Sunteți pe pagina 1din 137

Directional Well Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
Three items required for any
directional well
Build

rate
Hold inclination
Kick off point (KOP)

Assume two and calculate the


third

2006 PetroSkills LLC, All Rights Reserved

Planning
The

build rate can be chosen for any


number of reasons
To minimize the possibility of fatigue in
the drill pipe
Run an assembly that remains
steerable, rotary or motor
Minimize the possibility of a keyseat
Minimize torque and drag

2006 PetroSkills LLC, All Rights Reserved

Planning
The

hold inclination may be selected

Less than 10o, it is difficult to maintain


the direction of the wellbore
Greater than 30o, it becomes
increasingly hard to clean the cuttings
from the hole
Hole cleaning is the most difficult
between 45o and 60o
Above 60o, wireline tools may not fall in
an open hole
Above 70o, wireline tools may not fall in
cased hole

2006 PetroSkills LLC, All Rights Reserved

Planning
The

kickoff point can be selected


based on hole conditions
The kickoff point may be selected so
that the build section will be cased at the
end (selected based on casing seat)
It may be advantageous to drill a
troublesome portion of the well vertically
and get it cased
Directional drilling usually takes longer

2006 PetroSkills LLC, All Rights Reserved

Planning
If the troublesome zone has lost
circulation, LCM in the mud is hard on
MWD tools
A zone that sloughs substantially may
slough faster if sloughing is due to stress
and the well is drilled at an appreciable
inclination
It may be better to finish the build curve
and start drilling the hold section before
drilling a troublesome formation

2006 PetroSkills LLC, All Rights Reserved

Planning
Example 4-1 (on page 4-2)
shows how to determine the hold
angle when the build rate and
kickoff point have already been
selected
Kickoff

point is 2000 feet


Build rate is 2o/100 feet
Target TVD is 9800 feet
Target DEP is 2926 feet
Total depth is 10,000 feet TVD
2006 PetroSkills LLC, All Rights Reserved

Planning
Determine the hold inclination
and the detailed MD, TVD and
DEP for the well

2006 PetroSkills LLC, All Rights Reserved

Planning
The hole can be divided up into
sections
Vertical

to KOP

Build
Hold

or tangent to target
Hold or tangent to TD

2006 PetroSkills LLC, All Rights Reserved

Planning
Determine the MD, TVD and DEP
for the vertical to KOP section
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

Build
Hold to
Target
Hold to TD

2006 PetroSkills LLC, All Rights Reserved

DEP
0.00

Planning
Determine
the hold
inclination
from the
chart
Inclination
is 22o

22o

2006 PetroSkills LLC, All Rights Reserved

Planning
Determine the MD, TVD and DEP
of the build section
I 2 I1
MD
Br

22 0
MD
1100 feet
2 / 100

2006 PetroSkills LLC, All Rights Reserved

Planning

180 MD sin I 2 sin I1


TVD
I 2 I1

180 1100 sin 22 sin 0


TVD
1073.17
22 0
DEP

180 MD cos I1 cos I 2


I 2 I1

DEP

1801100 cos 0 cos 22


208.60
22 0

2006 PetroSkills LLC, All Rights Reserved

Planning
For the build section
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

Build

1100.00

1073.17

208.60

Hold to
Target
Hold to TD

2006 PetroSkills LLC, All Rights Reserved

DEP

Planning
You can also use the build up
tables in the Appendix

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate the MD, TVD and DEP
for the hold section
TVD rem

= 9800 2000 1073.17

TVD rem

= 6726.83

DEP rem

= 2926 0 208.60

DEP rem

= 2717.40

MD

of the hold section

2006 PetroSkills LLC, All Rights Reserved

Planning
MD

DEP
sin I

2717.40
MD
7254.01
sin 22

Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

Build

1100.00

1073.17

208.60

Hold to
Target

7254.01

6726.83

2717.40

Hold to TD
2006 PetroSkills LLC, All Rights Reserved

DEP

Planning
Calculate the MD, TVD and DEP
of the hold to TD
The TVD is 200.00 feet from 9800
feet to 10,000 feet
TVD
MD
cos I
MD

