CONTENTS
1. GENERAL
2. INTENT OF SPECIFICATIONS
3. SPECIAL STIPULATIONS TO BIDDERS
4. SYSTEM PARAMETERS, OPERATION AND CONTROL PHILOSOPHY
5. GENERAL TECHNICAL REQUIREMENTS
6. ELECTRICAL
7. CIVIL
8. CONDITION OF CONTRACT FOR FIELD SERVICES
9. MISCELLANEOUS
(A GOVERNMENT OF INDIAENTERPRISE)
PROJECT OFFICE
ST
BHAGWANTOWER, 1 FLOOR
CUTTACK ROAD,
BHUBANESWAR 751006
1
INDEX
DESCRIPTION
SECTION
PAGE NO
GENERAL
1-5
INTENT OF SPECIFICATIONS
1-17
1-11
1-64
1-27
ELECTRICAL
1-97
CIVIL
1-21
1-23
MISCELLANEOUS
1-55
SECTION 1
1.0
GENERAL
M/S. National Aluminium Company Ltd. (NALCO), Angul have undergone 2nd phase
expansion of their Captive Power Plant (CPP).The 9th & 10th units are added in 2nd phase
expansion of the Existing Captive Power Plant (CPP) by increasing the station capacity to
1200MW. Facility for Storage and Handling of about 90,000 t additional uncrushed Coal has
been envisaged to be added in 2nd phase expansion of Captive Power Plant. The new
uncrushed coal storage yard shall be equipped with stacker and reclaimer machines and
shall have uncrushed coal supply connectivity to old and new coal bunkers
bu
through
respective Crusherhouse.
2.0
3.0
Basic Data
Material to be handled
Feed size
Specific gravity of coal
Moisture (%)
No of working days / yr
No of working shift / day
3.1
3.2
3.3
There are two (2) nos. of existing Track Hopper Buildings with underground
undergrou RCC hopper.
3.4
Each TrackHopperBuilding has four (4) nos. of paddle feeders of travelling type at its bottom
to scoop coal from the track hopper. Two paddle feeders are mounted on individual
conveyor.
3.5
There are two (2) underground conveyors at bottom of each track hopper. Both conveyors
are running parallel at the bottom of the track hopper1.
hopper 1. The parallel conveyor installed at
the bottom of track hopper2
hopper run in opposite direction.
3.6
There are two (2) Bunker Bays. The old BunkerBay meets the crushed coal requirement for
Unit 1 6 whereas the new BunkerBay meets the crushed coal requirement for unit 7 to 10.
Thus, there are two separate conveyor paths. Each path has two conveyor streams running
in parallel.
Page 1 of 5
3.7
Rated & designed capacity of each conveyor stream is 800 TPH & 960 TPH respectively.
3.8
Two parallel conveyors with moving tripper are installed on the top of each BunkerBay. One
moving tripper is provided on each conveyor installed on the top of BunkerBay.
Bun
Moving
trippers feed the crushed coal in desired bunkers as per requirement.
3.9
3.10
3.11
There are three uncrushed coal storage yards with stacker cum reclaimer machine (SCR) in
present CHP. One SCR machine is provided on each storage yard.
3.12
Storage yard 1 & 2 receive uncrushed coal from track hopper 1 & 2. Storage yard 3 receives
uncrushed coal
oal from track hopper 2 only.
3.13
Scooped uncrushed coal from track hopper 1 is conveyed to old Crusher house and then to
coal bunker bay of Units 1-6
1 6 through conveyor path that is conveying crushed coal to coal
bunkers Bay of Units 1-6.
6.
OR,
Uncrushed coall is conveyed to storage yard 1 & 2. Preparation of coal Stock Pile is carried
out by installed Stacker--cum-Reclaimer
Reclaimer (SCR) machine. Uncrushed coal is reclaimed by SCR
machine and conveyed to either of boiler bunkers through dedicated conveyor paths which
is operating for these two boiler bunker bays.
OR,
It is conveyed to boiler bunker Bay of Units 7 to 10 through new Crusherhouse
Crusher
by conveyor
path that is feeding crushed coal in boiler bunkers of Unit 7 & 8. SCR machine is positioned
in by-pass mode whilee conveying coal from track hopper 1.
3.14
Scooped coal from track hopper 2 is conveyed to Crusher house and then to coal bunker bay
of Units 7 to 10 through conveyor path that is conveying crushed coal to coal bunkers Bay of
Units 7 to 10.
OR,
It is conveyed to boiler bunker Bay of Units 11 6 through conveyor path linked with track
hopper 1. OR, It is conveyed to storage yard 3. Preparation of stockpile is made with the help
of SCR machine. Coal from the Stock Pile is reclaimed by SCR machine and is fed on to yard
conveyor. The yard conveyor discharges the coal on to the conveyor path linked with boiler
bunker bay of Units 7 to 10.
Page 2 of 5
OR,
It is conveyed to the storage Yard 1&2 through the conveyor paths linked with track hopper
1.
4.0
4.2
4.3
4.4
4.5
4.6
4.7
For Receipt of uncrushed coal for the proposed Additional Coal Storage and Handling
System, uncrushed coal conveyed
con
to JH-7 by existing conveyor BC-115
115 from Track Hopper
No.2 can be diverted either to existing conveyor BC-116
BC 116 or to new conveyor BC-118A
BC
at
Junction House JH-7.
7. The new conveyor BC-118A
BC 118A will convey material to the proposed
Additional Coal Storage Yard
Yard through a new conveyor system under development. For this,
the existing Junction House JH-7,
JH 7, shall be modified to accommodate the tail end of new
conveyor BC-118A.
118A. The discharge chute of the existing conveyor BC-115
BC 115 shall be replaced
Page 3 of 5
For storage of uncrushed coal in the Additional Coal Storage Yard under development, the
coal received through conveyor BC-118A
BC 118A will be conveyed to the Yard through conveyors BCBC
119 & BC-120
120 and new Junction Houses JH-10
JH
& JH-11.
1. The conveyor BC-120
BC
will be
equipped with a Slew Stacker Machine. The Slew Stacker Machine will be capable of forming
two identical stock piles of uncrushed coal on either side of its track. The length of each
stock pile will be 275 m. The storage capacity
capacity of each Stock Pile will be 45,000 t of uncrushed
coal. The rated capacity of stacking system is 800 t/hr
4.9
For Reclaiming the uncrushed coal from Additional Coal Storage Yard, a Bucket Wheel
Reclaimer will be provided. The Bucket Wheel Reclaimer will be installed on conveyor BC 120 such that its discharge is collected on the yard conveyor BC-120.
BC 120. The BWR will be
operating on the same track as that of the Slew Stacker Machine. Simultaneous operation of
stacking and reclaiming is also proposed on the yard conveyor BC-120.
120. Uncrushed coal
reclaimed on conveyor BC-120
BC 120 will be conveyed to new Junction House JH-12.
JH
The rated
capacity of the reclaiming system shall be 800 t/hr.
4.10
4.11
4.12
For Conveying the uncrushed coal to the old Crusher house, uncrushed coal received on
conveyor BC-121
121 shall be conveyed to new Junction House JH-13.
JH 13. At this new Junction
House JH-13,
13, conveyor BC-121
BC 121 will discharge the material to the extended tail end of the
Page 4 of 5
Dust Suppression System will be provided at all transfer points at various Junction Houses
and uncrushed coal storage yard.
4.14
on and air conditioning facilities will be provided in Switch gear cum MCC
Suitable ventilation
room, Battery room, Transformer rooms.
4.15
PLC based operation & control system is being provided for additional coal storage &
handling system. Controls are being suitably interfaced with existing conveyor system
through limit switches.
Page 5 of 5
SECTION 2
1.0
1.1
INTENT OF SPECIFICATIONS
This specification is intended to cover the following activities and services in respect of
all the equipment of Wagon Tippler and Conveyor System Package to be installed for
National Aluminium Company Limited (NALCO), Captive Power Project located in Angul
Angu
of Orissa State in India.
(a.) The broad scope of work covers the following:
i. Detailed design and engineering of all the equipment and equipment system(s).
ii. Complete manufacture including shop testing/ type testing.
iii. Providing engineering data, drawings, Commissioning procedures and O & M
manuals, etc. for the Owner/RITESs
Owner
s review, approval and records.
iv. Packing and transportation from the manufacturers works to site.
v. Receipt, unloading, storage, preservation and conservation of equipment at
site.
tion, pre-assembly,
pre assembly, (if any), erection, testing and satisfactory operation
vi. Fabrication,
of all the equipment including successful completion of facilities.
vii. All associated civil, structural,electrical
structural
and C&I works.
viii. Commissioning and completion of facilities and Performance Guarantee Tests.
ix. Furnishing of mandatory spares and handing over to NALCO stores.
x. Supply of commissioning spares
xi. Reconciliation (if any) with custom authorities.
authorities
xii. Satisfactory conclusion of the contract.
(b.) The equipment and services to be furnished and installed as required in this Technical
Specification shall also meet all the requirements as stated in other sections of bid
documents which shall be considered as a part of this technical specification as bound
herewith.
(c.) The Contractor
or shall be responsible for providing all materials, equipment and services,
specified or otherwise (unless specifically excluded) which are required to fulfill the
intent of ensuring operability and the reliability of the complete system covered under
this specification.
(d.) It is not the intent to specify completely herein, all aspects of design and construction of
equipment. Nevertheless, the equipment shall conform in all respects to high standards
of engineering, design and workmanship and shall be capable of performing in
continuous commercial operation.
(e.) Whenever a material or article is specified or described by the name of a particular brand,
manufacturer or trade mark, the specific item shall be understood as establishing type,
function and
d quality desired. Other manufacturers products may also be considered
Technical Specification Sec-2,:Intent
:Intent of Specifications
Page 1 of 17
Page 2 of 17
Page 3 of 17
Equipment and services covered under WAGON TIPPLER AND CONVEYOR SYSTEM PACKAGE
are described in the subsequent sections:
1.2
1.3
TENDER DRAWINGS
1.3.1
The drawings listed elsewhere, form part of the specification and shall supplement the
requirements specified herein. The scope and terminal points for the equipment to be
furnished under this package shall be as identified in these drawings and read in conjunction
co
with the text of these specifications. These drawings are preliminary drawings for bidding
purpose only and subject to changes that may be necessary during the detailed engineering.
In case of any conflicts / contradiction among various volumes
volumes / sections / annexures /
chapters / appendices / tender drawings of bid documents, the same shall be referred to the
Owner for clarifications whose decision shall be final and binding. No extra claims shall be
allowed on this account.
1.3.2
2.0
IPTION OF PROJECT
BRIEF DESCRIPTION
NALCO intends to augment the coal handling facilities at its Captive Power Plant by an
additional annual volume of 2.0 Million tonnes.
For this purpose, it intends to install a wagon tippler and connecting conveyor System to
receive the above quantum of coal through rail mode. The wagon tippler system shall be
suitable for handling all prevailing wagons in coal circuits such as BOX / BOX-N
BOX / BOXNHA /
BOX N.MKDII.
The facility provided shall be suitable to accommodate locomotives of maximum
maxi
140 T
weight passing through the platform at a maximum speed of 8kmph.
The Wagon Tippler System shall have an in built weighing mechanism (load cell type) below
the platform for weighment of wagons prior to and after each tippling cycle to record the
exact quantity of coal unloaded from each wagon.
Coal received at the tippler hopper would be transported by belt conveyors and integrated
to existing system for feeding the existing and the new stockpiles under development.
2.1
Page 4 of 17
WagonTippler(WT-1)
1) is to be utilised for unloading of IR coal rake. A Side arm charger is
envisaged for placement of loaded wagon on the tippler table & retrieval of empty wagon
from the tippler table after tippling. Clear access shall be provided for movement of pay
loaders on the hopper side of Wagon tippler. Wagon tippler hopper grating is to be
positioned and designed
d accordingly.
(ii) Apron feeder is proposed under the Wagon tippler for extracting coal from the Wagon
tippler hopper and feed into the apron feeder which in turn discharges crushed coal on to
the proposed receiving conveyor RC-1.
RC Conveyor RC-1 will transfer
sfer the coal to conveyor RC-2
RC
at the new transfer tower TP-1.
TP Conveyor RC-2
2 shall feed coal on to existing Conveyor BCBC
103/BC-115
115 at the existing junction house (JH-1).
(JH 1). The rated capacity of all the conveyors in
this package shall be 1200 TPH.
(iii) The existing CHP control and monitoring system is PLC based. It is proposed to provide
an independent PLC based control for smooth, efficient & trouble free operations of Wagon
Tippler and conveyor system package. The control and monitoring system for belt conveyors
con
covered under this Package shall be integrated with the existing control system such that the
operation of existing CHP is not hampered. Necessary interlocks and software changes in the
existing PLC logic are also envisaged in this package.
3.0
SCOPE OF WORK
3.1.1
The scope of Wagon Tippler and Conveyor System Package to be furnished, erected and
commissioned under this specification shall be as detailed hereinafter. The Contractor shall
be fully responsible for system and detailed design, engineering,
engineering, manufacture, shop
fabrication, assembly, testing and inspection at manufacturers works, packing, dispatch,
transportation, transit insurance, custom clearance etc. as applicable, delivery to site,
unloading, handling and storage at site, insurance during
during storage, construction, erection,
including erection supervision, testing, inspection, commissioning and handing over to
Owner and Guarantee testing including all associated electrical, civil & structural works as
specified, unless specifically excluded
exclude as per Section-Terminal
Terminal Points & Exclusions.
3.1.2
The scope of the contractor shall be deemed to include all such items which although are
not specifically mentioned in the bid documents and/or in Contractors proposal but are
needed to make the system complete in all respects for its safe, reliable, efficient and
trouble free operation and the same shall be furnished and erected unless otherwise
specifically excluded in this document. The general description of the proposed system and
the broad scope off work under the specification shall include but not be limited to as
detailed below.
3.1.3
An underground RCC Wagon Tippler Hopper, machinery hatches with wagon tippler hopper,
associated underground tunnel, transfer point and pent house complete with civil,
ci structural
and electrical works for Wagon Tippler hopper and machinery hatches, steel grating over
hopper portion, removable chequered plate covers over openings in machinery hatches for
handling underground equipment, equipment handling facilities for
for apron feederinside
feeder
Page 5 of 17
below wagon tippler hopper including the structural steel shed with E.O.T crane over the
WT-1
1 and other equipment/systems such as Dust Suppression system, ventilation system,
drainage system etc. as specified elsewhere in the specification.
specification. However, the track work is
excluded from Contractors scope however rails over tippler table and the track for Side Arm
Charger are included in Contractors scope.
3.1.4
3.1.5
Side arm charger associated with the Wagon Tippler complete with travel rails, drive
equipment along with necessary controls, associated electricals, civil/structural works &
accessories.
3.1.6
One (1) no. Apron feeder complete with drives, all mechanical, electrical accessories &
supportingg structure etc.
3.1.7
3.1.8
3.1.9
3.1.10 Complete chute work along with chute plug switches and actuator operated flap gates in all
Transfer points,
nts, maintenance platforms along with suitable approach.
3.1.11 Adequate number of ventilation equipment for ventilating the wagon tippler hopper,
underground conv. RC-1
1 upto Pent House, complete with all mechanical, electrical, civil and
structural works.
3.1.12 Pressurised Ventilation system for all Switchgear rooms, MCC rooms complete with all
mechanical, electrical, accessories, civil and structural works.
Page 6 of 17
Page 7 of 17
3.1.24 First fill of all consumables e.g.; oils and lubricants for one year toppings requirements.
r
3.1.25 Preservative shop coating, final painting of all structures and equipment under the scope.
unction houses, Wagon
3.1.26 (a) Adequate fire alarm & detection of coal conveyor gallery area, Junction
tippler area, Electrical switch gear rooms, Control
Control rooms, Battery rooms, Transformer
rooms, cable spreader rooms etc. consisting of heat detectors(both
detectors(both ceiling mounted &
Canopy mounted type), smoke detectors, LHS cables, manual call points, fire alarm panels at
main control room of Wagon Tippler, repeater
repeater panel at CISF Fire control room near CPP
main gate etc shall be considered. Fire alarm & detection
de ction system shall be of Intelligent
Addressable type of Notifire/Siemens make.
(b)
b) The successful bidder is to obtain necessary approval from TAC for the complete Fire
protection System of Wagon Tippler Package.
(c)
c) Underground pipes will be M.S heavy duty with coating wrapping by 4mm thick coal tat
tape conforming to IS15337 (latest version). Over ground pipes shall be of heavy
he
duty GI
pipes with fittings etc. Suitable number of water actuated deluge valves shall be provided
for the hydrant system. Hydrant line will be tapped suitably from the existing hydrant net
work.
d) The coal conveyors shall also be provided with MVW (Medium Velocity Water) Spray
(d)
System which
h will be operating automatically for protection of conveyors.
3.2
3.2.1
Unless specifically excluded, contractors scope of work shall include all electrical works
wor as
required for putting into successful operation of the Wagon Tipplers & Associated Conveyors
covered under this specification.
3.2.2
LT SWITCHGEAR
415V Switchgear/motor control centers distribution boards, AC & DC fuse boards, local
emergency stop push button stations for all drives and local motor starters as required for
plant and equipment.
3.2.3
MOTORS
Motors along with couplings and coupling guards for all rotating auxiliaries are covered
under this package. All motors shall be with cable glands & lugs.
3.2.4
CABLES
HT & LT Power cables, control cables, Instrumentation cables and any special cables required
for connection between equipment / devices in Contractors scope and also cables between
Owners equipment and Contractor's equipment.
3.2.5
Page 8 of 17
(a) All cabling with cable accessories, cable trays with supporting structure, terminations and
jointing kits, trenches, overhead trestle, duct banks etc. as required for the cables to be
supplied by the Contractor.
(b) Grounding and lightning protection for the plant and equipment under Contractors
scope along with its interconnection to the nearest Owners earth grid at two points.
3.2.6
ILLUMINATION SYSTEM
Complete illumination system as required for complete internal and external lighting of
associated plant, equipment and buildings covered under Contractors scope including 2
Nos. of Lighting Masts for area lighting in W.T. area.
3.2.7
CONTROL SYSTEM
An independent Control desk, PLC panels, I/O
I/O racks, UPS, battery & battery chargers etc. for
the control of Wagon Tipplers and other equipment.
One (1) No. control building to be located near WT-1
WT 1 . This building shall have two floors i.e.
ground & first floors. The first floor of control room shall house PLC panels, control desks for
operation of WT-1.
1. One office room (5m x 5m) at the first floor. There shall be a projected
viewing balcony at a suitable location to have clear view of the Wagon Tipplers
Tipp
during
operation. The ground floor shall house the MCC, DBS, Battery DBS etc.
3.3
CIVIL WORKS
3.3.1
The work to be performed under this specification consists of providing all labor, materials,
construction equipment, tools and plant, scaffolding, supplies, transportation, all incidental
items not shown or specified, but reasonably implied or necessary for successful completion
of the work including Contractors supervision and in strict accordance with the drawings
and specifications. The nature of work shall generally involve earthwork in excavation
including very deep underground excavation, de-watering,
de watering, shoring and strutting, sheet
piling, back filling around completed structures and plinth protection, area paving, disposal
of surplus excavated materials,
aterials, piling, concreting including reinforcement and form work,
brick work, fabrication and erection of structural / miscellaneous steel works, inserts,
architectural items & finishes such as plastering, painting, flooring, doors, windows &
ventilators,, glass and glazing, rolling shutters etc., permanently colour coated profiled steel
sheeting,, Aluminum industrial troughed sheets,
sheets anchor bolts, R. C. C. trenches with covers,
drainage, damp proofing, water proofing and other ancillary items. Supply of cement,
reinforcement steel, structural steel sections ,MS rounds, chequered plates, flats etc will be
within the scope of the bidder.
bidder
3.3.2
The work shall have to be carried out both below and above ground level and shall be
involving, basements, equipment
equipment foundations, grounding, slabs, beams, columns, footings,
rafts, walls, steel frames, brick walls, stairs, trenches, pits, access roads, culverts, conveyer
Page 9 of 17
galleries, trestles, penthouses, Wagon tippler hopper, underground tunnels, transfer points,
finishes,
hes, complete architectural aspects, drainage and all other civil, architectural and
structural works associated with the complete Wagon Tippler and conveyor system
Package.
3.3.3
Scope of work shall also include dismantling and modifications of the existing
exi
structures/facilities, which may be required to facilitate, inter connection between the
existing and the new structures or facilities and making good the dismantled/modified
structures.
4.0
TERMINAL POINTS
Terminal point for Wagon Tippler and conveyor system commences from wagon tippler
complex upto feeding points at conveyors BC-103
BC
& BC-115,
115, in Junction House (JH-1)
(JH
including the modification necessary to the Junction Houseand
and interconnection with the
existing system. Within these terminal points, all equipment and services, civil, structural
and architectural works, electrical distribution, piping network etc. as required for wagon
tippler and conveyor system package will be furnished and erected by the contractor
co
unless
specifically excluded.
4.1
Contractor's Scope responsibilities shall include but not be limited to the following:
4.1.1
Wherever Contractor is permitted by Owner to take support from any of the Owners
Structures, the Contractor shall ensure that no damage is done, to the Owners Structures
including Painting thereof. In case of any damage to the Owners Structure and/or Painting,
then the Contractor shall rectify the same to the complete satisfaction of the Owner.
4.1.2
4.1.3
4.1.4
Water supply connections for dust suppression, service water system & cooling water shall
be provided by the Owner, details of which are given elsewhere in the specification. Further
network of piping including all compressors, pumps, tanks, necessary
necessary accessories, supports
and fittings etc. for distribution of water for dust suppression and service water system in all
transfer points, control rooms, MCC rooms, toilets, Machinery hatches of the Wagon tippler
etc. shall be under the scope of the contractor.
contra
4.1.5
Road lighting in wagon tippler area, for the roads, is included in the scope of Contractor.
4.2
EXCLUSIONS
Page 10 of 17
4.2.1
Supply, laying and fixing of rail track for the inhaul and out haul siding is excluded from
fr
the
scope of this Contract. However, supply, laying and fixing of rail over Wagon Tippler table
and for side arm charger is included in the scope of this Contract.The
Contract.The approaches of wagon
tippler where track is to be laid on concrete base( to the extent required)
equired) and aligning with
the inhaul/outhaul
haul/outhaul track junctions is also included in the scope of this contract the cost of
which is deemed to be included in the quoted rate of relevant items.
items
5.0
5.1
The rated capacity of the Conveyors shall be 1200 TPH.. The design capacity of the conveyors
shall be 1320 TPH.. The mechanical and structural / civil system shall be designed for 1320
TPH capacity and round the clock operation with both the streams operating
operatin simultaneously.
5.2
5.3
For the purpose of volumetric computation, the bulk density of the coal shall be taken as
a
800 kg/m3. Therefore for calculation of belt conveyor capacity, for their drives & drive
motors kW requirement, and sizing (volume calculations) of chute, hoppers etc. the above
bulk density shall be considered. For all other purposes viz. for stresses/ load on structures,
loading on Apron Feeder tables, sizing of actuators for flap gates, calculations of plugged
chute/ hopper loads etc. the bulk density of the coal shall be taken as 1100 kg/ m3.
5.4
5.4.1
For the purpose of conducting guarantee test coal, the following flow path would be
assessed.
Page 11 of 17
Contractor shall also demonstrate that all intermediate equipments can perform as per
specification and design requirement during PG Test.
5.4.3
Performance and Guarantee tests have been elaborated elsewhere in the specification.
6.0
ENGINEERING
NG SCHEDULES
6.1
Within one month of acceptance of Award Letter, Contractor shall submit, for review and
approval, detailed engineering schedules, based on Master Network (as per requirement of
bid documents), to the Owner / Consultant, showing the logic & duration of activities in the
following areas :
a) Detailed engineering, including submission and approval of quality plans and PG test
procedure.
b) Inputs required from Owner for smooth and timely execution of contract.
6.2
The Contractor shall submit within 30 days of letter of award a master list of drawings
incorporating the scheduled dates of submissions. The schedule date of submissions should
match with the manufacturing and erection programme submitted in the detailed Master
Network Schedule. The list shall be updated every month reflecting the additions / deletions
during the period.
6.3
The network schedule shall be updated at a frequency mutually agreed upon for the
purposes of progress monitoring. However, for the purpose of identification of Contractor's
Contractual Liability the agreed Master Network shall only be applicable.
7.0
7.1
Guarantee
The Bidder shall guarantee that equipment offered shall meet the rating, performance and
functional requirement stipulated
stipulated for various equipment covered in this specification. The
Bidder shall also furnish a declaration in the manner prescribed and included in the Bid
Proposal Sheets and other Schedules for certain guaranteed parameters which shall attract
levy of liquidated
uidated damages for shortfall in performance.
7.2
Performance Requirement
Guaranteed parameters of the major equipments shall be as follows:
7.2.1
Page 12 of 17
7.2.2
Equipment Capacity
Capacity of individual equipment shall be tested separately:
(i) Each Wagon Tippler : 20 tips/hour (Guaranteed)
(ii) Each Apron feeder : 1200 TPH (Guaranteed)
7.2.3
Contractor shall also demonstrate that all intermediate equipments viz. Gates, Dust
suppression, Ventilation System etc. can perform as per specification and design
requirement.
7.2.4
Performance and guarantee requirement of various other equipments have been elaborated
elsewhere.
8.0
8.1
8.2
Equipment
Wagon Tippler
Guaranteed
parameter
20 Tips /Hour
Apron Feeder
1200TPH
1200TPH
Short fall
By One tip per hour
By two tips per Hour
Beyond two tips per hour
By 0.5%
By 1.0%
Beyond 1.0%
By 0.5%
By 1.0%
Beyond 1.0%
LD amount to be
imposed
1% of order value
2% of order value
Rejected
1% of order value
1.5 of order value
1.5%
Rejected
1% of order value
15 of order value
15%
Rejected
Page 13 of 17
The LD shall be assessed on the basis of conveyor equipment having the poorest
performance.
9.0
10.0
10.1
All equipment / systems to be supplied shall conform to type tests as per relevant
re
standards
and proven type.
10.2
The Bidder / Contractor shall furnish the reports of all the type tests carried out within five
years of the date of bid opening as per specification and relevant standards for all
components / equipments / systems. These reports should be for the tests conducted on
identical / similar components / equipments / systems to those offered / proposed to be
supplied under this contract.
10.3
In case contractor is not able to submit report of type test(s) conducted in last five years, or
in case type test report(s) are not found to be meeting the specification / relevant standard
requirements, then all such tests shall be conducted under this contract by the Contractor
free of cost to Owner, and reports shall be submitted for
f approval.
10.4
All acceptance and routine tests as per relevant standard and specification shall be carried
out. Charges for these shall be deemed to be included in the bid price.
11.0
11.1
SPARES
GENERAL
The Contractor shall include in his scope of supply all the necessary Mandatory spares, start
up and commissioning spares and recommended spares and indicates these in the relevant
schedules of the Bid Form and Price Schedules. The general requirements pertaining to the
supply of these spares have been
b
described in the following paras.
11.2
MANDATORY SPARES
Page 14 of 17
RECOMMENDED SPARES
12.1
In addition to the spare parts mentioned above, the contractor shall also provide a list of
recommended spares for 1 year of normal operation of the plant and indicate the list and
total prices in relevant schedule of the Bid Form and Price Schedules. This list shall take into
consideration the mandatory spares specified in this Volume, and should be independent of
the list of the mandatory spares. The Owner reserves the right to buy any or all of the
recommended spares. The recommended spares shall be delivered at project site at least
two months before the scheduled date of initial operation. However, the spares shall not be
dispatched before the dispatch of the main equipment.
12.2
Price of recommended spares will not be used for evaluation of the bids. The price of these
spares will remain valid upto 6 months after placement of Notification of Award for the main
equipment during which the Contractor shall provide necessary justification for the quoted
prices for these spares. However, if the Contractor fails to provide the aforesaid justification
of the quoted prices, the prices of recommended spare shall remain valid for 2 months from
the last date of providing such justification to the satisfaction
satisfaction of the Owner.
Page 15 of 17
13.0
START-UP
UP & COMMISSIONING SPARES
up and commissioning spares are those spares which may be required during the startstart
Start-up
up and commissioning of the equipment/system. All spares used till the plant is handed over
to the Owner shall come under this category. The Contractor shall provide for an adequate
stock of such start up and commissioning spares to be brought by him to the site for the
plant erection and commissioning. They must be available at site before the equipments are
energized. The unused spares, if any, should be removed from there only after the issue of
Taking Over certificate. All start up spares which remain unused at the time shall remain the
property of the Purchaser.
Purchase
14.0
14.1
COMMON REQUIREMENTS
The Contractor shall include in his scope of supply all the necessary Mandatory
Man
spares, start
up and commissioning spares and recommended spares and indicate these in the relevant
schedules of the Bid Form and Price Schedules. The general requirements pertaining to the
supply of these spares is given below.
14.2
The Contractor shall indicate the service expectancy period for the spares parts (both
mandatory and recommended) under normal operating conditions before replacement is
necessary.
14.3
All spares supplied under this contract shall be strictly inter changeable with the parts for
which they are intended for replacements. The spares shall be treated and packed for long
storage under the climatic conditions prevailing at the site e.g. small items shall be packed in
sealed transparent plastic with desecrator packs as necessary.
necess
14.4
All the spares (both recommended and mandatory) shall be manufactured along with the
main equipment components as a continuous operation as per same specification and
quality plan.
14.5
14.6
Each spare part shall be clearly marked or labeled on the outside of the packing with its
description. When more than one spares part is packed in a single case, a general
description of the content shall be shown on the outside of such case and a detailed list
enclosed. All cases, containers and other packages must be suitably marked and numbered
for the purposes
urposes of identification.
14.7
All cases, containers or other packages are to be opened for such examination as may be
considered necessary by the Owner.
14.8
The contractor will provide the Owner with all the addresses and particulars of his sub
suppliers
ers while placing the order on vendors for items/components/equipments covered
Page 16 of 17
under the contract and will further ensure with his vendors that the Owner, if so desires, will
have the right to place order for spares directly on them on mutually agreed terms
term based on
offers of such Contractors.
14.9
The Contractor shall warrant that all spares supplied will be new and in accordance with the
contract Documents and will be free from defects in design, material and workmanship.
Page 17 of 17
SECTION 3
(SPECIAL STIPULATIONS TO BIDDERS)
1.1.
GENERAL
1.1.1
This Technical Specification shall be read in conjunction with Commercial, General Condition
of Contract and other project requirement mentioned in this specification.
1.1.2
The Bidder shall quote for complete scope of work as covered in this specification.
1.1.3
This Technical Specification is for turnkey supply of the plant & equipment and related
structures including execution of structural steel works and civil works as specified in
subsequent chapters, along with necessary modification, as detailed in the Scope of Work
and Technical Specification.
1.1.4
1.1.5
The Bidder shall submit the drawings / documents, technical data / information as
mentioned in various sections and annexure without which the Bid shall be considered as
incomplete and may not be considered further.
1.1.6
The Bidder shall submit along with the bid a work schedule in the form of a bar chart
indicating the commencement and completion dates of each activity
activity such as preparation of
design, approval of design & drawings, preparation & approval of fabrication drawings,
procurement of steel and other material, ordering of bought out items, their delivery to
shop, major shop activities like fabrication of structures/
structures/ manufacture of equipment,
assembly, shop testing, inspection, shop painting &dispatch
&
to the site, schedule of erection,
final painting after erection at site, testing and commissioning of Plant and Equipment,
without which the bid may not be considered.
consi
1.1.7
The Bidder shall clearly indicate the clause wise compliance to the specification. Non
compliance with this and generalized statements like. "The equipment shall be
manufactured as per IS standard / our specification etc" may result in rejection
reje
of the Bid.
The deviation, if any, shall be clearly specified clause-wise
clause wise in the format enclosed with this
technical specification. In absence of deviation indicated, it will be presumed that the Bidder
has no deviations.
1.1.8
Page 1 of 11
1.1.9
If the Bidder feels that any information/ data described in the technical specification needs
to be modified, he shall indicate the same specifically and submit an alternative proposal, on
the basis of the design data, that he considers suitable and capable of meeting the
requirement of this specification.
Page 2 of 11
1.1.16 The offer shall be complete in all respects and any additional equipment, accessories,
auxiliaries, services, work etc. which are not specifically mentioned in the specification but
are required for smooth and trouble free operation and to achieve performance required to
be guaranteed in terms of the Bid Document, shall be included by the Bidder in the offer.
1.1.17 The make of all bought out items shall be as per List of preferred makes of supplies and
equipment mentioned in tender document.
1.1.18 Metric systems & English language shall only be used throughout the Bid and in the
drawings.
1.1.19 The Bidder shall satisfy himself about his ability for completing the work as per the time
schedule before submitting his offer. In case the Bidder is unable to adhere to the schedule
indicated in this specification, the Bidder need not submit their offer against this Bid.
Bid
1.1.20 A complete list of exclusions from Bidder's scope of work shall be clearly indicated in the Bid.
1.1.21 In case of any contradiction between Instructions to Bidder and Technical Specifications,
stipulation in the Technical Specification shall prevail.
1.1.22 The Bidder has to carry out the work is such a manner that it does not affect the plant
operations. If other Contractors are also engaged at the same work site for other jobs, the
Bidder shall work in co-ordination
ordination with them such that the
the work of other Contractor is not
affected. For integration of new facilities & the existing one, shutdowns period in phases, as
per the schedule mutually agreed between Purchaser and successful Bidder would be
provided. Hence, Bidder shall indicate in their offer, the stages at which the shut downs are
required and their respective duration.
1.1.23 All parts of equipment requiring replacement or inspection or lubrication shall be so
arranged/ assembled that they are easily accessible without the need of dismantling of other
equipment or structures. All electrical cables shall be so laid that they are not liable to be
damaged and can be easily inspected and maintained and when necessary any damaged
cable can be accessed & replaced individually.
1.1.24 All equipment shall be complete with adequate safety devices wherever a potential hazard
to personnel exists. Provision for safe access of personnel working to and around equipment
for operation and maintenance, shall be provided.
1.1.25 The Bidder shall train the Purchasers personnel in all disciplines of the operation &
maintenance of the plant & equipment being provided by them under the contract.
maximu possible
1.1.26 Standardization of components and assemblies shall be carried out to the maximum
extent to ensure interchangeability/as well as to minimize inventory levels.
Page 3 of 11
1.1.27 Bidders shall furnish drive ratings of all equipments including conveyors along with the offer.
Conveyor profiles enclosed with this specification are indicative
indicat only.
1.1.28 The Bidder shall include in his scope of supply, a complete set of new and unused special
tools and tackles required for operation and maintenance of the plant and equipment. The
list of tools & tackles considered in the bid shall also be submitted.
1.1.29 The Bidder shall include in his scope, the requirement of initial fill of oils, lubricants, grease,
and all other consumables required for startstart up, testing, commissioning and performance
guarantee
uarantee tests of the unit/equipment. A list of such consumables shall also be furnished by
the successful Bidder for Purchasers use.
1.1.30 The Bidder shall include in his scope the supply of spares required for successful
commissioning of plant & equipment.
equipment. The list of commissioning spares considered in the bid
shall also be furnished along with the bid.
1.1.31 The Bidder shall quote separately for the spares required for the normal operation and
maintenance of the plant and equipment for a period of 24 months to be reckoned from the
date of taking over of the plant and equipment. A list of the spare parts shall also be
furnished along with item wise price.
subcont
1.1.32 The successful Bidder shall not offload the contract or part thereof to any subcontractor
without written permission of the purchaser. In the event of subletting of any part of the
work with due permission by the purchaser, the fact that such permission has been
accorded shall not absolve the successful Bidder from any of his obligations and liabilities
under the contract.
1.1.33 Subject to availability and at the request of the successful Bidder, water for construction
purpose will be made available by the Purchaser at one mutually agreed point at site. The
successful Bidder shall make
make his own arrangement for any further distribution at his own
cost. Water supply shall be free of cost and shall be provided as specified under clause no.
54.13 b) of the GCC.
1.1.34 Power Supply
Subject to availability and at the request of the successful
successful Bidder, Electric Power will be
made available at one point only at a distance not more than 500 meters away from the
Contractors premises. The power will be supplied at 400/440 Volt and shall be metered and
charged at the rate as specified in the GCC.
GCC. The successful Bidder should have sufficient
number & capacity of DG sets to meet the emergency power requirements in the event of
failure in power supply.
1.1.35 Civil and structural steel works
Page 4 of 11
1.2
ERECTION
1.2.1
The successfull Bidder shall be responsible and perform the following with respect to the
erection of the Plant and supplies.
1.2.2
The scope of work of the successful Bidder shall be complete erection of the Plant and
Equipment etc. as specified in the Technical Specification.
Specification. The Bidder shall make all
arrangements to deliver the equipment at their site stores by wagons / truck / trailers, build
his own stores (covered, uncovered and air-conditioned,
air conditioned, if necessary) for the proper storage
of equipment, maintain the stores
stores and all related documents and records, transport the
equipment to site for erection purpose and take an ErectionErection cum- Storage insurance policy
covering all the risks including third party liability for all supplies as well as human life. All
security arrangements also shall be made by the successful Bidder. Space only for stores and
site office shall be made available to the Bidder by the Purchaser.
1.2.3
The successful Bidder shall take the equipment from their site stores and transport the same
to erection site.
1.2.4
The successful Bidder shall unpack and do visual checking against physical damages to the
equipment / cases, cleaning of equipment before start of erection. Damage / shortage if any,
will be reported to the Purchaser / consultant and shall be rectified / replaced expeditiously,
free of charge to Purchaser so as not to upset the erection and commissioning schedule.
Delay on account of settlement of insurance claims by the successful Bidder shall not be
considered an excuse for delay in completion.
The successful Bidder shall lay and maintain properly all the temporary supply lines in the
erection site for temporary power and water required for storage and erection purposes
from a single point to be provided by the Purchaser. Drinking water shall also be made
available at one central point at site. The successful Bidder shall make his own arrangement
for any further distribution.
1.2.5
1.2.6
Page 5 of 11
The successful Bidder shall provide all temporary ladders, scaffolding materials, platforms,
supports and other necessary facilities required for handling, erection, testing and visual
inspection of supplies at the point
point of installation and shall also provide necessary packing
plates, wedges, shims, levelling screws etc. required for erection of equipment and
technological structures.
1.2.8
The successful Bidder shall provide erection consumables like oxygen and acetylene gas,
welding rods, solder lugs, oil, grease, kerosene, cotton waste, etc. required for erection of
equipment and technological structures.
1.2.9
Page 6 of 11
1.2.15 Installation
stallation and connection of all piping and fittings within the scope of work shall be
responsibility of the successful Bidder.
1.2.16 The successful Bidder shall be responsible for checking the correctness of erection of
mechanical equipment, technological
technological structures and auxiliary systems, electrical equipment
etc. as per the specification.
1.2.17 The successful bidder has to carry out the work in such a manner that it does not affect the
operation of other plant/ shop. If other Contractors are also engaged
engaged in the same work site
for other jobs the bidder shall work with them in a co-ordinated
co ordinated manner.
1.2.18 The successful Bidder shall be responsible for the management of erection work with proper
and adequate supervision for ensuring progress of erection
erection work and quality of
workmanship.
1.2.19 The successful Bidder shall deploy required number of supervisory, skilled, unskilled and
auxiliary labour as required for the erection work: as per detail mobilisation schedule (to be
furnished with Bid by successful Bidder) and comply with such reasonable
reasonabl instructions of the
Purchaser / Consultant in the interest of satisfactory progress and completion of the work
according to the schedule. The successful Bidder shall work in 3 shifts per day basis for
meeting the completion target, if required within the contract price.
1.2.20 The successful Bidder shall organise the work in a manner that other work at site is not
impeded and the workmen therein not endangered and shall arrange temporary access at
site, if required for the erection work.
essful Bidder shall return to the Purchaser all crates, packing cases and packing
1.2.21 Successful
materials excess commissioning spares, oil and lubricants at a place designated by the
Purchaser.
during erection.
1.2.22 The successful Bidder shall conduct all necessary tests / checks during
1.2.23 The successful Bidder shall attend to the rectification of erection defects, if any,
expeditiously. The successful Bidder shall arrange all testing instruments for such testing at
site.
1.2.24 The successful Bidder shall carry out final painting of the Plant & Equipment and
technological Structures etc. erected as per the instructions stipulated in the Technical
Specification.
1.2.25 The successful Bidder shall be responsible for total commissioning of the Plant and
equipment including cold trial run and demonstration of Performance Guarantee Test. The
Purchaser's supervisory and skilled operating personnel shall, however, be available to work
under the guidance and supervision of the Bidder. Necessary raw materials, auxiliaries,
auxiliari
Page 7 of 11
utilities, electricity and operating personnel shall be made available by the Purchaser
covering 3 shifts operation as per the programme agreed to in advance.
reliabl and
1.2.26 The Successful Bidder shall supervise running of the Plant for satisfactory, reliable
regular operation and performance after its successful commissioning for establishing
performance guarantees.
1.2.27 Electrical energy and construction water shall be supplied by Purchaser to the successful
Bidder during erection, at one point.
1.2.28 All safety measures required to be adopted as per the Statutory Regulations & the Safety
Rules of the Plant shall be strictly followed by the successful Bidder during the execution of
the Contract. The successful Bidder shall depute safety engineers
engineers for strictly compliance of
safety rules & regulations.
1.2.29 The successful Bidder shall intimate the Plant authorities in writing well in advance about
the requirement of shut down of any of the existing units / facilities for inter connection /
incorporation
orporation of additional facilities. The shut down period shall be mutually discussed and
finalised. The work to be undertaken during the shutdown period shall be planned
meticulously to reduce the shut down period to the minimum.
1.2.30 The successful Bidder shall comply with all statutory Rules, Regulations with respect to the
employment of labour at site.
1.2.31 The successful Bidder shall carry out any and all such works, as may be required, to build a
Plant complete in all respect as per the Technical Specification and achieve the Performance
Guarantees and other parameters as given in the subsequent chapter of this specification.
1.2.32 Any loss of plant and equipment due to imprudence, negligence and / or inequitable
treatment and handling shall be replaced by the Successful Bidder / his sub-contractor
sub
at his
own cost.
1.3
PAINTING
All parts of the equipment
ipment shall be thoroughly cleaned of loose mill scales, rust or foreign
matters.
All parts excepting motors, resistors, gears etc. shall be painted at shop and at site with two
coats of epoxy zinc based on zinc dust.
Interior of all gear housing shall be painted with oil resistant paint. All machine pads,
bearings surface or structures or housing shall be painted with white lead. All parts,
inaccessible after assembly, shall be painted and assembled while the paint is wet.
Page 8 of 11
After erection, the damaged portion of the painted surface shall be retouched and an
intermediate coat / final coat of PVC copolymer alkyd resin with micaceaus iron oxide (MIO)
shall be applied. The colour shall be as per the choice of the Purchaser.
The subsequent one final coat of paint of PVC copolymer alkyd with weather resistant
pigment (approved by the Purchaser) and glossy finish shall be applied.
The details of the dry film thickness (DFT) of the different coats shall be as follows:
a)
b)
c)
Primary coat
Intermediate coat
Final coat
:
:
:
The painting scheme & colour code shall be approved by the Purchaser. The successful
Bidder shall refer to Section 8 for further detail off painting scheme & colour codes.
1.4
1.5
PRELIMINARY ACCEPTANCE
1.6
After completing the erection of a unit or agreed portion thereof, the successful Bidder shall
give a notice in writing stating that the job is complete in all respects and ready for
preliminary acceptance. The job shall be visually inspected by representatives
representa
of the
Successful Bidder and Purchaser / Consultant to ascertain whether supply, fabrication and
erection are as per contract drawings and Technical Specification. All observed defects,
deficiencies and omissions shall be noted down. If the defects, deficiencies and omissions
are not major in the opinion of the Purchaser / Consultant, the successful Bidder shall be
issued a preliminary acceptance certificate mentioning the defects, deficiencies and
omissions. The noted defects, deficiencies and omissions
omissions shall be made good by the
successful Bidder within a period of 3 to 4 weeks.
FINAL ACCEPTANCE
Before commencement of final acceptance test of the building or unit, the successful Bidder
shall make available required numbers of complete sets of ordinary prints of drawings,
required numbers of set of DOD list for the drawings and one set of reproducible film of all
Page 9 of 11
SCOPE OF WORK
1.7.1
Design, manufacture, inspection, shop & primary coat of paint & supply of complete
plant & equipment, fabrication (shop & site) of building structures & technological
structures, civil construction materials, power distribution, electrics, instrumentation &
automation, illumination, all utilities & services, in-plant
in plant road networks, drainage
systems, landscaping, fire detection & alarm system, fire fighting pump house, as
required, for complete
mplete & trouble free operation of Coal Handling System in an
integrated manner.
Applying final finish coat of paint as per approved procedure & shades before handing
over, first fill of lubricant & oil, special tools & tackles, mobile equipment, handling &
hoisting equipmentt etc.
Page 10 of 11
Arrangement of all erection equipment viz. cranes, hoists, winches, etc, and safety
appliances as required for erection of plant & equipment. Appointment of safety officer
by the contractor shall be included.
1.7.2
Page 11 of 11
SECTION 4
1.0
1.1
2.0
PARAMETERS
2. 1
Conveyor System
i. Rated Capacity (Guaranteed) : 1200 TPH
ii. Design capacity : 1320 TPH
iii. Belt width : 1200 MM
iv. Belt speed : 3.5 m/sec. (approx.)
2.1.1
Wagon Tipplers
(a) No. required: 1 (One)
(b) Guaranteed tips per hour per tippler: 20
2.1.3
2.1.4
Apron Feeder
(a) No. required : One (1)
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 1 of 64
2.1.5
2.1.7
2.1.8
2.1.9
Ventilation System
A Mechanical Ventilation System
For Underground Areas a Minimum of 15 supply air changes and minimum 7 exhaust
air changes per hour.
For other Areas a Minimum of 10 supply air changes per hour.
B. Pressurized Ventilation System:
System: Minimum 15 supply air changes per hour
C. Air Conditioning System :
Adequate number of air changes to Maintain
Maintain uniform temp. & humidity.
2.1.10 Chutes
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 2 of 64
Minimum clear cross section of chute shall be 1200 mm x 1000 mm (inside both ways).
2.1.11 Hoists
Suitable hoists as specified elsewhere shall be provided for erection & servicing of all major
equipment. The equipment to be covered shall include (but not limit to) all conveyor drive
units, all pulleys, Apron feeder, sump pumps, various DS/service water/potable water pumps,
gravity take up units, removal of equipment from tunnels, lifting of belt drum at all transfer
tr
houses.
2.1.12 All other equipment under the scope shall be suitable to the system capacities parameters
as specified above.
3.0
3.1
This section is intended to cover design, engineering manufacture, supply, erection, testing
tes
and commissioning of the complete control and instrument panel/desk with annunciation
panel, etc. as specified hereinafter complete in all respects, required for the system.
3.2
General Requirements
The instruments and controls to be furnished and erected
erected under this specification are as
required for safe and satisfactory operation of the plant & equipment under Wagon Tippler
and Conveyor System Package, as outlined under mechanical section and as specified
elsewhere in the specification. For the equipment
equipment and materials procured by the Contractor
from his sub-vendors,
vendors, the Contractor shall study the specification, safety requirements,
interface drawings for such equipment and material in detail and shall coordinate his work
with his subvendors and supply instrumentation and control to ensure suitability of the
system.
3.2.1
Standards / Codes
All construction, installation, workmanship, design & equipment shall conform to acts, rules
& regulations of the jurisdiction within which the project is to be located, and to the current
edition of the following or equivalent standards or codes, in so far as they apply:
American Iron & Steel Institute (AISI)
American Society for Mech. Engineers (ASME)
American Society for Testing & Materials (ASTM)
American Wire Gauge (AWG)
Institute of Electrical & Electronic Engineers (IEEE)
Instrument society of America (ISA)
National Electrical Code (NEC)
National Electrical Manufacturers Association (NEMA)
Bureau of Indian Standards (BIS)
Conveyor Equipment Manufacturers Association
Ass
(CEMA)
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 3 of 64
Guideline for wagon tipplers issued by RDSO G33 (Rev. 1) of May 2010 with latest
amendments if any.
3.2.2
3.3
3.3.1
Construction
Control desks/panels and annunciation system shall be provided as per the requirement of
electrical Section. Annunciations, indications, electrical meters and instrumentation shall be
provided as specified. Ammeters shall be provided on control desk for all
a motors rated 30
kW and above and for all equipment.
3.3.2
Design
The Contractor shall provide a comprehensive control indication and annunciation scheme
for the plant & equipment under wagon tippler and conveyor system package and integrate
the same with the existing control & monitoring scheme of the CHP. Contractor shall furnish
a block diagram and write-up
write up on the scheme proposed. The final scheme will be approved by
the Owner/RITES and the Contractor shall be required to execute the approved scheme.
scheme In
general, interlocking shall be achieved through feed-back
feed back signals from field equipment. A
comprehensive Annunciation and Indication scheme shall be provided such that, it will be
possible for the operator to locate and identify the fault from the display
disp
ace of Control
desk. The scheme shall include the basic remote control instrumentation, indication and
annunciation requirements as per various technical specification requirements. However,
the Contractor may offer any alternative proposal which he considers
considers to be equal, superior
to the scheme as described in subsequent clauses below for achieving reliable and trouble
free operation of the plant, for consideration of the Owner.
4.0
4.1
4.2
The existing coal handling system is being controlled from the following control points. The
existing control
ol philosophy of the coal handling plant is being described below for the
contractor to understand the existing system and suitably plan integration of the controls
and interlocks of the proposed control system of the wagon tippler package with the existing
existin
system.
4.2.1
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 4 of 64
4.2.2
4.2.3
In addition to the remote control of various equipments, local stop push button
butto stations
shall be provided for all equipment.
4.3
SYSTEM OPERATION
4.3.1
Typical Operation philosophy of the plant, in general, as elaborated below is for the
information of the contractor to facilitate development of the control & monitoring scheme
of wagon tippler and conveyor system package and integration with the existing control &
monitoring system of existing CHP.
(a.) Coal flow path selection shall be done from Owners existing control desk to select
conveying paths.
(b.) The coal handling system operator
operator will select any one of the paths from the main control
desk. The flow stream path is then selected by positioning different flap gates at desired
positions. Once the system is in the operation, the gates can not be moved from their
positions and path. Flap gates which do not form
f rm the stream in which coal flow is taking
place, can be operated at any time.
(c.) The Control system will be designed for both Auto & Manual operation of the
conveyors in the selected path. Auto/Manual Selection shall be done from
from Owners existing
control desk.
Auto Mode : In the Auto mode, the conveyors and related equipment will start
sequentially when the System Start is activated. During stopping, when the System Stop
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 5 of 64
Conveyor System
(a) Normally the operation of the apron feeder and the reclaim conveyor shall be controlled
from main control room for evacuating coal from tippler hopper.
(b) The approach of a Railway wagon rake to the plant shall be signaled (visual and audible) in
the wagon tippler Control room as well as to the main coal handling plant control room, as
soon as the rake come within 100 meters distances from the wagon tippler.
(c) Each conveyor shall be protected against damage to the edge of the belt due to excessive
sideways movement by providing adequate number of belt sway switches. In addition, each
conveyor shall be provided with one (1) No. speed detection device (zero speed switch). The
zero speed switches shall be designed to sense belt speed.
failur by providing
(d) All the conveyors shall be protected from roll back due to power failure
mechanical / or electrical locking system.
(e) The starting sequence of the conveyors shall follow a direction opposite to that of flow of
material. The details of Coal flow diagram of the existing stage-I
stage I CHP shall be furnished to
the successful bidder.
(f) Any individual equipment (belt conveyor etc.) should not be allowed to start unless the
equipment immediately following the same in the direction of flow of material is already in
operation.
(g) Pull-cord
cord switches shall be provided along the length of each belt conveyor, which shall
enable the respective conveyor to be stopped immediately. Each pull operated chord switch
and belt sway switch shall be tagged and shall be identifiable in the main control room.
fore
personnel
sonnel working nearby when starting any conveyor.
(h) Siren shall be provided to fore-warn
(i) Interlocking of various conveyors shall be achieved with Flap Gate, limit switches and zero
speed switches.
if provided, is in open condition. This
(j) Motors shall start only when the brake/rail clamp if-provided,
signal
al shall be obtained from limit switch provided for that purpose.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 6 of 64
(k) Once a conveyor trips, flap gate directing coal from this conveyor shall change over its
position with a time delay and shall come back to the original position again, to prevent
jamming of gate.
(l) Where ever scoop type coupling provided for HT motors, the coasting time of respective
conveyor, thruster brake, actuator selection and the chute size shall be so selected such that
there is no spillage of coal from any downstream conveyors.
4.3.3
Interlocking
a) The following conveyors / equipment are considered under interlock scheme ::
(1.) All conveyors
(2.) All gates
(3.) Wagon tippler
(4.) Apron Feeder
b) The following equipment will not come under interlock of the conveyor scheme.
(1.) All dust suppression systems & service water system.
(2.) Ventilation systems
c) All conveyors and equipment have local push button stations each consist of :
(1.) Pos - I, Pos - II & stop button for flap gate
(2.) Emergency stop push button (Red) for other equipment
d) Belt scale is started when relevant conveyors are started.
e) The dust suppression systems will be energized as soon as the conveyors are energized.
f) Coal Handling plant shall be tripped in case of detection of fire. Necessary input contact
shall be made available
lable to the Contractor in the Owners main control room.
g) Interlock for H.T. Motor : H.T. motors used will continue to run on no load by
disengaging the fluid coupling in case of failure of any process interlock. The H.T.
motors will however be tripped in case of any motor fault like O/L, high motor winding
temperature etc. In addition, in case of normal stop command, after running of the
system, motors will stop.
h) The following are the various safety interlocks for the conveyors and other equipment.
This list
st is indicative only and the Contractor shall develop a comprehensive interlocking
scheme.
Conveyors
a). Pull - Chord switch - not operated
b). Belt sway switch - not operated
c). Underspeed switch - closed at 90% speed of the conveyor within designed
accelerating time.
d). Motor protection - not tripped
e). Local stop PB reset
f). Chute Block switch - not operated.
g). Brakes for conveyor not operated.
h). Trip circuits healthy.
i). Temp. of fluid coupling oil - not high
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 7 of 64
Wagon Tippler
a). Motor O/L - not tripped
b). Local E-Stop PB - reset
c). Stop PB in main CHP control room - reset
d). All Limit Switches reset
e). All limit switches not tripped
Apron Feeder
a). Motor O/L - not tripped.
b). Local stop PB - reset.
Flap Gates
vel limit switches - reset.
a). End of travel
b). Torque limit switches - reset.
c). Local stop - reset.
4.3.4
4.3.5
4.3.6
Annunication System:
The Control desk shall be provided with adequate number of facia type annunciation
windows for the following audio-visual
audio visual fault annunciation purposes. Wherever group
annunciation is provided, alarm status of individual equipment shall be provided on mimic.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 8 of 64
All audio visual annunciation of following parameters should be incorporated in the HMI of
PLC.
(a) 33 kV Breaker Trip (Group wise for each board)
(b) 415 V MCC Breaker Trip (MCC wise)
(c) Bus under voltage for each LT MCC
(d) Following group wise annunciation
annunciation shall be provided for transformers :
(i) Buchholz alarm
(ii) Winding/oil temperature high alarm
(iii) Oil level low alarm
(iv) Buchholz trip
(v) Winding/oil temperature high trip
(e) A.C Control Supply failure.
(f) D.C. Control Supply failure.
(g) Annunciation supply failure.
(h) Both CPU fail
(i) Stand by CPU in service
(j) LT motor overload tripped (Group).
(k)) Belt sway switch operated (Group)
(l)) Pull cord switch operated (Group)
(m)) Zero speed switch operated. (Group)
(n)) Chute plugged (Group)
(o) Wagon rake arrival.
(p)) Wagon Tippler tripped (group)
(q) Apron feeder.
Dust suppression/service water system faults and trips (system wise)
(r)Dust
(s)) Water level low in tanks (group)
(t)) Oil temperature of fluid coupling high
(u) 20% spare windows
For identification of the fault for a particular conveyor or equipment, status indication
against that conveyor / equipment in the mimic will start fast flickering and the annunciation
window will be blinking against that particular fault. In addition, a buzzer (alarm) will also
start
tart sounding. After acknowledgement of the fault, the buzzer will stop, but the fast
flickering on the mimic and the steady glow on the annunciation window will continue until
the fault is cleared and the Reset push button is pressed. When the fault is cleared
cl
and the
Reset push button is pressed, the status indication of that conveyor / equipment on the
mimic will start slow blinking if it is on selected path otherwise it will go off and the steady
glow in the annunciation window will go off. However, pressing
pressing of the Reset push button
before clearance of the fault, will have no effect on the lamps.
At the time of a fault, the faulty conveyor / equipment, as well as the preceding conveyors /
equipment in the interlock sequence, will stop except H.T. motors for which only scoop
coupling will be disengaged and motor will continue to run for process fault. In case of
motor fault, H.T. motor will trip but the succeeding conveyors / equipment will continue to
run. The status indication against the preceding conveyors
conveyors / equipment will start slow
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 9 of 64
blinking while the faulty conveyor / equipment will be fast blinking. Start command shall not
be initiated unless reset button in pressed after clearance offault.
The sequence of operation of the annunciation system shall be as follows:follows:
Ann. Window
Status indication
Buzzer
Ann. Window
Status indication
Buzzer
Status
: Off.
: Steady glow
: Off.
: Blinking.
: Fast blinking
: Sounding.
: Steady glow.
: Fast blinking
: Off.
Condition
Normal :
Fault :
4.3.7
(a.)
Conveyors / Equipment
1. It shall be possible to spray the water on to coal stream only when corresponding
conveyors/equipments are running with material at spray application points.
2. If a running pump trips stand-by
stand
pump shall start automatically.
lly. It shall be possible to select
any of the pumps as auto standby from main CHP control room.
3. Pump/pumps shall trip with a time delay, if discharge valves fail to open. Suitable
pressure/flow switch shall be provided to sense this condition.
4. Pumps shall trip in case of low level of water in tank.
5. All feeding pumps to tank shall trip in case of high-high
high
level in tank.
6. All the controls shall be through control desk.
Page 10 of 64
Sump Pumps
(a) Sump Pumps shall start and stop by the level switches in the sump automatically.
Further manual override start / stop push button shall be provided locally on ground
level.
auto
(b) Any of the pumps can be selected as auto-standby.
(c) If the sump level continues to be high even after the first pump is under operation
second pump shallll start automatically.
(d) The following indications for sump pumps shall be provided on local Control Panel.
(1.) Water level high
(2.) Motor ON/OFF/TRIP.
4.3.9
Wagon Tippler
Wagon Tippler shall be controlled from the local control panel suitably placed. Requirement
Require
of operation as described elsewhere in the specification shall be complied with. Following
indications shall also be provided on the local control panel:
(a.) Motor ON/OFF
(b.) Motor O/L protection operated
(c.) Brakes applied (if provided)
(d.) Hydraulic power pack indications as applicable.
Page 11 of 64
automatic controls for positioning, tipping and discharging the entire contents
contents of the wagons
into the hopper.
5.1
5.1.1
5.1.2
Wagon unloading equipment shall be suitable to handle any type of wagons being used by
Indian Railways for transportation of coal. Thus side arm charger and
and wagon tippler shall be
suitable to handle all standard broad gauge (1676 mm) wagons of RDSO design used by
Indian Railways conforming to latest revision of IS: 10095.
5.1.3
Maximum moving dimensions of locomotive & wagon as per Indian Railway norms shall be
adopted for providing clearances with respect to structures, equipment and tippler
arrangement.
5.1.4
Complete wagon tippler and accessories shall have the approval of concerned Indian Railway
Authorities and RDSO. Further, the contractor shall submit to the Owner detailed drawings
of wagon tippler and accessories including civil and structural drawing only after getting the
same approved from the concerned Railway authorities.
5.1.5
The bidder shall obtain all statutory approvals from the relevant Railway authorities,
authorit
before
the wagon tippler complex is put into operation. Any statutory payment charges, to be made
to the concerned authorities shall be to Bidders account. It is the responsibility of the
Contractor to carry out any modifications as required by the Railway
Railway authorities, at no extra
cost to the Owner.
5.2
5.2.1
The wagon tippler hopper shall be of RCC construction and adequately sized to
accommodate the coal load for atleast two (2) nos. 8 wheeled wagons of RDSO design used
by Indian
ian Railways. For effective volumetric capacity computation of the hopper, the angle
of repose of coal shall be considered as 37. The minimum valley angle of the hopper shall
be considered as 60. The hopper shall have opening below which apron feeders shall
sh be
provided to evacuate coal from the hopper and feed onto associated belt conveyors below.
Complete inside surfaces of the hopper shall be provided with 50 mm thick guniting. Further
it shall be possible to empty out all the coal, without any dead stock
stock from the hopper.
5.2.2
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 12 of 64
5.3
5.4
DESIGN REQUIREMENT
Keeping in view Technical guideline issued by RDSO (Research & design services organization
)G 33 Rev.01 issued on May10 & effective from Dec10, the specification of wagon tippler
along with apron feeder to be designed as under:
a) Wagon tippler capacity
: 25 Tips per Hour
b) Load handling capacity of wagon tippler
: 140 Ton
5.4.1
5.4.2
During each cycle of operation, the tippler shall be capable of holding, completely unloading
and replacing the wagon to its original position without damage to the tippler or the wagon
or the track.
5.4.3
The tippler shall be suitable for continuous operation, 24 hours a day, round the clock.
5.4.4
The wagon tippler structure shall be designed to conform to the requirements of Indian
Railways Research, Design and Standards Organisation, (RDSO) - G 33 Rev.1 with regard
to the nature of loading, impact factor and allowable stresses. It shall be the sole
responsibility of the contractor to ensure that each and every component of the wagon
tippler is adequate in rigidity, strength and of heavy duty construction of first class quality to
guarantee against failure or major damage, assuming proper maintenance and usage. The
tippler shall be designed to allow passage of all standard broad gauge (1676 mm) Indian
Railways diesel locomotives over tippler table at restricted speed.
5.4.5
The wagon tippler shall be suitably counter balanced at each stage of operation so as to
require minimum driving power.
5.5
5.5.1
This specification calls for an electronic static weighing system to measure / record the
quantum of coal, wagon wise on the wagon tippler table before & after tippling. The
weighbridge with adequate no. of load cells shall be provided beneath the wagon tippler
ti
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 13 of 64
platform with a minimum accuracy of 1% of the gross weight of the wagon. The platform
shall be freely supported on the weigh bridge before and after tipping for accurate weighing.
The wagon tippler weighbridge shall be designed to statically weigh the
th wagons in an
uncoupled condition. The system shall comprise of a weighbridge, a tippler table, load cells,
weight digitizer and an intelligent terminal with printer with the facility for computerized
printed output of data gross weight, tare weight, wagon
wagon no., time, date etc. the weighbridge
shall be chosen to accommodate all types of wagons as per RDSO guidelines to move coal.
The weighbridge shall be supported on minimum 4 nos. compression type load cells
mounted on free motion structural unit assembly.
motion weigh scales in both in-haul
in
and out-haul
haul tracks shall be provided
Alternatively, in-motion
for the purpose. The load cells shall be suitable for dusty environmental conditions. The
calibration of the weigh bridge shall be the scope of the bidder. The bidder
bidder shall co-ordinate
co
with statutory authority to get the necessary stamping & other requirements.
6.0
CONSTRUCTION REQUIREMENT
6.1
6.1.1
Cradle
The cradle shall consist of a pair of heavy welded steel plate sections reinforced with
stiffeners and connected
cted by side bearer beams pivotally attached, each section being fitted
with a massive trunion shaft carried in bronze bushed cast steel bearings on each side,
bolted to steel pedestal carried on concrete pedestals. Circumferential driving rack shall be
rigidly
gidly bolted to the peripheries of the sectors. The sectors shall be made of cast steel.
