Sunteți pe pagina 1din 16

CHANGE ORDER REQUEST (COR)

COR No:
Contract No:
Project No:

Date :
Contractor:

Description of Change:
1)
2)

Reason of Change:

Drawing and specification Reference:


Drawing No.

Section No.

OWNER / REPRESENTATIVE

CONTRACTOR

By :

By :

Date :

Date :

The COR represents any and all amount Contractor claims for the change referred to herein
(including any claim fro delay or impact upon the Project Schdule, Milestone of other Contract
time)

CHANGE ORDER (CO)


CO No:
Contract No
Project No

Date
:
:

Contractor
Address
Attention

:
:
:

Except as otherwise expressly provided herein, Contractor agrees to perform the work described herein in
accordance with the Contract Documents. Contractor shall notify surety of this Change Order.
Description of CO :

Pricing :

Days (added) (deleted) as a result of this CO


Revised Substantial Completion Date is
Revised Final Completion Date is

:
:
:

ORIGINAL CONTRACT PRICE


PREVIOUS CO NUMBERS (_____ through______)
AMOUNT OF THIS CO
CURRENT CONTRACT PRICE

This CO represents final adjustment for, any and all amount due or to become due Contractor for changes
referred to herein. Contractor further releases all other claims, if any (except those claims previously submitted
in accordance with the Contract), for additional compensation under this Contract Agreement, including
without limitation any rights Contractor may have for additional compensation arising out of delays or
disruption of impact upon Contractor's schedule, any Milestone or other Contract time as may have arisen
prior to the date of this CO. Unless otherwise provided herein, the time of completion and other terms and
conditions of the Contract remain unchanged.

OWNER / REPRESENTATIVE
By :
Title :

CONTRACTOR
By :
Title :

Date :

Date :

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI ATAS
LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG UNTUK TETUAN
ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Proposal Of R.C. Beam Cracks Epoxy Injection Work


Item
1.0

Descriptions

Date :

3/14/2011

Rate (RM)

Amt (RM)

SOR

Unit

Qty

New

line

20.00

1,280.00

25,600.00

a) 32mm diameter x 200mm depth

New

nos

92.00

50.00

4,600.00

b) 16mm diameter x 160mm depth

New

nos

158.00

36.00

5,688.00

To supply skilled labour, tools, equipments amd


Concresive 1333 low viscosity Epoxy resin to
do Injection work to approx. 2m crack line

(Any additional point based on RM84.00 / point @100mm c/c)

2.0

To supply skilled labour, tools, equipments amd


Concresive 2525 solvent free epoxy resin binder
to fill up holes for:

Note :
1) The above works shall be carried out by Specialist namely Alvatis Technologies (M) Sdn Bhd.
2) Quantities shall be provisional and subjected to final measurement.

Total Addition Cost :

35,888.00

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA
2 TINGKAT DI ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG
PERAI TENGAH, PULAU PINANG UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING
SDN. BHD.

Ref : E.I. No. EI-81135C-P500-008 dated 4th March 2011


Drawing Reference : 81135C-AR-06, AR-TD-14 & AR-03
(For COR & CO No. 13)
Item

SOR

Description

Unit

Qty.

Rate

Ref

Amount
(RM)

Omission
Change of Staircase detail S1 & S2
1

1.1

115mm thk half brick wall

m2

914.96

29.67

(27,146.95)

5.1

Cement sand plastering

m2

1,829.93

21.74

(39,782.58)

3.1

Painting internally

m2

1,829.93

12.12

(22,178.70)

4.4

300x300mm Homogeneous tiles

m2

83.40

72.72

(6,064.69)

4.4

Nosing tiles

121.20

19.19

(2,325.83)

partition

m2

137.97

121.20

(16,721.96)

100mm thk Dry wall partition

m2

202.57

101.00

(20,459.56)

To omit partition at New BDG01 1st Floor


4

1.3

1.3

100mm thk Half glass gypsum board

To omit Door and Window


6

8.2

AD 4 Alum frame alum. single swing door

no

5.00

303.00

(1,515.00)

8.2

AD 5 Alum. Frame double swing door

no

2.00

1,010.00

(2,020.00)

8.2

SS 2 Alum frame half glass sliding door

no

3.00

9,898.00

(29,694.00)

