GROUP : AAP1143A
DATE OF SUBMISSION : 01 JULY 2013
LECTURER : PN WAN NORIZAN BINTI WAN ISMAIL
1)
2)
3)
4)
5)
6)
MEMBERS NAME
MUHAMAD AZRI BIN NAWI
HAZWANI IZZATI BINTI ZAIDIN
NAJIHAH BINTI SALMAN
NUR AMILA BINTI SHMSURI
AHMAD FAZLIN BIN AZMI
SITI MAISARAH BINTI ZAKARIA
MATRIC NUMBER
2012483274
2012601888
2012839724
2012828384
2012282074
2012416918
CONTENT
no
Contents
page
1 | Page
[DEVELOPMENT PROCESS]
Acknowledgement
Introduction
Project background
Modern approach
11
18
29
Conclusion
30
References
31
ACKNOWLEDGEMENT
2 | Page
[DEVELOPMENT PROCESS]
INTRODUCTION
3 | Page
[DEVELOPMENT PROCESS]
Development process is the most important aspects of effectively. The development involves
assessing customer needs, developing offerings that meet these needs, testing these products
to make sure they are effective and appealing, and then introducing them to target markets in
interesting and attention-worthy ways.
Research
Marketing research is the first step in the product planning and development process. A
company can do formal marketing research by conducting surveys and polls in person, over the
telephone or online; asking customers what they want in a new product and how a company's
new offerings can most effectively meet their needs. A company also can conduct informal
marketing research simply by speaking to customers through day-to-day interactions and
observing their purchasing behavior. These observations can provide invaluable information
about the features and functionalities that should be integrated into new products.
Budgeting
Planning and developing new products costs money, and a company should embark on
this
process with a budget that provides a clear idea of how much money is available for
researching, developing and marketing. Creating a budget for new product development
involves deciding whether this process will be financed via ongoing company activities, such as
ongoing sales of an existing product line, or whether it is worth taking out a loan, or approaching
investors for additional funds.
Prototypes
The heart of the new product planning and development process involves creating prototypes,
which are sample products that provide real data about how these offerings work and whether
they meet customer needs. The process of creating prototypes involves experimenting with
materials in order to develop a product that can be created within the company's budget. The
prototype phase of product development involves interaction between product developers and
the company's manufacturing department in order to design a product that can be produced on
a larger scale.
DEVELOPER
4 | Page
[DEVELOPMENT PROCESS]
Definition
An entrepreneur who provides the organization and capital required making building available
in anticipation of requirement of market in return for profit.
He is the one who responsible to carrying out of building engineering, mining or other
operation in, on, over, or under land, or making of any material change in the use of any building
or other.
As for our developer for this case study is MRCB. This company is the one that organize and
provide the capital cost for this construction.
5 | Page
[DEVELOPMENT PROCESS]
Consultant board should be chooses carefully to ensure the construction process is going
smooth.
Determine the source of finance
Each construction must have a stable financing cost. This cost must be provided continuously
and the source must be recognized and verify by the local authorities.
The RIBA plan of works, is basically a set of guidelines and sets out the process by which a
construction project should be run. It is set out in stages that are feasibility, design and
construction. The step in RIBA planning :
Figure 1
2.
Modern Approach :
6 | Page
[DEVELOPMENT PROCESS]
It considers the development in more holistic context which commences from inception and at
demolition of the project for rebuilding purposes. Besides that, it to cost control considers all
cost involved in project lifecycle. The stage in it which is :
INCEPTION
CONSTRUCTION
IN USE
DEMOLITION
Figure 2
The types of construction process that apply in our case study is modern approach. Modern
approach is being used in the construction of semi-d house project. All the process need to be
plan earlier and do an early planning. This construction takes time until 15 months. Each
process needs to be handle carefully and smartly.