200
215.71
cos 22

2006 PetroSkills LLC, All Rights Reserved

Planning
DEP TVD tan I

DEP 200 tan 22 80.81

Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

Build

1100.00

1073.17

208.60

Hold to
Target

7254.01

6726.83

2717.40

215.71

200.00

80.81

10,570.72 10,000.00

3006.81

Hold to TD
Total

2006 PetroSkills LLC, All Rights Reserved

DEP

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
Class Problem Problem 1 on
page 4-39
Given

the target data in Example 1


Target TVD is 9800 feet
Target DEP is 2926 feet
Build rate is 2o/100
Hold inclination is 35o
Calculate the KOP
2006 PetroSkills LLC, All Rights Reserved

Planning
Solution
Draw

a picture to determine what


information you have, what can be
calculated and what is needed

2006 PetroSkills LLC, All Rights Reserved

Planning
Can

calculate
the
change in
TVD and
DEP for
the build
curve

TVD of build section


DEP of build section
Inclination = 35
9800
TVD of hold section
DEP of hold section

2926

2006 PetroSkills LLC, All Rights Reserved

Planning
Determine

the MD to get to 35 at a
build rate of 2/100 feet
I 2 I1
MD
Br

35 0
MD
1750 feet
2 / 100

2006 PetroSkills LLC, All Rights Reserved

Planning

180 MD sin I 2 sin I1


TVD
I 2 I1

180 1750 sin 35 sin 0


TVD
1643.18
35 0
DEP

180 MD cos I1 cos I 2


I 2 I1

DEP

1801750 cos 0 cos 35


518.09
35 0

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
You

have the departure


of the build
TVD of build section
section and total departure so you can
DEP of build section
calculate the departure of the hold
Inclination = 35
section
9800
DEPhold = 2926 518.09 =TVD
2407.91
of hold section
From

the right triangle in theDEP


hold
of hold section
section, the TVD of the hold section
can be calculated
2926

2006 PetroSkills LLC, All Rights Reserved

Planning
tan I

DEPhold
TVDhold
TVD of build section

TVDhold

DEPhold 2407.91

DEP
3438of.85
build section
tan I
tan 35
Inclination = 35

The

kickoff9800
point can be calculated
TVD of hold section
from the target TVD less the
hold TVD
and the build TVD
DEP of hold section
KOP = 9800 3438.85 1643.18
KOP = 4717.97 feet
2926

2006 PetroSkills LLC, All Rights Reserved

Planning
There are many ways to drill a
directional well
Example 4-2 (page 4-13) shows
drilling the same directional well
using a Type II directional well or
S curve

2006 PetroSkills LLC, All Rights Reserved

Planning
Example 4-2
KOP

= 2000
Build rate = 2.5o/100
Drop rate = 1.5o/100
Target TVD = 9800
Target DEP = 2926
Total depth = 10,000 TVD

2006 PetroSkills LLC, All Rights Reserved

Planning
Determine
hold
inclination
from the
chart
Hold
inclination is
24o

2006 PetroSkills LLC, All Rights Reserved

24o

Planning
Determine the MD, TVD and DEP
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

Build
Hold
Drop
Vertical to TD

2006 PetroSkills LLC, All Rights Reserved

DEP
0.00

Planning
Determine the MD, TVD and DEP
for the build and drop sections
Can be calculated using the
radius of curvature calculations
or can use the buildup charts
Dropping from 24o to 0o will give
the same TVD and DEP as
building from 0o to 24o
2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
Build and drop sections
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

960.00

932.17

198.14

1600.00

1553.62

330.23

Build

DEP

Hold
Drop
Vertical to TD

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate the TVD and DEP of
the hold section
TVD rem

= 9800 2000 932.17


1553.62 = 5314.21
DEP rem = 2926 198.14 330.23 =
2397.63

Calculate the MD of the hold


section
2006 PetroSkills LLC, All Rights Reserved

Planning
MD ( TVD 2 DEP 2 )0.5
MD (5314.212 2397.63 2 )0.5 5830.05'