Addition
Change of Staircase detail S1 & S2
1

1.1

115mm thk half brick wall

m2

1,068.90

29.67

31,714.30

5.1

Cement sand plastering

m2

2,137.80

21.74

46,475.83

3.1

Painting internally

m2

2,137.80

12.12

25,910.17

4.4

300x300mm Homogeneous tiles

m2

108.57

72.72

7,895.17

4.4

Nosing tiles

161.40

19.19

3,097.27

Total Omission Cost :

(52,816.53)

Drawing no. AR-TD-14 Rev 0.1

Original
Omission
Revised staircase detail S1
Location
Grd Flr
1st Flr
Roof

L
16
17
19.68

H
8
6.6
3

Revised staircase detail S2


Grd To Roof
15.806 11.23

Revised Drawings
Addition
Less
Door
7.56
3.78
3.78

Ref Window Area (m2)

0.36

3.78

120.44
108.42
54.9
283.76

173.72
457.48138

L
16.2
19
22.124

21.194

H
8
6.6
3

Less
Door
11.34
3.78
3.78

11.23

5.67

Window

0.36

Area (m2)
118.26
121.62
62.23
302.11

232.34
534.45

Summary
1) Brickwork
2) Plastering
3) Painting

Omission
Half glass partition
- New Room 4
17
- Open Space
25

914.96 m2

1,068.90 m2

1,829.93 m2
1,829.93 m2

2,137.80 m2
2,137.80 m2

m2
3.6
3.6

AD4
AD4
SS2

1.89
3.78
7.56

NIL

59.31
86.22
(7.56)

137.97 m2
100mm thk drywall partition
New Room 4
0
3.6
Stator
11.6
3.6
Packing
12
3.6
- PM Room
16
3.6
- Stator
9.4
3.6
- Packing
11.54
3.6

NIL
AD4
SS2
AD5
AD4
AD5

39.87
39.42
53.69
31.95
37.64

1.89
3.78
3.91

1.89
3.91

202.57 m2
Door & Window
AD4
AD5
SS2

nos
nos
nos

Homogeneous tiles to staircase


S1
Grd Floor
6.088 2.52
1 0.87
1st Floor
7.142 2.52
Roof Level

Grd Floor
1st Floor

5.745

5
2
3

m2

S1

15.34
0.87
18.00

2.52

14.48

S2
6.586 2.634
6.587 2.636

6.086
1
6.086
1
6.086

2.94
0.87
3.476
1.12
3.476

m2
17.89
0.87
21.15
1.12
21.15

6.671
6.671

3.476
3.476

23.19
23.19

S2
17.35
17.36

83.40 m2
Nosing tiles
Grd Floor
1st Floor
Roof

S1

108.57 m2
S1

1.2
1.2
1.2

23
18
14

27.6
21.6
16.8

1.4
1.7
1.7

23
19
15

32.20
32.30
25.50

1.2
1.2

26
20

31.2
24
121.2 m

1.7
1.7

23
19

39.10
32.30

S2
Grd Floor
1st Floor

161.40 m

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Ref

Desciption

Unit

Qty

Rate

Amount (RM)

OMISSION
1.0
Surface water ''U'' shaped drain
1.1 7.32 450mm wide Concrete drain
1.2 7.33 600mm wide Concrete drain

m
m

2.0
Reinforcement Concrete Sump
2.1 7.41 450mm x 450mm
2.2 7.42 750mm x 750mm

(51.00)
(196.00)

136.35
171.70

(6,953.85)
(33,653.20)

Nos
Nos

(1.00)
(3.00)

303.00
505.00

(303.00)
(1,515.00)

Nos
Nos

(2.00)
(1.00)

808.00
1,010.00

(1,616.00)
(1,010.00)

m2

(258.00)

5.05

(1,302.90)

4.2 7.10 Trim, grade and roll sub-grade to required cambers


and gradient as described

m2

(258.00)

0.81

(208.98)

4.3 7.11 50mm thick (Consolidated) of sand blanket to the


required cambers and gradients.

m2

(258.00)

2.42

(624.36)
-

4.4 7.12 230mm thick (consolidated) of 50mm crusher run as


base course rolled to two layers to the required
cambers and gradients, watered and blinded as
described and thoroughly consolidated by 25 tonne roller

m2

(258.00)

9.39

(2,422.62)

4.5 7.13 65mm thick (consolidated) of 40mm asphalt concrete


as binder course rolled to the required cambers and
gradients

m2

(258.00)

