Lifting Plan

Lifting Plan No:-01


Project: - Al KHEESA PROJECT DN 071
Date: - -Contractor: - CGC jv SACYR
1. Equipment:What Type:2. Time: - 6:00 Am to 6:00 pm
From: --to
Brief Description Of Lifting Operation: - Hoisting up the ---unloading
of cement pipes.
(Please Descript what activity will going to do)
3. Name of appointed Person from Contractor:Mr. John Godstime
4. List means of identification (i.e. what clothing or color helmet etc will
identify them from other site workers.
Vest- Florescent Green
Safety helmet- GREEN.
5. Description of Loads:a. Weight- Max weight of load shall be 80% of SWL.
b. Characteristics- Miscellaneous types of materials, equipment
c. Method of lifting- Using web belt sling and shackle.
d. Center of gravity- Align with crane hook.
e. Lifting point or method of sling- To be determined by lifting supervisor.
6. Lifting Equipment or appliance to be used:a. Make / Model: - boom crane 19370
b. Maximum capacity 25 T
c. Main Boom Length- 10 M
d. Maximum Radius- 3 M
e. Safe Working Load- 25 T
7. Proximity Hazards:a. Overhead Power Lines- None

Lifting Plan

b.
c.
d.
e.
f.
g.

Underground Tunnels- None


Airports- None
Other Strictures- None
Underground Services- None
Other Carnages -None
Others (specify)-NA

8. Ground conditions & Appropriate Controls:Ground area is level and compacted Hardcore, concrete slab
Steel plate supports to be used for the outrigger base
Outrigger is fully extended
Width of access area is adequate to allow passenger of crane including full
extended outriggers.
9. Are Temp Workers involved in the lift.
Described- 4 workers for support the lifting team
10.
What demarcation will be used:a. Is the area an exclusion zone- Yes.
b. What barriers and signage- Isolate area with warning tape or orange
plastic net and warring signages. (Danger, Keep Out Signage)
11.
Control of load (tag lines etc)
Use of Tag line.
12.
Crane Rigging requirement (ground condition)Stable and level ground
outrigger base.
13.

Access/Egress (Lifting Equipment-vehicles etc.)

14.
Wind speed( what is maximum wind speed for safe lifting, how is it
recorded)- 25Knots(as per QCS 2010)
15.
Is lifting Open or blind? Describe of method of
signaling/dogging-(Specify the number of signalers to be used.)
One signalman is to be used. Communication is by hand signals, Visual
contact between operator and signalman is maintained. Whatever visibility is

Lifting Plan

not possible. Communication between operator and signalman shall be by


radio.
16.
Communication? (What means)
Communication between operator and signalman by hand signals and by
radio.
17.
Have appropriate CGC JV SACYR and crane operator checklist
been completed.Yes.
18.

Crane Operator Appointed Person (Contractor) Review & Date.

SignatureDate19.
Approved by CGC JV SACYR HSE Officer.
SignatureDateThe lifting plan is to be used no matter the type of lift; standard lifts may
need to be reviewed weekly to ensure nothing has changed. Should the
lifting operation come under scrutiny the lifting plan is evidence of
addressing all aspect pertaining to the planning of the operation. If lifts are
to be repetitive (standard) type then the one lifting plan can be put in place
and remain as long as no significant changes have taken place. However as
stated preciously it must be reviewed weekly by contractors appointed
person.
Note: - For all the Lifting operation must prepare lifting plan to submit HSE
Dept. before commencement. And attach together Lifting permit.
WORK AREA: ZONE

Lifting Plan

DEPT.
Name:
Date :
Signature :

Originator / ( )

Mr. John Godstime

HSE Manager /

Eng.Enrique Fjardo