2006 PetroSkills LLC, All Rights Reserved

Planning
The hold section can be entered
into the table
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

Build

960.00

932.17

198.14

Hold

5830.05

5314.21

2397.63

Drop

1600.00

1553.62

330.23

Vertical to TD

2006 PetroSkills LLC, All Rights Reserved

DEP

Planning
Add the vertical to total depth
Section

MD

TVD

Vertical to
KOP

2000.00

2000.00

0.00

Build

960.00

932.17

198.14

Hold

5830.05

5314.21

2397.63

Drop

1600.00

1553.62

330.23

200.00

200.00

0.00

10,590.05 10,000.00

2926.00

Vertical to TD
Total

2006 PetroSkills LLC, All Rights Reserved

DEP

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning
The hold inclination can also be
calculated using trigonometry
You draw a picture of the well
and then solve for the angle of
inclination based on the
triangles

2006 PetroSkills LLC, All Rights Reserved

Planning
r = 2864.79

2000

D
I

9800
2006 PetroSkills LLC, All Rights Reserved

7800

The well has a


kickoff point of
2000, a build rate
of 2/100, and a
target of 9800 TVD
and 4060 DEP
Calculate the
inclination I

B
DEP = 4060

Planning
r = 2864.79

2000

D
I

7800

Calculate the length


of line BC from the
DEP and the radius
of curvature of the
build

BC 4060 2864.79
BC 1195 .21'

9800
2006 PetroSkills LLC, All Rights Reserved

B
DEP = 4060

Planning
r = 2864.79

2000

D
I

BC
AB
1195 .21
A tan 1

7800

tan A

7800

Calculate angle A of
triangle ABC where
B is a right angle

A 8.71

9800
2006 PetroSkills LLC, All Rights Reserved

B
DEP = 4060

Planning
Calculate the length
of side AC

r = 2864.79

2000

AB
cos A
AC
7800
AC
cos 8.71
AC 7891.04

9800
2006 PetroSkills LLC, All Rights Reserved

7800

B
DEP = 4060

Planning
r = 2864.79

2000

D
I

AD
AC
1 2864 .79
A cos

7891.04

7800

Calculate angle A of
triangle ADC where
D is a right angle

cos A

A 68.71

9800
2006 PetroSkills LLC, All Rights Reserved

B
DEP = 4060

Planning
Calculate the angle
A of DAB

r = 2864.79

2000

I 68.71 8.71

7800

I 60.0

9800
2006 PetroSkills LLC, All Rights Reserved

B
DEP = 4060

Planning
r = 2864.79

2000

D
I

I 90 60.0

7800

Calculate the
inclination required
to hit the target

I 30.0

9800
2006 PetroSkills LLC, All Rights Reserved

B
DEP = 4060

Planning
The hold inclination can also be
calculated using a method
developed by Wiggins, et. al.
called the single equation
Single equation simplifies
horizontal, directional planning
However, a number of equations
must be solved before using the
single equation
2006 PetroSkills LLC, All Rights Reserved

Planning
The paper is still one of the
simplest methods for calculating
the hold inclination
It works for both a type I and
type II well
It even works for horizontal wells
with a tangent section

2006 PetroSkills LLC, All Rights Reserved

Planning
r1

180
B r

(4-1)

r2

180
Br

(4-2)

R r1 r 2

(4-3)

TVD TVD4 TVD1

(4-4)

X DEP4 R

(4-5)

L TVD X R

2 1/ 2

TVD R X L

R 2 L2

I sin 1

(4-6)

2006 PetroSkills LLC, All Rights Reserved

Single Equation

(4-7)

Planning
Nomenclature

TVD1

r1
I
TVD2

True Vertical Depth


I
TVD3

TVD4

I
DEP2
DEP3
DEP4

Departure
2006 PetroSkills LLC, All Rights Reserved

r2

Planning
The equations can be used to
determine the hold inclination in
Example 4-3 (page 4-24), which
is the same problem as Example
4-1
TVD1