Necessary features of safety against coming down of wagon tippler in the event of failure of
one of the drive pinions and / or gear racks shall be provided and the same
sam shall be clearly
indicated in the bid.
6.2
6.2.1
Rail Table
The rail table shall be constructed of rolled steel joints with standard steel rails (52
kg/metre) mounted on it. The table shall be pivoted from arms extended from the sectors.
The table shall be covered with chequered plates between the rails.
6.3
6.3.1
The wagon shall be clamped automatically by hydraulic system and firmly on the cradle
during the tipping without any damage or undue pressure on any part of the wagon and no
hand adjustment of any sort shall be necessary. Sliding side stop pads shall be of resilient
material to prevent damage to either the wagon or the stops.
6.4
Spill Plate
6.4.1
Fixed to the cradle of the tippler shall be a plain steel spill plate for deflecting material into
the tippler hopper.
6.5
Driving Gear
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 14 of 64
6.5.1
Multiple pinions meshing with cast steel racks bolted to the end sectors shall impart drive
through hydraulic drive with each pinion drive through slow speed high torque hydraulic
hydr
motors using gear boxes as applicable. Suitable oil coolers shall be provided for hydraulic
power pack. Suitable dust protective cover shall be provided.
6.6
Brake
6.6.1
An automatic electro hydraulic brake shall be furnished to hold the tippler in any position
with the load and against any movement except that provided by drive.
6.7
Limit Switches
6.7.1
Limit switches of suitable type which can be readily adjusted to give the desired tippling
angle shall be provided. An emergency over tip limit
limit switch operated by a striker on the
tippler trunnion shaft shall be furnished.
6.8
Ballast
6.8.1
Ballast necessary for counter weight and balancing the tippler shall be provided as per the
requirement.
6.9
Lubrication
6.9.1
All bearings shall be properly lubricated. Grease nipples and reservoirs shall be furnished
where necessary.
6.10
Guards
6.10.1 All gears inside machinery pits and other moving parts shall be securely guarded.
6.10.2 All necessary base plates, guide plates, chequered plate covering for drive pit and any other
pits, all required fixing materials, inserts and sleeves shall be furnished.
7.0
7.1
DATA SHEET
GENERAL
Wagon Type
Moving Profile
No. of tips (guaranteed)
Designed
Rail Gauge
Weigh bridge
Duty
7.2
Page 15 of 64
A.
: RCC Construction.
: To accommodate atleast 2 nos. 8 wheeled wagons.
wagons
: One (1)
Wagon Tippler
Type
Tipping angle
Duty Requirement
Counter balancing
Cradle
Driving Gear
(i) Racks
(ii) Pinion
Rail Table
Drive
Brake
Clamping
Top & side stops
: 37
: 50 mm thick guniting.
: 300 mm x 300 mm
: 200 mm x 36 mm thick flats.
8.0
8.1
GENERAL
8.1.1
Side Arm Charger shall be furnished complete with travel rails, drive equipments and
associated accessories.
8.1.2
The rake comprising of specified maximum number of wagons shall be pushed into the
reach of inhaul equipment by a locomotive. Further placing of wagons over tippler platform
and moving out the empty wagons shall be accomplished with the help of side arm charger.
c
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 16 of 64
8.2
8.3
DESIGN REQUIREMENT
8.3.1
A single module of side arm charger shall be used for inhaul and outhaul operations. Thus,
side arm charger shall be used for indexing forward the rake of 60 nos loaded wagons,
placing decoupled wagons on the tippler table and out hauling
hauling the empty wagons.
8.3.2
The rake of 60 loaded wagons will be brought by locomotive and placed on the retipping
line such that the leading wagon will be within the reach of the side arm charger. Now the
side arm charger will be coupled to the leading wagon,
wagon, pull the rake of 60 nos. loaded
wagons towards tippler table. The first wagon will be decoupled manually from the rake and
signal will be given to the side arm charger operator that the wagon is de-coupled.
de
Now the
leading wagon will be placed centrally
centrally onto the tippler table by side arm charger,
(simultaneously ejecting the empty wagon from the tippler table). After the loaded wagon is
placed on the tippler table, the arm is de-coupled
de coupled from the loaded wagon. Adequate
clearance between tippler table and
and empty wagon shall be ensured. The side arm charger
will stop at the end of its strokes, the arm will be swung vertically-up
vertically up and the machine will
move towards in-haul
haul direction and occupies the initial position. In the meantime, the
tippler will tip the loaded wagon placed on the tippler table and return to its original
position. Before tippling operation of wagon tippler is completed, the arm of the side arm
charger will be swung to horizontal position and will be coupled to the rake of remaining
loaded wagons at waiting position just before the tippler table and is now ready for the next
cycle to start. After the tippling operation of wagon tippler is completed the cycle will be
repeated.
8.4
TECHNICAL REQUIREMENTS
8.4.0
8.4.1
CONSTRUCTION REQUIREMENT
The Side Arm Charger shall be suitable to handle60
handle number of loaded wagons.
wagons The pusher
arm shall be vertically rotatable arm mounted on a carriage running back and forth parallel
to the train track.
8.4.2
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 17 of 64
8.4.3
The arm shall be raised and lowered by means of hydraulic cylinder mounted on the
carriage.
iage. Suitable means shall be provided to prevent damage to the arms should the arm be
accidentally lowered into the side of wagon.
8.4.4
The arm shall be of robust construction either of cast steel or of heavy duty fabricated steel
for the required duty.
8.4.5
The construction of the head assembly of the push arm shall be such that no damage is
suffered by the couplers of wagons and engagement of arm over the coupling assembly as
well as transmittance of indexing forces to accelerate, run and decelerate the train during
the positioning cycle shall be very smooth.
8.4.6
The carriage frame shall be a suitable fabrication assembly of large proportions massive
enough in strength and rigidity for the required duty.
8.5
8.5.1
The travel carriage with push arm shall be propelled to and fro, parallel to train track
through hydraulic motor driving through a gear box and EHT brake.
8.5.2
The rating of the drive equipment and its characteristics shall match with indexing forces
required
quired to be exerted in varying amounts depending upon train dynamics and to suit
haulage of 60 wagon loaded rake.
8.5.3
The travel carriage shall ride on vertical bearing wheels and will be guided by horizontal
bearing wheels by suitably transmitting the thrust load from the positioned arm to the
foundation. The wheels/rollers shall be of forged steel and shall run on the rails supported
over the RCC pedestal.
8.5.4
Cushioned emergency bumpers (buffers) shall be provided at the forward and return end of
carriage travel run for protection. These shall be designed to arrest the machine without
undue shock in case the machine exceeds its extremities because of any mal-operation.
mal
9.0
9.1
DATA SHEETS
GENERAL
: 1 (One) no
Quantity
No. of wagons to be handled By
each side arm charger at a time
: 60
No. of tips by wagon tippler
: 20 (min.) per hour (guaranteed)
: 25 per Hour (designed)
DESIGN & CONSTRUCTION REQUIREMENTS
9.2
Arm
Arm Drive
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 18 of 64
Carriage Frame
Travel Carriage drive
Motor
Travel brake
Bearings for sheaves
10.0
10.1
APRON FEEDER
GENERAL
Apron feeders complete with all accessories shall be furnished for wagon tippler hoppers as
specified.
10.2
10.3
DESIGN REQUIRMENTS
Apron feeders shall be of robust construction & designed for handling ROM coal as specified
and without any choking particularly during rainy season when coal is sticking. A drible
conveyor shall be provided for proper clean up. The pan and chain shall be of proven design
and shall be with adequate factor of safety.
10.4
CONSTRUCTION REQUIREMENT
The frame shall be manufactured from rolled steel section welded and bolted together to
form a rigid structure.
cture. The roller shall be life time lubricated and shall be manufactured from
alloy steel.
The chain Link shall be forged steel. Pins and rollers shall be of hardened steel. The chain link
shall be bolted to the pans. Apron/pan shall be of suitable thickness
thickn
which shall be
constructed out of fabricated MS with wear resistant liner plate or special alloy steel without
any liner plate for the duty requirement. The pan would be fitted directly to the chain
attachment. The head and tail end shall be of sturdy steel construction suitably stiffened.
The sprocket shall be made of cast alloy steel with case hardened teeth or forged steel. The
traction wheel shall be made of cast steel with case hardened surface. Tensioning
arrangement with sufficient travel shall be
be provided for the tensioning of the chain.
chain
Complete dribble belt system consisting of head pulley, tail pulley, drive, motor, stringers,
deck plates etc. shall be provided.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 19 of 64
10.5
DATA SHEET
Capacity (TPH)
Angle of Installation
Chain Link
Apron pan
Traction wheel
Rollers
11.0
12.0
12.1
Page 20 of 64
12.2.4 Thee gears used shall be helical conforming to IS:3681 (latest revision) or worm reduction
units or spiral bevel speed reduction units conforming to suitable Indian Standards. The
dimensions of the shaft end shall conform to IS:3688 or its latest revision. Above
Ab
40 kW drive
rating, all gearboxes shall be helical or bevel helical type only.
12.2.5 Recommended oil grade shall be compatible with gear internals like material of bearing,
cages. Further, all gearboxes shall have suitable breather plugs, dipstick, drain plug etc.
12.3
COUPLINGS
12.3.1 Flexible / Rigid Couplings
Approved type of couplings shall be used for power transmission depending upon duty
requirements. The design of the coupling shall be such that it can take shock and
misalignment without sacrificing its efficiency. Geared type flexible coupling shall be used on
low speed side
ide for all conveyors and other drive chains where gear box is provided. Other
couplings in the drive chains shall be either rigid or flexible type, depending upon the
requirement of equipment design and shall be finalized during detailed engineering.
12.3.2 Fluid Couplings
Fluid couplings shall be provided in all the drive machinery for wagon tipplers & associated
belt conveyor systems if the actual power requirement at motor output shaft is more than
40 kW. The fluid coupling for LT motors shall be of traction
traction type. Cooling water coils for
traction type fluid coupling shall not be accepted. Scoop tube type fluid coupling shall be
provided for conveyors with HT motors. Suitable electrically operated actuators shall be
provided for scoop tube operation from local as well as remote. Suitable provision for
alternate manual operation shall also be kept. Separate pump with motor shall necessarily
be provided for circulating the fluid coupling oil through oil cooler. Independent
arrangement for forced cooling water
water supply using 2X100% capacity pumps to oil cooler
shall be provided by Contractor. Suitable interlock using flow switches shall be provided in
both oil as well as water lines to trip the drive motor in the event of flow in either lines
falling below/ acceptable
eptable levels. Suitable pressure indicators and flow indicators shall be
provided in the cooling water lines along with all-relevant
all relevant valves, strainers and accessories.
Necessary isolation valves shall be provided in the oil / water line for maintenance of any
equipment in the line. Necessary interlock shall also be provided so that the HT motor
cannot be started from remote / local unless position of scoop tube permits no load start of
the motor. Tripping of downstream equipment while the system is under normal
n
operation
shall result in scoop tube re-positioning
re positioning to permit no load run of the concerned HT motor.
Temperature switch shall be provided in the oil circuit and shall trip the system in case of
high oil temperature. Selection of rating & speed of actuator
actuator for scoop type fluid coupling
shall be made taking into consideration the coasting time of downstream and upstream
conveyors and the engagement/disengagement time achievable. The scoop tube operation
must be such so to ensure quick draining out of oil
oil from the operating circuit, by providing a
double speed motor.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 21 of 64
12.4
12.4.1
Continuous Motor Rating (Name Plate Rating) at 50 Degree Centigrade Ambient temp. for
Electric Motors
For conveyors of belt conveyor systems and belt for In line magnetic separator:
a)
*120%
120% of actual power at drive motor output shaft at specified design capacity
b)
WT, SAC, apron feeders: *110%
110% of actual power requirement at drive motor output
shaft at guaranteed (rated) capacity.
c)
Mono-rail
rail hoists (travel and hoisting), various pumps of DS systems, service water
systems, cooling water system, potable water system and sump pumps: *110% of
actual power requirement at drive motor output shaft at guaranteed (rated)
capacity.
Ventilation Fans: *110%
110% of actual power requirement at drive motor output shaft at
d)
guaranteed (rated) capacity. In case of belt drive, the efficiency of transmission shall
be considered as 95%.
*The
The actual power at drive motor output shaft
shaft shall be calculated after considering all the
losses of down the line equipments of the drive train.
1.0
Drive Equipment Rating
a) For Conveyors : 120% of actual design requirement
b) Other Equipment 1 x 100 % duty: 120% of actual design requirement
c)) Other Equipment 2 x 50 % duty: 110 % of actual design requirement
2.0 DESIGN & CONSTRUCTION REQUIREMENT
2.1.0 Gear Box
2.1.1 Type
(a) Below 40 KW: Helical, worm, bevel as per requirement without cooling coil
(b) Above 40 KW: Helical / bevel helical without
w
cooling coil
2.1.2
Service Factor:
As per accepted engineering practice / manufacturer's
recommendations
2.1.3 Ambient temperature for Thermal rating: 50o C Minimum
2.1.4 Mounting: On Machined/Ground Surfaces
2.1.5 Output Rating:
a) For belt conveyor systems @ Service factor X {1.2 times the actual power
requirement at drive pulley shaft at design capacity}
b) For other equipment @ Service factor X {1.2 times the actual power requirement
of the driven equipment }
@ Service factor shall include all the components considered by the supplier and should be
clearly indicated in manufacturers gear box selection catalogues.
2.1.6 Duty: 24 Hrs. Continuous
2.2.0 Flexible Couplings:
2.2.1 Type: Geared capacity.
2.2.2 Rating: Not less than
han motor rating.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 22 of 64
2.3.0 Fluid Couplings: For all motors having rating more than 40 KW.
2.3.1 Type
(a) L.T. Motors: Traction type
(b) H.T. motors: Scoop tube type.
2.3.2 Rating: Not less than motor rating
13.0
13.1
EOT CRANE
GENERAL
An E. O. T. crane complete with all accessories shall be furnished for maintenance at wagon
tippler house.
The design, manufacture, supply erection and commissioning of EOT crane complying with
all the currently applicable statutes, regulations and safety codes in the locality
loca
where the
equipment is to be installed. The EOT crane shall conform to the latest edition of the
standards and codes. Other internationally acceptable standards/codes, which insure equal
or higher performance than those specified, shall also be accepted.
accepted. Nothing in this
specification shall be construed to relieve the contractor of the required statutory
responsibility. In case of any conflict in the standard and this specification, the decision of
the Engineer shall be final and binding.
13.2
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 23 of 64
13.3
- 6 M/Min
- 8 M/Min
- 10 M/Min
- 30 M/Min
13.3.5 (a) Normal Span: Actual span & other dimensions as required as per structural steel
shed of wagon tippler shall be evaluated by the bidder and confirmed in the bid.
13.3.6 (b) RailCenter to Center: Bidder to confirm
13.3.7 Gantry Rail heights above floor level: Bidder to confirm
13.3.8 Hook lift above floor
floor level to be provided: Bidder to confirm depending upon actual
site condition
13.3.9 Type of Hook - Shank type
13.3.10 Available head height above rail top: to be confirmed by Bidder
13.3.11 Available side clearance from gantry rail center: Bidder to confirm
13.3.12 Location
Wagon tippler shed, Bay Length & Width: Bidder to confirm
13.3.13 Electric power supply - 415 Volt, 3 Phase, 50 HZ A.C. Supply
13.3.14 Gantry rail size - Bidder to confirm.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 24 of 64
14.0
14.1
14.2
DESIGN REQUIREMENTS
14.2.1 For the Hoists with more than 2.0 tonne lifting capacity or more than 10.0 M lift, with the
exception of hoists for GTU and bend pulleys motor operated hoist blocks for both long
travel and lift shall be provided. Other hoist blocks shall be of hand operated type for both
travel and lift. For hoists for GTUs and bend pulleys clause no. 1.02.18 shall be referred to.
All monorails coming out of the buildings shall be provided
provided with electric hoist blocks,
irrespective of load and lift. Minimum 3 meter length of Cantilever shall be provided in
monorails coming out of the building to lower the equipment to ground level clearing the
building sidewalls and any other facilities beneath
beneath the floor upto ground level.
14.2.2 The exact lift/travel and the number of the hoisting mechanisms and the mode of lifting
equipments to various floors of the buildings shall be as decided by the Owner/RITES
Owner
at the
time of detailed engineering. Use
Use of single hoist shall be avoided for handling more than one
equipment. Clear height shall be maintained when handling one equipment over other, in
such case dismantling of any equipment shall not be permitted. The center line of monorail
shall not deviatee by more than 500 mm from the center of gravity of any equipment that is
to be lifted. Contractor shall take clear note of the fact that the number and monorail
hoisting systems shall also be decided considering the movement of the equipment being
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 25 of 64
lifted over/by the side of other equipments without removing the later. The necessary
levels of floors in various buildings shall be decided considering the above requirement.
g
level.
14.2.3 Monorails shall be extended outside the building to handle the equipment to ground
For monorail/hoist routed inside the buildings, suitable machinery well and removable
handrailing and grating shall be provided on various floors of buildings, as necessary, to
handle the equipment.
14.2.4 Electrically operated monogirder type
type hoists shall consist of following major components.
a) Electrically operated trolley complete with drive motor (Trolley travel speed maximum 15
m/min.).
b) Hoist cable, hoisting block and hooks complete with drive motor (Hoisting speed
maximum 6m/min.).
c) Limit switch to prevent overhoisting, over lowering and over travel.
d) Festoon arrangement of feeding power to trolley assembly.
e) Erection hardware.
f) Pendent control station suspended from hoist.
g) Control Panel mounted on wall.
designed and constructed in accordance with the latest revision of
14.2.5 The electric hoist shall be designed
IS:3938 and shall be suitable for duty class 2.
14.2.6 For electric hoists, trolley movement and hoisting shall be effected by using two separate
motors. Motors shall be as per technical requirements
requirements discussed elsewhere. However the
motors shall be suitable for 150 starts per hour at 40% CDF.
14.2.7 Trolley for motorized / manual cross travel shall be designed to accommodate a wide range
of I beams and shall be capable of travelling on straight as well as curved monorails with the
design being such to maintain uniform distribution of pressure on the flanges.
14.2.8 Motor operated geared trolley shall have two (2) pairs of wheels, one pair of which shall be
driven through motor.
14.2.9 Wire rope shall be of pre-formed
pre formed type, hemp cored, regular lay 6/36 construction with a
breaking strength of 160 -175
175 kgf/ sq. mm. Reverse bend of ropes is not acceptable.
Minimum number of falls of rope shall be four (4).
14.2.10 All gears and pinions shall be of hardened and tempered steel with machine cut teeth in
metric modules. Surface hardening of steel is not acceptable.
14.2.11 All running shafts and wheels shall be fitted with roller bearings with a rated life not less
than 20 years based on equivalent
eq
running time as per IS:3938.
14.2.12 An electromechanical brake shall provided for hoisting as well as cross travel. Brake lining
shall be of asbestos.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 26 of 64
14.2.13 Cast iron parts, wherever used, shall be of minimum grade 30, IS:210.
n pulley blocks shall be designed to IS:3832, the operating hand chain shall conform to
14.2.14All chain
IS:2429 grade 30 pitched and polished and the load chain to IS:6216 grade 80. The chain
pulley block shall be suitable for duty class 2. Hooks shall be as per IS: 8610 & with
antifriction bearing for bottom look.
14.2.15 All hoists/chain pulley blocks shall be selected to have minimum headroom and shall be
selected to lift heaviest piece of equipment. Further, it shall be possible to handle any
equipment without disturbing
disturb other equipment.
14.2.16 The hand chain wheels shall be of cast steel, the wheels shall be with flanges and designed
to ensure effective operation of hand chain. Further, suitable local brake shall be provided as
per IS:3832 to arrest and sustain loads
load in all working positions.
14.2.17 The velocity rates, effort on chain required to raise the safe working load and travel and
speed shall be within the limit specified in IS:3832. Proof load test shall be carried out as per
IS:3832. Balance requirements shall be as discussed in earlier clauses pertaining to electric
hoists.
14.2.18 Hoist for Gravity Take up arrangement and bend pulley.
For handling bend pulley, take-up
take up pulley and counter weights following hoisting
arrangement shall be provided:
(1) For handling bend pulleys, hooks of adequate capacity shall be provided at the top of gallery.
Further minimum four (4) nos. manually operated chain pulley blocks of adequate capacity
shall also be provided for the entire coal handling plant for handling bend pulleys.
(2) For handling take-up
up pulleys, manual hoist along with mono rail beam of adequate capacity
having cross travel, arrangement shall be provided at bottom of gallery to handle take-up
take
pulley only of conveyors.
(3) For handling take-up
up weight, a separate manual
manual hoist with mono rail beam of adequate
capacity shall be provided to hold complete counter weight (inclusive of all counter weight
blocks). This hoist shall be provided for holding the counter weight and shall be located in
the zone of counter weight travel.
14.3
CONSTRUCTION REQUIREMENT
14.3.1 The hoist mechanism shall consist of a grooved rope drum driven by electric motor through
gears. Each end of the rope shall be anchored to the drum in such a way as the anchorage is
readily available for maintenance.
maintenance. Each rope shall have not more than two (2) full turns of
the drum when the hook is at its lowest position and one (1) spare groove when the hook is
at its highest position. The leading rope taken by the drum should not slope sideways when
slack and
nd it should not be caught between the gear wheel.
14.3.2 Rope drum, gear box, block etc. should be fabricated out of weldable quality steel.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 27 of 64
14.3.3 Trolley wheels shall be of single flange type in the taper treads. The wheels shall be mounted
on antifriction
iction bearings and shall be easily removable for repair/replacement.
14.3.4 The load hook shall be swiveling type forged circular shank section and shall confirm to
IS:8610.
points shall be grouped
14.3.5 All gears and bearings shall be lubricated by grease. All lubricating points
together in easily accessible position.
14.3.6 The bottom block shall be of enclosed type and shall have guard against rope jamming in
normal use. It shall have standard forged swivel shank hook fitted on antifriction thrust
bearing.. Lock to prevent hook from rotation and locking arrangement to prevent accidental
unlocking shall be provided. Pulley of the bottom block shall be provided with antifriction
bearings.
14.3.7 All parts requiring replacement/inspection/lubrication shall be accessible without need for
dismantling of other parts/structures.
14.3.8 All components of hoists of identical capacity and duty shall be interchangeable.
14.3.9 Hoists shall have permanent inscription in English on each side readily recognizable from
floor level stating safe working load.
14.3.10 Pendant shall be provided with flourscent up/down/forward/reverse travel push buttons
and indicating lamps. Its power supply shall be limited to 24V AC.
14.3.11 The control panel shall be wall mounted type & easily approachable from the floor by a
standing man.
14.3.12 For Inspection / maintenance of hoist components a fixed platform (of min 1.5 x 1.5m) with
ladder shall be provided for each hoist.
independent motorised hoist for its handling /
14.3.13 Each inline magnetic separator shall have independent
maintenance purpose. Each suspended magnet shall also be provided with a dedicated
electric hoist.
14.4 DATA SHEET : MONORAILS AND HOISTS
1.0
GENERAL
Functional Requirement : To transfer equipments to maintenance area
a
or outside
1.1
the building.
2.0
2.1.0
2.1.1
2.1.2
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 28 of 64
2.1.3
2.1.4
2.1.5
2.1.6
IS:4682 :Code of practice for lining of vessels and equipment for chemical
processes.
Page 29 of 64
15.2.3 Transfer chutes shall be adequately sized and sloped to ensure smooth flow of coal without
any accumulation anywhere.
15.2.4 Complete chute work above the drive floor for conveyors provided with In-line
In
belt
magnetic separators shall be of 10 mm thick SS - 304 in the zone of magnetic field.
15.2.5 Direct impact of material on conveyor belt shall be avoided by providing an inclined surface
at 60 degrees valley angle at the feeding point to guide the material in the direction of belt
travel. Further, chute
ute construction below flap gate shaft shall be such that there will not be
any accumulation of coal dust between chute and flap gate in that zone.
15.2.6 Hoppers and Chutes shall be made of minimum 20 mm thick TISCRAL or equivalent material.
However, Contractor
ntractor to submit test certificates stating composition of material and
mechanical properties of these wear resistant steel to the Owner during detail engineering.
Long chutes guiding flow from considerable height shall be provided with impact plates
wherever
ever change in direction of flow takes place. Hinged inspection doors (generously sized)
of leak proof construction shall be provided for access/ maintenance purpose, at
approachable heights for chutes and flap gates. All chutes should have one inspection door
at every floor and for the ones in between the floors (more then 1.5 meter above the
operating floor level) suitable access for trouble free maintenance shall be provided.
Maximum distance between two inspection doors in a chute shall be 2 mtrs. For sealing
s
of
inspection doors labyrinth type arrangement (with rubber inserted in grooves) to be
provided. In addition to positive locking arrangement, mounting bolts, to tighten the door
further against rubber shall also be provided.
15.2.7 Bottom side of the chutes on which the coal slides shall be welded to the side plates to form
a trough. Bottom sides along with its adjacent sides shall be flanged and made from TISCRAL
or equivalent material of 20 mm thickness. The non-striking
non striking surface i.e. the covers of
o the
trough shall be of 10 mm thick mild steel and bolted to the flange provided on the trough.
Inside welding shall be provided in the corners for permanent sealing. Further, the chute
boxes not more than 1.5 m in length shall be joined through bolted flange
fl
connection to
form the chute legs. Adequate care shall be taken to locate the flange joint away from floor
level for easy maintenance. Bolted flange joints shall be of dust tight construction and
necessary sealing material shall be provided in all the flange connections for adequate
sealing. Complete chute work in the region of flap gates shall be fabricated from 20 thk
TISCRAL or equivalent. In case of vertical chute (valley angle more than 80 degree) complete
chute, work shall be of 20 mm thick TISCRAL
TISCRAL or equivalent material. While finalising the
chute work inside the building, arrangement for shifting and replacing chute legs, proper
handling arrangement/wall openings, trolleys, hoists shall also be provided. While
fabricating the chute, the constituent
constituent plates used shall be in one piece. No welds in between
shall be allowed. In the zones of direct impact due to Coal trajectory, wear resistant backing
plate with stiffners shall be provided in coal flow chutes. Similar backing plates & stiffening
arrangement
ement shall also be provided on the chute surfaces having direct coal fall.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 30 of 64
15.2.8 Hoods over the conveyor head pulleys shall be made of suitably stiffened minimum 4 mm
M.S. Plates and shall be provided with hinged and gasketed inspection doors with suitable
suit
access to them. Further, serrated rubber seal shall also be provided at the very inlet of head
chute to minimise dust nuisance.
15.2.9 Separate maintenance sealed door shall be provided for access to belt cleaners in head
pulley hood impact plates, flap gates for maintenance and inspection doors shall be of
hinged with positive locking facility.
15.3.
Skirt Boards
15.3.1 Skirt board shall ensure centralised loading of conveyor belt to avoid coal spillage. Suitable
Skirt Plates of minimum 3.0 meters length shall be provided at each feeding point of
conveyor. The width of the Skirt Boards shall be two-third
two third the conveyor belt width.
width In the
beltswhere coal of appreciable lump size (250 mm) is being conveyed,
conveyed, the gap between the
bottom of the skirt board and the belt shall be made to increase uniformly in the direction of
belt travel. The height of the skirt boards shall be sufficient to contain the material volume
as it is loaded on the belt and shall not be less than 750 mm. The skirt plates shall be fitted
with modular segmented and replaceable rubber skirting pads having facility of adjusting the
pressure on the belt conveyor and shall have provision of on line removal for the purpose of
easy maintenance. Such segmented rubber pads with its holding
holding down adjustment
arrangements shall be of proven design. The edges of segmented pads shall be installed at
an angle for providing a better seal. All care shall be taken while designing, to combine good
sealing with minimum belt wear.
15.4
Flap Gates
15.4.1 The motor operated 2 position flap gates shall be provided in transfer chutes as specified
and shall be complete with electrically operated actuators. The gates shall be of robust
construction and suitable for trouble free operation. The face of the flap gate shall be made
out of 20 mm thick TISCRAL or equivalent material.
15.4.2 The equipment shall be capable of being operated for at least 15 switchings per hour at
rated load and thrust and shall be suitable for 10 Nos. consecutive switchings at rated
r
load
and thrust. The equipment shall be shop tested to prove this requirement.
15.4.3 The motor rating for the actuator shall be so selected as to provide sufficient thrust for
operation of the flop gates against the moving weight of coal and/or flap
flap gate. The flap gate
travel shall be in the range of 60 deg. to 70 deg. The motor shall be completely dust tight.
15.4.4 Lever arm shall be provided between actuator and flap gate shaft for obtaining required
thrust. The linkage mechanism proposed shall be indicated in the Bid.
15.4.5 The actuators shall be capable of preventing any over travel. Suitable travel dependent limit
switches controlling the travel of the flop gates on either direction shall be furnished. These
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 31 of 64
shall be placed internal to the drive unit and shall be completely dust-proof.
dust
The limit
switches shall be capable of adjustments to vary the total length of travel of the gates.
15.4.6 Suitable thrust dependent limit switches shall be provided in the actuator, which shall trip
off thee actuator motor in case of excessive thrust due to jamming of the gates during its
travel in either direction. The same shall also be integral to the drive unit and shall be dust
proof.
15.4.7 Provision for alternative manual operation shall also be made
made using declutchable
handwheel. The diameter of handwheel shall be selected considering convenient force to be
applied by a single operator. However, minimum diameter of hand wheel shall be 500 mm.
Limit switch for safety of person operating the hand wheel shall be provided.
15.4.8 All the two way chutes, one way of which is leading towards the future conveyor, shall be
provided with blind flange and flap gate with a provision to mount an actuator in future.
15.4.9 The Contractor shall furnish calculations for selection of actuator for each location for
approval of Owner/RITES
/RITES.
15.4.10 Suitable stiffening arrangement shall be provided between the two faces of the gate plate.
At the end of the travel the total length of edge of the flap gate shall
shall rest on a suitable
projected surface from chute to prevent leakage of coal dust through the available clearance
between chute and flap gate.
15.4.11 Maximum feasible counterweights shall be provided for better utilisation of system.
However, for calculation
lation of thrust required, the benefit of counterweight shall not be taken
into considerations.
15.4.12 Suitable self aligned double row ball bearings in dust tight housing shall carry the gate shaft.
Suitable provision for re--greasing shall be provided.
15.4.13 For standardisation purposes, only one standard type of actuator for flap gates shall be
provided. The standard type actuator shall be selected for maximum thrust as calculated for
various locations. Flap gate actuator as a whole and individual component
component wise shall be
completely interchangeable for all locations.
15.4.14 The material of shaft shall be EN-8
EN 8 or equivalent. The diameter of the shaft shall be suitable
for motor stalled condition and associated twisting.
15.4.15 Approach/maintenance platforms complete with the chequered plate floor, hand rails,
ladders etc. shall be provided for all flap gates.
15.4.16 Shaft & flap gate shall be tightly fitted to each other.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 32 of 64
15.4.17 On both faces of flap gate main plate, 20mm thick TISCRAL liner plate
plate or equivalent material
shall be provided.
15.5 DATA SHEET : CHUTES AND HOPPERS
1.0
GENERAL
1.1 Coal Parameters As specified elsewhere
2.0 DESIGN & CONSTRUCTION
2.1.0 Chutes & Hoppers
MinimumValley Angle: 60 degrees
2.1.1
2.1.2
Material :
(a) Chute work
Sliding zones & adjacent sides
No striking/ Non sliding zones
Chute with valley angle 80 degree and above
Page 33 of 64
Maximum effort
: Convenient for single
operator by declutchable hand wheel regardless
of electrical power.
Minimum Handwheel : Diameter 500 mm
(b)
2.3.5 Flap gate shaft
(i) Diameter: minimum 130 mm
(ii) Material: EN-8
16.0
16.1
16.1.1 The specification is intended to cover design, engineering, manufacture, supply, erection,
testing and commissioning of the complete, Dust Control and Miscellaneous Systems as
specified hereinafter required for the Wagon Tippler Package. The Contractor shall refer to
the other sections and scheme indicated in the tender drawings to appraise himself of the
work and scope of supply of the other Contractors/Owner's and shall coordinate his work
with the work of other Contractors.
16. 1.2 Dust Control System
The dust control system to be furnished under this specification is required for control of
fugitive dust emissions from dust generation points such as transfer points, feeders etc. Dust
control is achieved by dust suppression system.
system. Contractor shall guarantee and offer dust
control system which shall not allow a dust concentration in the ambient air inside the
buildings more than acceptable limits as per Owner/RITES
Owner
approved guidelines or any
internationally recognized hygienic Standards/Codes.
Standards/Codes. The Capacity of dust control system
specified elsewhere is for Contractors guidance only. Contractor shall provide adequately
sized fool proof dust control systems the performance of which should be guaranteed by the
Contractor. However, the
he capacity of the offered system shall not be less than the specified
values. Further, for computation of design capacity of the pumps, permanent recirculation
lines as shown in tender drawings shall also be considered. Water scheme dust suppression
shall be provided as indicated in tender drawings. Clarified water shall be used for Service
water system, Plain water dust suppression system shall be used for all receipt and discharge
points in Transfer.
16.1.3 Miscellaneous Systems
Service water system, potable water system, cooling water system & sump pumps shall be
provided as specified elsewhere in this specification and as indicated in tender drawings.
16.2 Scope
16.2.1 Plain Water Dust Suppression System
Complete with water supply system, piping, spray
spray heads, pumps, drive motors with canopy
(wherever required), couplings with enclosure, electricals, supporting structures,
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 34 of 64
approach/maintenance platforms, handling for equipment, civil and structural works and
necessary accessories shall be provided for WT hopper top & all transfer points, etc.
16.2.2 Sump Pump
4x100% sump pumps alongwith level switches and piping up to nearest Owner's drain (max.
up to 50.0 meters from outside the building) shall be provided at all locations wherever
natural drainage is not possible. Sump pumps along with drain pits shall be provided at other
locations also, if required, during detailed engineering stage. Sealing pumps with valves,
piping fittings and other accessories for sealing of sump pumps shall be provided.
16.2.3 Service Water System
Service water distribution system complete with water supply system, valves, quick
couplings, hose pipes with nozzle, piping, pumps, drive motors with canopy, couplings with
enclosure, electricals, including supporting structures, handling for equipments, civil and
structural works and necessary accessories shall be provided throughout the coal handling
plant area in Contractors scope.
16.2.4 Pipings, Fittings, Valves and Specialities
The material to be supplied for completing the pipe work shall include but not be limited to
the following :
(1) Straight piping, bends, tees, elbows, branches, laterals, crosses, reducing unions,
couplings, caps, blank flanges, saddles etc. necessary for making reliable piping system.
(2) Gaskets, ring joints,
ints, jointing material etc. as required.
(3) Instrument tapping connections, stubs.
(4) Gate, globe and check valves to start/stop, regulate and to prevent back flow.
(5) Duplex Strainers.
(6) Anchors, hangers and supports as required including secondary steel embedments etc.
(7) Bolts, nuts, fasteners as required for interconnection piping, valves and fittings as well
as for terminal points.
(8) The entire water piping of DS/SW/PW/CW shall be routed/supported on concrete
pedestal and conveyor galleries. Whereever the layout does not permit the pipes to be
routed over ground, the same shall be buried in conformity to the relevant standards &
shall be provided with necessary protective coating as per relevant standards.
(9) Painting, anti-corrosive
corrosive coatings etc. inside and outside pipes
pipes as necessary.
(10) Welding electrodes and welding rods.
(11) The area around storage tanks strainers, two valves etc. (located out side pump house)
shall be paved with drains.
16.3
Terminal Points
Owner shall provide supply of water for dust suppression system, service water, potable
water at one terminal point as elaborated elsewhere. Beyond the terminal point, the
complete pipe work along with associated valves, specialities, instruments, fittings and
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 35 of 64
supports, pumps, tanks, etc. as required for the satisfactory operation of dust control,
service water & potable water systems shall be furnished by the Contractor.
16.4
16.5
16.5.1 At specified locations dust suppression system shall be provided which comprises spray
nozzles discharging plain water in a fine spray to capture air borne dust particles and direct
them into the main
in coal flow. Water shall be discharged via a pipe work system through
spray heads at the dust suppression zones.
16.5.2 Water shall be drawn from the water storage tank by 2x100% electric motor driven pumps
and discharged into tank from where 2x100% duty
duty electric motor driven pumps shall
discharge the water via a pipe network system through spray heads at the dust suppression
zones. Solenoid valves shall be provided for open/close control of water line to each spray
head. Each spray head shall consist of minimum 4 nos. nozzles. Spray heads shall be
provided at coal loading and receipt zone. Pressure at inlet to spray head shall not be less
than 2.5 Kg/sq.cm(g).
16.5.3 The dust suppression system over the WT hopper shall have a canopy on which fogging
nozzles
zzles are fixed at specified distance. Each nozzle header shall be provided with adequate
number of spray nozzles spaced at 500 mm interval so that the entire length & width of the
wagon tippler hopper are covered by a grid of nozzles. Further, the water spray
s
shall be of
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 36 of 64
fogging type with a minimum pressure of 2.5 kg/sq.cm(g) at spray nozzle inlet. It should be
possible to operate any number of zones simultaneously. The operation of wagon tippler
dust suppression system shall be automatic so that the fogging
fogging water spray shall get
activated only when the tippling is in operation.
16.5.4 Each spray head shall have a provision for installing a pressure gauge whenever required.
Further, pressure gauges shall be provided at least at two locations.
16.5.5 Sump Pumps
Sump pumps shall be vertical centrifugal type with separate discharge pipe and shall be
capable of developing required head at rated capacity for continuous operation. Sump
pumps shall be suitable for handling coal slurry & sludge. Head capacity
capacity curve of the pump
shall be rising type up to the shut off condition. Sump pumps alongwith level switches &
piping upto nearest Owner's drain (max upto 50.0 mtrs. from outside the building) shall be
provided at all locations wherever natural drainage is not
not possible. Further sump pumps
alongwith drain pits shall be provided at other locations also, if required, during detailed
engineering stage. The capacity of each pump shall not be less than 50 cub. M/hr.
Continuous motor rating (name plate rating) at 50 deg. C. for sump pump shall have at least
10% margin above the maximum load demand of the equipment in the entire operating
range (including run out condition of pumps in case of parallel operation). The maximum
load demand shall include the drive losses in the transmission system. Size of the sump pit
shall not be less than 2.0 meters x 2.0 meters x 2.5 meters. One no. of settling pit, of
adequate size, before the sump pit shall also be provided so that water without heavy coal
particles goes into sump pump
pump pit. High and low level switches shall be provided in the sump
pump pit.
16.5.6 Service Water (SW) System
Service water connections are to be provided in conveyor galleries and tunnels at 50 meter
intervals. Adequate number of these connections shall be provided in all transfer houses
with minimum one no. at each floor. Each connection shall be provided with one (1) no. 32
NB globe valve and quick coupling. One (1) No. Hose pipe with nozzle shall be provided in
each building. Service water distribution
distribution system shall be designed considering the water
scheme and water requirement indicated in tender drawings.
16.6
CONSTRUCTION REQUIREMENT
The pumps shall be complete with drive motors, baseplate and other accessories. The
constructional features of the pump shall be as follows:
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 37 of 64
a. Pump casing may be axially or radially split. The casing shall be of robust construction.
Casing drain and vent connections shall be provided.
b. Impeller shall be made in one piece and securely keyed to the shaft. Locking device shall
be provided to prevent its loosening during all conditions of operation.
c. Wearing rings shall be of renewable type. Opposed wearing surface shall be of hardened
h
material and shall have a hardness difference of at least 50 BHN.
d. Replaceable shaft sleeves shall be provided to protect the shaft where it passes through
bearings and stuffing boxes. The end of the shaft sleeve assembly shall extend through
the packing
acking gland. Shaft sleeve shall be securely locked or keyed to the shaft to prevent
loosening or rotation. Shaft and shaft sleeves shall be machined and assembled for
concentric rotation.
e. The design of the shaft shall take into consideration the critical speed, which shall be at
least 20% away from operating speed.
f. Pump bearings shall be of antifriction type. Bearings shall be readily accessible without
disturbing the alignment of pump.
g. Packed stuffing boxes shall be of sufficient length to prevent leakage
leakage along the shaft and
shall be complete with all packing and lantern rings required.
h. Pumps shall be furnished complete with an approved type of flexible -coupling.
i. Couplings guards made of expanded metal and bolted to the base plate shall be
furnished.
j. The common base plate for pumps and motor shall be in one piece and shall be made of
fabricated steel.
cum
k. Pump speed shall be less than 1500 rpm for pumps of capacity more than 10 cum/hr.
16.6.1.3
The power, head and flow characteristics of each pump shall be suitable for parallel
operation. The Power characteristics of the pumps shall be of non overloading type.
16.6.1.4
All rotating parts of the pumps shall be statically and dynamically balanced.
16.6.1.5
16.6.1.6
Design duty point of pump shall match with the average value of
of maximum and minimum
flow rates of the pump in the stable operation zone.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 38 of 64
16.6.1.7
16.6.2
Sump Pumps
16.6.2.1
The column pipe shall serve as a housing for the line shaft and bearing and support for
bowl (casing). The line shaft bearing shall be supported from the pump column pipe.
Individual sections of column pipe shall be coupled by flanged joints. The flange outside
diameter shall not exceed the bowl outside diameter.
16.6.2.2
Casing shall house the impeller and shall be hydraulically designed to minimize radial
thrust. Further suitable sealing arrangement shall be provided to prevent the leakage of
pumped liquid into the column pipe.
16.6.2.3
The impeller shall be semi open or open (non clogging) as per standard design of the
Manufacturer. All rotating parts including the impeller shall be statically and dynamically
balanced. Impeller shall be securely fastened to the impeller shaft with keys taper
bushings or locknuts and shall be specifically designed to pass large solids or unscreened
liquids. The clearances between stationary and moving part shall be such as to allow
sustained performance without excessive maintenance.
16.6.2.4
16.6.2.5
16.6.2.6
16.6.2.7
The type of couplings for the line shaft shall be such to prevent loosening during reserve
rotation.
16.6.2.8
16.6.2.9
For meeting the sealing/lubricating water requirement, Contractor to provide seal water
pumps (2x100% capacity).
aft sleeves shall be furnished. The shaft sleeve shall be securely locked to
16.6.2.10 Replaceable shaft
shaft to prevent loosening while in operation.
16.6.2.11 Replaceable type wear rings shall be provided for casing and/or impellers wherever
applicable.
16.6.2.12 For the following accessories shall be provided for sump pumps
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 39 of 64
(i) Base plates together with foundation bolts and nuts. The base plate shall
accommodate the discharge pipe, which is to be terminated above the floor level.
(ii) Motor stool.
return valves and gate valves
valves on pump discharge lines (unless otherwise
(iii) Non-return
specifically excluded).
(iv) Lifting lugs, eye bolts etc.
(v) Pre-lubricating
lubricating tank with accessories (if necessary).
(vi) Sleeves and inserts to be embedded in concrete.
(vii) Coupling guard, if necessary
16.6.2.13 The pump shaft shall be connected to motor shaft by a heavy duty rigid/flexible coupling
or the pump shall be V-belt
V
driven.
16.6.3 PIPING, FITTINGS, VALVES AND SPECIALTIES
16.6.3.1 Piping & Fittings
(a) Material of construction of piping and fittings shall not be inferior to those given in data
sheet of this section.
(b) All piping shall be capable of withstanding the maximum pressure in the corresponding
line at the relevant temperature.
(c) In general pipe sizes 65 mm NB and larger are to be joined by butt welding and pipe work
of size 50 mm NB and below by socket welding/screwed connections. Joints at valves or
specialities shall be flanged for sizes 65 mm NB or large and screwed for sizes 50 mm NB
and below. All galvanized piping shall be joined by screwed connections.
connections. Minimum pipe
diameter selected for DS/SW/PW/Cooling Water System (along with branch pipes) shall
be 32 NB.
(d) End preparation for butt welding shall be done by machine/flame cutting. Socket weld
and preparation shall be saw/machine cut.
(e) Hangers and supports
ports shall be capable of carrying the sum of all concurrently acting
loads. They shall be designed to provide the required supporting effects and allow pipe
line movements as necessary. All guides, anchors, braces, dampers, expansion joints and
structural steel to be attached to the building/structure, trenches etc. shall be provided.
The type of hangers and components for all piping shall be selected and approval
obtained from the Owner/RITES.
Owner
(f) All piping shall be routed on ground on concrete pedestals and at road crossings, these
shall be laid through hume pipes.
16.6.3.2 Valves and Specialties
(a) Valves & Specialties shall be used to start, stop or regulate the flow. All valves/specialities
below 50 mm size (for isolation purpose) in service water/dust suppression/potable water
lines should be plug type of proven make.
(b) All valves shall be suitable for most stringent service conditions i.e. flow, temperature and
pressure under which they may be required to operate.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 40 of 64
(c) Gate/sluice valves shall be used for isolation of flow of pipe lines above 50 NB and Globe
valves shall be used for regulating the flow.
(d) Valves shall be provided with back seating bush to facilitate gland renewal during full open
operation.
(e) All gate and globe valves of size 65 NB and large shall be bolted bonnet, outside screw, rising
type with flanged ends. Valves of size 50 NB and smaller shall be with screwed ends.
(f)
(g) Material of construction of valves shall not be inferior to those given in data sheet of this
section.
(h) Globe valves shall be provided with contoured plug to have well controllability.
(i)
(j)
Non-return valves shall be swing check type. These valves will have a permanent arrow
inscription on its body to indicate direction of motion of the fluid.
All valves shall be provided with hand wheel, chain operated, extension spindle and floor
stand wherever required so that they can be easily operated either at a lower or higher
elevation as the case may be.
(k) Strainer shall be of duplex type designed with 3 way valves so that one filter can be cleaned
while the other is in operation. Suitable vent and drain valves shall also be provided. Screen
opening area shall be at least four times the pipe cross sectional area. Pressure drop in clean
conditions shall not exceed 1.5 MWC at full flow.
(l)
Bib cocks provided for potable water system shall be made of stainless steel
Page 41 of 64
impregnated tar felt. The lap joint of the felt shall be generally touched with heavy duty
bitumastic paint.
16.7
2.0
DESIGN REQUIREMENT
2.1
2.1.1
2.1.2
2.1.3
Dust Suppression
ration: Water sprayed through nozzles.
Operation:
Pumps: 2x100% for water
Spray Head
(i) Minimum No. of nozzles per spray head: 4 (Four)
(ii) Pressure at inlet: Minimum 2.5 kg/sq. cm
2.2.0
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.3.0
Sumps Pumps
(i) Type: 2x100% electric motor driven
(ii) Capacity: 50 cub.m/hr minimum with 10% margin
(iii) Head: 20% margin on computed head
2.3.1
Drain Pits: Minimum 2x2x2.5 mts. and 1 No. settling pit for slurry & high/low level
switches in drain pit.
2.3.2
2.4.0
2.4.1
2.4.2
2.4.3
Hose pipes with hose reel: One in each building of 25 mtr. Length with nozzle
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 42 of 64
3.0
CONSTRUCTION REQUIREMENTS
3.1
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.1.7
3.1.8
3.1.9
3.2.0
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
Sump Pumps
Type: Vertical, centrifugal, single stage,
stage, semi open or open (non clogging) type impeller.
Duty: Intermittent. However, to be designed for contineous operation.
Fluid to be Pumped: Sludge/Coal slurry
Suction Condition: Submerged
Pump speed (maximum): 1000 RPM
Type of coupling between pump and motor: Directly driven through flexible or rigid
coupling/V-Belt
3.2.7 Location of pump thrust bearing: In motor stool
3.2.8 Materials
(a) Casing: Alloy Cast Iron (350 BHN) (min. 2.7% Ni, 1% Cr.)
(b) Impeller: Alloy Cast Iron (350 BHN) (min. 2.7% Ni, 1% Cr.)
(c) Impeller: Shaft Stainless steel
(d) Line Shaft: EN-8
8 to BS; 970
(e) Column pipe and discharge pipe: Fabricated steel to IS: 226 (min. 6mm thick).
(f) Shaft sleeve: Hardened stainless steel to 400 BHN
(g) Base Plate: Steel to IS: 226 up to 20mm thickness and IS: 2062 over 20mm thickness.
3.2.9 Accessories Provided with the Pump
i. Lubrication and sealing water system: Yes
ii. Common base plate for Pumps and Motor and Motor stool: Yes
iii. Anchor Bolts, nuts, sleeves and inserts (which will be embedded in concrete): Yes
iv. Coupling, guards lifting lug, eye bolt, positioning Dove: Yes
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 43 of 64
3.3.4 Valves
Size > 65 NB: Bolted bonnet outside screw rising type.
i.
ii.
Size < 50 NB: Union bonnet with screwed ends for Globe valves & screwed
ends for plug valves.
3.3.5 Materials for Pipework
For sizes 200 NB and Larger: ERW carbon steel pipes to API-5LGr.B
API
minimum
thick 6.35 mm or plate fabricated and welded pipes to IS:3589, Class-2.
Class
(b) For sizes 150 NB to 65 NB: ERW carbon steel black pipes to IS:1239 (Part-I,
(Part Heavy
Class).
(Part Heavy
(c) For sizes upto 50 NB: ERW carbon steel galvanized pipes to IS:1239 (Part-I)
class.
(a)
3.3.6
(a)
(b)
(c)
(d)
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 44 of 64
(iii)
(iv)
(v)
(vi)
(e)
(f)
Bourdon
Block
Movement
: AISI 316 SS
: AISI 316 SS
: AISI 316 SS
Case and Bezel : Die cast Alum. Weather proof case stove
enameled block with screwed type inner bezel of ABS plastic
and glycerin filled.
(vii) No. of contacts : 2 NO + 2 NC
(viii) Type of contact : Adjustable throughout the range.
(ix) Degree of protection : IP. 65
Solenoid valve (to be provided with isolating valve)
(i) Type
: 2/2 way Diaphragm type pilot operated
(ii) Diaphragm : molded synthetic rubber
(iii) Body
: Forged brass / SS
(iv) Pressure : 0.5 to 20 kg/cm2
(v) Protection : Class IP 65
Flow Switch (to be provided with isolating valves)
(i) Body
: Forged steel
(ii) Extension Rod/wire
: SS-304
(iii) Sleeve and Sleeve pipe: SS-304
SS
(iv) Cover
: Die cast aluminum
(v) Max. working pressure
: 10 kg/sq.cm
(vi) Repeatability
: 0.5%
(vii)No. of contacts
: 2 NO + 2 NC
(viii)Type of contact : Adjustable throughout the range.
(ix) Protection
: class IP 65
(g)
Level Switch
(i) Type : Displacer operated magnetic type
(ii) Displacer: SS 316
(iii) Wire rope: SS 316
(iii) Spring Housing Spring and sleeve pipe: SS 316
(iv) Cover: Cast Aluminum
(v) No. of Contacts: 2 NO + 2 NC
(vi)Type of Contact: Adjustable throughout the range.
(viii)Protection: class IP 65
(h) Level gauges
(i) Type: Float type mechanical gauge with
wit arrow scale
(ii) Accuracy: (+/--) 1% of full scale range
(iii) Material of construction
(a) Float & Guide wire: 316 SS
(b) Elbows: Suitable grade of SS
(c) Housing: Mild Steel
(d) Cable fastener: SS 304
(i) Nozzles
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 45 of 64
VENTILATION SYSTEMS
17.1 GENERAL
17.1.1 INTENT OF SPECIFICATION
The specification is intended to cover design, engineering, manufacture, supply, erection,
testing and commissioning of the complete Ventilation & air conditioning systems as
specified hereinafter for the smooth and trouble free operation of plant & equipment of
Wagon tippler package.
17.1.1.1 The Contractor shall refer to the other sections enclosed to appraise himself of the work
and scope of supply of the other Contractors and shall coordinate his work with the work of
other Contractors.
17.2
GENERAL DESCRIPTION
Page 46 of 64
gain into the room, adequate no. of air changes etc. to maintain a uniform temperature and
relative humidity within the air conditioned areas.
17.3
SCOPE
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 47 of 64
Page 48 of 64
17.5.13 All fan mountings shall have adequate arrangement for vibration isolation.
non working fan shall be prevented by dampers. The dampers
17.5.14 The reverse flow through non-working
shall be made out of 18 SWG MS sheets.
17.5.15 Design duty point of the fans shall match with the average value of maximum and minimum
flow rate of the fan in the stable operation
oper
zone.
17.5.16 Filters
17.5.16.1 Metallic Filters
Metallic cleanable filters shall be provided as required. Max. air velocity considered shall be
2 m/sec.
17.5.16.2 HDPE Filters
HDPE filters should have an efficiency of 90% down to 5 microns. Velocity
Velocity across the filter
shall be limited to 2.5 m/sec.
17.5.17 High efficiency filter (for A/C purpose). Filtration efficiency shall not be less than 99.9% down
to 5 microns. Pr. drop across the filter under clean condition shall not be more than 10 mm
w.c.
Conditioning Unit
17.5.18 Packaged Air-Conditioning
PAC units shall be provided as required.
17.5.19 PAC units shall be factory tested and assembled self contained units complete with
refrigerant compressor, coils, fans, insulation and wiring. Various parts of PAC units
wherever required shall be insulated with expanded polyethylene conforming to IS:4671.
17.5.20 The PAC unit shall comprise of an evaporator (indoor air) blower section and an air cooled
condenser (outdoor air) section. Heavy gauge steel cabinet factory finished with two coats of
epoxy paint of approved colour, shall be used to house components of PAC.
17.5.21 The evaporator and condenser coils shall be arranged for direct expansion cooling and shall
be formed of aluminum fins mechanically bonded to seamless copper tubes and electrically
tinned. The inter-connecting
connecting refrigerant circuits shall comprise of multiple cylinder hermetic
compressor(s) and motor(s) with all necessary isolation valves, suction gas controlled
thermal expansion valves, with adjustable set point, sight glass, copper tubing and pipeline
ancillaries. The condenser coils shall be air cooled by propeller type fans complete with
safety guards. The condensing coils shall be suitably arranged to avoid radiant heat pick-up
pick
from solar sources.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 49 of 64
17.5.22 Condenser capacity control shall be provided by means of variable speed fans and head
pressure sensing.
17.5.23 The evaporator air blower(s) shall be centrifugal forward curved type belt driven by
individual motor(s) and suitable for the external static pressure. The fan assembly shall be
isolated from the casing by anti-vibration
anti vibration mounts. The fan/motor drive shall be capable of
capacity adjustment by pulley changes within +15% of design duty.
17.5.24 High efficiency filters shall be provided
provided in the main supply air duct and in the fresh air
connection to return air duct.
17.6
Construction Requirements
17.6.1 General construction details of various equipment under Contractors scope shall be as
elaborated in subsequent clauses below.
17.6.2 Roof Ventilators and accessories
Roof ventilators and accessories shall be provided as required.
17.6.3 Impeller shall be axial flow type, cast in one piece finished all over and carefully dynamically
balanced after final assembly. All impellers shall consist of high efficiency aerofoil blades.
Impellers shall be mounted directly on the motor shaft.
17.6.4 Casing shall be of heavy gauge construction and shall be properly reinforced for rigidity.
Access door with suitable locking arrangement
arrang
shall be provided.
17.6.5 Hood shall be of hinged type providing easy access to motor and impeller. It will also protect
them from rain and any other contingencies. Weather-proof
Weather proof lockable type disconnect switch
shall be provided such that the hoods can be opened only when the disconnect switch is in
OFF positions. On larger sizes of roof ventilators, hoods shall be of split construction. 15
mm mesh galvanised bird screen shall be provided. The hoods will have low pressure drop
across it.
17.6.6 Suitable
uitable arrangement shall be provided for mounting the roof ventilators such that ingress
of rainwater into the building will be avoided completely.
17.6.7 Axial Flow Fans
Axial flow fans shall be provided as required.
17.6.8 Impellers shall be axial flow
flow type and single piece cast aluminum with aerofoil blades
construction. It shall be finished all over and balanced dynamically. Impeller shall be
mounted directly on the motor shaft.
17.6.9
Casing shall be of heavy gauge construction properly reinforced for rigidity. It shall be
provided with suitable supports. Access door shall be provided in the casing for easy access
to motor and impeller. Suitable arrangement for mounting of motor shall be provided.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 50 of 64
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 51 of 64
The media of the filter shall be made from either special synthetic non-woven
non
bond fiber
design or made from micro fiber glass media. It shall be supported with GI wire mesh or
aluminum mesh and shall be housed in an aluminum sheet frame. It shall be of washable
type several times.
17.6.21 Package A/C Unit
.22 A separate cubicle shall be provided within the overall casing to house the thermostatic
17.6.22
controls, which shall be electric/electronic solid state, prewired and tested. The refrigerant
system shall be protected by pressure limiting devices, electric and thermal overloads and
unloading facilities to provide the required control range tolerances. A low voltage room
thermostat shall be provided for wall mounting. The casing shall be fitted with all necessary
coil drains and service connections/
entries.
17.. 6.23 PAC (duty/standby) units shall be selected manually and be ON/OFF switched. The units
shall be fully packaged and incorporate integral room air sensing control thermostats and
manufacturers work fitted safety interlocks. All controls shall be prewired
prewir to unit mounted
control/power terminal boxes.
17.6.24 Ventilation and Air Conditioning system ducting
17.6.25 All GI sheet metal ductwork required for ventilation and air conditioning system shall be
furnished by the supplier. All ducts and plenums unless otherwise noted shall be constructed
out of standard quality galvanised steel sheet. All sheet metal ducts shall be fabricated and
installed in conformity to the requirements of IS:655. Steel supports for the ductwork shall
be furnished as required. The thickness of ducting steel shall be 1 mm min. For ducting with
large size exceeding 1300 mm it shall be 1.25 mm. The flexible connection between fan and
ducting shall be on Teflon impregnated canvas. The zinc coating on GI sheet shall be 275
gm/cm2.
17.7
Mech. Ventilation System: To provide ventilation using fans for specified areas.
No. of air changes per hour
(a) For overground building: Not less than 10 supply air changes & 7 Exhaust air
changes
(b) For underground areas: Not less than 15 supply air changes & 7 Exhaust air changes
1.1.2 Equipment
(1) Underground tunnel: Centrifugal fans/Axial Fans
(2) All other places: Axial fans, roof ventilators
1.2.0 Pressurised ventilation
ventilation system: To provide clean air to all MCC / Switchgear buildings
1.2.1 No. of air changes per hour: Not less than 20
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 52 of 64
Page 53 of 64
Page 54 of 64
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 55 of 64
r) Suitable access staircase with safety hand railing shall be provided to all floors of junction
houses.
s) Wall sheeting shall generally start from the lowest working floor and extend up to roof level
with louvers at each
h floor level to ensure adequate natural ventilation.
t) Monorails for maintenance hoists shall be provided for maintenance and repair of various
equipments located on the floors.
18.2 Components of structures
a) Gallery Trusses and Roof
Gallery truss shall be of latticed type construction. The trusses shall be adequately braced at
top and bottom chord level to transfer the horizontal wind forces to end portals.
b) Stringer Beam
These beams shall be suitably spaced to support the conveyor stringer supports and shall
transfer load to gallery. Walkways on either side of the conveyor shall also be supported on
these stringer beams.
c) Supporting Trestles
Intermediate trestles shall be two legged and shall deliver loads from gallery trusses to the
foundations. In addition, four legged trestles shall be provided which will act as fixed support
to transmit all longitudinal forces between expansion block, in addition to other forces.
d) Junction Houses
layout as well as equipment
i) Floors - Floor beam layout shall be arranged to suit equipment layout
anchoring system.
ii) Columns - In addition to loads from floor and roof, columns shall be designed to transmit
horizontal load due to belt tension/snapping of belts to the foundation.
e) Belt Tensioning Device
belt tensioning device which may be
Suitable structures shall be provided to accommodate belt-tensioning
located either under the conveyor gallery or in the junction house itself.
f)
(i)
(ii)
Wall Structures
Wall runners with necessary sag rods shall be provided to support wall sheeting in
conveyor galleries and junction houses.
Walls shall be provided with louvers and translucent sheeting at appropriate levels,
to provide natural ventilation and lighting.
Page 56 of 64
Page 57 of 64
18.3
b)
In absence of specified dynamic factor to be considered for the load from the belt
conveyor, a dynamic factor of not less than 1.3 shall be considered for the design of
floor beams and gallery girders.
Gallery trusses and stringers as well as floor beams
beams of junction house shall be checked
for obviating occurrence of resonance and shall be designed such that the ratio of
applied frequency to natural frequency shall not lie within the range 0.7 to 1.5.
c)
d)
e)
The contractor after the award of work shall submit design criteria to owner /
consultant for approval before
befo submission of design drawings.
f)
The design drawings shall be submitted in complete for a unit along with design
calculations both in hard copy and soft copy. Design shall be done using STAAD.
g) The effective ratio of utility of all main sections shall be limited to 0.85
h) Structural schematic general arrangement with plans at various levels, elevations along
each row and axes, sections, considered loads and load diagrams with location etc. and
Structural design drawings with BOQ and Table of members
members containing design forces shall
be submitted for Owners/Consultants approval. However the approval shall be limited
to checking of overall dimensions, general stability of system, effective load transfer and
deflection limits etc. The approval shall not relieve the contractor of his responsibility of
correctness in design, adequacy of connections, accuracy etc.
i) Submission of Stability certificate for all the steel structures is under the scope of the
contractor.
18.4
Unless specified otherwise hereinafter, all the live loads shall be considered in
accordance with IS: 875 (Part-2)
(Part -1987.
Wind loads shall be considered in accordance with IS: 875 (Part-3)-1987.
(Part 1987.
Seismic loads shall be considered in accordance
accordance with IS:1893(part1)-2002
IS:1893(part1)
and
1893(part 4)-2005
Live loads from conveyor on the gallery floor shall be as per conveyor suppliers load
data.
While designing the fixed support/rigid trestles in an expansion block of conveyor
gallery the following loads (in addition to wind load) shall be considered.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 58 of 64
(i) Forces due to difference in frictional resistance of top and return idle rollers of
conveyor.
(ii) Forces due to inertia of rollers at the time of starting of conveyor belt.
(iii) Break down load caused by snapping of belt
belt (in case of multiple conveyors,
snapping of one belt at a time) shall be considered.
(iv) Special loads if any
f)
Gallery girders and floor shall be designed for the following live loads,inclusive of
spillage loads on floors.
i) Walkway/Supporting beams for floor - 4.0 KN/m
ii Under the conveyor belt - 0.75 KN/m
iii) Gallery girder, for floor load of - 3.0 KN/m
g)
Dust load on roof of junction house and conveyor galleries shall be considered as
follows:
i. For building and structures located at a distance of 300m from the dust
producing units - 0.5 KN/m
ii. At a distance of 300 m to 800 m from the dust producing unit - 0.25 KN/m
As per technological requirements, provision of supporting the following, and load
arising thereof shall be considered in the design of conveyor gallery.
i) Ventilation duct.
ii) Electrical cables/cable racks.
iii) Fire Fighting equipment.
Junction house floors shall be designed for the following loads:
i) Live load on floor - 5.0 KN/m
ii) Tension from conveyor belt
ii) Load duee to equipment located on floor.
iv) Load due to jamming of chutes.
v) Erection loads anywhere on the floor.
h)
i)
18.5
j)
Combination of loads
The various loads specified shall be combined in accordance with clause 8.0 of IS: 875
(Part-5)-1987
1987 to give the most severe loading condition for design of structures.
k)
Stress enhancements
Permissible limits of stress may be increased, wherever permissible, in accordance with
IS:800-1984.
