Documente Academic
Documente Profesional
Documente Cultură
- 26967840,42,45,26967900,26868681
OE Fax - 26865206, 26567341
E-Mail : nrebops@yahoo.com
Dated 17.08.09
- sd(A K Rajput)
S.E. (Operations) & Member Convener USMG
Sr.
No.
1.
BBMB
Director (PR)
2.
DTL
GM (SLDC); DGM;
3.
HVPNL
4.
HPSEB
SE(SLDC)
5.
J&K
CE (C&S), Jammu;
6.
PSEB
CE (SLDC); DD (SLDC)
7.
RVPN
CE (C&LD); EE (SLDC)
8.
UPPCL
9.
PTCUL
10.
UJVNL
General Manager-GV
11.
PowerGrid, NR-I
GM (O&M); Ch Manager
12.
THDC
13.
PowerGrid, NR-II
DGM
14.
CEA
Dir (LD&T)
15
NRLDC
CM (CS); CM (TS)
16
NRPC
SE (Operations); EE (O-I)
PGCIL) :
It was also deliberated and decided that till such time the above link is commissioned,
the temporary link provided during 11/2008 for HPSEB between Baspa-II and SLDC
Shimla is to be made functional by POWERGRID. This temporary link is non functional
since Jan. 2009.
USMG may like to confirm the minutes.
2.0 NMS of Digital Microwave System:
In the last meeting POWERGRID had stated that for the monitoring of communication
equipment installed under ULDC scheme, Network Monitoring System (NMS) has been
installed at Regional System Control and Coordination (RSCC) Center. With the help of
NMS, healthiness of communication equipment (Card level) and healthiness of DC/AC
power supply etc are monitored on 24x7 basis. NMS is vital part of communication
network and in absence of NMS it would be very difficult to maintain the system as
maintenance engineer would be running in blind alley. Matter was taken up with NOKIA
and they had informed that their present NOKIA NMS software can not run on any other
OS, however they have developed new software NETVIEWER which operates on
windows based system. They have indicated that total financial implication for changing
2
present NMS system with new one would be approx. Rs 1.3 Crores. Formal offer shall be
submitted by NOKIA or their authorized representative after survey at all SLDC/RSCC.
However, AMC contractor of wideband had proposed that they would replace the NMS
at RSCC only, without any cost implication to POWERGRID. If NMS is to be replaced
at all SLDCs charges shall be as per NOKIAs offer.
POWERGRID in the last meeting had indicated that there are two parts of NMS viz. (i)
NMS for Fibre Optic; and (ii) NMS for Microwave system. For the above mentioned
microwave system, cost wise Radio Communication System constitutes about 20% and
remaining 80% cost component is that of Multiplexers (Muxs). The Radio portion is
being phased out gradually and Optical Fibre Cable (OPFC) is being installed in its
place. Multiplexers will still remain in the system.
Constituents and MS , NRPC suggested that possibility of buy back of the released
obsolete equipment from existing system should be explored. POWERGRID stated
that this could form part of the negotiations for awarding AMC.
USMG also decided that POWERGRID would send proposal to each constituent
indicating total cost implications of the scheme, as well as the cost to be borne by each
constituent, in turn the constituents would take up the matter with their management and
would revert back in the matter, before the next meeting.
PSEB has given consents to the proposal of PGCIL for replacement of NMS system
at PSEB SLDC & the charges, Rs.15.47 Lac( including BBMB share) as worked out
by PGCIL. as per CERC orders, shall be paid by them.
HPSEB has intimated that necessary approval for replacement of existing Microwave
NMS with new NMS has been conveyed to POWERGRID.
Other constituents may like to update.
Members may like to deliberate.
In the last meeting POWERGRID had intimated that M/S AREVA had phased out S900 RTUs and the cost of spare cards of these RTUs as per rates quoted by M/S
AREVA were on higher side. Constituents had discussed the issue and decided that
as discussed in the 8th NRPC meeting, constituents might go ahead and procure the
RTUs themselves. The AMC contract would be negotiated in October, 2009 and
AMC related issues would be discussed in the next USMG meeting.
Members may like to deliberate
HPSEB is presently paying approximately Rs. 100 lac (approximately) towards AMC
of SCADA/EMS system installed at SLDC Shimla and-LDCs at Kunihar and
Hamirpur including service charges & overhead charges etc. The total cost of the
installed system (H/W & S/W) for which AMC has been awarded is around Rs. 5.6
crore. Presently, EMS packages such as Load Forecasting (Forecasting available on
1 hour basis against requirement of 15 minutes basis), Operation Scheduling are not
being used in the entire NR Control Centres for one reason of the other. Also, State
Estimator, Contingency Analysis, Security Enhancement and Load Flow Analysis
packages are being used only to some extent owing to common NR model and older
version packages. Only SCADA data, HDR data and to some extent HIM data is
being utilized for monitoring and report generation. HPSEB has proposed that
whenever the present system is upgraded, SCADA portion (HW / S/W) of the
system including OAG (Open Access Gateway) should be installed by the central
agency i.e PGCIL, for all the constituents having provision for the integration of
EMS packages for uniformity.
finalized. It is apprehended that the new system cost may not be commensurate
with AMC cost owing to the warranty to be given by the vendor for the new system .
Members may like to deliberate
6.0 Changing the Isolator and Breaker Numbers in ULDC SCADA System as per
field conventions:
BBMB had earlier stated that the Isolator and Breaker numbers defined in the ULDC
SCADA System are different from the actual numbers given to these devices in the field.
This necessitates frequent references to physical drawings as the device numbers
indicated on SCADA Displays and Logs do not match with the field drawings and
reports. This makes the operations and reporting in control centre difficult and prone to
errors. Efforts have been made by BBMB to implement the naming conventions of
ULDC SCADA System in the field but the same has been viewed with apprehension by
our field organizations. This is due to the fact that the existing numbering scheme is
being used for a long time and departure from the same may lead to confusion. Hence in
to
implement field numbering scheme in the SCADA System. BBMB opined that the
changes outside of BBMB System would be minimal but the exercise would be quite
fruitful in the long run.
USMG had opined that it might be done on one or two stations on sample basis for
the time being and share the experience with others. BBMB may like to update on
the issue.
Members may like to deliberate.
7.0 EXPANSION OF NR UNIFIED LOAD DESPATCH AND COMMUNICATION SCHEME of
NR (PHASE-II)
During the 8th NRPC meeting, held at Udaipur on 25th April 2008, it was decided that
constituents may go ahead independently for the expansion of their respective parts of the
ULDC scheme (Phase-II). The USMG would decide a minimum standard requirement
indicating which data should flow to RLDC and SLDC so as to ensure the proper
integration of ULDC expansion in the northern region.
The matter was discussed in detail during the last USMG meeting. During discussion,
for consideration of the committee. The proposed committee would come out with a
common approach paper and recommendations for implementation of ULDC-phase II
scheme The Committee would submit its report within two months time.
The report of the sub committee is under deliberation among the members of the sub
group. The draft report is enclosed at annexure.
