Sunteți pe pagina 1din 15

Well Completions And Productivity

Outline Procedure for the Installation of a Dual Concentric ESP System.


Occidental, Ecuador, Block 15

Disclaimer Notice
This information is presented in good faith, but no warranty is given by and Schlumberger
assumes no liability for advice or recommendations made concerning results to be obtained from
the use of any product or service. The results given are estimates based on calculations produced
by a computer model including various assumptions on the well, reservoir and treatment. The
results depend on input data provided by the Operator and estimates as to unknown data and can
be no more accurate than the model, the assumptions and such input data. The information
presented is Schlumberger's best estimate of the actual results that may be achieved and should
be used for comparison purposes rather than absolute values. The quality of input data, and
hence results, may be improved through the use of certain tests and procedures which
Schlumberger can assist in selecting.
Freedom from infringement of patents of Schlumberger or others is not to be inferred.
Copyright Statement This document remains the property of Schlumberger and is Confidential
and Trade Secret. Do not disclose, use, or reproduce without written approval from Schlumberger.

Rev
A

Description
Draft issued for comment

278588872.doc

Rev: A

Date

Check

30/05/2005

EGJ

Page: 1 of 15

Appr

Client
Appr

Date: 31/05/2005

Schlumberger Private

Prepared by Brian Scott, Euan Jamieson

Well Completions And Productivity

Special Equipment

Well Control

Tubular Torque Values

Lower Completion Preparation

Running Lower Completion

Pressure Testing the Model S Packer and Casing

Upper Completion Preparation

Upper Completion Spooler layout

Tailpipe Assembly
Schlumberger Private

10 Lower ESP / Pod System


11 Intermediate Assembly
12 Upper ESP / Flow Crossover System
13 Running Outer Production Tubing
14 Running Inner Production Tubing
15 Attached Drawings
15.1

Completion Drawing

15.2

Bypass Clamp Orientation Drawing

15.3

Bypass Space Out Drawing

278588872.doc

Rev: A

Page: 2 of 15

Date: 31/05/2005

Well Completions And Productivity

Special Equipment

Well Control
TBA?

Tubular Torque Values

Connection
2-7/8 8.6lbs/ft New Vam
3-1/2 9.3lbs/ft EUE
5-1/2 20lbs/ft New Vam
5-1/2 17lbs/ft BTC
7 26.0lbs/ft BTC

Minimum ft lbs
1170
2350
5860

Optimum ft lbs
Maximum ft lbs
1300
1430
3130
3910
6510
7160
Refer Pipe Markings
Refer Pipe Markings

Lower Completion Preparation


Fluid Cleanliness?
All completion assemblies are torqued, measured, drifted, and pressure tested prior to
running the completion.
A casing scraper should be run on the workstring and a 8.525 wireline gauge ring should be
run on wireline prior to running the completion assembly.
Remove wellhead bore protector
Ensure all the tie-down bolts are fully retracted

278588872.doc

Rev: A

Page: 3 of 15

Date: 31/05/2005

Schlumberger Private

Dual Stove Pipe (25 Tons)


Pod Work table
2-7/8 Safety Clamp (20 Tons)
2-7/8 Vam FJL Lifting Nubbins
7 Pod Pressure Test Sub
2-3/8 Slips, Dog Collar, Elevators and Pick-up Elevators
2-7/8 Slips, Dog Collar, Elevators and Pick-up Elevators
3-1/2 Slips, Dog Collar, Elevators and Pick-up Elevators
5-1/2 Slips, Dog Collar, Elevators and Pick-up Elevators
7 Slips, Dog Collar, Elevators and Pick-up Elevators
API Drifts for 2-7/8 8.6lbs/ft, 3-1/2 9.3lbs/ft, 5-1/2 17.0lbs/ft, 5-1/2 20.0 lbs/ft,
7 26.0 lbs/ft
MultiSensor RIH Panel