Limiting deflection
a.
b.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 59 of 64
i)
ii)
iii)
18.6
Gallery Trusses
Top of End portal of gallery truss
Traverse deflection of top of Trestle
Span / 400
H / 325 where H =Height of portal above beams
H/1000 where H = Height of trestle above foundation
18.6.1 Drawings
The Contractor shall prepare fabrication drawings, erection drawings, bill of materials,
drawing office despatch lists / shipping documents, schedule of bolts and nuts and as built
drawings. All drawing work shall be in metric system and all writing work shall be in English.
The work shall be carried out as described in General Technical Specifications for structural
s
works.
18.6.2 Material of Construction
18.6.2.1All steel and other materials used for steelwork and in association with steelwork shall
conform to appropriate Indian standards. Only tested materials shall be used unless written
authority is obtained for the use of untested materials for certain secondary structural
members.
Unless otherwise specified in the drawings
i.
All rolled sections and plates upto 20 mm thk. Shall conform to Grade-E250
Grade
& quality
A of IS: 2062-2006
2006 and shall generally be of tested quality.
ii.
Plates above 20 mm thk. and plated structures subjected to dynamic loading shall
conform to Grade-E
Grade 250 & quality B as per IS: 2062-2006.
iii.
For High Tensile steel requirements, material conforming to IS: 8500 or SAILSAIL MA
(HYA or HYB) shall be used.
18.6.2.2
18.6.2.3
18.6.2.4
18.6.2.7
18.6.2.8
Steel tubes for structural purpose shall conform to IS: 1161 (of Grade Yst 240)
Corrugated Galvanised Sheets shall conform to IS: 277 with appropriate Zinc coating for
the selected thickness of sheet on roof and sides. (1.0mm thk for roof and 0.8mm thk for
sides)
Aluminium industrial troughed sheets conforming to IS: 1254 shall be used as follows:
i) On roof - 0.91mm thick ii) On side walls - 0.71mm thick
Translucent sheets shall be fibre glass reinforced polyester sheets of matching profile as
per IS: 12866.
Colour coated sheets shall be as per appropriate standard.
Gutters shall be of copper bearing steel conforming to Grade "A" as per IS:2062.
18.6.2.9
18.6.2.5
18.6.2.6
18.6.2.10 All black bolts, nuts and locknuts shall conform to IS: 1363 and IS: 1364 (for precision and
semi precision hexagonal bolts) of property class 6.4unless otherwise specified. Washers
shall conform to IS: 6610
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 60 of 64
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 61 of 64
e)
f)
g)
h)
i)
j)
k)
l)
m)
n)
o)
i) Removal of bends, kinks, twists, etc. for parts damaged during transportation and
handling;
ii) Cutting chipping, filing, grinding, etc., if required, for preparation and finishing of site
connections;
iii) Reaming for use of next higher size bolt for holes which do not register or which are
damaged.
iv) Welding of connections in place of bolting
bolting for which holes are either not drilled at all or
wrongly drilled during fabrication.
Other rectification work such as
i) Re-fabrication
fabrication of parts, damaged beyond repair during transportation and handling or
incorrectly fabricated.
ii) Fabrication of partss omitted during fabrication by oversight or subsequently found
necessary.
drilling of holes which do not register and which cannot be reamed
iii) Plug-welding and re-drilling
for use of next higher size bolt.
Fabrication of minor items/missing items or such important
important items as directed by the Owner /
Consultant.
Assembly at site of steel structural components wherever required including temporary
supports and staging.
Making arrangements for and providing all facilities for conducting ultrasonic X-ray
X
or
gamma ray tests on welds; getting the tests conducted by reputed testing laboratories,
making available test films/ graphs,reports and interpretation.
Rectifying at site, damaged portions of shop primer by cleaning and touchup paint.
Erection of structures including making connections by bolts/high strength friction grip bolts
/ welding.
Alignment of all structures true to line, level plumb and dimensions within specified limits of
tolerances as per IS :12843 Tolerance for Erection of Steel Structures.
Application of second coat of primer paint and two coats of finishing paint at site after
erection.
Grouting of all column bases after proper alignment of columns and only after obtaining
clearance from Owner / Consultant.
Conducting preliminary acceptance and final acceptance
a
tests.
Preparation of as built drawings, preparing of sketches/drawings to suit
field engineering decisions, availability of material, convenience of fabrication,
transportation and erection and changes during fabrication and erection.
All such works are subject to approval by the Owner / Consultant.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 62 of 64
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 63 of 64
shall not be done in foggy weather. During application, paint agitation must be provided
where such agitation is recommended by the manufacturer.
Painting shall be applied at painting manufacturer's
manufacturer's recommended rates. The number of
coats shall be such that minimum dry film thickness specified is achieved. The dry film
thickness (DFT) of painted surfaces shall be checked with ELCOMETER or measuring gauges
to ensure specified DFT.
All structures shall receive one coats of primer paint at shop after fabrication before
despatch after surface preparation has been done as per requirements.
Unless otherwise specified all structures after erection shall be given one coat of primer and
two coats of finishing
shing paint of approved colour and quality. The under coat shall have
different tint to distinguish the same from the finishing coat.
The proposed make, quality and shade of paint shall have the approval of Purchaser /
Consultant.
Technical Specification:Sec-4,System
System Parameters, Operation & Control Philosophy
Page 64 of 64
SECTION 5
1.0
INTRODUCTION
This part covers technical requirements which will form an integral part of the Contract. The
following provisions shall supplement all the detailed technical requirements brought out in
the Technical Specifications and the Technical Data Sheets.
2.0
BRAND NAME
Whenever a material or article is specified or described by the name of a particular brand,
b
manufacturer or vendor, the specific item mentioned shall be understood to be indicative of
the function and quality desired, and not restrictive; other manufacturer's products may be
considered provided sufficient information is furnished to enable the Employer to determine
that the products proposed are equivalent to those named.
3.0
COMPLETENESS OF FACILITIES
3.1
Contractors may note that this is a contract inclusive of the scope as indicated elsewhere in
the specification. Each of the plant shall
shall be engineered and designed in accordance with the
specification requirement. All engineering and associated services are required to ensure
that a completely engineered plant is provided.
3.2
All equipments furnished by the Contractor shall be complete in every respect, with all
mountings, fittings, fixtures and standard accessories normally provided with such
equipment and/or those needed for erection, completion and safe operation & maintenance
maintenan
of the equipment and for the safety of the operating personnel, as required by applicable
codes, though they may not have been specifically detailed in the respective specifications,
unless included in the list of exclusions. All similar standard components/
components/ parts of similar
standard equipment provided, shall be interchangeable with one another.
4.0
4.1
In addition to the codes and standards specifically mentioned in the relevant technical
specifications for the equipment / plant / system,
system, all equipment parts, systems and works
covered under this specification shall comply with all currently applicable statutory
regulations and safety codes, including the following:
a. Bureau of Indian Standards (BIS)
b. Indian electricity act
c. Indian electricity
city rules
d. Indian Explosives Act
e. Indian Factories Act and State Factories Act
f. Indian Boiler Regulations (IBR)
g. Regulations of the Central Pollution Control Board, India
h. Regulations of the Ministry of Environment & Forest (MoEF), Government of India
Page 1 of 27
i. Pollution
n Control Regulations of Department of Environment, Government of India
j. State Pollution Control Board.
k. Rules for Electrical installation by Tariff Advisory Committee (TAC).
l. Guideline for wagon tippler G33 Rev.01 of May 2010.
m. Any other statutory codes / standards / regulations, as may be applicable.
4.2
Unless covered otherwise by Indian codes & standards and in case nothing to the contrary is
specifically mentioned elsewhere in the specifications, the latest editions (as applicable as
on date of bid opening),
pening), of the codes and standards given below shall also apply:
(a.) Japanese Industrial Standards (JIS)
(b.) American National Standards Institute (ANSI)
(c.) American Society of Testing and Materials (ASTM)
(d.) American Society of Mechanical Engineers (ASME)
(e.) American Petroleum Institute (API)
(f.) Standards of the Hydraulic Institute, U.S.A.
(g.) International Organisation for Standardization (ISO)
(h.) Tubular Exchanger Manufacturer's Association (TEMA)
(i.) American Welding Society (AWS)
(j.) National Electrical Manufacturers Association (NEMA)
(k.) National Fire Protection Association (NFPA)
(l.) International Electro-Technical
Electro
Commission (IEC)
(m.) Expansion Joint Manufacturers Association (EJMA)
(n.) Heat Exchange Institute (HEI)
4.3
In thee event of any conflict between the codes and standards referred to in the above
clauses and the requirement of this specification, the requirement of Technical Specification
shall govern.
4.4
4.5
4.6
4.6.1
Design of Facilities
All thee design procedures, systems and components proposed shall have already been
adequately developed and shall have demonstrated good reliability under similar conditions
elsewhere. The Contractor shall be responsible for the selection and design of appropriate
appropria
Page 2 of 27
4.7.1
Contractors may note that this is a contract inclusive of the scope as indicated elsewhere in
the specification. Each of the plant and equipment shall be fully integrated, engineered and
designed to perform in accordance with the technical specification. All engineering and
technical services required ensuring a completely engineered plant shall be provided in
respect of mechanical, electrical, control & instrumentation, civil & structural works as per
the scope. The Contractor shall
shall furnish engineering data/drgs. in accordance with the
schedule of information as specified in Technical Specification and data sheet.
4.7.2
4.7.3
The documentation that shall be provided by the Contractor is indicated in the various
sections of specification. This documentation shall include but not be limited to the
following :
4.8
INSTRUCTION MANUALS
The Contractor shall submit to the Employer, Instruction Manuals for all the equipments
covered under the Contract. The Instruction manuals shall contain full details required for
erection, commissioning, operation and maintenance of each equipment. The manual
ma
shall
be specifically compiled for this project. The Instruction Manuals shall comprise of the
following.
4.8.1
Erection Manuals
The erection manuals shall be submitted prior to the commencement of erection activities
of particular equipment/system.
equipment/system. The erection manual should contain the following as a
minimum.
a) Erection strategy.
b) Sequence of erection.
c) Erection instructions.
d) Critical checks and permissible deviation/tolerances.
e) List of tool, tackles, heavy equipments like cranes, dozers, etc.
f) Bill of Materials
g) Procedure for erection.
h) General safety procedures to followed during erection/installation.
Page 3 of 27
4.8.3
4.8.4
DRAWINGS
(a.) All documents submitted by the Contractor for Employer's review shall be in electronic
form (soft copies) along with the number of hard copies. The soft copies to be supplied
shall be either in CDs, or through direct transfer via E-mail,
E mail, etc. depending upon the
nature/volume/size of the document. The drawings submitted for approval could be in
the Image form.
Page 4 of 27
(b.) Final copies of the approved drawings shall be submitted in vector form on CDROM
along with the requisite number of hard copies.
(c.) All documents/text information shall be in latest version of MS Office.
(d.) All drawings submitted by the Contractor including those submitted at the time of bid
shall be in sufficient detail indicating the type, size, arrangement, weight of each
component for packing and shipment, the external connection, fixing arrangement
arrangeme
required, the dimensions required for installation and interconnections with other
equipments and materials, clearance and spaces required between various portions of
equipment and any other information specifically requested in the drawing schedules.
(e.) Each
ach drawing submitted by the Contractor (including those of sub-vendors)
sub vendors) shall bear a
title block at the right hand bottom corner with clear mention of the name of the
Employer, the system designation, the specifications title, the specification number, the
th
name of the Project, drawing number and revisions. If standard catalogue pages are
submitted the applicable items shall be indicated therein. All titles, notings, markings
and writings on the drawing shall be in English. All the dimensions should be in metric
m
units.
sub vendors) shall bear Employers
(f.) The drawings submitted by the Contractor (or their sub-vendors)
drawing number in addition to contractors (their sub-vendors)
sub vendors) own drawing number.
Employers drawing numbering system shall be made available to the successful
succe
Contractor so as to enable him to assign Employers drawing numbers to the drawings
to be submitted by him during the course of execution of the Contract.
(g.) The Contractor shall also furnish a Master Drawing List which shall be a
comprehensive list of all drawings/ documents/ calculations envisaged to be furnished
by him during the detailed engineering to the Employer in line with engineering
information flow schedule (to be tied up with successful Contractor). Such list should
clearly indicate the purpose
purpose of submission of these drawings i.e. FOR APPROVAL or
FOR INFORMATION ONLY.
(h.) Similarly, all the drawings/ documents submitted by the Contractor during detailed
engineering stage shall be stamped FOR APPROVAL or FOR INFORMATION prior to
submission.
(i.) The furnishing of detailed engineering data and drawings by the Contractor shall be in
accordance with the time schedule for the project. The review of these documents/
data/ drawings by the Employer will cover only general conformance of the data/
drawings/
awings/ documents to the specifications and contract, interfaces with the
equipments provided by others and external connections & dimensions which might
affect plant layout. The review by the Employer should not be construed to be a
thorough review of all dimensions, quantities and details of the equipments, materials,
any devices or items indicated or the accuracy of the information submitted. The
review and/ or approval by the Employer / Project Manager shall not relieve the
Contractor of any of his responsibilities
responsibilities and liabilities under this contract.
(j.) After the approval of the drawings, further work by the Contractor shall be in strict
accordance with these approved drawings and no deviation shall be permitted without
the written approval of the Employer.
Employe
Page 5 of 27
(k.) All manufacturing, fabrication and execution of work in connection with the equipment
/ system, prior to the approval of the drawings, shall be at the Contractors risk. The
Contractor is expected not to make any changes in the design of the equipment
/system,
system, once they are approved by the Employer. However, if some changes are
necessitated in the design of the equipment/ system at a later date, the Contractor may
do so, but such changes shall promptly be brought to the notice of the Employer
indicating the reasons for the change and get the revised drawing approved again in
strict conformance to the provisions of the Technical Specification.
(l.) Drawings shall include all installations and detailed piping and wiring drawings.
(m.) Assessing & anticipating the requirement
requirement and supply of all piping and equipment shall
be done by the contractor well in advance so as not to hinder the progress of piping &
equipment erection, subsequent system charging and its effective draining & venting
arrangement as per site suitability.
suita
(n.) Any software used by the contractor shall be given to the project manager and
concerned engineer of employer. The contractor shall make the engineer of the
employer aware of the programme. Any computer aided programme shall be approved
subject to giving entire detail to the project manager.
(o.) Drawings must be checked by the Contractor in terms of its completeness, data
adequacy and relevance with respect to Engineering schedule prior to submission to
the Employer. In case drawings are found to be submitted
submitted without proper endorsement
for checking by the Contractor, the same shall not be reviewed and returned to the
Contractor for re-submission.
submission. The contractor shall make a visit to site to see the existing
facilities and understand the layout completely
completely and collect all necessary data /
drawings at site which are needed as an input to the engineering. The contractor shall
do the complete engineering including interfacing and integration of all his equipment,
systems & facilities within his scope of work as well as interface engineering &
integration of systems, facilities, equipment & works under Employers scope and
submit all necessary drawings/ documents for the same.
(p.) All drawings shall be reviewed and approved by Engineering coordinator, including the
following drawings / data which require specific approval.
1. Data sheets for various equipments / systems.
2. Field testing procedures for various equipment and piping system.
3. Pre commissioning / commissioning procedures including flushing, Chemical
cleaning,
g, steam blowing and hydro test etc. (Wherever applicable) O&M manual
shall also be reviewed and approved by Employer. The content of O&M manual
shall be as specified elsewhere in the specification.
4. Guarantee test procedures.
5. Any other drawings that may be required by the Engineer from time to time.)
6. Data furnished in the bid shall be binding on the contractor even if superior to
the technical specification requirement and any revision shall be done with the
owner/RITES
/RITESs agreement.
Page 6 of 27
(q.) The Contractor shall submit adequate prints of drawing / data / document for
Employers review and approval. The Employer shall review the drawings and return
one (1) copy to the Contractor authorizing either to proceed with manufacture or
fabrication, or marked to show changes
changes desired. When changes are required, drawings
shall be re-submitted
submitted promptly, with revisions clearly marked, for final review. Any
delays arising out of the failure of the Contractor to submit/rectify and resubmit in time
shall not be accepted as a reason for delay in the contract schedule
(r.) Upon review of each drawing, depending on the correctness and completeness of the
drawing, the same will be categorised and approval accorded in one of the following
categories :
CATEGORY I Approved
CATEGORY II Approved subject to incorporation of comments/ modification as
noted. Resubmit revised drawing incorporating the Comments
CATEGORY III Not approved. Resubmit revised drawings for approval after
incorporating comments/modification as noted.
CATEGORY IV For information
informat
and records.
(s.) Vendor shall resubmit the drawings approved under Category II and III within three (3)
weeks of receipt of comments on the drawings, incorporating all comments. Every
revision of the drawing shall bear a revision index wherein such revisions
revisio shall be
highlighted in the form of description or marked up in the drawing identifying the same
with relevant revision Number enclosed in a triangle (eg. 1, 2, 3 etc).
In case Vendor does not agree with any specific comment, he shall furnish the
explanation for the same to owner / consultant for consideration. In all such cases
vendor shall necessarily enclose explanations along with the revised drawing (taking
care of balance comments) to avoid any delay and/or duplication in review work.
It is responsibility of the Vendor to get all the drawings approved in the Category I
& IV (as the case may be) and complete engineering activities within the agreed
schedule. Any delay arising out of submission and modification of drawings shall
not alter the contract
ontract completion schedule. Vendor shall not make any changes in
the portions of the drawing other than those commented upon. If changes are
required to be made in the portions already approved, the vendor shall resubmit
the drawing identifying the changes
change for owner/RITESs
s review and approval.
(t.) If Vendor fails to resubmit the drawings as per the schedule, construction work at site
will not be held up and work will be carried out on the basis of comments furnished on
previous issues of the drawing. These comments
comments will be taken care by the contractor
while submitting the revised drawing.
(u.) All engineering data submitted by the Contractor after final process including review
and approval by the Project Manager/ Employer shall form part of the contract
documentss and the entire works covered under these specification shall be performed
in strict conformity with technical specifications unless otherwise expressly requested
by the Project Manager in writing.
Page 7 of 27
4.9
4.9.1
Page 8 of 27
FAX : TELEPHONE :
ORDINATOR (NALCO SC)
NALCO- SITE CO-ORDINATOR
Name :
Designation :
Address :
a) Postal :
b) Telegraphic :
TELEX :
FAX : TELEPHONE :
4.9.2
Page 9 of 27
by the Engineer shall not relieve the contractor of any of his responsibilities or liabilities
under the contract.
4.9.4
Erection Drawings
(a) Contractor shall furnish erection drawings for the guidance of his/ RITESs site staff at
least 4 weeks before scheduled commencement of erection or the first shipment,
whicheverr is earlier. These shall generally comprise of fabrication/assembly drawings,
various component/part details drawings, assembly, clearance, data requirements etc.
The drawings shall contain details of components/ equipment with identification
numbers, match
ch marks, bills of materials, assembly procedures etc.
(b) For all major equipment apart from above details, assembly sequence and instructions
with check lists shall be furnished in the form of erection manuals CLAUSE NO.
4.9.5
4.9.6
TECHNICAL CO-ORDINATION
ORDINATION MEETING
(a) The Contractor shall be called upon to organise and attend monthly Design/ Technical
Co-ordination
ordination Meetings (TCMs) with the owner/owners representatives and other
Contractors of the Employer during the period of contract. The Contractor shall attend
such meetings at his own cost as and when required and fully co-operate
co
with such
persons and agencies involved during the discussions.
(b) The Contractor should note that Time is the essence of the contract. In order to expedite
the early completion of engineering activities, the Contractor shall submit all drawings as
per the agreed Engineering Information Submission Schedule. The drawings submitted
by the Contractor will be reviewed by the Employer as far as practicable
practica within three (3)
weeks from the date of receipt of the drawing .The comments of the Employer shall
then be discussed across the table during the above Technical Co-ordination
Co ordination Meeting (s)
wherein best efforts shall be made by both sides to ensure the approval
approval of the drawing.
(c) The Contractor shall ensure availability of the concerned experts / consultants/
personnel who are empowered to take necessary decisions during these meetings.
(d) Should any drawing remain unapproved for more than one (1)) weeks after its first
submission, this shall be brought out in the monthly Engineering Progress and Exception
Report with reasons thereof.
(e) Any delays arising out of failure by the Contractor to incorporate Employers comments
and resubmit the same during the TCM shall
shall be considered as a default and in no case
shall entitle the Contractor to alter the Contract completion date.
Page 10 of 27
EQUIPMENT BASES
A cast iron or welded steel base plate shall be provided for all rotating equipment which is to
be installed on a concrete base, unless otherwise specifically agreed to by the Employer.
Each base plate which support the unit and its drive assembly, shall be
be of a neat design with
pads for anchoring the units.
4.9.9
PROTECTIVE GUARDS
Suitable guards shall be provided for protection of personnel on all exposed rotating and/or
moving machine parts. All such guards shall be designed for easy installation and removal for
maintenance purpose.
Page 11 of 27
Each main and auxiliary item of plant including instruments shall have permanently attached
to it in a conspicuous position, a rating plate of
o non-corrosive
corrosive material upon which shall be
engraved manufacturers name, equipment, type or serial number together with details of
the ratings, service conditions under which the item of plant in question has been designed
to operate.
Each item of plantt shall be provided with nameplate or label designating the service of the
particular equipment.
Such nameplates or labels shall be of white non hygroscopic material with engraved black
lettering or alternately, in the case of indoor circuit breakers, starters,
starters, etc. of transparent
plastic material with suitably coloured lettering engraved on the back. The name plates shall
be suitably fixed on both front and rear sides.
Items of plant such as valves, which are subject to handling, shall be provided with an
engraved chromium plated nameplate or label with engraving filled with enamel..
All segregated phases of conductors or bus ducts, indoor or outdoor, shall be provided with
coloured phase plates to clearly identify the phase of the system
4.9.14 TOOLS AND TACKLES
The Contractor shall supply with the equipment one complete set of all special tools and
tackles and other instruments required for the erection, assembly, disassembly
disassembly and proper
maintenance of the plant and equipment and systems (including software). These special
tools will also include special material handling equipment, jigs and fixtures for maintenance
and calibration / readjustment, checking and measurement
measurement aids etc. A list of such tools and
tackles shall be submitted by the Contractor alongwith the offer. The price of each tool /
tackle shall be deemed to have been included in the total bid price. These tools and tackles
shall be separately packed and sent
sent to site. The Contractor shall also ensure that these tools
and tackles are not used by him during erection, commissioning and initial operation. For
this period the Contractor should bring his own tools and tackles. All the tools and tackles
shall be off reputed make acceptable to the Employer.
4.9.15 Welding
If the manufacturer has special requirements relating to the welding procedures for welds at
the terminals of the equipments to be per formed by others the requirements shall be
submitted to the Employer in advance of commencement of erection work.
4.9.16 COLOUR CODE FOR ALL EQUIPMENTS/ SERVICES
All equipment/ services are to be painted by the Contractor in accordance with Employers
standard colour coding scheme, which will be furnished to the Contractor during detailed
engineering stage.
4.10
Page 12 of 27
4.10.1 PROTECTION
All coated surfaces shall be protected against abrasion, impact, discoloration and any other
damages. All exposed threaded portions shall be suitably protected with either metallic or a
nonmetallic protection device. All ends of all valves and pipings and conduit equipment
connections shall be properly sealed with suitable devices to protect them from damage.
The parts which are likely to get rusted, due to exposure to weather, should also be properly
treated and protected in a suitable manner. All primers/paints/coatings shall take into
account the hot humid, corrosive & alkaline, subsoil or over ground environment as the case
may be.
4.10.2 Preservative Shop Coating
All exposed metallic surfaces subject to corrosion shall be protected by shop application of
suitable coatings. All surfaces which will not be easily accessible after the shop assembly,
shall be treated beforehand and protected for
for the life of the equipment. All surfaces shall be
thoroughly cleaned of all mill scales, oxides and other coatings and prepared in the shop.
The surfaces that are to be finish-painted
finish painted after installation or require corrosion protection
until installation, shall be shop painted with atleast two coats of primer. Transformers and
other electrical equipments if included shall be shop finished with one or more coats of
primer and two coats of high grade resistance enamel. The finished colors shall be as per
manufacturers
ufacturers standards, to be selected and specified by the Employer at a later date.
Shop primer for all steel surfaces which will be exposed to operating temperature below 95
degrees Celsius shall be selected by the Contractor after obtaining specific approval
ap
of the
Employer regarding the quality of primer proposed to be applied. Special high temperature
primer shall be used on surfaces exposed to temperature higher than 95 degrees Celsius and
such primer shall also be subject to the approval of the Employer.
Empl
All other steel surfaces which are not to be painted shall be coated with suitable rust
preventive compound subject to the approval of the Employer.
All piping shall be cleaned after shop assembly.
Painting for Civil structures shall be done as per relevant part of technical specification
4.11
Page 13 of 27
(a) His organisation structure for the management and implementation of the proposed
quality assurance programme
(b) Quality System Manual
(c) Design Control System
(d) Documentation and Data Control System
(e) Qualification data for Contractors key personnel.
(f) The procedure for purchase of materials, parts, components and selection of subsub
contractors services including vendor analysis, source inspection, incoming raw-material
raw
inspection, verification of materials purchased etc.
(g) System for shop manufacturing
manufacturing and site erection controls including process, fabrication
and assembly.
conforming items and system for corrective actions and resolution of
(h) Control of non-conforming
deviations.
(i) Inspection and test procedure both for manufacture and field activities.
(j) Control of calibration and testing of measuring testing equipment.
(k) System for Quality Audits.
(l) System for identification and appraisal of inspection status.
(m) System for authorising release of manufactured product to the Employer.
(n) System for handling, storage and delivery.
(o) System for maintenance of records, and
(p) Quality plans for manufacturing and field activities detailing out the specific quality
control procedure adopted for controlling the quality characteristics relevant to each
item of equipment/component.
4.12
4.12.1 All materials, components and equipment covered under this specification shall be
procured, manufactured, erected, commissioned and tested at all the stages, as per a
comprehensive Quality Assurance Programme.
Programme. An indicative programme of inspection/tests
to be carried out by the contractor for some of the major items is given in the respective
technical specification. This is, however, not intended to form a comprehensive programme
as it is the contractors responsibility to draw up and implement such programme duly
approved by the Employer. The detailed Quality Plans for manufacturing and field activities
shall be drawn up by the Contractor and will be submitted to Employer for approval.
Schedule of finalisation
ation of such quality plans will be finalised before award. Monthly
progress reports on MQP/FQP submission/approval shall be furnished on enclosed format
No. QS-01-QAI-P-02/F1.
e
various
4.12.2 Manufacturing Quality Plan will detail out for all the components and equipment,
tests/inspection, to be carried out as per the requirements of this specification and
standards mentioned therein and quality practices and procedures followed by Contractors/
Sub-contractors/ sub-supplier's
supplier's Quality Control Organisation,
Organisation, the relevant reference
documents and standards, acceptance norms, inspection documents raised etc., during all
stages of materials procurement, manufacture, assembly and final testing/performance
testing. The Quality Plan shall be submitted on electronic media e.g. floppy or E-mail
E
in
addition to hard copy, for review and approval. After approval the same shall be submitted
in compiled form on CD--ROM.
Technical Specifications: Sec-5,General Techn
chnical Requirements
Page 14 of 27
4.12.3 Field Quality Plans will detail out for all the equipment, the quality practices and procedures
etc.
tc. to be followed by the Contractors "Site Quality Control Organisation", during various
stages of site activities starting from receipt of materials/equipment at site.
4.12.4 The Contractor shall also furnish copies of the reference documents/plant
standards/acceptance
ndards/acceptance norms/tests and inspection procedure etc., as referred in Quality
Plans along with Quality Plans. These Quality Plans and reference documents/standards etc.
will be subject to Employers approval without which manufacturer shall not proceed.
proce
These
approved documents shall form a part of the contract. In these approved Quality Plans,
Employer shall identify customer hold points (CHP), i.e. test/checks which shall be carried
out in presence of the Employers Project Manager or his authorised representative and
beyond which the work will not proceed without consent of Employer in writing. All
deviations to this specification, approved quality plans and applicable standards must be
documented and referred to Employer along with technical justification
justification for approval and
dispositioning.
4.12.5 No material shall be despatched from the manufacturers works before the same is
accepted, subsequent to predespatch final inspection including verification of records of all
previous tests/inspections by Employers
Employers Project Manager/Authorised representative and
duly authorised for despatch by issuance of Material Despatch Clearance Certificate (MDCC).
4.12.6 All material used for equipment manufacture including casting and forging etc. shall be of
tested quality
lity as per relevant codes/standards. Details of results of the tests conducted to
determine the mechanical properties; chemical analysis and details of heat treatment
procedure recommended and actually followed shall be recorded on certificates and time
temperature
emperature chart. Tests shall be carried out as per applicable material standards and/or
agreed details.
4.12.7 The contractor shall submit to the Employer Field Welding Schedule for field welding
activities in the enclosed format No.: QS-01-QAI-P-02/F3.
QS
The field welding schedule shall be
submitted to the Employer along with all supporting documents, like welding procedures,
heat treatment procedures, NDT procedures etc. at least ninety days before schedule start
of erection work at site.
4.12.8 All welding and brazing shall be carried out as per procedure drawn and qualified in
accordance with requirements of ASME Section IX/BS-4870
IX/BS 4870 or other International equivalent
standard acceptable to the Employer. All welding/brazing procedures shall be submitted
submitte to
the Employer or its authorized representative for approval prior to carrying out the
welding/brazing.
4.12.9 All brazers, welders and welding operators employed on any part of the contract either in
Contractors/sub-contractors
contractors works or at site or elsewhere
elsewhere shall be qualified as per ASME
Section-IX or BS-4871
4871 or other equivalent International Standards acceptable to the
Employer.
Page 15 of 27
4.12.10 Welding procedure qualification & Welder qualification test results shall be furnished to the
Employer for approval.
al. However, where required by the Employer, tests shall be conducted
in presence of Employer/authorised representative.
4.12.11 Unless otherwise proven and specifically agreed with the Employer, welding of dissimilar
materials and high alloy materials shall
sh be carried out at shop only.
4.12.12No welding shall be carried out on cast iron components for repair.
4.12.13 All the heat treatment results shall be recorded on time temperature charts and verified
with recommended regimes.
tive examination shall be performed in accordance with written procedures
4.12.14 All non-destructive
as per International Standards, The NDT operator shall be qualified as per SNT-TC-IA
SNT
(of the
American Society of non-destructive
non destructive examination). NDT shall be recorded in a report, which
whic
includes details of methods and equipment used, result/evaluation, job data and
identification of personnel employed and details of correlation of the test report with the
job. All Bar stock / forgings of diameter equal to or greater than 50mm shall be ultrasonically
u
tested. In general all plates of thickness equal to or greater than 40mm and for pressure
parts, pates of thickness equal to or greater than 25mm shall be ultrasonically tested unless
as specified otherwise in respective equipment specification.
specificati
4.12.15The Contractor shall list out all major items/ equipment/ components to be manufactured in
house as well as procured from sub-contractors.
sub
All the subcontractor proposed by the
Contractor for procurement of major bought out items including castings, forging, semisemi
finished and finished components/equipment etc., list of which shall be drawn up by the
Contractor and finalised with the Employer, shall be subject to Employer's approval. The
contractors proposal shall include vendors facilities established at the respective works, the
process capability, process stabilization, QC systems followed, experience list, etc. along with
his own technical evaluation
ation for identified sub-contractors
sub contractors enclosed and shall be submitted
to the Employer for approval within the period agreed at the time of pre-awards
pre
discussion
and identified in "DR" category prior to any procurement. Monthly progress reports on subsub
contractor
ctor detail submission / approval shall be furnished. Such vendor approval shall not
relieve the contractor from any obligation, duty or responsibility under the contract.
4.12.16For components/equipment procured by the contractors for the purpose of the contract,
after obtaining the written approval of the Employer, the contractors purchase
specifications and inquiries shall call for quality plans to be submitted by the suppliers. The
quality plans called for from the sub-contractor
sub
shall set out, during the various stages of
manufacture and installation, the quality practices and procedures followed by the vendors
quality control organisation, the relevant reference documents/standards used, acceptance
level, inspection of documentation raised, etc. Such
Such quality plans of the successful vendors
shall be finalised with the Employer and such approved Quality Plans shall form a part of the
purchase order/contract between the Contractor and sub-contractor.
sub contractor. Within three weeks of
the release of the purchase orders
orders /contracts for such bought out items /components, a
copy of the same without price details but together with the detailed purchase
specifications, quality plans and delivery conditions shall be furnished to the Employer on
Page 16 of 27
QA DOCUMENTATION PACKAGE
The Contractor shall be required to submit the QA Documentation in two hard copies and
two CD ROMs.
4.13.1 Each QA Documentation shall have a project specific Cover Sheet bearing name &
identification
ation number of equipment and including an index of its contents with page control
on each document. The QA Documentation file shall be progressively completed by the
Suppliers sub-supplier
supplier to allow regular reviews by all parties during the manufacturing. The
final quality document will be compiled and issued at the final assembly place of equipment
before despatch. However CD-Rom
CD Rom may be issued not later than three weeks.
below:
4.13.2 Typical contents of QA Documentation is as below:(a) Quality Plan
(b) Material mill test reports on components as specified by the specification and approved
Quality Plans.
Page 17 of 27
(c) Manufacturer / works test reports/results for testing required as per applicable codes
and standard referred in the specification and approved Quality Plans.
(d) Non-destructive
ructive examination results /reports including radiography interpretation
reports. Sketches/drawings used for indicating the method of traceability of the
radiographs to the location on the equipment.
(e) Heat Treatment Certificate/Record (Time(Time temperature Chart)
(f) All the accepted Non-conformance
Non conformance Reports (Major/Minor) / deviation, including
complete technical details / repair procedure).
(g) Inspection reports duly signed by the Inspector of the Employer and Contractor for the
agreed Customer Hold Points.
(h) Certificate
te of Conformance (COC) wherever applicable.
(i) MDCC
4.13.3 Similarly, the contractor shall be required to submit two sets (two hard copies and two CD
ROMs), containing QA Documentation pertaining to field activities as per Approved Field
Quality Plans and other agreed manuals/ procedures, prior to commissioning of individual
system.
4.13.4 Before despatch / commissioning of any equipment, the Supplier shall make sure that the
corresponding quality document or in the case of protracted phased deliveries, the
t
applicable section of the quality document file is completed. The supplier will then notify the
Inspector regarding the readiness of the quality document (or applicable section) for review.
If the result of the review carried out by the Inspector is satisfactory,
satisfactory, the Inspector shall
stamp the quality document (or applicable section) for release. If the quality document is
unsatisfactory, the Supplier shall endeavor to correct the incompleteness, thus allowing to
finalize the quality document (or applicable
applicable section) by time compatible with the
requirements as per contract documents. When it is done, the quality document (or
applicable section) is stamped by the Inspector. If a decision is made despatch, whereas all
outstanding actions cannot be readily cleared
cleared for the release of the quality document by
that time. The supplier shall immediately, upon shipment of the equipment, send a copy of
the quality document Review Status signed by the Supplier Representative to the Inspector
and notify of the committed date for the completion of all outstanding actions & submission.
The Inspector shall stamp the quality document for applicable section when it is effectively
completed. The submission of QA documentation package shall not be later than 3 weeks
after the despatch
spatch of equipment.
4.13.5 TRANSMISSION OF QA DOCUMENTATION
On release of QA Documentation by Inspector, one set of quality document shall be
forwarded to Corporate Quality Assurance Department and other set to respective Project
Site of Employer. For the
the particular case of phased deliveries, the complete quality
document to the Employer shall be issued not later than 3 weeks after the date of the last
delivery of equipment.
4.14
Page 18 of 27
Page 19 of 27
make modifications that may be necessary to meet the said objections or shall inform in
writing to the Project Manager/Inspector giving reasons therein, that no modifications are
necessary to comply with the
th contract.
(e) When the factory tests have been completed at the Contractors or sub-contractors
sub
works,
the Project Manager /Inspector shall issue a certificate to this effect fifteen (15) days after
completion of tests but if the tests are not witnessed by the Project Manager /Inspectors,
the certificate shall be issued within fifteen (15) days of the receipt of the Contractors test
certificate by the Project Manager /Inspector. Project Manager /Inspector to issue such a
certificate shall not prevent the Contractor
Contractor from proceeding with the works. The completion
of these tests or the issue of the certificates shall not bind the Employer to accept the
equipment should it, on further tests after erection be found not to comply with the
contract.
here the contract provides for tests whether at the premises or works of the
(f) In all cases where
Contractor or any sub-contractor,
contractor, the Contractor, except where otherwise specified shall
provide free of charge such items as labour, material, electricity, fuel, water, stores,
apparatus
pparatus and instruments as may be reasonably demanded by the Project Manager
/Inspector or his authorised representatives to carry out effectively such tests on the
equipment in accordance with the Contractor and shall give facilities to the Project
Manager/Inspector
er/Inspector or to his authorised representative to accomplish testing.
(g) The inspection by Project Manager / Inspector and issue of Inspection Certificate thereon
shall in no way limit the liabilities and responsibilities of the Contractor in respect of the
th
agreed Quality Assurance Programme forming a part of the contract.
(h) To facilitate advance planning of inspection, the Contractor shall furnish quarterly inspection
programme indicating schedule dates of inspection at Customer Hold Point and final
inspection
ion stages. Updated quarterly inspection plans will be made for each three
consecutive months and shall be furnished before beginning of each calendar month.
(i) All inspection, measuring and test equipment used by contractor shall be calibrated
periodically depending on its use and criticality of the test/measurement to be done. The
Contractor shall maintain all the relevant records of periodic calibration and instrument
identification, and shall produce the same for inspection by NALCO. Wherever asked
specifically,
ically, the contractor shall re-calibrate
re calibrate the measuring/test equipment in the presence
of Project Manager / Inspector.
4.16
Page 20 of 27
Page 21 of 27
endanger the safe operation of the equipment, shall not be considered as reasons for
with- holding the aforesaid permission
ctor shall furnish the commissioning organization chart for review & acceptance
Contractor
of employer at least eighteen months prior to the schedule date of synchronization of
1st unit. The chart should contain:
a) Experience of the Commissioning Engineers.
b) Role and responsibilities
sponsibilities of the Commissioning Organisation members.
c) Expected duration of posting of the above Commissioning Engineers at site.
GUARANTEE TESTS
(i)
4.17
(a) The final tests as to the guarantees shall be conducted at Site, by the Contractor. The
Contractor's Commissioning and start-up
start up Engineers shall make the unit ready for such
tests. Such test will be commenced, within a period of three (3) months after the
successful completion of Trial Operation. Any extension of time beyond the above three
months shall be subject to Employer's approval.
(b) These tests shall be binding on both the parties of the Contract to determine
compliance of the equipment with the performance guarantee.
(c) Any special equipment, tools and tackles required for the successful completion of the
Guarantee Tests shall be provided by the Contractor, free of cost.
cost The bidder should
particularly note that suitable and necessary method and arrangement for the PG test
for 1200TPH of the new conveyor integrating into 800 TPH of existing conveyor system
has to be made by him/them acceptable to owner/RITES at no extra cost.
(d) The guarantee figures and design/performance parameters of the equipment shall be
proved by the Contractor during these Guarantee Tests/ and or during the 'Trial
operation' as detailed
detailed out elsewhere. Should the results of these tests show any
deterioration from the guaranteed values, the Contractor shall modify the equipment as
required to enable it to meet the guarantees. In such case, the Guarantee Tests shall be
repeated and all cost
cost for modifications including labour, materials and the cost of
additional testing to prove that the equipment meets the guarantees, shall be borne by
the Contractor.
(e) The specific tests to be conducted on equipment have been brought out in the technical
specification.
4.18
Test Codes
The provisions outlined in the ASME Performance Test Codes shall be used as a guide for all
the above test procedures unless otherwise specified in the technical specifications.
4.19
TAKING OVER
Upon successful completion
completion of Initial Operations and all the tests conducted to the
Employer's satisfaction, the Employer shall issue to the Contractor a Taking over Certificate
Page 22 of 27
as a proof of the final acceptance of the equipment. Such certificate shall not unreasonably
be with held
ld nor will the Employer delay the issuance thereof, on account of minor
omissions or defects which do not affect the commercial operation and/or cause any serious
risk to the equipment. Such certificate shall not relieve the Contractor of any of his
obligations
ations which otherwise survive, by the terms and conditions of the Contract after
issuance of such certificate.
4.20
NOISE LEVEL
Page 23 of 27
The equivalent 'A' weighted sound pressure level measured at a height of 1.5 m above floor
level in elevation and at a distance of one (1) metre horizontally from the nearest surface of
any equipment / machine, furnished and installed under these specifications, expressed in
decibels to a reference of 0.0002 microbar, shall not exceed 85 dBA.
4.23
4.24
ELECTRICAL ENCLOSURE
All electrical equipments and devices, including insulation, heating and ventilation devices
shall be designed for ambient
am
temperature (500C) and a maximum relative humidity (75%).
4.25
Page 24 of 27
All instruments and control devices provided on panels shall be of miniaturized design,
suitable for modular flush mounting on panels with front draw out facility and flexible plugin connection at rear.
All electronic modules shall have gold plated connector fingers and further all input and
output modules shall be short circuit proof. These shall also be tropicalised & components
shall be of industrial grade or better.
bette
4.26
4.27
4.28
4.29
JUNCTION BOXES
The junction boxes shall be made of minimum 2 mm thick sheet steel. Gland plates shall be
removable type and made of 3 mm thick sheet steel. The boxes shall be provided with
detachable cover or hinged door with captive screws. Top of the box shall be arranged
arran
to
slope towards the rear of the box. The box shall be hot dip galvanized and shall be provided
with suitable neoprene gaskets to achieve degree of protection of IPIP-55 as per IS: 2147.
Adequate spacing shall be provided to terminate the external cables.
cables. The boxes shall be
suitable for mounting on various types of steel structures. The terminal blocks provided shall
be of 650 V grade, rated for 10 A for control cables. Suitable numbering for terminal blocks
Page 25 of 27
6.
7.
8
9
10
11
12
13
NO OF PRINTS (SETS)
(SETS)
NO. OF CDROMs
1 CD
1 CD
2 CD-ROMs
ROMs
2 CD-ROMs
ROMs
1 CD
2 CD-ROMs -
2CD ROMS
2CD ROMS
2CD ROMS
2CD ROMS
2CD ROMS
2CD ROMS
2CD ROMS
14
2 CD
15
16
Progress Reports
Project completion report
4
10
2 CD
2CD ROMS
17
18
Page 26 of 27
19
20
21
22
23
set
4 sets
2 CD ROMS
1 CD
1 CD
2 CD ROMS
2 CD ROMS
Page 27 of 27
SECTION 6
ELECTRICS FOR WAGON TIPPLER SYSTEM
1.0
1.1
1.2
1.3
Page 1 of 97
The design, manufacture, performance, testing and installation (including earthing and other
essential provisions) of equipment and accessories covered under this specification shall, in
general, comply with the latest issue of the following:
follow
Page 2 of 97
1.5
Safety
All equipment shall be complete with approved safety devices wherever a potential hazard
exists and with provision for safe access of personnel to and around equipment for
operational and maintenance
enance functions.
The design shall include not only those usually furnished with elements of machinery but also
the additional covers, staircases, ladders, etc which are necessary for safe operation of the
plant. All danger and caution notice boards shall
shall be in Hindi, English and Oriya.
The Contractor must take sufficient care in moving his construction plants and equipment
from one place to another so that those may not cause any damage to the property of the
Purchaser particularly to the overhead and underground cables and other service lines.
When the work is carried out at night or in the obscure day light, adequate arrangements for
flood lighting in the working area shall be made by the Bidder.
Bidde
The safely postures/regulations for the prevention of accidents shall be displayed by the
Bidder at appropriate places. Notices and warning signs shall be displayed for all sources of
dangers.
All electrical drives and equipment must be equipped with safety devices. The safety
provisions shall conform to the recognized standards, safety codes and statutory regulations.
All safety measures as required to be adopted as per the statutory regulations
regulati
and the safety
rules of the plant shall be strictly followed by the Contractor during the execution of the
Contract.
Adequate number of first aid boxes as defined in the State Factory Rules shall be provided and
maintained at all the work sites.
1.6
Coding/Numbering
ding/Numbering Scheme
A coding scheme for identifying the drawings, plant and equipment, structures, spares and
shipping documents shall be adopted by the contractor in a sequential manner.
1.7
Contractor's License
The contractor shall possess a valid and
and competent contractor's license of specified voltage
issued by the electrical licensing authorities of the Govt. of Orissa for carrying out electrical
installation work of the type and magnitude covered in this document, in the state of Orissa.
The contractor
ctor shall also be required to obtain labour license from Statutory Authority.
Page 3 of 97
Copy of the license shall be made available to the Purchaser/consultant for verifications during
the execution of contract.
All linemen, wiremen, electricians, supervisors and
and engineers engaged by the Bidder or his
sub-Bidder
Bidder shall possess necessary valid license issued by the statutory authority and the same
shall be submitted for verification, if called for.
1.8
2.0
SCOPE AND BRIEF DESCRIPTION OF WORK AND ELECTRICAL SYSTEM DESIGN CRITERIA
2.1
General
The scope of work includes the basic engineering, detailed design engineering, manufacture or
procurement of electrical equipment, shop testing, packing, transportation, loading, delivery
at site, unloading, storage at site, handling, erection, pre-commissioning
pre commissioning tests and
commissioning of all equipment/system including preliminary acceptance test, performance
guarantee and post commissioning services, including
including insurance cover during transit, storage,
erection and commissioning. The job shall be done on turnkey basis. Scope of Bidder shall also
include the following:
Supply of commissioning spares
Supply of mandatory spares required for one year normal O&M
Supply of special tools and tackles for the equipment/systems supplied
2.2
Bidder shall provide complete design inputs in form of assignment indicating complete
requirements of civil building to accommodate comfortably an electrical substation consisting
consistin
of electrical equipment under his scope as well as the equipment under scope of the
Purchaser, if any meeting all the required statutory clearances. The building shall be finalized
and constructed by the bidder
Bidder shall also provide the following design
design inputs for detailed design and engineering of
civil and structural works i.e. foundations, room, etc. The same shall be taken into
consideration while designing the civil buildings by the bidder:
Page 4 of 97
er shall also take into consideration of various aspects like clearances, approach, roads,
Bidder
safety exits, cable trenches, transmission lines, foundations, floor opening, inserts,
underground GI pipes, office premises, etc while finalizing the designing of civil
c installations
and building within battery limit of the package.
2.4
cope of the Bidder starts from tapping 33KV source including supply of 33KV/415KV
Scope
transformers and corresponding switchboards, bus ducts and down below all the electrical
equipments etc.
For WT System Bidder shall include complete electrics including all the equipment/services on
turnkey basis as per requirement irrespective of the same ass specified in the specification or
not. Separate set of suitable rated 33/0.44 kV transformers,
ormers, dedicated MCC for WT System
machine, PLC, UPS with sealed maintenance free batteries, VVVF drive control system,
junction boxes, other equipment, etc shall be included for smooth operation of wagon tippler
system.
Air conditioning of control room to be done with suitable capacity by air cooled packaged AC.
AC
For other LT drives and mechanism, Bidder shall include dedicated MCCs consisting of required
number and capacity of outgoing feeders.
For dry fog type dust suppression
suppression systems of transfer points in junction houses, Bidder shall
include a dedicated MCC in pump cum compressor house.
For miscellaneous and non-critical
non critical loads like power socket cabinets, ventilation, AC power
requirement of 33KV switchboard / 415V PCC
PCC / transformer marshalling boxes, etc, Bidder
shall include a dedicated PDB.
For illumination of WT System (Wagon Tippler, Apron feeder) including conveyors and
substation, dust suppression room and adjoining areas / sub areas, Bidder shall consider a
dedicated LDB and sufficient number of SLDBs. SLDB shall be timer control. Two numbers
flood light high mast towers 30m high eachshall
shall be included for illumination of WT Area with
metal Halide
lide Lamps. Illumination of street light and conveyor gallery shall be with LED lamps
within a radius of 500m of wagon tippler.
tippler
Page 5 of 97
A separate room shall be provided adjacent to WT control room to house the Dust suppression
MCC, Pumps, compressors etc for the DS System by the Bidder. Bidder shall furnish the
complete requirements
quirements including size, cable trenches/opening, etc. The pressurized ventilation
shall be provided by the Bidder in this Dust Suppression Room.
The number of MCCs / DBs shall be provided as per requirement by the bidder.
Following shall also be included
inclu
in the Bidders scope:
Pressurized ventilation system for the switchgearroom.
switchgearroom
Pressurized ventilation system for the Dust Suppression cum MCC room.
Air conditioning of battery and battery charger rooms.
Exhaust fan in the transformer rooms.
The bidderr shall supply the PLC for safe operation of WT System. Necessary integration with
existing PLC of new coal yard will be scope of tenderer.
tender . Design and installation of electrics shall
ensure operation of complete integrated electrics of the various drives/mechanism
drives/m
without
any constraint during maintenance.
Bidder shall also consider sufficient numbers of local auxiliary PDBs to cater miscellaneous
loads of WT System. These PDBs shall be located at various places and exact locations shall be
finalized duringg detailed engineering.
HT Power cables and LT power/control cables shall be laid in different cable trays. LT power
cables and LT control cables shall also be laid in different trays. 24V DC cables shall be laid
entirely in different dedicated trays.
Cable trays in single tier or in multitier shall be installed in vertical arrangement everywhere to
avert coal accumulation and space reduction. Cable trays shall be supplied by the bidder.
Power supply of all voltage levels including 415V AC or 220V DC, 24V DC etc, shall be arranged
by Bidder himself by providing suitable systems. 24V DC supply shall be through screened
cable to be supplied by the Bidder.
Only at receiving point of 33KV, control supply of 415V AC and 220V DC shall be made
available by the
he purchaser.
purchaser
Following HT cabling shall also be included by the Bidder apart from the above:
1. ACSR conductor for O/H transmission of 33kv line.
2. Cabling required for underground track/road crossings of33 kV System including intake
pump well feeder and ashpond feeder.
feeder
Standard power and control cables (Trailing Cables) of required sizes in adequate quantum
shall be supplied and terminated by the Bidder. Hence, complete HT & LT trailing cables for
Wagon Tippler, etc
tc shall be supplied and laid by the bidder.
Cables used for 24 VDC supply for PLC system shall be laid separately from 230 V AC control
cables.
Page 6 of 97
All cables Power cable, Control Cable, Trailing Cable, instrumentation cables, signal cables,
screened cables,
es, special cables, fibre optic cables shall be supplied, laid and terminated by the
Bidder as per actual site requirement.
Cabling shall include laying and termination at both ends, cable trays and cable accessories for
the cables to be laid by the Bidder.
Bidd
Bidder shall consider all required cables for cable engineering, preparation of cable schedule,
terminal plans, cable support structure layout, cable layout drawings, etc. All cable trays,
accessories, termination kits, glands, lugs, clamps including clamps, etc shall be included in the
scope for all the cables (to be supplied by the Successful Bidder) interconnecting both side
equipment or one side equipment of the Bidders scope.
All drives shall be controlled and monitored at existing WT SYSTEM control room from the PLC.
Bidder shall include PLC and all the interfacing/ interconnecting cabling and cable trays. All
Cables required for this interfacing, shall be supplied and laid by the Bidder. Copper power
cables, if required by the bidder, shall also be under scope of supply and laying of the bidder.
Ampere meters for all conveyor belts are to be installed at the control room for monitoring
the current of each drive.
Bidder shall consider numeric PLC and type of Inputs / Outputs (I/Os) required for WT system
for smooth and trouble free operation of various drives / mechanism from the WT SYSTEM
control room. Sufficient number of I/Os in PLC extension shall be considered as per actual
act
requirement. Exact number and type of I/Os shall be decided during detailed engineering
based on approved schemes.
Bidder shall also consider sufficient number of I/Os in PLC control and monitoring for electrical
power distribution system for the electrical power distribution system starting from 33KV till
the down most voltage level.
New PLC of WT shall be interfaced with existing PLC of Coal Handling Plant for operation of BC
115 and BC 103.
The earthing system shall be provided for complete
complete WT SYSTEM plant. The new earthing
system shall be connected to the existing earthing system.
Bidder shall also consider earthing of following equipment:
33kv substation equipments.
WT LT distribution transformers Neutral as well as body earthing
415
5 WT SYSTEM PCC at WT SYSTEM substation in switchgear cum MCC room
Control panel for power distribution equipment at existing WT control room
LT busducts
Charger panels, DCDB, etc at WT substation in switchgear cum MCC room
Underground eart mat.
Page 7 of 97
Bidder shall consider earthing ring mains at each electrical premise and connect the electrical
equipment with the rings. The earthing ring mains shall be connected with underground
earthing mats to be provided by the bidder made of 2x40mm dia solid MS rod. Adequate
number of risers shall be made available for connection with his earthing ring main. For
transformer neutral earthing, bidder shall consider dedicated plate earthing.
Lightning protection shall be provided by the bidder for complete WT SYSTEM including tall
installations covered under the battery limit.
Bidder shall also include complete illumination of the premises under the battery limit and all
the above electrical premises coming at WT SYSTEM substation and adjoining areas.
conditioning, ventilation and exhaust fans for various rooms / premises of WT SYSTEM
Air-conditioning,
along with their complete electrics shall be under scope of the Bidder. The battery and battery
charger room shall be air-conditioned. Switchgear cum MCC room of WT substation shall have
pressurized ventilation. Transformer rooms of the WT substation shall have exhaust fans.
fans
All interconnection for power, control and instrumentation/signal amongst equipment
equipmen
supplied by the Bidder shall be under Bidder's scope of work. Similar interconnections
including power, control and signal between Purchaser's equipment and Bidder's equipment
shall be done by the Bidder. All the cable terminations at both ends, cable trays
tr
and cable
accessories shall be under Bidder's scope.
2.5
General
The design, manufacture, assembly and testing as well as performance of the equipment shall
conform to the relevant IS : specifications (latest revision) and other relevant standards. In
case IS specifications is not available in respect of certain items, the Bidder may base his
proposals on IEC/BS/VDE/DIN recommendations or other reputed national or international
standards subject to the approval of the Purchaser/RITES.
Purchaser
. All equipment supplied and all work
done including system design and detailed engineering shall also comply with the statutory
requirements of the Government of India and the Government of Orissa.
b)
Climatic Conditions
Electrical Equipment selection and derating shall generally be based on ambient temperature
of 50oC. The equipment offered shall be suitable for smooth, efficient and trouble free service
in the climate prevailing at Angul.
c)
Page 8 of 97
Following power utilization standard voltage levels shall be adopted for various systems:
1. Station supply
3. Power supply to PLC extension
4. DC control supply
5. Plant illumination
Welding socket / power
6.
receptacles
Special socket outlets for
7.
portable lamps
8. Sockets for electrical tools, etc
9 Emergency illumination
d)
Permissible variations
The system / unit / plant / equipment shall be designed suitably for following variation in
voltage and frequency;
Voltage
+/-10%
10%
Frequency
+/-5%
+/- 10 %
+/-5%
- 15 %
- 15 %
e)
The short circuit ratings of all the equipment like MCCs, motors, PDBs / LDBs, cables, power
socket & lighting cabinets, etc shall be selected keeping in view the fault level capacities of the
Purchasers electrical equipment.
The three phase symmetrical short circuit rating at 33 kV level shall be 25kA.
25
The three phase
symmetrical short circuit rating at 415 V level shall be 50kA.
The rated short circuit withstand duration for 33 KV shall be 3 sec, whereas for 415 V system,
it shall be 1.0 sec.
f)
Page 9 of 97
System Earthing
Page 10 of 97
4.0
TECHNICAL SPECIFICATION
4.1
Page 11 of 97
conditions for start and tripping of various drives shall be provided as per approved logic
diagrams.
ed hardwired control panel / desk shall also be provided by the bidder at WT control
A dedicated
room to control and monitor electrical power distribution system.
Controls of all equipments of wagon tippler including conveyors all interlocks shall be PLC
based. The PLC system shall be latest version having dual redundant processor with HMI based
control station. There shall be two HMI control system with one operating station and other
an engineering station. The system shall be designed with 10% extra input/output provision.
p
Input/output of PLC(analog & digital) shall have at least 10% extra channel wired up to TBs
TB in
the panels. A portable programming station (Laptop) with all the ladder logic/
programming/software shall be provided for engineering and troubleshooting
troubleshooti functions. The
system shall be capable of communicating with the existing PLC system of the CHP(The
existing PLC is of GE Fanuc makemake Model 90-30,CPU-370).
370). The vendor shall be responsible for
communicating and displaying the important parameters of wagon
wagon tippler PLC system to the
existing CHP PLC through optical fibre cable. All electrical power distribution system shall be
controled and monitored through PLC.
PROTECTION SYSTEM
Protections for the different electrical equipment are enlisted below:
motor comprehensive
omprehensive numeric motor protection shall be provided in the
For Protection of LTT motor,
switchboard.
Laying of control and power cables including supply and laying of signal cables from motors to
switchboard shall be in the scope of Bidder.
ensive numeric motor protection including but not limited to the following:
Comprehensive
Instantaneous over current protection
Differential protection (for rating above 1000 kW)
Instantaneous time over current protection in two phases and definite time delayed over
current
urrent alarm on the third phase
Negative phase sequence protection
Thermal overload taking -ve and +ve phase sequence into account
Earth fault
Locked rotor protection
Winding temp monitoring and alarm for rating beyond 1000 kW
Under voltage protection
protectio
Microprocessor based numeric motor protection relay shall also have following facilities:
Communication facility with open protocol like IEC/Modbus.
Relay should store last five fault records (minimum) with date and time stamping.
Relay should have no.
o. of start menu for start inhibition.
Relay should have facility for displaying three phase and neutral current
Technical Specification:Sec-6, Electrical
Page 12 of 97
Relay should have heavy duty tripping contact which will be used for breaker tripping
Battery backup facilities
The Motor Protection Relays shall also have the following additional features:
Fault recording facility
Password protection
Local/remote communication facility with open protocol
Minimum 4 nos. BI and 4 nos. BO
Protection of LT motor (less than 75 kW)
Motors below 75 kW shall be fed from MCC through MCCB with power contactor and overload
relay.
Motors of 5 kW and above but below 75 kW, shall have fed through MCCBs (for short circuit
protection), numeric motor protection relay like MPR-300
MPR 300 or equivalent
equivalen (for overload and
other motor protection) and power contactors.
For motor below 5 kW, MPCBs may be considered in place of MCCBs.
Single phasing protection shall also be provided in the MCC modules.
METERING
Following metering shall be provided in various MCC/DBs;
415 V MCC
1. 415 V INCOMER (EACH) AMMETER (DIGITAL TYPE)
VOLTMETER
kWH METER
2. BUS COUPLER
AMMETER
3. OUTGOING
AMMETER (DIGITAL TYPE)
MOTOR FEEDER (EACH)
PDB
1. 415 V INCOMER
COMER (EACH)
4.2
Page 13 of 97
Page 14 of 97
Page 15 of 97
Page 16 of 97
Minimu
m
rating
of
MCCB
Minimum
rating of
contactor
(AMPS) AC3
duty
*
*
*
25
40
40
4
4
6
4x 2.5(copper)
4x 2.5(copper)
4x6
*
*
*
*
*
*
*
*
*
*
*
*
*
*
40
63
63
63
100
100
160
160
200
400
400
400
400
400
6
10
16
16
25
35
50
70
95
12 x 2
12 x 2
12 x 2
15 x 3
15 x 3
20 x 3
20 x 5
20 x 5
30 x 5
40 x 5
40 x 5
40 x 5
4 x 16
4 x 16
3.5 x 35
3.5 x 35
3.5 x 70
3.5 x 70
3.5 x 95
3.5 x 120
3.5 x 185
3.5 x 185
2(3.5 x 120)
2(3.5 x 120)
2(3.5 x 120)
2(3.5 x 185)
Minimum size of
power cable
Aluminium
(sq.mm)
Page 17 of 97
Page 18 of 97
POTENTIAL TRANSFORMERS
1. Type
: Cast Resin
2. Primary/secondary
voltage ratio
415V
3
110V
3
: Numeric
: Microprocessor based.
TYPES OF CABLES
Page 19 of 97
Page 20 of 97
Where such sealants or adhesives shall be exposed to high electrical stress, same shall be track
resistant type.
Straight through joints and end sealing termination kits of 33 KV (UE) grade cross-linked
cross
polyethylene cables shall be of well tried out design compatible for XLPE insulation. The
joints/ends sealing kits shall be of heat shrinkable type and shall be complete with stress
grading material, protective and lug sealing sleeves, self tightening earthing clamp, slide angle
sleeve etc. Outdoor termination shall have necessary skirting over protective sleeving to
increase the creepage distance and the sleeves shall ensure total protection against ingress of
moisture. Straight through joints shall feature moisture proof
proof environmental seal, mechanical
protection and impact resistance envelope around the joined cables.
The end termination and straight through joints shall conform to the relevant standards. The
complete termination / joint kits shall be of reliable and field proven design having been fully
type tested and relevant type test reports shall be furnished.
In addition the termination and joint shall be tested for various accelerated aging tests such as
thermal aging, weathering etc. to have long and trouble
trouble free service. Necessary type test
certificates for aging tests shall also be furnished.
Following type of cable termination and joints shall be used for HT cables in indoor and
outdoor applications:
1.
2.
3.
Tapex type
Heat shrinkable type
Pre moulded push on type
Page 21 of 97
Cable clamps
All cables shall be clamped with GI (minimum size of 25x3mm) / Al (minimum size of 25x4)
clamps and single core cables shall be clamped with trefoil clamps made of non-magnetic
non
materials.
Page 22 of 97
Electrical design
Bus duct shall be suitable for 33KV/415
415 V, 3 phase, 50 Hz. neutral solidly grounded system and
shall be covered with canopy if required to be installed outdoors.
outdoors. Rated short time withstand
current not less than the system short circuit level specified for 1 sec for 415V. Rated peak
withstand current not less than 2.1 times the system short circuit level.
Rated continuous current shall be as per requirement while in enclosure and at specified
ambient temperature with maximum temperature
temperature of bus bars limited to 85C.
85 Neutral bus in
LT with rating not less than half the rating of phase bus.
The bus duct shall be rectangular, non-segregated
non segregated phase, totally enclosed type.
Insulation level
Rate insulation voltage, one minute PF withstand
withstand voltage & impulse withstand voltage shall be
as specified in technical particulars.
Rate current
Rated continuous current as specified while in enclosure and at specified ambient
temperature with maximum temperature of bus bars limited to 85C.
85
Neutral bus in LT with rating not less than half the rating of phase bus.
Page 23 of 97
Construction details
Degree of protection for enclosure IP 52 or better for indoor installation.
Enclosure material:: The minimum thickness shall be 2.5 mm. Tender shall include enclosure
with the thickness required
red for the shape and mechanical/ electrical strength point of view.
Aluminium enclosure shall be provided for rating equal or more than 3000A. MS enclosure
may be provided for LT bus ducts of rating less than 3000A. Provision shall also be provided
for draining moisture.
Maximum temperature of enclosure under rated operating conditions limited to 70C.
70 Rubber
bellows shall be provided at transformer end to take care of vibration.
GI supporting structures, wherever required, shall be provided with necessary hardwares. In
horizontal run of more than 10 mtr of bus ducts expansion joint with copper flexibles shall be
provided at every 10 mtr interval.
Maximum temperature of enclosure under rated operating conditions limited to 70C.
70
Bolted covers with gaskets shall
shall be provided for easy inspection and access to insulators and
bus bar joints.
Gasketted (Neoprene) connections shall be provided between adjacent sections of metallic
enclosure.
Tinned copper flexible shall be considered for connection of bus ducts at transformer end as
well as PCC end.
Rubber bellows at transformer end shall be provided to take care of vibration.