7 | Page
IN- USE
[DEVELOPMENT PROCESS]
1)
2)
Evaluation
3)
Acquisition
4)
5)
6)
7)
PROJECT BACKGROUND
The project that we found to do for our assignment is Cadangan Membina 16 Unit Rumah
Berkembar Satu Tingkat Jenis B-T Di Atas Lot 762-77, 20 Unit Rumah Berkembar Satu Tingkat
8 | Page
[DEVELOPMENT PROCESS]
Jenis B-M Di Atas Lot 778-797, 12 Unit Rumah Berkembar Satu Tingkat Di Atas Lot 716-827.
This project is for the development phase 2A at half of scheme combination development at
government land which size 53.05 acres at Seri Iskandar City. Besides that, it also for Tetuan
Seri Iskandar Development Sdn. Bhd.
The main contractor companies that is involved in this construction project is Pembinaan
Khuang Seng Sdn. Bhd which address at No 51-A Laluan Pinji Seni 4, Taman Pinji Seni, 31650
Ipoh, Perak .Next for this project the contract sum is RM 6122 330.00. Date of commencement
this project is 28 January 2010 and for date of completion is 27 April 2011. The project took 15
months to finish.
SITE ORGANIZATION CHART
PROJECT MANEGER: TAN CHOR HENG
STRUCTURAL
ARCHITECTURAL
CIVIL
Figure 3
9 | Page
[DEVELOPMENT PROCESS]
Figure
4
CLIENT AND LIST OF CONSULTANT
CLIENT:
ADRESS:
PHONE:
EMAIL:
ARCHITECT:
ADRESS;
PHONE:
MOBILE:
CIVIL ENGINEER:
ADRESS:
PHONE:
FAX:
STRUCTURAL ENG:
ADRESS:
PHONE:
FAX:
M & E:
ADRESS:
PHONE:
FAX:
10 | P a g e
[DEVELOPMENT PROCESS]
QS:
ADRESS:
PHONE:
MOBILE:
Figure 5
MODERN APPROACH
Inception
Stage
1
Stage
2
Construction
Stage
3
In-use
Stage
4
Demolition
Stage
5
Stage 1 Inception
The project construct 48 unit of semi-d house at the Bandar Seri Iskandar, Perak.
First the developer appoint land survey to do Feasibility Study.
The site is suitable for construct residential building because near with;
i.
Town and village.
The site is near with the town of Bandar Universiti, Seri Iskandar and near with
ii.
Kampung Bota
Educational building.
Educational building that near with the site which are UITM Seri Iskandar, UTP
Teronoh and SK Seri Iskandar.
11 | P a g e
[DEVELOPMENT PROCESS]
iii.
Commercial Building
The commercial building that near with the site which are Tesco, Billion, Aeon
Figure 6
Figure 7
Stage 2 Design & Costing
12 | P a g e
[DEVELOPMENT PROCESS]
The client, Seri Iskandar Development Corporation SDN.BHD appoint the design team
of the project which are :
i.
Architect Ahmad Fadzil Mohamad Architect
ii.
Civil Engineer Kahiri Consult
iii.
Structure Engineer Perunding Amarbina Sdn. Bhd
iv.
Mechanical & Electrical Tham Zamin Bersekutu
v.
Quantity Survey Kas Juruukur Bahan Sdn. Bhd
vi.
Main Contractor Pembina Khuan Heng Sdn. Bhd
The lump sum cost for this construction is RM 6, 122, 330.00
The client will send the Certificate of Completion and Compliance letter to the Building
Control and Public Safety to make sure the construction is safe.
The Architect will agree with the quality and standard of construction and it will proceed
with construction process.
The duration taken for design and costing the project is 5month.
Figure 8
Stage 3 : Construction
The phase of the project are project planning, installation and commissioning
The duration of the project is 2 1/2 years
Date of commencement
Date of completion
[DEVELOPMENT PROCESS]
Completion period
15 month
Figure 9
Task of the project: project was completed on time within budget and specified quantity.