Meanwhile PSEB has stated that since all the states would have to arrange funds /
consultants/ global tendering individually and the constituents shall have to pay for
PGCIL/ BBMB share also , these duplication of work may prove costly for the
constituents. Moreover at least
decrease inventory of spares/ cost of AMCs. PSEB is considering to re- open the
decision taken during 8th NRPC meeting. PSEB has requested that members may
deliberate accordingly , so that the SLDCs may be upgraded in a cost effective
manner , under unified approach.
Members may like to deliberate.
8.0 Commissioning of telemetry system between Baspa HEP and HPSEB by
M/S PGCIL
It was decided that POWERGRID would install PLCC Link from Nathpa JhakriAbdullapur-Bawana Line for providing reliable telemetry of Baspa HEP at the expense of
HPSEB and HPSEB would take care of its maintenance aspects. It was also agreed that
till the permanent link was established, the temporary link provided by POWERGRID
would be made available.
HPSEB has stated that POWERGRID has not taken any action for restoration of
temporary link which is down since Jan. 2009. This link need to be restored immediately
without any further delay as already three months have elapsed ever since POWERGRID
agreed to do the same during 23rd USMG meeting. Further, action taken for installation
of new PLCC link from Jhakri-Abdullapur-Bawana line for providing reliable telemetry
of
POWERGRID.
HPSEB has requested that necessary directions in this regard are required to be issued to
POWERGRID to take immediate action.
POWERGRID/HPSEB may like to update.
7
PSEB has requested that a core group considering one member from each
constituent and one member from NRLDC/ PGCIL may be formed for making all
the EMS applications functional.
Members may like to deliberate.
110
PSEB has stated that NRLDC has withdrawn real time data of few important system
parameters from the website. These real time values/status of various RTUs was quite
useful for system operation/monitoring. PGCIL/ NRLDC may issue some password to
constituents to access this real time data on internet, if the same has been withdrawn due
to some security constraints. The original feature of web sites may please be re-stored.
Member may like to deliberate.
12.2
Replacement of defective battery cells of UPS installed under ULDC
Scheme ( Agenda by BBMB)
Various cells of the battery banks of UPS System installed under ULDC Scheme at
various Sub-LDCs and SLDCs are lying defective since last many months. The matter
has been discussed at various Monthly Review Meetings and the AMC vendor of UPS,
M/s Emerson, has given various deadlines since last many months, but the firm is just
using dilatory approach and have not replaced the cells till date. The details of cells lying
defective at BBMB Sub-LDCs is as under:
Station
Cell Nos
Defective Since
Charkhi Dadri
Cell No 72
13.03.2008
15.04.2009
28.07.2009
Jamalpur
Besides this, many battery cells at BBMB Sub-LDCs and SLDC Chandigarh have been
found to be weak. POWERGRID may be requested to take immediate necessary steps to
get the cells replaced.
POWERGRID/ BBMB may like to update.
13.0 ANY ADDITIONAL AGENDA POINT
14.0 DATE, TIME AND PLACE OF NEXT MEETING
The Group may decide the date and venue of the next meeting.
Utility
DTL
HPSEB
HVPNL
HVPNL
HVPNL
HVPNL
HVPNL
HVPNL
HVPNL
PDD , J & K
PSEB
PSEB
PSEB
PSEB
PSEB
PSEB
PSEB
PSEB
PSEB
PTCUL
PTCUL
kV Level
220
220
220
220
220
220
220
220
220
400
220
220
220
220
220
220
220
220
220
400
220
Station
DSIDC
Larji
Cheeka
Daulatabad
IMT Manesar
Jorian
Nilokheri
Palli
Tepla
Baglihar
Bajakhana
Botiawala
Derabassi
Dhuri
Hambran
Khasa
Kotli Suratmali
Patran
Rajla
Kashipur
Haldwani
22
23
24
25
26
27
28
29
30
31
32
33
34
35
PTCUL
PTCUL
RRVPNL
RRVPNL
RRVPNL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
PGCIL
PGCIL
220
220
220
220
220
400
221
220
220
220
220
220
400
220
Pantnagar
Roorkee
Barsingsar
Dholpur
Jallore
Greater Noida
Orai
Almoh
Attrauli
Chibra Mau
Dohna
RPH
Roorkee
Sitarganj
Sl No.
Utility
kV Level
Remarks
RTU was to be installed.Not integrated yet.
HPSEB
HPSEB
HVPNL
PDD , J &
PDD , J &
PDD , J &
PDD , J &
PDD , J &
PDD , J &
K
K
K
K
K
K
Station
400
132
220
220
220
220
132
132
132
Baspa
Andhra
Fatehabad
Chenani
Hiranagar
Pampore
Lower Jhelum
MiranSahib
Upper Sindh
Remarks
RTU Integrated but some configuration
problem.Data not available at NRLDC
PLCC problem
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
POWERGRID
PTCUL
RRVPNL
RRVPNL
RRVPNL
UJVNL
UJVNL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
UPPCL
PGCIL
PGCIL
PGCIL
PGCIL
400
220
400
220
220
220
220
220
220
220
220
220
220
220
400
400
400
400
Kankrauli
Maneribhali
Jodhpur
Flodi
Bhilwara
Chibro
Ramganga(H)
Agra-II
Allahabad Cant
Badaun
Basti
Noida
Saharanpur
Sahibabad
Patiala
Dulhasti
Bareily
Uri
28
29
30
31
PGCIL
PGCIL
PGCIL
DTL
400
220
400
220
Balia
Raibareily
Gorakhpur
Kashmeri Gate
Data intermittent
Data intermittent
Data intermittent
Not available since 23.07.09
Data highly intermittent
Data incorrect-ABB SAS problem
Not available since 11.07.09
Not available since 18-01-09-ABB SAS
problrm.
Data not available since 30.07.09
Data intermittent
Restored
1GENERAL
This document describes the specifications for the Remote Terminal Unit (RTU). The
Contractor shall supply RTU, associated equipment and required number of panels for
housing of all the hardware envisaged for the RTU and system interface cubicle (SIC).
The contractor shall be responsible for supplying all the hardware, software, and
installation, cabling and field implementation for RTU as defined in this Specification. The
contractor shall also provide complete documentation, training and testing to fully support
the hardware and software provided. The RTU shall be used for real-time supervision
and control of substation/ power plant through a SCADA system at Remote Control
Centre (RCC). The RCC is also referred to as Master station or SCADA system. Strict
compliance to standards, scalability, modular and open architecture.
The owner may not initially use all capabilities of the RTU specified in this document.
However, regardless of the RTU configuration purchased, the RTU shall be capable of all
functions specified herein. The optional functions, if any specified in the specifications,
may be implemented with the addition of necessary hardware and software modules in
the field as and when required by the owner without any additional financial implications
except for |hardware cost if any.
(Commercial)
It is Owner's intent that the Contractor uses as much standard hardware and software as
possible; however, all of the functional requirements of this Specification must be
satisfied. The use of the Contractor's standard hardware and software may cause the
Contractor to conclude that there is a need for additional items not specifically mentioned
in this Specification. The Contractor shall supply all such items and provide a complete
RTU design that meets all of the Owner's functional requirements defined in this
Specification.