Seal off bushing and frames complete with bolts.
Provision shall be provided for draining the moisture.
Provision shall be provided for mounting the bus ducts on brackets.
The bus duct shall include straight run, 90 degree bend, Phase crossover chamber,
transformer end chamber, tinned copper flexible, wall frame assembly, rubber bellows and
other accessories as per the requirements.]
Busbars
rs and connections.
Bus bar material shall be EC grade aluminium alloy equivalent to E91E WP conforming to IS
5082-1981.
Final operating temperature of both bus bars and joints under continuous operation in
enclosure limited to 85C
C by thermometer method. While designing the bus duct, site
condition and solar radiation shall be taken care of.
Bus bar arrangement shall be as per IS 5578-1991.
5578 1991. Phase identification shall be by colour at
ends and at regular intervals. Busbar joints shall be of bolted type, cadmium
cadmium plated with zinc
bichromated high tensile steel bolts, nuts and spring washers and coated with oxide inhibiting
grease prior to jointing.
Copper flexible busbars shall be tinned. Copper flexible connections shall be provided for
termination on equipment as well as on expansion joints.
Bimetallic joints /strips shall be provided for jointing between dissimilar metals (if required).
Bus bar support insulators of non-hygroscopic
non hygroscopic material having impact and di-electrical
di
strength with an anti-trackin
tracking contour.
Bus duct of 3000 A and above rating shall be interleaved type.
Bus conductor shall be given a coat of black mat point.
Protective earthing
Double earthing shall be provided for enclosure of bus ducts.
Technical Specification:Sec-6, Electrical
Page 24 of 97
Black/white/light yellow
Exterior
IS - 8623
415V, 50 Hz
50C
System earthing
Solidly grounded
50 KA
500 V
Aluminium Alloy
As specified
Aluminium
:`
To be provided
As specified
50 kA
1 sec
Indoor
Page 25 of 97
Insulation level
Insulation class
1.1 kV
2.5 kV
2.5 kV
Support insulator
Type
Clearance
Phase to Phase
25.4m
Phase to earth
19.0m
Material
Thickness of material
Required
Space heaters
Required
Bus conductor
85C
70C
Enclosure
Accessories
Page 26 of 97
Paint shade
Interior:
yellow
Black/white/light
Exterior: Approved
One set in one of the bus
duct portion of each
PCC/board.
4.4
ELECTRIC MOTORS
General
All motors shall generally conform to IS 325 and CBIP publication No. 140. Motors shall run
continuously at rated output with + 5 % variation in frequency and + 10 % variation in voltage
and + 10 % combined
ned variation of frequency and voltage (absolute sum). Motor shall not stall
due to momentary drop in voltage up to 70 % of rated value and shall run satisfactorily for five
minutes at a supply voltage of 75 % of rated value.
The limiting value of voltage at rated frequency under which motor will successfully start and
accelerate to rated speed with load shall be assumed to be a constant value of 80 % rated
voltage throughout the starting period.
All motors shall be supplied with foundation bolts (if applicable),
applicable), drain holes with plugs.
Motors shall be designed for 50oC ambient temperature.
Motors supplied shall be complete with required double compression cable glands, crimp type
cable lugs and first filling of lubrication, name plate, etc. Lifting facility
facility to be provided for all HT
motors and big size LT motors. Guards shall be provided to prevent accidental touch for
couplings and for free shaft ends shall be provided.
Degree of protection for motor and bearings shall be IP-55
IP 55 for indoor and IP55 with
wit rain
canopy and weather proof construction for outdoor. Motor shall be suitable to withstand at
least three successive starts from system cold condition and two starts from hot condition at
normal system voltage and frequency.
The drive motor shall havee at least 15 % margin over the maximum power requirement of the
driven equipment after considering all losses, de-rating
de rating due to temperature and specific site
and operating conditions.
Page 27 of 97
Page 28 of 97
Page 29 of 97
which has to be connected to the motor protection relay. Speed switch shall be capable to
withstand 120 % of the overspeed in either direction.
Insulation of motors shall be designed conforming to IEC 34-15/
34 15/ 1990. Gland plate for single
core cable shall be non-magnetic
magnetic type.
All motors shall have individual dedicated handling and lifting facilities preferably by dedicated
electric hoist.
4.5
:
:
Number and capacity of PDB given in the enclosed Single Line Diagram is minimum and
indicative. Bidder shall provide as per actual load requirement and same shall be finalized
during detailed engineering.
AUXILIARY POWER DISTRIBUTION BOARD
Aux. PDBs shall be suitable for 415V, 3 phase, 4 wire,
wire, 250A, 50 kA (short time rating for 1 sec.)
indoor type. Board shall be single front, metal clad, front matched, dust and vermin proof,
non-drawout,
drawout, fully compartmentalized and extensible on both sides, IP54 type enclosure.
Page 30 of 97
4.7
33/.415 kV
Page 31 of 97
Capacity
Nominal voltage (kV)
Max system voltage (kV)
Power frequency withstand voltage (kV)
System earthing
No. of phases
Frequency
Impulse test withstand voltage (kV)
Short time current rating (for all current
carrying parts)
Fault level (3 phase symmetrical)
Type of Cooling
Connection HV winding
Connection LV winding
Connection Symbol
33
35
75
Low resistance earthed
3
50 Hz
170
25 kA for 3 sec
25kA
ONAN
DELTA
STAR
Dyn 11
HT/LT transformers shall be of the latest design, oil immersed type as per IS : 1886 and testing
as per IS 2026 part I.. All dry type air natural transformers shall be suitable for indoor use line
up with power control centre as unit type.
Bidder shall ensure that manufacturer shall have his own in-house
in house core cutting facilities on
CNC machines.
ken to make enclosed equipment proof against entry of rats, lizards and
Special care shall be taken
other creeping reptiles which may create electrical shortshort circuits inside live equipment. The
design of each transformer shall be such that the risk of accidental short-circuits
short
due to
reptiles or vermin shall be obviated.
The transformer shall be of cast resin type. The tap changing arrangement shall be of
removable link type.
Each transformer shall be suitable for operation at full rated power on all tappings without
exceeding the temperature rise of 800C over the ambient of 50oC. Minimum class of Insulation
shall be F.
The transformers shall be designed to be capable of withstanding, without injury, the thermal
and mechanical effects of short-circuits
short
between phases or between
n phase and earth at the
terminals of any winding with full voltage applied across the other winding. All transformers
shall be capable of withstanding specified through fault current for minimum of 2 seconds as
per IS: 2026 (Part-1).
The transformers shall
all be designed to suppress harmonic currents, especially the third and
fifth, so as to eliminate distortion in the wave form and consequent additional insulation
Technical Specification:Sec-6, Electrical
Page 32 of 97
stress, noise on communication system and undesirable circulating currents between the
neutrals
ls at different transformer stations.
The Transformers shall operate with minimum noise and vibration. The cores, protective
housings and other structural parts shall be properly constructed and windings properly
braced so that the mechanical vibrations are kept to the minimum, thus reducing the noise. To
this effect, the laminations shall also be bonded together with appropriate resin. The core-coil
core
assembly shall also be fixed in such a manner that no shifting or deformations occur during
shipment or installation.
Each transformer shall be designed for minimum no-load
no load and load losses within the economic
limit.
All electrical connections and contacts shall be of ample section for carrying the rated current
without excessive heating.
all be of stainless steel, brass, gunmetal or other suitable material to prevent
All mechanism shall
sticking due to rust or correction. If any temporary fitting is fixed to the protective housing of
the transformer for transporting / handling purpose, these shall be identical
identica as well as
instructions and illustrated drawings shall be furnished to facilitate their removal at site after
erection.
4.7.2
Core
The framework, clamping arrangement and general structure of the cores of each transformer
shall be of robust construction and shall be capable of withstanding any shock to which they
may be subjected during transport, installation and operation. The assembled core shall be
securely clamped on the limbs and the yoke to build up a rigid structure. The clamping
pressure
sure shall be uniform over the whole of the core and so adjusted as to minimize noise and
vibration in the core when the transformer is in operation. The framework and the core bolts
shall be effectively insulated from the core so as to reduce the eddy-currents
eddy
rents to the minimum.
The magnetic circuit shall be built of high quality, low loss, non-ageing.
non ageing. Cold rolled, grain
oriented, silicon steel laminations (CRGO Prime Grade) having excellent magnetic properties
and specially suitable as core material. Laminations
Laminations shall be insulated from each other with
material having high inter-lamination
inter lamination insulation resistance and rust inhibiting property and
also capable of withstanding stress and mechanical vibration.
Necessary cooling ducts shall be provided for heat dissipation
dissipation from the core so that the
anticipated maximum hot spot temperature in the core shall not be injurious to any material
used in the core assembly.
clamping frame shall be provided with lifting eyes having ample strength to lift the
The core-clamping
complete
te core and winding assembly.
Suitable provision shall be made in the dry type transformers for effective core earthing.
Technical Specification:Sec-6, Electrical
Page 33 of 97
4.7.3
Winding
The coils used for transformer winding shall be made of insulated, continuous and smooth
electrolytic copper conductors of high conductivity and of 99.9% purity. Similar coils shall be
connected by accessible joints brazed or welded and finished smooth. No corona discharge
shall result on the winding during induced voltage test as specified in applicable standard.
The insulating materials for dry type transformers shall be of type not inferior to Class F. All
insulating materials shall be of proven nature
nature and shall be suitable for the suitable for the
limits indicated in the applicable standards as well as the maximum possible winding
temperature and shall not deteriorate when the transformer is operated continuously at its
specified rating at the specified
specif ambient temperature.
coil insulation shall be so designed that the dielectric stress is
The inter-turn and inter--coil
uniformly distributed throughout the winding under all operating conditions.
The windings shall be dry cast resin type.
er windings shall be designed for basic Impulse insulation level not lower than
The transformer
those specified above.
4.7.4
Dry type transformer shall be provided with suitable protective sheet steel housing, with
minimum IP
P 23 degree of protection for the enclosure. The housing shall have ventilation
louvers provided with wire mesh screens and shall be supplied with suitable lifting lugs. Safety
limit switches shall be provided and wired in such a way that the incoming supply
supp may be
disconnected whenever any one of the sides of the enclosures are opened with the
transformer in energized condition.
Sufficient precautions shall be taken so that doors are closed fully. Door locks shall be
provided and keys shall be universal type.
4.7.5
Circuit Links
Off-Circuit
circuit tapping links shall be provided on the HV side with appropriate register plate to
The off-circuit
show the link location. The links shall be provided with a separate door for access. The door
shall be provided with appropriate safely limit switches which will trip the transformer HV / LV
sides in open condition.
4.7.6
Cooling
Page 34 of 97
CTs for back up earth fault (51N) as well as for restricted earth fault (64) shall be provided on
the neutral end.
Neutral bushing CT shall be removable
removable at site without opening transformer tank cover/active
part. Secondary leads of 4 sq.mm shall be brought to a weatherproof terminal box and from
there to the marshalling box.
Neutral bushing CTs of suitable ratio, class and adequate burden shall be provided by the
Bidder to cater to the requirement of all standard protection associated with the transformer
of this capacity. CTs for REF shall be PS class.
4.7.8
Marshalling Box
Enclosure mounted marshalling box to be supplied with all controls instruments, protection,
accessories & fitting as required for the transformer and its associated ancillaries. The box
shall be made of 2 mm sheet steel with IP 54 degree of protection.
heet steel marshalling box of dust-proof
dust proof design shall be provided to accommodate
Sheet
temperature measurement as well as control system, as may be necessary. The box shall be
mounted on the transformer enclosure and shall be provided with internal lighting, space
spa
heater and thermostat with their controls accessible from outside.
The box shall be provided with suitable hinged steel doors at the front and all equipment shall
be so placed as to accessible from the front. Provision shall be made for padlocking the doors.
Suitable glazed windows shall be provided at appropriate positions to give an unrestricted
view of the temperature indicators etc, without opening the door.
All initiating
tiating contacts of shall be wired up to the terminal block in the box. All control wiring
shall be with 1.1kV grade stranded PVC insulated armoured copper cable of 2.5 sq.mm.
Terminal blocks shall have 20% spare capacity.
The external connections between
between the apparatus on the transformer and the marshalling box
shall be done with suitable heat resisting copper conductor cables of core size not less than
2.5 sq. mm. The cables required to connect the marshalling box and transformer accessories
shall be adequately
dequately protected against mechanical damage. There shall be no joints or tappings
between two terminations of any cable. Not more than two terminations shall be made at any
one terminal. All terminations at various devices and terminal blocks shall be provided
pr
with
plastic ferrules having engraved numbers. All terminals and links shall be so arranged as to
facilitate easy checking and testing of relays, instruments etc. Provision shall be made for
termination of power cables as well as multi-core
multi
control cables in the marshalling box.
The control circuit terminal blocks provided for external cable connections shall be provided
with screw type terminals and shall be complete with terminal screws, links, cable carries etc,
Each terminal block shall have 20%
20% spare terminals and all wiring shall be such that it is easily
identifiable and accessible for maintenance.
Page 35 of 97
All devices, wires and terminal blocks within the marshalling box shall be clearly identified by
symbols corresponding to those used on relevant schematic or wiring diagrams.
Enclosure class of marshalling box shall be IP-55.
IP
Terminal Arrangement HV/LV terminals shall be suitable for cables considered.
4.7.9
Details of Fittings
Requisite number of Resistance type temperature detectors shall beprovided with solid state
type temperature signaliser for dry type transformer. The temperature signaliser shall be
provided with two sets of contacts, one
one for alarm and the other for circuit-breaker
circuit
trip. The
signaliser shall be provided with digital read out for the temperature being measured and for
the zone where the current measurement.
Two nos. earthing terminals of adequate mechanical and electrical capacity shall be provided.
Separate earthing terminals shall also be provided on the enclosure, marshaling box and
terminal boxes.
Rating and diagram plates shall be provided as per adopted
adopted standards for each transformer.
Lifting lugs and hauling holes as required shall be provided for the transformer as well as for
the enclosure.
Page 36 of 97
Suitable under-carriage
carriage fitted with flat rollers shall be provided. The rollers shall have
adequate mechanical
ical strength and shall be so designed that the transformer shall roll without
undue effort after it has remained immobile for a long period. The edges of rollers shall be
duly rounded off to permit skidding of transformer on flat surface.
(33KV/
4.7.11 Technical Particulars of HT Transformers (33KV/440V)
1.0
1.1
1.2
1.3
1.4
1.5
1.6
2.0
2.1
2.2
2.3
2.4
General
Make
Type
Service
Duty
Degree of Protection
Reference Standard
Rating
Rated output
Quantity
Type of cooling
Rated voltage Volt
H. V.
L. V.
2.5
No. of phases
2.6
Rated Frequency Hz
2.7
Vector group reference
2.8
Connection
H. V.
L. V.
LVn
2.9
Insulation
H. V.
L. V.
2.10 Insulation level kVp/kV
H. V.
L. V.
3.0
Temperature
3.1
Reference ambient temp.
3.2
Temp. rise over reference ambient
a)
Top Oil measured by
b)
In winding by
4.0
Tappings
4.1
Type
4.2
Taps
4.3
Taps provided on HV winding
5.0
Method of earthing
Technical Specification:Sec-6, Electrical
:
:
:
:
:
:
Reputed Make
Two winding
Outdoor
Continuous
IP:55
IS/IEC Equiv
:
:
:
:
:
:
:
:
:
:
:
:
Delta
Star
Grounded through NGR
:
:
Uniform
Uniform
:
:
:
:
75/28
40/10
:
:
500C Thermometer
550C Resistance
:
:
:
:
33kv
440V
3
50
Dyn11
500C
6.0
6.1
6.2
6.3
6.4
6.5
6.6
7.0
7.1
7.2
8.0
9.0
10.0
10.1
10.2
11.0
Page 38 of 97
: Yes
ACB/MCCB
Line contactors
Inverter Equipment
Converter Inverter
Filter network
up transformer, as required
Step-up
Page 39 of 97
By-pass
pass arrangement shall be provided to operate the motor in case of failure in
frequency converter.
Thyristor converter
Minimum ratings of thyristor cells
PIV rating
:
2.5 times the peak value of line voltage
dv/dt rating
:
200V/microsecond for voltage control and
1000V/microsecond for inverter control.
di/dt rating
:
100A/ microsecond.
Protective features
AC line surge suppression network
net
Over load
Earth fault
Transformer fault
Page 40 of 97
Sequence module
Zero speed/over speed monitor as applicable
V/f control
Current limiter
Counter current/ regenerative braking unit as applicable
active electronic components used shall be of industrial grade hermetically sealed
Regulated power supply for reference setting:
Voltage variation of (+/-)) 0.1 % with an input variation of +10% - 15%
Steady state regulation of (+/-)0.25%
(+/
% guaranteed against 100 to 200 % load disturbance and +
3%, -6%
6% input supply frequency variation.
Facility to accept speed reference from computer/ programmable controller
Construction features
Floor mounted, free standing
Dust and vermin proof
Sheet steel clad
Minimum 2.5 mm thick for panels.
Minimum 2.0 mm thick for doors and side covers.
Suitable to withstand vibrations to be encountered in steel plant application.
Cubicles with illumination lamps, door switches, space heaters and adequate sockets
for soldering.
All control blocks plug in-type with necessary test sockets.
Units shall be self contained and serviceable.
Enclosure and Ventilation
Enclosure conforming to IP-52
IP
or more with weather proof enclosures
Units shall be provided with cooling fans and louvers at the bottom sides. All louvers shall
have fine mesh behind them.
Ventilation through individual ventilation ducts, from bottom not acceptable.
4.9
RELAY PANELS
Relay panels (RP) housing aux. contactors, timers, relays, etc. shall be provided for equipment
control, sequential control, monitoring, safety alarm signals, annunciation signals, interlocking
of drives ,signal exchange, interface with future system etc. shall be provided. Constructional
features of R.P. shall be similar to MCC. At least 10 % spare auxiliary contactors, timers &relays
shall be provided in the relay panel whose contacts and coils shall be wired up to terminals.10
terminals.
% spare terminals shall also
als be provided. 10 % of auxiliary contactors, timer and relays shall be
provided as spares which will be wired upto terminals.
4.10
Page 41 of 97
Input power supply shall be fed through UPS system. However, PLC shall be capable of
withstanding power supply from electrical feeder. Alternate source of power supply
arrangement or second UPS shall be provided to take care of the situation when the original
UPS fails.
in power supply units
Built-in
Suitable for thee power supply system as specified above.
Independent units for the following:
CPU and associated electronic units
i)
sensing the status of input devices
ii) driving outputs if outputs are relays
iii) Insulation level 2.5 kV for 1 minute.
Protection againstt surge protection & short circuit
Electronic over current protection with feedback feature.
Central processor unit
in type
Modular and plug-in
32 bit microprocessor based
Scan time 2 m sec per one K Words of instructions or better
Provision to latch desired outputs.
The processor shall have in-built
in built provision for examining input conditions, compare,
compute, logical, conversion from/ to BCD, bit manipulation, block memory manipulation,
diagnostic, shift, sequencing, conditional jumping, subroutine instructions.
In-built
built PID instruction shall be preferred over separate PID hardware Module.
Timer & counter modules shall be provided wherever required.
Memory units
Modular and plug-in type
Word length 32 bit as per CPU
Expandable in blocks of 4K Words
Minimum size 16K Words
EPROM/ RAM with battery back-up
back
Back-up
up battery shall be as follows:
i) Rechargeable Ni-Cd
Cd batteries with necessary charging circuit, Lithium or any other
internationally acceptable type.
ii) Able to retain memory for a minimum of 1 year with no power applied to the controller.
Input units
High density (32/16 Channels), modular and plug-in
plug type
Insulation level of 1.5 kV
Input interrogation voltage 24V DC
Discrete input units shalll have the following:
i)
Filter to take care of contact bounce
ii) Opto-isolation
isolation to isolate the input device from the controller
Technical Specification:Sec-6, Electrical
Page 42 of 97
iii) LED status indication iv) BCD input units suitable for four digit input
Analog input units shall be as follows:
i) Suitable for 4-20
20 mA / 0-10V
0
/ +/-10V inputs
ii) With necessary A/D converter
Pulse/ frequency input module shall have range up to 50 kHz. For very high frequency
applications, the range shall be up to 1 MHz.
Output units
plug type
High Density (32/16 Channel), modular and plug-in
Discrete output units shall be as follows:
i) Opto-isolated
isolated outputs with insulation level of 1.5 kV
ii) Rated for 24V DC, 2A
Power devices like contactor or odd voltage actuating device shall be
b actuated through
relays
LED status indication
BCD output units shall be as follows:
i) Suitable for four digit output
ii) Rated to drive seven segment LED displays
iii) With insulation level of 1.5 kV
Analog outputs shall be as follows
i) Suitable for 4-20mA/
20mA/ 0-10V/
0
+/-10V
10V outputs capable of driving Digital / Analog Panel
Meters
ii) With necessary D/A converters
iii) With insulation level of 1.5 kV
iv) Any special requirement to control field devices shall be met by using separate
interface modules
PC based programming unit:
PC used for Programming Terminal shall be commercial grade and latest available in the
Suitable for developing programs in ladder diagram/ block diagram or statement form
With facility for loading the program from floppy
The terminal shall be capable of developing multiple programs offline without connecting to
the programmable controller.
Self diagnostic features
Parity errors, cycle errors and under voltage
Failure in central processor unit, memory and power supply.
sup
Indication of type of failure
Automatic turning OFF of all outputs or optionally holding of all outputs in their last state on
failure detection.
Additional features
Fully pre-programmed
Connection of field devices with input units through
throu ordinary multi--core copper control
cables of 1.5 sq. mm size, upto a length of 500 m.
Technical Specification:Sec-6, Electrical
Page 43 of 97
Connection of remote input/ output units to programmable controller through remote I/O
units, wherever substantial saving in cabling is envisaged.
Serial interface,
ce, RS232C and better shall be provided
High speed communication among PLC and operator consoles/ display units shall be
provided through ethernet
Latest appropriate model of HP Inkjet Printer to get hard copy of the program dump/ data
logging / alarm
m logging / event logging / data trending etc. [Printer covered also under
Programming Unit. Only one printer shall be supplied.]
Special features
Switch to disable all outputs of the controller during start-up/
start up/ debugging
Fuse failure indication for outputs Mounted spares
Min of 30 % of I/O modules used of each input & output type (with at least one module of
each type) shall be offered as unused spare for each I/O rack. Minimum of 30% I/O rack
slots shall be kept reserved
rved for future expansion.
30 % spare memory capacity shall be provided
Constructional features
Unitised construction
Floor mounted, free standing and indoor type
Bottom cable entry
Sheet steel clad
Dust and vermin proof
Suitable to withstand vibrations as per application
All modules plug-in
in type
Enclosure
42 class
Conforming to IP-42
Conforming to IP-54
54 class for remote I/O cubicles located in shops/ bays.
Miscellaneous
air
ditioned enclosure, shall be suitable for
Programmable controllers, even if housed in air-conditioned
normal industrial environment and ambient temperature upto 500C. A suitable fan with inlet
air filter shall be provided at the top of each PLC panel for proper air circulation.
Dual redundant processor shall be envisaged. Redundancy shall be provided in such a way
that in case of failure of the main processor, the standby shall takeover automatically. The
changeover shall be bump less and the system shall be fail proof. Redundancy
Redundan shall be
provided for complete processor system including CPU, Memory, Power supply and
Communication sub system.
Failure of a single processor shall not affect the system.
In case of failure of complete processor system, outputs shall take fail safe state
st
automatically.
It shall be possible to generate the first out alarm contact by the PLC in case where a group
of parameters are likely to trip a system.
Page 44 of 97
4.11
The communication subsystem between PLC processor and I/O subsystem shall be dual
redundant.
munication subsystem between processor subsystem and PLC console shall be dual
The communication
redundant, consisting of two separate communication interfaces and two buses, each one
configured in redundant mode.
No hardwired alarm system is required. All the alarms are to be displayed in OWS of PLC
with multi tone buzzer and with alarm history provision.
The software provided at the time of supply should be of latest version.
Necessary license to be provided along with the software.
The OS (Operator Station) desk and operator
operator chair to be supplied by the bidder.
UNINTERRUPTIBLE POWER SYSTEM (UPS)
General System Description
The required kVA, 50 Hz, single phase UPS system shall provide continuously operating
uninterrupted power supply to critical AC loads such PLC,
PLC, instrumentation, etc.
The capacity of UPS shall be suitable to feed power requirement of the PLC which shall control
and monitor all the drives/mechanism of proposed additional coal handling system.
The UPS system shall include but not necessarily limited to the following equipment:
One 100% rated battery bank
One set of Float Charger (FC) and one set of Float cum Boost Charger (FCBC) complete
with associated incoming AC switchgear.
Two nos. 100% capacity inverter banks.
One no. DC switchgear, connecting
connecting above and also inverter banks stated above
One no. 3 phase to 1 phase transformer and associated AC switchgear, 230V, 1 phase
voltage stabilizer and backup source static switch.
One no. 240 V UPS ACDB
One no. four way manual bypass switch
Static switches
All inter connecting cables/wiring with connection accessories and other required items
to make the system complete.
Mode of Operation
Normal Mode
During the normal operation the UPS shall be used to provide power to the critical loads.
loa The
primary AC source shall be used to supply power to the rectifier charger. Two (2) no. chargers
shall feed regulated DC power to their individual inverter banks and simultaneously float
charge the backup batteries.
Emergency Mode
Page 45 of 97
Upon failure of primary AC source supplying three phase power to the battery chargers, the
input power to the inverters shall be supplied from the back up batteries. When the AC power
is restored, input power for the inverter and power for recharging the battery
b
shall
automatically be supplied from the rectifier charger. The batteries shall supply the inverter
whenever the chargers are unable to supply the sudden load demand or their response to the
load change is slow.
The output of the UPS shall feed all
all the essential loads through the ACDB. The connection
from the UPS to ACDB shall be through a switch and fast acting semiconductor fuses, trip fuses
and micro switch with alarm contacts. The feeders shall be designed by the bidder to suit the
load requirements.
Battery Charger
Two (2) nos. each of 100% capacity, battery chargers shall be provided for each UPS system.
These chargers shall be of static type and shall be provided with suitable transformer and full
wave, SCR type rectifiers. Chargers shall share automatically the load during parallel operation
of the inverter system and shall maintain output voltage within plus or minus one percent of
the nominal value from no load to full load.
Suitable ripple filtering circuits shall be provided to give a smooth DC output. The ripple
content shall be limited to less than +5% on resistive load.
The rectifier charger shall have float, equalising and boost charging facility as well as furnish
the inverter input current. In the `Boost' mode, the boost' chargers
chargers shall recharge the
completely discharged battery to full capacity in eight (8) hours.
In charger system, all the standard protection, metering and static annunciation shall be
provided.
Static Inverters
The two (2) nos. 100% capacity, (IGBT) required
required kVA inverters shall be static type consisting of
SCR type inverter, static filters, integrated control modules including necessary oscillators,
voltage regulators, current limiting and surge suppression networks. In addition, the inverters
shall have
ve features of soft start, wave shaping, transient recovery etc. Any other equipment
required for normal operation of the inverter shall be included irrespective of whether
specified or not.
The output from the inverter shall be 240V AC, sine wave 1 phase.
phase. The output of the UPS shall
be distributed to the essential loads through the AC switchgear. The connection from the UPS
to the AC switchgear shall be through a switch and a quick acting fuse. The feeders shall be
designed by the bidder to suit the load requirements.
Page 46 of 97
Page 47 of 97
Batteries
1. Type
2. Application
3. Number of cells in each bank in series
4. Ambient temperature
5. D.C. nominal system voltage
6. Ampere hour capacity
7. Charging method proposed
8. Emergency load duration
: VRLA, SMF
: UPS System
: As per requirement
: Min.temp. :5.0 deg.C Max.temp. :50 deg. C
: Suitable to inverter system
: Bidder to furnish along with calculations
cal
: . Float and boost
: 60 Minutes (battery back up time)
Page 48 of 97
9. Continuous load/duration
: As per requirement
Battery chargers
: 2 nos. (1 FC + 1 FCBC)
1. Number required
2. Type
: Static
3. Method of charging
: Float and boost charge type
4. DC system voltage
: To suit the system
5. Automatic voltage regulator required(AVR)
: Yes
6. Regulation with AVR
: +/-1%
7. Permissible harmonics at rated continuous load : +/-2%
+/
8. D.C. load requirement
a) Momentary : As per requirement
b) Emergency : As per requirement
c) Continuous : As per requirement
9. Maximum time for boost charging
: 8 Hours
Inverters
1. Type
2. Suitable for parallel oper
3. Service
4. Output rating
5. Output Voltage
6. Phase
7. Frequency
8. Total harmonic content
any single harmonic.
9. Duty
10. Overload capacity
11. Efficiency
12. Cooling
13. Synchronization with source
: Continuous.
: 125% for 15 minute at 0.8 p.f
: Not less than 80% at rated load
: Natural air cooled
: Yes
: Static
: suitable for parallel operation
: Indoor
: As required
: 240 V A.C.
: Single phase
: 50 Hz
: 5% RMS maximum not more than 3% distortion
distort
in
4.12
4.13
Normal AC lighting
DC Emergency lighting.
light
Maintenance lighting
Peripheral, road/street and area lighting within battery limit
Page 50 of 97
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
Ceiling fans
Receptacles
Lux
250
Fitting type
FTL
2.
Battery room
100
FTL
3.
4.
Transformer room
MCC room
FTL
FTL
5.
WT Control Room
200
250
lighting
250
6.
7.
8.
9.
Junction house
Conveyor gallery
Peripheral lighting
Street / road / area lighting
200
100
20
20
MH
MH
MH
SV
FTL
Remarks
AC normal lighting DC
emergency lighting
AC normal lighting DC
emergency lighting
AC normal lighting
AC normal lighting DC
emergency
AC normal lighting DC
emergency lighting
AC normal lighting
AC normal lighting
AC normal lighting
AC normal lighting
Page 51 of 97
Lighting DBs of all the areas shall preferably be located inside the rooms like switchgear cum,
control room, etc.
Sufficient numbers of LDBs, SLDBs, lighting poles, 415/240 V switch socket outlets, ceiling fans
with regulators, earthing pits, MCB controlled socket outlet, junction boxes, etc shall be
considered under scope of the Bidder as per actual requirement.
DC emergency lights shall be fed from separate DCELDB. Similarly, power receptacles shall be
fed from dedicated Receptacles DB. DCELDB at WT SYSTEM substation shall be fed from
Purchasers DCDB. Receptacle DB shall be fed from Bidders PDBs/aux. PDBs.
icient numbers of DCELDBs and Receptacles DBs shall be considered by the Bidder as per
Sufficient
requirement.
LIGHTING DISTRIBUTION BOARD (LDB)
415V, 3 phase, 4 wire, 600A, 50 kA (short time rating for 1 sec.) indoor type.
Board shall be single front, metal clad,
clad, front matched, free standing, floor mounted, dust and
vermin proof, non-draw-out,
out, fully compartmentalized and extensible on both sides, IP54 type
enclosure. Incomers shall be draw out type. LDBs shall have a series of panels of uniform
height placed side
de by side having front access for operation as well as cabling and access for
maintenance of busbars. LDBs shall have two incomers and one bus coupler.
Separate busbar compartments provided on the top shall have bolted covers in the front and
rear. The main busbars shall have continuous current rating as required. The rating of the
neutral busbar shall be 50 % of the phase busbars. The busbars shall be of aluminum alloy
conforming to IS 5082. The busbar sizes shall be so selected that with the passage of rated
current, the temperature rise over 500C ambient does not exceed 400C as measured by
thermometer.
Each cubicle shall have segregated feeder compartments arranged in tier formation with each
compartment housing one feeder circuit with lockable hinged
hinged door having neoprene gasket all
around. Modular construction shall be adopted to cater for different sizes of feeders. The
cubicles shall have common horizontal busbar chamber at the top and vertical risers at the
back. The cable compartment shall be provided
provided on the side with cable entry arrangement from
bottom. The busbar and cable compartments shall be provided with bolted cover plates. The
rear cover shall be easily removable type construction.
The LDBs shall conform to IS 8623 for factory built assemblies,
assemblies, IS 13947 for general
requirement of switchgear and IS 5578 & IS 11353 Guide for making and identification of
conductors and apparatus terminals.
Page 52 of 97
The LDBs shall be fabricated from CRCA sheets with 2 mm thickness for all members except
the doors of the modules, the rear covers, the covers of cable chambers and busbar chambers
which may be of 1.6 mm with adequate stiffeners to prevent buckling. Non-load
Non
bearing
partition walls may be of 1.6 mm thick sheet steel.
The cubicles shall be made up of bolted sheet steel members and side panels of pressed sheet
steel with neoprene gasket at all joints and openings including doors.
Bus bars shall have same cross-section
cross section throughout the length. Rating of the neutral bus bar
ba
shall be 50% of the main bus bar. Earth bus bar shall run in bottom chamber throughout the
length of the panel.
The LDBs shall have necessary provision at either end for future extension by bolting
additional section.
The busbar shall be supported with
wi high quality non-hygroscopic,
hygroscopic, insulating, self extinguishing
and fire retardant insulating material, of adequate mechanical strength so as to withstand,
without damage, effects of available short-circuit
short circuit current. The busbars shall also be properly
spaced
d of facilitate taking vertical connections to individual units. The connections to
individual units shall be taken by taped busbars. The busbars shall be of uniform cross-section
cross
and the main busbars shall run throughout the length of the board. Similarly vertical droppers
shall extend for the full height of the panel except the bottom chamber. The connection
between busbars of different metals as well as their connection with the terminals of the
equipment shall be made in such a way to prevent corrosion and local heating.
Liberal space shall be provided for cabling and to accommodate any conventional type of cable
glands for PVC insulated and PVC sheathed armoured aluminum conductor cables.
The cables compartment shall have provision for clamping of cables
cables inside compartment on
perforated sheet steel sections.
The LDB shall have following meters in each of the two incoming feeders:
One no. digital type voltmeter with accuracy class of 1.0
One no. digital type ammeter with accuracy class of 1.0
One no. digital energy meters with accuracy class of 1.0
Suitable CTs with accuracy class of 1.0 shall be provided in the incomer modules for the above
metering.
Moulded Case Circuit Breakers
LDBs shall have moulded case circuit breaker triple pole, air break type with independent
manual quick make and quick break type. MCCB shall be capable of breaking rated current at
0.3 pf at rated voltage. MCCB shall withstand the fault current envisaged for 415V system and
shall be current limiting type. All outgoing
outgoing feeders shall have earth fault protection.
Technical Specification:Sec-6, Electrical
Page 53 of 97
The MCCBs shall be suitable for panel mounting and shall be fixed type. All live parts shall be
enclosed in moulded case and all contacts shall be silver plated. The breakers shall be trip-free
trip
and with quick make & break operating mechanism. The MCCBs shall
sha be provided with
ambient temperature compensated bi-metal
bi metal overload releases and a magnetic short-circuit
short
release with inverse time characteristic. Releases shall be either static or microprocessor
based.
The operating handle shall be included with module
module door such that the door can be opened
only with the breaker in the OFF position. The MCCB handle after the breaker tripped due to
a fault shall occupy an intermediate position. The breaker shall be capable of interrupting a full
fault current corresponding
onding to the fault level specified.
MCCBs shall have a breaking capacity of 50kA at 415V. Current limiting MCCBs are not
permitted.
The LDB shall be consisting of following feeders:
Incomer
:
Bus coupler
:
Outgoing
:
63 A MCCB 10 Nos.
2 Nos. each of 600 A MCCB with over current and earth protection.
p
1 No. of 600 A MCCB
125 A MCCB
Page 54 of 97
Outgoing
Outgoing
:
:
SLDB, Type B (To be used for 250 W HPSV/MH light fittings inside the building)
Incomer
:
MCCB, 4 POLE, 63 A : 1 No.
Outgoing
:
MCB, DP (63 A) : 3 Nos.
Outgoing
:
MCB, SPN (16 A) : 6 Nos. per phase (Total 18 Nos.)
SLDB, Type C (To be used for 250W/150W/70 W HPSV/MH light fittings outside building)
Incomer
Outgoing
Outgoing
:
:
:
SLDB, Type D (To be used for 250 W HPSV/MH street light fittings)
Incomer
Outgoing
:
:
Sufficient number of SLDBs of different types (A, B, C and D) shall be used as per requirement
of different areas and sub-areas
sub areas of the coal handling plant. Exact quantity of SLDBs of various
types shall be finalized during detailed engineering. Bidder shall
shall consider as per requirement
subject to minimum one number of each type of SLDB.
RECEPTACLE DISTRIBUTION BOARD
Receptacles DB shall be suitable for 415V, 3 phase, 4 wire, 125 A, indoor type.
Board shall be single front, metal clad, front matched, dust
dust and vermin proof, draw-out,
draw
fully
compartmentalised and extensible on both sides, IP54 type enclosure.
Shall have isolated busbar chamber for main busbar at the top, running through out the length
of the board. Chamber shall have removable cover.
usbars shall have same cross section through out the length . Rating of the neutral busbar
Busbars
shall be 50% of the main busbar. Earth bus bar shall run in bottom chamber throughout the
length of the panel.
Shall have Moulded case circuit breaker (MCCB) triple
triple pole, air break type with independent
manual quick make and quick break type. MCCB shall be capable of breaking rated current at
0.3 pf at rated voltage. MCCB shall withstand the fault current envisaged for 415V system.
Generally all boards will have following
f
feeder arrangement.
Incomer
Outgoings
Page 57 of 97
socket outlets shall be controlled by rotary type switch mounted flush in the socket outlet box.
Operating handle of the rotary switch shall be fixed in such a manner that it will not be
possible either to insert or to withdraw
withdraw the plug without switching off the supply. All socket
outlets shall be supplied with heavy duty type plug and cap with chain. The isolating switches
shall be of industrial type of category AC 23. The isolator shall be housed in dust and verminvermin
proof sheet
heet steel enclosure suitable for terminating aluminum conductor cables either directly
by means of cable gland or through conduits. The current rating for the socket outlets shall be
20 A. Wherever called for HRC fuses shall be incorporated in the socket outlet box.
Inscription plate shall be provided indicating the voltage rating and feeder identifications for
the switch socket outlet.
MCB Controlled Socket Outlet
The MCB controlled socket outlet shall be similar to the above switch socket outlet and
provided with industrial type socket outlet with cover suitable for 240V, 20A single phase AC
and controlled through single pole 20A MCB.
Ceiling Fans and Regulators
Ceiling fans regulators shall be designed, manufactured and tested as per IS:374. The fans shall
have totally enclosed, capacitor start and run motors, suitable for operation on 240V, single
phase, 50 Hz AC system. The electronic type regulator shall have ON OFF position next to
the lowest speed contact, shall be provided with necessary harmonic filters and shall be
suitable for operation at 500C ambient temperature.
Down rods required for installation of ceiling fans shall be included by the Bidder.
Bidde
Lighting Poles
Steel tubular road lighting poles with single outreach shall be of swaged and welded
construction conforming to IS:2713-1969
IS:2713
with latest amendments.
The outer surface of pole above foundation shall be painted with two coats of red oxide
o
zinc
chromate primer paint as per IS:2713 and finished with two coats of synthetic enamel paint of
approved shall not be less than 100 microns.
The outer surface of the pole embedded in concrete foundation as well as the entire inner
surface shall bee painted with two coats tar based general type black paint.
The poles shall be provided complete with fixing arrangement for loop-in
loop in and loop out box and
lighting fittings. The Bidder shall submit a drawing indicating the general arrangement and the
finall design and arrangement shall be subject to purchasers approval.
The 415 loop-in loop-out
out box shall be weather-proof,
weather proof, dust tight, sheet steel enclosure suitable
for outdoor installation. The box shall have hinged front with front locking device. 3 Nos. open
Technical Specification:Sec-6, Electrical
Page 58 of 97
Page 59 of 97
Page 60 of 97
Page 61 of 97
Page 62 of 97
essentially have a 3 points suspensions system. The mobile luminaries carriage shall be
evenly balanced Rubber Paddle Guide Ring shall be incorporated as a buffer arrangement
between mobile luminaries carriage and mast shaft. This
This is to prevent damage to mast
surface during raising and lowering operation of mobile luminaries carriage.
g. The winch shall be provided with a separate control panel housing the control for the winch
drive motor and controls for switching the luminaries.
luminaries. It shall be complete with switch fuse
units/MCCBs, starters, contactors, etc that may be necessary to the operation of the light
tower. It shall be suitable for outdoor installation with IP-65
IP 65 degree of protection. It shall
be suitable for mounting on a suitable plinth adjacent to the high mast tower.
self sustaining type without the need
h. The winch must be of robust design and completely self-sustaining
for brake -shoe,
shoe, springs or clutches. It can be removed from the mast for maintenance if
the need arises in the future
future with the lower carriage on the top. The reduction gear of the
winch shall be of endless worm gear, operating in oil bath. The minimum safe working limit
of the winch shall not be less than 750 Kg.
when the mobile luminaries ring is
i. A minimum 6 turns of wire rope shall be on the drum when
fully lowered to rest on the luminaries supporting arms.
j. The winch is entirely selfself sustaining under all normal circumstances and it is not
dependent on the brake or restraining device that uncontrolled or dangerous runaway
runaw
speed shall occur in the event of the total failure of this device. Slip test on winch is carried
out by the manufacturer. Test certificate and report shall be submitted up, on request.
shall be at least 1.5 meter Per
k. The speed of the raising and lowering of lantern carriage ring shall
minute.
l. The high mast shall be fitted with flexible standard G.I / S.S. hoisting wire ropes of 7 x 19
construction with a minimum breaking strength of 1900 kgs. The combine lifting capacity of
the hoisting wire ropes shall have
have a factor of safety not less than 5 times the safe working
load (SWL) of the winch and shall be entirely suitable for the design application.
m. A transition plate shall be incorporated to balance the carriage from below of the mast.
n. Cable for lighting and winch control shall be as per approved scheme. The cables shall be
clamped or rolled so that no twisting of cables happens while the winch is hoisted or
lowered. Electrical cable shall be PVC coated round flexible cable suitable for small bending
radius. One standard multi core flexible electrical cable with 4 sq mm conducting areas
shall be provided for connecting of power supply to the light source and shall terminate at
the stationary connecting board in the base compartments.
o. The high mast shall be suitable for asymmetrical loading of with 16 nos. of 2 x 400 W MH
luminaries mounted on the lantern carriage. The luminaries shall be grouped in individual
240V RYB circuits fed through time switches. It shall be possible to switch the
t
lamp
bypassing the timer. The timer shall be programmable digital/analogue quartz controlled,
Technical Specification:Sec-6, Electrical
Page 63 of 97
high accuracy real time clock. It shall be set from 6 PM to 6 AM or any other intermediate
time. The tendered shall indicate the controls offered by him clearly
clearly in the offer.
p. The successful Bidder shall submit design and preliminary data for the design of foundation
of the high mast tower indicating the requirements of embedded inserts etc. The
foundation shall be designed and provided by the purchaser. Bidder to include foundation
bolts etc which shall be embedded in the foundation. Grouting of the bolts shall be done by
the Bidder.
q. The high mast shall be provided with lightning protection with airair termination and downdown
comers as per requirements of BIS and aviation warning lamps as per statutory and civil
aviation requirements. All metallic portions of the high mast shall be effectively earthed
and provided with two earth pits near the base. Effective earthing for luminaries shall be
provided during normal operation
o
and in lowered position.
(Part
r. Mast structure is designed to withstand wind velocity conforming to IS 875 (Part-III)-1987.
Mast Design Criteria
The high mast and the lowering system with the required number of floodlights and lamp
controls gears etc.
tc. In place shall be capable of withstanding a sustained basic wind speed of
180 Km/ hrs.
The design shall be in such a manner that it is capable of withstanding external forces exerted
by wind pressure and should have a minimum wind load factor of 1.25 and material factor of
1.15. Design life of mast shall be 25 years.
CONSTRUCTIONAL FEATURES OF MAST
The mast shaft shall be made with the best steel grade, in compliance with MS ISIS 2062/BSEN
10025 having adequate characteristics w.r.t. minimum yield strength, tensile strength and
minimum elongation for thickness.
The steel grade for accessories shall also be MS IS 2062 or equivalent, having adequate
characteristics w.r.t. minimum yield strength, tensile strength and minimum elongation for
thickness.
Each mast section to be delivered to site shall have a minimum length of 10.7 Mtrs. The Mast
sections shall have Single longitudinal weld from Bottom to Top.
The base shall have a flange plate for high mast onto the concrete foundation by anchor bolts.
The mast shall be fabricated and welded longitudinally to form a tapered section with
telescopic friction
on slip joints. All welding shall be to IS 816 / 82 having the following basic
requirements.
Page 64 of 97
The wall thickness of each section shall be designed to withstand the loads to which the high
mast shall be subjected to, but shall not be less than 8 mm for base section and 6 mm for
other sections and minimum base dia shall not be less than 530 mm.
Connection between the various sections, shall be achieved by telescopic slip joints, the
overlapping length being at least 1600mm slip joint assembly shall be perform at site. Shaft
section shall not be joined by circumferential weld or bolting at site.
The base plate shall be free from lamination
lamination and shall be single flange constructed with holes
jig drilled for anchor bolts passage. The bottom of the base mast section shall be securely
welded to the base plate by complete penetration fillet welding. The welded connection of the
base plate to the mast section shall fully develop the strength of the section.
The base section shall be equipped with a hinged service door. The service door opening shall
be complete with a close fitting weatherproof and equipped with a vandal resistant lock. The
service
ervice door shall not be smaller than 1400 mm x 300 mm the opening shall be reinforced by a
thick steel door frame.
Base plate of suitable dimensions and thickness, diameter, size and the placement of anchor
bolts shall be determined by calculations. Anchor
Anchor bolts shall be of deformed steel
reinforcement bars having the adequate characteristics w.r.t. tensile strength.
Welding of two or more anchor rods of shorter lengths to achieve the design length shall not
be permitted. No welding shall be allowed on
o the anchor rod body.
Adequate earthing and earthing terminal shall be provided within the access door area of each
Mast. All high mast shall be hot dip galvanized, in accordance with IS 2629 / TR 7 Timer control
panel shall be provided with overload and single phase preventor. Timer control panel shall
be outdoor type.
Motor capacity of the winch
Motor shall be of hoist duty and of adequate capacity with 15 % minimum margin over
mechanical power requirement. Minimum capacity of 2.2 kW shall be considered.
consi
4.15 EARTHING AND LIGHTNING PROTECTION
EARTHING PROTECTION
Bidder shall include complete earthing of WT substation, MCC rooms, Wagon tippler,
apron feeder & conveyor drives
etc. The
underground earthing mats also
shall be done by the Bidder. Risers shall be available at all the premises for
interconnection of own earthing network. However, Bidder shall provide
provide complete separate
earthing for transformer neutrals.
Bidder shall include the following in each and every substation:
Technical Specification:Sec-6, Electrical
Page 65 of 97
1.
2.
3.
Bidder shall include complete earthing material including earthing strips, earth electrodes
other accessories for treated earth pits, etc. and carry out earthing ring mains, earth pits,
interconnections, equipment earthing, all associated
associated civil works, etc at all the ubstations.
All the connections of earthing ring mains with available underground earthing grid of
respective substation/premise shall be under scope of the Bidder.
Separate dedicated treated earth pits shall be provided
provided for transformer neutrals. Two nos.
such earth pits shall be provided for each of the transformers. The treated earth pits shall be
consisting of 3 mtr 65 NB GI pipes, funnels, clamps, 3 mtr long 40 mm MS rod electrodes, MS
cover with lifting lugs, associated
assoc
civil works, etc.
All the equipment located in the WT premises / sub-premises
sub
e.g. 33 KV switchboard, LT PCCs,
busducts, transformer bodies, charger panels, DCDBs, LDBs, SLDBs, receptacles, control panels,
MCCs, etc shall be connected by the Bidder with earthing ring mains at least two different
points.
Electronic earthing shall be considerd for PLC, etc
Bidder shall also consider earthing of following equipment to be installed by the bidder.
33kV
kV WT switchboard at WT substation in switchgear cum MCC room
WT distribution transformers (2 nos.) Neutral as well as body earthing
415 WT SYSTEM PCC at WT SYSTEM substation in switchgear cum MCC room
Control panel for power distribution equipment at existing WT control room
LT busducts (2 sets)
Charger panels, DCDB, etc at WT substation in switchgear cum MCC room
Bidder shall consider earthing ring mains at each electrical premise and connect the electrical
equipment with the rings. The earthing ring
ring mains shall be connected with underground
earthing mats (consisting of 2x40MM dia to be installed by the bidder.. For transformer neutral
earthing, bidder shall consider dedicated plate earthing.
Bidder shall include complete earthing material including
including earth electrodes, risers, GI earthing
strips, other accessories, etc. and carry out main earth grid mat, earthing ring mains, earth
pits, risers, interconnections, equipment earthing, all associated civil works, etc within battery
limit of the package. Allll the interconnections with other earthing systems of the plant and
with existing systems shall be under scope of the Bidder.
The Bidder shall obtain the actual soil resistivity of the plant area by carrying out soil resistivity
tests and design the earthing
thing system accordingly.
Page 66 of 97
While designing the earthing system, Bidder shall note the following fault levels at 415 V bus
shall be 50 kA. Plant earthing system shall be designed such that overall earthing resistance is
less than 1(One) Ohm without interconnections.
interco
The materials shall be galvanized steel laid over the ground and mild steel buried inside the
ground/concrete.
Fault clearing time for sizing of earth conductors and for calculations of the maximum
allowable step and touch potential shall be taken 1 sec. Maximum allowable temperature rise
for steel bolted joints shall be taken as 3100C taking ambient temperature of 50oC.
The earthing system shall be generally designed on the basis of the following codes &
standards:
IS 3043 Code of practices for safety and standards
IEEE 80 Guide for safety in AC substation grounding
Indian Electricity Rules
Entire system shall be earthed so that the values of the step and contact potentials in case of
faults are kept within safe permissible limits.
limit
Parts of all electrical equipment and machinery not intended to be alive shall have two
separate and distinct earth connections each to conform to the stipulation of the Indian
Electricity Rules.
In case of HT system, E/F current will be made to flow through copper screen tape provided
over inner sheathing. Screen will be connected to earth bus at both ends. In case of LT the TNTN
S system will be followed, i.e. neutral bus of the switchgear shall be connected to switchgear
earth bus and then to DBs shall
sha be through armouring of cable.
Bidder shall submit the layout drawings of earthing network with supported calculations for
approval of purchares/consultant. Taking approval of Electrical inspector/CEA and providing all
inputs to them like data/drawings
data/drawing are under scope of the Bidder.
The materials shall be galvanized steel laid over the ground and mild steel buried inside the
ground/concrete.
Earthing of SLDBs, power receptacles, etc shall be connected with respective source LDBs
through armouring off cables.
Earthing conductors run on walls/floors/cable and equipment structures etc. shall be
supported at suitable intervals and painted with black oxide paint.
The armour of cables and all conduits for cables shall also be connected to the earthing mains.
m
A continuous earth strip shall run in each side of cable channel and in cable ducts/tray route.
All joints in the branch connections except at earthing electrode shall be welded and painted
black. At road/rail crossings earthing strips/rods shall be laid through conduits/concrete ducts.
Technical Specification:Sec-6, Electrical
Page 67 of 97
The armour of cables and all conduits for cables shall also be connected to the earthing mains.
A continuous earth strip shall run in each side of cable trenches.
All joints in the run of the main earthing conductors will be welded or brazed type. Connection
to equipment structure shall be bolted type. All welded joints
joints shall be protected from
corrosion by applying bitumen paint.
Earthing system shall be distinct and separate from the lightning equipment earthing system.
Earthing Conductors and Installation Accessories for Equipment Earthing System
All electrical equipment installed by the successful Bidder as well as equipment installed by
Purchaser shall be effectively earthed in conformity with relevant clauses of Indian Electricity
Rules (1956) and in accordance with IS: 3043 to the complete satisfaction
satisfaction of the Chief
Electrical Inspector to Government of Orissa State. All non-current
non current carrying metallic conduit
parts of various electrical equipment as well as cable armouring, metallic conduits, GI pipe,
cable racks, trays, brackets, supporting structures
structures etc. shall be effectively earthed.
Main earth mat comprising 40 mm dia MS rods and earth electrodes and riser upto + 1.0 M
level shall be supplied and installed by the ownr. All other equipment to complete the earthing
of equipment installed by the Bidder shall be in the scope of the Bidder. The Bidder shall also
connect his sub earth mat to the main earth mat provided by the Bidder.
Conductor size adopted for earthing ring shall in no case be less than that of the earth
continuity conductors connected
connected to it. The size of conductors used for overground sub earth
mat in switchgear rooms/ control rooms/ plant buildings/ areas shall be 65 mm x 8 mm
galvanized mild steel strips. 50 mmx 6mm galvanized MS strips will be used for earth buses
inside the buildings/
ldings/ floors/ platforms etc. and also for earth conductors laid along cable trays.
For buildings having a number of floors, separate earthing ring shall be established in each
floor and shall in turn be connected to the Purchasers earth mat.
Separate earthing system shall in no case have cross-sectional
cross sectional area less than 6 sq mm stranded
GI wire.
Size of earth conductors selected for system earthing and earthing of various equipments shall
be as follows.
Galvanized Iron flat conductor strips shall be used for neutral earthing. The minimum size of
conductors for neutral earthing of various transformers shall be as given below unless a higher
size is required from the viewpoint of higher available fault current.
tran
: 75mm x 10mm
LV neutral of 33/0.440 kV, 1600 KVA transformers
The minimum size of galvanized Iron flats for earthing of various equipment shall be as
follows:
Technical Specification:Sec-6, Electrical
Page 68 of 97
Ring mains
LT PCCs/board
Control Panels
LT Busducts
DC Distribution Board
LDB
SLDB
Push button station
Transformer bodies
Cable tray (running earthing)
:
:
:
:
:
:
:
:
:
:
75mm x 10mm
65mm x 8mm
50mm x 6mm
50mm x 6mm
50mm x 6mm
50mm x 6mm
25mm x 3mm
6 sq mm stranded
50mm x 6mm
50mm x 6mm
LIGHTNING PROTECTION
d plant structures including switchgear building and junction houses shall be
All buildings and
protected against atmospheric flash over and lightning strokes in such a manner as to
eliminate any danger to the personnel employed therein. Stipulations of IS : 2309 - 1969 shall
be followed.
A 'Faraday Cage' made of hot galvanised strip steel connected to all buried pipes and steel
structures crossing this cage ring shall be laid around plant as earthing device. This shall be
separate from the electrical equipment earthing ring
ri main.
Design shall be as per the standard like IS 2309 (latest revision) and Indian Electricity Rules.
All lightning arrestor earth leads of the plant shall be connected to this cage ring.
Air termination network should cover all salient points of the structure. All metallic structures,
ducts and the like above the roof of the structure shall be bonded to and form part of the air
termination network. Vertical air termination points shall project at least 30 cm above the
object on which it is fixed.
Down conductors shall follow the most direct path possible between air termination and earth
termination avoiding sharp bends. Down conductor shall have a testing point adjacent to the
earth electrode. Each conductor shall have an independent earth termination. All earth
terminations shall be interconnected.
Earthing electrodes and grid for lightning protection will be distinct separate from the earthing
system for earthing of electrical equipment and at no place will be connected to other
earthing system.
4.16
MISCELLANEOUS ELECTRICS
SAFETY
Page 69 of 97
All equipment shall be complete with approved safety devices wherever potential hazard to
personnel exists and with provision for safe access of personnel to and around equipment for
operational and maintenance functions. The design shall include all reasonable
reaso
precautions
and provisions for the safety of operating and maintenance personnel.
Special care shall be taken to make enclosed equipment proof against entry of rats, lizards and
other creeping reptiles which may create electrical shortshort circuits inside
side live equipment.
MINOR CIVIL WORKS
Minor civil works associated with cabling, earthing, conduit installation, illumination systems,
lighting poles, for buried cables, for erection of equipment supplied by the Bidder, foundation
of lighting masts/poles,
es, etc shall be included under scope of bidder. Similarly minor civil works
like widening of floor openings / cable trenches, wall opening for cables, minor chipping, etc
shall be included under scope of bidder.
LOCAL CONTROL STATION
Near all drives local
cal control stations shall be provided. Local stations shall have Cast
Aluminium body, dust and vermin proof, and structure mounting. Stat and stop push buttons
shall be mounted on front hinged gasketted and lockable door. Local/remote selector switches
shall
all be provided on local control stations. Stop push button shall be lockable type. In addition,
ammeters shall be provided on local control stations for HT drives. Suitable knockouts with
glands shall be provided on the bottom or top cover for cable entry.
entry. Terminals shall be suitable
for 2 cores of 2.5 sq.mm conductors with 10% spare terminals. Enclosure shall be conforming
to IP55 with proper rain canopy.
ELECTRICS OF DUST SUPPRESSION SYSTEM
Bidder shall include complete electrics of dust suppression systems coming in the scope within
the battery limit. Bidder shall provide complete electrics including MCC, drives/mechanism,
associated cabling & their termination, local DBs, all power and control ccessories, all related
annunciations, etc.
ELECTRICS OF AIR-CONDITIONING
CONDITIONING AND VENTILATION SYSTEM
Bidder shall include complete electrics of air-conditioning
air conditioning system and ventilation system.
Complete electrics for the following shall be included:
Ventilation system for the switchgear cum MCC room at WT SYSTEM substation
Exhaust fans for the two numbers transformer rooms at WT SYSTEM substation
Air-conditioning
conditioning system for the battery and battery charger room at WT SYSTEM
substation
stem for dust suppression MCC room
Ventilation system
Page 70 of 97
Bidder shall include complete electrics of hoists coming in the scope within the battery limit.
Bidder shall provide complete electrics including source feeders, associated cabling & their
termination, local DBs, all power and control accessories, all related
related annunciations, etc.
All the hoist control panel shall be located at workable height and platform shall be provided
for each hoist at one point for maintenance purpose.
33 KV OVERHEAD LINES
In coming power supply to Wagon tippler, apron feeder, & conveyor system will be taken
from 33KV Lean Slurry substation located near the 220KV switch yard with provision of
lighting arrester, load brake switch, 33KV VCB, CT,PT relay and control panel housed in a
suitable building comes under bidders scope. Laying
Laying Power cable/Transmission line from
the substation to wagon tippler area along with provision of transformer, switch gear system
& panels will be the scope of the bidder. Approximate distance from the substation to the
wagon tippler area will be 2.00 Km.
Km. However, actual distance & Suitable route for laying of
cable will be assessed by the party in consultation with NALCO. The transmission line(33 KV)
where ever crossing roads shall be through double run underground cabling arrangement as
per relevant regulations.
gulations.
The bidder shall also execute underground cabling and other necessary work for crossing
railway track of the existing Intake Pump House and Ash pond 33KV overhead transmission
lines with provision of DP,lighting arrester and associated switchgear.
switchge
Cost of power cable/transmission line shall be in scope of bidder.
RS joist poles of size to 200 X 100 mm shall be erected by excavation of pit size 700 mm X
700 mm to a depth of 1/5th of the pole. The pole shall be erected upright to the plumb. MS
channel shall, be used for V type cross arm of size 100 X 50 X 6.4 mm. The spacing between
two extreme conductors shall be 1100 mm and the 3rd conductor shall be provided on the
top of the mast. Suitable porcelain pin type insulators shall be used. A continuous
con
earth wire
shall be provided for RS joist pole earthing and securely fastened to each pole and
connected to earth, at 4 points in every 1.6 km, the spacing between the points, being as
nearly equidistant as possible. Galvanized steel guard wire mesh
mesh having breaking strength of
635 kg shall be connected to earth at different points and shall be used in over head while
crossing street/passage. Suitable lightening arrester shall be provided in the four pole
structure.
Page 71 of 97
Technical details of HT transformer and other switch gear will be submitted to NALCO / RITES
for its approval. The conductor for 33KV line shall be of ACSR
ACSR (dog/Rabbit) type.
The HT transformer (33KV/0.44KV)
(33KV/
shallll be located in the near the wagon tippler area. The
switch gear will be designed in conformity to CEA norms having provision of LA, PT, CT, ISO etc.
Fencing and development of switch gear will be the scope of the bidder. The switch gear will
be located near wagon tippler area.
Room size to be decided by the bidder to house all required equipments (HT & LT switch
gears) at the ground floor.
WT Control room and operating panel will be located at
at first floor of the building.
Bidders are also advised to visit the site and assess the actual quantum of work to be done for
this diversion and include accordingly.
The operation of the WT SYSTEM plant shall be monitored and controlled from the proposed
WT control rooms by means of VDU operator interface on a microprocessor based
programmable logic controller (PLC). The system shall be envisaged for the purpose of initial
operation, protection and interlock, data acquisition, close loop control, data archiving,
a
etc for
fully automatic operation. The system shall be capable of monitoring and displaying the status
of equipment, including the analog and digital signal displaying of status in the form of
diagram, trend bar chart, overview, logs, etc with the
the help of CRT, keyboard, mouse and
printers.
Necessary hardware and software license of the proposed PLC shall be provided.
provided PLC
programme, ladder logic and control philosophy shall be submitted by the bidder for approval
of NALCO/RITES.
The preferred make of PLC shall be GE-FANUC
GE
make.
i)
ii)
iii)
iv)
v)
vi)
vii)
Type
Quantity
System Voltage
Maximum system voltage
Continuous current
Rated short time current rating
Interrupting capacity at 36 kV
Page 72 of 97
The VCB shall be indoor drawout type with numerical type over current (50+51), earth fault
(51N) relay with timer for instantaneous overcurrent protection as we as master
trip and trip circuit supervision relay. The VCB shall be capable of withstanding through fault
current of 31.5kA for 3 sec. and shall be provided
with
remote
closing
and
tripping facilities. Under voltage relay with timer shall be provided in line PT.
transformer
nsformer differential protection shall also be provided. PT shall be provided with protection
core of 3P class and metering core of CL 0.5. CT shall be provided with protection core of
5P20 class and metering core of CL 0.5. For transformer
transformer differential protection PS class CT shall
be considered.
The closing coil of the breaker shall be suitable for operation between 85 to 110 percent
of 220 V DC control power supply voltage available from batteries.
The circuit breaker shall have redundant shunt trip device. The trip coil shall be designed
to operate satisfactorily when the voltage at the terminals of the shunt trip coils is
between 70 to 110 per cent of 220 V DC control power supply voltage available from
batteries. VCB
B shall be provided with dual trip coil. For actuation of trip coils, similar set of
contacts shall be provided separately for each trip coil. Hence, necessary arrangement for
duplication of contacts shall be done inside the panel
panel if multiple No. of similar contacts are not
available.
The circuit breaker shall be power operated with motor wound spring closing mechanism with
electrical spring release coil. The motor shall be suitable for operation on 240 V AC single phase
supply. Means shall however be provided for manual operation of the breaker under
emergency or for testing and adjustments.
The operating mechanism shall be anti pumping and trip free type.
perated mechanism shall be so designed that the spring gets
The spring operated
recharged immediately after closing.
automatically
Imploding type surge suppressor and earthing truck with full capacity circuit breaker, three
(3) Nos. single phasee PT, selector switch and test plugs shall be considered at the outgoing side of
VCB.
Both incoming and outgoing terminals of VCB shall be suitable for terminating 33 kV (E)
grade XLPE insulated PVC sheathed, 3core, aluminium conductor
condu
cables.
The circuit breaker shall be provided with necessary auxiliary switches for indication,
control, interlocking, protection and alarm. Six spare auxiliary contacts, three (3) NC and
three (3) NO shall be left
eft free in the breaker. All the contacts shall be wired to the terminal
block.
Space heaters to prevent moisture condensation within the enclosure shall be provided in
relay and control cubicle. Heaters shall be suitable for operation
operation from 230 V, AC 50 Hz, single
phase supply.