= KOP = 2000

TVD4

= Target TVD = 9800

DEP4

= Target DEP = 2926


2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate r1 and r2
r1

180
180

2864.79'
Br (2 / 100 )

eqn 4 1

r2 0 eqn 4 2

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate R from equation 4-3
R r1 r2 2864.79 0 2864.79

eqn 4 3

Calculate TVD from equation 4-4


TVD TVD4 TVD1 9800 2000 7800 eqn 4 4

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate X with equation 4-5
X DEP4 R 2926 2864.79 61.21 eqn 4 5

Calculate L with equation 4-6

L TVD X R
L 7255.12

1
2

7800 61.21 2864.79

2006 PetroSkills LLC, All Rights Reserved

1
2

eqn 4 6

Planning
Calculate the hold angle with equation
4-7
TVD R X L

I sin

R L

eqn 4 7

(7800 )(2864.79 ) ( 61.21)(7255.12)


I sin 1

2
2
2864
.
79

7255
.
12

I sin 1 0.3746
I 22.0 o

The hold inclination needs to be 22o


2006 PetroSkills LLC, All Rights Reserved

Planning
Example 4-4 on page 4-25
Given

the same problem as Example


4-2 on page 4-13
Calculate the hold angle with the
single equation for the Type II well

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate r1 and r2
r1

180
180

2291.83'
Br (2.5 / 100 )

eqn 4 1

r2

180
180

3819.72'
Br (1.5 / 100 )

eqn 4 2

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate R from equation 4-3
R r1 r2 2291.83 3819.71 6111 .55

Calculate TVD from equation 4-4


TVD TVD4 TVD1 9800 2000 7800

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate X with equation 4-5
X DEP4 R 2926 6111 .55 3185.55

Calculate L with equation 4-6

L 7800

L TVD X R
2

1
2
2

( 3185.55) 6111 .55


L 5799.71

2006 PetroSkills LLC, All Rights Reserved

1
2

Planning
Calculate the hold angle with equation
4-7
TVD R X L

I sin

R 2 L2

(7800 )(6111 .55) ( 3185.55)(5799.71)


I sin 1

6111 .55 2 5799.07 2

I 24.28 o

2006 PetroSkills LLC, All Rights Reserved

Planning
Class Problem Problem 2 on page
4-39
Target

TVD = 2850 m
Target DEP = 800 m
Drill an S curve or type II wellbore
KOP = 626 m
Build rate = 1.5o/30 m
Drop rate = 1.5o/30 m
Be vertical at a TVD of 2850 m
2006 PetroSkills LLC, All Rights Reserved

Planning
TVD4 = 2850m
TVD1 = 626m

626
1.5/30m
I
TVD2

Build = 1.5/30m
Drop = 1.5/30m
DEP4 = 800m

True Vertical Depth

Find the hold Inclination


I

TVD3

2850
I
DEP3

Departure

DEP2

800

2006 PetroSkills LLC, All Rights Reserved

1.5/30m

Planning
Calculate r1 and r2
r1

180
180

1145 .92 m
Br (1.5 / 30)

r2

180
180

1145 .92 m
Br (1.5 / 30)

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate R from equation 4-3
R r1 r2 1145 .92 1145 .92 2291.84

Calculate TVD from equation 4-4


TVD TVD4 TVD1 2850 626 2224

2006 PetroSkills LLC, All Rights Reserved

Planning
Calculate X with equation 4-5
X DEP4 R 800 2291.84 1491.84

Calculate L with equation 4-6

L 2224

L TVD X R
2

1
2
2

( 1491.84) 2291.84
L 1385.36

2006 PetroSkills LLC, All Rights Reserved

1
2

Planning
Calculate the hold angle with equation
4-7
TVD R X L

R 2 L2

I sin 1

(2224 )(2291.84 ) ( 1491.83 )(1385.36 )

