

The common 2 types of


package control

HERVE
BARON

The different Plant


drainage systems

HERVE
BARON

The dynamic forces to


which an Off-Shore
Plant is subject

HERVE
BARON

The Oil & Gas Engineering Guide - 2nd edition


Table of Contents

The overall process

HERVE
BARON

Use this as standard,


question deviations.

HERVE
BARON

Understand the new


3D-model centered
engineering process

HERVE
BARON

Know the interfaces


between disciplines...
and with Vendors

HERVE
BARON

Understand what
drives the Project
schedule

HERVE
BARON

The Oil & Gas Engineering Guide - 2nd edition


Table of Contents

Methods & tools

HERVE
BARON

Use these methods as


standard, question
deviations.

HERVE
BARON

Implement powerful
procedures

HERVE
BARON

Request meaningful
progress reports

HERVE
BARON

Implement effective
Project Control

HERVE
BARON

The Oil & Gas Engineering Guide - 2nd edition

This book is destined to both:

Oil & Gas companies Project execution personnel

Oil & Gas contractors Project execution personnel

HERVE
BARON

The Oil & Gas Engineering Guide


2nd edition

If your are on the Client side, i.e., contracting Engineering


services, this book will help you to:

Specify to an Engineering supplier what you want: what


deliverables and with what contents,
Set a standard in Engineering execution that you and your
supplier can adhere to: design stages/gates, methods to be
used, etc.
Specify the progress report you want, with the meaningful
indicators,
Ask the right questions to assess the true progress,

HERVE
BARON

The Oil & Gas Engineering Guide


2nd edition

If your are on the Contractor side, i.e., performing Engineering


activities, this book will help you to:

Understand the work of each discipline and the overall


picture,

Challenge what one discipline tells you,

Understand the critical areas,

Put in place the right methods to be successful,

HERVE
BARON

The Oil & Gas Engineering Guide


2nd edition
Order direct on the publisher website:
http://www.editionstechnip.com/en/catalo
gue-detail/1111/oil-gas-engineering-guidethe.html

S-ar putea să vă placă și