Well Completions And Productivity

Running Lower Completion


Make up onto the Schlumberger setting tool the following assembly
2-7/8 Model A Tubing shear plug
2-7/8 EUE L-80 Seating nipple with 2.25 R profile
2-7/8 x 10 foot EUE L-80 pup joint
Tailpipe adapter from seal bore x 2 7/8 EUE
10-foot seal bore extension
Seal bore coupling
9-5/8 Model S wireline set permanent seal bore packer
Wire line adapter kit for 9-5/8 permanent packer
RIH to setting depth with the assembly at a normal running speed.
Note: The casing must be in good condition and the packer set in a section of the hole
that is relatively straight.
Set packer.
POOH with the setting tool.

Inspect shear stud to the ensure proper shear was obtained.


6

Pressure Testing the Model S Packer and Casing


Make up a 9-5/8 retrievable compression set packer and locator seal assembly onto the
work string
Run in hole and set the retrievable packer approximately 20ft above the Model S
permanent packer, below the upper perforations.
Note: The retrievable packer is set with right hand rotation and then applied (set down)
weight of 30,000 lbs will energize the packing elements.
Pressure the tubing to 1500Psi to test the completion packer assembly, and hold for 5
minutes.
Once the packer has been tested continue to pressure up on the tubing to blow out the
tubing shear plug. The pressure to blow the tubing shear plug will be approximately
2500Psi.
Note: In case the plug blows prematurely a slickline plug can be set in the R nipple to
test the packer.
Release the retrievable packer and continue to RIH. Tag the completion assembly to
ensure it is properly set and verify the setting depth. A set down weight on the assembly
of 15,000 lbs is sufficient.
POOH to above the upper perforations and reset the retrievable packer. Test the casing
by applying 1000Psi down the annulus.
Release the packer and POOH.

278588872.doc

Rev: A

Page: 4 of 15

Date: 31/05/2005

Schlumberger Private

At surface inspect the setting tool and wireline adapter kit to ensure all parts are
recovered.

Well Completions And Productivity

Upper Completion Preparation


All completion assemblies are torqued, measured, drifted, and pressure tested prior to
running the completion.
Mark the motors along their full length (each section) showing the alignment of the
Pothead (so that alignment of the Pothead can be seen at the base of each lower motor)
Fit the motor base adaptors and MultiSensors to the ESP Motors for both the lower and
upper systems, observing the correct orientation for the pressure discharge line (refer
bypass clamp orientation drawing)
Pick up and make up the 15ft spacer pup joint to the Pod hanger. Lay the completed sub
assembly on the deck.
Pick up and make up the upper most bypass tubing assembly to the bypass leg of the
flow crossover assembly. Lay the completed sub assembly on the deck.
Stroke out the Telescopic Swivel Nipple 12.

Schlumberger Private

Upper Completion Spooler layout


XXXXXX

278588872.doc

Rev: A

Page: 5 of 15

Date: 31/05/2005

Well Completions And Productivity

Tailpipe Assembly
Pick up the mule shoe, seal units, spacer tube, locator seal assembly and pup joint. RIH
and secure the pup joint in the rotary table with slips and dog collar.
Pick up and make up the seating nipple and 1 x 3-1/2 EUE tubing joints. Pick up to
remove slips, and RIH with the assembly. Secure the tubing joint in the rotary table with
slips and dog collar.
Pick up and make up the first blast joint. Pick up to remove slips, and RIH with the
assembly. Secure in the rotary table with slips and dog collar. Continue to make up the
remaining 2 blast joints in the same manor.
Pick up and make up the shear sub (with pup joints). Ensure the shear sub is fitted with X
number of shear screws to give a shear force of XXXlbs. Pick up to remove slips and
RIH with the assembly. Secure pup joint in the rotary table with slips and dog collar.
Pick up and make up the remaining X x 3-1/2 EUE tubing joints. RIH and secure the last
joint in the rotary table with slips and dog collar.