Period ->1 June 2010 22 June 2010
1) 16 units B-T
a) Block 3a
- Gred Beam R.C. Works is completed.
- Underground soil pipe and piping works is in progress, will be completed by end of
-
this month.
Gred floor slab backfill and concreting works will be start by first of July and complete
b)
-
by middle of July.
Gred column R.C works will be start after completion floor slab.
Block 3b
Gred beam R.C. works is in progress, will be complete by middle of July.
Underground piping works will be start by middle of July.
2) 20 units B-M
a) Block 2a
- Ground beam R.C. Works is in progress, will be complete by first of July.
- Underground piping works will be start on July and complete by week of July.
- Ground floor slab backfill and concreting works will be starts by second week of July.
- Ground beam R.C. Works will be start after completion floor slab.
b) Block 2b
- Pipe cap R.C. Works is in in progress, will be completed.
- Ground beam R.C. Works is in progress, will be complete by middle of July.
- Underground piping works and floor slab backfill works will be start by middle of July
and complete by end of July.
3) 12 units B-T
a) Block 1a & b
- Pile cap R.C. Works is in progress, will be complete by end of this month.
- Ground beam R.C. Works will be start by first of July and complete by end of July.
The project does not have any delayed time because the project is on the time.
The project is within the budget that is RM 6,122 330.00.
14 | P a g e
[DEVELOPMENT PROCESS]
Stage 4 : In-use
Cracks
ii)
15 | P a g e
[DEVELOPMENT PROCESS]
iii)
Piping leakage
iv)
Electrical problem
Feedback from project appraisal in practice will help to reduce possible defects.
Stage 5 : Demolition
Demolition is the tearing-down of buildings and other structures. Demolition contrasts
with deconstruction, which involves taking a building apart while carefully preserving
valuable elements for re-use.
Figure 10
A wrecking ball in action at the demolition of the Rockwell Gardens
16 | P a g e
[DEVELOPMENT PROCESS]
But our project have a long life span between 80 to 100 years.
So, no need demolition until there are any worst condition.
17 | P a g e
[DEVELOPMENT
PROCESS]
STEPS
IN DEVELOPMENT
PROCESS
1. Site
identification
2. Evaluation
3.
Acquisition
7. Sales and
promotion
6.
Implementation
& construction
4. Design
and costing
5. Development
permission &
approval
Figure 11
1. Site identification
18 | P a g e
[DEVELOPMENT PROCESS]
The location of the site is being identify. Place to build the building should be concern
as after the building constructed, it is difficult to change another site. This could lead
2. Evaluation
Research is being conducted during this step. Evaluations on market research. This means
about the age and population of the people who live nearby the area. The feasibility study is
been studied on the profit that will be gain from the building. The cost of the development is
reasonable and the economic viability of the project can be attained.
o
Figure 12
figure 13
3. Acquisition
o There is several types of acquisition:
Private treaty
19 | P a g e
[DEVELOPMENT PROCESS]
Figure 14
figure 15
Formal tender
Formal tender is any formal letter that set out in writing. The advantages of
formal tender are it is more certainty than private treaty, and it is more
flexibility and discretion than selling by public auction.
Public auction
There are ways to conduct public auction
i.
All leasing by public auction shall be by oral or by sealed bid.
ii.
The auction is conducted under the direction of the department or by
iii.
iv.
20 | P a g e
[DEVELOPMENT PROCESS]
Figure 16
figure 17
Joint venture
A contractual agreement joining together two or more parties for the purpose
of executing a particular business undertaking. All parties agree to share in
iii.
[DEVELOPMENT PROCESS]
iii.
-
Figure 18
figure 19
Sector
Owner/Developer
Duties
The person who wishes to have a
development project constructed on a
piece of land.
They employ
various
consultants,
22 | P a g e
[DEVELOPMENT PROCESS]
Consultant
Architect
application
on
owner/developer
behalf
of
to
the
obtain
the
of
execution
the
projects
and
and
Engineer
electrical engineering.