(Commercial):
v.
vi.
vii.
viii.
ix.
Collecting, processing and transmitting status changes, accumulated values and analog
values.
Receiving and processing digital commands from the master station(s).
Accepting polling messages from at least two master station(s) simultaneously using
partitioned databases for each master station.
At least six serial communication ports (4 x RS232 + 2 x RS485) with the provision of
adding at least additional 4 serial communication ports by way of addition of required
hardware. The RS 232 ports shall be configurable for data transmission rates from 200 to
19200 bits per second. The RS232 (Unbalanced) communication ports shall use CCITT
V.24 and V.28 signal specifications and RS485 (Balanced) communication ports shall
use V.11 or V.35 signal specifications to interface with other equipment.
Support multiple concurrent protocols in each CPU including the following :
Local/Remote Host Communication Protocols
IEC 60870-5-101
IEC 60870-5-104
DNP 3.0 (Serial & TCP/IP)
1.1.1 Redundancy in CPU and Power supply for communication with RCC.
The RTU shall be provided with redundant CPUs and Power supply unit so that the RTU
can communicate with the Remote Control Centre even when one of the redundant units
fails. A failover process shall cause the assignment of all the functions of the failed unit to
the healthy unit. The failover between the two redundant units shall be transparent and
shall not require any manual intervention.
The failover process of the power supply units shall not cause any interruption in the
functioning of the RTU.
The failover of process of the CPU shall be completed within 30 seconds of the failure of
the primary CPU. All the functions in the RTU shall be operational within 30 seconds of
the failover operation i.e. one minute from the time of failure.
b)
NOTE: 1) TWO MODEMS IN THE RTU AND TWO STANDALONE MODEMS FOR REMOTE END SHALL BE
SUPPLIED.
5.
6.
7.
8.
9.
sensing voltage shall not exceed 48 Vdc. The sensing voltage source shall be isolated
from that of the RTU logic power such that any noise or a short circuit across the sensing
supply's output terminals would not disrupt the RTU operation other than the shorted
digital status input.
The RTU shall store all status changes detected for retrieval by the master stations. For
communication delays or short-term failure of communications with a master station, the
RTU shall store a minimum of 300 status change events. The RTU shall report any
overflow of this status change buffer to the master stations.
1.3.1 Two-State Devices
All switching devices (breakers, isolators etc) shall be supported by a dual-contact status
indication. Breakers with re-closing capability shall also be supported with momentary
change detection (MCD). All other status indications shall be two-state single-contact
status inputs without MCD.
Single-contact two-state status point inputs will be from a single normally-open (NO) or
normally-closed (NC) contact. Dual-contact two state status point inputs will be from two
complementary contacts (one NO and one NC). A switching device status is valid only
when one contact is closed and the other contact is open. Invalid states shall be reported
when both contacts are open or both contacts are closed. The state definition shall be set
by Owner for each contact position.
The RTU shall be set to capture contact operations of 20 ms or more duration.
Operations of less than 20 ms duration shall be considered no change (contact bounce).
The duration used to determine change versus bounce shall be adjustable from 4 to 25
ms.
The RTU shall collect digital status input data and time-of-operation from fast-operating
devices. The RTU shall time-stamp the data using its internal clock with a time resolution
of one millisecond. The time resolution will enable Owner's personnel to determine the
sequential operation of device state changes. Any digital status input data point in the
RTU shall be assignable by Owner as an SOE point. Each time a SOE status indication
point changes state, the RTU shall time-tag the change and store the change (open,
close) and the time-tag of the event in SOE buffers within the RTU. The SOE buffer shall
be sized for at least 1000 events.
When requested from a SCADA system master station, the RTU shall transmit the SOE
data stored in its buffer corresponding to that master station. An acknowledgement of
receipt by the master station shall be made prior to the loss of any data in the RTU SOE
buffer. Data not received at the master station shall be retransmitted. An indication that
SOE storage at an RTU is approaching capacity (at 80%) shall be transmitted to the
master station in the normal periodic scan so that a priority scan can be sent by the
master station to retrieve the SOE data. An additional indication shall provide the status
of RTU SOE data buffer overflow.
When commanded from the master station, the appropriate raise or lower output shall be
operated for the selected time interval. The raise/lower output for each point shall operate
over a range of 0.1 to 4 seconds.
Select-check-operate sequence for control output. The verification message for check
before-operate control sequences shall be obtained by re-encoding the verification
message directly from the control point selection lines. Thus, a simple reflection of the
received message is not acceptable.
2.
Partitioned database for each master station and control point shall be selectable only
from one master station. A Control point in the RTU once selected by a Master station
shall not be operable from another Master station.
3.
4.
No more than one control point shall be selected at any given time in the RTU. A
detection and lockout method shall be provided that prevents a control operation if more
than one control point has been selected.
5.
6.
The control selection shall be automatically cancelled if after receiving the "control
selection" message, the "operate" command is not received within the set time period.
7.
8.
No false output shall result during power up or power down. No false output shall
result from inadvertent connections to a circuit card.
9.
10. All control output connections shall have protective covers.
Local/Remote switch shall allow testing of the control outputs without activating the
control output relays.
A status input indication shall be provided for the Local/Remote switch to allow the
SCADA system to monitor the position of the switch.
1.5 Time Synchronization
The RTU shall maintain real-time clock and shall have an internal RTU time base with a
stability of 1 ppm i.e. 3.6 milliseconds per hour or better. The RTU shall maintain the realtime clock information even when the auxiliary power to the RTU is switched OFF.
The accuracy of the internal clock for shall be maintained by protocol messages from the
master station. The RTU time will be set from time synchronization messages received
from master station at every 10 minutes when using the IEC 60870-5-101/IEC 60870-5104 communication protocol over dedicated lines. The RTU shall be provided with
suitable hardware and software for accepting time synchronisation from a GPS using
IRIG -B/ASCII time messages/1 pps signals.
Any hardware required for multiplication of the ports of the GPS shall also be supplied by
the Contractor.
1.6 Power Supply
The RTU power supply module shall have following characteristics:
1.
2.
3.
4.
5.
6.
7. Each RTU shall have the capability of automatic start-up and initialisation following
restoration of power after an outage without need of master station intervention. All
restarts shall be reported to the connected master stations.
8.
9. Secondary power shall be provided to the RTU at 230 Vac, 50 Hz, single-phase for noncritical auxiliary equipment including heaters, internal lighting, and internal maintenance
outlets.
1.6.1 Power Supply Protection
Over voltage and under voltage protection shall be provided to the input and output of the
power supply in addition to output over current protection to safeguard the RTU internal
logic from being damaged as a result of a component failure in the power supply and to
prevent the RTU internal logic from becoming unstable and causing mal-operation as a
result of voltage fluctuations.
1.6.2 Power Supply Failure Indicators
The RTU shall have a status point which shall be set if the power to the RTU has been
cycled (off-on) for any reason (including maintenance). The successful transfer of this
indication to master station shall reset the power fail status point.