2291.84 2 1385.36 2

I sin 1

I sin 1 0.4225
I 24.99 o

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Planning a horizontal well is
different from a normal
directional well
It takes more coordination
between disciplines within the
company and with service
companies

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Normal Directional Well
Target

is defined by departure and

TVD
Target has tolerances in the
horizontal plane (North and East)
Target may be plus or minus 100 feet
or 30 meters

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Horizontal Well
Target

is a TVD target and is usually


more important than the DEP target
Target tolerances are much smaller
The formation thickness can be
anywhere from 3 feet (1 m) to more
than 100 feet (30 m)
It is harder to hit the target and takes
greater care
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Gather Information
Offset

well data such as bit records,


mud logs, open hole logs, daily
drilling reports, directional
information, etc.
There are few if any horizontal
exploratory wells

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
First, Define the Reason for
Drilling the Horizontal Well
Prevent

water or gas coning


Intersect vertical fractures
Increased reservoir exposure to
increase production
Avoid vertical fractures to minimize
water production, etc.
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
The reason for drilling the
horizontal drives the completion
which drives the drilling
If drilled to prevent water coning,
the wellbore would be placed
near the top of the reservoir, etc.

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Geology
The

geology in a horizontal well is


extremely important
TVD targets can be very small and
bed dip can be a major consideration
Most often geology can be more
complicated than predicted

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

Planned Geology

Actual Geology

Resulted in a technical success and an economic failure

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
If

the geology is not precisely known,


the drilling engineer must allow for
geologic interpretation while drilling
Will probably require some
geosteering tools

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
May

drill a pilot hole, log, plug back


and sidetrack
Usually better to drill pilot hole at
some angle
Geological Correlation
Gas
Optimized Placement
of Completion

Identification
of Formation and
Fluid Interfaces

Oil
Water

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
If the geologic data is
inadequate, the chances of a
commercially viable horizontal
wellbore decreases significantly

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Placement of Horizontal Within
the Zone
Top

for water coning


Bottom for gas coning
Traverse for natural fractures or in a
portion more highly fractured

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
The well may be drilled from top
to bottom to counteract vertical
permeability barriers
Shale

Fractured Reservoir
Shale
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Placement of Horizontal Within
the Zone
Fracture

orientation determines
direction of horizontal
May be placed in a portion of the
reservoir not swept by a water flood

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Completion requirements
Open

hole, slotted liner, screen,


gravel pack, cased and cemented,
slotted liner and ECPs.
Hole size requirements
Flowing well, gas lift, submersible
pump, rod pump, hydraulic pump,
PCP pump
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Contingency

for future problems with


water or gas coning
Does the build curve need to be
cased and cemented
Sidetracking existing well or drilling a
new well

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Determining build rate
New

well or sidetrack existing well


Less directional drilling costs less
money (higher build rates to a point)
Steerable versus non-steerable
(hitting the target)
Hole size

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Fluid

level and pumping method


Generally you pick either the build
rate or the kick off point and calculate
the other
Most of the time, the build rate is
selected and the kick off point is
calculated
The final inclination is determined by
the bed dip
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Build rate accuracy of directional
equipment
Generally

not greater than plus or


minus 10%, may be worse in some
areas
Have to plan for possible deviation
from predicted versus actual
performance

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
500.00
550.00
600.00

TVD

650.00

10%

700.00

10%
o

750.00

8 o/100'

20 /100'
-10%

-10%

800.00
0.00

100.00

200.00

300.00

400.00

500.00

DEPARTURE

2006 PetroSkills LLC, All Rights Reserved

600.00

700.00

800.00

900.00

Horizontal Planning
Plan

tangent section

Short section in build curve planned to


be straight
Requires multiple trips unless build rate
is low enough to use steerable

Fractional

orientation

Kick off higher than required and kill


some build rate by rotating the motor for
a short distance several times
Must be steerable to an extent