Usually designs and submits plans for
approval by the approving authorities
of his specific area of specialization
and
supersizes
the
economics.
He prepares bills of quantities , tender
and contract documents, normally calls
Quantity Surveyor
23 | P a g e
[DEVELOPMENT PROCESS]
Land Surveyor
Town planner
Project Manager
monitoring implementation of a
development project.
The application approval for this project made by Jabatan Kerja Raya (JKR) , Indah Water , Fire
Fighter , Tenaga Nasional Berhad (TNB) , Majlis Daerah, Pejabat Tanah and Lembaga Air.
Approval Authorities
Approving Section
24 | P a g e
[DEVELOPMENT PROCESS]
Jabatan Kerja Raya
Indah Water
Fire Fighter
Majlis Daerah
Lembaga Air
Pejabat Tanah
Application on generation,
However, for this project , the architect is responsible for the development permission and
approval. The architect will check the form and determine the approval whether it is approved or
denied.
25 | P a g e
[DEVELOPMENT PROCESS]
The approval
authorities will
check and observe
the form report.
The application
result :
Approved or Denied
Figure 20
6. Implementation and Construction
Type of contractors
Main Contractor
Responsibilities
Specializes either in building or civil
engineering works or both , enters into
a main contract with the owner for the
execution and completion of the
construction project.
Enters into contracts with nominated
sub-contractors and nominated
suppliers and be responsible for due
Nominated Sub-Contractor
Other sub-contractors
[DEVELOPMENT PROCESS]
sub-contractors to execute work of a
It is an essential and integral part of the development process. The disposal whether
process.
For this project , the developer decides to make banners to promote the development of
the building. The banners are hang in the middle of the town so that people could see
there is a development of houses to sale. Figure shows an example of banner to
promote the house that need to be sold.
Figure 21
Besides that , radio , internet (blog & website ) also have been used in as an alternative
to promote the residential building. Next, they also open their booth at the Tesco nearby
to promote this project. So the customers who want to buy the house can discuss with
the promoters of the project . Figure 2 shows an example of booth open to promote the
residential project development.
27 | P a g e
[DEVELOPMENT PROCESS]
Figure 22
Types of Cost
A)
Land Cost
53.03
000.00
B)
Construction Cost
= RM 127 548.54
28 | P a g e
[DEVELOPMENT PROCESS]
C)
Professional Fees
D)
Management Cost
5% x RM 6122330.00
= RM 918 349.50
E)
Financing Cost
This
Interest Rate
Connection with the borrowing of funds
Known as borrowing cost
project
financing
cost
is
private
confidential
CONCLUSION
In conclusion, our group choose the project of Cadangan Membina Rumah Berkembar 1
Tingkat Jenis B-T di Atas Lot 762-777, 20 unit Rumah Berkembar 1 Tingkat Jenis B-M di Atas
Lot 778-798 and 12 Unit Rumah Berkembar 1 Tingkat Jenis B-T di Atas Lot 716-827.
This project is modern approach type. There are 5 stages in this type which are
inception , design and costing, construction , in-use and demolition. Besides that , there are 7
steps of development process for this construction which are site identification , evaluation,
acquisition , design and costing, development approval and construction , implementation and
construction and sales and promotion. Every stages and steps have their own function.
Besides that, there are an analysis of development expenditures. There are 4
development expenditures which are land cost , construction cost, professional fees ( architect,
29 | P a g e
&
[DEVELOPMENT PROCESS]
engineer and quantity surveyor fees) , management cost and financing cost basically. Every
cost has their own rate/per cent from the construction cost obviously.
REFERENCES
http://www.google.com/search?
q=maintenance+of+piping+systems&source=lnms&tbm=isch&sa=X&ei=jFXzUcmxNIOPr
[DEVELOPMENT PROCESS]