All printed circuit card cages and all slots within the cages shall be clearly labelled.
Printed-circuit cards shall be keyed for proper insertion. It is desirable that printed-circuit
cards be keyed to prevent insertion into incorrect locations.
All circuit protection breakers shall be of the manually operated, moulded-case type, and
shall provide thermal over-current and instantaneous short-circuit protection in each pole.
1.7.4 Noise Level
The audible noise generated by the RTU equipment shall not exceed 50 dbA measured
at one meter from the enclosure.
The RTU will be installed inside buildings without temperature or humidity control. The
RTU shall be capable of operating in ambient temperatures from 0 to +50 deg C with rate
of temperature change of 20 deg C/hour and relative humidity up to 95% non-condensing
at 40 C.
1.9 Availability Requirements
The RTU will perform data acquisition and control of important equipment necessary for
the operation of Owner's power system. Any failure of an RTU to perform its functions will
adversely affect power system operations. An availability of at least 99% is required
excluding communication and power source. The failure of any RTU function and
hardware shall be considered as unavailability of the RTU. The methodology to calculate
the availability is defined in section "SCADA specification ".
1.10 RTU Size and Expandability
The RTU shall be supplied for the sizing as per Appendix IA (BOQ). The RTU shall
contain alteast 20% spare capacity for every I/O point type, as wired spare capacity
which can be used without any hardware additions in the RTU/SIC Panels including TBs,
wiring etc. In addition to the above, the RTU shall have the capacity to add additional I/O
modules to expand the overall point count of the RTU by a minimum of 50% of the
supplied capacity. All the I/O points available in the modules/cards supplied in the RTU
shall be wired to TBs.
1.11 RTU design & Maintainability
The RTU design shall facilitate isolation and correction of all failures. The following
features which promote rapid problem isolation and replacement of failed components
shall be provided:
Self-diagnostic capabilities within each RTU which can be initiated at the RTU site
On-line error detection capabilities within the RTU and detailed reporting to the
connected master stations of detected errors
acceptance tests to the extent possible. This testing will include, but not be
limited to the following test :
RTU initialization
c) Laptop PC
A Pentium-IV or better laptop PC shall be used for the above mentioned software tools.
The laptop PC shall be provided with all hardware accessories including cables,
connectors etc. required for interfacing with Master station and RTU. A carrying case and
a suitable power adaptor (input 230VAC, 50Hz) for laptop PC shall also be supplied.
1.14 DOCUMENTATION
The Contractor shall submit hardware and software documentation in three sets for
RTU/SIC to Owner for review and approval. After approval four set of all the documents
shall be submitted as final documentation. Any changes observed during field
implementation shall be incorporated in the as-build drawing and four sets of same shall
be submitted to owner.
Further contractor shall provide documents in soft copy as well (CD media) in two
sets. 2 sets of CD/Floppy for system back up shall also be provided to restore the
complete system including RTU database in case of system crash due to unforeseen
reasons.
TABLE 1
List of Tests on RTU/SIC
Test
Nos
Check for BOQ, Technical details, Construction & Wiring as per RTU/SIC
drawings
Type
test
Routine
test
Field
test
17
18
19
20
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
21
29
30
31
Test
Nos.
1
2
3
4
5
6
7
8
Test Name
Surge Immunity Test
Electrical Fast
Transient Burst Test
Damped Oscillatory
Wave Test
Electrostatic
Discharge Test
Radiated
Electromagnetic Field
Test
Damped Oscillatory
Magnetic Field Test
Power frequency
magnetic field
Power frequency
voltage withstand
EUT
status
on
Level-3
on
Level-3
2kV
1kV
on
Level-3
2.5kV
1kV
2.5kV
on
Level-3
on
Level-3
on
Level-3
on
Level-3
off
off
2 kVp
Test Level
1.2/50s impulse
voltage withstand
10
Insulation Resistance
Test
off
11
12
on
on
I/O points
CM
2kV
Passing Criteria
A
No break down
or flashover
shall occur
No break down
or flashover
shall occur
As per
manufacturer
standard
0
0
Committee Draft
considerations only critical component of the Northern Region were included in the
project. Subsequent to commissioning of ULDC Scheme the expansion of Power System
has taken place at considerable pace, parallelly organizational, regulatory and
technological changes have also taken place, the constituents have felt the need for
expansion of ULDC system by inclusion of more component of the Grid for monitoring.
The need and implementation methodology for expansion of ULDC scheme of northern
region was discussed by the constituents in various forums. Finally during 8th NRPC
meeting after deliberations it was agreed in principle that the expansion of ULDC scheme
shall be taken up by the constituents independently. It was also decided that the
communication parameters, minimum standards and time frame would be finalized.
POWERGRID help may also be sought by the constituents for up gradation/expansion of
the ULDC scheme. As a follow up the issue was deliberated in the 23rd USMG meeting
held on 25th April 2009 at NRPC. The relevant portion of the NRPC and USMG MOM are
enclosed at annexure-I. Accordingly NRPC has constituted a Sub-Committee comprising
of
the
following
members
vide
their
letter
of
reference
NO.
SE
(i) Framing of guidelines for the specifications to be finalized by the constituents for
expansion/replacement of SCADA/EMS system for grid operation;
(ii) Framing of Guidelines for integration of new substations/power plants to the control
centers;
(iii)Framing of guidelines for finalizing specifications for inter control centre (LDCs)
connectivity for data exchange; and
(iv) Design criteria for communication system for LDC facilities.
Major components of the Northern Region ULDC Scheme are EMS/SCADA system, RTUs
and Microwave (MW), Fiber Optic (FO), PLCC based communication system along with
auxiliary power supply system. The SCADA/EMS system has been installed at Northern
Regional Load Despatch Centre (NRLDC) under central sector and at SLDCs/Sub-LDCs in
the state sector. The RTUs and communication equipment are installed at substations and
power plants in the states as well as in the central sector. Under ULDC Project
communication systems comprising of Power Line Carrier Communication (PLCC),
Microwave and Fiber Optic based communication were established. PLCC is being used to
transfer data from RTU locations to the nearest wide band / control center locations.
Wideband communication system comprising of Microwave and Fiber Optics is being used
for data transfer between control centers and from substations located on wideband nodes.
Microwave links have been established with 8 Mbps capacity, whereas fiber optic links are
established with STM-1 (155 Mbps) capacity. As regards functionality at various control
centers, it may be mentioned that SCADA and EMS have been provided at NRLDC as well
as at all the SLDCs with almost identical functionality whereas at Sub-LDCs only SCADA
facility has been provided with storage of data for limited period.
The ULDC scheme which has been in operation since 2002 was conceptualized in late
1990s, the specifications were framed around 1995-96 and orders were placed by 1998.
Subsequent to commissioning, during the last around seven years the users have gained
wide experience on the system, at the same time several changes have taken place within
and outside organizations in a very short span of timed, the power system is growing at a
very fast speed, the technology changes in the field of communication and information
technologies have also taken at equal pace.