21.92

(5,655.36)

4.6 7.14 40mm thick (consolidated) of 20mm asphalt concrete


as wearing course rolled to the required cambers
and gradients.

m2

(258.00)

12.93

(3,335.94)

4.7 7.15 Bituminous tack coat applied at the rate 0.50 litre/square.

m2

(258.00)

0.71

(183.18)

4.8 7.16 Bituminous prime coat applied at the rate 0.50 litre/square.

m2

(258.00)

0.71

(183.18)

3.0

TRASH SCREEN
Supply and install sump c/w trash screen
3.1 7.48 750mm x 750mm
3.2 7.48 900mm x 900mm

4.0
4.1

ROAD WORK (At Entrance)


7.9

Excavate oversite to sub-grade formation level; get out


and get out excavated material from site

Total Omission:

(58,967.57)

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Ref
A

Desciption

Unit

Qty

Rate

Amount (RM)

ADDITIONAL
DRAINAGE WORK

1.0
Surface water ''U'' shaped drain
1.1 7.31 300mm wide Concrete drain
1.2 7.32 450mm wide Concrete drain
1.3 7.33 600mm width Concrete drain along the boundary of
exist (Utusan) Factory (omitted under CO No. 5)
1.4 New 450mm wide Concrete drain with 2 layer brc A8

m
m

152.00
51.00

126.25
136.35

19,190.00
6,953.85

m
m

92.00
97.00

171.70
190.00

15,796.40
18,430.00

Nos
Nos
Nos
No
No
Nos

2.00
3.00
1.00
1.00
1.00
2.00

303.00
490.00
630.00
2,700.00
3,240.00
1,500.00

606.00
1,470.00
630.00
2,700.00
3,240.00
3,000.00

Nos

2.00

3,300.00

6,600.00

4.00

440.00

1,760.00

m2

131.00

5.05

661.55

5.2 7.10 Trim, grade and roll sub-grade to required cambers


and gradient as described

m2

131.00

0.81

106.11

5.3 7.11 50mm thick (Consolidated) of sand blanket to the


required cambers and gradients.

m2

131.00

2.42

317.02

5.4 7.12 230mm thick (consolidated) of 50mm crusher run as


base course rolled to two layers to the required
cambers and gradients, watered and blinded as
described and thoroughly consolidated by 25 tonne roller

m2

131.00

9.39

1,230.09

5.5 7.13 65mm thick (consolidated) of 40mm asphalt concrete


as binder course rolled to the required cambers and
gradients

m2

131.00

21.92

2,871.52

5.6 7.14 40mm thick (consolidated) of 20mm asphalt concrete


as wearing course rolled to the required cambers
and gradients.

m2

131.00

12.93

1,693.83

5.7 7.15 Bituminous tack coat applied at the rate 0.50 litre/square.

m2

131.00

0.71

93.01

2.0
2.1
2.2
2.3
2.4
2.5
2.6

7.41
New
New
New
New
New

Reinforcement Concrete Sump


450mm x 450mm (original - 750mm x 750mm)
600mm x 600mm (original - 750mm x 750mm)
900mm x 450mm (original - 450mm x 450mm)
1900mm x 750mm (Additional)
1900mm x 900mm (Additional)
5mm thick corrosion resistant steel plate

3.0
TRASH SCREEN
3.1 New Supply and install sump c/w trash screen
Size: 1.90m x 0.75m
(original - 750mm x 750mm (1 no), 900mm x 900mm (1no)

4.0
Precast Reinforcement Concrete Scupper Pipe
4.1 New 750 mm diameter Discharge with orifice to external drain (didnt
5.0

5.1

ROAD WORK
PREMIX ROADS (at section 01 - 02) Extend from 6.1m to 6.56m
along Exist. (Utusan) Factory as per drawings
7.9

Excavate oversite to sub-grade formation level; get out


and get out excavated material from site

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Desciption
Ref
5.8 7.16 Bituminous prime coat applied at the rate 0.50 litre/square.

