Implementation
Farias, V. S. , Fernandes, N. C.
GTECCOM/MidiaCom - Department of Telecommunications Engineering (PPGEET/TET)
Universidade Federal Fluminense (UFF)
Niteroi, RJ - Brazil
AbstractThis paper proposes a quantitative evaluation of
the classic discussion on cost-benefit and risk management
involved in the implementation of telecommunications networks
for Substation Automation Systems (SAS). The goal is to find
the optimal point for investing in quality and reliability in order
to maximize the profitability of the project. Various IEC 61850
substation automation system (SAS) architectures are compared
in terms of price, reliability, and their impacts in the power grid
quality and cost of ownership of the project. The method used
in this paper is the life cycle cost analysis (LCCA). It enables an
objective decision of the topology options considering the high
reliability requirements of SAS networks. This paper discusses
how to make the best out of this new approach in protection and
supervision of power systems.
KeywordsSubstation automation system, life cycle cost, availability analysis, IEC 61850
I.
I NTRODUCTION
IEC 61850 is gaining strength as standard for communication in substations. It defines requirements for a smart and
reliable replacement for the existing substation automation
systems (SAS). A well planed and implemented SAS will
improve safety, reliability, and reduce downtime for a substation. This is achieved by performing countermeasures in case
of critical failures faster than by manual operation. Indeed
the automation system functions are divided into two groups:
control/monitoring functions and fault clearance/protection
functions. The first are responsible for gathering information
about the state of the substation electrical equipment and
the other for taking action to clear an abnormal condition,
maintaining the grid sanity in case of an exceptional situation.
There is a multiplicity of proprietary communication protocols to perform automation in SAS, most using hardwired connections to the power equipments. Usually, these
solutions do not provide interoperability between different
manufactures, increasing costs in maintenance and substation
expansions. The IEC 61850 standard enables interoperability,
service definitions, and conformity tests. Assuring that devices
from different vendors will work in the same network, the
communication and basic services are thoroughly mapped
and defined, thus ensuring quality and safety. Also, the use
of a mainstream communication such as Ethernet instead of
hardwired point to point connections provides high flexibility,
reduction in the number of cables, and ease of installation.
This paper proposes a methodology to perform a quantitative analysis of the cost-benefit and risk management in
R ELATED W ORK
Life Cycle Cost Analysis as determining factor for optimization in system design is applied in [1] and documented
in [2]. Hinow and Mevissen use LCC to determine the
substation layout using genetic algorithms [1]. This work,
however, does not apply to SAS, but to substation bus,
composed of electrical equipments. An application example of
the LCCA for process bus topology, which includes part of the
telecommunication equipments of a substation, is shown in [3].
In this paper, the authors test three topologies for the process
bus of a substation. The analysis, however, is preliminary and
further details are required to specify the cost-benefits of these
topologies. Also, many parameters used in the analysis are not
correlated to any real scenario.
This paper proposes a way to quantify the cost benefit of
a SAS based on the analysis of the downtime through LCC.
We used the topologies described in [4], which provides the
basis for the failure probability in a SAS used in our paper.
This paper, however, does not treat the downtime analysis.
As in [7], we calculate the substation downtime, but we
consider LCC applied in the Brazilian scenario using the
main substation telecommunication network topologies. Also,
while [7] is focused in availability and reliability, we evaluate
cost benefit and funding.
III.
Cost - With so many difficulties to comply the standard requirements, the cost to implement and maintain
an SAS Ethernet network rises rapidly. Performing
an effective analysis of cost is mandatory in order to
assure a profitable project.
A qualitative analysis shows that the strict latency and availability requirements of the substation automation applications
might demand approaches with redundancies for critical components. The basics of some popular architectures are the
following[11]:
Cascade - Low cost as single advantage. No redundancies lower overall availability and the single path will
rise the latency if the network has too many elements.
Star - Has lowest latency among the simple topologies, fairly higher cost and a single point of
failure[11].
IV.
The optimal cost efficient solution for the system implementation and ownership (CLC ) will take into consideration
the acquisition cost CA (t), the maintenance cost CR (t), and
the operation and renewal cost CO (t) [1]:
(1)
CR (t) =
X CA i(t)
Lifei
(2)
(3)
(4)
It is important noticing that Crep (t) is relative to replacements due to failures in the equipments, while CR (t) corresponds to replacement because of ageing. Thus the component
replacement cost (Crep (t)) is the sum of the component prices
(Crepi) weighed by the component failure probability (Fpi).
Crep (t) =
n
X
Crepi.F pi
(5)
n=1
V.
The objective in this analysis is to determine the economical viability of the investment in SAS. The cost calculations
will reveal when and how to implement the protection system.
Its expected that very important substations will demand
higher investments in reliability. On the other hand, for small
substations, the high costs of automation on the moment of
the present study might be prohibitive for implantation.
We apply our model considering the Brazilian scenario. A
failure that causes interruption of transmission functions has
a penalty of energy delivery interruption. In Brazils specific
case, Cf p (t) (Eq. 4) is also known as PVI (Parcela Variavel
por Indisponibilidade) - the unavailability variable parcel [14].
The government establishes a fine based on the duration of
interruption and amount of energy not delivered. The value to
be discounted from the companys receipt due to interruption
in the energy delivery is calculated as follows:
BP
PV I =
Kp
1440D
BP
+
1440D
NO
X
i=1
NP
X
i=1
DV DPi
Koi DV ODi
(6)
Fig. 1. Main network topologies for SAS, which are evaluated using the proposed life cycle cost analysis. The switches (ESW) are colored blue; BCUs are
green. Connected NCCSs, IPCs, and HMIs.
IPC
ESW
EI
BCU
HMI
NCCS
Price (BRL)
13000
1800
128
24000
3000
13000
Lifespan
20
15
25
15
20
20
VI.
CR(year)
650
120
5,12
1600
150
650
Fpi
0,06993
0,08696
0,00333
0,00966
0,10000
0,06993
Crep (year)
909,09
156,528
0,42624
231,84
300
909,09
2.08
2.13
2.14
6
x 10
x 10
Manual
Centralized Ring
Redundant Star
Centralized Star
2.3
R ESULTS
N C(yr)i =
2.38
2.8
2.78
Manual
Simple Cascading
Redundant Cascading
Decentralized Star
2.76
2.74
2.72
(9)
2.48
2.49
2.5
2.51 2.52
Base Payment (R$)
2.53
2.54
6
x 10
Fig. 2. Network topologies evaluated using the proposed life cycle cost
analysis.
1.008
Manual
Centralized Ring
Redundant Star
Centralized Star
Relative Cost
1.006
1.004
1.002
1
2
4
6
Base Payment (R$)
10
6
x 10
(a) Normalized costs for a substation layout with centralized SAS topologies
1.02
Manual
Simple Cascading
Redundant Cascading
Decentralized Star
Relative Cost
1.015
1.01
1.005
1
2
4
6
Base Payment (R$)
10
6
x 10
(b) Normalized costs for a substation layout with decentralized SAS topologies
Fig. 3. Network topologies evaluated using the proposed life cycle cost
analysis.
layouts except the layout single radial. The impact of implementation of SAS in this kind of layout is very light.
VII.
C ONCLUSION