STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

LIST OF CONTENTS

1. PLANT DETAILS
2. TESTING OBJECTIVES
3. TESTING PROPOSALS
4. SERVICES REQUIRED
5. SAFETY PRECAUTIONS
6. EMERGENCY PROCEDURES
7. STATE OF THE PLANT
8. COMMISSIONING PROCEDURE
9. COMPLETION CRITERIA
10.APPENDICES

SHEET 1 OF 20

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 2 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

1.0

PLANT DETAILS :

1.1

415 Volts LT switchgear consists of two bus sections A &


B with a bus coupler between them. The two sections are
fed from two individual power transformers 1A and 1B in
case of switchboard & upstream breakers in case of MCCs &
ACPs.

The Transformers get their supplies from 11KV unit

switchgear feeders TRF1 & TRF2.


switchboard feeds

415 Volts Unit

the boilers and turbine

service

auxiliaries,

(MCCS) Soot blower MCCs,Battery chargers(220 V ,24 V DC)


Emergency switchgear and other unit auxiliaries.

The

single line diagram of the Unit service switchboard

is

given below :
11 KV UNIT BUS 1A

11 KV UNIT BUS 1B

TRF 1

TRF 2

2000 KVA UNIT


TRANSFORMER
1A

2000 KVA UNIT


TRANSFORMER
1B

I/C 2

I/C 1

B/C

415 UNITS SERVICE


SWITCHBOARD NO-1
Single Line Diagram Unit Service Switchboard

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 3 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

LT SWITCHGEARS in NTPC Simhadri Project:


I.SWITCHBOARDS
1. Unit emergency switchboard(1DG,2DG)
2. Unit Service Switchboard(1DA,2DA)
3. ESP-1 to 4 LT Main switchboard
(1DC,1DD,1DE,1DF,2DC,2DD,2DE,2DF)
4. Station service switchboard(0DA,0DB,0DC)
5. Ash system compressor switchboard(0DD)
6. Ash water Power House switchboard(0DF)
7. Off side plant services switchboard(0DG)
8. Switchyard Service Switchboard(0DH)
9. CHP Switchboard-1
10.CHP Switchboard-3
11.CWPH Switchboard
12.ADM Bldg. Switchboard
13.Raw Water Pump House Switchboard
14.Ash Water Recirculation Service switchboard
15.Sea Water Power House switchboard
16.Bunker service switchboard
17.Sweet Water Makeup Power House switchboard
II Motor Control Centres
1. Turbine MCC(1KA,2KA)
2. Turbine valves MCC(1KB,2KB)
3. Coal mill MCC (1HE,2HE)
4. Boiler MCC(1HA,2HA)
5. Boiler Valve MCC(1HB,2HB)
6. Boiler Damper MCC(1HC,2HC)
7. Boiler AC Distribution Board(1HD,2HD)
8. Track Hopper MCC
9. PT MCC
10.DM Plant MCC
11.CMB MCC
12.ETP MCC
13.Hydraulic Generation Plant MCC
14.Chimney lighting MCC
15.Emergency Chimney board
16.ESP Area MCC
17.ESP A/C & Vent MCC
18.Ash SILO MCC (1QA,2QA)
19.Air Washer MCC(1SA,2SA)
20.AC & Vent MCC (1TA,2TA)
21.Aux. Boiler MCC(0SA)
22.Station AC Distribution Board
III.Aux Control Panels:
ESP 1 to 4 Aux Control Panels (Unit # 1 & Unit # 2)

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 4 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

2.0

TESTING OBJECTIVES :

2.1

The

objectives

of

these

tests

on

the

415

Volts

unit

service switchgear are to ensure that the equipment has


been erected satisfactorily, is suited for the duty it is
required

to

perform,

meets

the

design

and

contact

specifications and is to the appropriate Indian, NTPC and


other relevant engineering standard or code of practices.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 5 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

3.0

TESTING PROPOSAL :

3.1

Every

415

LT

switchgear

consists

of

number

of

equipments and it is proposed that these will be checked


individually
procedures

using
which

standard
will

be

check

lists

recorded

in

and

the

test

testing

schedule.
3.2

Certain

protections

and

inter-tripping

tests

will

be

detailed in the testing schedule.


3.3

The 415 V unit service bus sections B&C will be charged


through the 2000 KVA unit service transformers A or B as
per availability of the transformers and 11 KV unit bus.