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

Tangent Section
Inclusive

Fractional
Orientation

2006 PetroSkills LLC, All Rights Reserved

Smooth Arc

Horizontal Planning
Drill

with a steerable system

Can adjust build rate by sliding and


rotating but the build rate is limited

Can

also wag the motor

Orient left and right of high side to kill


some of the build rate
More dogleg severity in the build section
Difficult to predict the results

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Soft

landing

Plan for a lower


build rate in the
last 20 degrees of
build and run a
steerable motor in
that section

r1

+
r2

Soft Landing

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Horizontal planning requires
input from:
Geology
Drilling
Reservoir
Production
Service

companies

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
FAILING TO PLAN IS PLANNING
TO FAIL

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Example 4-5 (page 4-33) shows
how to calculate the kickoff point
for a horizontal well with a
planned tangent section
Target

TVD = 4800 feet


Build rate = 12o/100 feet
Tangent section at 60o
Tangent section length = 50 TVD
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the TVD required in the
first build section to 60o
MD

I 2 I1
60 0

500 feet
Br
12 / 100

TVD

180 MD sin I 2 sin I1


I 2 I1

TVD

180 500 sin 60 sin 0


413.50 feet
60 0
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the TVD required in the
second build section from 60o to
90o
I 2 I1 90 60
MD

250 feet
Br
12 / 100
180 250 sin 90 sin 60
TVD
63.97 feet
90 60

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
The TVD of the tangent section is
50 feet
Calculate the KOP
KOP

= 4800 413.50 50 63.97


KOP = 4272.53 feet

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Seldom is the bed dip 0o making
the calculation of the kickoff
point more complicated
Example 4-6 (page 4-34) shows
how to calculate a KOP when the
bed dips at 5o

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Apparent

bed dip is 5o (drilling down

dip)
Build rate = 14o/100 feet
Bed thickness = 50 feet
TVD of the target below the surface
location is 4000 feet
Want to drill from the top of the
producing formation at the beginning
of the horizontal to the bottom at the
end of the horizontal
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate angle A in triangle ABC
BC
A sin 1

AC
1

50

A sin
1.43
2000

The inclination of the horizontal


would be 90o minus the bed dip
minus the angle A
I

= 90 5 1.43 = 83.57o
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the DEP to reach the
horizontal inclination of 83.57o
I 2 I1 83.57 0
MD

596.93 feet
Br
14 / 100

180 MD cos I1 cos I 2


DEP
I 2 I1
DEP

180 596.93 cos 0 cos 83.57


363.42 feet
83.57 0

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the length of side DE in
triangle ADE
tan A

DE
AE

DE tan A AE
DE tan 5 363.42 31.80 feet

The formation will be


encountered 31.80 feet deeper at
a DEP of 363.42 feet
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the TVD for the build
curve
TVD

180 MD sin I 2 sin I1


I 2 I1

180 596.93 sin 83.57 sin 0


TVD
406.68 feet
83.57 0

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the kickoff point
KOP

= 4000 + 31.80 406.68


KOP = 3625.12 feet

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Class problem Problem 3 on
page 4-39
Same

as example 4-6 but drilling up


dip instead of down dip
What is the hold inclination of the
horizontal and the kickoff point

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
KOP
3553.50

Angle of Horiz. = 93.57o

TVD=
408.46

1.43o
C

4000 ft
D
A
E

DE=38.04

DEP=434.74

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate angle A in triangle ABC
BC
A sin 1

AC
1

50

A sin
1.43
2000

The inclination of the horizontal


would be 90o plus the bed dip
minus the angle A
I

= 90 + 5 1.43 = 93.57o
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the DEP to reach the
horizontal inclination of 93.57o
I 2 I1 93.57 0
MD

668.36 feet
Br
14 / 100
180 MD cos I1 cos I 2
DEP
I 2 I1

180 668.36 cos 0 cos 93.57


DEP
434.74 feet
93.57 0

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning

B
C

4000 ft
D
A
E

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the length of side DE in
triangle ADE
tan A