Page 73 of 97
One (1) set of relay and control panels consisting of two (2) feeders and PT complete
with mimic buses, instruments, controls, indication, alarm annunciation relays and
alarm facia and protection relays as required for the
the 33 kV feeder for the proposed plant and
as described below shall be provided.
The mimic
diagram
shall
provide
single
line representation of the 33 kV
system. The control and relay panel shall be located inside the room for new 33 kV VCB
panel.
The relay and control panel shall be floor mounted type, having sheet steel of 2.5 mm
thickness. A equipment shall be mounted such that removal and replacement
replacement may be
accomplished individually without interruption of service to adjacent equipment. The relay and
control panel shall have rear access.
Test devices shall be provided for C.T. circuits. CTs shall not be open circuited
circuited during testing
operation.
Adequate illumination shall be provided inside each cubicle. CFL lamps suitable for 230 V,
50 Hz, single phase supply shall be provided.
Potential circuits for
suitable MPCB/MCB.
instrumentation and
and for metering each shall be protected
by
Annunciator shall be suitable for 220 V DC operation. It shall have a single DC alarm common to
all points.
Space heaters to prevent moisture condensation within
within the enclosure shall be provided in
relay and control cubicle. Heaters shall be suitable for operation from 230 V, AC 50 Hz, single
phase supply.
A relay shall be numerical type having communication port conforming
protocol as per IEC61850 for direct interfacing with plant
commun
communication
Page 74 of 97
front design. The distribution board shall be suitable for cable entry from the bottom.
Devices requiring operation shall
shall be located in between 450 mm and 1900 mm from the floor
level .
The ACDB shall have indicating voltmeter with selector switch, PT, MPCB & MCB at the line
side of the distribution board. Ammeter with selector switch, CT, MPCB &
MCB shall
also be provided. These instruments shall be flush type located on the front door of the
compartments. The sizes of ammeter and voltmeter shall be 96 mm x 96 mm. Phase
indicating lamps shall be provided
vided at the bus side of incomer.
The ACDB shall be fabricated from minimum 2.0 mm thick CRCA sheet steel with load
bearing members comprising 2.5 mm thick CRCA sheet steel. The degree of
protection
shall be IP:54.
A the outgoing feeders shall be of MCCB/MCB unit.
Power circuit isolation shall be possible without opening the front door and shall have
provision for padlocking in OFF position with the door closed. ON/OFF indications
shall be provided for a feeders by means of cluster LED lamps.
The main phase busbars and tappings shall be made of aluminium having cross sectional
areas to be substantiated during engineering
engineering but in no case the current density shall
be more than 80 A/sq cm. The busbars shall be suitably supported on non hygroscopic
moulded glass reinforced plastic insulators so as to be capable of withstanding
withstand
dynamic
forces due to 50 kA through fault short circuit. All joints shall be coloured PVC taped.
Temperature rise of busbars/joints while carrying the rated current shall not be more
than 45C over maximum ambient
ambient temperature of 45C when measured by thermometer.
Tappings from the main busbars to individual feeder compartments shall be by means of
insulated single core copper cables with stranded conductor for feeders upto 100 A ratings
above which aluminium busbars shall be used. All copper to aluminium joints shall be
provided with bimetallic nuts/bolts/washers.
A continuous 50 mm x 10 mm aluminium earth bus shall be provided throughout the
length
gth of the panels and shall be located in a separate chamber at the bottom with
removable front cover. Provision shall be kept for taking earth connections to external earth
mat. PVC insulated (Green coloured) copper wires shall
shall be used to connect all noncurrent
carrying metallic parts, doors, etc to the earth bus.
All relays, instruments, meters, pushbuttons, switches and other devices of any feeder
shall be located on the respective compartment only.
All operating handles, control switches, pushbuttons, indicating lamps, instruments, meters
etc shall be mounted on the front of the cubicles.
Page 75 of 97
stands shall
be made of good quality teak wood suitably treated with two coats of
linseed oil and three coats of antisulphuric acid paint.
coated
Inter row and intertier connectors for the batteries shall be made of copper
with lead. The terminals of each cell shall be indelibly identified for polarity. The
terminals of battery outgoing leads shall have provision for connecting lead coated
copper bars which shall be suitably extended upto the room wall for termination of external
aluminium conductor, XLPE insulated cables. Suitably terminals shall also be provided for taking
takin
external connections from cell by aluminium conductor XLPE insulated cables.
The cells shall be delivered in dry and discharged condition. Sufficient quantity of electrolyte
ready to fill condition shall be supplied for the
the first filling of the batteries in nonreturnable
airtight plastic/polypropylene containers. Ten (10) percent extra electrolyte shall
also be
provided.
Page 76 of 97
Encl: IP-45
Control voltage 220 V DC
Page 77 of 97
Page 78 of 97
Fire Prevention:Proper design and use of quality material, equipment so as to avoid overloading in
Distribution board, wiring system including sub main, switch & sockets shall be ensured by the
bidder.
Insulating mats in front of PCC, MCC or control panel, protective rubber gloves, earth rods,
artificial respiration apparatus, line mans belt etc shall be provided in substations by the
bidder.
re extinguishers for various switch gear location, substations, PCC, MCC suitable for
Fire
electrical fire (class C)
C) like dry chemical powder, carbon-dioxide,
carbon dioxide, carbon-tetra
carbon
chloride type
shall be provided along with fire buckets filled with sands.
Comprehensive fire protection system in conformity with the requirements of national
building code, ECBC 2007 shall be ensured by the bidder.
5.0
Page 79 of 97
5.1 Inspection
Extent of inspection
The extent of inspection & testing by the Purchaser shall vary from equipment to equipment
as per design requirements.
However, indicative extent of inspection for electrical equipment is furnished below:
Extent of inspection to be carried out shall be finalised with the Contractor after award of the
contract on the basis of scope of supply, technical specification and approved GA drawings.
However, in case of similar bulk manufactured items, methods of sampling for inspection of
different lots shall be governed by relevant Indian or international
international standards.
In case of critical components, the Purchaser reserves the right to undertake 100% inspection.
Final inspection & testing shall be done as per the following:
Verification of test certificates
Visual, Workmanship & painting
Dimensional
Witnessing of routine/acceptance/type/special tests as per relevant standards.
Witnessing of proto-type
type tests, as applicable
Verification of type test certificates for identical equipment
Approved QAP
The inspection shall be carried out on the basis of QAP dully approved by Purchaser /
consultant.
INSPECTION CATEGORIES
All the electrical equipment have been classified in three categories for inspection and issuing
dispatch clearance by the Purchaser/consultant. The three categories are:
Category-A
All the tests shall be inspected by the Purchaser/Consultant. Dispatch clearance shall be given
by Purchaser/Consultant
haser/Consultant after the equipment is inspected and found as per requirement and
as per TS. All types tests certificates shall e submitted by the Bidder in this case.
Category-B
Inspection shall be carried out by prime bidder and inspection waiver certificate
certificate shall be issued
by Purchaser/Consultant based on type test certificates and routine tests certificates furnished
by the Bidder. Purchaser/Consultant shall issue dispatch clearance accordingly.
Category-C
Page 80 of 97
Dispatch clearance shall be given by Prime bidder without any certificates based on technical
data sheet furnished by the Bidder.
5.2
S. N.
DESCRIPTION
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
HT CABLE
LT MOTORS
LT POWER AND CONTROL CABLES
MCC
TRANSFORMER
PLC & CONTROL DESK
UPS
ON LOAD 33 kV ISOLATOR
TRAILING CABLE / FLEXIBLE (EPR) CABLE
PDB/LDB/SLDB/AUX. PDB
SIGNAL, INSTRUMENTATION AND OTHER SPECIAL CABLES
CABLE ACCESSORIE
LIGHT FITTINGS
EARTHING AND LIGHTNING PROTECTION MATERIALS
FIRE SEALING MATERIALS
LOCAL PUSH BUTTON STATIONS
POWER SOCKET CABINET AND LIGHTING CABINET
CONTROL AND RELAY PANEL
415V FEEDER PILLAR
33KV VCB
LT DISTRIBUTION BOARD
33KV LIGHTENING ARRESTER
33KV ISOLATOR AND EARTH SWITCH
33KV CT,PT
BATTERY,BATTTERY CHARGER,DCDB
FIRE EXTINGUISHER
JB,RUBBER MAT,DANGER BOARD,FIRE BUCKET,FIRST AID
BOX,HAND GLOVES,SHOCK TREATMENT CHART,DISCHARGE
ROD.MEGGAR
INSPECTION
CATEGORY
A
B
B
A
A
A
A
A
A
B
B
C
C
C
C
B
B
A
A
A
A
B
B
B
A
C
C
Testing
General
Test of all equipment shall be conducted as per latest BIS. Wherever no such standard exists,
tests shall be as per International Standards like IEC/DIN/BS/IEEL/JIS, etc.
All routine tests shall be carried out at manufacturer's works in presence of Purchaser or his
representative.
Page 81 of 97
The Bidder shall submit type test certificates (not more than 5 years old) for similar equipment
supplied by him elsewhere. In case type test certificates
certificates for similar equipment is not available,
the same shall be conducted in presence of Purchaser or his representative, without any
financial implications to Purchaser.
The Bidder shall be responsible for satisfactorily working of complete integrated
integr
system and
guaranteed performance.
Site Tests and Checks
General
All the equipments shall be tested at site to know their condition and to prove suitability for
required performance.
The test indicated in following pages shall be conducted after installation. All tools, accessories
and required instruments shall have to be arranged by contractor. Any other test which is
considered necessary by the manufacturer of the equipment, contractor or mentioned in
commissioning manual has to be conducted at
a site.
In addition to tests on individual equipment, some tests/checks are to be conducted /
observed from overall system point of view. Such checks are highlighted under miscellaneous
tests but these shall not be limited to as indicated and shall be finalized
finalized with consultation of
client before charging of the system.
The contractor shall be responsible for satisfactory working of complete integrated system and
guaranteed performance.
All checks and tests shall be conducted in the presence of clients
clients representative and test
results shall be submitted in six copies to client and one copy to Electrical Inspector. Test
results shall be filled in proper Performa.
After clearance from Electrical Inspector system/ equipment shall be charged in step by step
method.
Based on the test results clear cut observation shall be indicated by testing engineer with
regard to suitability for charging of the equipment or reasons
reasons for not charging are to be
brought by the contractor.
Trial Run Test
After the successful test of each equipment as per standard test procedure the entire control
system shall be put on trial run test on actual site conditions and operation of the system.
sy
Acceptance Test
Page 82 of 97
The acceptance test on the system shall be carried out by the supplier as per mutually agreed
test procedures to establish satisfactorily functioning of the system as a whole and each
equipment as part of the system.
Site Tests
The tests to be carried out on the equipment at pre-commissioning
pre commissioning stage shall include
following but not limited to the following:
MCC
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
MOTORS
1. IR test of stator and rotor windings.
2. Ensure that checking/testing of associated switchboard,
switchboard, cables, relays /meter
interlocks as mentioned in relevant are completed.
3. Check tightness of cable connection
4. Winding resistance measurement of stator and rotor.
5. Checking continuity of winding.
6. Check tightness of earth connections.
7. Check space heaters and carryout heating of winding (if required)
8. Check direction of rotation in de-coupled
de coupled condition during kick start
9. Measure no load current for all phases.
10. Measurement of temperature of body during no load and load conditions.
11. Check for tripping of motor from local/remote switches and from
electrical/technological protection.
12. Checking of vibration
13. Checking of noise level
14. Shaft voltage measurement (if required)
15. Tan delta test, if required
Technical Specification:Sec-6, Electrical
Page 83 of 97
16. During load running, measurement of stator and bearing temperatures (if applicable)
for every half an hour interval till saturation comes.
17. Checking tightness of foundation bolts
18. Check operation of speed switch (if there)
19. Check continuity of temp. detectors.
20. Check alignment, paralleling of
of shafts, level of lubricating oil etc. as per manufacturer's
manual
21. Check for polarisation index of stator winding, R10/R1 by motorised megger (The value
should not be less than 2.0). R60/R10 absorption co-efficient
co efficient shall not be less than 1.5.
TRANSFORMER
IR test on each winding to ground and between windings.
1.
2.
Turns ratio test on each tap
3.
Polarity and vector group test
4.
Measurement of winding resistance by Kelvin bridge
5.
IR, wiring and operational tests on all control devices in control cabinet,
cabi
oil level
indicator, winding and oil temp. indicators etc.
6.
Checking of earthing wrt transformer tank (flexible from top cover to tank) other
parts, neutrals.
7.
Testing of buchholz relay for alarm and trip conditions.
8.
For bushing CTs, tests applicable shall be as for current transformers.
9.
Setting of oil/winding temperature indicators, level gauge and checking of alarm/trip
circuits.
10. Check insulators for cracks.
11. Checking for oil leakage and arresting of leakages (if there)
t
12. Checking of operation of all valves.
13. Checking for open position of all the valves (except drain and filter valves)
14. Filtration of oil by using line filter, vacuum pump, and heater set.
15. BDV test on oil samples from top and bottom.
16. Checking of oil for acidity, water content tan delta etc. as per IS 335.
17. Measurement of magnetising current and no load loss.
18. Measurement of PI value.
19. Checking of silica gel breather.
20. Checking of noise level at no load and at full load.
21. Checking of air circulation conditions
c
for indoor transformers.
22. Conducting magnetic balance test
23. Checking of other points given in manufacturer's commissioning manual.
24. Frequency response analysis for HT transformers (at manufacturers works)
UNINTERRUPTED POWER SUPPLY (UPS)
1.
Visual check
IR value by megger
2.
3.
Current limit test
4.
Ripple test
5.
Supply variation
Technical Specification:Sec-6, Electrical
Page 84 of 97
6.
7.
Functional test
Capacity test wrt time
PDB/LDB/SLDB/AUX.PDB
1. IR test before and after HV test.
2. HV test with 2.5 kV megger
3. Functional test for all feeders
4. Testing and calibration of all meters
5. Checking and calibration of overload relays and protective relays as per supplier's
commissioning manuals.
6. Check operation of contactors from local and remote points
7. Checking of interlockings between incomers/bus coupler
coupler and other feeders.
8. Test to prove interchangeability of similar parts
9. Tests to prove correct operation of breakers at minimum and maximum specified
control voltages
neutral earth bus, cable armour, location of E/F
E/ CT
10. Checking of earthing connection for neutral-earth
etc. as per the scheme.
11. Check test, service and drawout position of all the breakers and operations of
mechanical flag indicator and electrical indication lamps.
12. Check functioning of various elect. schemes like autochangeover signalling etc.
13. Breaker : IR value checking with breaker ON. Phase to phase & phase to earth and
between phases in off position
CABLES & CABLE SUPPORTING STRUCTURES
1. Checking of continuity/phasing and IR values for all the cables before and after HV test.
2. Checking of earth
arth continuity for armour.
3. Check for mechanical protection of cables.
4. Check for identification (tag number system) distance placement of cable marker, cable
joint etc. as per the cable layout drawing.
5. Check earthing of cable structures.
6. Check clearances
ces from light fittings for cable structures
7. Check proper fixing of cable structures.
8. Check for proper drainage and removal of water from cable trenches
Page 85 of 97
9.
SN
Title
Code of practice for electric al wiring installations.
3 IS : 8081 1976
4 IS : 8884 1978
9 IS:3646(Part 1) 1966
10 IS:3646(Part-3) 968
11 IS:3646(Part-3)-1968
12 IS:4347 1967
Page 86 of 97
SN
Title
Code of practice e for industrial lighting.
Code of practice e for library lighting.
Code of practice for selection, installation and
maintenance of switchgear and control gear; General
16 IS:10118(Part-2)-1982
1982
17 IS:101118(Part-3)-1982
1982
18 IS:10118(Part 4) - 1982
19 IS:4146 1983
20 IS: 4201 1983
21 IS:5547 1983
22 IS:2309 1989
23 IS:3043 1987
24 IS:5216(Part01) 1982
26 IS:3696(Part-2) 1966
27
28
29
30
31
32
33
34
35
36
37
38
Page 87 of 97
SN
Title
39 IS:4237 1983
40 IS:675(Part-1) 1973
41 IS:6875(Part2) 1973
42 IS:6875(Part-3)-1980
43 IS:10027-1981
44 IS:4064(Part 1) -1978
1978
45 IS:2675 1983
46 IS:8828 1978
48 IS:12640 1988
49 IS:2959 1985
50 IS:2516(Part01/Sec 1
1985
51 IS:12021 1987
52 IS:5039 1983
Page 88 of 97
SN
Title
Factory built assemblies of switch gear and control
gear for voltages up to and including 1000 v AC and
1200 v DC : General requirements.
55 IS:8544(Part 1) 1977
56 IS:8544(Part 2) 1977
57 IS:8544(Part 4 ) 1979
POWER CABLE
58 IS:694 1990
59 IS:1554(Part 1) -1988
1988
60 IS:4288 - 1983
60 IS:4289(Part 1) 1984
Conduits for
requirement.
electrical
installations:
General
62 IS:9537(Part 2) 1981
Page 89 of 97
SN
Title
Flexible (pliable) non-metallic
metallic conduits for electrical
installations.
65 IS:3419 1989
65 IS:5133 (Part-1) 1969
66
67
67
68
68
69
IS:2412 1975
IS: 371 1979
IS: 3854 1988
IS: 4615 1968
IS:4160 1967
IS:1293 1988
72 IS:9974(Part 1) -1981
1981
72
73 IS: 1258 1987
73 IS: 3323 1980
76 IS:6616 1982
Page 90 of 97
SN
82 Is:3528 1966
83 IS: 3553 1966
84 IS: 9030 1976
85 IS: 7537 1974
86 IS: 9583 1981
87 IS: 9583 1981
Electric Appliances
88 IS: 6236 1971
89 IS: 1248 (Part 1) 1983
Title
Page 91 of 97
SN
Title
AC electricity meters: Volt-ampere
ampere hour meter for
restricted power factor range : General requirements.
Current
transformers:
transformers.
Current
transformers:
Protective
current
transformers for specific purpose applications.
Fuses
108 IS: 9224 (Part 1 ) 1979
109 IS: 9224 (Part 2 ) 1979
Protective
current
current
D Type fuses
Methods of tests for IC Engines
Code of Practice for Selection ,installation &
maintenance of Transformers - Selection
Page 92 of 97
SN
Title
Code of Practice for Selection ,installation &
maintenance of Transformers - Installation
116 10322/Pt.3/1984
117 10322/Pt.4/1984
119 1239/Pt.1/1990
120 1239/Pt.2/1992
121 1255/1983
122 12640/Pt2/2001
123 13118/1991
124 1367/Pt.3/1991
125 1367/Pt.XIII/1983
126 13925/Pt1/1998
127 13925/Pt2/2002
Page 93 of 97
SN
Title
Specification for Low voltage switchgear and control
gear - General Rules
129 13947/Pt.2/1993
130 13947/Pt.3/1993
131 1445/1977
132 1460/2000
133 14772/2000
134
135
136
137
2016/1967
2026/Pt.1/1977
2026/Pt.2/1977
2026/Pt.3/1981
139 2086/1982
140 2121/Pt.1/1981
141 2121/Pt.2/1981
142 2268/1994
143 2551/1982
144 2713/Pt.1 to 3
145 3043/1987
146 3419/1988
Page 94 of 97
SN
148 3764/1992
149 3837/1976
Title
AC Metal Enclosed Switchgear and controlgear for
rated voltage Above 1kV and upto and including 52kV
Code of Safety for excavation work
Accessories for rigid steel conduits for electric wiring
150 3842/Pt1 to Pt.12/1967Pt.12/1967 Application guide for electrical Relays for ac system
1977
151 3854/1997
152 398/Pt.1/1976
153 398/Pt.2/1976
154 398/Pt.3/1976
155 398/Pt.4/1994
156 398/Pt.5/1992
157 4540/1968
158 4722/2001
161 5300/1969
162 5613/Pt.1/Sec.1/1985
Page 95 of 97
SN
Title
Code of Practice for Design , Installation and
Maintenance of over head power lines - Lines upto
and including 11kV: Installation and Maintenance
164 5613/Pt.2/Sec.1/1985
165 5613/Pt.2/Sec.2/1985
166 5613/Pt.3/Sec.1/1989
167 5613/Pt.3/Sec.2/1989
168 6639/1972
169 7098/Pt.1/1988
170 7098/Pt.2/1985
171 7098/Pt.3/1992
172 7935/1975
173 808/1989
Page 96 of 97
SN
Title
Specifications for Low Voltage Switchgear and
Controlgear Assemblies : Particular requirements for
Equipments Where unskilled Persons have access for
their use
175 9537/Pt.3/1983
176 9537/Pt.4/1983
177 9537/Pt.4/1984
178 9974/Pt.1/1982
Electrotechnical
definitions.
Electro
technical
Measurements.
Electro technical
aspects.
vocabulary
Fundamental
vocabulary:
vocabulary:
Lighting
Electrical
General
Page 97 of 97
SECTION 7
(CIVIL)
1.0
1.1
1.2
GENERAL
This section of the bidding document deals mainly with the technical specification needed
for the design and preparation of detailed drawings, getting the design and drawings
approved by the Engineer, fabrication, erection and construction of the necessary civil,
structural
tural and architectural works associated with the wagon Tippler plant.. The work shall
have to be carried out both below and above ground level and shall be involving, basements,
equipment foundations, slabs, beams, columns, footings, rafts, walls, steel frames, brick
walls, stairs, trenches, pits, finishes, complete architectural aspects, drainage, sanitation,
water supply (from terminal points to various buildings, conveyor galleries) and all other civil
and structural works associated with the wagon Tippler
Tip
Plant.
The specifications are intended for the general description of the work, quality and
workmanship. The specifications are not, however, intended to cover minutest details and
the work shall be executed according to the relevant latest Indian Standard Codes / I. R. S. /
I. R. C. specifications. In absence of the above, the work shall be executed according to the
best prevailing local Public Works Department practices or to the recommendations of
relevant American and British Standards or to the
the instructions of the Engineer. List of I. S.
Codes to be followed is mentioned in the Technical Specifications. The Contractor is
expected to get clarified on any doubts about the specifications, etc. before bidding, in
writing with the Employer in respect
respect of interpretation of any portions of this document.
2.0
2.1
The layout and levels of all structures, etc. shall be made by the Contractor at his own cost
from the general grid of the plot and bench mark given by the Engineer. He shall provide all
instrument, materials and men to the Engineer for checking the layout and levels. However,
the Contractor shall be fully responsible for correctness of layout and levels.
The contractor has to mobilize well qualified survey team along with the survey equipment
for day today survey work. They should use Total Station survey instrument for this
purpose.
The contractor has to setup his own laboratory to facilitate the checking of quality of civil
works with equipments for checking of aggregate,
aggregate, sand, concrete cube, etc.
Area cleaning including jungle,rubbish,grass,trees etc are to be included in the scope of
bidder.
2.2
2.3
2.4
3.0
3.1
3.2
3.3
DRAWINGS / DOCUMENTS
The drawings included in the Bidding Document provide a general idea about the work to be
performed under the scope of this contract. These are preliminary drawings for bidding
purposes only and are by no means the final drawings or show the full range of the work
under the scope. Work has to be executed according to drawings prepared by the contractor
co
and approved by the Engineer.
Conceptual arrangement of civil works supported by calculations shall be submitted along
with tender bids. Later on, detailed construction drawings and design calculations for all civil
works for static as well as dynamic analysis (wherever essential) shall be submitted for
approval prior to undertaking construction work.
Design calculations shall be done in STRAPP / M.S. Office (latest version) and Drawings shall
Page 1 of 21
3.4
3.5
3.6
3.7
4.0
WORK DESCRIPTION.
It includes the Civil, Structural and Architectural works related mainly to the following areas
(but not limited to):
4.1
Wagon Tippler Hopper, Machinery Hatches and Underground Tunnel
Wagon Tippler hopper and machinery hatches shall consist of underground portion, which
shall be of R. C. C., and above ground portion, which shall be of structural steel shed covered
with Aluminium Industrial troughed sheets. It essentially consists of R. C. C. frames with R. C.
C. wall panels on the sides and R. C. C. raft at the bottom, fixed to the frames. The top beam
of the R. C. C. frame supports the rail supporting beams and the hopper. Minimum thickness
of R. C. C. raft at bottom shall be 600 mm. Minimum thickness of RCC side walls shall be 600
mm at bottom and 300 mm at top.
No columns shall be provided inside the Machinery Hatches.
The vertical and inclined portion of coal hopper shall be provided with 50 mm thick guniting
(shotcreting). Details of shotcreting have been given elsewhere in this specification
Expansion joints shall be provided at a maximum distance of 40m unless otherwise
otherw
instructed. 600 mm wide water stop fabricated with 22G copper plate with bitumen board
fillers and polysulphide sealing compound as specified elsewhere shall be used as expansion
joint material. Floor shall be provided with cross slope not flatter than 1 in 50 towards side
drains. Side drains shall be sloped towards sump where sump pumps as specified elsewhere,
shall be provided. The slope of side drains shall not be flatter than 1 in 400. Arrangement
shall be made for disposal of water right up to the discharge point. Side drains and sump
shall have removable type steel grating cover. Gratings shall be galvanized to grade 610
gm/m.2 Water proofing / Damp proofing of under ground portion of hopper and machinery
hatches, tunnels, underground (i. e. basement)
basement) portion of transfer houses shall be done by
providing the following treatments: Chemical injection grouting for inner faces (details as
specified elsewhere). Polymer modified cementitious coating on earth side face as per the
following :
ter surface of walls, frames and roof slabs coming in contact with earth,
1). On the outer
polymer modified cementitious coating in two layers as specified and as per manufacturers
specifications shall be provided directly on the concrete surface.
(2.) 50 mm thick P. C. C. (1 : 2 : 4 with 10 mm nominal size stone aggregates) shall be
provided under the raft i.e. over the lean concrete, followed by polymer modified
Page 2 of 21
4.2
Overhead conveyors shall be located in a suitably enclosed gallery of structural steel. The
overhead gallery shall consist of two vertical latticed girders having rigid jointed portal frame
at both ends. Cross beams at floor level supporting conveyor stringer beams shall be made
of single rolled steel beam or single channel section (ISMB or ISMC) or plate girder.
Horizontal bracings are to be provided at top & bottom plan of the gallery (latticed girders
shall be braced together in plan at the top and bottom).Common end portal frame shall not
be used for adjacent conveyor spans. Roof trussshall be provided at upper
upp node points of
latticed girders to form an enclosure. Themaximum span of overhead gallery shall be limited
to 25 meters unless higher spanis required due to site conditions, which shall be subject to
approval of the Engineer.The gallery should as far as possible be erected as a box section
keeping all thevertical and horizontal bracing tied in proper position. The gallery should be
checkedfor all erection stresses that are likely to develop during handling and erection and
ifrequired, temporary strengthening
strengthening of gallery members during erection shall be made.Seal
Technical Specification:Sec-7, Civil
Page 3 of 21
plates under the conveyor galleries shall be provided in such a way thatcomplete gallery
bottom shall form a leak proof floor.
The ground conveyors shall be located in suitably enclosed gallery of structural steel
consisting of rigid portal frames spaced at regular intervals and suitably braced. Plinth
protection along with drains shall be routed along the ground conveyors. Hand railing
r
should
not be supported on conveyor supporting stringers. The walkways shall be chequered plate
construction with anti - skid arrangement.
Conveyor gallery shall have Aluminum industrial troughed sheets conforming to IS:1254 on
roof & both sides. Adequate provision of windows shall be kept on both sides of conveyor
gallery as appended in Mechanical Section. Windows shall be provided with wire mesh as
specified elsewhere in this specification. Cross - over with chequered plate platform and
ladder for crossing over the conveyors shall be provided at approximately every 100 M
intervals of conveyor. Crossover shall preferably be located over four-legged
four
rigid trestle
location. For railway tracks passing below overhead conveyor gallery and along conveyors,
the railway clearances both underground as well as over ground shall have to be adhered to
for design, execution and erection of foundations, trestles, galleries etc., so that movement
of locomotives and wagons is not hampered in any way during
during execution and afterwards.
However at the location where the overhead conveyor gallery crosses road, minimum
clearance of 8.0m above the road crest shall be provided.
a) All gallery supporting trestles shall be four legged type only. One end of each gallery span
shall be hinged to the supporting trestle and the other end shall be slide type. Slide type
support shall be with P. T. F. E. bearings to allow both rotation & longitudinal movements.
a)
In between transfer houses / buildings, four legged trestles
trestles shall be placed at a
maximum interval of 90 metres. The arrangement shall be such so as to ensure that force in
the longitudinal direction (i. e. along the conveyor length) of conveyor gallery of length not
more than 90 m is transferred to any four legged
legged trestle. In the space between each
successive four legged trestles, two legged trestles shall be provided at regular intervals. The
end supports resting on the four-legged
four legged trestle can have either ends hinged or one hinge and
the other on slide type depending
depending on the arrangements. Slide type support shall be with P. T.
F. E. bearings to allow both rotation & longitudinal movements. End of conveyor gallery
which will be supported over transfer house, shall be so detailed that only vertical reaction is
transferred
ferred from conveyor gallery and no horizontal force in longitudinal direction is
transferred from conveyor gallery to transfer house structure and vice - versa. For trestles
and trestle foundations for conveyor galleries located adjacent to existing structures,
struc
over
ground and under ground facilities, location and details of these trestles and foundations
shall have to be decided such that there is no interference both underground as well as over
ground with existing structures and facilities. Trestle columns
columns / ground conveyor portal
column base shall be kept 300 mm higher than the existing ground level.
4.3
Transfer Houses
The over ground portion of the transfer house shall be framed structure of structural steel
work with Aluminium Industrial troughed sheet
sheet side cladding and R. C. C. floors and roof
over structural beams. However the lower portion of side cladding for a minimum height of
0.9 m above the finished floor level shall be one brick thick wall plastered on both side. In
some areas like MCC floors etc., one brick thick wall cladding shall be provided. Brick wall
cladding shall be supported on encased wall beams and suitably anchored to adjoining
columns and beams. Roof shall be provided with water proofing treatment as specified
elsewhere. Adequate steel doors and windows for proper natural lighting and ventilation
Technical Specification:Sec-7, Civil
Page 4 of 21
shall be provided. In addition to steel windows, panels of suitable size to suit the
architectural treatment and made of translucent sheets of polycarbonate material shall also
be provided
d on the side cladding for natural lighting.
4.4
These shall be R. C. C. framed structures with columns, beams, slabs and foundations etc.
Cladding shall be of brickwork with plastering on both sides. Roof shall be provided
pro
with roof
water proofing treatment, as specified elsewhere in the Technical specification. In case of
control building suitable permanent interconnection shall be provided at appropriate level
with the existing respective buildings. All air - conditioned
oned areas, shall be provided with the
suspended permanently colour coated aluminium false ceiling system (details specified
elsewhere). Adequate aluminium doors and windows shall be provided for natural lighting,
ventilation and view.
4.5
Pump Houses
Thesee shall be of R.C.C. or steel framed structure with columns, beams, slab andfoundations
etc. cladding shall be of brick work with plastering on both sides. Roofshall be provided with
roof water proofing treatment as specified elsewhere.Underground sump and water tanks
shall be of R.C.C. Adequate number of doors,Windows and Rolling Shutters shall be
provided.Galvanized steel ladder / rung ladder shall be provided for access to the roof level
ofthe pump house and water tanks.
4.6
Pent House
These shall be of R. C. C. framed structures with columns, beams, slabs andfoundations etc.
Cladding shall be of brickwork with plastering on both sides. Roofshall be provided with roof
water proofing treatment as specified elsewhere. Adequate nos. of steel doors and windows
window
shall be provided for natural lighting and ventilation.
4.7
Toilets
Toilet with potable water line facilities shall be provided in each of the following locations:
In all M. C. C. Rooms Control Building Each unit shall have brick enclosure, and the following
fittings.
i ) Squatting type, white, vitreous china Orissa 1 No. pattern, W.C. pan with high level
flushing cistern ( C.I. ) and all requisite fittings
ii ) Bowl type Urinal with automatic flushing 2 Nos. cistern ( C.I. ) and all requisite fittings
iii ) Wash Basin 630 mm x 450 mm with 2 Nos.two taps and all requisite items
iv ) Mirror 600 mm x 450 mm x 5.5 mm thick 2 Nos.with bevelled edges ( Superior sheet
glass )
v ) C.P. Brass Towel Rod 600 x 20 mm 1 No.
vi ) Liquid Soap Container 2 Nos.
vii ) Washing Tap ( CP Brass ) 2 Nos.
viii ) Overhead Polyethylene water tank 1 No.(min. 500 litres capacity)
ix ) Suitable provision for installation of water coolers.
4.8
Staircase
All roofs & floors of transfer houses shall be accessible through staircase. However,for the
pump houses, access to the roof will be provided by cage ladder. All stairs other than those
of M. C. C. rooms and control rooms shall be of steel (minimum
(minimum 1000 mm wide)and
maximum rise should not be more than 180 mm and minimum tread width 250 mm.
Stringers shall be of rolled steel channel( minimum ISMC 250 )and tread shall be of steel
gratings. Stairs shall be provided with 32 mm dia nominal bore medium
medium duty M. S. pipe hand
rail. Handrails (for staircases, around openings, in walkways etc.) shall be of standard weight
steel pipe of flush welded constructions, ground smooth using 32 mm nominal bore medium
class pipe provided with double rail, top rail about
about 1.0 metre above platform level and pipe
posts spaced not more than 1.5 metres apart. Angle handrail post may be provided when
Technical Specification:Sec-7, Civil
Page 5 of 21
5.0
5.1
Page 6 of 21
drains of minimum size of 300 mm width and 300 mm depth all around the periphery. All
drains shall be of R. C. C. construction. All open drains shall have removable steel grating
designed for loads as specified under loading clause.
clause. Minimum thickness of grating
(Galvanised to 610 gm/m) 2 shall be 12 mm. However at entry or road crossing points
minimum thickness shall be 40 mm. The opening size of grating shall not be more than 90
mm x 35 mm. All drains as well as pre - cast covers
vers shall be provided with edge protection
angles and lifting hooks. However, drains in coal stockyard area shall have pre cast R. C. C.
covers. RCC pre - cast cover weight shall not be more than 65 Kgs. RCC pre-cast
pre
covers near
entry or at road crossings shall be designed for 10 T wheel load at centre. RCC pre cast
covers shall be designed for central point load of 75 Kgs. The scope for foul water from
toilets shall include layout and laying of sewers up to the Employers main sewer line for
sewerage system
stem together with all fittings and fixtures and inclusive of ancillary works such
as connections, manholes and inspection chambers within the building and from the
building to the Employers sewer line. For rain water down comer and those to be used for
conveying
onveying water / coal slurry generated from cleaning of conveyor gallery and buildings
floors, Galvanised MS pipes conforming to IS: 1239 (for 150 mm NB Medium grade pipes)
with welded joints shall be used for MCC buildings, pump houses, penthouse, control
contro
rooms. Galvanised steel ERW pipes (273mm OD, 4mm thk) of steel grade Fe330 conforming
to IS: 3589 with welded joints shall be used for all TPs, and Conveyor galleries. Galvanising
shall be as per IS: 4736. The minimum mass of zinc coating shall not be less than 400
gms/sq.m. as per IS:6745. The zinc coating shall be smooth and shall be subjected to testing
as per IS: 2633, for uniformity of coating. The zinc coating shall be free from all defects as
per IS: 2629. All rain water down comers shall be provided
provided with roof drain heads and
complete with shoes bends, junctions, sockets, adapters, brackets and finished with anti
corrosive painting over a coat or primer. For design of building drainage system IS: 1742 shall
be followed. For sanitary / sewerage pipes
pipes above ground, sand cast iron pipes conforming to
IS : 1729 with leak proof lead joints. For underground drain pipes, minimum class NP - 2
pipes conforming to IS: 458. At road crossings, concrete pipes of class NP 3 conforming to IS:
458 and at rail crossing
sing R.C.C. box culvert to be provided. For sewerage below ground
stoneware pipes conforming to IS: 651 with concrete bedding and haunch.
6.0
Permanently colour coated sheet of approved shade and colour using galvanized
galvanize mild steel
sheet of minimum 0.6mm BMT(bare metal thickness i.e. metal thickness excluding thickness
for coating and galvanizing) galvanised to grade 275 as per IS 277,of minimum yield strength
of 250 Mpa of drawing grade as per IS 513 or high tensile steel
steel of minimum 0.5mm
BMT(bare metal thickness i.e. metal thickness excluding thickness for zinc aluminium
coating and colour coating ) coated with zinc aluminium alloy @ 150gm/sq.m.of minimum
yield strengthof 350 as per AS1397. Steel shall be colour coated
coated with total coating thickness
of 35 microns (nominal) comprising of silicon modified polyester (SMP with silicon content of
30% to 50%) paint or Super Polyester paint, of minimum 20 microns (nominal) dry film
thickness (DFT) on external face on 5 microns (nominal) primer coat and 5 microns (nominal)
SMP or super polyester paint over 5 microns (nominal) primer coat (or 10 micron SMP/super
polyester paint) on internal face. SMP and Super polyester paint systems shall be of category
3 as per AS2728. Coated surface
surface shall be provided with a protected guard film (polyethylene)
of about 40 microns to avoid any damage to the coating during handling. For metal deck,
minimum 0.8 mm (bare metal thickness i.e. metal thickness excluding thickness for coating
and galvanizing)
izing) galvanised to grade 275 as per as per IS 277, of minimum yield strength of
250 Mpa of drawing grade as per IS 513, troughed profile having nominal trough depth 44
mm and pitching of 130 mm shall be used. However alternative profile meeting the strength,
stren
defection and other functional requirements such as sections modulers and moment of
inertia shall be provided. To minimize the number of joints, the length of the sheet shall
Technical Specification:Sec-7, Civil
Page 7 of 21
preferably be not less than 4.5 cut pieces shall not be used, unless specifically
specifi
approved by
the Engineer. However, the actual length shall be such so as to suit the purling / runner
spacing. No negative tolerance shall be allowed in bare metal thickness. The nominal depth
of trough shall be 30 mm. The polycarbonate sheet to be used
used for cladding and glazing
purpose in conveyor galleries shall have toughed profile to match with the metal cladding
profile. Minimum 2.0mm thick fire retardant and UV resistant polycarbonate clean sheet of
GE plastic or equivalent approved make shall be used. The polycarbonate sheet shall be
installed along with the metal cladding so as to have a watertight lapping arrangement.
Suitable detailing shall be made to cater for the thermal expansion. IS: 14434 to be referred
for other details. Polycarbonate sheet
sheet minimum 6mm thick multi (twin) wall fire retardant
(Continuous use under temperature 100 oC), impact resistant and ultraviolet resistant sheet
shall be provided (as glazing) in transfer houses, pump houses, etc.
7.0
Roof Details
Roof slab shall be minimum 150 mm thick and shall have minimum 10 dia HYSD
reinforcement bars placed at 200 mm center both ways at top and bottom. For efficient
disposal of rain water, the run off gradient for the roof shall not be less than 1: 100. This
gradient can be provided
ided either in structure or subsequently by screed concrete M-15
M
(using
12.5 mm coarse aggregate) and / or cement mortar (1:4). However, minimum 25 mm thick
cement mortar (1: 4) shall be provided on top to achieve smooth surface.900 mm high and
minimum 100 mm thick R. C. C. parapet wall shall be provided over roofs of all buildings.
Parapet wall shall have suitable coping. External face of parapet wall of the buildings
provided with metal cladding shall also be finished with metal cladding of design and colour
col
as per approved architectural drawings. Junction of roof and parapet shall be provided with
150 x 150 mm size concrete fillet. Drain level shall be provided with 45 x 45 cm size khurras
having minimum thickness of 30 mm of M-15
15 concrete over PVC sheet of 1 m x 1m x 400
micron and finished with 12 mm 1 : 3 cement : sand plaster. Roofs of all transfer houses,
crusher houses, control rooms, M. C. C. rooms, penthouse etc., shall have roof water
proofing treatment. Roof water proofing treatment shall be provided
ided using high solid
content liquid applied urethane based elastomeric water proofing membrane to give
uniform joint less dry film thickness of minimum 1.5 mm (as per ASTM C 836 and C 898),
with separate wearing course as per ASTM C - 898. This treatment shall also include
application of polymerized mastic over the roof to achieve smooth surface and primer coat.
Wearing course on the top of membrane shall consist of 25 mm thick P. C. C. (M-15)
(M
cast in
panels of maximum 1.2 x 1.2 m size and reinforced with 0.56 mm diameter galvanized
chickenwire mesh and sealing of joints using sealing compound / elastomeric water proofing
membrane. Pathways for handling of materials and movement of personnel shall be
provided with 22 mm thick chequered cement concrete tiles as per IS : 13801 for awidth of
1000 mm in place of P. C. C.
8.0
The floor slabs shall be minimum 150 mm thick and shall have minimum 10 dia HYSD
reinforcement bars placed at 200 mm center both ways at top and bottom Floors of transfer
points shall have cross slope of not flatter than 1: 80, towards the floor washing drainage
outlets, for efficient drainage. For ground conveyor & crusher house slope shall be 1:100.
Chequered plates (used for floors, walkways etc.) shall be minimum
minimum 6 mm thick o/p or as
indicated on drawings. The chequered plate pattern shall be approved by Employer / RITES.
Mild steel flats/angles of suitable size shall be welded to the bottom portion of chequered
plates at a designed spacing to stiffen chequered
chequered plates suitably. Chequered plates shall be
fixed by staggered welding of suitable size. Floors of trenches shall have integral finish to
concrete base. Toe guard of size 100 x 6 mm shall be provided at various openings provided
in floors e.g. around stair
stair case openings, chute openings and other similar cutouts. For
conveyor walkways, angle runner to act as toe guard shall be provided. All along the
Technical Specification:Sec-7, Civil
Page 8 of 21
10.0
Earthing Mat
2X40 mm Dia MS rod as earthing mat, placed at a distance of 1.0M away and at depths
between 0.60M and 1.00M shall be supplied and laid all around
around the periphery of buildings,
structures, and outdoor equipment, as per the approved drawings. Risers of 40 mm Dia MS
rod and connecting to the above Earthing mat shall also be supplied and laid in position by
the Contractor, as per the approved drawings.
drawings. Risers shall be laid up to a height of 300 mm
above the local Ground level, at each of the columns of the buildings on outside of the
buildings, and minimum 2 (Two) numbers for structures and outdoor equipment. The
contractor also supply and lay necessary
necessary number of 3.0 M deep vertical 40 mm Dia MS rod
Earthing electrodes and connecting them to the Earthing mat, as per the approved drawings
and the supplying and laying of 40 mm Dia MS Rods for connecting the Contractor's earthing
mat with the Employer's
r's earthing mat separately at two locations.
11.0
Fencing
Fencing with toe wall and steel gates shall be provided around the transformers. Fencing
shall comprise of PVC coated GI chain link fencing of minimum 8G (including PVC coating) of
mesh size 75 mm and of height 2.4 m above the toe wall. The diameter of the steel wire for
chain link fence (excluding PVC coating) shall not be less than 12G. Fence posts shall be of
pre cast R. C. C. of minimum M20 grade. All corner posts will have two stay posts and every
tenth post will have transverse stay post. Suitable R. C. C. foundation for the post and stays
shall be provided based on prevailing soil conditions. Gates shall be sturdy with locking
provisions. Toe walls of brick masonry shall be provided between fence posts all along the
run of the fence with suitable foundation. Toe wall shall be minimum 200 mm above the
formation level with 50 mm thick P. C. C. coping (1: 1. 5: 3) and shall extend minimum 300
mm below the formation level. Toe wall shall be plastered
plastered on both sides and painted with
two coats of cement paint of approved colour and shade. Toe wall shall be provided with
weep holes at suitable spacing.
Technical Specification:Sec-7, Civil
Page 9 of 21
12.0
LOADING
For consideration of loads on structures IS : 875 - Code of practice for structural safety
sa
of
buildings shall be followed. In addition to the dead load, live load, equipment load
(including impact / vibration). Temperature loads etc. various loading conditions arising due
to operation and maintenance of equipment shall be considered in the design. The structure
and equipment shall also be designed for seismic loads as per the Criteria for Earthquake
Resistant Design of Structures and equipment" and the Criteria for Wind Resistant Design of
Structures and equipment" specified in the Annexure
Annexure A and B respectively in Civil Section,
whichever is governing. Wind and seismic forces shall not be considered to act
simultaneously. The following minimum live loads shall be adopted for the design of various
structures. If actual expected load is more than the specified load, then actual load is to be
considered
a )Roofs 150 Kgs. / Sq. M. for accessible roofs and 75 Kgs. / Sq. M. for non
accessible roofs. In addition to this coal dust load of 150 Kgs.
Kgs. / sq. m. shall also be
considered.
b ) R. C. C. floors 500 Kgs. / Sq. M.
c ) Stair and balconies 500 Kgs. / Sq. M.
d ) Toilet rooms 200 Kgs. / Sq. M.
e )Chequered plate floors 400 Kgs. / Sq. M.
f ) Walkways ( including walkways in 300 Kgs. / Sq.
Sq. M.conveyor galleries )
g)Conveyor galleries In addition to the live loads, loads due to cable trays, fire fighting /
service water pipes shall also be considered @ 125 Kgs. / m ( minimum ) on each of the
longitudinal girder. Roof-truss
Roof
members are to
o be checked for supporting fire fighting
pipes/Service water pipes.
h ) Road Culverts and its allied For class 'AA' loading and checked for structures including R.
C. C. pipe class A loading as per IRC standard crossing & road crossing of trenches.
i ) Channels / trenches In addition to earth pressure and water pressure, etc. additional
earth pressure due to surcharge of 2T / Sq. M. shall
j ) Covers for trenches/channels Covers for channels & trenches, shall be designed for a live
load of 0.4T Sq.M.
M. &loading mentioned under clause in trenches, whichever is critical.
k ) Sumps and tanks and other In addition to earth pressure with a underground basement
type
surcharge of 2T / Sq. M. (or surcharge structures due to Railway loading whichever
is critical for Railway load bearing structures etc.) and sub - soil water pressure etc. These
are also to be designed for the following conditions :
i ) Water / liquid inside and no earth outside (applicable only to such structures which are
liable to be filled up with water or any liquid ).
ii ) Earth with surcharge outside and no water / liquid inside
iii ) For underground (basement) structures protection against buoyancy during execution
and after execution shall be ensured without superimposed loadings with minimum factor
of safety of 1.2 against buoyancy.
l ) Unit weight of coal shallbe taken as 1100 Kgs. / cum. Fordesign purposesIf the erection
er
load is higher than the specified live loads on any floor or part thereof,then the erection
loads are to be considered for the design.Permissible increase in stresses of materials and
bearing pressure of soil due to windload or seismic load shall be as per relevant I. R. S. and I.
S. code.
13.0
DESIGN CRITERIA
The loads for all railway load bearing structures e. g. track hopper includingmachinery
hatches, wagon tippler, tunnel and under ground transfer houses etc. and the analysis and
the design of these structures shall be made strictly in accordancewith the provisions
pr
of
Indian Railway Bridge rules (latest edition), and Indian RailwayCodes of practice (latest
Technical Specification:Sec-7, Civil
Page 10 of 21
edition) with all amendments up to the date of opening ofbids. However, the axle load for
analysis and design shall be considered as 35 MT.Coal heap of 1.2m
1.2m height shall be
considered above hopper top for design of, hopper and supporting elements of hopper. The
analysis, design anddetail drawing for the structure coming below the railway track shall be
got approvedby the contractor from the concerned railway
railway authorities before taking
upconstruction. All necessary payment for the above work shall be made by the bidder to
the railway authority.The design of all R. C. C. structures shall be carried out as per code of
practice forplain and reinforced concrete for general building construction, IS : 456 ( latest ).
The steel structures shall be designed and fabricated as per code of practice for use of
structural steel in general building construction, IS : 800 ( latest ) and other relevant IS
Standards. Minimum
mum size of the angle section to be used as structural members shall be
50X50X6. Minimum weld size shall be 6 mm. Connections shall bedesigned for 70% of shear
capacity of the member or the actual shear force, whichever is higher. The building shall
conform to local bye - laws, rules and regulations for industrial buildings and also B. I. S.
publications, SP 32 and 41. Slotted holes shall not be assumed to act as expansion joint for
relieving of stresses and suitable bearings shall be provided at the supports.
supp
All gallery
supporting trestles shall be so proportioned that the transverse deflection of gallery due to
wind / seismic load should not exceed trestle height / 1000 as stipulated in IS: 11592. This
deflection condition shall be strictly followed. The
The transfer house structures shall be so
designed that transverse deflection at places where conveyor galleries meet, should be
equal to the respective transverse deflection of conveyor supporting trestles. Horizontal
bracing system shall be provided at floor
floor levels around the openings. Shear force in steel
columns shall be transferred to the pedestals / foundations exclusively either through
foundation bolts or the shear key arrangement. For design of liquid retaining structures, IS :
3370 ( Part - I to IV ) ( latest ) shall be followed. Face of the structure in contact with liquid
shall be designed as un -cracked
cracked section. For design of R. C. C. pipes for culverts, latest
editions of IS : 458, IS : 783 should be followed. For design of all underground structures
struct
/
foundations, ground water table shall be assumed at the formation level ( i. e. the adjoining
ground level ). Design of Hopper walls shall be done for both Static & Dynamic flow condition
using Walkers theory. Design of masonry walls shall be made as per IS : 1905. Civil task
drawing indicating various equipment loading and supporting arrangement and floor loads
to be submitted along with the design calculation. For metal roofing and side cladding, the
spacing of purlins/runners shall be such that the
the deflection of metal sheet used is limited to
span/250 under adverse loading condition. Minimum reinforcement shall be provided at the
top face of the footing, even if, no reinforcements are required as per design
14.0
CONCRETE
All R. C. C. works to the done under this specification, unless specified otherwise shall be
design mix concrete. Minimum grade of concrete for various structures shall be as follows:
a ) M35 - For all railway load bearing structures
b ) M25 - For underground / sub structural R. C. C. work (other than railway load bearing
structures).
C ) M20 - For R. C. C. superstructure works including ground floor slabs, trenches & drains.
Minimum 75 mm thick P.C.C M-7.5
M 7.5 shall be provided as mud mat below all foundations. For
concreting of underground structures requiring water tightness, plasticizer cum water
proofing admixture shall be added to the concrete mix. Both coarse and fine aggregates shall
conform to IS: 383 for concrete, shotcreting etc. unless otherwise directed. Batching plant
or reversible drum mixer with weigh batcher and concrete pumps must be used for all
concreting works(RCC).
15.0
15.1
Excavation Details
Excavation in soil
Excavation for foundation shall be to the bottom of lean concrete and as shown on drawing
Technical Specification:Sec-7, Civil
Page 11 of 21
or as directed by the Engineer. The bottom of all excavations shall be trimmed to required
levels and when excavation is carried below such levels by error, it shall be brought back to
the specified level by filling with concrete of nominal mix 1 : 3 : 6 (cement:
(cement: coarse sand: 40
mm down aggregates ), as directed by the Engineer. The Contractor shall ascertain for
himself the nature of materials to be excavated and the difficulties, if any, likely to be
encountered in executing this work. Cofferdams, sheet piling,
piling, shoring, bracing to maintain
suitable slopes, draining etc. shall be provided and installed by the contractor, to the
satisfaction of the Engineer. Surplus excavated materials shall be disposed off by the
contractor at locations within plant boundary wall as directed by the engineer. The
Contractor shall have to constantly pump out any water collected in excavated pits and
other areas due to rain water, springs etc. and maintain dry working conditions at all times
until the excavation, placement of reinforcement, shuttering, concreting, Backfilling is
completed. The Contractor shall remove all slush/muck from the excavated areas to keep
the work area dry. The Contractor, if required, shall employ sludge pumps, for this purpose.
15.2
Excavation
avation in rock
For the work of excavation in rock, Contractor shall engage specialized agency having
experience of excavation in rock involving wedging and blasting. The agency shall be subject
to approval of Engineer and the Contractor shall furnish details
details of relevant experience in
support while seeking approval for the agency.
agency Only Control Blasting shall be resorted
resort to
with the written permission of the Engineer. In case blasting method can not be adopted
considering the safety aspect of the existing rail
rail network, buildings, structures etc, hard rock
shall be excavated by using expansive chemical or any other suitable means.
means All the
statutory laws, (Explosives Act etc.) rules, regulations, Indian Standards etc. pertaining to the
acquisition, transport, storage, handling and use of explosives etc. shall be strictly followed.
The contractor shall obtain Licenses from Competent Authorities for undertaking blasting
work as well as for procuring, transporting to site and storing the explosives as per
Explosives
es Act. The Contractor shall be responsible for the safe transport, use, custody and
proper accounting of the explosive materials. Surplus excavated materials shall be disposed
off by the contractor at locations within plant boundary wall as directed by the
th engineer.
The Contractor shall have to constantly pump out any water collected in excavated pits and
other areas due to rain water, springs etc. and maintain dry working conditions at all times
until the excavation, placement of reinforcement, shuttering,
shuttering, concreting, backfilling is
completed.
15.3
De-watering
watering of Deep Excavations
For deep underground structures like wagon tippler hopper, machinery hatches, tunnels and
underground transfer houses, requiring open excavation with extensive de - watering,
completely
letely dry working conditions during excavation, shuttering, placement of
reinforcement, concreting, water proofing of structures, backfilling and any other operation
shall be maintained by suitable de - watering method of suitable capacity.
15.4
Backfilling,
ng, Disposal and Stacking of materials
Page 12 of 21
maintaining of the Kuccha roads shall be the responsibility of the Contractor. The
transported material shall be neatly stacked as directed by the Engineer. Double handling of
materials shall be avoided as far as possible. However, depending on site condition
excavated materials carried beyond a lead of 500 m may also be required to be brought back
for filling purpose. Materials to be used for filling purpose shall be stone, sand or other
inorganic materials and they shall be clean and free from shingle, salts, organic matter,
m
large
roots and excessive amount of sod, lumps, concrete or any other foreign substances which
could harm or impair the strength of the substances in any manner. All clods shall be
suitably broken to small pieces. When the materials are mostly rock boulders, these shall be
broken into pieces not larger then 150 mm size. Sand used for filling shall be clean, medium
grained and free from impurities. Fines less than 75 microns shall not be more than 20%. In
any case, the materials to be used for filling purposes shall have the prior written approval of
the Engineer. In case the materials have to be brought from pits / quarries, then it shall be
the Contractors responsibility for identification ion of such quarry areas, obtaining approval
from their use from concerned authorities, excavation / quarrying loading and carriage of
such material, unloading and filling at specified locations. The Contractor shall pay any fees,
royalties etc. that may have to be pain for utilizationof borrow areas.
16. 0
GALVANISING
SING
All burrs and irregular edges of the structural steel members to be galvanized shallbe ground
smooth before galvanizing.Purity of Zinc to be used for galvanizing shall be 99.5 % as per IS :
209 ( latestedition ).The weight of the zinc coating shall be at least 610 Gms. /m2unless
noted otherwise.
17.0
Minimum, 12 mm dia ( NB ) threaded nozzle of suitable length, shall be provided over the
surface and along the construction joint line in a grid pattern at a spacing not exceeding
excee
1.5
m c / c before concreting operation. Adequate precaution shall betaken to keep the nozzles
plugged at both ends to prevent them from getting closedby concrete. For fixing of any
nozzle in set concrete suitable size hole shall be drilled, preferably
preferably by using repercussive
hammer drill electrically operated, in grid pattern and grouting nozzle shall be fixed in these
holes. After the nozzles are fully set, neat cement slurry admixed with water soluble non shrink polymer / monomer based chemical shall
shall be injected through the net - work of
nozzles with low pressure grout pumps at a pressure of about 2.0Kgs. /cm2. Cement slurry
shall be prepared by mixing cement with non-shrink
non shrink polymer/monomer @ 500 gm/50 kg bag
of cement and water, ensuring that Water: Cement ratio does not exceed 2 (by weight).
Wetter the structure, lesser should be the water cement ratio. The property of the
polymer/monomer should be such that when it is mixed with water @0.5% by weight of
water, the viscosity of the resultant solution
solution (water and polymer/monomer) should not be
more than 1.2 centipoises. Plasticizing agent shall be added wherever required. The grouting
shall be started at very low pressure and increased gradually to a required pressure. The
grouting shall continue, till
till the hole refuses to take any further grout, even at an increased
pressure. Applied pressure shall not be more than the designed strength of the concrete.
After completion of grouting operation, the nozzles shall be sealed properly to the
satisfaction of the Engineer.
18.2
Mixing
The liquid polymer shall be stirred well and cement based powder shall then be added
Technical Specification:Sec-7, Civil
Page 13 of 21
slowly to make a Slurry Mix. For preparation of Brush Topping Mix, quartz sand shall be
added slowly and mixed well till a homogeneous mixture is obtained. The mix shall be used
within half an hour of the preparation. Addition of quartz sand may not be necessary, in case
dry power contains the same.
18.3
Properties of Coating
It must adhere to wet surface. It should develop adequate bond strength, with the concrete
surface, not less than 2N / Sq. mm.Co - efficient of permeability shall be about 5x10Cm /
Sec.-1 0 Waterr absorption after continuous soaking shall not be more than 1 %. The
materials shall be permeable under water vapor. The material shall be resistant to acids and
alkalis present in the soil and underground water with normal pH value between 4 and 14.
The co - efficient of thermal expansion of the material shall be close to that of concrete
18.4
Application
The concrete surface shall be cleaned and made free from grease, oils or loosely adhered
particles. The surface shall be damp without any free water. For
For exterior underground part,
application (b) pertaining to Brush topping Mix shall be followed.
19.0
Architectural Features
All architectural features of buildings like control rooms, M. C. C.rooms, transfer houses and
conveyor galleries etc. shall be detailed by contractorsqualified
contractorsqualified architect. Necessary
projections, fins etc. in addition to the minimumspecified elsewhere in this specification
shall be provided as required. The Contractor for Employer/RITESs approval shall submit
detailed architectural drawings along with colour schemes. Nothing extra shall be payable
for any changes required while getting the drawings / schemes approved and for executing
the same.In case structural column base plates are proposed below the floor level, the same
shall be encased with adequate
adequate cover up to the finished floor level with minimum M -20
grade concrete. Dowels shall be left from the pedestals to be lapped to the
skinreinforcement of the encasing.
20.0
Glazing
Page 14 of 21
21.0
False Ceiling
All air - conditioned areas, shall be provided with the suspended permanently colour coated
aluminium false ceiling system with corrosion resistance aluminium alloy panels of minimum
m
thickness 0.5 mm. 50 mm thick mineral wool insulation (as per IS: 8183) having a density of
32 kg/cum for glass wool or 48 kg/cum for rock wool, bound in polythene bags shall be laid
on top of panels. Additional hangers and height adjustment clips shall be provided for
returns air grills, light fixtures, A. C. ducts etc. Suitable M. S. channel (Minimum ISMC 75)
grid shall be provided above the false ceiling level for movement of personnel to facilitate
maintenance of lighting fixtures, AC ducts etc. Under deck insulation shall be provided on
the ceiling (underside of roof slab) and underside of floor slab of air - conditioned areas
depending upon the functional requirements. This under deck insulation shall consist of 50
mm thick mineral wool insulation
insulation mat conforming to IS: 8183 having a density of 32 kg/cum
for glass wool or 48 kg/cum for rock wool, backed with 0.05mm thick aluminium foil and 24G
x 25 mm mesh wire netting and shall be fixed to the ceiling with 14G wire ties.
22.0
Battery Room For Floor and dado, bitumen primer followed by 12 mm thick bitumastic 6 mm
thick potassium silicate mortar bedding and 20 mm thick A. R. tiles shall be provided. Dado
height shall be minimum 2.0 m from floor. M. S. Grating / Chequered
Chequered plate cover and any
other steel structure likely to come in contact with chemicals shall be provided with epoxy
coating 150 microns thick over epoxy primer. Acid / Alkali resistant lining material shall
conform to the following: Bitumen primer shall conform
conform to IS: 158. Bitumastic compound
shall conform to IS: 9510. Where the height of bitumastic layer on vertical surface is more
than 2.0 m, the bitumastic layer shall be reinforced with diamond pattern expanded metal
steel sheets conforming to IS: 412. A. R. tiles shall conform to IS: 4457. Mortar: Potassium
silicate and resin type mortars shall conform to IS : 4832 Parts I and II respectively.
23.0
FINISHING SCHEDULE
The contractor's scope also includes all doors, windows, glazing, rolling shutters, finishes,
f
damp proofing, inserts, anchor bolts, embedments, stairs, nosing, railings, toe - guards,
ladders, edge protection angles, etc. The Contractor shall adhere to the finishing schedule as
given.
23.1
Flooring
I. P. S. ( cement concrete flooring ) with metallic hardener topping shall be provided for all
floors in transfer houses, including ground floors of transfer houses, ground conveyors,
operating floor of pump houses, M. C. C. rooms, cable vault / cable spreader rooms,
maintenance
enance and unloading areas, general storage areas and all other areas in plant
buildings where heavy duty flooring is required. Heavy Duty Ceramic Tiles ( matt finish ) shall
be provided for toilets, office rooms, laboratories, control rooms and control equipment
eq
rooms. Well polished Kota stone shall be provided for staircases, passages, lobbies and
general circulation areas. The floor shall be laid on an already laid and matured concrete
base. Sunken R. C. C. slab shall be provided in toilet area so as to keep the finished floor
level of these areas same as that of the surrounding area Wherever specified metallic
hardener topping shall be 12 mm thick using uniformly graded iron particles, properly
treated. Wherever specified Heavy duty ceramic tiles of size
size 300 x 300 x 7 mm thick
(minimum) of reputed manufacturer (Kajaria, Spartek or equivalent) of approved finish,
shade and colour to be used. The tiles shall have a scratch resistance of minimum 5 on
Mohrs scale and shall have a bending strength of 350 Kgs.
Kgs. / cm.2 Paving details shall be
similar to grade slab excluding metallic hardener. Skirting in general shall be 150 mm high.
Technical Specification:Sec-7, Civil
Page 15 of 21
Dado in toilets and pantries shall be up to 2.1 m height from finished floor level. Skirting and
dado shall match with the floor finish.
f
23.2
For all air - conditioned areas and stair case acrylic emulsion paint of approved make and
shade over 2-3 mm cement based putty of approved make shall be provided.
provided For toilets
minimum 5 mm thick decorative coloured
coloured ceramic tiles of approved make and shade with
approved pattern up to 2.10 m. height from finished floor level shall be provided. Oil bound
distemper over 2-3 mm cement based putty of approved make above 2.10 m height shall be
provided. For all other areas
areas oil bound distemper ( IS : 428 ) of approved shade over cement
based putty of approved make shall be provided. For battery room and other areas coming
in contact with acid / alkali fumes, chemical resistant chlorinated rubber paint shall be
provided abovee 2.1 m height. Up to 2.1 m height from finished floor level acid alkali resistant
tiles shall be provided as specified elsewhere. All R. C. C. ceilings shall be oil bound
distemper over cement based putty.
putty
24.0DOORS,
DOORS, WINDOWS AND ROLLING SHUTTERS.