3.4

Other LT switchgears are thereafter charged as per the


requirement and availability of supplies

3.5

It will be the duty of the Testing team leader to ensure


that when the system is operating under load condition,
all the equipment which is the subject of this testing
schedule shall be externally inspected for any sign of
stress

or

abnormality

and

that

report

is

prepared

recording the results of inspection and a copy attached


as an appendix to this schedule.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 6 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

4.0

SERVICES REQUIRED :

4.1

In General for carrying out these tests the services

the items listed below are required variable 220

Volts

of
D.C

and 415/240 Volts A.C supplies.


4.2

INSULATION TESTER 500V DC- HAND OPERATER

4.3

CALIBARATION

SOURCE

METERS/TRANSDUCERS.
4.4

MICRO OHM METER.

KID

FOR

CALIBARATION

OF

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 7 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

5.0

SAFETY PRECAUTIONS :

5.1 SAFETY OF THE PLANT :


5.1.1

The test method must be strictly adhered to at all


times except in the following situation.
a.
b.
c.

In an emergency situation.
By agreement with the working party.
On instruction of the test team leader.

5.2

SAFETY OF THE PERSONNEL :

5.2.1

All

the

members

of

the

testing

team

and

persons

associated with this testing/commissioning schedule


should be familiar with the testing procedures and
the equipments involved in testing.
5.2.2

There should be safe access to and escape routes


from confined areas.

5.2.3

The area under test should be clearly defined.

5.2.4

Access to the area under test should be restricted,


proper caution boards should be displayed at the
test area.

5.2.5

Permanent and adequate lighting facilities should be


available at all times.

5.2.6

All

handrail,

stairs,

guards

and

trench

covers

should be properly fitted/replace.


5.2.7

The test area should be clear of obstructions.

5.2.8

Safety clearance certificates and safety clearance


notifications

should

be

in

force

for

the

installations to be energised.
5.2.9

The

operating

about testing.

personnel

should

be

kept

informed

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 8 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

6.0

EMERGENCY PROCEDURE :

6.1

It will be the responsibility of the testing team leader


to inform all members of the testing team what actions
are to be taken in the event of fire, accident or other
major incident.

6.2

Telephone numbers for first aid/ambulance, fire stations


and hospitals should be per monthly displayed adjacent to
every telephone.

6.3

First aid charts for treatment of electrical shock should


be displayed near the test area.

6.4

In the event of any sign of abnormality, the source of


supply

for

the

particular

isolated immediately.

equipment/area

should

be

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 9 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

7.0

STATE OF THE PLANT :

7.1

The following items and their associated equipments


must be erected, complete, accessible for testing
and available for use.
In case of charging Unit Service switchboard
1.

11KV cables from 11KV unit bus 1A and 1B to 2000 KVA


unit service transformers 1A and 1B respectively
2000 KVA (11KV/415V) unit service transformers 1A
and 1B.

2.

415 V bus ducts from unit service transformers 1A


and 1B to 415V unit service switchboard 1 section A
& B and tie from section A to section B.

3.

415 V unit service switchboard no.1 complete with


all its circuit breakers contractors and associated
equipments.

7.2

As above other Switchboards, MCCs and Aux. Control


panels are to be charged according to their
readiness and the availability of upstream supply.

7.3

Erection completion certificates and manufacturers


test certificates should be available for contactors
and associated equipments.

7.4

The tie between emergency switchboard and the 415V


unit service switchboard must be dead and isolated
from

all

sources

of

supply

and

safety

procedure

followed to ensure that the tie remain dead.


7.5

For the checks and tests to be carried out by


energising the equipment to normal working voltage,
the 11KV unit switchgear no-1 sections A&B should be
in an energised condition and the SCLs for the

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 10 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

feeder Outgoings to A&B unit service transformers


should be completed and found satisfactory.
7.6

For carrying out standard check lists and test


procedures which from a part of this testing
schedule, all equipments covered by this testing
shall be dead and isolated from all sources of
supply.

7.7

The associated DAS/Annunciation scheme is complete,


tested and in service.

7.8

The control supplies are available.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 11 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.0

COMMISSIONING PROCEDURE :

8.1.1

Carry out functional checks to prove the operation


of interlocks/inter-tripping between the 415 Volts
incoming and buscoupler breakers in each switchboard
& MCC

8.1.2

Carry out functional checks to prove the operation


of interlock and intertripping between the 11 KV
upstream

and

415

Volts

circuit

breaker

wherever

required.
GENERAL CHECKS:

i)

INSPECT ANY PHYSICAL DAMAGE IN THE BUSBAR,


INSULATION, PANEL DOORS, POWER & SLIDING CONTACTS
ETC. AND TO BE RECTIFIED IF FOUND

ii)

MAKING THE PANEL INSIDE DUSTFREE & FREE FROM FOREIGN


MATERIALS

iii) CHECKING THE TIGHTNESS ALIGNMENT & CLEARANCE OF BUS


BARS ,SMOOTHNESS IN RACKING IN & RACKING OUT OF
MODULES,PROPER MAKING OF SLIDING CONTACTS, TIGHTNESS

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 12 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

OF INPUT POWER CABLES AND MODULE POWER CONTROL O/PS


& CONTROL INTERNAL WIRINGS
iv)

INSPECT ALL RELAYS AND MAKE SURE THAT ANY BLOCKING


USED FOR SHIPPING PURPOSE IS REMOVED AND THE
ARMATURE

v)

MOVES FREELY.