Unit
m2

Qty
131.00

Rate
0.71

Amount (RM)
93.01

Total Addition:

87,442.39

TOTAL ADDITIONAL COST:

28,474.82

PLB-KH BINA SDN BHD


CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Project:

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Ref

Desciption

Unit

Qty

Rate

Amount (RM)

OMISSION
1.0
Surface water ''U'' shaped drain
1.1 7.32 450mm wide Concrete drain
1.2 7.33 600mm wide Concrete drain

m
m

(51.00)
(196.00)

136.35
171.70

(6,953.85)
(33,653.20)

(22.00)

959.50

(21,109.00)

Nos
Nos

(1.00)
(3.00)

303.00
505.00

(303.00)
(1,515.00)

Nos
Nos

(2.00)
(1.00)

808.00
1,010.00

(1,616.00)
(1,010.00)

m2

(258.00)

5.05

(1,302.90)

4.2 7.10 Trim, grade and roll sub-grade to required cambers


and gradient as described

m2

(258.00)

0.81

(208.98)

4.3 7.11 50mm thick (Consolidated) of sand blanket to the


required cambers and gradients.

m2

(258.00)

2.42

(624.36)
-

4.4 7.12 230mm thick (consolidated) of 50mm crusher run as


base course rolled to two layers to the required
cambers and gradients, watered and blinded as
described and thoroughly consolidated by 25 tonne roller

m2

(258.00)

9.39

(2,422.62)

4.5 7.13 65mm thick (consolidated) of 40mm asphalt concrete


as binder course rolled to the required cambers and
gradients

m2

(258.00)

21.92

(5,655.36)

4.6 7.14 40mm thick (consolidated) of 20mm asphalt concrete


as wearing course rolled to the required cambers
and gradients.

m2

(258.00)

12.93

(3,335.94)

4.7 7.15 Bituminous tack coat applied at the rate 0.50 litre/square.

m2

(258.00)

0.71

(183.18)

4.8 7.16 Bituminous prime coat applied at the rate 0.50 litre/square.

m2

(258.00)

0.71

(183.18)

2.0

Box Culvert
7.35 1500x1200mm Box Culvert

3.0
Reinforcement Concrete Sump
2.1 7.41 450mm x 450mm
2.2 7.42 750mm x 750mm
4.0

Trash Screen
Supply and install sump c/w trash screen
3.1 7.48 750mm x 750mm
3.2 7.48 900mm x 900mm

4.0
4.1

ROAD WORK (At Entrance)


7.9

Excavate oversite to sub-grade formation level; get out


and get out excavated material from site

Total Omission:

(80,076.57)

PLB-KH BINA SDN BHD


CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Project:

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Ref
A

Desciption

Unit

Qty

Rate

Amount (RM)

ADDITIONAL
DRAINAGE WORK

1.0
Surface water ''U'' shaped drain
1.1 7.31 300mm wide Concrete drain
1.2 7.32 450mm wide Concrete drain
1.3 7.33 600mm width Concrete drain along the boundary of
exist (Utusan) Factory (omitted under CO No. 5)
1.4 New 450mm wide Concrete drain with 2 layer brc A8

m
m

174.00
-

126.25
136.35

21,967.50
-

m
m

92.00
97.00

171.70
190.00

15,796.40
18,430.00

7.35
New
New
New

Box Culvert
1500mm x 1750mm Box culvert
100mm dia perforated holes at base
Supply and lay non-woven geotextile
100mm dia bakau piles at 3m length

m
no
m2
nos

22.00
88.00
45.00
525.00

959.50
85.00
15.00
18.00

21,109.00
7,480.00
675.00
9,450.00

7.41
New
New
New
New
New

Reinforcement Concrete Sump


450mm x 450mm (original - 750mm x 750mm)
600mm x 600mm (original - 750mm x 750mm)
900mm x 450mm (original - 450mm x 450mm)
1900mm x 750mm (Additional)
1900mm x 900mm (Additional)
5mm thick corrosion resistant steel plate

Nos
Nos
Nos
No
No
Nos

2.00
3.00
1.00
1.00
1.00
2.00

303.00
490.00
630.00
2,700.00
3,240.00
1,500.00

606.00
1,470.00
630.00
2,700.00
3,240.00
3,000.00

Nos

2.00

3,300.00

6,600.00

4.00

440.00

1,760.00

m2

131.00

5.05

661.55

5.2 7.10 Trim, grade and roll sub-grade to required cambers


and gradient as described

m2

131.00

0.81

106.11

5.3 7.11 50mm thick (Consolidated) of sand blanket to the


required cambers and gradients.