Schlumberger Private

278588872.doc

Rev: A

Page: 6 of 15

Date: 31/05/2005

Well Completions And Productivity

10

Lower ESP / Pod System


Pick up the Pod bottom sub assembly in the elevators and make up to 3-1/2 EUE
tubing. RIH and set the 7 pup joint in the slips.
Pick up and make up the first Pod casing joint. Remove the slips and RIH. Continue to
make up the remaining X x 7 Pod casing joints in the same manor.
Rig up slick line and set the 2.250 Plug in tailpipe seating nipple.
Pick up the Pod top sleeve with pup joint attached using the pressure test sub and make
up. RIH and set in slips securing with dog collar.
Pressure test the Pod assembly to 3000Psi for 15mins. Remove the pressure test cap
and recover the plug.
Locate the work-table over the top of the Pod assembly ensuring that the top threads of
the Pod are protected.
Pick up the lower motor with MultiSensor attached. Make up the pressure discharge
line to the MultiSensor and pressure test to 3000psi for 15mins.

Slowly run the assembly into the Pod casing, servicing the motor as required. Land the
motor lifting clamp on the worktable.
Pick up and make up the tandem protectors. Pick up the assembly and remove the UT
motor lifting clamp.
Tie in the lower ESP MLE to the motor pothead and perform electrical tests on ESP and
MultiSensor.
Fit the MLE clamp to the lower neck of the lower protector, and torque to 55ft lbs.
Secure the MLE and pressure discharge line in the cable clip and torque to 25 ft lbs.
Slowly run the assembly into the Pod casing, servicing the protector as required.
Fit the MLE clamp to the lower neck of the upper protector, and torque to 55ft lbs.
Position the open end of the 3/8 and chemical injection lines below the cable clip.
Secure the MLE, pressure discharge line, 3/8 and chemical injection lines in the
cable clip and torque to 25 ft lbs.
Continue to RIH and land the protector lifting clamp on the worktable.
Pick up and make up the lower pump (with intake). Pick up the assembly and remove
the protector lifting clamp.
Fit the MLE clamp to the lower neck of the pump (above the intake) and torque to 55ft
lbs. Secure the MLE, pressure discharge line, 3/8 and chemical injection lines in
the cable clip and torque to 25 ft lbs.
Slowly run the assembly into to the Pod casing. Land the pump lifting clamp on the
worktable.
278588872.doc

Rev: A

Page: 7 of 15

Date: 31/05/2005

Schlumberger Private

Fit the MLE clamp to the lower neck of the motor, and torque to 55ft lbs. Secure the
pressure discharge line in the cable clip and torque to 25 ft lbs.

Well Completions And Productivity

Make up the pressure discharge sub to the pump flange.


Pick up the Pod hanger assembly (with the spacer pup joint and discharge head
attached). Make up the discharge head to the pressure discharge sub flange.
Pick up and remove the pump lifting clamp. Cut the pressure discharge line and
terminate to the pressure discharge sub.
Fit the MLE clamp to the discharge head, and torque to 55ft lbs. Secure the MLE, 3/8
and chemical injection lines in the cable clip and torque to 25 ft lbs.
Slowly run the assembly into the Pod casing until the hanger is at working height. Cut
the 3/8 and chemical injection lines and terminate in the ports on the underside of the
Pod hanger.
Fit the penetrator / pigtail into the adaptor in the Pod hanger. Measure and mark MLE for
cable splice. Retrieve the penetrator / pigtail from the hanger.
Splice the MLE to the penetrator / pigtail. Re-fit the penetrator to the hanger and secure.
Pressure test the seals through the hanger test port in accordance with BIW procedures.