With the above background, in order to meet the growing demand of the users due to
structural and regulatory changes, expansion of power system requirements and technical
obsolesce
the
committee
has
examined
the
various
aspects
of
ULDC
SLDC
UPSEB
Sub-LDC
(RTUs)
SLDC
HVPNL
Sub-LDC
(RTUs)
RTUs - 36
SLDC
PSEB
Sub-LDC
(RTUs)
Moradabad
(17)
Panipat
(12)
Patiala
(12)
Panki
(13)
Narwana
(15)
Jalandhar II
(20)
Rishikesh
(27)
Dadri
(14)
Lalton
Kalan
(8)
Sultanpur
SLDC
RVPNL
Sub-LDC
(RTUs)
3
Heerapura
( 12)
Bhilwara
(29)
Kota
(11)
Ratangarh
(12)
SLDC
J&K
SLDC
BBMB
SLDC
HPSEB
SLDC
DVB
Sub-LDC
(RTUs)
Sub-LDC
(RTUs)
Sub-LDC
(RTUs)
Sub-LDC
(RTUs)
Gladini
(8)
Dadri
(5)
Hamirpur
(8)
Bawana
(5)
Bemina
(8)
Ganguwal
(6)
Kunihar
(8)
Bamanauli
(12)
Jalandhar I
(4)
Gazipur
(8)
Panipat
Gopalpur
CPCC
Kanpur
RTUs - 6
Hardware Architecture
The distributed hardware configuration of the existing SCADA/EMS system includes the following
subsystems:
SCADA/EMS servers
support the functions of SCADA, Real-time Dispatching, Power System Analysis and
Operation Scheduling functions.
Operate in a primary-standby relationship for redundancy purposes.
Consist of two high performance Digital 64-bit RISC based AXP machines
(Alphaservers) in a dual redundant configuration (Primary and Stand-by)
Communication Front-ends(CFEs) that drives the serial communication lines connected to the
RTUs.
ICCP (Inter-Control centres Communications Protocol)
servers
that
support
inter-site
Management
Console
that
provide
the
Configuration
management,
fault
SCADA/EMS
Servers
Communication
Front-end
ISR
Servers
DTS
Server
ICCP
Servers
Operator
Consoles
(*)
DTS
Operator
Consoles
WAN
Routers
Development
Server
Development
Console
Network
Management
Console
Peripheral
Equipment
To
SLDCs,
To RTUs
Remote
VDUs
Headquarters
(*) Five 2-CRT consoles, two 1-CRT consoles and one Operations Scheduling Console
Design Criteria
The design criteria adopted for ULDC scheme was constrained with the available technology and
organisational set up prevailing at that time, these aspects have gone through several changes.
Due to organisational and regulatory changes in the power sector the functional requirements of
the constituents have also undergone change. With the availability of advance cost effective,
techno-economic products, we are now in a better position to meet these requirements. In the
following paragraphs the design considerations which need changes especially in respect of
integration of various components have been elaborated.
Now in stead of conventional transducers , Multi function transducers (MFTs) are also available
which gives the output in Modbus protocol in digital format for all types of values being acquired
under ULDC, the MFTs can also provide no of additional parameters
current, phase voltage, energy values etc. At the same time the wiring in the panels is also
reduced. As MFTs provide digital output it is directly connected to the communication port of the
RTUs removing the requirement of analog input card in the RTUs, this will effectively reduce the
cost of RTUs as well wiring the panels. Therefore, it would be better option to adopt MFTs in
stead of individual transducers. The diagram below indicts the existing as well the proposed
arrangement.
4 -2 0 m
M W
T
M
4 -2 0 m
4 -2 0 m
4 - 2 0 m
V A r
V o lt
P T
F r e q
Existing Arrangement
T r a n s d u c e r
CT
M O D B US/
M u ll ti F u n c ti o n
T ra n sd u ce r
PT
Proposed Arrangement
3
IE C 60 87 0- 51 03
RTU Design:The analog data is acquired by the RTU through the transducers as explained above. The digital
data is directly wired to the RTUs. The design of existing RTUs is robust and flexible. The RTUs
are operating in uncontrolled environment. The analog and digital I/O can be added by addition
for electronic cards. However, there is no back up to Power Supply and CPU of RTUs which is
available in present day RTUs. The back ups to Power Supply and CPU would make RTU more
reliable. Further non availability of spares at reasonable price making it difficult to expand the
existing RTUs.
RTU to Communication Front End (CFE):- Around 350 RTUs were installed in the ULDC project
in various constituents which reports to the Sub-LDC or SLDC. The Central Sector RTUs are
reporting directly to NRLDC. The protocol adopted for RTU data to control centre is IEC 60870-5101. As IEC-60870-5-101 protocol has been used for RTU data communication, one serial port is
required in the CFE for each RTU. This has its limitations in management for number of spares,
expandability due to interdependency between hardware and software ,obsolescence and OEM
dependency.
With the introduction of IEC 60870-5-104 protocol ,the dependency on the hardware and software
has reduced. In this protocol the communication between RTU and CFE is IP based instead of
serial connection, thus removing the serial interface card and hardware dependency on the
OEM.
Control panels is being replaced by Intelligent Electronic Devices (IEDs) and the Protocol IEC
61850 is being adopted for the communication among different equipments of the substation.
However IEC 61850 protocol is presently limited to within substation itself and the protocol IEC
61870-5-101/104 is still followed for communication between SAS and control centre
Control centre
Substation/Plant
IEC 60870-5-101
IEC
3
01
-5-1
0
8
60
Serial
Serial
Serial
SAS
GATEWAY
IED
IEC 61850
RTU
Serial
Transducer
4-20mA
CFE
Existing Arrangement
CFE
IP
SAS
C
IE
4
-10
5
0
87
60
IP
RTU
GATEWAY
IED
IEC 61850
Control centre
IEC 60870-5-104
IP
Substation/Plant
MFT/
MODBUS
Energy
Meter
Current Practice
The usage of IEC 60870-5-104 protocol has its implication on the design of communication
network also. Presently most of the RTUs are reporting on PLCC at least on first half. IEC
60870-5-104 protocol works on IP based communication, analog Communication can not meet
this requirement. Therefore IEC 60870-5-104 protocol can be adopted selectively only as long as
practice of usage of analog PLCC is continued. This aspect of communication design has been
discussed in detail in the subsequent Para.
Database Model:The database modeling concept being followed in Northern Region is based on Common
Regional Model both for content as well as tools/process. In the present procedure for data base
modification the excel sheet of data base is made by the constituents which is forwarded to
NRLDC. The changes in database are incorporated in SCADA System at NRLDC which are then
propagated to other control centers. The procedure being followed is described in the diagram
given below. Non timely updating of data modeling results into poor visualization of the Network.
Therefore, if any constituent is not able to update its ICCP database due to any reason its
implication is reflected on the usage of functions by the other constituents also therefore
interdependency of the constituents is quite high as far as data base modeling is concerned this
as of data base model needs review.