24.1 Doors and Windows
All doors, windows and ventilators
venti
of control room building and M. C. C. buildings shall have
Electro colour coated (anodised) aluminium frame work with glazing. All doors of office and
toilet areas shall be of factory made prepre laminated particle board (M D F exterior grade). All
other buildings shall have steel doors, windows and ventilators. Single glazed
glaz panels with
aluminium framework shall be provided as partition between two air - conditioned areas
wherever clear view is necessary. Coal conveyor galleries shall have steel windows of
openable type. The window shutters shall be provided with M. S. louvers.
louv
All steel doors
shall consist of double plate flush door shutters. The door shutter shall be 45 mm thick with
two outer sheets of 18 G rigidly connected with continuous vertical 20 G stiffeners at the
rate 150 mm centre to centre. Side, top and bottom edges of shutters shall be reinforced by
continuous pressed steel channel with minimum 18G. The door shall be sound deadened by
filling the inside void with mineral wool. Doors shall be complete with all hardware and
fixtures like door closer, tower bolts,
bolts, handles, stoppers aldrops, etc. Windows of coal
galleries shall be provided with welded wire fabric of 1.6 mm thick wire as per IS: 4948 and
12 mm x 30 mm mesh size. Wherever functionally required rolling shutters shall be provided
and these shall be electrically
ctrically operated. In transfer points, windows near floors shall be steel
and openable types. The window shutters shall be provided with MS louvers. Windows /
ventilators at higher level can be of steel with fixed glazing. All openable windows shall be
provided
ovided with suitable stays. All windows and ventilators onground floor of all switchgear
Page 16 of 21
and M. C. C. buildings shall be provided with suitable anodized aluminium grill. Fire - Proof
doors with panic devices shall be provided at all fire exit points as per
per the recommendations
of statutory regulatory bodies These doors shall generally be as per IS : 3614 ( Part I and Part
II ). Fire rating of the doors shall be as per requirements of statutory regulatory bodies.
However minimum rating shall be 2 hours. These
These doors shall be double cover-plated
cover
types
with mineral wool insulation. Hollow extruded section of minimum 3 mm wall thickness as
manufactured by INDAL or equivalent shall be used for all aluminium doors, windows, and
ventilators. Doors and windows on external
external walls of the buildings having brick enclosures i.e.
enclosure other than with Aluminium Industrial troughed sheet cladding, shall be provided
with sunshade over the openings with width 600 mm more than the opening width.
Projections from the wall for
for the sunshade shall be 450 mm over window openings and 750
mm over door openings. Minimum size of door provided should be 2.1 m high and 1.2 m
wide, except for toiler rooms, where door may be 0.75 m wide. All doors ( other than those
in W/C and urinal areaa ) shall be double plate flush door shutters. For W/C and urinals area,
wooden panel doors shall be provided. Area of windows shall be at least 10 % of the floor
area of the respective building. The area of translucent polycarbonate sheet panels shall also
als
be at least 10 % of the floor area of the respective building. Monorail doors shall be provided
with steel stays / chains etc for convenient operation of the shutters. The louvre blade shall
be Z shaped and made out of 18G sheets in EZ7 steel frames. The
The frames shall be of ISMC
100.
24.2
Rolling Shutters
Rolling Shutters/ grills shall be with motor drives, gear arrangement including all accessories
and shall conform to IS: 6248. All electrical work shall be in strict accordance with the
relevant Indian Electricity Rules. After installing the shutters, the Contractor shall test the
performance of the shutter in presence of the Engineer. The shutters shall be smoothly
operable under all ambient conditions. All control and locking devices shall give fault free
f
performance.
25.0 PAINTING
Painting of all steel structures, including seal plates, hand rails, steel doors & windows,
ventilators, louvers, Rolling Shutters Stair Cases (except gratings), etc. shall be as per
specification mentioned elsewhere in this document.
26.0 Miscellaneous
26.1 Ordinary form work shall be used in roofs and floor slabs in transfer houses, footings,
pedestals, cable trenches, pits etc., Plywood form work shall be used for all over ground
exposed work like columns, beams, floors and
and ceilings in control room and M. C. C. buildings.
26.2 Monorail girders and fixtures shall be provided for monorails at the locations as
required and as described elsewhere in these specifications or drawings. Monorail openings
in the walls shall be provided
provided with steel frame doors preferably sliding type or otherwise
open able inside, access platforms and ladders.
26.3Steel
Steel frame around openings in roof and on external walls for mounting of exhaust
fans shall be provided.
nk cementitious grout of reputed manufacturer as approved by
26.4 Ready mix non - shrink
the Employer shall be used for grouting of block outs and foundation bolts, underpinning of
base plates and machine bases. Crushing strength of grout shall be one grade higher than
the foundation concrete. Minimum crushing strength shall be 30 N / mm2 unless higher
strength requirement is specified by the equipment supplier or the grout manufacturers.
26.5The
The bottom of steel in case of cable / pipe galleries and trestles shall be generally 3m
Page 17 of 21
abovee the ground except for rail / road crossing where it shall be 8m above the rail top /
road crest/ground. Further in bunker areas it shall be 8 m above the ground.
26.6Polysulphide
Polysulphide Sealing Compound shall be two-part
two part polysulphide sealant and shall be
from
om approved manufacturer, conforming to IS : 12118. Materials shall consist of
polysulphide polymer and a curing agent. Gun grade material shall be used unless otherwise
specified. The application of the sealant shall be strictly followed as per manufacturers
manufactur
guidelines
27.0 SHOTCRETING
27.1 General Requirements
27.2 Generally, shotcreting shall be done in accordance with IS : 9012.
27.3 Reinforcement for shotcreting shall be as detailed below, unless specified otherwise.
(i) Reinforcement in one direction
direction consisting of 6 mm M. S. bars at 750 mm c / c shall be
connected to the lugs for fastening of the wire fabric. This shall be used in case of 50 mm or
above thick shotcreting.
(ii) Wire fabric conforming to IS : 1566 shall be used as reinforcement and shall
sh consist of
wire, 3 mm diameter, spaced 50 mm both ways and shall be electrically cross welded. Wire
fabric shall be securely tied to 6 mm bars for 50 mm thickness. Adjacent sheet of wire fabric
shall be lapped at least 100 mm and tied.
(ii) Clear coverr to reinforcement mesh shall not be less than 15 mm. 22.01.03
Minimum
thickness of shotcreting shall be 50 mm. for abrasion resistant work and 25mm for ordinary
surface protection work.
27.4
Material
27.5
Application
After the placement of reinforcement and / or welded mesh and not more than six ours
prior to the application of shotcrete, the surface shall be thoroughly cleaned of all loose
aterials and dirt. The Contractor shall properly prepare the surfaces, reinforcement
reinfo
and / or
welded esh to receive the shotcrete. Cleaned surfaces shall be wetted not more than hour
prior to hotcreting.
The mix as placed on surface shall be one part cement to three parts approved sand by
mass. Cement and sand shall be dry mixed;
mixed; not water shall be added after mixing and before
sing in the gun. The quantity of water when added shall be only that which is sufficient to
hydrate the cement. For average atmospheric conditions, the water cement ratio for
shotcrete in place shall be between 0.35 and 0.5 by mass.Suitable admixture shall be used
wherever required.
A uniform pressure of not less than 25 Kgf / Cm2 at the nozzle shall be maintained.
Necessary adjustments shall be made to ensure this pressure, taking into account the length
of ose and height of the place to be shotcreted, above location of the machine.
The application shall proceed in an upward direction. Beams, stiffeners andintermediate
walls, if any, shall be wrapped with wire fabric and completely covered with hotcreting.
hotcreting All
rebound shall be removed from the area of application as the work progresses andsuch
rebound material shall not be reused.
Technical Specification:Sec-7, Civil
Page 18 of 21
As soon as the freshly shotcreted surface shows the first dry patches, a fine spray 0f water
shall be applied to keep too moist.
moist. After the surface has hardened, it shall be kept
continuously moist for minimum seven days. If there is extreme heat, especially when
ccompanied by hot winds, the shotcreted surface, immediately upon completion, shall be
covered with burlap or similar covering,
covering, which must be kept continuously moist for 14 days
after shotcreting. The temperature of the lining shall not be permitted to exceed 38 oC
during placing and curing.
29.0
All tests required for all materials, quality of workmanship or any other tests asdesired by
the Engineer shall be at contractors cost.
30.0 MATERIALS
30.1 For Civil, Structural and Architectural works
Employer will not supply any material. All materials including cement, reinforcementsteel
and structural steel, whatsoever required for
for execution and completion of theentire scope
of work covered under this specification shall be arranged by thecontractor at his own cost.
All materials procured by the contractor shall meet thequality requirements specified in this
specification.The contractor
ractor shall keep sufficient stock of cement and steel at site at any
point oftime when the work is in progress excluding what has been already incorporated
inthe works, so that any disruption / delay in availability of these materials
duringprocurement willll not affect the progress of work at site. The minimum quantity
ofsuch materials in stock at site shall not be less then the Requirement of one( 1 )month in
case of Cement and Requirement of two ( 2 ) Consecutive months in caseof Steel.
30.2 Cement
The contractor shall use cements conforming to, IS: 455, IS: 8112. Higher grade of cement
namely GR - 53 of ordinary portland cement conforming to IS: 12269 can also be used.
30.3 Reinforcement steel shall conform to:
to
a) Mild steel grade I of IS: 432 Part I and grade A of IS: 2062.
b) High yield deformed bar of IS: 1786 (Gr. Fe 415 and Fe. 500).
30.4 Structural steel:
olled sections and plate shall conform to Grade A as per IS: 2062-1992
2062 1992 and/or as per
Rolled
specification specified at relevant clauses.
clauses
31.0
The contractor shall furnish guarantee for the water proofing or similsr work wherever it is
included in civil work for three years. The contractor shall furnish a Bank Guarantee
equivalent to 105 of the value of water proofing work to be valid additional two years
beyond the defect liability period of the contract. The BG/SD towards the defect liability
period can be returned only on submission of bank guarantee for water proofing as stated
above.
32.0
Page 19 of 21
All standards, specifications, acts and code of practice referred to herein shall be the latest
editions including all applicable official amendments and revisions. Other Indian, foreign
Codes and Standards not listed here but referred to elsewhere within this
thi specification shall
also be deemed to be part of this list. In case of conflict between this specification and those
(IS standards, codes etc.) referred to herein, the former shall prevail. Some of the relevant
Indian standards, Acts and Codes applicable to this section of the specification are listed
below
IS : 383 Specification for coarse and fine aggregates from natural sources for Concrete.
IS : 432 Specification for mild steel and medium tensile steel bars and hard drawn steel wire
for concrete reinforcement.
nforcement.
IS : 456 Code of practice for plain and reinforced concrete.
IS : 458 Specification for concrete pipes.
IS : 516 Method of test for strength of concrete.
IS : 800 Code of practice for use of structural steel in general building construction.
construction
IS : 814 Specification for covered electrodes for metal arc welding for weld steel.
IS : 816 Code of practice for use of metal arc welding for general construction.
IS : 817 Code of practice for training and testing of metal arc welders.
IS : 875 (Pt. I to V) Code of practice for design loads other than earthquake) for buildings
and structures.
IS : 1038 Steel doors, windows and ventilators.
IS : 1172 Basic requirements for water supply, drainage and sanitation.
IS : 1361 Steel windows
ows for industrial buildings.
IS : 1786 Specification for high strength deformed steel bars and wires for concrete
reinforcement.
IS : 1892 Code of practice for subsurface investigation for foundation.
IS : 1893 Criteria for earthquake resistant design of structures.
IS : 1904 Code of practice for design and construction of foundations in soils; general
requirements
IS : 1905 Code of practice for structural safety of buildings -Masonry
Masonry walls.
IS : 1948 Specification for aluminium doors, windows and ventilators.
IS : 2062 Steel for general structural purposes. IS : 2131 Method of standard penetration
test for soils.
IS : 2212 Code of practice for brickwork.
IS : 2645 Specification for Integral cement water proofing compounds.
IS:2720 (Part-II, Methods
ethods of test for soils - determination for water content
IV TO VIII, XIV, etc code of practice for earth work on canals. XXI, XXIII, XXIV, XXVII TO XXIX,
XL)
IS : 2911 Code of practice for design and construction of pile foundations.
(Part-1/Sec.1) Driven
iven cast in situ concrete piles. (Part-1/Sec.2)
(Part 1/Sec.2) Bored cast-in-situ
cast
concrete
piles. (Part-IV)
IV) Load test on piles. IS : 2974 (Part I Code of practice for design and
construction of machine TO V) foundations.
IS : 3370 (Part I to Code of practice for concrete
concrete structures for the storage of IV) liquids.
IS : 3658 Code of practice for liquid penetrant flaw detection.
IS : 3664 Code of practice for ultra sonic testing by pulse echo method.
IS : 4326 Code of practice for earthquake resistant design and construction
construction of buildings.
IS : 4990 Specification for plywood for concrete shuttering work.
IS : 5624 Specification for foundation bolts.
IS : 7215 Tolerances for fabrication steel structures.
IS : 8112 Specification for 43 grade Ordinary Portland Cement.
Cement
IS : 9103 Specification for admixtures for concrete.
Technical Specification:Sec-7, Civil
Page 20 of 21
Page 21 of 21
SECTION 8
1.0
GENERAL
1.1
The following provisions shall supplement the conditions already contained in the other parts
of these specifications and documents and shall govern that portion of the work of this
contract which is to be performed at site. The erection requirements and procedures not
specified in these documents shall be in accordance with the recommendations of the
equipment manufacturer, or as mutually agreed to between the Employer and the Contractor
prior to commencement of erection work.
1.2
The Contractor upon signing of the Contract shall, in addition to a Project Coordinator,
nominate another responsible officer as his representative at Site suitably designated for
fo the
purpose of overall responsibility and co-ordination
co ordination of the Works to be performed at Site. Such
a person shall function from the Site office of the Contractor during the pendency of Contract.
2.0
2.0.1 In
n addition to the local laws and regulations, the Contractor shall also comply with the
Minimum Wages Act and the Payment of Wages Act (both of the Government of India) and
the rules made there under in respect of its labour and the labour of its sub-contractors
sub
currently employed on or connected with the contract.
2.0.2 All registration and statutory inspection fees, if any, in respect of his work pursuant to this
Contract shall be to the account of the Contractor. However, any registration, statutory
inspection
pection fees lawfully payable under the provisions of the Indian Boiler Regulations and any
other statutory laws and its amendments from time to time during erection in respect of the
plant equipment ultimately to be owned by the Employer, shall be to the account of the
Employer. Should any such inspection or registration need to be re-arranged
re arranged due to the fault
of the Contractor or his Sub-Contractor,
Sub Contractor, the additional fees for such inspection and/or
registration shall be borne by the Contractor.
2.1
3.0
Technical Specification:Sec-8l
Page 1 of 23
Employer for review, Employer's acceptance of such site routings shall be obtained
obta
before the
piping is erected. All these site run piping shall be installed in such a manner as to present an
orderly and neat installation. They shall be located as to avoid obstruction of access and
passages. Valves, instruments or any other special items shall be located convenient for
operation by the operating personnel. Pipe runs shall be plumb or level except where pitch for
drainage is required. Pipe runs that are not parallel to the building structure, walls or column
rows shall be avoided. No miscellaneous pipe shall be routed and installed above or adjacent
to electrical equipment.
4.0
PIPING SUPPORTS
4.1
Hangers, supports and anchors shall be installed as required to obtain a safe, reliable and
complete pipe installation. All supports shall be properly levelled and anchored when
installed. The anchors shall be so placed that thermal expansion will be absorbed by bends
without subjecting the valves or equipment to excessive strains.
4.2
5.0
CODE REQUIREMENTS
The erection requirements and procedures to be followed during the installation of the
equipment shall be in accordance with the relevant Indian Electricity Rules & Codes, Indian
Boiler Regulations, ASME codes and accepted good practices, the Employer's Drawings and
other applicable Indian recognised codes and laws and regulations of the Government of
India.
6.0
6.1
In no circumstances will the Contractor interfere with fuses and electrical equipment
belonging to the other Contractor or Employer.
Technical Specification:Sec-8l
Page 2 of 23
6.2
Before the Contractor connects any electrical appliances to any plug or socket belonging to
the other Contractor or Employer, he shall:
a) Satisfy the Employer that the appliance is in good working condition;
b) Inform the Employer of the maximum current rating, voltage and phases of the
appliances;
appli
may
c) Obtain permission of the Employer detailing the socket to which the appliances
be connected.
6.3
No repair work shall be carried out on any live equipment. The equipment must be declared
safe by the Employer and a permit to work issued before any work is carried out.
6.4
The Contractor shall employ the necessary number of qualified, full time electricians to
maintain his temporary electrical installation.
7.0
REMOVAL OF MATERIAL
No material brought to the Site shall be removed from the Site by the Contractor and/or his
Sub-Contractors
Contractors without the prior written approval of the Employer.
8.0
9.0
9.1
Suitable access to site and permission to work at the Site shall be accorded to the
th Contractor
by the Employer in reasonable time.
9.2
In the execution of the Works, no person other than the Contractor or his duly appointed
representative, Sub-Contractor
Contractor and workmen, shall be allowed to do work on the Site, except
by the special permission,
sion, in writing by the Employer or his representative.
Page 3 of 23
resident representative of
of the Contractor and the same shall be deemed to have been
communicated to the Contractor at his legal address.
OPERATION WITH OTHER CONTRACTORS
11.0 CO-OPERATION
operate with all other Contractors or tradesmen of the Employer, who
11.1 The Contractor shall co-operate
may be performing other works on behalf of the Employer and the workmen who may be
employed by the Employer and doing work in the vicinity of the works under the Contract. The
Contractor shall also arrange to perform his work as to minimise, to the maximum extent
ex
possible, interference with the work of other Contracts and their workmen. Any injury or
damage that may be sustained by the employees of the other Contractors and the Employer,
due to the Contractors work shall promptly be made good at his own expense.
expen The Employer
shall determine the resolution of any difference or conflict that may arise between the
Contractor and other Contractors or between the Contractor and the workmen of the
Employer in regard to their work. If the work of the Contractor is delayed
delayed because of the any
acts of omission of another Contractor, the Contractor shall have no claim against the
Employer on that account other than an extension of time for completing his works. Employer
shall have full access to visit the contractors site
site at any time for inspection and surveillance
checks.
11.2 The Employer shall be notified promptly by the Contractor of any defects in the other
Contractors works that could affect the Contractors Works. The Employer shall determine
the corrective measures
res if any, required to rectify this situation after inspection of the works
and such decisions by the Employer shall be binding on the Contractor.
12.0 DISCIPLINE OF WORKMEN
The Contractor shall adhere to the disciplinary procedure set by the Employer in
i respect of his
employees and workmen at Site. The Employer shall be at liberty to object to the presence of
any representative or employee of the Contractor at the Site, if in the opinion of the Employer
such employee has mis-conducted
mis
himself or is incompetent,
mpetent, negligent or otherwise
undesirable then the Contractor shall remove such a person objected to and provide in his
place a competent replacement.
13.0 CONTRACTORS FIELD OPERATION
13.1 The Contractor shall keep the Employer informed in advance regarding his field activity plans
and schedules for carrying out each part of the works. Any review of such plan or schedule or
method of work by the Employer shall not relieve the Contractor of any of his responsibilities
towards the field activities. Such
Such reviews shall also not be considered as an assumption of any
risk or liability by the Employer or any of his representatives and no claim of the Contractor
will be entertained because of the failure or inefficiency of any such plan or schedule or
method of work reviewed. The Contractor shall be solely responsible for the safety, adequacy
and efficiency of plant and equipment and his erection methods.
Technical Specification:Sec-8l
Page 4 of 23
13.2 The Contractor shall have the complete responsibility for the conditions of the WorkWork Site
includingg the safety of all persons employed by him or his Sub-Contractor
Sub Contractor and all the
properties under his custody during the performance of the work. This requirement shall
apply continuously till the completion of the Contract and shall not be limited to normal
working hours. The construction review by the Employer is not intended to include review of
Contractors safety measures in, on or near the WorkWork Site, and their adequacy or otherwise.
14.0 PHOTOGRAPHS AND PROGRESS REPORT
14.1 The Contractor shall furnish
furnish three (3) prints each to the Employer of progress photographs of
the work done at Site. Photographs shall be taken as and when indicated by the Employer or
his representative. Photographs shall be adequate in size and number to indicate various
stages of erection. Each photograph shall contain the date, the name of the Contractor and
the title of the photograph.
14.2 The above photographs shall accompany the monthly progress report detailing out the
progress achieved on all erection activities as compared
compared to the schedules. The report shall also
indicate the reasons for the variance between the scheduled and actual progress and the
action proposed for corrective measures, wherever necessary.
14.3 The Contractor shall submit the progress of work in video cassettes
cassettes (2 copies) quarterly
highlighting the progress and constraints at site.
15.0 MAN-POWER REPORT
15.1 The Contractor shall submit to the Employer, on the first day of every month, a man hour
schedule for the month, detailing the man hours scheduled for the month, skill-wise
skill
and areawise.
15.2 The Contractor shall also submit to the Employer on the first day of every month, a man
power report of the previous month detailing the number of persons scheduled to have been
employed and actually employed, skill- wise and the areas of employment of such labour.
16.0 PROTECTION OF WORK
The Contractor shall have total responsibility for protecting his works till it is finally taken over
by the Employer. No claim will be entertained by the Employer or the representative of the
Employer for any damage or loss to the Contractors works and the
the Contractor shall be
responsible for complete restoration of the damaged works to original conditions to comply
with the specification and drawings. Should any such damage to the Contractors Works occur
because of other party not being under his supervision
supervision or control, the Contractor shall make
his claim directly with the party concerned. If disagreement or conflict or dispute develops
between the Contractor and the other party or parties concerned regarding the responsibility
for damage to the Contractors
Contractors Works the same shall be resolved as per the provisions of the
as specified at clause no 11 of this chapter entitled Co-operation
Co operation with other Contractors.
The Contractor shall not cause any delay in the repair of such damaged Works because of any
Technical Specification:Sec-8l
Page 5 of 23
delay in the resolution of such disputes. The Contractor shall proceed to repair the Work
immediately and no cause thereof will be assigned pending resolution of such disputes.
17.0 EMPLOYMENT OF LABOUR
In addition to all local laws and regulations pertaining to the employment of labour to be
complied with by the Contractor pursuant to GCC, the Contractor will be expected to employ
on the work only his regular skilled employees with experience of the particular work. No
female labour shall be employed
employed after darkness. No person below the age of eighteen years
shall be employed.
All travelling expenses including provisions of all necessary transport to and from Site, lodging
allowances and other payments to the Contractors employees shall be the sole responsibility
of the Contractor.
The hours of work on the Site shall be decided by the Employer and the Contractor shall
adhere to it. Working hours will normally be eight (8) hours per day Monday through
Saturday. Contractors employees shall wear identification
identification badges while on work at Site.
In case the Employer becomes liable to pay any wages or dues to the labour or any
Government agency under any of the provisions of the Minimum Wages Act, Workmen
Compensation Act, Contact Labour Regulation Abolition
Abolition Act or any other law due to act of
omission by the Contractor, the Employer may make such payments and shall recover the
same from the Contractors payments.
18.0 FACILITIES TO BE PROVIDED BY THE EMPLOYER
18.1 Space
The Contractor shall advise the Employer
Employer within thirty (30) days from the date of acceptance
of the Notification of Award about his exact requirement of space for his office, storage area,
pre-assembly
assembly and fabrication areas, labour and staff colony area, etc. The above requirement
shall be reviewed by the Employer and space as decided by Employer will be allotted to the
Contractor for construction of his temporary structures/ facilities like office, storage sheds,
pre-assembly
assembly and fabrication areas, labour and staff colony, toilets, etc. for Contractor's as
well as his Sub-Contractors
Contractors use.
18.2 Electricity
The Contractor shall submit to the Employer within thirty (30) days from the date of
acceptance of the Notification of Award, his electrical power requirements, if any, to allow the
planning
anning of the same by the Employer. The Contractor shall be provided with supply of
electricity on chargeable basis for the purposes of the Contract, only at two locations in the
Employers Site and at 415V level. The Contractor shall make his own further distribution
arrangement. All temporary wiring must comply with local regulations and will be subject to
Employers inspection and approval before connection to supply. The free supply of power will
not be provided for the use in the labour and staff colony.
colony. Power supply for labour and staff
colony shall be provided at one point and the Contractor shall be charged at rates prevalent at
Technical Specification:Sec-8l
Page 6 of 23
the site. Illumination of wagon tippler and the conveyor area shall be the scope of the
tenderer.
18.3 Water
Contractor shall make all arrangements himself for the supply of construction water as well as
potable water for labour and other personnel at the worksite/colony.
18.4 Communication
The Employer will extend the telephone facilities, if available at Site, for purposes
purpos of Contract.
The Contractor shall be charged at actuals for such facilities.
19.0 FACILITIES TO BE PROVIDED BY THE CONTRACTOR
19.1 Contractor's site office Establishment
The Contractor shall establish a site office at the site and keep posted an authorized
autho
representative for the purpose of the contract, pursuant to GCC.
19.2 Tools, tackles and scaffoldings
The Contractor shall provide all the construction equipments, tools, tackles and scaffoldings
required for pre-assembly,
assembly, installation, testing, commissioning and conducting Guarantee
tests of the equipments covered under the Contract. He shall submit a list of all such materials
to the Employer before the commencement of preassembly at Site. These tools and tackles
shall not be removed from the Site
Site without the written permission of the Employer. The
Contractor shall arrange Dozer, Hydra, Cranes, Trailer, etc. for the purpose of fabrication,
erection and commissioning.
19.3 Testing Equipment and Facilities:
The contractor shall provide the necessary
necessary testing, equipment and facilities.
19.4 Site laboratory for civil works:
Contractor shall provide and maintain a site laboratory for the testing of construction material
under the direction and general supervision of employer.
19.5 First-aid
19.5.1 The Contractor shall provide necessary first-aid
first aid facilities for all his employees, representatives
and workmen working at the Site. Enough number of Contractors personnel shall be trained
in administering first-aid.
Contractor, in case of any emergency, the services of an
19.5.2 The Employer will provide the Contractor,
ambulance for transportation to the nearest hospital.
19.6 Cleanliness
19.6.1 The Contractor shall be responsible for keeping the entire area allotted to him clean and free
from rubbish, debris etc. during the period of Contract. The Contractor shall employ enough
number of special personnel to thoroughly clean his work-area
work area at least once in a day. All such
rubbish and scrap material shall be stacked or disposed in a place to be identified by the
Technical Specification:Sec-8l
Page 7 of 23
Employer.
oyer. Materials and stores shall be so arranged to permit easy cleaning of the area. In
areas where equipment might drip oil and cause damage to the floor surface, a suitable
protective cover of a flame resistant, oil proof sheet shall be provided to protect
prote the floor
from such damage.
19.6.2 Similarly the labour colony, the offices and the residential areas of the Contractors
employees and workmen shall be kept clean and neat to the entire satisfaction of the
Employer. Proper sanitary arrangements shall be
be provided by the Contractor, in the workwork
areas, office and residential areas of the Contractor.
20.0 LINES AND GRADES
All the Works shall be performed to the lines, grades and elevations indicated on the
drawings. The Contractor shall be responsible to locate and layout the Works. Basic horizontal
and vertical control points will be established and marked by the Employer at Site at suitable
points. These points shall be used as datum for the works under the Contract. The Contractor
shall inform the Employer
yer well in advance of the times and places at which he wishes to do
work in the area allotted to him so that suitable datum points may be established and checked
by the Employer to enable the Contractor to proceed with his works. Any work done without
being
ng properly located may be removed and/or dismantled by the Employer at Contractors
expense.
21.0 FIRE PROTECTION
21.1 The work procedures that are to be used during the erection shall be those which minimise
fire hazards to the extent practicable. Combustible
Combustible materials, combustible waste and rubbish
shall be collected and removed from the Site at least once each day. Fuels, oils and volatile or
flammable materials shall be stored away from the construction and equipment and materials
storage areas in safe
fe containers. Untreated canvas, paper, plastic or other flammable flexible
materials shall not at all be used at Site for any other purpose unless otherwise specified. If
any such materials are received with the equipment at the Site, the same shall be removed
re
and replaced with acceptable material before moving into the construction or storage area.
21.2 Similarly corrugated paper fabricated cartons etc. will not be permitted in the construction
area either for storage or for handling of materials. All such materials used shall be of water
proof and flame resistant type. All the other materials such as working drawings, plans etc.
which are combustible but are essential for the works to be executed shall be protected
against combustion resulting from welding
welding sparks, cutting flames and other similar fire
sources.
21.3 All the Contractors supervisory personnel and sufficient number of workers shall be trained
for fire-fighting
fighting and shall be assigned specific fire protection duties. Enough of such trained
personnel
ersonnel must be available at the Site during the entire period of the Contract.
Technical Specification:Sec-8l
Page 8 of 23
21.4 The Contractor shall provide enough fire protection equipment of the types and number for
the warehouses, office, temporary structures, labour colony area etc. Access to such fire
protection equipment, shall be easy and kept open at all time.
22.0 SECURITY
The Contractor shall have total responsibility for all equipment and materials in his custody
stores, loose, semi-assembled
assembled and/or erected by him at Site. The Contractor
Contrac
shall make
suitable security arrangements including employment of security personnel to ensure the
protection of all materials, equipment and works from theft, fire, pilferage and any other
damages and loss. All materials of the Contractor shall enter and leave the Employer Site only
with the written permission of the Employer in the prescribed manner.
23.0 CONTRACTORS AREA LIMITS
out the boundary limits of access roads, parking spaces, storage and
The Employer will mark-out
construction areas for the Contractor and the Contractor and his personnel shall not trespass
the areas into other areas of the plant. In case of a need for the Contactors personnel to work
in the areas beyond that marked out for him, the same shall be done only with the written
permission of the Employer.
OPERATION WITH THE EMPLOYER
24.0 CONTRACTORS CO-OPERATION
In case where the performance of the erection work by the Contractor affects the operation of
the system facilities of the Employer, such erection work of the Contractor shall be scheduled
to be performed only in the manner stipulated by the Employer and the same shall be
acceptable at all times to the Contractor. The Employer may impose such restrictions on the
facilities provided to the Contractor such as electricity, etc. as he may think fit in the interest
of the Employer and the Contractor shall strictly adhere to such restrictions and co-operate
co
with the Employer. It will be the responsibility of the Contractor to provide all necessary
temporary instrumentation and other measuring devices required during start-up
start
and
operation of the equipment systems which are erected by him. The Contractor shall also be
responsible for flushing and initial filling of all the oil and lubricants required for the
equipment furnished and installed by him, so as to make such equipment ready for operation.
The Contractor shall be responsible for supplying such flushing oil and other lubricants.
COMMISSIONING AND COMMISSIONING ACTIVITIES
25.0 PRE-COMMISSIONING
(a)
GENERAL
The Contractor upon completion of installation of equipments and systems, shall conduct
pre-commissioning
commissioning and commissioning activities, to make the equipment/systems ready for
safe,
reliable
and
efficient
operation
on
sustained
basis.
All
pre
precommissioning/commissioning
/commissioning activities considered essential for such readiness of the
equipment/systems including those mutually agreed and included in the Contractors quality
Technical Specification:Sec-8l
Page 9 of 23
(c)
The following activities shall be carried out by the contractor, prior to schedule date of
commissioning
ioning of the equipment/systems installed by him.
The contractor shall furnish the organization chart of his operation and commissioning
engineers for the acceptance of employer. Adequate number of operation and
commissioning engineers shall be deployed
deployed by the contractor to effectively meet the
requirement of round the clock operation in shifts also, till the plant is taken over by the
employer.
(ii) The contractor shall submit the bio-data
bio data containing the details of experience of his
operation and commissioning
mmissioning engineers for the acceptance of employer.
(iii) The contractor shall furnish the deployment schedule of his operation and commissioning
engineers for the acceptance of the employer.
(iv) Apart from above, contractor shall ensure deployment of sufficientskilled/semisufficientskilled/semi
skilled/unskilled manpower during pre-commissioning
pre commissioning and commissioning activities.
(i)
(d)
(e)
The Contractor shall also be responsible for flushing and initial filling of all oils and lubricants
required for the equipment furnished and installed by him so as to make such equipment
ready for operation. The Contractor shall be responsible for supplying such flushing oil and
other lubricants unless otherwise specified elsewhere in these specifications and documents.
Page 10 of 23
COMMISSIONING ACTIVITIES
ompletion of pre-commissioning
pre commissioning activities/tests, the contractor shall initiate
(a)
Upon completion
commissioning of facilities. During commissioning the Contractor shall carry out system
checking and reliability trials on various sub-systems
sub
of the facilities.
(b) Contractor shall carry out the checks/tests at site to demonstrate to the Employer that
each of the equipment of the supplied complies with requirements stipulated and is installed
in accordance with requirements specified.
Before the plant is put into initial operation
operation the Contractor shall be required to conduct
(c)
test to demonstrate to the Employer that each item of the plant is capable of correctly
performing the functions for which it was specified and its performance, parameters etc. are
as per the specified/approved
specified/approved values. These tests may be conducted concurrently with those
required under commissioning sequence.
(d) Other tests shall be conducted, if required by the Employer, to establish that the plant
equipment are in accordance with requirements of the specifications.
specifica
The Contractor shall conduct all the commissioning tests and undertake commissioning
(e)
activities pertaining to all other auxiliaries and equipments including all electrical
equipment/systems not specifically brought out above but are within the scope
sco of work and
facilities being supplied and installed by the Contractor and follow the guidelines indicated
above or elsewhere in these technical specifications(Sectionspecifications(Section VI)
(f)
Initial Operation
Technical Specification:Sec-8l
Page 11 of 23
Technical Specification:Sec-8l
Page 12 of 23
(j) The Contractor shall be responsible for making suitable indoor storage facilities to store
all equipment which require indoor storage. Normally, all the electrical equipments such as
motors, control gear, exciters and consumables like electrodes, lubricants
lubricants etc. shall be stored
in the closed storage space . The Employer, in addition, may direct the Contractor to move
certain other materials, which in his opinion will require indoor storage, to indoor storage
areas which the Contractor shall strictly comply with.
29.0 CONSTRUCTION MANAGEMENT
(a) The field activities of the Contractors working at Site, will be coordinated by the Employer
and the Employer decision shall be final in resolving any disputes or conflicts between the
Contractor and other Contractors
Contractors and tradesmen of the Employer regarding scheduling and
co- ordination of work. Such decision by the Employer shall not be a cause for extra
compensation or extension of time for the Contractor.
Contractors working at Site, at a time
(b) The Employer shall hold weekly meetings of all the Contractors
and place to be designated by the Employer. The Contractor shall attend such meetings and
take notes of discussions during the meeting and the decisions of the Employer and shall
strictly adhere to those decisions in performing
performing his Works. In addition to the above weekly
meeting, the Employer may call for other meeting either with individual Contractors or with
selected number of Contractors and in such a case the Contractor if called, will also attend
such meetings.
(c) Time is the essence of the Contract and the Contractor shall be responsible for
performance of his works in accordance with the specified construction schedule. If at any
time, the Contractor is falling behind the schedule, he shall take necessary action to
t make
good for such delays by increasing his work force or by working overtime or otherwise
accelerate the progress of the work to comply with the schedule and shall communicate such
actions in writing to the Employer, satisfying that his action will compensate
compensate for the delay. The
Contractor shall not be allowed any extra compensation for such action.
(d) The Employer shall however not be responsible for provision of additional labour and/or
materials or supply or any other services to the Contractor except
except for the coordination work
with other Contractors, if necessary.
30.0 FIELD OFFICE RECORDS
The Contractor shall maintain at his Site Office up-toup
date copies of all drawings,
specifications and other Contract Documents and any other supplementary data complete
with all the latest revisions thereto. The Contractor shall also maintain in addition the
continuous record of all changes to the above Contract Documents, drawings, specifications,
supplementary data, etc. effected at the field and on completion of his total assignment under
the Contract shall incorporate all such changes on the drawings and other Engineering data to
indicate as installed conditions of the equipment furnished and erected under the Contract.
Technical Specification:Sec-8l
Page 13 of 23
Such drawings and Engineering data shall be submitted to the Employer in requisite number
of copies.
31.0 CONTRACTORS MATERIALS BROUGHT ON TO SITE
(a) The Contractor shall bring to Site all equipment, components, parts, materials, including
construction equipment, tools and tackles for the purpose of the Works under intimation to
the Employer. All such goods shall, from the time of their being brought vest in the Employer,
but may be used for the purpose of the Works only and shall not on any account be removed
or taken away by the Contractor
Contractor without the written permission of the Employer. The
Contractor shall nevertheless be solely liable and responsible for any loss or destruction
thereof and damage thereto.
(b) The Employer shall have a lien on such goods for any sum or sums which may at any time
be due or owing to him by the Contractor, under, in respect of or by reasons of the Contract.
After giving a fifteen (15) days notice in writing of his intention to do so, the Employer shall be
at liberty to sell and dispose off any such goods, in such manner as he shall think fit including
public auction or private treaty and to apply the proceeds in or towards the satisfaction of
such sum or sums due as aforesaid.
(c) After the completion of the Works, the Contractor shall remove from the Site under
u
the
direction of the Employer the materials such as construction equipment, erection tools and
tackles, scaffolding etc. with the written permission of the Employer. If the Contractor fails to
remove such materials, within fifteen (15) days of issue of
of a notice by the Employer to do so
then the Employer shall have the liberty to dispose off such materials as detailed under as
specified at clause no 31 (b) above and credit the proceeds thereto to the account of the
Contractor.
TY AND CONTRACTORSLIABILITY
32.0 PROTECTION OF PROPERTY
(a) The Contractor shall be responsible for any damage resulting from his operations. He
shall also be responsible for protection of all persons including members of public and
employees of the Employer and the employees of other
other Contractors and SubSub Contractors and
all public and private property including structures, building, other plants and equipments and
utilities either above or below the ground.
(b) The Contractor will ensure provision of necessary safety equipment such as barriers, sign
- boards, warning lights and alarms, etc. to provide adequate protection to persons and
property. The Contractor shall be responsible to give reasonable notice to the Employer and
the Employers of public or private property and utilities
utilities when such property and utilities are
likely to get damaged or injured during the performance of his Works and shall make all
necessary arrangements with such Employers, related to removal and/or replacement or
protection of such property and utilities.
utilities
Technical Specification:Sec-8l
Page 14 of 23
33.0 PAINTING
All exposed metal parts of the equipment including pipings, structure railings, etc. wherever
applicable, after installation unless otherwise surface protected, shall be first painted with at
least two coats of suitable primer which matches
matches the shop primer paint used, after throughly
cleaning all such parts of all dirt, rust, scales, greases, oils and other foreign materials by wire
brushing, scraping or sand blasting and the same being inspected and approved by the
Employer/RITES for painting.
nting. Afterwards, the above parts shall be finished painted with two
t
coats of synthetic enamel paint.
paint. The minimum thickness of paint film shall not be less than
100 microns. The quality of the finish paint shall be as per the standards of Bureau of Indian
Standards (BIS) or equivalent and to be of the colour as approved by the Employer.
34.0 INSURANCE
34.1 In addition to the conditions covered under the Clause entitled Insurance in Section General
Conditions of Contract (GCC), the following provisions will also apply to the portion of works
to be done beyond the Contractors own or his Sub-Contractors
Sub Contractors manufacturing Works.
34.2 Workmens Compensation Insurance
This insurance shall protect the Contractor against all claims applicable under the Workmens
Workmen
Compensation Act, 1948 (Government of India). This policy shall also cover the Contractor
against claims for injury, disability disease or death of his or his Sub-Contractors
Sub Contractors employees,
which for any reason are not covered under the Workmens Compensation
Compensati Act, 1948. The
liabilities shall not be less than the following:
Workmen's Compensation - As per Statutory Provisions
Employee's Liability - As per Statutory Provisions
Property Damage: Rs.100,000 for each occurrence
34.3 Comprehensive General Liability Insurance
34.3.1 The insurance shall protect the Contractor against all claims arising from injuries, disabilities,
disease or death of members of public or damage to property of others, due to any act or
omission on the part of the Contractor, his agents, his employees, his representatives and
Sub-Contractors
Contractors or from riots, strikes and civil commotion. This insurance shall also cover all
the liabilities of the Contractor arising out of the Clause entitled Defence of Suits in Section
General Conditions
nditions of Contract (GCC).
34.3.2 The hazards to be covered will pertain to all the Works and areas where the Contractor, his
Sub-Contractors,
Contractors, his agents and his employees have to perform work pursuant to the
Contract.
illustrative list of insurance covers normally required and it will be the
34.4 The above are only illustrative
responsibility of the Contractor to maintain all necessary insurance coverage to the extent
Technical Specification:Sec-8l
Page 15 of 23
both in time and amount to take care of all his liabilities either direct or indirect, in pursuance
pursuanc
of the Contract.
35.0 UNFAVOURABLE WORKING CONDITIONS
The Contractor shall confine all his field operations to those works which can be performed
without subjecting the equipment and materials to adverse effects during inclement weather
conditions, likee monsoon, storms, etc. and during other unfavourable construction conditions.
No field activities shall be performed by the Contractor under conditions which might
adversely affect the quality and efficiency thereof, unless special precautions or measures are
taken by the Contractor in a proper and satisfactory manner in the performance of such
Works and with the concurrence of the Employer. Such unfavourable construction conditions
will in no way relieve the Contractor of his responsibility to perform the Works as per the
schedule.
36.0 PROTECTION OF MONUMENTS AND REFERENCE POINTS
The Contractor shall ensure that any finds such as relic, antiquity, coins, fossils, etc. which he
may come across during the course of performance of his Works either during excavation or
elsewhere, are properly protected and handed over to the Employer. Similarly the Contractor
shall ensure that the bench marks, reference points, etc., which are marked either with the
help of Employer or by the Employer shall not be disturbed in any way during the
performance of his Works. If, any work is to be preformed which disturb such reference, the
same shall be done only after these are transferred to other suitable locations under the
direction of the Employer. The Contractor shall provide
provide all necessary materials and assistance
for such relocation of reference points etc.
37.0 WORK & SAFETY REGULATIONS
37.1 The Contractor shall ensure proper safety of all the workmen, materials, plant and
equipments belonging to him or to Employer or to others, working at the Site. The Contractor
shall also be responsible for provision of all safety notices and safety equipment required both
by the relevant legislation and the Employer as he may deem necessary.
37.2 All equipment used in construction and erection by Contractor shall meet Indian/International
Standards and where such standards do not exist, the Contractor shall ensure these to be
absolutely safe. All equipments shall be strictly operated and maintained by the Contractor in
accordance with
th manufacturers operation Manual and safety instructions and as per
Guidelines/Rules of Employer in this regard.
37.3 Periodical Examinations and all tests for all lifting/ hoisting equipment & tackles shall be
carried-out
out in accordance with the relevant
relevant provisions of Factories Act 1948, Indian Electricity
Act 1910 and associated Laws/Rules in force from time to time. A register of such
examinations and tests shall be properly maintained by the Contractor and will be promptly
produced as and when desired by Employer or by the person authorised by him.
Technical Specification:Sec-8l
Page 16 of 23
37.4 The Contractor shall provide suitable safety equipment of prescribed standard to all
employees and workmen according to the need, as may be directed by Employer who will also
have right to examine these
these safety equipments to determine their suitability, reliability,
acceptability and adaptability.
37.5 The Contractor shall provide safe working conditions to all workmen and employees at the
Site including safe means of access, railings, stairs, ladders, scaffoldings etc. The scaffoldings
shall be erected under the control and supervision of an experienced and competent person.
For erection, good and standard quality of material only shall be used by the Contractor.
37.6 The Contractor shall not interfere or disturb electric fuses, wiring and other electrical
equipment belonging to the Employer or other Contractors under any circumstances,
whatsoever, unless expressly permitted in writing by the Employer to handle such fuses,
wiring or electrical equipment.
equipment
37.7 No electric cable in use by the Contractor/Employer will be disturbed without prior
permission. No weight of any description will be imposed on any cable and no ladder or
similar equipment will rest against or attached to it.
37.8 The Contractors shall employ necessary number of qualified, full time Electricians/ Electrical
Supervisors to maintain his temporary electrical installations.
37.9 In case any accident occurs during the construction/ erection or other associated activities
undertaken by the Contractor thereby causing any minor or major or fatal injury to his
employees due to any reason, whatsoever, it shall be the responsibility of the Contractor to
promptly inform the same to the Employer in prescribed form and also to all the authorities
authoritie
envisaged under the applicable laws.
37.10 The Employer shall have the right at his sole discretion to stop the work, if in his opinion the
work is being carried out in such a way that it may cause accidents and endanger the safety of
the persons and/or property, and/or equipments. In such cases, the Contractor shall be
informed in writing about the nature of hazards and possible injury/accident and he shall
comply to remove shortcomings promptly. The Contractor after stopping the specific work
can, if felt
elt necessary appeal against the order of stoppage of work to the Employer within 3
days of such stoppage of work and decision of the Employer in this respect shall be conclusive
and binding on the Contractor.
for any damages/ compensation for stoppage of work due
37.11 The Contractor shall not be entitled for
to safety reasons as provided above and the period of such stoppage of work will not be taken
as an extension of time for completion of the facilities.
38.0 FOUNDATION DRESSING & GROUTING FOR EQUIPMENT/ EQUIPMENT BASES
Technical Specification:Sec-8l
Page 17 of 23
38.1 The surfaces of foundations shall be dressed to bring the top surface of the foundations to the
required level, prior to placement of equipment/equipment bases on the foundations.
38.2 All the equipment/ equipment bases, shall be grouted and finished as per these specifications
unless otherwise recommended by the equipment manufacturer.
38.3 The concrete foundation surfaces shall be properly prepared by chipping, grinding as required
to bring the top of such foundation to
to the required level, to provide the necessary roughness
for bondage and to assure enough bearing strength.
38.4 Grout
The grout shall be high strength grout having a minimum characteristic compressive strength
of 60 N/mm2 at 28 days. The grout shall be chloride - free, cement based, free flowing, nonnon
metallic grout. The Grout shall have good flowability even at very low water/ grout powder
ratio. The Grout shall have characteristics of controlled expansion to be able to occupy its
original volume to filll the voids and to compensate for shrinkage. Grout shall be of pre-mix
pre
variety so that only water needs to be added before use. The mixing of the Grout shall
conform to the recommendations of the manufacturer of the Grout.
t Grout
38.5 Finishing of the Edges of the
The poured grout should be allowed to stand undisturbed until it is well set. Immediately
thereafter, the dam shall be removed and grout which extends beyond the edges of the
structural or equipment base plates shall be cut off, flushed and removed.
removed. The edges of the
grout shall then be pointed and finished with 1:2 cement mortar pressed firmly to bond with
the body of the grout and smoothened with a tool to present a smooth vertical surface. The
work shall be done in a clean and scientific manner and the adjacent floor spaces, exposed
edges of the foundations, and structural steel and equipment base plates shall be thoroughly
cleaned of any spillage of the grout.
38.6 CHECKING OF EQUIPMENT AFTER GROUTING
After the grout is set and cured, the Contractor
Contractor shall check and verify the alignment of
equipments, alignment of shafts of rotating machinery, the slopes of all bearing pedestals,
centering of rotors with respect to their sealing bores, couplings, etc. as applicable and the like
items to ensure that
hat no displacement had taken place during grouting. The values recorded
prior to grouting shall be used during such post grouting checkcheck up and verifications. Such pre
and post grout records of alignment details shall be maintained by the Contractor in a manner
acceptable to the Employer.
39.0 SHAFT ALIGNMENTS
All the shafts of rotating equipment shall be properly aligned to those of the matching
equipments to as perfect an accuracy as practicable. The equipment shall be free from
excessive vibration so as to avoid overheating of bearings or other conditions which may tend
to shorten the life of the equipment. The vibration level of rotating equipments measured at
Technical Specification:Sec-8l
Page 18 of 23
bearing housing shall not exceed forty (40) microns and shall conform to VDI 2056.All
bearings,
gs, shafts and other rotating parts shall be thoroughly cleaned and suitably lubricated
before starting.
40.0 DOWELLING
All the motors and other equipment shall be suitably doweled after alignment of shafts with
tapered machined dowels as per the direction
directi of the Employer.
41.0 CHECK OUT OF CONTROL SYSTEMS
After completion of wiring, cabling furnished under separate specification and laid and
terminated by the Employer, the Contractor shall check out the operation of all control
systems for the equipment
equipment furnished and installed under these specifications and documents.
42.0 COMMISSIONING SPARES
42.1 It will be the responsibility of the Contractor to provide all commissioning spares including
consumable spares required for initial operation till the Completion of Facilities. The
Contractor shall furnish a list of all commissioning spares within 60 days from the date of
Notification of Award and such list shall be reviewed by the Employer and mutually agreed to.
However. such review and agreement will not absolve the Contractor of his responsibilities to
supply all commissioning spares so that initial operation
operation do not suffer for want of
commissioning spares. All commissioning spares shall be deemed to be included in the scope
of the Contract at no extra cost to the Employer.
42.2 These spare will be received and stored by the Contractor atleast 3 months prior to the
schedule date of commencement of initial operation of the respective equipment and utilised
as and when required. The unutilised spares and replaced parts, if any, at the end of
successful completion of guarantee tests shall be the property of the Contractor and he will be
allowed to take these parts back at his own cost with the permission of Employer. Employer
will be informed of the list of commissioning spares brought to site by the contractor before
bringing the same to the site.
43.0 CABLING
43.1 All cables shall be supported by conduits or cable tray run in air or in cable channels. These
shall be installed in exposed runs parallel or perpendicular to dominant surfaces with right
angle turn made of symmetrical bends or fittings. When cables
cables are run on cable trays, they
shall be clamped at a minimum intervals of 2000mm or otherwise as directed by the
Employer.
43.2 Each cable, whether power or control, shall be provided with a metallic or plastic tag of an
approved type, bearing a cable reference number indicated in the cable and conduit list
(prepared by the Contractor), at every 5 meter run or part thereof and at both ends of the
Technical Specification:Sec-8l
Page 19 of 23
cable adjacent to the terminations. Cable routing is to be done in such a way that cables are
accessible forr any maintenance and for easy identification.
43.3 Sharp bending and kinking of cables shall be avoided. The minimum radii for PVC insulted
cables 1100 V grade shall be 15 D where D is the overall diameter of the cable. Installation of
other cables like high
igh voltage, coaxial, screened, compensating, mineral insulated shall be in
accordance with the cable manufacturers recommendations.
43.4 In each cable run some extra length shall be kept at a suitable point to enable one or two
straight through joints to be made, should the cable develop fault at a later date.
43.5 Control cable terminations shall be made in accordance with wiring diagrams, using
identifying codes subject to the Employers approval. Multicore control cable jackets shall be
removed as required
equired to train and terminate the conductors. The cable jacket shall be left on
the cable, as far as possible, to the point of the first conductor branch. The insulated
conductors from which the jacket is removed shall be neatly twined in bundles and
terminated.
inated. The bundles shall be firmly but not tightly tied utilizing plastic or nylon ties or
specifically treated fungus protected cord made for this purpose. Control cable conductor
insulation shall be securely and evenly cut.
rol cables shall be covered with a transparent insulating sleeve so as to
43.6 The connectors for control
prevent accidental contact with ground or adjacent terminals and shall preferably terminate in
Elmex terminals and washers. The insulating sleeve shall be fire resistant and shall be long
enough to over pass the conductor insulation. All control cables shall be fanned out and
connection made to terminal blocks and test equipment for proper operation before cables
are corded together.
44.0 EQUIPMENT DELIVERY AND ERECTION
44.1 General Requirements
(a.) This part covers Contractor's responsibilities for packing, shipping, warehousing and the
installation of all equipment and materials furnished and installed under this specification.
(b.) The Contractor shall submit for Employer's approval draft manual for Equipment Delivery
and Erection covering detailed instructions, write up, technical data, drawings, check-lists,
check
documentation formats for all activities after equipment manufacture upto installation of
equipment. This manual shall cover general
general instructions for all equipment and specific
instructions for individual equipment wherever required and shall include at least the
following :
ware housing and storage.
i. Instructions for packing, shipping, receiving handling, ware-housing
ii. Instructions for location and
and installation of equipment furnished by this specification.
iii. Installation drawings for field mounted equipment, panels, cubicles and other
equipment covered under this specification.
iv. Instruction relating installation of piping/ tubing, support and routing drawings of
impulse pipes/signal tubes and tube/cable trays.
Technical Specification:Sec-8l
Page 20 of 23
Technical Specification:Sec-8l
Page 21 of 23
(h) Packaging or shipping units shall be designed within the limitations of unloading facilities
and the equipment which will be used for transport. Complications
Complications involved with ocean
shipment and the limitations of ports, railways and roads shall be considered. It shall be the
Contractor's responsibility to investigate these limitations and to provide suitable packaging
to permit safe handling during transit and at the job site.
(i) Electrical equipment, control and instrumentation shall be protected against moisture and
water damage. All external gasket surfaces and flange faces, couplings, motor pump shafts,
bearing and like items shall be thoroughly cleaned and coated
coated with rust preventive
compound as specified above and protected with suitable wood, metal or other substantial
type covering to ensure their full protection.
(j) Equipment having antifriction or sleeve bearings shall be protected by weather tight
enclosures.
(k) Coated surfaces shall be protected against impact, abrasion, discolouration and other
damage. Surfaces which are damaged shall be repaired.
(l) All exposed threaded parts shall be greased and protected with metallic or other substantial
type protectors. All female threaded openings shall be closed with forged steel plugs. All
pipings, tubing, and conduit equipment and other equipment openings shall be sealed with
metallic or other rough usage covers and tapped to seal the interior of the equipment
piping, tubing,
ing, or conduit.
(m) Provisions shall be made to ensure that water does not enter any equipment during
shipment or in storage at the plant site.
(n) Returnable containers and special shipping devices shall be returned by the manufacturer's
field representative at the Contractor's expense.
(o) While packaging the material, care shall be taken for the limitation from the point of view of
availability of railway wagon sizes in India.
44.3 Equipment Installation
(a.)
General Requirements
The Contractor shall furnish all construction materials, tools and equipment and shall perform
all work required for complete installation of all control and instrument equipment furnished
under this specification. Contractor shall prepare detailed installation
installation drawings for each
equipment furnished under this specification for Employer's approval. Installation of all
equipment/systems furnished by this specification shall be as per Employer's approval.
Erection procedures not specified herein shall be in accordance
accordance with the recommendations of
the equipment manufacturers. The procedures shall be acceptable to the Employer. The
Contractor shall coordinate his work with other suppliers where their instruments and devices
are to be installed under specifications.
specifications
(b.) Installation Materials
All materials required for installation, testing and commissioning of the equipment shall be
furnished by the Contractor.
(c.) Regulatory Requirements
Technical Specification:Sec-8l
Page 22 of 23
All installation procedures shall confirm with the accepted good engineering practice
practi and with
all applicable governmental laws, regulations and codes.
(d.) Cleaning
All equipment shall be cleaned of all sand, dirt and other foreign materials immediately after
removal from storage and before the equipment is brought to installation site.
(e.) Equipment Assembly
Equipment installed under these specifications shall be assembled if shipped unassembled.
The equipment shall be dismantled and reassembled as required to perform the installation
and commi ssioning work described in these specifications.
specifications
(f.) Defects
All defects in erection shall be corrected to the satisfaction of the Employer and the Project
Manager. The dismantling and reassembly of Contractor furnished equipment to remove
defective parts, replace parts, or make adjustments shall be included
included as a part of the work
under these specifications. The removal of control and instrument equipment in order to
allow bench calibration, if required, and the re-installation
re installation of the said equipment after
calibration shall also be included as a part of the work under these specifications.
45.0 DEVIATIONS DISPOSITIONING:
Any deviation to the contract and employer approved documents shall be properly recorded
in the format prescribed by NALCO. Al the deviations shall be bought to the knowledge of
employers representative for suitable dispositioning.
DESTRUCTIVE TESTING ( NDT):
46.0 NON-DESTRUCTIVE
The contractor shall record results of NDTs carried out at site in the format acceptable to
employer. All the radiographs & its report duly signed & correlated to the job shall
sh be handed
over to the employer. Sensitivity of all the test equipment shall be compatible to the job &
acceptance norms agreed.
47.0 TESTING EQUIPMENT & FACILITIES:
Contractor shall provide the testing equipment and facilities necessary to carry out tests &
inspections.
Technical Specification:Sec-8l
Page 23 of 23
SECTION 9
(MISCELLANEOUS)
PAINTING
1.0
1.1
GENERAL
This specification covers the materials, tools, facilities and quality requirement for surface
preparation and painting of steel structures, equipment, piping including supports, hangers,
gas and air ducts including hangers, chutes etc.
g" referred herein covers rust preventive, preventive and decorative coating
The term "painting"
along with surface protection.
1.2
Surfaces in direct bonded contact with concrete, aluminium, asbestos, brass; bronze,
galvanized steel, stainless steel, cast iron and other corrosion
corrosion resistant alloys,
rubber/synthetic polymers are not required to be painted unless specified except for aesthetic
purposes or for identification bands. Except for such surfaces, painting and surface
preparation shall be provided to protect all surfaces
surfaces that shall be subjected to atmospheric
action and exposed to corrosive medium.
All machined mating surfaces (eg. flanges) shall be properly cleaned, greased and protected
before dispatch.
1.3
The complete paint system for any item includes the following
fo
activities:
i) Proper surface preparation
ii)
Application of primer coats
iii)
Application of intermediate coats
iv)
Application of finished coats
All the above coats shall be of quality paint products and of approved make as stipulated in
this specification. The
he work shall also include supply of all paint materials as per specification
described herein and of approved quality.
2.0
SURFACE PREPARATION
2.1
Surface preparation being a pre requisite for any paint application, shall be such as to clean
the surface
ace thoroughly of any materials which will be conducive to premature failure of the
paint substrates.
All surfaces shall be cleaned of loose substances and foreign materials, such as dirt, rust, scale,
oil, grease, welding flux, etc. irrespective of whether the same has been spelt out in the
standards in order that the prime coat is rigidly anchored to the virgin metal surface. The
surface preparation shall conform to pictorial representation of surface quality grade of DIN
2.2
Technical Specification:Sec-9,Miscellaneous
Page 1 of 55
55928 (Part 4) or BS 4232 or IS 1477 - 1971 ( Part I ). Any grease, oil, dust or foreign matter
deposited on the surface after preparation
preparation shall be removed and care taken that the surface is
not contaminated with acids, alkalis moisture or other corrosive chemicals. The prime coat
shall be applied as soon as possible after the surface preparation is completed.
2.3
The acceptable surfacee preparation quality / grades are described under each painting system.
The procedures covered are solvent cleaning, hand tool cleaning, power tool cleaning and
blast cleaning.
2.4
Solvent cleaning
The surface shall be cleaned by wiping, immersion, spraying
spraying or vapor contacting of a suitable
solvent or washing with an emulsion or alkaline solution to remove oil, grease, dirt, old paint,
etc. Solvent cleaning shall not remove rust, scales, mill scales or weld flux. Therefore, before
application of paint,, solvent cleaning shall be followed by other cleaning procedures as stated
elsewhere.
2.5
2.6
2.7
Blast cleaning
3.0
Technical Specification:Sec-9,Miscellaneous
Page 2 of 55
A single pack air drying phenolic modified alkyd composition with zinc phosphate as
a primer paint.
Air drying time
- About 60 minutes (touch dry)
-Overnight (hard dry)
Dry film thickness
- 40 microns (min)
(DFT / Coat)
4.0
3.2
3.3
INTERMEDIATE PAINTS ( I )
These paints shall be applied over primer coats as an intermediate layer to provide
weatherproof seal of primer coats.
4.1
pack air drying high build epoxy resin based paint with MIO.
A two-pack
Air drying time
- 6 to 8 hours (touch dry)
- 7 days (full cure)
DFT / coat
- 100 microns
Compatible with
- Primer P2
Technical Specification:Sec-9,Miscellaneous
Page 3 of 55
5.0
5.1
Finish Paint F1
A single pack air drying high gloss phenolic alkyd modified synthetic enamel paint suitably
pigmented.
-3 to 4 hours (touch dry) -24
24 hours (hard dry)
Air drying time
DFT / coat
- 25 microns (min)
Compatible with
Intermediate I1
- Primer P1
Colour
- generally all shades
5.2
Finish Paint F2
A two pack air drying epoxy polyamide enamel suitably pigmented.
Air drying time
- 2 to 3 hours (touch dry)
- 7 days (full cure)
DFT / coat
- 40 microns (min)
Compatible with
Intermediate I2
- Primer P2
Colour
- generally all shades
5.3
Finish Paint F3
A single pack heat resistant silicon resin based paint with leafing Aluminium powder.
Air drying time
- 3 to 4 hours (touch dry)/24 hrs (hard dry)
DFT / coat
- 20 microns (min)
Compatible with
- no primer paint except P3
(shalll be applied on blast cleaned steel surface)
Colour
- smooth aluminium
6.0
PAINT APPLICATION
6.1
6.2
Paint shall not be applied when the ambient temperature is 500 C and
d above or 450 C and
below.. Also paint shall not be applied in rain, wind, fog or at relative humidity of 80 % and
above unless the manufacturer's recommendations permit. Application of paint shall be only
by spraying or brushing as per IS 486 - 1983 and IS 487 - 1985.
Technical Specification:Sec-9,Miscellaneous
Page 4 of 55
6.3
Each coat of paint shall be continuous, free of pores and of even film thickness without thin
spots.
6.4
Each coat of paint shall be dry sufficiently before application of next coat.
6.5
The colour code to be followed during painting shall be intimated to the successful Tenderer
during finalization of order.
6.6
In the event of conflict between this general procedure for painting and the paint
manufacturer's specification, the same shall
shall be immediately brought to the notice of the
Purchaser. Generally in cases of such conflicts, manufacturer's specifications /
recommendations shall prevail.
6.7
General compatibility between primer and finishing paints shall be certified by the paint
manufacturer
anufacturer supplying the paints.
6.8
Areas that become inaccessible after assembly shall be painted before assembly (after
painting clearance has been given by the inspecting authority) after requisite surface cleaning
as specified.
h cannot be painted but require protection shall be given a coat of rust inhibitive
Surfaces which
grease according to IS 958 - 1975 or solvent deposited compound according to IS 1153 - 1975
or IS 1674 - 1960.
6.9
6.10 Parts of steel structures embedded in concrete shall be given a protective coat of Portland
cement slurry immediately after fabrication and after surfaces of this part is thoroughly
cleaned from grease, rust, mill scales, etc. No paint shall be applied on this part.
shade of the paint shall have the approval of the Purchaser.
6.11 The proposed make, quality and shade
6.12 Zinc rich primer paints which have been exposed several months before finishing coat is
applied shall be washed down thoroughly to remove soluble zinc salt deposits.
6.13 The machine finished
hed surfaces shall be coated with white lead and tallow before shipment or
before being put out into the open air.
6.14 Total DFT for heat resistant paints should not exceed 100 -120
120 microns, otherwise flaking
occurs ( as per paint manufacturer's recommendations
recomme
).
6.15 Heat resistant paints should be applied by brush.
7.0
PAINTING SCHEME
7.1
For a complete painting scheme of any item being painted, all types of paints are to be
procured from the same manufacturer as approved by the Purchaser.
7.2
Legend
Technical Specification:Sec-9,Miscellaneous
Page 5 of 55
SP
Surface preparation quality
2P1
Two (2) coats of primer paint type P1
1I1
One ( 1 ) coat of intermediate paint type
I1 2F1 - Two ( 2 ) coats of finish paint type F1
DFT
Dry film thickness
Type of paint products like P1, P2, P3, I1, I2, F1, F2 and F3 have been specified under sl.
nos.03, 04 and 05 of this specification.
7.3
The painting scheme to be followed for various equipment/ structures is briefly given below
for guidance to the Tenderer.
Painting scheme
Sl. No.
Description
DFT
Total
At shop
At site
SP - St 3
1.
Steel structure
2P1+1I1
2F1
100
2.
3.
Mechanical
SP - Sa 2 1/2 (or St 3)
equipment(temp.
not over 80 deg C)
Both static and
2P1+1I1
2F1 & 2F2
rotary equipment
or 2P2+1I2
for
indoor
or
outdoor duty
Equipment
with
hot
surfaces SP- Sa 2 1/2
(temp. 200 deg C
and above)
P3
2F3
205
(260)
100
8.0
Colour code
For painting certain standard colour as listed below, shall be used by the bidder.