Slowly run the assembly into the Pod casing until the hanger engages the top sleeve.
Lift outer locking ring to allow witness of correct seal engagement in top sleeve seal
bore.
Make up outer locking ring to top sleeve. Connect a hand pump and chart recorder to
the Pod hanger test port and pressure the hanger seals to 3000Psi for 15 mins.
Connect the 3/8 and chemical injection line to the ports on the top face of the Pod
hanger.
Run in hole, and set the string in the 3-1/2 slips on the handling sub above the Pod
hanger.

278588872.doc

Rev: A

Page: 8 of 15

Date: 31/05/2005

Schlumberger Private

Remove the worktable from the top of the Pod

Well Completions And Productivity

11

Intermediate Assembly
Pick up the first joint of 3-1/2 EUE tubing and make-up to the top of the Pod assembly.
RIH through the rotary table slowly to a suitable working height position for the cable
splice. Secure the string in the rotary table with slips and dog collar.
Splice upper pigtail to MLE extension.
Pick up to remove slips. Continue to RIH and secure slips and dog collar.
Pick up and make up the shear sub (with pup joints). Ensure the shear sub is fitted with X
number of shear screws to give a shear force of XXXlbs. Pick up to remove slips.
RIH with the assembly installing cross coupling clamps at each coupling. Secure pup
joint in the rotary table with slips and dog collar.
Continue to RIH making up the remaining 2 x 3-1/2 EUE pup joints, installing cross
coupling clamps at each coupling.
Set the last 3-1/2 EUE tubing joint in the slips.

Schlumberger Private

278588872.doc

Rev: A

Page: 9 of 15

Date: 31/05/2005

Well Completions And Productivity

12

Upper ESP / Flow Crossover System


Fit the swivel lift nubbin to the pump support assembly. Pick up the assembly with
elevators and make up to the string with the tongs.
Pick up to remove slips. Lower the assembly through the rotary table (bypass still held by
elevators)
Position the ESP worktable (stove pipe) over the rotary table. Fit the bypass safety clamp
to the groove in the tubing, and torque to 200ft/lbs.
Note: The bypass tubing will be grooved to provide a suitable location for the heavy duty
safety clamp to be fitted.
Unlatch the elevators. Pick up the first bypass tubing sub assembly with the elevators
and make up to the string using the tongs.
Note: The bypass tubing lengths will have been predetermined and supplied specifically
for each system in order to facilitate make ups with the power tongs .
Remove the safety clamp and the worktable. POOH and re-set the slips below the Pump
Support Sub.

Bypass Tubing

90

ESP Lifting Clamp


ESP Lifting Clamp Bolt Flanges

ESP
Plan view of
optimum clamp fitting arrangement

Manoeuvre motor and MultiSensor over the spear on the pump support sub. Make up the
spear to the base of the MultiSensor with wrenches.
Pick up to remove slips. Secure the lower ESP cable, 3/8 and Chemical injection
lines in the pump support cable clip.
Slowly RIH to the MultiSensor. Make up the pressure discharge line to the
MultiSensor and pressure test to 3000Psi for 15mins.
RIH with the assembly servicing the motor as required. At the motor flange, fit the safety
clamp to the groove on the bypass tubing and torque to 200ft lbs.
278588872.doc

Rev: A

Page: 10 of 15

Date: 31/05/2005

Schlumberger Private

Pick up the motor with the MultiSensor already attached.


Note: When fitting the lifting clamp to the motor, observe the line previously marked for
the pothead orientation. Fit the clamp so that when the ESP Motor is alongside the
bypass tubing, the clamp bolt flanges will lie at 90 to the tubing with the pothead
alignment mark in the correct position relative to the bypass tubing.
Refer to the bypass clamp orientation drawing and see diagram below:

Well Completions And Productivity

Unlatch the elevators. Pick up the next bypass tubing sub assembly with the elevators
and make up to the string using the tongs. (see bypass space out drawing)
Remove the lower motor lifting clamp.
Pick up the upper motor.
Note: Use the same orientation procedure as detailed for the lower motor, when fitting the
lifting clamp to the upper motor.
Make up the upper motor to the lower motor.
Remove the safety clamp. Ensure the pothead alignment mark is still correctly orientated
with respect to the bypass tubing. Fit the bypass clamp to the lower neck of the upper
motor and torque to 55 ft lbs. Secure the lower MLE, lower 3/8 and chemical injection
lines in one cable clip. Secure the pressure discharge line from the upper MultiSensor
in the other cable clip. (as per bypass clamp orientation drawing). Torque both clips
to 25ft lbs
RIH with the assembly servicing the motor as required. At the motor flange, fit the safety
clamp to the groove on the bypass tubing and torque to 200ft lbs.