CHECK ALL DOORS FOR PROPER MOUNTING WITH RESPECT TO


THE SWITCH HANDLE.

vi)

CHECK DOOR INTERLOCK MECHANISM

vii) TEST THE PTs,CTs & RELAYS INVOLVED. KEEP THE


RECOMMENDED SETTINGS FOR THE RELAYS LIKE
OVERCURRENT, UNDERVOLTAGE & OVERLOAD PROTECTIONS,
CALIBRATE THE METERS (AMMETERS, VOLTMETERS, POWER
METERS & ENERGY METERS ETC)
viii) TEST THE INSULATION OF BOARDS WITH 500 V DC MEGGER &
THE VALUE SHOULD BE AS PER THE RELEVANT IS
SPECIFICATION (MORE THAN 5 MEGA OHMS)
ix)

CHECK CLOSING & TRIPPING INTERLOCKS,OVERLOAD RELEASE


SETTING OF ALL ACBs IN THE PANEL

x)

CHECK THE PROTECTION CIRCUIT WIRING CONNECTIONS BY


CONDUCTING PRIMARY INJECTION CURRENT

xi)

CHECK

THE INPUT POWER CABLE TERMINATIONS FROM

TRANSFORMER SECONDARY

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 13 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

xii) ENSURE

THE PHASE SEQUENCE AND CT LINKS ARE PROPER

BEFORE CHARGING THE PANEL.


xiii)

CHECK CLOSING & TRIPPING MECHANISM OPERATES


SMOOTHLY BOTH MANUALLY AND ELECTRICALLY

xiv) SPACE HEATERS & THERMOSTAT SHALL BE IN GOOD


CONDITION

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 14 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.2 ENERGISING CHECKS

8.2.1

Check that safety Notices have been displayed at the


test area and that the safety clearance certificate
has been issued and is effective.

8.2.2

Check

that

communications

have

been

stabilised

between 11 KV switchgear,415 Volts switchgear and


the UCB.
8.2.3

Ensure that the 11 KV and 415 Volts circuit breakers


for

charging

breakers

are

between

in

isolated

Emergency

position.

switchboard

Also

tie

No-1

and

buscoupler breaker at unit service switchboard No-1


are OFF and isolated.
8.2.4

Ensure that the 415 volts V.T.s for Section A & B


are in position and

8.2.5

Ensure

that

all

fuses
the

in service.

outgoing

feeder

breakers,

contactors and Isolators of 415 Volts switchgear are


off and isolated.
8.2.6

Ensure that the control circuit fuses for 11 KV and


415

volts

circuit

breakers

for

the

power

transformers and those for the 415 volts bus coupler


breaker of switchboard are put on.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 15 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.2.7

Ensure that protection relay settings are correct


for feeder VCBs at HT switchgear and incomers at LT
switchgear.

8.3 ENERGISING PROCEDURE:

8.3.1

Energise the 415 volts switchgear control circuit


bus

8.3.2

from its normal source of supply.

Put the 415 volts circuit breaker(Incomer 1) in test


position with selector switch in LOCAL

8.3.3

close and open the breaker from local and check that
the status indications are correct.

8.3.4

Carry out the tests 8.3.2 & 8.3.3 for the next
incomer and

buscoupler for the same LT

Switchgear.
8.3.5

Put the 11 KV breaker for power transformer - A in


test position with the selector switch to interlock
OUT position.

8.3.6

Close and open the 11 KV breaker from local and

check that status indications are correct

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 16 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.3.7

Put the selector switch to interlock IN and close


and open the breaker from UCB and check that status
indications are correct.

8.3.8

Carry out the tests 8.3.6 8.3.8 for 11 KV breaker


Transformer B

8.3.9

Put the 11 KV breaker transformer A in service


position with the selector switch to interlock IN
position.

8.3.10

Close the 11 KV breaker from UCB to first

energise

the Power Transformer A


8.3.11

Open and close the 11 KV breaker

8.3.12

Note the ammeter for the transformer H.V side for


any

abnormal

current.