m2

131.00

2.42

317.02

5.4 7.12 230mm thick (consolidated) of 50mm crusher run as


base course rolled to two layers to the required
cambers and gradients, watered and blinded as
described and thoroughly consolidated by 25 tonne roller

m2

131.00

9.39

1,230.09

5.5 7.13 65mm thick (consolidated) of 40mm asphalt concrete


as binder course rolled to the required cambers and
gradients

m2

131.00

21.92

2,871.52

5.6 7.14 40mm thick (consolidated) of 20mm asphalt concrete


as wearing course rolled to the required cambers
and gradients.

m2

131.00

12.93

1,693.83

5.7 7.15 Bituminous tack coat applied at the rate 0.50 litre/square.

m2

131.00

0.71

93.01

2.0

2.0
2.1
2.2
2.3
2.4
2.5
2.6

3.0
TRASH SCREEN
3.1 New Supply and install sump c/w trash screen
Size: 1.90m x 0.75m
(original - 750mm x 750mm (1 no), 900mm x 900mm (1no)

4.0
Precast Reinforcement Concrete Scupper Pipe
4.1 New 750 mm diameter Discharge with orifice to external drain (didnt p m
5.0

5.1

ROAD WORK
PREMIX ROADS (at section 01 - 02) Extend from 6.1m to 6.56m
along Exist. (Utusan) Factory as per drawings
7.9

Excavate oversite to sub-grade formation level; get out


and get out excavated material from site

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-016 dated 23rd March 2011


(For COR & CO No. 14)
No.
SOR
Desciption
Ref
5.8 7.16 Bituminous prime coat applied at the rate 0.50 litre/square.

Unit
m2

Qty
131.00

Rate
0.71

Amount (RM)
93.01

Total Addition:

121,980.04

TOTAL ADDITIONAL COST:

41,903.47

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-022 dated 18th March 2011


(For COR & CO No. 16)
No.
SOR
Ref
1.0

Desciption

Unit

Qty

Rate

Amount (RM)

BDG01-Existing building - To omit internal walkable service


platform inside existing BDG01 Assembly area.
Omission

1.1

4.9

2.0

To omit internal walkable service platform

kg

(9,600)

7.07

(67,872.00)

(22,300)

7.07

(157,661.00)

20.20
29.34
2.79
2.79
198.11
174.78

343.40
3,344.76
6,037.56
934.65
3,367.87
270.91

BDG01-Existing building - To omit MEP Evaporative Cooler


service platform from existing BDG01 along Gridline Ex 8/A-J,
Ex 9/A-J and Ex.10/A-J from package CSA 500
Omission

2.1

4.9

To omit MEP service platform at BDG01 exisitng building

kg

2.2

4.9

Addition
MEP service platform at BDG01 new extension building

kg

3.0

3.1

4.0

4.1
a) 3.1
b) 3.2
c) 3.3
d) 3.4
e) 3.7
f) 3.11

BDG01 & BDG02 - To dismantle 2nos of the existing canopy


link connected between BDG01 and BDG02 at Gridline Ex.5
and Ex.7
Addition
To dismantle existing canopy link
a) Semi-skilled labour
b)
BDG01, BDG02 & BDG05 - Column and piling for walkway
canopy to be omitted.
Omission
Pile caps
Excavation
Sawn formwork to sides
T20
R10
VRC G30
50mm thk Lean concrete

m3
m2
kg
kg
m3
m2
Total Omission:

17
114
2,164
335
17.00
1.55

(211,233.85)

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-022 dated 18th March 2011


(For COR & CO No. 16)
No.
SOR
Ref

Desciption

Unit

Qty

Rate

Amount (RM)

PLB-KH BINA SDN BHD


Project:

CADANGAN PINDAAN DAN TAMBAHAN SERTA MEMPERBAIKI KEPADA KILANG SEDIA ADA 2 TINGKAT DI
ATAS LOT 2815, H.S. (D) 40497, MUKIM 1, JALAN JELAWAT, SEBERANG PERAI TENGAH, PULAU PINANG
UNTUK TETUAN ALLIANCE CONTRACT MANUFACTURING SDN. BHD.

Ref : E.I. No. EI-81135C-P500-022 dated 18th March 2011


(For COR & CO No. 16)
No.
SOR
Ref

Desciption

Unit

Total Addition:
TOTAL ADDITIONAL COST:

Qty

Rate

Amount (RM)

(211,233.85)

S-ar putea să vă placă și