Remove the upper motor lifting clamp. Pick up the tandem protectors and make up to the
top of the upper motor.
Tie in the upper ESP MLE to the UT motor pothead and perform electrical tests on ESP
and MultiSensor.
Remove the safety clamp. Fit the bypass clamp to the lower neck of the protector and
torque to 55 ft lbs. Secure the lower MLE, lower 3/8 and chemical injection lines in
one cable clip. Secure the MLE and the pressure discharge line from the upper
MultiSensor in the other cable clip. (as per bypass clamp orientation drawing). Torque
the clips to 25ft lbs
RIH servicing the protectors as required. At the lower neck of the upper protector fit the
bypass clamp and torque to 55 ft lbs. Secure the lower MLE, lower 3/8 and chemical
injection lines in one cable clip. Position the end of the upper 3/8 chemical injection line
below the bypass clamp. Secure the upper MLE, pressure discharge line and upper
3/8 chemical injection line in the other cable clip. (as per bypass clamp orientation
drawing). Torque the clips to 25ft lbs.
RIH with the assembly servicing the protectors as required. At the protector flange, fit the
safety clamp to the groove on the bypass tubing and torque to 200ft lbs.
Unlatch the elevators. Pick up the next bypass tubing sub assembly with the elevators
and make up to the string using the tongs. (see bypass space out drawing)
Remove the protector lifting clamp. Pick up the lower pump with intake attached and
make up to the top of the protectors.
Remove the safety clamp. Fit the bypass clamp to the lower neck of the pump (above the
intake) and torque to 55 ft lbs. Secure the lower MLE, lower 3/8 and chemical
injection lines in one cable clip. Secure the upper MLE, upper 3/8 chemical injection line
and the pressure discharge lines in the other clip (as per bypass clamp orientation
drawing). Torque the clips to 25ft lbs.
278588872.doc

Rev: A

Page: 11 of 15

Date: 31/05/2005

Schlumberger Private

Unlatch the elevators. Pick up the next bypass tubing sub assembly with the elevators
and make up to the string using the tongs. (see bypass space out drawing)

Well Completions And Productivity

RIH with the assembly to the pump flange. Fit the safety clamp to the grooved on the
bypass tubing and torque to 200ft lbs.
Unlatch the elevators. Pick up the next bypass tubing sub assembly with the elevators
and make up to the string using the tongs. (see bypass space out drawing)
Remove the lower pump lifting clamp. Pick up the middle pump and make up to the top
of the lower pump.
Remove the safety clamp. Fit the bypass clamp to the lower neck of the middle pump
and torque to 55 ft lbs. Secure the lower MLE, lower 3/8 and chemical injection lines
in one cable clip. Secure the upper MLE, upper 3/8 chemical injection line and the
pressure discharge lines in the other clip (as per bypass clamp orientation drawing).
Torque the clips to 25ft lbs.
RIH with the assembly to the pump flange. Fit the safety clamp to the grooved on the
bypass tubing and torque to 200ft lbs.
Rig up slickline and set plug in the nipple above the Pod hanger assembly. Pressure test
the 3- tubing and bypass tubing to 3000 psi for 15 mins. Recover plug.