Further at the time of ULDC implementation the electrical boundaries of the region were very
clearly defined, now Northern Region has been interconnected with other regions through several
synchronized links which are planned to increase in future, the regional electrical boundaries
have become multiple and are difficult to manage without regular data update in sync with other
regions.
Northern Region
constituents make the commitment for purchasing power in the power plants installed in other
regions or even in other countries. This may necessitate the model and data exchange between
different vendors and various regions at RLDC level. The complications in electrical network
modeling due to increased interconnections between the regions, regional level modeling would
not be adequate. Further under ULDC Scheme SCADA/EMS system in region is from a single
supplier. For expansion/upgradation requirement SCADA/EMS system of a single vendor in a
region would not help due to increased interconnection among regions. Keeping all this in view it
is suggested that each constituent take the responsibility of modeling of the network under its
jurisdiction and exchange the electrical model with other constituents. At NRLDC level regional
model up to a certain voltage level would only be required. The model and data exchange
between constituents and NRLDC may be required, this shall be possible only when the common
standard is followed by all the constituents.
Co m m o n D A TA
B ase M o d el
S te p 4
S te p 3
ep
S te p 2
St
S te p 1
RLDC END
S te p 3
ep
M e rg e a t
RSCC
End
D BB Tool
4
ep
t
S
St
Step 5
DBB
M a s te r
F ile s ( E x c e l)
DBB
M a s te r
F ile s
In c re m e n ta l
DBB
F ile s
SLDC END
Co m m o n D A TA
B ase M o d el
DBB Tool
e
St
C o p y o f M a s te r D B B f ile s a n d M a s te r D a ta B a s e
m o d e l to A L L S L D C s b y R L D C
I n c r e m e n ta l C h a n g e s b y S L D C fo r th e ir A r e a s in
D B B file s , im p o r t in to M a s te r D a ta b a s e M o d e l
a n d v a lid a tio n .
C o p y o f v a lid a t e d in c r e m e n ta l D B B file s fr o m
3
S L D C to R L D C
I m p o r t o f In c r e m e n ta l D B B file s o f S L D C a n d
R L D C in t o m a s t e r d a t a b a s e m o d e l a n d v a lid a t io n
a n d c r e a t io n o f fin a l C o m m o n d a ta b a s e m o d e l a t
RLD C end
The standard for CIM (common information model) data modeling for EMS applications (IEC
61970) has been published to take care of the above issue. The database handling can be
harmonized by standardizing the data model using CIM in Indian Context. Hence it is important to
develop the CIM model content applicable to our system
centre to control centre communication is ICCP. The central sector data and data of other
constituents is acquired by the all the constituents from the NRLDC. Now since the constituents
are purchasing power from other power plants installed in other regions also, the generation data
of these plants would be required at the SLDC level. Presently NRLDC is acquiring the data of
other regions through NLDC which can be shared with constituents also.
The implementation and configuration setting for ICCP exchange requires support from the
original contractor. The support of Siemens for Integration of Maharashtra SLDC with WRLDC
and support of GE for integration of WRLDC& SRLDC with NLDC were taken. In Uttrakhand
case, the services of AREVA has also been envisaged for modification at NRLDC end. The
requirement of such support services would increase if the SSCADA systems of different venders
are installed in various constituents, timing of installation would also be an issue.
Apart from above , Secured ICCP protocol and WAN routers with Firewalls need to be deployed
for enhancing the security of system. However secure ICCP can not be unilaterally implemented
at one node as it will need matching support from remote node also.
Time Synchronization:- In the NR ULDC system, A GPS clock is available at each Control
centre which synchronizes the CFE. The RTUs are being time synchronized from the CFE using
the feature of IEC 60870-5-101 protocol. With the adopted methodology of time synchronization
inter RTU time accuracy of around 10 milliseconds is expected. When IEC 60870-5-104 protocol
is used for
suggested that each RTU is provided with GPS for time synchronization as the cost of GPS is not
very high.
The events are being time stamped at RTU and maintained in file system which is transferred to
control centre either on demand or periodically. Further these files are being merged at SLDC
and NRLDC through a script.
Recently while integrating the SAS system it has been observed that time stamped events are not
being maintained in the file system but it is being transferred as an event with time stamp
message to the control centre as part of IEC 60870-5-101 protocol implementation.
Accordingly another script was written to merge the file system and SOE time stamped message
into the separate file.
The ICCP protocol implementation has also the feature to transfer the events with time stamp.
However its deployment need overall change in SOE handling and a switch to making all SOE as
part of ISR is recommended.
Number Of Control Centers:- In NR-ULDC scheme the number of Sub-LDCs were chosen by
each constituents as per area of responsibility. Sub-LDC can observe the network of their area
only. If one Sub-LDC desires to check the Status of neighboring area of their State it is not
feasible in the present format. After Electricity Act 2003, SLDC is the apex body for the operation
within its jurisdiction. The responsibility has increased and accordingly the work load in the
system. Operators would need enhanced visibility of the system. The underlying control centers
of the discom would also need exchange of data with state load dispatch centers. Further with the
growing importance of control centers for Power system Operations and enhanced security threat
, it has become the need of the hour to create a backup Control centre. It is suggested that the
back up SLDC can be created at one of the Sub-LDCs. But the constituents who do not have any
Sub-LDC and NRLDC would need to determine the location for backup SLDC. The data flow from
both the RTUs to both SLDCs (Main and backup) would be directly from the RTUs preferably. In
case this is not possible due to communication constraints, some of the RTUs can be converted
as Data concentrator which can communicate to both the SLDCs (Main and Back Up) Other SubLDCs can be provided with the operator console of SLDC. The main and backup Control Centre
would provide no of advantages over the existing arrangements. A Comparison chart for the
comparison of backup Control centre vs SubLDC is given in the table below:-
S.No.
Subject
In
case
of
Emergency
at
Main
SLDC
Control centre
Database
Maintenance
Manpower
Communication
channel rerouting
ICCP
CFE
ICCP
NRLDC
SLDC
3
ICCP
WB Location
RTU
MUX
CFE
CFE
Sub
LDC
Sub
LDC
NRLDC
ICCP
CFE
Main
SLDC
Rem
ote
CFE
ICCP
101
SLDC
CFE
CFE
Remote CFE
Backup
Remote
Console
WB Location
RTU
cum DC
MUX
RTU
RTU
RTU
RTU
RTU
RTU
Energy Management system:-
3.0
RTU
RTU
4.0
5.0
These will necessitate in the development of applications for the following applications in the
Indian Context:A.
Scheduling Application
B.
C.
D.
E.
The Transmission capacity has to be declared by each SLDC and RLDC for open Access
Applications and Power exchange. This will need the modeling of RLDC and SLDC separately as
per their jurisdiction. The modeling of the boundary area or the equivalency and data exchange
criteria for Power flow Applications will need to be taken care during design of the Power flow
Applications.