Check

the

transformer

externally for any abnormality.


8.3.13

If 8.3.13 is O.K.,put the 415 Volts breaker (Incomer


1) for Transformer A in SERVICE position with the
selector switch in REMOTE.

8.3.14

Close the 415 Volts Incomer 1 breaker from UCB to


first energise the section A of LT switchboard.

8.3.15

Note the ammeter in section A for any abnormal


current. Also note the voltmeter in SEC A and check
that the bus voltages are O.K. and that the under

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 17 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

voltage

relays

are

in

picked

up(energised)

condition. Check phase rotation.


8.3.16

Check externally for any abnormality with the 415


Volts LT switchboard.

8.3.17

Initiate tripping through overcurrent relay on the


11 KV side and check that both the 11 KV and 415
Volts breakers of the power transformer A trip.

8.3.18

If 8.3.16 and 8.3.17 are O.K., put the 415 Volts


buscoupler breaker for LT switchgear in SERVICE
position with the selector switch in REMOTE

8.3.19

Close the 11 KV and 415 Volts breakers(Incomer 2)


for power transformer B in TEST position

8.3.20

Close the 415 volts buscoupler breaker from UCB to


first energise the section B of the LT switchgear

8.3.21

Note the ammeter in incomer-A panel for any abnormal


current. Also note the voltmeter in bus section B
for correct bus voltages.

8.3.22

Check that the undervoltage relays in section B are


in pickuped condition (energised) condition.

8.3.23

Check externally for any abnormality with the 415


Volts in bus section B

8.3.24

Switch off the bus coupler breaker

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 18 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.3.25

If 8.3.22 to 8.3.24 are O.K., put the 11 KV breaker


for power transformer B in SERVICE position with
its selector switch to interlock IN

8.3.26

Close the 11 KV breaker for power transformer B from


UCB to first energise the transformer.

8.3.27

Open and reclose the 11 KV

8.3.28

Note

the

ammeter

on

the

breaker
11

KV

side

of

the

with

the

transformer for any abnormal current


8.3.29

Check

externally

for

any

abnormality

transformer B
8.3.30

If 8.3.29 and 8.3.30 are O.K., put the 415 Volts


breaker(Incomer 2) for Transformer B in SERVICE
position with its selector switches in REMOTE

8.3.31

Close the 415 volts breaker for the transformer to


energise the bus section B

8.3.32

Note the ammeter and voltmeter in bus section B for


any abnormal current and voltage.

8.3.33

Check phase rotation of B section and phase in &


phase out between section A & B

8.3.34

If

everything

with

the

transformers

and

the

LT

switchgear are O.K. keep the transformers and the


415 volts bus energised for 24 hours.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 19 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

8.3.35

After 24 hours check that there is no abnormality


with

the

transformers

and

the

415

Volts

LT

switchgear. Also check periodically bucholtz relay


for any chapped gas on in.
8.3.36

For MCCs & Aux. Control panels ,Upstream breakers


and interconnecting cables will come into picture in
stead

of

11

KV

outgoing

feeder

and

power

transformers.

9. COMPLETION CRITERIA

RESPECTIVE LT POWER TRANSFORMERS & 415 V SWITCHGEAR


PANELS

ARE CHARGED. VOLTAGE SUPPLY EXTENDED UPTO

SWITCHBOARD,MCC or ACP as the case may be AND VOLTAGES ARE


FOUND IN POSITIVE PHASE SEQUENCE WITH NO ABNORMALITY IN
CURRENT AND EXTERNAL BODY OF THE PANEL.

STATION: NTPC SIMHADRI

BHEL REF NO : PS-DC-186-500NTPC REF NO: SIM/1/TS/


/

SHEET 20 OF 20

PLANT AREA : ELECTRICAL SYSTEM


TESTING SCHEDULE : LT SWITCHGEAR

10. APPENDICES
DRAWINGS

: SLD OF ELECTRICAL SYSTEM AUX POWER


DISTRIBUTION
SCHEMATIC DIAGRAM OF LT SWITCHGEARS (USS,MCC,ACP)

MANUALS

: O &

M MANUAL FOR LT SWITCHGEAR (PE-OM-186506-0328)

DATA FOR LT SWITCHGEAR (PE-OM-186-5060327)

LOG SHEETS :

I)

IR VALUES,BUS BAR RESISTANCE

VALUES

OF LT SWITCHGEAR
II)

TEST REPORT OF RELAYS,PTs,CTs INCLUDED IN


THE SYSTEM

III)

UNDERVOLTAGE,OVERCURRENT& EARTHFAULT
SETTINGS RECOMMENDED/KEPT