Pick up the upper pump. Make this up to the top of the lower pump. Remove the safety
clamp and pump lifting clamp.
Fit the bypass clamp to the lower neck of the upper pump and torque to 55 ft lbs. Secure
the lower MLE, lower 3/8 and chemical injection lines in one cable clip. Secure the
upper MLE, upper 3/8 chemical injection line and the pressure discharge lines in the
other clip (as per bypass clamp orientation drawing). Torque the clips to 25ft lbs.
RIH with the assembly to the top of the pump flange. Fit the safety clamp to the grooved
on the bypass tubing. Make up the pressure discharge sub to the pump flange.
Orientate the discharge head over the pressure discharge sub. Slowly lower the
elevators. This will allow the telescopic swivel nipple to contract. Make up the discharge
head on the flow crossover assembly to the pressure discharge sub.
Remove the pump lifting clamp (if it was not removed prior to the last action).
Close the telescopic swivel nipple and lock using lock ring. Take the weight of the
assembly with the elevators. Remove the safety clamp and worktable.
Cut the pressure discharge line and terminate to the pressure discharge sub.
Fit the bypass clamp to the discharge head and torque to 55 ft lbs. Secure the lower
MLE, lower 3/8 and chemical injection lines in one cable clip. Secure the upper MLE
and upper 3/8 chemical injection line in the other clip. Torque the clips to 25ft lbs.
RIH to the flow crossover tool. Secure the MLEs and lines into the clips at either side of
the tool.

278588872.doc

Rev: A

Page: 12 of 15

Date: 31/05/2005

Schlumberger Private

Pick up the flow crossover assembly with the elevators. Make up the bypass tubing leg of
the assembly to the string using the tongs. The flow crossover may be swivelled away
from the rotary table so that the discharge head leg does not obstruct the next action.

Well Completions And Productivity

RIH to suitable location for the cable splices. Splice the lower MLE, lower 3/8 and
chemical injection lines to the main cable (main cable with 2 x 3/8 capillary tube). Splice
the upper MLE and upper 3/8 chemical injection line to the other main cable (main cable
with 2 x 3/8 capillary tubes)

Schlumberger Private

278588872.doc

Rev: A

Page: 13 of 15

Date: 31/05/2005

Well Completions And Productivity

13

Running Outer Production Tubing


Run in hole with 5-1/2 production tubing, installing cross coupling clamps at each
coupling to secure and protect the two power cables.
100ft above the top perferations record the up and down string weights.
Continue to RIH until the tailpipe assembly enters the packer.
Space out the completion in the isolation packer and land off in the wellhead.
Rig up slickline and run in hole with 3.688 standing valve. Land standing valve in flow
crossover nipple profile and pressure test 5 production tubing to 3000Psi for 15 mins.
Pull out of hole with 3.688 standing valve. Rig down slickline.

14

Running Inner Production Tubing

Make up the 2-7/8 internal production tubing to the stinger sub assembly and RIH.
Space out the 2-7/8 internal production tubing in the flow crossover assembly and land
off in the wellhead.
Rig up slickline, run the 1.687 standing valve and set in the seal assembly nipple profile.
Pressure test the 2-7/8 EUE tubing string against 1.687 standing valve to confirm
pressure integrity of 2-7/8 tubing and stinger seal assembly to 3000Psi for 15 mins.
Monitor the pressure via the MultiSensor for possible indication of leaks.
Bleed off pressure and RIH with slickline to retrieve standing valve.
Pull out of hole with 1.687 standing valve and rig down slickline.
Continue to nipple down BOP, nipple up Xmas tree, etc.

278588872.doc

Rev: A

Page: 14 of 15

Date: 31/05/2005

Schlumberger Private

Pick up stinger assembly, taking care not to damage seals.

Well Completions And Productivity

15

Attached Drawings

15.1 Completion Drawing


15.2 Bypass Clamp Orientation Drawing
15.3 Bypass Space Out Drawing

Schlumberger Private

278588872.doc

Rev: A

Page: 15 of 15

Date: 31/05/2005

S-ar putea să vă placă și