8.1
DESCRIPTION
COLOUR
11 kV, AC machine
3.3 kV, AC machine
400 V, AC machine
460 V, DC machine
250 V, DC machine
230 V, AC equipment
110 V, AC equipment
All indoor control and switchgear panels
Light grey
Post office red
Brilliant green
Azure blue
Oriental blue
Light orange
Canary yellow
Grey
Technical Specification:Sec-9,Miscellaneous
SHADE
IS:5
631
538
221
104
174
557
309
697
AS
Page 6 of 55
8.3
Drinking water
Industrial water
Hydraulic power water
Compressed air
Instrument air
Vacuum
Technical Specification:Sec-9,Miscellaneous
Colour
Base - Sea green
Band - White
Base - Sea green
Band - French blue
Base - Sea green
Base - Sea green
Band - Light brown
Base - Sea green
First band - French blue Second
band - Signal red
Base - Sea green
Band - Light orange
Base - Sea green
Band - Black
Base - Sky blue
Base - Sky blue
Band - Light brown
Base - Sky blue
Band - Black
Base - Silver grey if Bitulac or AlAl
jacket
Band - Brilliant green
Base - Silver grey if Bitulac or AlAl
jacket
Band - French blue
Base - Al-jacket
Band - Dark violet
Base - Al-jacket
Band - Signal red
Base - Black
Base - Light brown
Band - Light grey
Base- Light brown
Shade as IS:5
217
217
166
217
217
410
217
166
537
217
557
217
101
101
410
101
628
221
628
166
796
537
410
631
410
Page 7 of 55
Transformer oil
Fuel oil
Coke oven/coal gas/other fuel gases
Freon (chlorofluore
methane and ethane)
derivative
Argon
Acetylene
LP gas
Nitrogen
Oxygen
Regenerated acid (dilute) (1)
Spent liquor
Wash liquor
Technical Specification:Sec-9,Miscellaneous
796
410
557
410
537
309
537
309
631
309
166
309
796
309
537
267
309
309
796
410
796
410
410
796
631
410
796
631
796
631
221
796
628
796
796
360
217
537
217
101
Page 8 of 55
Duct work
Lighting conduits
Instrument conduits
Power conduits
Technical Specification:Sec-9,Miscellaneous
Base - Aluminium
Base - Black
Band- Yellow
Base - Black
Band - Red
Base - Black
309
537
Page 9 of 55
MECHANICAL
Belt Conveyor
Sl.No.
QTY.
2.
3.
4.
5.
6.
DESCRIPTION
Pulleys
-Driving Pulley
-Non-Driving
Driving Pulley
Idlers
Input shaft assembly (only pinion & input shaft)
1st Reduction Gear
Oil seal
Coupling
7.
Hold back
8.
Safety devices
- Pull chord switches
- Belt sway switches
- Zero speed switches
5% of total quantity
5% of total quantity
5% of total quantity
1.
2.0
3.0
DESCRIPTION
Plummer box
Self aligning ball bearing
Gaskets
Limit Switch
Sealing
Oil Seal
QTY.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
Technical Specification:Sec-9,Miscellaneous
QTY.
1 set.
a)1 set. b) 2 sets
c) 1 set d) 1set
1 set.
1 No.
1 set.
1 set.each of
type and size
Page 10 of 55
7.
8.
9.
3.0
SL. DESCRIPTION
QTY.
NO.
1.
Speed Reducers (a)complete gear box assy., (b)oil seal and a)1 set. b) 4 sets
(c) bearing)
c) 2 set of each type and
rating
2.
Motor a) Motor including slip ring motor, b)Bearings c) Oil a)1 set. b) 1 sets
seal
c) 1 set of each type and
rating
3.
Brakes a) Complete assembly b) Linings and springs
1 set. of each type and rating
4.
Couplings with complete assembly, pins, bushes, and nuts
1 set. each type and
rating/sise
5.
a) Thyristor /VVVF cards/ Modules
a) 1 No. of each type. B) 2
b) Relays
No. of each type and rating
6
5.0
Technical Specification:Sec-9,Miscellaneous
Page 11 of 55
SL. NO.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
14
15
16
17
6.0
QTY.
1 No.
1 No.
1 No. of each type and size
1 No. of each type and size & direction.
1 No. of each type and size
1 Set of each type and size
1 Set of each type and size
20% of population
20% of population
20% of population
2 Sets of each type and size
20% of each type and size
10%
1 set of each type and size
1 set
1 No. of each type and size
1 Set of each type and size
Electric Hoist
SL. NO.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
7.0
DESCRIPTION
Head Pulley complete with shaft
Tail pulley complete with shaft
Drive Motor
Gear Box
Complete internals of gear box
including input and output shafts
Reduction gears
Fluid coupling, flexible coupling etc.
Traction rollers
Carrying idlers
Return Rollers
Sprocket segments
Link Chain
Pans (flights)
Hydraulic cylinder
Seal kit of hydraulic cylinders
Plummer blocks
Bearings
DESCRIPTION
Ball bearing
Needle bearing with inner race
Bush bearing
Rope tightener
Rope guide
Rope sheave
Thrust bearing
Roller bearing with inner race
Brake lining
Limit switch complete
Rotor pinion
QTY.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
1 set.
DESCRIPTION
Grooved sheave
Pinion
Bearing
QTY.
2 sets
1 set
1 set
Manual Hoist
SL. NO.
1.
2.
3.
Technical Specification:Sec-9,Miscellaneous
Page 12 of 55
4.
B.
Shaft pin
1 set
ELECTRICAL
Sl. No.
MCC
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
DESCRIPTION
QUANTITY
14.
Sl. No.
1.
DESCRIPTION
Lightning arrester
2.
3.
Relays
QUANTITY
1 set each at receiving and WT
substation
1 set each at receiving and WT
substation
1No. of each at receiving and WT
substation
1.
2.
3.
4.
5.
6.
7.
33 KV SYSTEMS
MOTORS
Technical Specification:Sec-9,Miscellaneous
Page 13 of 55
PDB/LDB/SLDB/AUX. PDB
1.
2.
3.
4.
5.
1.
2.
3.
4.
1 set
1 set
1 no.
1 no. of each type/ ratio
1.
2.
3.
Thyristor fuse
Electronic logic card for UPS
Electronic logic card for PLC
LT TRANSFORMER
UPS/PLC
Ammeter
Indicator Lamp Assembly
Control switch
Push button
1.
2.
3.
4.
Lamps
Fittings
Control gear complete
Timer
ILLUMINATION
C.
Technical Specification:Sec-9,Miscellaneous
QUANTITY
1 set of each type
1 set of each type
1 set of each type
20% of requirement
1 set of each type
Page 14 of 55
Coupling
1 set of each type
Bearings
1 set of each type
2 sets of each type
Gland Packing
Nozzles
Nozzles
10% of requirement
Valves
Valves
1 set of each type
Exhaust Fans
Bearings
1 set of each type
Dry Fog & Plain Water Sprinkling type Dust Suppression Systems
Water Pump
Impeller
1 set of each type
Coupling
1 set of each type
1 set of each type
Bearings
2 sets of each type
Gland Packing
Nozzles
Nozzles
10% of requirement 20%
Nozzle tips
of requirement
Sprinklers
Nozzles
10% of requirement
Solenoid Valves
Solenoid Valves
10% of requirement
Pressure gauges
Pressure Gauges
1 set of each type
Sensors and Instruments
Sensors & Instruments
1 set of each type
Valves
Valves
1 set of each type
Pressure Regulating Units PRU
1 set of each type
(PRU)
Flow Activation Station FAS
1 set of each type
(FAS)
Compressor
Bearings
1 set of each type
Couplings / V Belts
1 set of each type
1 set of each type
Pulleys
1 set of each type
Filters
1 set of each type
Gaskets / O Rings
1 set of each type
Valves /Safety valves
1 set of each type
Piston rings
Technical Specification:Sec-9,Miscellaneous
Page 15 of 55
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
- Yes/ No
Questionnaire
The Bidder shall fill in this questionnaire and submit in hard as well as a soft copy with their
Bid. This data shall form a part of the contract with successful Bidder.
2.1
General
1.
2.
3.
4.
5.
6.
Technical Specification:Sec-9,Miscellaneous
Page 16 of 55
A. WAGON TIPPLER
GENARAL
Type:
Designed capacity
Guaranteed capacity
Make:
Capacity:
Angle of tipping:
Drive:
Tippler drive:
Side arm charger:
Indexer:
Clamping:
Wt. of the machine
Tippling time cycle:
Rail Gauge:
Drive Rack Assembly
Spherical roller bearing SKF NO.24168
ECACK30/W33/Equivalent.
CLAMP CYLINDER
Bore
Rod
Stroke
Tippler Ballast-25T
25T at each end frame Made
from concrete with steel scrap
DRIVE PINION
P.C.D
Face width
No.of teeth
Pressure angle
Material
CYLINDER FOR INHAUL CLICKING STOP
Bore
Rod
Stroke
Technical Specification:Sec-9,Miscellaneous
Page 17 of 55
APRON FEEDER:
GENERAL
Make:
Capacity:
Pan width:
Length:
Motor
DRIBBLE CONV.
GENERAL
Conv.Belt
Belt width
Belt length
Technical Specification:Sec-9,Miscellaneous
Page 18 of 55
C.
WEIGHBRIDGE
GENERAL
Make
Quantity required
Carrying capacity /strength
Weighing capacity
Type
Platform size
Mounting
Resolution
Taring facility
Auto tare
Purpose
Cycle of weighment
Duty
Power supply required
Operating temp.range
Platform size
Material of construction
Load cell
Load cell capacity
D.
Technical Specification:Sec-9,Miscellaneous
Specification
Page 19 of 55
Excitation voltage
Safe overload
Ultimate overload
Insulation resistance
Protection
Cable
E.
F.
CONTROLLER
GENERAL
CHARACTERISTIC
Model no.
Type
Power supply
Operating temperature
Range
Resolution
Non - linearity
Repeatability
Excitaton to transducer
Display
Input
Output
Programmable parameters
Casing dimension
SPECIFICATION
Technical Specification:Sec-9,Miscellaneous
Page 20 of 55
No.of teeth
Pressure angle
Material
RACK FOR SAC TRAVEL
Total nos
Pitch
Pressure angle
Teeth per rack
Material
HYD.POWER PACK DETAILS FOR SAC
TYPE
Oil pump proportional control of capacity
Tank capacity
Electric motor for SAC
Cooling
HYD.MOTOR DETAILS FOR SAC
Hyd.motor double displacement type
Motor model:
Displacement:
Details of Motor
Pressure (Max)
Torque theoritical
Power
Speed (Max)
SAC RAISE & LOWER CYLINDER
Bore
Rod
Stroke
SAC UNCOUPLING CYLINDER
Bore
Rod
Stroke
SAC DELATCH CYLINDER
Bore
Rod
Stroke
G.
INDEXER
Type of side arm charger (sac)
Max.rake (Train) size that Indexer can handle
Type of luffing system for Indexer
Track gauge
Technical Specification:Sec-9,Miscellaneous
Page 21 of 55
Technical Specification:Sec-9,Miscellaneous
Page 22 of 55
Bore
Rod
Stroke
2.2
BELT CONVEYORS
Sl. No
1
2
3
4
5
6
7
10
11
Description
Belt Conveyor System
Conveyor capacity, Mt/h
a) Rated (guaranteed)
b) Design
Belt width, mm
Belt speed, m/sec
Length, centre to centre, m
Lift, m
Max. angle of inclination, degree
Radius of curvature for :
a) Concave
b) Convex
Details of take-up
i) Type of take-up
a) For Boom conveyor of stacker / reclaimer
b) For Intermediate Conveyor of stacker
c) For all other conveyors
Belting
i) Type of fabric
ii) Cover grade
iii) Cover thickness, mm
- Face cover, mm
- Back cover, mm
iv) No. of plies
v) Troughing angle
vi) Factor of safety
vii) Normal working tension
viii) Type of belt joint
i) Idler type:
a) Carrying (except in case of reversible conveyor)
b) Return
c) At loading point
ii) Idler Spacing
a) Carrying
b) Return
c) At loading point
d) Self aligning (carrying side)
e) Self aligning (return side)
Pulleys :
i) Minimum shell thickness
ii) End disc thickness
Technical Specification:Sec-9,Miscellaneous
Page 23 of 55
12
13
14
15
16
17
18
19
20
21
22
23
Technical Specification:Sec-9,Miscellaneous
Page 24 of 55
a) Type
b) Rating
c) Protection
Flexible couplings
a) Type
b) Rating
Drive motors
a) Type
b) Make
c) Insulation class
d) Motor nameplate rating, kW at 500 C ambient
e) Protection Class
24
25
2.3
2.4
Description
Chutes & hoppers construction
Minimum valley angle (from the horizontal), degree
Material & Plate thickness
a) Sliding zones and adjacent sides
b) Non striking/ non sliding zones
c) Chute with valley angle 80 and above
d) In the zone of magnetic field of ILMS
e) In the zone of flap gates
f) Discharge Hoods over head pulleys
g) Location of Inspection door/sealing
Skirt board
a) Plate thickness, mm
b) Length of each skirt board, m
c) Height, mm
d) Width, mm
e) Top cover plate thickness , mm
Description
Make
Dimensions
Material of construction of the gate
Liner plate specification
Method of fixing of liner plates
Type and make of drive and rating
Capacity and designation of the equipment
Total weight and weight of individual parts
Type of actuator and thrust in kg of each actuator
Stroke in mm of each actuator
Velocity mm per of each actuator
Motor: Type, rating, power supply, class of duty, insulation, make
number of starts/ hours
Technical Specification:Sec-9,Miscellaneous
Page 25 of 55
13.
14
15.
2.5
ELECTRIC HOISTS
Sl. No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
Description
Location
Capacity
Duty classification as per IS:3938-1983
IS:3938
Total weight of hoist including electrical equipment
Make of hoist block
Speeds with safe working load
Lifting height
a) Above floor level
b) Below floor level
Wire ropes
a) Type of construction
b) Size
c) Number of falls
d) Factor of safety
Rope drum
a) Materials
b) Diameter
Drives
a) Type & material of gear box
b) Gear & pinion
c) Material & hardness
Motors
a) Type & number
b) Kw rating
c) Synchronous speed
d) Class of insulation
e) Pull out torque
f) Frame size
Brakes
a) Type
b) size
c) Torque rating
Type & details of limit switches
Type of couplings
Type of bearings
Lifting hook
a) Type
b) Material
Type & details of control
Trolley Speed with safe working load
Wheels
Technical Specification:Sec-9,Miscellaneous
Page 26 of 55
20.
21
22.
23.
24.
25.
26.
27.
28.
29.
30.
2.6
a) Numbers
b) Diameter
c) Material & hardness
d) Max. wheel load
e) Wheel base
Drive
a) Type & material of gear box
b) Gears & pinions
c) Material & hardness
d) Kw rating
e) Synchronous speed
f) Class of insulation
g) Pull out torque
h) Frame size
Brakes
a) Type
b) Size
c) Torque rating
Type & details of limit switches
Type of coupling
Type of bearings
Type & details of controls
Clearance diagram indicating the basic dimensions
Type & lubrication provided
Type & size of cables
Location & control details of hoist block power feeding
Any other information
EOT CRANE
Sl. No.
Description
(a)
1.0
2.0
3.0
4.0
(b)
1.0
Technical Specification:Sec-9,Miscellaneous
Page 27 of 55
(c)
1.0
2.0
3.0
4.0
5.0
6.0
2.7
MANUAL HOISTS
Sl. No
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
11.
12.
13.
3.0
Description
Name of the manufacturer, type & model no
Numbers offered & their location
Safe working load for each hoist (in tones)
Duty class as per IS:3832-1983
IS:3832
Head room, mm
Lift, mm
Minimum radius of curvature of which this hoist can negotiate (mm)
Weight of each hoist
Specification of each chain
Tools & tackles included in offer
Commissioning spares & 2 years
Operating spares included in offer
Any other information
Technical Specification:Sec-9,Miscellaneous
Page 28 of 55
5) General Arrangement of Major Equipment showing plan, elevation, cross sections along with
mounting details, with broad dimensions
d
and technical parameters.
6) Basic calculation substantiating selection of all major equipment, motors, gear boxes,
couplings, brakes etc.
7) Equipment wise List of commissioning spares and consumables with item wise description and
quantity included
d in the main offer.
8) Equipment wise list of 2 years operational spares (un-priced).
(un priced). The list shall indicate description
and quantity for each item.
9) List of special tools and tackles
10) Details /drawings for Civil & Structural Engineering works.
11) Single line diagram of power distribution system.
12) Electrical schematic diagrams
13) Cable specifications, cables schedule and cable layout drawings.
14) Any other structural / mechanical / electrical etc. drawings / data mentioned elsewhere in
the technical specification as well as considered necessary by the Purchaser/ Consultants.
15) List of exclusion, if any from Bidders Scope of Work.
16) List of deviations from technical specification.
4.0
4.1
ELECTRICS
DRAWINGS/DOCUMENT TO BE SUBMITTED BY THE TENDERER
Drawings / Data / Documents along with the Bid
1.
Detailed scope of work with general description of the system & equipment offered
specifying the important features and detailed design criteria and design philosophy
including full details of reference data, assumptions, etc.
2.
3.
4.
5.
Technical Specification:Sec-9,Miscellaneous
Page 29 of 55
6.
Equipment wise List of commissioning spares and consumables with item wise
description and quantity included in the main offer.
7.
8.
9.
Work Schedule with bar chart indicating all activities for electrics.
4.2
1.
2.
3.
Connected load and Maximum demand of each section of 33 kV switchboard/ 415 V PCC
4.
5.
Technical Specification:Sec-9,Miscellaneous
:
:
Page 30 of 55
: List to be submitted
: List to be submitted
: List to be submitted
MOTOR
1. Make, type & applicable standard
2. Furnish following for all drives
Sl. No
Application
Working
/Standby
Rated Parameters
kW
Voltage
MCC
1. Make, Type & Applicable Standard
2. Rated Voltage, current & Frequency
3. Short time rating
4. Bus bar material & type of sleeving
5. Protection class
Components of MCC
1 Air Circuit Breaker
2. MCCB
3. AC Contactor
4. DC Contractor
5. Thermal Relay
6. Control Devices
7. Meters
Technical Specification:Sec-9,Miscellaneous
Speed
Enclosure
Qty
:
:
:
:
:
Make & Type
:
:
:
:
:
:
:
Page 31 of 55
Rating of Single
Volt,
Front/
Amps
Double
Front
RELAYS
1.
2.
3.
4.
Make
Type
Draw out type with built in test facility
Relay details
1.
2.
3.
4.
Make
Type
Reference standard
Size
METERS
CURRENT TRANSFORMER
1.
Make, type & applicable standard
2.
Ratio & accuracy class: metering/protection
3.
Rated voltage short time rating
POTENTIAL TRANSFORMER
1.
2.
3.
4.
5.
Type
Primary/secondary voltage ratio
Method of connection
Rated voltage factor
Class of insulation
Technical Specification:Sec-9,Miscellaneous
Page 32 of 55
Components of DB
1.
2.
3.
4.
5.
6.
Breaker
MCCB/MCB
AC Contactor
Thermal Relay
Control Devices
Meters
DB-WISE DATA
Sl.
No
DB
Designation
Rating
of
Volt,
Amps
Single
No.of
Front / bus
Double sections
Front
Connected Max.
load
per load
per
section
section
No. of Overall
panels dimensions
Make
Output range
Accuracy
Maximum burden on CT/PT
Nominal input/rated I/V
Overload capacity without loss in accuracy
LIGHTNING PROTECTION
1.
2.
3.
4.
5.
6.
: Places to be indicated
:
: Yes/No
:
:
:
EARTHING
1.
2.
3.
Technical Specification:Sec-9,Miscellaneous
:
:
:
Page 33 of 55
4.
5.
6.
:
:
: Included
UPS SYSTEM
1. Make of the system
2. Capacity in kVA
3. Battery back up time
4. Make & type of battery
5. Number of cells per battery
6. Overall dimension(L x B x H) mm of battery
7. Ventilation requirements
8. Make, Rating & type of charger
9. Make, Rating & type of rectifier transformer
10. Make & current rating of SCR & Diode
11. Make & rating of inverter
12. Make & type of static transfer switch
13. Make & rating of manual bypass switch
TRANSFORMER
1. Name of manufacturer
2. Service-whether
whether indoor or outdoor
3. Type of cooling
4. Rating
a. Rated KVA
b. Rated current, amp (rms), HV/LV
c. Rated voltage, kV (HV/LV)
5. Temperature rise above 500C ambient
a. In oil by thermometer, 0C
b. In winding by resistance, 0C
c. Hot spot temperature in winding limited to, 0C
6. Insulation class
7. Vector group
8. Type of tap changer with capacity/steps/range
9. Tapping provided on HV side?
10. Losses
load loss at rated voltage and frequency
a. No-load
b. Load loss at rated load
c. Cooler loss
11. Impedance at rated current frequency
12. Reactance at rated current and frequency, %
13. Efficiency at 0.80 p.f lag % at 100%/75%/50% load
14. Load/p.f. at which max. efficiency occurs, % full load
Technical Specification:Sec-9,Miscellaneous
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
: Yes/No
:
:
:
:
:
:
:
Page 34 of 55
Technical Specification:Sec-9,Miscellaneous
:
:
:
Page 35 of 55
LIGHTING MAST
General
1. Make
2. Material of construction
3. Cross section of mast in polygon (No. of sides)
4. Thickness in mm (bottom/middle/top sections)
5. Length of individual sections (mm)
6. Base dia & top diameter (OAF)
7. Type of joints
8. Length of overlap (joint at site mast Section in mm):
9. Thickness of galvanization (minimum)
10. Size of opening door at base (mm)
11. Type of locking arrangement & door construction:
12. Weights in kgs of 30 mtrs high mast
13. Dynamic loading as prevailing actual at site
14. Maximum wind pressure (Basic wind speed)
15. Maximum gust speed
ed time
16. Factor of safety for wind load
17. Factor of safety for other loads
:
:
:
:
:
:
Lantern Carriage
1. Diameter of carriage ring (mm)
2. Load carrying capacity
3. Total weights of assembly with fittings
4. Number of fittings
:
:
:
:
Winch
1. Make of winch, number of drums per winch
2. Capacity
3. Operating speed
4. Method of operation
5. Tested load per drum (kg)
Wire Rope
1. Grade
2. Number of ropes/thickness
3. Construction
4. Breaking load capacity
5. Factor safety
Cable
1. Type
2. Make
3. Current carrying capacity
4. Cable size
Technical Specification:Sec-9,Miscellaneous
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
Page 36 of 55
5.0
5.2
Bidders shall furnish all information as stipulated in relevant chapter. Bidders shall
also furnish the following information:
a)
Process flow, process instrumentation and control diagram and water and
compressed air balance diagrams.
b)
c)
d)
All relevant basic design calculations supporting the selection of equipment, location
of valves, specials and supports along with forces and moments of fixed support.
5.3
Ventilation Systems
a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
Technical Specification:Sec-9,Miscellaneous
Page 37 of 55
5.4
Centrifugal Fan
a) Make & Model No
b) Quantity, no.
c) Type of blade
d) Capacity, m3/h
e) Total pressure, mm WC
f) Speed, rpm
g) Shaft power, KW
h) Total Efficiency, %
i) Motor rating, KW/ pole
j) Fan Characteristic Curve
k) Impeller Diameter, mm
l) Velocity at inlet & outlet of fan, m/sec m
m) Weight of fan and motor, kg
n) Coupling details
o) Vibration isolator type & quantity
p) Thickness of scroll, blade, Back plate, shaft mm
q) Noise level at 1m distance
r) Overall size
s) Drive Motor rating suggested
5.5
5.6
Exhaust fan
a) Make & Model
b) Capacity in m3/h.
c) Total Pressure, mm WC
d) Material of construction and its thickness
e) Speed in rpm.
f) Drive details.
g) Shaft Power consumption.
h) Wheel diameter
i) Efficiency
j) Static & Dynamic weight of fan & motor assembly
Technical Specification:Sec-9,Miscellaneous
Page 38 of 55
5.8
5.9
Technical Specification:Sec-9,Miscellaneous
Page 39 of 55
j) Shaft power
k) Drive details
a. Motor make
b. Motor KW
c. Insulation class
d. Frame size
l) Bearing type & make
m) Type of coupling
n) Vibration level
o) Noise level at 1 m distance from pump set
5.10 Dry Fog & Plain Water Sprinkling type Dust Suppression Systems
a) Technical details and quantity of main equipment including Nozzles, PRU, FAS and
Instrumentation for Auto Operation.
b) Technical details and quantity
quantity of auxiliary equipment including air compressors, pumps,
etc.
c) Technical details of circular swiveling sprinklers
d) Compressed air & water requirement, capacity of compressor, air receiver, capacity of
water pump unit etc.
e) Total power consumption. Capacity of each motor for pump and compressor.
f) Details of air & water pipelines with sizes and quantities.
g) Details of valves and fittings
h) Details of solenoid valves, sensors, pressure gauges and other instruments.
i) Details of tanks
j) Details of hood / skirt boards modification
k) Size of compressor cum pump house.
l) Size of only pump house (In case compressed air is not provided)
5.11 Split Air Conditioner
a) Make & Model
b) Quantity
c) Capacity in TR (Nominal / Actual
d) Air Flow m3/h
e) Flow direction and volume control grill
f)
Material of construction
g) Compressor type
h) Drive details and total power consumption
i)
Overall dimensions
j)
Refrigerant type
k) Filter efficiency
Technical Specification:Sec-9,Miscellaneous
Page 40 of 55
l)
m)
n)
o)
p)
Weight of unit
Noise level at 1m distance in dB(A)
Fixing details.
Vibration level.
Accessories included
6.0
b)
c)
Block Scheme diagram for all fire protection system along with tentative BOQ for major
equipments.
d)
e)
f)
g)
h)
i)
j)
k)
Technical Specification:Sec-9,Miscellaneous
Page 41 of 55
Format - 1
1.0
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14
15.
16.
17.
18.
19.
20.
21.
COMPANY SEAL
Technical Specification:Sec-9,Miscellaneous
Page 42 of 55
Format - 2
2.0
Purchaser
Location
& Customers
PO No. and
Date
4
Period
& Details
Year
of of work
Completion
5
6
7
Capacity
of plant
8
Total cost of
work done by
bidder
9
NOTE: Bidder may also furnish the above details for ongoing assignments.
SIGNATURE ___________________
DESIGNATION ___________________
COMPANY ____________________
DATE ____________________
COMPANY SEAL
Technical Specification:Sec-9,Miscellaneous
Page 43 of 55
Format - 3
8.0
Drawings
2
Title
3
SIGNATURE ___________________
DESIGNATION ___________________
COMPANY ____________________
DATE ____________________
COMPANY SEAL
Technical Specification:Sec-9,Miscellaneous
Page 44 of 55
SCHEDULE OF COMPONENTS IN USE AT NALCOS EXISTING COAL HANDLING PLANT, CPP, ANGUL
Components schedule given below are for information to Bidders for standardization and
interchangeability with existing Coal Handling Plant only. Bidders must take a note of
o these
components details while selecting a new supply to control the inventory level.
A)
Pulley
Diameter
(mm)
Drive/
630
Discharge 630
Pulley
630
800
Non Drive 400
Pulleys
400
500
B)
C)
Face
width
(mm)
1150
1150
1150
1150
1150
1150
1150
Shaft
Diameter
(mm)
125
150
165
175
90
100
115
Bearing
Diameter
(mm)
115
140
150
160
75
90
100
Shaft
length
(mm)
1690
2095
2100
2120
1760
1760
1770
PlummerBlockCenter
(mm)
1550
1650
1650
1650
1650
1650
1650
Bearing size
65
75
90
100
115
125
140
150
160
22215K
22217K
22220K
22222K
22226K
22228K
22232K
22234K
22236K
Technical Specification:Sec-9,Miscellaneous
Reduction Ratio
16 : 1
16 : 1
16 : 1
20 : 1
20 : 1
16 : 1
125:1
Page 45 of 55
D)
Baffle Ratio
1.5B
1.5B
1.5B
1.5B
Idler Schedule
The idlers are drop in slot type.
Technical Specification:Sec-9,Miscellaneous
Page 46 of 55
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21
22
EQUIPMENT
GEAR BOXES
CONVEYOR BELTS
MAKE
ELECON, FLENDER, SHANTHI, SEW, NAW, GRAEVES
DUNLOP, NIRLON, MRF, PHOENIX, NORTHLAND, FORECH, ANIL
RUBBERS, ORIENTAL.
IDLER
ELECON, TRF, KALI, KRUPP, MACMET, HINDUSTAN UDYOG
PULLEY
ELECON, TRF, KALI, HEC, HINDUSTAN UDYOG, McNALLY
BHARAT, HITECH, MASYC, KRUPP, SIMPLICITY, ARUDRA,
MACMET.
BEARINGS
SKF, FAG, NTN, NBC, NORMA, TATA, EAST EUROPIAN,
EUROPIAN ZKL
SLEW RING BEARINGS ROTHE ERDE, TITANUS, LYC-CHINA
FLEXIBLE COUPLING
FMG, DAVID BROWN, HICLIFF, CONCORD, ROMA, WELLMAN
INCAD. GREAVES LTD., NAW, GBM, ALLFLEX
FLUID COUPLING
PEMBRIL, FLUDOMAT, VOITH, ELECON
FASTENERS
GKW, SUNDERAM, PRECISION FASTENERS
MANUAL HOISTS
WH BRADY, KANUBHAI, HERCULES, TRACTEL TIRFOR, REVA
ENGG. MM ENGRS, BRADY&MORRIS
OIL SEALS
VACCA, RUBBER EQPT. & ENGG. CO. L TD
LUBRICATION
TECALEMIT, SURMAC, LUBCON, PRAKASH, AFMC, HELIOS
PROTOS, LINCOLN HELIOS
POWER PACK
REXROTH, PARKER, ETON, YUKEN, VICKERS, HAGGLUNDS
HYDRAULICS
REXROTH, YUKEN, CARTER, VELJAN CYLINDERS UTL,
MONTECH, WIPRO, OSCAR, HAGGLUNDS, PARKERCALZONI
HOSES
AEROLEX, GATES INDIA PVT. LTD
a) BELT CLEANERS
a) HOSCH, KAVERI,TECHNOFAB, PROMAC, BMH CONCARE
b) SKIRTS AND SKIRT b) UNITED TECHNO MECH, TEGA, KAVERI, HOSCH
SEALING
ARRANGEMENT
ACTUATOR OPERATED UNITED TECHNOMECH, PREPEC, PEBCO
FLAP GATES
IN LINE MAGNETIC ELECTRO-ZAVOD,
ZAVOD, MBIL, ELECTROMAG, POWER BUILD, MCI,
SEPARATORS
ELECTROMAGNETIC INDUSTRIES
BELT WEIGH SCALES
SCHENK-JENSON,
JENSON, TRANSWEIGH, IPA, SARTORIUS
BELT SWITCHES
JAYSHREE, SCHNEIDER, TELEMECHANIC, INDUSTRY SYNDICATE,
PROTO CONTROL
BRAKES
BCH, INDUSTRIES SYNDICATE, STORM KRAFT, ELECTROMAG,
SPEED O CONTROL, STROMAG
ELEC. HOISTS
ARMSEL, SHIVPRA, WH BRADY, BRADY & MORRIS, GRIP
ENGRS., HI-TECH,
TECH, CENTURY CRANE, TUOBRO FURGUSON,
UNITECH
Technical Specification:Sec-9,Miscellaneous
Page 47 of 55
In case the Tenderer/ Contractor intends to substitute any particular make of equipment /
components/
ents/ materials by their/ his own make other than that listed in this document, the
Tenderer shall clearly bring out the same in his tender along with justification and indicate the
makes offered by him. It will be prerogative of the Purchaser to accept or reject the tenderers
own makes so offered.
1.2.
ELECTRICAL
Sl.No
1.
ITEM
415 V MCC/ (Drawout type)
2.
3.
HT Cables
4.
LV Motors
5.
6.
Bimetal Relays
7.
Contactors
Control
Switches
Switches/Selector
Technical Specification:Sec-9,Miscellaneous
Page 48 of 55
9.
Fuse Switch
10
Timers
11
Fuse
12
ELCBs
13.
MCBs
14
MCCBs
15
Meters
16
Technical Specification:Sec-9,Miscellaneous
Page 49 of 55
17
18
Lighting Fixtures
19
Terminal Blocks
20
21
Transducer
22
LT Transformer
23
PLC
24
UPS
25
Control Desk
27
VVVF Drive
29.
33 K V Isolator
30
Trailing Cables
Technical Specification:Sec-9,Miscellaneous
Page 50 of 55
3. UNIVERSAL
31
HT Switch gear
32
HT Transformer
33
33KV VCB
34
Protection relays
35
36
LV CT/PT
37
HVCT/PT
38.
39.
Lightning Arrests
1.WSI
2.ELPRO.
40.
41.
42.
43.
44.
Cable accessories
ACSR/AAAC Conductor
415V PCC
45.
1.DRIESCHER PANNIKER
1.BAJAJ
2.PHILIPS
1.DOWELLS
1.RELIANCE CONDUCTORS
1. L&T
2.SIEMENS
1.RAYCHEM RPG
46.
Technical Specification:Sec-9,Miscellaneous
1. BHEL
2 Siemens
3. ABB
1. BHEL
2
Siemens
3
TELK
4
ABB
5
AREVEA
1. ALSTOM
2.ABB
3.SIEMENS
1.ABB
2.ALSTOM
3EASUN REY ROLLE LTD
4L&T (FOR NUMERICAL RELAYES ONLY) .
5SIEMENS (FOR NUMERICAL RELAYES ONLY) .
1.ALSTOM
RELIABLE ELECTRONIC COMPONENT PVT.LTD.
2.RELIABLE
3.SWITORN DEVICES
1.COTROL AND SWITCH CO.LTD.
2.GEILBERT & MAXWELL ELECTRICAL
3.KAPPA ELECTRICALS
4.L&T
5.NARYAN POWER TRON PVT.LTD.
6.SILKAANS ELECTRICAL
7.PRECISE ELECTRICAL
8.PROGATI ELECTRICAL PVT.LTD.
1.AE
2.BHEL
3.CGL
4.SILKAANS
5.JYOTI
6.KAPPA
7.ABB
8.PROGATI.
1.APLAB
2.MINILEC
3.IL
1.CCI
2.UNIVERSAL
3.POLYCAB
4.NICCO
Page 51 of 55
1.3.
1.3
47.
Signal
cable
and
48.
VRLA battery
49.
Battery charger
Instrumentation
5.KEI
6.CORDS
7.GEMSCAB
1.CCI
2.UNIVERSAL
3.POLYCAB
4.NICCO
5.KEI
6.CORDS
7.GEMSCAB
1.AMAR RAJA
2.EXIDE
1. AMAR RAJA
2.CHABI ELECTRICAL
3.CALDYNE
4.HBL NIFE
Technical Specification:Sec-9,Miscellaneous
Page 52 of 55
1.0
3.
4.
5.
6.
7.
8.
9.
10.
11
12.
13.
14
15.
DESCRIPTION
QUANTITY
Manually operated Hydraulic Jack
2 Nos
i) 50T X 150 mm stroke
Bastard (Rough Cut) Files 250 mm size
i)
Flat
1 No.
ii)
Round
1 No.
1 No.
iii)
Half Round
1 No
iv)
Triangular
Fine Cut Files 250 mm size
i)
Flat
1 No.
ii)
Round
1 No.
iii)
Half Round
1 No.
iv)
Triangular
1 No
Adjustable Outside Micrometer Interchangeable Anvil
Type
i)
0-150 mm
1 No.
ii)
150 600 mm
1 No
Inside Micrometer
i) 50 150 mm
1 No
Vemier Calipers
i)
0-150 mm size
1 No.
ii)
0 300 mm size
1 No
Feeler Gauge
i)
10 mm thk. 6 inch
1 No.
ii)
10 mm thk. 12 inch
1 No
Sprit Level
i) 150 mm
2 No
Torque Wrench with socket
75 150 kg.m
1 set
Standard Ring spanners
(Upto 32 mm )
1 set
Standard D.E. spanners
(Upto 32 mm )
1 set
Adjustable spanners
(Upto 50 mm each set of 3 Nos.)
1 set
Socket Head Spanners
(Box Spanners 10 to 32 mm )
2 set
Sledge Hammers
i)
5 kg.
2 Nos.
ii)
10 kg
2 Nos
Nylon Faced Hammers (4 Sizes)
1 set
Technical Specification:Sec-9,Miscellaneous
Page 53 of 55
16.
17
18.
19.
20
21.
22.
23
24
25.
26.
27
28.
29
30.
31
32
33
34.
35.
36.
37
38
39
Technical Specification:Sec-9,Miscellaneous
2 Nos
6 Nos
2 Nos
1 No.
1 No
1 No.
1 No
1 No.
1 No
1 No.
1 No
1 Set
2 Nos
2 Nos
2 Nos
1 No
2 Nos
2 Sets
4 Nos
2 Nos
2 Nos.
2 Nos
2 Sets
2 Nos
2 Nos.
2 Nos.
2 Nos
2 Nos
2 Sets
4 Nos
1 No.
1 No
Page 54 of 55
40.
41.
42.
43.
44.
45
46
47
48.
49
50
51
52
53.
2.0
Tong Tester
Portable Emergency Light (Hand Torch with Dry Cells)
100 W Hand Lamp with 50 M Flexible Wire
Hand drills (pistol)
Digital Multimeter
Digital Clamp meter
Hand drill Electrical & 1
Crimping Tool ( Hand Operated) - 5 mm2 to 16 mm2
Crimping Tool ( Hand Operated) -16 mm2 to 240 mm2
Milli Ohm Meter
Combination Plier
Nose Plier
Earth Megger
Phase Sequence meter (0 415V)
2 Nos
2 Nos
2 Nos
2 Nos
1 No
1 No
2 Sets
1 Set
1 Set
1 No
2 Nos
2 Nos
1 No
1 No.
DESCRIPTION
DRAWING NO
Layout of Coal Storage Yard & 1034/Q6Q3/A-02A/LO
02A/LO-001 Rev 05
Handling System
FD-CHP
6-08-0-07734-01
02728-M-BM-CS-GA--0027 Rev C
CKIH-3901-M0-B057
B057 Rev D
CKIH-3901-M0-B004
B004 Rev C
conveyor
Technical Specification:Sec-9,Miscellaneous
Page 55 of 55
Annexure - II
Special Instructions to Bidders
1.0
COMPLETION SCHEDULE
The schedule for completion in all respect as per Tender Documents from Brief Order (BO) date is
specified in Instruction to Bidders.
2.0
DUE DATE
Please ensure your offer, complete in all respects reaches us by the bid due date specified in
Instructions to Bidders. Offers received after the bid due date and time will be considered as Late
Offers and will not be considered.
3.0
PRICE FORMAT
Please furnish the prices strictly as per the format enclosed. Prices shall not appear any where
else in the offer, and if prices are mentioned any where else the same shall not be considered.
Prices should be submitted in duplicate sealed super scribed envelope along with un-priced copies
as per Tender documents (Un-priced copy of price bid should also be enclosed with un-priced
copies with prices blanked out but Quoted/ Not Quoted marked against respective clauses).
4.0
VALIDITY OF BIDS
The bid should be kept valid for acceptance for a period of 4 (four) months from the final due date
for bid submission.
5.0
5.1
All evaluation shall be made on landed and erected on destination basis including design and
engineering, supply of equipment, spares etc. (excluding One Year O&M Spares) and all other
erection, construction, installation, supervision and commissioning charges along with the taxes
and duties for the same, as per scope of Tender Documents.
5.2
:
:
:
:
:
:
:
:
:
:
As quoted
As Quoted
As Quoted
1+2+3
0.25% on (4)
As quoted
4+5+6
@ 2% on (7)
7+8
On FOT Despatch point price
Page 1 of 9
11.
12.
13.
5.3
Price loading on account of payments and other conditions required by various vendors will be
based on following:(i)
Payment terms:
a)
(ii)
Firm Price
No loading
(b)
In case of ceiling on
Price Variation Clause
(c)
(d)
No formula and no
ceiling specified by vendor
- do -
(iii)
Vendors should quote firm inland freight charges from dispatch point to Site at Angul,
Orissa. If a vendor does not quote firm inland freight charges then their offer will be loaded
with maximum of the inland freight charges as quoted by the other bidders from that region
or based on estimation by NALCO in case there is no other offer from that region.
(v)
Any differential in taxes and duties will be cost loaded on case-to-case basis. If a vendor
states that taxes/duties are not applicable at present and will be charged as applicable at
the time of delivery then no advantage will be given.
(vi)
(vii)
Cost loading in respect of utilities will be considered where guaranteed consumptions have
been asked in NIT as per methodology defined in the NIT.
5.4
5.5
No deviation to terms & conditions of the bid documents is allowed. Further Non acceptance of
following commercial clauses shall lead to rejection of bid:
Page 2 of 9
(i)
Bids that do not meet the qualification criteria as specified in the NIT/ bid documents shall
be summarily rejected.
(ii)
A bid with incomplete scope of work and / or which does not meet the technical
specifications and requirements as specified in the NIT documents shall be considered as
non-responsive and rejected.
(iii)
Prices must be furnished in accordance to the price schedule format enclosed and strictly
based on the terms specified related to the bid prices in the instructions / conditions. Non
compliance to this requirement shall make the bid liable for rejection.
(iv)
Bidders are requested to note that exceptions / modifications taken by them to the
following clauses of Tender Documents - Commercial may result in rejection of their bid :(a)
(b)
(c)
(d)
(e)
(f)
6.0
Proforma of Bank Guarantee for Advance Payment, if any, and Contract - cum Performance Bank Guarantee
Contract Performance Guarantee clause
Completion Schedule
Period of validity of bid
Guarantee / Warranty
Replacement of Defective parts and materials
REFERENCE LIST
The bidders are requested to submit a list of buyers to whom the same or similar type of equipment
have been supplied by them and which are under operation. The detailed addresses of such
buyers office/works including Telephone, Fax Nos. and Contact Person and Order Reference are
to be mentioned.
Page 3 of 9
APPENDIX - A
TO
SPECIAL INSTRUCTIONS TO BIDDERS
INDEX
SL. NO.
DESCRIPTION
1.0
COST OF BIDDING
2.0
SITE VISIT
3.0
BIDDING DOCUMENT
4.0
5.0
6.0
7.0
LANGUAGE OF BID
8.0
9.0
10.0
11.0
12.0
COMPARISON OF BIDS
13.0
14.0
AWARD CRITERIA
15.0
17.0
ISSUE OF ORDER
Page 4 of 9
1.0
COST OF BIDDING
1.1
All direct and indirect costs associated with preparation and submission of bid (including clarification
meetings and site visit, if any) shall be to bidders account and NALCO / RITES, will in no case, be
responsible or liable for these costs, regardless of the conduct or outcome of the bidding process.
2.0
SITE VISIT
2.1
Bidder is advised to visit and examine the Site, its surrounding and familiarize himself of the
existing facilities and environment and collect all other information which he may require for
preparing and submitting the bid and entering in to the contract. Claims and objections due to
ignorance of existing conditions or inadequacy of information will no be considered after
submission of the bid and during implementation.
2.2
The bidder or any of his personnel or agents will be granted permission by the Owner to enter upon
his premises and land for the purpose of such inspection but only upon the explicit condition that
the bidder, his personnel or agents will release and indemnify the owner and his personnel or
agents from and against all liability in respect thereof and will be responsible for personnel injury
(whether fatal or otherwise), loss of or damage to property and any other loss, damage, cost and
expenses incurred as a result thereof.
2.3
For site visit, the intending bidder may contact General Manager (CPP), NALCO, Angul, Orissa
Phone- 06764- 220 158, Telefax 06764- 220 646 or General Manager (Projects), RITES Ltd,
Bhubaneswar, Phone: 0674 2572690, 09438677075. Fax 0674 2575 284. or Sr.
DGM(Civil)/RITES, Bhubaneswar, phone-09437283829.
3.0
BIDDING DOCUMENT
3.1
The Bidder is expected to examine all instructions, forms, terms and specifications in the
Bidding Document. The Bidding Document together with all its attachments thereto, shall be
considered to be read, understood and accepted by the Bidder, unless deviations are specifically
stated in seriatim (giving reference s. no. of Bidding Document) by the Bidder. Failure to furnish all
information required by the Bidding Document or submission of a bid not substantially responsive to
the Bidding Document in every respect will be at Bidders risk and may result in the rejection of his
bid.
3.2
The Bidders must fulfill the Qualification Criteria given in the Instructions to Bidders and furnish all
necessary documentary evidence in support of Bidders experience/ capability as required, along
with the bid. In the absence of the requisite documents, NALCO / RITES reserves the right to reject
the bid without making any reference to the Bidder. Bidders must make their own judgment on
the adequacy of the documents/ information they provide. In case any information provided by
Bidder is found to be incorrect, the bid will be rejected, and the Earnest Money Deposit of
such Bidder will be liable for encashment.
Bidder must buy Bidding Document by paying the requisite document fee before the sale
closing date & time. In case the Bidding Document is downloaded from website t h e requisite
Bidding Document Fee in the form of DD payable to NALCO shall accompany the bids.
3.3
Page 5 of 9
4.0
4.1
Bidder shall examine the bidding document thoroughly in all respect and if any conflict, discrepancy,
error or omission is observed, bidder may request clarification within the cutoff date and 3 weeks
prior to the bid closing date. Such clarifications request shall be addressed to the following:
GM (Projects), RITES Ltd.,Regional Project Office, Bhagwan Tower(1st Floor), Cuttack Road,
Bhubaneswar -751006, Phone:-0674-2575493, Fax:0674-2575284, E-mail : bbsrpo@rites.com
4.2
Any failure by bidder to comply with the aforesaid requirement shall not excuse the bidder, after
subsequent award of contract, from performing the work in accordance with the contract.
4.3
Response to queries/ clarifications raised will be sent as expeditiously as possible. The response
shall not form part of the bidding document unless issued as an addendum/ amendment.
4.4
Bidders are expected to resolve all their clarification/ queries to the bidding document and submit
their bid in total compliance to biding document without any deviation/ stipulation/ clarification.
4.5
PRE-BID MEETING
The Tenderer or his official representative is invited to attend a pre-bid meeting which will take place at
the Office of General Manager(Project), CPP, Nalco,Angul on 10.09.2012 at 10.30 hours.
The Tenderers are required to submit any question on issues relating to the tender, in writing or by
telefax or by E-mail so as to reach general Manager(Project), RITES Ltd.,Regional Project Office,
Bhagwan Tower(1st Floor), Cuttack Road,Bhubaneswar -751006 not later than 3 (three) days before
the date fixed for the meeting.
The purpose of the meeting will be to clarify the issues raised and to answer supplementary questions
on such issues.
Minutes of the meeting including the text of the questions raised (without identifying the source of
enquiry) and the responses given will be uploaded on RITES website. Any modifications of the
Tender Document which may become necessary as a result of the Pre-bid Meeting shall be made
exclusively through the issue of an Addendum / Corrigendum and not through the Minutes of the PreBid Meeting. The Minutes of the Meeting as described above and the Addendum / Corrigendum, if
any, will be uploaded on RITES website only.
Non-attendance at the Pre-bid Meeting will not be a cause for disqualification of a tenderer.
5.0
5.1
At any time prior to the bid due date, NALCO / RITES may, for any reason, whether at its own
initiative or in response to a clarification requested by a prospective Bidder, modify the Bidding
Document and issue amendment in the form of Addendum.
Page 6 of 9
5.2
Any addendum thus issued will become part of bidding document and bidder shall submit original
addendum/ compliance letter duly signed and stamped in token of his acceptance.
5.3
In order to afford prospective Bidders, reasonable time in which to take the amendment into account
in preparing their bids, NALCO /RITES may, at its discretion, extend the bid due date.
6.0
6.1
Bidders shall treat the biding documents and contents therein as strictly confidential.
6.2
The bidding document is and shall remain the exclusive property of the OWNER without any
right to bidder to use them for any purpose except for the purpose of bidding.
7.0
LANGUAGE OF BID
7.1
The bid prepared by the Bidder and all correspondence/ drawings and documents relating to
the bid exchanged by Bidder and NALCO /RITES shall be written in ENGLISH language. Any
printed literature furnished by the Bidder written in another language should be accompanied
by an ENGLISH translation. In case of any conflict, for the purpose of interpretation of the bid, the
ENGLISH translation shall govern.
8.0
8.1
The Bidder shall prepare required number of copies of the bid, clearly marking each Original
Bid and Copy of Bid as appropriate. In the event of any discrepancy between them, the Original
Bid shall govern.
8.2
The original and all copies of the bid shall be typed or written in indelible ink and shall be signed
by the Bidder or a person duly authorized to bind the Bidder to the Contract. The name and
position held by each person signing must be typed or printed below the signature. The person
or persons signing the bid shall initial all pages of the bid, except for unamended printed
literature.
8.3
The complete bid shall be without alterations, interlineations or erasures, except as may be
necessary to correct errors made by the Bidder, in which case such corrections shall be rewritten &
initialed by the person or persons signing the bid.
9.0
9.1
The Bidder may modify or withdraw his bid after the bids submission, provided that the
modification/ withdrawal notice is received by the Owners/ Consultant prior to the bid due date &
time.
The Bidders modification or withdrawal notice shall be prepared, sealed, marked and despatched
in accordance with the provisions of Bidding Document. A withdrawal notice may also be sent
Page 7 of 9
by Cable or Telefax but must be followed by a signed confirmation copy dated not later than
the deadline for submission of bids.
9.2
No bid shall be modified subsequent to the due date & time or extension, if any, for submission
of bids.
9.3
No bid shall be allowed to be withdrawn in the interval between the deadline for submission of
bids and the expiration of the period of bid validity specified by the Bidder. Withdrawal of a bid
during this interval shall result in the forfeiture of Bidders Earnest Money Deposit .
10.0
10.1
Un-priced part of the Bid shall be opened in the RITES, Bhubaneswar Office, in the presence
of Bidders representatives (duly authorized by a competent person and having the Letter of
Authority who choose to attend, on date, time as mentioned in the Instructions to Bidders. The
Bidders representatives, who are present, shall sign a register evidencing their attendance.
Bidders whose bids are not opened for any reason, including non-receipt of original Earnest
Money Deposit, will not be allowed to be present during bid opening.
10.2
The Bidder(s) names, modifications, bid withdrawals and the presence or absence of the
requisite Earnest Money Deposit and such other details as the NALCO/RITES, at its discretion,
may consider appropriate will be announced and recorded at the time of opening of un-priced
bids as specified in the Instruction to Bidders/ Tender Documents.
11.0
11.1
12.0
COMPARISON OF BIDS
12.1
The Consultant will evaluate and compare bids previously determined to be substantially responsive
pursuant to the provisions of the Bidding Document.
12.2
Arithmetical errors will be rectified on the following basis:If there is a discrepancy between the unit price and the total price that is obtained by
multiplying the unit price and quantity, the unit price shall prevail and the total price will be
corrected. If there is a discrepancy between the total amount and the sum of total prices, the sum
of the total prices shall prevail and the total bid amount will be corrected. Further, if there is a
Page 8 of 9
discrepancy between the quoted lump sum price, and its separate break-up prices (if any), the
quoted lump sum price shall prevail.
13.0
13.1
No Bidder shall contact the NALCO / R I T E S on any matter relating to its bid, from the time
of bid opening to the time the Contract is awarded.
13.2
Any efforts by a Bidder to influence the NALCO / RITES in the Owners/ Consultants bid
evaluation, bid comparison or contract award decisions may result in the rejection of the Bidders
bid.
14.0
AWARD CRITERIA
The Owner will award the Contract to the successful Bidder whose bid has been determined to
be the lowest evaluated, responsive bid, provided further that the Bidder is determined to be
qualified to satisfactorily perform the Contract.
15.0
15.1
NALCO / RITESO reserves the right to accept or reject any bid, and to annul the bidding process
and reject all bids, at any time prior to award of contract, without thereby incurring any liability to
the affected Bidder or Bidders or; any obligations to inform the affected Bidder or Bidders of the
ground for the Owners/Consultants action.
15.2
The submission of any bid connected with these documents and specifications shall
constitute an agreement that the Bidder shall have no cause for action or claim, against the
Owner for rejection of his bid. The Owner shall always be at liberty to reject or accept any bid or
bids at his sole discretion and any such action will not be called into question and the Bidder shall
have no claim in that regard against the Owner.
ISSUE OF ORDER
The Owner will send to the successful bidder B rief Order/ Work Order incorporating all
the terms and conditions agreed between the parties.
Within 15 days of receipt of the Order, the Bidder shall sign and return it to the Owner for their
records.
16.0
16.1
16.2
17.0 In case of contradiction between relevant Indian Standards, General Conditions of Contract,
Special Conditions of Contract, Specifications, Drawings, Schedule of Prices / Rates, the following
shall prevail in order of precedence:
i) Brief of Order, Detailed Letter of Acceptance along with Statement of Agreed Variations (if any) and
its enclosures.
ii)
Schedule of Rates.
iii)
Technical Specifications
iv)
Drawings.
v)
Addendum to Tender Documents (Commercial).
vi)
Tender Document Commercial(Indigenous).
vii) Relevant Indian Standards / Specifications
Annexure II, Special Instructions to Bidders
Page 9 of 9
TENDER DOCUMENTS
COMMERCIAL (INDIGENOUS)
Page 1 of 56
CONTENTS
GENERAL CONDITIONS OF CONTRACT
Sl. No.
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
33.00
Page No.
APPLICATION
DEFINITION OF TERMS
CONTRACTOR TO INFORM HIMSELF FULLY
SCOPE OF WORK
DESIGN REQUIREMENTS
CONTRACT PRICE
TAXES
PERFORMANCE BOND
PROTECTIVE PAINTING, PACKING & MARKING
SHIPMENT PARTICULARS
INSURANCE
DELIVERY
LIQUIDATED DAMAGES FOR DELAY IN COMPLETION
IMPORT LICENSE AND FOREIGN EXCHANGE
CONTRACTORS DOCUMENTS, DRAWINGS AND
INSTRUCTION MANUALS
MISTAKES IN DRAWINGS
MATERIALS AND WORKMANSHIP
SPARE PARTS AND SPECIAL MAINTENANCE TOOLS
COMPLETENESS OF EQUIPMENT
INSPECTION AND TESTING AT CONTRACTORS PREMISES
TESTS ON COMPLETION AND TRIAL RUN AT SITE
TAKING OVER
REJECTION OF DEFECTIVE PLANT
COMPLETION CERTIFICATE & FINAL CERTIFICATE
ENGINEERS DECISION
CERTIFICATE NOT TO AFFECT THE RIGHTS OF THE
PURCHASER OR THE CONTRACTOR
MINTENANCE AND GUARANTEE - WARRANTY PERIOD
NEGLIGENCE
POWER TO VARY OR OMIT WORK
SETTLEMENT OF DISPUTE
TERMINATION OF CONTRACT
DEDUCTION FROM CONTRACT PRICE
CO-OPERATION WITH OTHER CONTRACTORS AND
CONSULTING ENGINEERS
04
04
06
07
08
10
10
11
12
14
14
15
15
15
15
18
18
19
19
19
21
22
22
23
25
26
27
27
28
28
29
29
30
Page 2 of 56
30
Page No.
31
31
31
32
32
32
33
33
33
35
50
50
51
51
51
51
52
53
53
55
Page 3 of 56
1.00
APPLICATION
Unless otherwise provided in the Contract Agreement, these General Conditions of Contract shall
govern the work of the annexed Specification.
2.00
DEFINITION OF TERMS
In construing these General Conditions and the annexed Specification, the following words shall
have the meanings herein assigned to them unless there is something in the subject or context in
consistent with such construction.
2.01
The Owner/Purchaser shall mean the National Aluminium Company Limited , a company
incorporated in India, whose Registered Office is situated at NALCO BHAVAN, P/1, Nayapalli,
Bhubaneswar - 751 061.
2.02
The Contractor shall mean person, firm or a company whose tender has been accepted by the
Purchaser and shall include his/its heirs, executors, administrators, representatives and permitted
assigns.
2.03
The term Sub-Contractor used herein refers to a party or parties having a direct contract with the
Contractor to whom any part of the contract has been sublet by the Contractor with the consent in
writing of the Owner and shall include his heirs, executors, administrators, representatives and
assigns.
2.04
The Engineer shall mean an officer of the owner/purchaser as may be duly appointed and
authorized in writing by the purchaser to act as the Engineer on its behalf for the purpose of the
contract.
2.05
The `Engineers Representative shall be the person nominated by the Engineer in writing to act on
his behalf.
2.06
2.07
The Inspector shall mean any firm or person including any employee of the owner/purchaser as
may be duly appointed and authorized in writing by the owner/purchaser to inspect plant,
equipment and works included by the Contractor.
2.08
`Plant, Equipment, Works shall mean and include plant, stores and materials to be provided and
work to be done by the Contractor.
2.09
Contract means the Notice Inviting Tenders, Conditions of Tendering, and Tender Form, General
Conditions of Contract, Supplementary Conditions of Contract, Technical Specifications, price
Page 4 of 56
Schedule of Prices & Quantities, Letter of Intent of Purchaser, Drawings, Subsequent amendments
mutually agreed upon, and agreement to be entered under clause Contract Agreement of this
General Condition.
2.10
The `Specification shall mean the Specification annexed to these General Conditions and any
subsequent modifications thereof and the drawings and Schedules attached thereto (if any).
2.11
`Site means the lands and other places on, under, in or through which the Works are to be
executed or carried out and any other lands or places provided by the Owner for the purpose of the
Contract.
2.12
`Tests on Completion shall mean such tests as are prescribed by the Specification and/or tests
mutually agreed upon by the Purchaser and the Contractor to be made by the Contractor after
erection of the equipment to prove satisfactory operation as required by the Specification.
2.13
`Commissioning shall mean the first successful operation of the plant and equipment after all initial
adjustments, trials, cleaning and reassembly required at site, if any, have been completed.
2.14
`Acceptance Tests shall mean such tests as are required to prove the performance guarantees of
the plant given by the Contractor, before taking over of the plant by the Purchaser.
2.15
Initial Operation, `Reliability Run or Trial Operation shall mean continuous operation of the
contract plant and materials under varying loads to furnish proof of satisfactory operation for a
specified period which shall not be less than two (2) weeks.
2.16
Commercial Use shall mean that use of the equipment which the Contract contemplates or of
which it is to be commercially capable.
2.17
Warranty Period shall mean the period of guarantee as explained under clause `Maintenance and
Guarantee of these General Conditions.
2.18
Codes shall mean the applicable codes of State or Orissa as on the date of Letter of Intent and
any subsequent modification thereof before the plant has been delivered.
2.19
2.20
Notice of Award of Contract / Letter of Intent/ Award Letter shall mean the Purchasers letter /
Telex conveying his acceptance of the Tender subject to such reservations as may have been
stated therein.
2.21
Erection Supervision shall mean the supervision services rendered or exercised by the Contractor
during the erection of the plant as explained under clause `Erection Supervision Services of these
General Conditions.
Page 5 of 56
2.22
`Writing shall include any manuscript, typewritten or printed statement under or over signature or
seal as the case may be.
2.23
2.24
Words importing `Persons shall include firms, companies, corporations and other bodies whether
incorporated or not.
2.25
Words importing the singular only shall also include the plural and vice versa where the context
requires.
2.26
F.O.B. shall mean delivery free of expenses to the Purchaser on board the vessel at the port of
shipment.
2.27
F.O.R. Destination shall mean delivery free of expenses to the purchaser on rail wagons at
destination Railway Station/Siding as may be named.
2.28
F.O.R. Works shall mean loaded and stowed or trimmed, free of expenses to the Purchaser on
board rail wagons at the Contractors siding or at the nearest Railway Station for transportation.
2.29
Tonne shall mean 1000 kilogram weight, `Gallons shall mean imperial gallons unless mentioned
specifically.
2.30
`Manufacturers works or `Contractors works shall mean the place of work used by the
manufacturer, their collaborators or approved sub-contractors for the performance of the works.
2.31
Construction of Contract
Terms and conditions not herein defined shall have the same meanings as are assigned to them in
the Indian Sale of Goods Act (Act III of 1930) falling that in the Indian Contract Act (Act IX of 1872)
and falling that in the General Clause Act 1897.
3.00
Page 6 of 56
specifically mentioned in the specification or drawings, but otherwise necessary for ensuring
complete erection and safe and efficient commercial working of the plant and equipment. If he shall
have any doubt as to the meaning of any portion of these General Conditions and/or specification,
he shall set forth the particulars thereof and submit them to the Engineer in writing for clarification.
4.0
SCOPE OF WORK
4.01
Page 7 of 56
4.02
4.03
5.00
DESIGN REQUIREMENTS
5.01
All equipment and materials shall be designed and manufactured in conformance with standards
stated hereinafter.
5.02
Wind Load
Structures and outdoor equipment shall be designed to withstand a wind load as set forth in the
latest revision of Indian Standards IS: 875 of the Indian Standards Institution.
5.03
Earthquake
In general IS: 1893 shall be followed. Specific conditions/technical specification shall be referred
for specific design criteria.
5.04
Safety Features
The Contractor shall provide adequate guards for all couplings and other moving parts which could
be considered a hazard. Safety, sentinel and relief valves are to be located or piped in such a
manner as to safeguard personnel and property. All safety devices shall be in accordance with the
applicable Government regulations and requirements.
5.05
Page 8 of 56
In drawings or specifications wherever both Metric and British units are indicated, the Contractor
shall indicate the equipment dimensions on both the units. Location marking of all equipment shall
be in Metric Units.
5.06
Accessibility
Special attention shall be given to the design, arrangement and assembly of all equipments to
ensure ease of maintenance and renewal of parts.
5.07
5.08
Equipment, material and erection and other services shall be completed in all respects and
in strict accordance with the specifications, except that alternative proposals may be
submitted where stipulated provisions depart from the Contractors Standards, provided
that the substitutions are approved as equivalent by the Engineer and the reasons
therefore are stated by the Contractor in his proposal as a result of such substitution.
b)
Any request for substitution after the contract is awarded, shall be accompanied with the
difference in price and such substitution can only be made on approval by the Engineer on
behalf of the Purchaser in writing, provided that such substitution does not cause any
addition to the contract price.
a)
All work shall be done in accordance with the applicable portions of the current editions of
the codes and standards of the respective U.S.A., U.K. National and Technical Societies or
equal or with the standards and codes of the Government of India, and in accordance with
the applicable portions of the following codes and standards in particular:
Indian Boiler Regulations
Indian Electricity Act
Indian Electricity Rules
Indian Factories Act
Indian Explosives Act
Indian Standard Institution (IS)
British Standard Institution (BS)
American Society of Mechanical Engineers (ASME)
Institute of Electrical & Electronics Engineers Inc. (IEEE)
Page 9 of 56
Where conflicts occur between any of the laws, rules, regulations, standards, and so forth,
specified herein, the more stringent requirements shall govern the work.
CONTRACT PRICE
The lump sum prices quoted by the Contractor in his bid with additions and deletions as may be
agreed before signing of the Contract, for the entire scope of the work viz. supply and erection of
equipments covered under the specification and documents shall be treated as the Contract Price.
7.0
TAXES
7.01
The Contractor shall include all taxes, duties, royalty of whatever nature, octroi, other local taxes,
etc., if any, in the quoted price.
7.02
Sales tax or any other tax on material required for the work as also tax on works contract shall be
payable by the Contractor and Owner will not entertain any claim whatsoever.