Communication System:In NR ULDC scheme, the communication System from RTU to first wide band node/ Control
centre is mostly on PLCC and Communication between control centers is on Wideband
communication
ULDC system, for redundancy of the communication network between control centers the
communication system was strengthened by providing backup bandwidth from POWERGRID
telecom Network. The wide band communication diagram is attached at Appendix-I. Now DOT
has decided to allocate the Micro Wave frequency band to other service providers therefore now
MW links are to be replaced with FO based communication system. As the Power System is
expanding very fast, the need for wide band expansion also needs to be followed in similar
fashion. As per revised grid code any utility who wants to connect to the CTU system has to
provide the data and communication system up to CTU data collection Point. The relevant para
after amendment has been reproduced below. (The CERC order is attached at Annexure-II)
Similar provision may come from SERC for any applicant who want to connect to STU system. In
view of this the data collection point has to be defined as the wide band node. These nodes need
to be expanded and upgraded in line with the Transmission System Planning. In other words the
transmission planning and communication system planning should be in tandem. In case the
communication network is not expanded the new agencies may be forced to go for lease lines
between their substations/generating stations and RLDC/SLDC. Several Leased lines at control
centre could create unmanageable problems due to following reasons:5.0 Low bandwidth (less than E1) would not be available in the times to come especially for point
to point application as the commercial communication technology is gradually evolving
towards IP based network.
6.0 If low bandwidth network is not available, primary multiplexers may be required by each
agency. Several primary multiplexers at the control centre would create logistic as well as
integration problem at the control centers.
7.0 The leased lines can not be monitored by the control centers and may not be as reliable as
our captive communication network especially when the Power plants/Substations are at
remote locations.
Now the technology for Digital PLCC is also available and can be considered for the
communication planning for some standalone bandwidth requirement at RTU node. The digital
PLCC is also suitable for IEC- 60870-5-14 protocol usage.
Security Issues:- In the SCADA/EMS system design, the provision of availability of real-time
data was limited mainly to the operators only. For management the provison of Remote VDU was
provided on the SCADA/EMS LAN only. After restructuring of Power sector the number of stake
holders has increased and it has become now necessary to share the real time data on the public
domain. Accordingly the data was shared on public domain with firewall provision. The typical
Architecture being followed at NRLDC is given below:-
External
External
user
user
side
side
CICSO
firewall
DMZ
ZONE
web & email
server
SCADA
system
Router
POWERGRID
intranet
Similar interface has also been done by HVPNL,DTL, HPSEB, RRVPNL and
the data is shared on public domain . Since the system is integrated the cyber security
requirement may need strengthening.
The available SCADA/EMS system in NR in working on VMS operating system. Open VMS in an
old operating system, the virus penetration probability to this old operating system is
comparatively less, therefore the operating system is acting as shield to virus threat up to some
extent but this situation would not continue for long as the software developers have already
switched over to other operating systems. Presently the suppliers are providing the ICCP on
window based operating system, other applications are either already available on LINUX or in
the proceeds of switching over to LINUX operating system. It is also proposed in subsequent
paras that web system is to be provided with SCADA System to provide data to users other than
control room staff. This further necessitates the comprehensive cyber security systems.
So a policy needs to be framed in line with NERC for cyber security for all the stakeholders. The
security design needs regular auditing for threat perceptions by third Party. The cyber security
threat to the power system is a burning issue. Govt of India is also setting up a special cell for
countering cyber attacks and cyber terrorism which will entrust the responsibility of uniform
security measures to a particular organization for each sector/sub sector.
Training Simulator:- Continuous training is a necessity for control room operators and other
supporting engineers. Under ULDC Project a Digital simulator has been provided at NRLDC
which is to used for training of all the constituents engineers. Since common data base model
was adopted, training at one location for all the constituents was a very good idea as the trainees
can visualize the various power system situations at regional basis as well as at State level.
The operation business for State Load dispatch center operation is becoming different than that
of Regional Load dispatch operation and each SLDC has its own peculiarities and issues . The
need of training simulator is a need of the hour at SLDC also.
O&M: - In NR ULDC SCADA/EMS project provision was made for One Year Maintenance
contract during Warranty period and 2 Years maintenance contract after Warranty period. After
the completion of the maintenance period, AMC was awarded to original supplier on single tender
basis resulting into high O&M cost. It would be better to include the life time maintenance cost as
part of the original contract also so that AMC cost also becomes the part of the competitive price.
Tariff Mechanism and Life time:- The investment made by POWERGRID under ULDC project
is being recovered as tariff over a period of 15 years as the commercial life of the project has
been considered accordingly. However, the Pradhan Committee report and the Task force for
implementation of the report have recommended that life of computer Hardware and Software
should be 7 to 10 years. The draft regulations of CERC for tariff and charges of LDC facilities
also recommends the depreciation of computer hardware in 7 years and software in 3 years.
Recommendation:- Based on the above discussions the committee recommends the following
issues to be considered:2.0
All new RTUs and Substation Automation System for Generating Stations and
Substations to be procured with IEC 60870-5-101 protocol as well as IEC 60870-5-104
protocol. Once the IEC- 60870-5-104 protocol is implemented at the reporting control
center and IP based communication system is extended to the substation to be
integrated, the RTUs/SAS would require IEC-60870-5-104 protocol only. It should be
aimed to switch over to IEC60870-5-104 protocol as early as possible.
3.0
RTUs protocol interoperability profile to be followed both for RTU as well as control
centre is attached at Annexure-II.
4.0
All new RTUs to be procured should have feature of DATA Concentrator redundant
Power Supply and Redundant CPU.
5.0
All new RTUs to be procured with GPS system. A possibility of exploring the interface
with existing GPS of Substation need to be explored.
6.0
7.0
8.0
For some time control centre shall operate on both IEC 60870-5-101 as well as IEC
60870-5-104 protocol with ultimate intent to switchover to IEC 60870-5-104 protocol. New
CFE should be procured accordingly.
9.0
10.0
One of the Existing Sub_LDC should be converted as Back UP SLDC. CFE of existing
Sub-LDC should be made as Remote CFE of existing SLDC.
11.0
Database modeling should be Constituent specific and IEC 61970-CIM for EMS system
is to be adopted.
12.0
13.0
14.0
Data and communication System Planning should be made part of the transmission
system planning.
15.0
Security policy guideline and regular audit etc. is to be adopted by the agency identified
by GOI task force for countering cyber terrorism and cyber attacks.
16.0
17.0
18.0
The time line of the above implementation by all SLDCs should be matching with
termination of running AMC contract.
Annexure-I
Annexure-II
INTEROPERABILITY PROFILE of IEC 60870-5-101 protocol
This companion standard presents sets of parameters and alternatives from which subsets have to be
selected to implement particular telecontrol systems. Certain parameter values, such as the number of octets
in the COMMON ADDRESS of ASDUs represent mutually exclusive alternatives. This means that only
one value of the defined parameters is admitted per system. Other parameters, such as the listed set of
different process information in command and in monitor direction allow the specification of the complete
set or subsets, as appropriate for given applications. This clause summarizes the parameters of the previous
clauses to facilitate a suitable selection for a specific application. If a system is composed of equipment
stemming from different manufacturers it is necessary that all partners agree on the selected parameters.