DE
AD

DE tan A AD
DE tan 5 434.74 38.04 feet

The formation will be


encountered 38.04 feet shallower
at a DEP of 434.74 feet
2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the TVD for the build
curve
180 MD sin I 2 sin I1
TVD
I 2 I1
180 668.36 sin 93.57 sin 0
TVD
408.46 feet
93.57 0

2006 PetroSkills LLC, All Rights Reserved

Horizontal Planning
Calculate the kickoff point
KOP

= 4000 38.04 408.46


KOP = 3553.50 feet

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Geosteering is the drilling of a
horizontal, or other deviated
well, where decisions on well
path adjustment are made based
on real time geologic and
reservoir data

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Geosteering is required when the
marker is ill defined, target
tolerances are tight or geology
so complicated that as to make
conventional directional drilling
impractical (geometric steering)

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Geosteering methods
Drilling

rate
Samples
LWD (Logging While Drilling)
Gamma ray
Resistivity
Density Neutron
Sonic

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Because of the inaccuracy of
directional surveys and geology,
it may not be possible to
establish a horizontal wellbore
within the pay zone in small
targets (geometric steering)
Geosteering is required in order
to accomplish the task
2006 PetroSkills LLC, All Rights Reserved

Geosteering
Geologic
markers can be
used to
establish the
wellbore within
the pay zone if a
consistent
geologic marker
exists

Geologic Marker

Reservoir

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Penetration rate may indicate
geologic markers
Samples can be used to
determine the depth of geologic
markers though it is not
extremely accurate
LWD data can be used to
determine geologic markers
2006 PetroSkills LLC, All Rights Reserved

Geosteering
120 ft

Neutron
Density

100 ft

80 ft
Direction
Measurements
60 ft
GR
40 ft

Resistivity

20 ft

0 ft
Feet from Bit

Inclination
GR
Button Resistivity
Resistivity at Bit

Typical layout of
LWD tools within
the directional
bottomhole
assembly
Every well does not
require all of these
tools

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Inductive

Deep resistivity
can be used to
detect bed
boundaries

Propagati
Resistivity
on

InductiveAttenuation

Resistivity

Azimuthal

Resistivity
a
NonPay

2006 PetroSkills LLC, All Rights Reserved

Near-Bit
Electrical Resistivity

Geosteering
Once the well is
within the
reservoir, it must
be kept in the
reservoir
LWD such as GR
and resistivity

2006 PetroSkills LLC, All Rights Reserved

Top Reservoir

Base Reservoir

Geosteering
Azimuthal
resistivity and
GR can be used
to determine if
the wellbore is
close to the top
or bottom of the
formation

2006 PetroSkills LLC, All Rights Reserved

Geosteering

Top Reservoir
Oil

Water

Sometimes it is
desirable to
remain a fixed
distance above
the oil/water
contact
Resistivity tool

2006 PetroSkills LLC, All Rights Reserved

Geosteering
Drilling fault
blocks
Must recognize
when a fault is
encountered
and reestablish
the wellbore
within the pay
zone
2006 PetroSkills LLC, All Rights Reserved

Geologic Faults

Geosteering

Recovery Parameters

Angle of Incidence
Bit-to-Sensor Detection Distance
Decision Reaction Distance
Correction Curve Rate
Hold Distance to Re-entry
Anticipated Changes in Structure
Curve Distance to Recovery

c
b

a)
b)
c)
d)
e)
f)
g)

D
is
t
a
n
c
et
oR
e
e
n
t
r
y
, ft

250
200
150
100
50
0
1

2
3
4
5
Bad Exit Angle of Incidence, deg

Once the wellbore


has exited a pay
zone, it takes time
to get the wellbore
back in the zone
It depends upon
the angle leaving
the zone, the DLS
of the motor, and
the distance of the
sensor from the bit

2006 PetroSkills LLC, All Rights Reserved

Geosteering
If you want to use LWD, three
groups need to work together
Drilling
Geology
The

MWD vendor

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

Planning

2006 PetroSkills LLC, All Rights Reserved

S-ar putea să vă placă și