The selected parameters should be marked in the white boxes as follows:
Note :
In addition, the full specification of a system may require individual selection of certain
parameters for certain parts of the system, such as the individual selection of scaling factors for
individually addressable measured values.
SYSTEM OR DEVICE
(System-specific parameter, indicate the definition of a system or a device by marking one of the following
with an
System definition
Controlling station definition (master)
Controlled station definition (Slave)
NETWORK CONFIGURATION
(Network-specific parameter, all configurations that are used are to be marked with )
Point-to-point
Multiple point-to-point
Multipoint-party line
Multipoint-star
Unbalanced interchange
circuit V.24/V.28
Recommended if >1 200 bit/s
Balanced interchange
circuit X.24/X.27
100 bit/s
200 bit/s
300 bit/s
2 400 bit/s
4 800 bit/s
9 600 bit/s
600 bit/s
1 200 bit/s
(for unbalanced transmission only)
2 400 bit/s
4 800 bit/s
9 600 bit/s
19 200 bit/s
38 400 bit/s
56 000 bit/s
64 000 bit/s
Unbalanced interchange
circuit V.24/V.28
Recommended if >1 200 bit/s
Balanced interchange
circuit X.24/X.27
100 bit/s
2 400 bit/s
2 400 bit/s
200 bit/s
300 bit/s
4 800 bit/s
9 600 bit/s
600 bit/s
1 200 bit/s
(for unbalanced transmission only)
4 800 bit/s
9 600 bit/s
19 200 bit/s
38 400 bit/s
56 000 bit/s
64 000 bit/s
Balanced transmission
Unbalanced transmission
Frame length
255 Maximum length L (number of octets)
APPLICATION LAYER
Transmission mode for application data
Mode 1 (Least significant octet first), as defined in clause 4.10 of IEC 870-5-4, is used exclusively in this
companion standard.
Common address of ASDU
(system-specific parameter)
One octet
Two octets
Two octets
Three octets
One octet
Structured
Unstructured
Cause of transmission
(system-specific parameter)
One octet
Single-point information
Double-point information
Bitstring of 32 bit
Integrated totals
<1> :=
M_SP_NA_1
<2> :=
M_SP_TA_1
<3> :=
M_DP_NA_1
<4> :=
M_DP_TA_1
<5> :=
M_ST_NA_1
<6> :=
M_ST_TA_1
<7> :=
M_BO_NA_1
<8> :=
M_BO_TA_1
<9> :=
M_ME_NA_1
<10> :=
M_ME_TA_1
<11> :=
M_ME_NB_1
<12> :=
M_ME_TB_1
<13> :=
M_ME_NC_1
<14> :=
M_ME_TC_1
<15> :=
M_IT_NA_1
<16> :=
M_IT_TA_1
<17> :=
M_EP_TA_1
<18> :=
M_EP_TB_1
<19> :=
M_EP_TC_1
<20> :=
M_PS_NA_1
<21> :=
M_ME_ND_1
Single command
Double command
Set point command, scaled value(required only for analog output command)*
Bitstring of 32 bit
<45> :=
C_SC_NA_1
<46> :=
C_DC_NA_1
<47> :=
C_RC_NA_1
<48> :=
C_SE_NA_1
<49> :=
C_SE_NB_1
<50> :=
C_SE_NC_1
<51> :=
C_BO_NA_1
<70> :=
M_EI_NA_1
End of initialization
Interrogation command
Read command
<100> :=
C_IC_NA_1
<101> :=
C_CI_NA_1
<102> :=
C_RD_NA_1
<103> :=
C_CS_NA_1
Test command
<104> :=
C_TS_NA_1
<105> :=
C_RP_NA_1
<106> :=
C_CD_NA_1
Parameter activation
<110> :=
P_ME_NA_1
<111> :=
P_ME_NB_1
<112> :=
P_ME_NC_1
<113> :=
P_AC_NA_1
File ready
Section ready
Segment
Directory
<120> :=
F_FR_NA_1
<121> :=
F_SR_NA_1
<122> :=
F_SC_NA_1
<123> :=
F_LS_NA_1
<124> :=
F_AF_NA_1
<125> :=
F_SG_NA_1
<126> :=
F_DR_TA_1
Special use
(private range)
<137> :=
C_RC_NB_1
Remote initialization
General interrogation
(system or station-specific parameter)
Global
Group 1
Group 2
Group 3
Group 4
Group 5
Group 6
Group 7
Group 8
Group 9
Group 10
Group 13
Group 14
Group 15
Group 16
Group 11
Group 12
Clock synchronization
(station-specific parameter)
Clock synchronization (optional, if GPS is used for time synch. of the RTU)*
No additional definition
Short pulse duration (duration determined by a system parameter in the outstation)
Long pulse duration (duration determined by a system parameter in the outstation)
Persistent output
Counter request
Threshold value
Smoothing factor
Low limit for transmission of measured value
High limit for transmission of measured value
Parameter activation
(object-specific parameter)
Data Unit
type as per
IEC
ASDU-11
ASDU-1
ASDU- 2
ASDU-3
Description as
per IEC
Data polling
method
Measured value
scaled value
Single point
information
As cyclic data on
Class 2 polls
By exception
(spontaneous)
and on periodic
Group scan
By exception
(spontaneous)
Single point
information with
time tag
Double point
information
ASDU-4
Double point
information with
time tag
Pulse accumulators
ASDU-15
Integrated totals
Interroga
tion
group
Transmitted
after Class-X
request
Class 2
Info Obj.
Address
range
8448-
Group-1
Class 1 on
exception,
Class 1 after
Group 1 scan
Class 1 on
exception
376-
Class 1 on
exception,
Class 1 after
Group 1 scan
Class 1 on
exception
256-
Class 2
12544-
By exception
(spontaneous)
and on periodic
Group scan
By exception
(spontaneous)
Group-1
By periodic
counter
interrogation
Group-1
(counter
interrogati
on)
376-
256-
Analog Outputs
(Setpoint)
ASDU-48
Digital Control
command (CB
Trip/Close)
ASDU 46
Set point
command
Normalized
value
Double
command
4.
5.
6.
7.
The RTU shall respond to the Master stations request for the at least the following commands as
per the protocol:
- Status of Link
- Reset of Link
- Delay acquisition command *
- Clock synchronization command *
- General interrogation command
- Interrogation of Scan group 1 command (all status data)
- Interrogation of Scan group 2 command (all analog data)
- Class 1/2 data polling
If supervisory control commands are envisaged, then SBO procedure is to be used.
RTU shall send all Analog and status data in response to the General interrogation command.
All digital inputs are to be assigned to Scan group-1.
Analogs are defined as periodic data and are sent to RLDC on Class 2 request. The periodicity
varies from 10 seconds to 15 seconds depending upon the quantity of data and available
bandwidth.
Digital input state changes are to be reported spontaneously by RTU as Class 1 data. The Digital
input data have higher priority than Analog values. An integrity scan is performed for all the
digital inputs using Scan group-1 at every 10 minutes interval.
37120
33024-