7.03
Notwithstanding anything contain elsewhere in the contract the Owner shall deduct at source from
the payment due to the contractor the taxes as required under 13(A) of Orisaa Sales Tax Act or
amended from time to time or under any other statute. The amount so deducted shall be paid by
the Owner to the Sales Tax authority as per law. This is for the Contractor to deal with the Sales
Tax authority directly in respect of any claim or refund relating to the above tax and Owner shall not
be liable or responsible for any type of payment or reimbursement in this regard.
Page 10 of 56
7.04
All benefits of taxes duties by way of credit under CENVAT shall be passed on to the
Owner/Purchaser
8.0
9.00
Page 11 of 56
Dimensions of each package shall not exceed the maximum dimensions of packages which can be
accepted for transport over the `broad gauge system of the Railway concerned.
10.0
SHIPMENT PARTICULARS
10.01 Shipments
a)
Foreign Items
Responsibility of shipment of plant and equipment shall lie with the Contractor wherever
the contract is for complete supply and installation or supply delivered at site basis. The
Contractor shall notify the Purchaser of the date of each shipment from the port of
embarkation as well as date of arrival of such shipment at designated port of arrival for
information.
Responsibility of cleaning the same in the port including all handling shall lie with the
Contractor. Purchaser will only arrange to pay the customs duty as per information on CIF
values given by the Contractor sufficiently in advance.
The Contractor shall give complete shipping information concerning the weight, size,
content of each package including any other information the Purchaser may require.
b)
Indigenous Item
For all contracts for supply and installation or supply delivery at site basis, responsibility of
all transportation from works to site shall lie with the Contractor.
The Contractor shall notify the Owner of the date of each shipment from his works and the
expected date of arrival at the site for information of the Purchaser.
The Contractor shall also give all information concerning the weight, size and content of
each packing including any other information the Purchaser may require.
c)
The Contractor shall further be responsible for all inland transportation up to site for foreign
items after clearing through the port. Contractor shall also be responsible for making all
necessary arrangements for loading, unloading and other handling right from his works till
the site and also till the equipment is erected, tested and commissioned. He shall be solely
responsible for proper storage and safe custody of all equipment.
Page 12 of 56
a)
Foreign Items
Within seven (7) days of shipment following shall be airmailed to the Purchaser for
purpose of progress payment and necessary arrangement of payment of customs duty.
- Application of payment in standard format of the Owner (3 copies)
- Bill of Lading (5 non-negotiable copies)
- Invoice including break-up for customs purposes (6 copies)
- Packing list (6 copies)
- Pre-dispatch clearance certificate or shipping release, if any (3 copies)
- Test certificates, wherever applicable (3 copies)
- Certificate of origin
b)
Indigenous items
- Application for payment in standard format of Purchaser (3 copies)
- Invoice (6 copies)
- Packing list (6 copies)
- Pre-dispatch clearance certificate or shipping Release, if any (3 copies)
- Test Certificates wherever applicable (3 copies)
Page 13 of 56
11.0
INSURANCE
11.01 The Owner will arrange for INSURANCE of equipment and material, included under the scope of
contract, to cover a)
Risk in transit by ship/air between Contractors port of shipment/air port and Indian port of
entry.
b)
c)
Risks during storage and erection at the Project Site till the plant is fully commissioned
under an open general insurance policy. The Owner shall intimate the name of Insurance
Company and other details in due course.
11.02 The Contractor shall furnish dispatch particulars of each consignment including its value
immediately to the Insurance Company. If for any delay in intimating of dispatch particulars to the
Insurance Company on the part of the Contractor the claims for damages are rejected, the
contractor shall be fully responsible for replacement of the damaged equipment.
11.03 The risks that are to be covered under the insurance shall include, but not limited to, the loss or
damage in transit, theft, pilferage, riot, civil commotion, weather conditions, accidents of all kinds,
fire, war risk, etc. The scope of such insurance shall cover the entire value of the Works from time
to time.
11.04 In respect of equipment damaged in transit or during erection and commissioning, the Contractor
shall replace them expeditiously and the replacement cost payable by the Owner shall be limited to
the invoice of damaged equipment. In case of consignment received at the project site in outwardly
sound condition of package but found shortage/damage on being opened the liability for free
replacement will be accepted by the Contractor.
It is the responsibility of the Contractor to lodge a claim on the Insurance Co. on behalf of the
Owner. On receipt of all relevant document relating to the claim, Owner will pursue the matter with
the Insurance Co.
12.00 DELIVERY
Notification of delivery or dispatch in regard to each and every consignment shall be made to the
Purchaser immediately after dispatch or delivery. The Contractor shall further supply to the
Consignee a price invoice and packing account of all stores delivered or dispatched by him. All
packages, containers, bundles and loose materials forming part of each and every consignment
shall be described fully in the packing account, and full details of the contents of packages and
quantity of materials shall be given to enable the Consignee to check the stores on arrival at
destination.
Page 14 of 56
Six (6) marked up copies of technical particulars to make them conforming to accepted
proposals.
b)
Outline drawings of all equipment together with weights and sufficient overall dimensions
to enable the Purchaser to design foundations and structures and associated equipment.
Page 15 of 56
c)
Drawing submission schedule indicating list of all drawings with their respective titles and
dates shall be submitted to the Purchaser. The schedule shall also indicate the latest date
by which Contractor shall furnish all design calculations. The schedule shall be amended
or extended by the Contractor in consultation with the Purchaser as and when necessary.
15.03 Within a stipulated time period the Contractor shall submit for approval of the Purchaser the
following drawings and technical data:
a)
Dimensional layout drawings of the plant and equipment to be supplied under the contract
and all certified data relating to the design on foundation structures to enable the
Purchaser to arrange for construction of the necessary foundations and civil works.
All information regarding material and size of anchor bolt, nuts, sleeves, inserts and
supports which shall have to be embedded in concrete shall be furnished in the detailed
foundation drawing.
b)
Dimensional drawings showing individual equipment being supplied under the contract,
method and sizes of connections to the Purchasers other equipment, giving also the limits
of variations of the dimensions.
c)
d)
Schematic drawings of all wirings, connections and interlocking diagrams showing the
points where the connections have to be made by the Purchaser.
e)
Necessary structural and other calculations and data required for demonstrating fully that
all parts of the equipment to be furnished shall conform to the provisions and intent of the
contract.
The Contractor shall submit six (6) prints of each drawing for approval. Two (2) prints shall be
forwarded to the Purchaser and four (4) prints shall be forwarded to the Consulting Engineer.
When prints of drawings have been marked Approved except as noted, Resubmission required
the Contractor shall make necessary corrections and again submit corrected copies for approval as
per details stipulated. Further revision will be shown by number, date and subject in a revision
block.
Upon receipt of the prints which have been marked Approved or Approved except as noted:
Forward Final drawing the Contractor shall furnish within a reasonable time fourteen (14)
additional prints of each of drawings and one (1) reproducible transparency after minor corrections,
if any, to the Purchaser.
Relevant civil construction drawings if felt necessary by Consulting Engineer, shall be forwarded to
the Contractor in triplicate. He shall review incorporation of information furnished by him, such as,
Page 16 of 56
anchor bolt location, elevation etc. and return one certified copy each to the Purchaser and to the
Consulting Engineer.
Any manufacturing work in connection with the equipment prior to the approval of drawings shall be
at the Contractors risk. The Contractor shall make any change in the designs, with prior approval
of the Engineer, which are necessary to make the equipment conform to the provisions and intent
of the contract, without additional cost to the Purchaser. Approval of Contractors drawings shall
not be held to relieve the Contractor of any part of Contractors obligations to meet all the
requirements of the contract or of the responsibility for the correctness of the Contractors
drawings.
15.04 The details to be furnished shall include, but not restricted to the following:
a)
Finals plans and layout giving complete details against the above mentioned arrangement
plans including foundations plans.
b)
c)
Complete cabling drawing giving details of cables required, terminal details, layout of
trenches etc.
Detailed wiring diagrams and arrangements of conduits for wiring various controls and
instruments up to the required points.
d)
e)
f)
A complete list of special erection tools and tackles required for complete assembly.
15.05 Complete spare part hand books with details and diagrams, separate recommendations shall be
made for the parts required for first one year of operation of important equipment and sent to
Engineer for approval. Parts requiring frequent replacement shall be listed separately from parts
required for ensuring reliability in unforeseen emergencies. On finalization ten (10) set of such
spare part hand books shall be furnished to the Engineer.
15.06 Assembly and erection instruction within a reasonable time after signing of the contract but at least
three (3) months before starting erection the Contractor shall furnish ten (10) sets of the following
for the use of Purchasers field Engineers:
a)
Descriptive literature and drawings to illustrate the working principles, method of assembly
and dismantling.
b)
Instruction book for proper erection and assembly of all equipment and necessary
instructions for checking and recording proper assembly of the plant.
Page 17 of 56
Erection schedule giving the sequence of erection with reference to package/ assembly/
sub-assembly identification.
c)
Instruction sheets for proper balancing, alignment, adjustment, checking and calibrations
as may be necessary.
15.07 All drawings and technical data are to be furnished in English language only.
15.08 Final Drawings and Operation Maintenance Manuals
Before completion of the work, the Contractor shall furnish fourteen (14) complete sets of prints
and one (1) reproducible transparency of all detailed drawings of the equipment actually supplied
and as erected and assembled at site. In addition ten (10) sets of comprehensive manuals for use
in the operation and maintenance of the plant shall be supplied at least six (6) months before the
actual commissioning date to the Engineer.
15.09 Seven (7) copies of monthly fabrication progress report for all equipment and material shall be
supplied to the Engineer.
16.00 MISTAKES IN DRAWINGS
The Contractor shall be responsible for and shall pay for any alterations of the work due to any
discrepancies, errors or omissions in the drawings or other particulars supplied by him whether
such drawings or particulars have been approved by the Engineer or not.
If any dimensions figured upon a drawing or a plan differ from those obtained by scaling the
drawing or plan the dimensions as figured upon the drawing or plan shall be taken as correct.
17.00 MATERIALS AND WORKMANSHIP
All materials used in the manufacture of the equipment shall be selected from the best available for
the purpose, considering strength, durability and best engineering practice. Liberal factors of safety
shall be used through out the design and specially in the design of all parts subject to alternating
stresses or shocks.
All the work shall be performed and completed in a thorough workmanship like manner and shall
follow the best modern practice in the manufacture of high grade equipment notwithstanding any
omissions in the specifications.
Castings shall be free from holes, flaws, cracks or other defects and shall be smooth, close grained
and of true forms and dimensions. No plugged or filled up holes or other defects will ordinarily be
allowed. Such castings are liable to be rejected.
However, the Contractor may rectify minor casting defects by welding or other method in
accordance with the standard manufacturing practice provided such rectification does not affect the
Page 18 of 56
strength of the casting or impair the efficient working of the plant and prior approval of the
Purchaser is obtained for the same.
18.00 SPARE PARTS AND SPECIAL MAINTENANCE TOOLS
18.01 The spare parts as required for the equipment under supply are listed in respective specification.
The list is not exhaustive but only indicative.
The Contractor shall also supply list of Guaranteed Spares for two years normal operation
indicating parts name, catalogue no., quantity and unit prices on project site delivery basis. If any
short fall is noticed during 2 years from the date of commissioning the same shall be supplied free
of cost by the Contractor.
18.02 In case of machinery and plant, the Contractor shall include provision for such tools as he
recommends to be absolutely essential for proper maintenance and repair of the plant. A detailed
list of the tools along with the itemized prices shall be submitted along with the tender. In the
absence of this list, the tender is liable to be rejected. One new set of all special tools for
maintenance for each type of equipment shall be furnished by the Contractor at his own expense
and shall be dispatched along with the equipment.
18.03 The contractor shall also undertake that supplies of necessary maintenance equipment and spare
parts will be made available for the life of the plant offered through his Agents on a continuous
basis at reasonable price.
19.00 COMPLETENESS OF EQUIPMENT
The equipment shall be complete in every respect with all mountings, fixtures and standard
accessories which are normally supplied even though not specifically detailed in the specification.
The Contractor shall not be eligible for any extra payment in respect of such mountings, fittings,
fixtures and accessories which are needed for safe operation of the equipment as required by
applicable codes of the country though they may not have been included in the contract.
All similar component parts of similar equipment supplied shall be interchangeable with one
another.
The various equipment supplied under this contract shall be subject to the Purchasers approval
20.00 INSPECTION AND TESTING AT CONTRACTORS PREMISES
The Engineer and his duly authorized representative shall have at all reasonable times access to
the Contractors /Sub-contractors premises of works, and shall have the power at all reasonable
times to inspect drawings of any portion of the work or examine the materials and workmanship of
the plant during its manufacture there and if part of the plant is being manufactured on other
Page 19 of 56
premises, the Contractor shall obtain for the Engineer and his duly authorized representative
permission to inspect as if the plant is manufactured on the Contractors premises.
The Engineer shall on giving seven (7) days notice in writing to the Contractor setting out any
grounds of objections which he may have in respect of the work, be at liberty to reject any drawings
& all or any part of workmanship if the subject of any of the said grounds of objection, which in his
opinion are not in accordance with the contract. The Contractor shall give due consideration to
such objections and shall either make the modifications that may be necessary to meet the said
objections or shall confirm in writing to the Engineer giving therein that no modifications are
necessary to comply with the contract.
The Contractor shall give the Engineer and his duly authorized representatives notice of any
material being ready for testing and the Engineer or the said representative shall (unless the
inspection of tests is voluntarily waived), on giving twenty four (24) hours previous notice in writing
to the Contractor, attend at the Contractors premises (as the case may be) within fifteen (15) days
of the date on which the material is notified as being ready failing which visit, the Contractor may
proceed with the tests which shall be deemed to have been made in the Engineers presence. All
standard shop tests, physical and chemical tests required by the Standards or as may be
prescribed or approved by the Engineer shall be conducted by the Contractor. The Engineer
reserves the right to waive any of the above test requirement and to prescribe new test required if
found necessary to expedite the work or to conform to the latest and best practice. Definitions,
methods of measurement, calibration of instruments and required procedure as referred in the
above standard and/or those approved by the Engineer as equivalent shall be followed. The
Contractor shall forthwith forward to the Engineer duly certified copies of the test certificates in
quadruplicate (one copy to the Purchaser and three copies to the consulting Engineer) for
approval. Further ten (10) copies of the shop test certificate shall be bound with the instruction
manuals referred to in clause Contractors documents, drawings and instruction manuals.
In all cases where contract provides for tests, whether at the premises or works of the Contractor
or any sub-contractor, the Contractor, except where otherwise specified shall provide free of
charge to the Purchaser, such labor, materials, electricity, fuel, water, stores, apparatus and
instruments as may reasonably be demanded to carry out efficiently such tests of the plant, in
accordance with the contract and shall give facilities to the Engineer or his authorized
representative to accomplish such testing.
When the tests have been satisfactorily completed in the Contractor/Sub-contractors Works, the
Engineer shall issue a certificate to that effect within fifteen (15) days after completion of test, but if
the tests were not witnessed by the Engineer or his representative the certificate would be issued
within fifteen (15) days of the receipt of the test certificates by the Engineer. No plant shall be
transported before such a certificate has been issued. The satisfactory completion of these tests or
the issue of this certificate shall not bind the Purchaser to accept the plant should it on further tests
after erection, be found not to comply with the contract provisions.
Page 20 of 56
(II)
Placing in operation
(II)
Initial operation
(IV)
Reliability tests
(V)
(VI)
Load tests
The sequence of tests for individual equipment shall be as mutually agreed to between the
Contractor and the Engineer.
Duration of the trial operation of the complete equipment shall be 30 continuous days with available
wagon rakes during this period as mutually agreed and decided. The acceptance test shall be
carried out within two (2) months after the trial run has been satisfactorily completed. Any delay for
carrying out these works for force majeure reasons shall be given due consideration. Should the
result of these tests not come within the margin specified, the test shall, if required, be repeated
after necessary rectification measures recommended by the Contractor within one (1) month from
the date of plant is ready for retest, and the Contractor shall repay to the Purchaser all reasonable
expenses which he may be put to by such tests.
The performance and acceptance tests of the complete installation shall be carried out to prove the
guarantees specified for different equipment. These tests shall be made in accordance with
established and approved procedures. The Contractor shall submit within reasonable time after the
award of contract, detailed procedure for conductance of all tests for approval of the Engineer. The
procedure shall include the following information for such test:
Page 21 of 56
(I)
(II)
(II)
Instrument locations shown by a schematic diagram for each test. (Calibration certificates
for each instrument shall be furnished before commencement of test).
(IV)
All formulas, calculations, conversion factors, correction curves, etc. to be used for test
conductance.
(V)
Sample test report forms, and data sheet that will be used to record test results and
valuation of final results.
On completion of all tests, the overall efficiency of the plant shall be determined in accordance with
the procedure mutually agreed upon between the Contractor and the Engineer unless otherwise
covered under the Standards and Specification.
In all cases, where the contract provides for test at the site, the Purchaser, except where otherwise
specified, shall provide, free of charge, such labor, materials, fuel, water, electricity, lubricants as
may be required from time to time and as may reasonably be demanded to carry out such tests of
the plant, material or workmanship in accordance with the contract. Any special apparatus and
precision instruments required for site test shall be provided by the Contractor.
If for any reason, other than the fault of the contractor performance and acceptance tests for any
unit shall not be carried out within sixty (60) days of notice by the Contractor to the Purchaser of
the unit being ready for tests, then the Purchaser will issue an acceptance certificate on the last
day of such period and payments due to the Contractor on acceptance shall be made, but
nevertheless the Contractor, shall if called upon to do so by the Purchaser, within a period twelve
(12) months from the said last date, make the said tests on the same terms as provided in the
contract.
22.00 TAKING OVER
Upon successful completion of all the tests to be performed at site on equipment and systems
furnished and erected by the Contractor, the Engineer shall Issue to the Contractor a taking over
certificate as a proof of the final acceptance of the equipment. Such certificate shall not relieve the
Contractor of any of his obligations which otherwise survive by terms and conditions of the contract
after issuance of such certificate.
23.00 REJECTION OF DEFECTIVE PLANT
If the completed plant or any portion thereof, it is taken over under the clause Taking Over, be
found defective or fails to fulfill the requirements of the contract, the Engineer shall give the
Contractor notice selling forth particulars of such defects or failure, and the Contractor shall forth
Page 22 of 56
wile make the defective plant good or to make it comply with the requirements of the contract.
Should he fail to do so within a reasonable time, the Purchaser may reject and, replace at the cost
of the Contractor the whole or any portion of the plant as the case may be, which is defective or
fails to fulfill the requirements of the Contract. Such replacement shall be carried out by the
Purchaser within a reasonable time and at a reasonable price, and where reasonably possible to
the same specification and under comparative condition. The Contractors full and extreme liability
under the clause shall be satisfied by the payment to the purchaser of the original contract price
including charges of erection and/or supervision of erection plus the difference if any between the
replacement price of the equipment including charges for erection and /or supervision of erection
and the original contract price including charges for erection and / or supervision of erection in
respect of such defective plant.
In the event of such rejection, the Purchaser shall have the right to operate any and all equipment
as soon as and as long as it is in operating condition, whether or not, such equipment has been
accepted as complete and satisfactory, to enable him to obtain necessary replacement, except that
this shall not be construed to permit operation of any equipment which may become damaged by
such operation before any required alternations or repairs and/or replacement have been made. All
repairs or alternations or replacement required of the Contractor shall be made by the Contractor at
such times as directed and in such manner as will cause the minimum interruption in the use of the
equipment by the Purchaser. Should the Purchaser not so replace the rejected plant within a
reasonable time, the Contractors full and extreme liability under his clause will be satisfied by the
repayment of all money paid by the Purchaser to him in respect of such plant.
Nothing in this clause shall be deemed to deprive the Purchaser or affect any rights under the
contract which he may otherwise have in respect of such defects or deficiencies or in any way
relieve the Contractor of his obligations under the contract.
24.00 COMPLETION CERTIFICATE & FINAL CERTIFICATE
24.01 Application for Completion Certificate
When the contractor fulfils his obligation under the contract he shall be eligible to apply for
completion certificate in respect of the work by submitting the completion documents along with
such application for completion certificate.
The owner or his representative shall normally issue to the Contractor the completion certificate
within one month after receiving an application from the Contractor after verifying from the
completion documents and satisfying himself that the work has been completed in accordance with
and as set out in the construction and erection drawings, and the contract documents.
The contractor, after obtaining the completion certificate, is eligible to present the final bill for the
work executed by him under the terms of contract.
Page 23 of 56
Three sets of construction drawings showing therein the modification and corrections
made during the course of execution and signed by the Engineer.
(ii)
(iv)
(v)
(vi)
Materials appropriation statement for the materials issued by the owner for the works and
list of surplus materials returned to the owners store duly supported by necessary
documents.
Page 24 of 56
(vi)
(viii)
(ix)
Page 25 of 56
All equipment shall be free from any defect due to faulty design, materials and/or
workmanship.
(b)
The equipment shall operate satisfactorily and the performance and efficiencies of the
equipments shall not be less than the respective guaranteed values.
(c)
The efficiencies, temperature rises and other performance data furnished for the
equipment.
The guarantees have to be furnished on forms approved by the Engineer and shall be signed by
the Contractor and / or his sub-contractor.
If the Contractor finds, after his tender is accepted, that a variation in work, construction technique
or the quality of materials is necessary to fulfill the guarantees called for, such variations may be
made with the approval of the Engineer, provided the request for changes is made before signing
the contract the changes are to be made without any increase in the contract price.
The above guarantees shall be valid for a period of twelve (12) calendar months commencing
immediately on the satisfactory completion of the final tests at site or thirty six (36) months after
the last consignment to complete the plant is received at site,, whichever may be earlier. This
period of the guarantee shall be called the Warranty period. During this period, the contractors
liability shall be limited to the replacement of any defective parts that may develop in plant of his
own manufacture of those of his sub-contractors under the conditions provided for by the contract
under proper use and arising solely from faulty design, materials or workmanship provided always
that such defective parts as are not repairable at site, and are not essential in the meantime in the
commercial use of the plant, are promptly returned to the Contractors Works unless otherwise
arranged. All such replacements of defective parts mentioned above shall be made free of costs at
site by the Contractor and the return of the defective parts to the Contractors works shall be the
Contractors responsibility and shall be made at his expense. The Purchaser will, however, render
such assistance in this matter as well expedite the same. In the case of defective parts not
repairable at site but essential in the meantime for the commercial use of the plant, the Contractor
shall replace at site free of cost to the Purchaser the said defective parts before the defective parts
are removed to his Works.
If for rectification or replacement of any part of equipment or work due to defective materials,
manufacture or design, the services of the Contractor personnel are requisitioned within the
guarantee period, these services shall be made available free of any cost to the Purchaser.
Page 26 of 56
If it becomes necessary for the contractor to replace or renew any defective portions of the plant
under this clause, the provisions of this clause will apply to the portions of the plants so replaced or
renewed until the expiration of six (6) months from the date of such replacement or renewal or until
the end of the above mentioned period of twelve (12) months, whichever may be later. If any defect
be not remedied within a reasonable time, the Purchaser may proceed to do the work at the
Contractors risk and expenses but without prejudice to any other rights which the Purchaser may
have against the Contractor in respect of such defects.
If the replacement or renewals are of such character as may affect the efficiency of the plant, the
Purchaser shall have the right to give the Contractor within one month of such replacement or
renewal, notice in writing that tests on completion be made in which case such tests be carriedout as provided in clause tests a completion and trial run at site hereof. Should such test show
that the plant sustains the guarantee given in the Contract; the cost of the tests will be borne by the
Purchaser. Should the guarantee be not sustained, the cost of the test shall be borne by the
Contractor.
All replacement or renewals to be carried out by contractor during the maintenance period shall be
subject to such clauses of these general conditions as may be considered reasonable by the
Engineer.
Until the final certificate has been issued, the Contractor shall have the right of entry, at his own
risk and expenses by himself or his duly authorized representatives whose names shall previously
have been communicated in writing to the Engineer, at all reasonable working hours upon all
necessary parts of the works, for the purpose of inspecting the working and the records of the plant
and taking notes there from and, if he desires, at his own expense making any tests, subject to the
approval of the Engineer that work will not be unreasonably withheld.
The issue of the Engineers Certificate referred to in clause Certificate of Engineer shall in no way
expect the contractor from the provision of this clause.
At the end of the maintenance period, the liability ceases. In respect of goods not covered by the
first paragraph of this clause, the Purchaser shall be entitled to the benefit of any guarantee given
to the Contractor by the original supplier or manufacturer of such goods.
28.00 NEGLIGENCE
If the Contractor neglects to execute the work with due diligence and expedition or refuses or
neglect to comply with any reasonable orders given to him in writing by the Engineer in connection
with the work, or contravene the provisions of the contract, the Purchaser may give notice in writing
to the Contractor calling upon him to make good the failure, neglect or contravention complained or
should the Contractor fail to comply with such notice within a period considered reasonable by the
Purchaser from the date of service thereof, in the case of failure, neglect or contravention capable
of being made good within that time or otherwise within such time as may in the opinion or the
Purchaser be reasonably necessary for making it good, then and in such case the Purchaser shall
Page 27 of 56
have the option and be at liberty to take the work wholly or in part, out of the Contractors hand and
may carry on the work envisaged in the contract at a price with any other person or persons to
execute the same or any part thereof and provide any other materials, tools, tackle or labor for the
purpose of completing the works or part thereof. In such event the Purchaser shall without being
responsible to the Contractor for fair wear and tear of the same be entitled to seize and take
possession and have free use of all materials, tools, tackle or other things which may be on the
site, for use at any time in connection with the work to the exclusion of any right of the Contractor
over the same and the Purchaser shall be entitled to retain and apply and balance sum which may
otherwise be then due on the contract by him to the Contractor or such part thereof as may be
necessary, to the payment of the cost of execution of such work as aforesaid.
If the cost of executing the work as aforesaid shall exceed the balance due to the Contractor and
the Contractor fails to make good the deficit, the said materials, tools, tackle, construction plant or
other things, the property of the Contractor as may not have been used up in the completion of the
works, may be sold by the Purchaser and the proceeds applied towards the payment of such
difference and the cost of an incidental to such sale. Any outstanding balance existing after
crediting the proceeds of such sale shall be paid by the Contractor on the certificate of the
Engineer. But when all expenses cost and charges incurred in the completion of the work are paid
by the Contractor, all such materials, tools, tackle, construction plant or other things not used up in
the completion of the works and remaining unsold shall be removed by the Contractor. If the
proceeds of the above sale of the Contractors materials, tools, tackle, construction plant etc. are
insufficient to cover the executing the aforesaid work, the balance remaining after crediting the
proceeds of such sale shall be recoverable from the Contractor by encashing the Bank
Guarantee/available/ any other money payable by Purchaser or by action of law.
Not withstanding anything contained above, the Purchaser may determine the contract due to any
breach or failure of the Contractor, without notice before determining the contract as above, if in the
opinion of the Purchaser, the default or defaults committed by the Contractor is/are curable and
can be cured by the Contractor if an opportunity is given to him, then the owner may issue a notice
in writing calling upon the Contractor to cure the default within such time as may be specified in the
notice.
In the event of termination, the security deposit will be forfeited without reference to the Contractor
and if no amount is available towards Security Deposit, an identical amount is recoverable from the
contractor.
29.00 POWER TO VARY OR OMIT WORK
No alternations, amendments, omissions, additions, suspensions or variations of the work
hereinafter referred to as Variations, under the contract shall be made by the Contractor except as
directed in writing by the Engineer, but the Engineer shall have full power, subject to the provision
hereinafter contained from time to time during the execution of the contract by notice in writing, to
instruct the Contractor to make such variation without prejudice to the contract and the Contractor
Page 28 of 56
shall carry out such variation and be bound by the same conditions as far as applicable, as though
the said variation occurred in the contract.
If any suggested variations would, in the opinion of the Contractor, if carried out prevent him from
fulfilling any of his obligations or guarantees under the contract, he shall notify the Engineer thereof
within 10 days in writing and the Engineer shall decide forthwith whether or not the same shall be
carried out and if the Engineer confirms his instructions, the contractors obligations and
guarantees shall be modified to such and extent as may be justified. In the absence of any such
notification, the Contractor shall be bound to carry out the suggested variations without any
additional financial implication to Purchaser and it will amount to an absolute waiver of any claim
whatsoever.
30.00 SETTLEMENT OF DISPUTE
30.01 Except as otherwise specifically provided in the Contract all disputes concerning question of fact
arising under the Contract s hall be decided by the Engineer subject to a written appeal by the
Contractor to the Engineer, whose decision shall be final to the parties hereto.
30.02 Any disputes or differences including those considered as such by only one of the parties arising
out of or in connection with the Contract shall be to the extent possible settled amicably between
the parties.
30.03 If amicable settlement can not be reached then unresolved disputed issues may be settled by
arbitration as provided subsequently.
31.00 TERMINATION OF CONTRACT
Notwithstanding anything contained elsewhere in this contract, if at any time during the term of this
contract the plans of the Government of India and/ or the State Government change for any
reason, the Purchaser shall have the right to terminate the Contract by notice to the Contractor by
a registered letter. In respect of such changes the material that is complete as ready for
transportation within thirty (30) days after such notice, Purchaser agrees to accept delivery thereof
at the contract price and terms. In the case of the remainder of the undeliverable material, the
Purchaser may elect (a) to have any part thereof completed and take delivery thereof at the
contract price and (b) to cancel the residue (if any) and pay to the Contractor aprorated amount of
the contract price based upon the state of completion to be certified by him. The Contractor shall
deliver all such material in process of manufacture to the Purchaser and shall return to the
Purchaser any funds remaining to the Purchasers credit. No payment shall be made by the
Purchaser for any material not yet in process of manufacture on the date of notice of cancellation is
received.
32.00 DEDUCTION FROM CONTRACT PRICE
All costs, damages or expenses which the Purchaser may have paid, for which under the contract
Contractor is liable, may be deducted by the Purchaser from any money due or be coming due by
Page 29 of 56
him to the Contractor under the contract, or may be recovered by action of law or otherwise from
the Contractor. Further all legal and statutory deductions will be made and the Contractor is not
entitled to any reimbursement or claim what-so-ever except only a tax deduction certificate.
In the event of recovery to the necessary extent becoming impossible owing to insufficiency of the
performance bond and withheld amounts, the balance due to the purchaser, may be recovered in
any way the Purchaser may deem fit.
33.00 CO-OPERATION WITH OTHER CONTRACTORS AND CONSULTING ENGINEERS
The Contractor shall agree to co-operate with the Purchasers other contractors and Consulting
Engineers for associated equipment and freely exchange with them such technical Information as
is necessary to obtain the most efficient and economical design and to avoid unnecessary
duplication of equipment. No remuneration shall be claimed from the Purchaser for such technical
cooperation. The Purchaser and consulting Engineer shall be provided with two (2) copies each of
all correspondence addressed by the Contractor to other Contractors in respect to such exchange
of technical information.
If any part of the Contractors work depends for proper execution or results upon the work of any
other Contractor, the Contractor shall inspect and promptly report in writing to the engineer any
defects; in such works that render it unsuitable for such proper execution and results. His failure to
so inspect and report shall constitute an acceptance of the other Contractors work as fit and
proper for the reception of his work, except as to defects which may develop in the other
Contractors work after the proper execution of his work.
34.00 ASSIGNMENT OF CONTRACT
Any assignment of the contract or any part thereof or any rights or obligations there under, by the
Contractor without the prior written consent of the Purchaser shall be void.
The purchaser shall be at liberty to transfer and assign the contract only to Government Company
as defined in the Indian Companies Act-I of 1956, and such Company shall exercise all the rights
and be liable for all obligations of the Purchaser contained herein in the same manner as if the
agreement had been entered into between the said Company and the Purchaser. The purchaser
shall be also at liberty to entrust the carrying out of the agreement only to a Government Institution
and upon the Instructions of the purchaser, the Contractor undertakes to do all things necessary to
carry out of his obligations under the agreement with such institution as may be entrusted by the
purchaser as agent or otherwise. The Purchaser, however, shall not be in either case relieved or
discharged from any of his obligations and liabilities under the contract.
The contractors shall be advised in writing of the date of any such substitution.
Page 30 of 56
35.0
SUBLETING OF CONTRACT
The Contractor shall not without the consent in writing of the Purchaser, which shall not be
unreasonably withheld, assign or sublet his contract or any substantial part thereof other than for
raw materials, for minor details, or for any part of the works of which the makers are named in the
contract, provided that any such consent shall not relieve the Contractor from any obligation, duty
or responsibility under the contract.
For components/equipments procured by the Contractors for the purpose of the Contract; after
obtaining the written approval of the Owner, the Contractors purchase specifications and enquiries
shall call for quality plans to be submitted by the suppliers along with their proposals. The quality
plans called for from the vendors shall set out, during the various stages of manufacture and
installation, the quality practices and procedures followed by the Vendors quality control
organization, the relevant reference documents/standards used, acceptance level, inspection of
documentation raised, etc. Such quality plans of the successful vendors shall be discussed and
finalized in consultation with the Engineer and shall form a part of the purchase order/contract
between the Contractor and the vendor. Within 3 weeks of the release of the same purchase
order/contracts for such bought out items/components, a copy of the same without price details but
together with detailed purchase specifications, quality plants and delivery conditions shall be
furnished to the Engineer by the Contractor.
Page 31 of 56
Page 32 of 56
Page 33 of 56
The Purchaser; shall pay the Contractor for the service of each supervisor as follows:
(a)
As agreed rate; per-calendar day from the date on which supervisor leave his
headquarters up to and including the date of his return thereto. This rate is based up on a
normal 48 hours work-week of six (6) eight-hour workdays, Monday through Saturday.
Sunday will be normally a holiday but any other day of the week may be made a normal
holiday depending upon working conditions.
(b)
The Purchaser shall in addition to the charge specified in paragraph above, pay the
Contractor for any overtime work authorized by the Purchaser and performed by the
supervisor at an agreed overtime rate per hour for hours worked in excess of 8 hours per
day and all hours worked on the seventh day. There will be no overtime charge for work
performed on locally recognized or national holiday or time spent in traveling to and from
the supervisors headquarters.
(c)
Hours during which the supervisor is ready, willing and able to work up to 48 hours per
week shall be regarded as having actually been worked by him even though his services
are not in fact utilized.
The Purchaser shall secure any labor permit or any other authorization which may be required to
permit the Erection Supervisor to perform the services and any loss of the supervisors services
pending the procurement of any such permit or authorization shall be to the Purchasers account
and shall be paid for by the Purchaser.
The Purchaser shall furnish, at his own expenses, and assume responsibility for all labor and labor
supervision and shall make available all necessary installation to tools, except such special tools
as may be supplied by the Contractor pursuant to written agreement between the parties. The
supervisor may elect to bring certain personal tools which tools are to remain his property at all
times. The Purchaser shall assist the Supervisor in arranging entry and exit permit for such tools.
If any portion of the work of supervision by the Contractor proves to be defective within one (1)
year from the date of completion of supervision, the Contractor, if promptly notified thereof in
writing, will at his own expense, and at his option, with make repairs or supply replacement parts
directly to or for the equipment and necessary to correct any defect or defects in such equipment
directly resulting from such defective work of supervision on the part of the Contractor and will at
his own expenses, furnish the necessary supervision for such corrections. The contractors liability
in connection with his furnishing a supervisor hereunder shall in no event exceed the cost of
correcting any such defective work of supervision in the manner herein provided and upon the
expiration of the said one (1) year, all such liability shall terminate. In no event shall the Contractor
be liable for special, indirect or consequential damages.
The Contractor shall not be liable for loss of damage due to delays in furnishing the services or in
the work resulting form any cause beyond the Contractors reasonable control including
compliance with any Government regulations, orders or instructions, acts of God, acts of omission
Page 34 of 56
of Purchaser, acts of civil or military authority, fires, strikes, war earthquake, storm, volcanic
eruptions, landslide, riot or delays in transportation. The Purchaser shall advise the Contractor in
writing reasonably in advance of the date that the supervisor shall be required to start performance
of the services.
44.00 ERECTION OF PLANT AND MATERIALS
44.01 General
Unless otherwise mutually agreed to the provisions of this clause shall apply where the services for
erection of plant & material supplied by the contractor are included in the scope of work.
If so desired by the Purchaser, the Contractor shall receive the imported equipment, if any, at the
port of entry, clear them through Customs and make damage report through port broker. The
Contractor shall arrange for payment at prescribed rate of Customs Duty which will be reimbursed
by the Purchaser against Contractors valid documents.
The Contractor shall transport all imported equipment from port of entry to the site and unload all
Imported/Indigenous equipment at site. Escort service shall be provided, if necessary and called
for. All storage at port of entry or at railway station will be at Contractors charge.
The Contractor shall be responsible for complete installation of the equipment start-up and testing
at site.
All equipment and tools for transportation and erection shall be provided by the Contractor.
All materials and /or equipment, after receipt at site, shall be checked and verified against shipping
documents and all claims against loss or damage in transit shall be intimated to the purchaser. The
materials and/or equipment shall remain under the custody of the Contractor until the plant as a
whole is taken over by the Purchaser upon completion of the work. The Contractor shall take
adequate steps to ensure safety of such materials and / or equipment. Necessary stores receipt
certificates shall be issued to the Purchaser after the stores are checked and certified. No materials
and/or equipment pertaining to the Contract shall be removed from site without the consent in
writing of the Purchaser.
The Contractor shall be responsible for obtaining the correct reference lines for purposes of fixing
the alignment of various equipment.
44.02 Regulation of Local Authorities and Statues
The Contractor shall comply with the rules and regulations of local authorities during the
performance of his field activities. He shall also comply with the minimum wages Act, 1948 and the
payment of wages act (both of the Government of India) and the rules made there under in respect
of any employee or workmen employed or engaged by him or his sub-Contractor.
Page 35 of 56
All registration and statutory inspection fees, if any, in respect of his work pursuant to this contract
shall be to the account of the Contractor. However, any registration, statutory inspection fees
lawfully payable under the provisions of the Indian Boiler Regulations and any other statutory laws
and its amendments from time to time during erection in respect of the plant equipment ultimately
to be owned by the Purchaser, shall be to the account of the Purchaser. Should any such
inspection or registration need to be re-arranged due to the fault of the Contractor or his subContractor, the additional fees of such inspection and/or registration shall be borne by the
Contractor.
44.03 Work at Site
In the execution of work, no persons other than the Contractor or his appointed representative,
sub-Contractor and workmen shall be allowed to do work at site, except by the special permission
in writing of the Engineer or his representative, but access to the Works at all times shall be
accorded to the Engineer and his representative and other authorized officials or representatives of
the Purchaser.
Nevertheless, the Contractor shall not object to the execution of work by other Contractors or
tradesmen whose names shall have been previously communicated in writing to the Contractor by
the Engineer and afford them every facility for the execution of their several works simultaneously
with his own.
The Contractor shall at all times provide sufficient fencing, notice boards, lights and watchmen to
protect and warn the public and guard the works, and in default thereof the Purchaser may
provided such fencing, notice boards, lights and watchmen as he may deem necessary and charge
the cost thereof to the Contractor.
The work so far as it is carried out on the Purchasers premises shall be carried out at such time as
the Purchaser may approve and so as not to interfere unnecessarily with the conduct of the
Purchasers business but the Purchaser shall give the Contractor all reasonable facilities for
carrying out the work. No female labor shall be employed during dark hours.
The Contractor shall not employ for the purpose of the contract any person who is below the age of
eighteen years and shall pay to each laborer, for the work done by such laborer, wages not less
then the wages paid for similar work in the neighborhood. The Engineer shall have the right to
enquire into and decide any complaint alleging that the wages paid by the Contractor to any laborer
for the work done by such laborer is less than the wages paid for similar work in the neighborhood,
and to refuse appointment of labor less than eighteen years of age.
The Contractor shall make regular and prompt payment of wages to the laborers engaged on the
work and in not case the payment shall be delayed more than seven (7) days following the period
for which the wages are due. If it is found the workers are not paid regularly the contract is liable to
be rescinded. The Contractor shall comply strictly with the provisions of Labor Laws in this behalf.
Page 36 of 56
Page 37 of 56
During the progress of work the Contractor shall submit monthly progress reports and photographs
and such other reports on the erection work and organization, as the Engineer may direct. The
progress indicated be arrived by agreement between the Contractor and the Engineer. The
Contractor shall also submit an anticipated one (1) month progress schedule at the beginning of
each month describing in detail the anticipated progress for the following month. The Contractor
shall also submit every week a list of various categories of men working under him. Monthly
progress reports shall be submitted within the tenth day of the month following the reporting month.
44.08 Man - Power Report
The Contractor shall submit to Engineer, on the first day of every month, a man hour schedule for
the month, detailing the man hours scheduled for the month, skill wise and are wise.
The Contractor shall also submit to the Engineer on the first day of every month, a man power
report of the previous month detailing the number of persons scheduled to have been employed
and actually employed, skill wise and the areas of employment of such labor.
44.09 Extension of Time
The application for extension of time is to be given to owner/purchaser through the Engineer and
the owner/purchase may authorize extension of time after considering the due merits.
Whenever extension of time is granted by the owner/purchaser, the same shall be on the existing
terms and conditions of the contract and without any additional financial liability to the Owner. The
Contractor in any case shall have no claim whatsoever for any type of compensation on account of
any delay attributable to any one.
44.10 Liability for Accident and Damage
The Contractor shall Indemnify the Purchaser against any claims which may be made under the
workmans Compensation Act, 1923, or any statutory modification thereof or otherwise for or in
respect of any damages or compensation payable in consequence of any accident or injury
sustained by any workman or other person whether in the employment of the Contractor or not. In
every case in which by virtue of the provisions of sub-section (1) of Section 12 of the Workmans
compensation Act, 1923, the Purchaser is obliged to pay compensation to a workman employed by
the Contractor in execution of the works, the Purchaser will recover from the Contractor the amount
of the compensation so paid and without prejudice to the rights of the Purchaser under sub-section
(2) of Section 12 of the said Act. The Purchaser shall be at liberty to recover such amount or any
part thereof by deducting it from the Performance Bond or from any sum due by the Purchaser to
the Contractor whether under the contract or otherwise.
The Purchaser shall not be bound to contest any claim made against it under Section 12, subsection (1) of the said Act, except on the written request of the Contractor and upon his giving to
the Purchaser full security for all costs for which the Purchaser might become liable in
consequence of contesting such claim. In the event of claim being made or action brought against
Page 38 of 56
the Purchaser involving the Contractor and arising out of the matters referred to and in respect of
which the Contractor is liable under this clause, the Contractor shall be immediately notified thereof
and he shall with the assistance, if so required by the Purchaser, but at the sole expense of the
Contractor, conduct all negotiations for the settlement of the same, or of any litigation that may
arise there from. In such case the Purchaser, at the expenses of the Contractor, afford all available
assistance for any such purpose.
The Contractor shall be responsible for all loss, damage or depreciation to the plant until the plant
is taken over in accordance with clause Taking Over. The Contractor shall, during the progress
other work, properly cover up and protect the plant from injury by exposure to weather and; shall
take every reasonable, proper, timely and useful precaution against accident or injury to the same
from any cause shall be and remain answerable and liable for all accidents or injuries thereto
which, until the same be or be deemed to be taken over under clause Taking Over may arise or
be occasioned by the acts or omissions or the Contractor of his workmen or sub- Contractors, and
all losses and damage to the Plant arising from such accidents or injuries as aforesaid shall be
made good in the most complete and substantial manner by and at the sole cost of the Contractor
and to the reasonable satisfaction of the Engineer.
Until the plant shall be or deemed to be taken over as aforesaid the Contractor shall also be liable
for and shall be deemed to have agreed to indemnity the Purchaser in respect of all damage to any
property of the Purchaser or of others occasioned by the negligence or fault of the Contractor or
sub-contractor or his or their workmen or representatives or by defective design, work or material
or otherwise.
The Contractor shall pay all taxes due in India for the personnel employed by the Contractor work
arising out of their services in connection with the contract and obtaining at his (Contractors) own
cost work permits from competent authorities to enable any foreign personnel to work in India.
The Contractor shall be responsible for all formalities in connection with the passport, obtaining of
visas, police permits, and expenses for customs duties related to personal goods of foreign
personnel to be employed in the erection work. However, the Purchaser shall If requested, assist
the Contractor in obtaining visas and work permits for the foreign personnel to be deputed for the
erection work.
44.11 Cleanliness
During erection, the Contractor shall, without any additional payment, at all times keep the working
and storage areas used by him free from accumulation of waste materials or rubbish. If the
Contractor fails to remove the rubbish, within forty eight (48) hours, after being requested by the
Engineer, the rubbish will be removed by others and cost back charged to the Contractor. Any
inflammable material should be removed forthwith on request by the Engineer.
Page 39 of 56
Before completion of erection, the Contractor shall remove or dispose of in a satisfactory manner
all temporary structures, packing cases, waste and debris and leave the premises in a condition
satisfactory to the Engineer.
Similarly the labor colony, the offices and the residential areas of the Contractors employees and
workmen shall be kept clean & neat to the entire satisfaction of the Engineer. Proper sanitary
arrangements shall be provided by the Contractor, in the work areas office and residential areas of
the Contractors.
44.12 Co-ordination with the Purchasers Engineers
The Contractor shall at all times work in co-ordination with the Purchasers Engineers and afford
them every facility to become familiar with the erection and maintenance of the equipment.
In respect of observance of local rules, administrative matters, co-ordination with other Contractors
and the like, the Contractor and his personnel shall work under the Purchasers Engineer in charge
of the work.
44.13 Work and Services to be provided by the Purchaser
Unless otherwise agreed upon, the following works and services shall be provided by the
Purchaser for carrying out complete erection work:
(a)
Water Supply
Water supply for construction purpose will be provided by the Purchaser at one mutually
agreed point at site. Drinking water will also be made available at one central point at site.
The Contractor shall make his own arrangement for any further distribution. Such
distribution pipe network shall have the prior approval of the Engineer at site so as not to
interfere with the layout and progress of other construction works. The water supply shall
be free of cost. Contractor shall ensure that there is no wastage of water. On completion of
the work, the Contractor shall remove all such work and shall reinstate and make good any
work disturbed to the satisfaction of the Engineer.
(b)
Power Supply
(I)
Electric power will be supplied at 400/440 V and shall be metered and charged at
applicable rates.
(II)
Supply for execution of work will be made available at one point only. This point
will not be more than 500 meters away from the Contractors premises. The
Contractor shall make his own arrangement at his own cost for distribution of
Page 40 of 56
The Purchaser shall not however, guarantee the supply of electricity and no
compensation for any failure or short supply of electricity will be entertained and
this does not relieve the Contractor of his responsibility for timely completion of the
work as stipulated in the Contract.
(IV)
It shall be the responsibility of the Contractor to provide and maintain the complete
installation on the load site of the supply with due regard to safety requirement at
site. All cabling, equipment, installations etc. shall comply in all respects with the
latest statutory requirements and safety provisions, i.e. as per given in the
Central/State Electricity Acts and Rules etc. The Contractor will ensure that his
equipment and Electricity wiring etc. are installed, modified and maintained by a
licensed Electrician / Supervisor and before power is supplied, a test certificate is
to be produced to the Engineer for his approval.
(V)
At all times, IEA Regulations shall be followed failing which the Purchaser has a
right to disconnect the power supply without any reference to the Contractor. No
claim shall be entertained for such disconnection by the Engineer. Power supply
will be reconnected only after production of fresh certificate from authorized
electrical supervisors.
The Purchaser will not liable for any loss or damage to the Contractors equipment
as a result of variation in voltage or frequency or interruption of power supply or
other loss to the Contractor arising there from.
(VI)
(VII)
The Contractor shall ensure that the Electrical equipment installed by him are such
that average power factor does not fall below 0.9 at this premises. In case P.F.
falls below 0.9 in any month, he will reimburse to the purchaser at the rate same
as OSEBs rate for per unit fall of P.F. determined from time to time by Purchaser
all units consumed during the month.
(VIII)
The power supply required for Contractors colony near the plant site will be
determined by the Purchaser and shall be provided as per State Electricity Boards
Rules and other Statutory provisions applicable for such installations from time to
time. In case of power supply to Contractors colony, the power will be made
available at a single point and the Contractor shall make his own arrangement at
Page 41 of 56
his own cost for distribution to the occupants of the colony as per Electricity Rules
& Acts. The site area and colony shall be sufficiently lighted to avoid accidents.
(IX)
The Contractor will have to provide and install his own light and power meters
which will be governed as per Central/State Govt. Electricity Rules. The meters
shall be sealed by the Purchaser.
(X)
(XI)
After completion of work, the Contractor shall promptly dismantle, at his own cost
distribution and other facilities that he may have erected and shall also remove the
same within a reasonable time fixed by the Engineer and on his failure to do so the
Purchaser will be entitled to realize from his reasonable compensation fixed by the
Engineer and also to remove them at the cost of the Contractor.
(XII)
Only motors up to 3HP will be allowed to be started direct on line. For motors
above 3 HP and up to 100 HP suitable starting devices approved by the Purchaser
Engineer, shall be provided by the Contractor. For Motors above 100 HP slip ring
induction motors with suitable starting devices as approved by the Engineer shall
be provided by the Contractor.
(XIII)
The single line distribution system with loadings and specifications shall be
submitted to the Engineer for his approval before the system is installed. The
system shall conform to Central/State Statutory provisions Act, with latest
amendments and to the Approved specifications of the company. The installations
have to be inspected and approved by the Electrical Inspector, Govt. of Orissa
before energisation.
The total requirement of power shall be indicated by the tenderer in his tender and
confirmed within thirty days from the date of Letter of Intent.
(XIV)
(d)
The Purchaser will at his own discretion and convenience and for the duration of
the execution of the work make available near the site, land for construction of
Contractors field office, godowns, workshops and assembly yard required for the
execution of the contract. The Contractor shall at his own cost construct all these
temporary buildings and provide suitable water supply and sanitary arrangement
approved by the Engineer.
(II)
Page 42 of 56
the expenses of the Contractor will remove such surplus and rubbish materials
and dispose off the same as he deems fit and get the site cleared as aforesaid,
and the contractor shall forthwith pay the amount of all expenses so incurred and
shall have no claim in respect of any such surplus materials disposed off as
aforesaid. But the Purchaser reserves the right to ask the Contractor any time
during the pendency of the contract to vacate the land by giving 7 days notice on
security reasons on national interest or otherwise. A token rent of Rs. 100/(Rupees one hundred only) per hectare or part thereof per annum or part thereof
shall be charged for the land so occupied.
(III)
Land for residential accommodation for staff and labor will be made available at
the discretion of the Engineer and rent for the same will be as decided by the
Engineer according to location and area taken by the Contractor.
(e)
Electricity and drinking water at normal charges for labor quarters at a central point within
the land provided by the Purchaser. The cost of distribution, if any, shall be borne by the
Contractor.
(f)
Assistance to the Contractor in obtaining Indian visas, residential or working permits for the
permits for the personnel, if necessary.
(g)
Water and electricity as may be required for the initial starting up of the equipment free of
charge to Contractor.
(h)
Necessary Engineers, operators and other personnel for start up commissioning and
acceptance tests of the equipment free of charge to Contractor.
(i)
(J)
Clearing, unloading the equipment from the rail or road transport to Contractors
transport/vehicle and delivery the same to storage area. Demurrage charges, if incurred at
rail head or at site for default of the Contractor shall be paid by him
(ii)
Opening of packing cases, Inspection and checking of materials. Repair and replacement
of contract material damaged or lost in transit or at site.
Page 43 of 56
(iii)
(iv)
Complete erection of the equipment covered under the contract, final preparation for
testing, commissioning, final run and acceptance tests and putting the plant into
commercial operation.
(v)
All consumable stores required for the above work, except those mentioned under Clause
44.13 (i).
(vi)
Watch and ward to ensure security and safety of materials under the custody.
(vii)
(viii)
Daily transport for his erection personnel to and fro between residence and site.
(ix)
All erection tools and lifting tackles, also all equipment, tools and tackles for transportation
of all equipment to site. A list of such tools and tackle and equipment shall be submitted to
the purchaser before commencement of site work. These tools and tackle shall not be
removed from the site without written permission of the Engineer.
(x)
All ladders, platforms, temporary supports and facilities required for handing of heavy
packages at site required for erection.
(xi)
(xii)
Third Party Insurance at site and insurance of Contractors personnel employed at site as
required under Workmens Compensation Act.
(xiii)
(xiv)
(xv)
(xvi)
Applying final paint to all equipment, piping, hanger etc. covered under the contract.
(xvii)
(xviii)
If the Contractor uses his own crane, he must have a skilled crane operator.
(xix)
Contractor must take all safety precautions during work and the workmen must use safety
belts, tested gloves, masks and other devices as necessary for safety of personnel
Page 44 of 56
(xx)
Contractor should provide identity badges for his employees. These should be properly
displayed during working hours.
(xxi)
The Contractor shall employ only competent and skilled workmen fully experienced and
capable of performing duties assigned for them. When local laws required the employee
shall be required to acquire certificate of competency for his work from the competent
authority.
(xxii)
Communication
The Contractor will make his own arrangement for all his communications needs such as
telephone, telex etc. at his site office and his residential area. Purchaser will assist in
getting the above facilities, in case he finds and difficulty.
(xxiii)
First Aid
The Contractor shall provide necessary first-aid facilities for all his employees,
representatives and workmen working at site. Enough number of contractors personnel
shall be trained in administering first-aid.
(xxiv)
Welfare facilities
Contractor shall provide in his labor colony all necessary standard welfare facilities like
canteen, shopping facility etc.
Page 45 of 56
(a)
The work procedures that are to be used during the erection shall be those which minimize
fire hazards to the extent practicable. Combustible materials, combustible waste and
rubbish shall be collected and removed from the site at least once each day. Fuels, oil and
volatile or flammable materials shall be stored away from the construction and equipment
and materials storage area in safe containers. Adequate precaution shall be taken in
handling and storage of flammable gas. Care shall be taken to avoid and reduce hazards
from electrical short circuits and faults. Untreated canvas paper, plastic or other flammable
flexible materials shall not at all be used at site for any other purpose unless otherwise
specified. If any such materials are received with the equipment at the site, the same shall
be removed and replaced with acceptable material before moving into the construction
area of storage.
(b)
Similar corrugated paper fabricated cartons etc. will not be permitted in the construction
area either for storage or for handling of materials. All such materials used shall be of
water proof and flame resistant type. All the other materials such as working drawings
plans etc. which are combustible but are essential for the works to be executed shall be
protected against combustible resulting from welding sparks, cutting flames and other
similar fire sources.
(c)
All the Contractors supervisory personnel and sufficient number of workers shall be
trained for fire - fighting and shall be assigned specific fire protection duties. Enough of
such trained personnel must be available at site during the entire period of the Contract.
(d)
The contractor shall provide enough fire protection equipment of the types and number for
the ware - houses, office, temporary structures, labor colony area etc. Access to such fire
protection equipments shall be easy & kept open at all times.
All the equipments furnished under the Contract and arriving at site shall be promptly
received, unloaded and transported and stored in the storage spaces by the contractor.
(b)
The Contractor shall be responsible for examining all the shipment and notify the engineer
immediately of any damages, shortages; discrepancy etc. for the purpose of Engineers
information only. The Contractor shall submit to the Engineer every week a report detailing
all the receipts during the week. However, the Contractor shall be solely responsible for
any shortages or damage in transit, handling and/ or storage & erection of the equipment
at site. Any demurrage, wharfage and other charges claimed by the transporters, railways
etc. shall be to the account of Contractor.
Page 46 of 56
(c)
The Contractor shall maintain an accurate & exhaustive record detailing out the list of all
equipment received by him for the purpose of erection & keep such record open for the
inspection of the Engineer at any time.
(d)
All equipments shall be handled very carefully to prevent any damages or loss. No bare
wire, rope, slings etc. shall be used for unloading and/ or handling of the equipment
without the specific written permission of the Engineer. The equipment stored shall be
properly protected to prevent damages either to the equipment or to the floor where they
are stored. The equipment from the store shall be moved to the actual location at the
appropriate time so as to avoid damage of such equipment at site.
(e)
All electrical panels, control gear, motors and such other devices shall be properly dried by
heating before they are installed and energised. Motor bearings, slip rings, commutators
and other exposed parts shall be protected against moisture ingress and corrosion during
storage and periodically inspected. Heavy rotating parts in assembled conditions shall be
periodically rotated to prevent corrosion due to prolonged storage.
(f)
All the electrical equipment such as motors, generators, etc. shall be tested for insulation
resistance at least once in three months from the date of receipt till the date of
commissioning and a record of such measured insulation values maintained by the
Contractor. Such records shall be open for inspection by the Engineer.
(g)
The Contractor shall ensure that all the packing materials and protection devices used for
the various equipment during transit and storage are removed before the equipment are
installed.
(h)
The consumables and other supplies likely to deteriorate to storage must be thoroughly
protected and stored in a suitable manner to prevent damage or deterioration in quality by
storage.
(i)
All the materials stored in the open or dusty location must be covered with suitable
weatherproof and flame-proof covering material wherever applicable.
(j)
If the materials belonging to the Contractor are stored in areas other than those earmarked
for him the Engineer will have the right to get it moved to the area earmarked for the
Contractor at the Contractors cost.
(k)
The Contractor shall be responsible for making suitable indoor storage facilities to store all
equipment which required indoor storage. Normally, all the electrical equipment such as
motors, control gear, generators, exciters and consumables like electrodes, lubricants etc.
shall be stored in the closed storage space. The Engineer, in addition, may direct the
Contractor to move certain other materials which in his opinion will require indoor storage
areas which the Contractor shall strictly comply with.
Page 47 of 56
The field activities of the Contractors working at site will be coordinated by the Engineer
and the Engineers decision shall be final in resolving any disputes or conflicts between the
contractors and tradesmen of the Purchaser regarding scheduling and co-ordination of
work. Such decision by the Engineer shall not be a cause for extra compensation or
extension of time for the Contractor.
(b)
The Engineer shall hold weekly meetings of all the Contractors working at site, at a time
and a place to be designated by the Engineer. The Contractor shall attend such meetings
and take notes of discussions during the meeting and the decisions of the Engineer and
shall strictly adhere to those decisions in performing his works. In addition to the above
weekly meetings, the Engineer may call for other meetings either with individual
contractors or with selected number of contractors and in such a case the Contractor, if
called, will also attend such meetings.
(c)
Time is the essence of the Contract and Contractor shall be responsible for performance of
his woks in accordance with the specified construction schedule. If at anytime, the
Contractor is falling behind the schedule, he shall take necessary action to make good for
such delays by increasing his work to comply with the schedule and shall communicate
such actions in writing to the Engineer, satisfying that his action will compensate for the
delay. The Contractor shall note be allowed any extra compensation for such action.
(d)
The Engineer shall however not be responsible for provision of additional labor and/ or
materials or supply or any other services to the Contractor except for the co-ordination
work between various entities as set out earlier.
Without prejudice to the general obligation under the statutes the Contractor shall ensure
the safety of all the workmen, materials and equipment either belonging to his or to others
working at site.
b)
The Contractor will notify the Engineer of his intention to bring on to site any equipment or
any container, with liquid or gaseous fuel or other substance which may create hazard.
The Engineer shall have the right to prescribe the conditions under which such equipment
or container may be handled and used during the performance of the works and the
Contractor shall strictly adhere to such instructions. The Engineer shall have the right to
inspect any construction plant and to forbid its use, if in his opinion it is unsafe. No claim
due to such prohibition shall be entertained by the Purchaser.
Page 48 of 56
c)
d)
The Contractor shall be responsible for provisions of all safety notices and safety
equipment required both by the relevant legislations and the Engineer as he may deem
necessary.
e)
The Contractor shall be responsible for the safe storage of his and his sub - contractors
radioactive sources, if any.
f)
In no circumstances will the Contractor interfere with fuses and electrical equipment
belonging to the Purchaser or other Contractors.
g)
Before the Contractor connects any electrical appliances to and plug or socket belonging
to the other Contractor or Purchaser, he shall -
h)
i)
ii)
Inform the engineer of the maximum current rating, voltage and phases of the
appliances;
iii)
Obtain permission of the Engineer detailing the sockets to which the appliances
may be connected.
The Engineer will not grant permission to connect until he is satisfied that i)
The appliance is in good condition and fitting with a suitable plug;
ii)
The appliance is fitting with a suitable cable having two earth conductors, one of
which shall be an earthed metal sheath surrounding the cores.
i)
j)
No work shall be carried out on any live equipment. The equipment must be made safe by
the Engineer and permit - to - work issued before any work is carried out.
k)
The Contactor employs the necessary number of qualified, full time electricians to maintain
his temporary electrical installation.
Page 49 of 56
Page 50 of 56
circumstances. In the event of stoppage of the works the period of the option under this clause
shall be fourteen (14) days only, provided that should be above option be not exercised, the
contract may be terminated by the purchaser by notice in writing and the same power and
provisions reserved to the Purchaser in clause `Negligence in the event of taking the work out of
the Contractors hands shall immediately become operative.
47.00 GRAFTS AND COMMISSION ETC.
Any graft, commission, gift or advantage given promised or offered by or on behalf of the
Contractor or his partner, agent, officers, director, employee or servant or any one on his or their
behalf in relation to the obtaining or to the execution of this or any other contract with purchaser,
shall in addition to any criminal liability which it may incur, subject the contractor to the cancellation
of this and other contracts and also to payment of any loss or damage to the purchaser resulting
from any cancellation. The purchaser shall then be entitled to deduct the amounts so payable from
any money otherwise due to the Contractor under the contract.
48.00 COMPLETION OF CONTRACT
Unless otherwise terminated under the provisions of any other relevant clause, this contract shall
be deemed to have been completed all the expiration of the guarantee period as provided for under
the clause entitled `Guarantee Period as provided for under the clause entitled `Guarantee and
only on issue of a certificate to that effect and not otherwise.
49.00 DEFENCE OF SUITS
In any action in court is brought against the purchaser or Engineer or an officer or agent of the
purchaser, for the failure or neglect on the part of the contractor to perform any acts, matters,
convenants or things under the contract, or for damage or injury caused by the alleged omission or
negligence on the part of the Contractor, his agents, representatives or his sub-contractors,
workmen, suppliers, or employees, the Contractor shall in all such cases indemnify and keep the
purchaser, and the Engineer and / or his representative harmless from all losses, damages,
expenses or decrees arising of such action.
50.00 ARBITRATION
All disputes or differences arising under the contract whether during or after completion of the
contractor or whether before or after determination, for closure or breach of the contract (other than
those in respect of which the decision of any person is by the contract expressed to the final and
binding) shall after written notice by either party to the contract to the other of them and to the
Appointing Authority hereinafter mentioned be referred for adjudication to a sole Arbitrator to be
appointed as hereinafter provided.
Page 51 of 56
For the purpose of appointing the sole Arbitrator referred to above, the CMD NALCO who shall be
Appointing Authority will send within thirty days of receipt of the notice to the Contractor a panel of
three names of persons.
The Contractor shall on receipt of the names as referred select any one of the person names to be
appointed as a sole Arbitrator and communicate his name to the Appointing authority within thirty
days of receipt of the names. The Appointing Authority shall there upon appoint the said person as
the sole Arbitrator. If the Contractor fails to communicate such selection as provided above within
the period specified, the Appointing Authority shall make the selection and appoint the selected
person as the Sole Arbitrator.
If the Arbitrator so appointed is unable to / unwilling to act or resigns his appointment or vacates his
office due to any reason whatsoever sole arbitrator or shall be appointed as aforesaid. The work
under the contract shall not be stopped during the arbitration proceedings.
The Arbitrator shall be deemed to have entered on the reference on the date he issues notices to
both the parties fixing the date of first hearing.
The Arbitrator may, from time to time, with the consent of the parties, enlarge the time for making
and publishing the awards.
The Arbitrator shall give a separate award in respect of each dis pute or difference and shall give a
reasoned and speaking award / awards.
The venue of arbitration shall be at Bhubaneswar. However, if the situation so warrants, it may as
and when required, he held at the place where the site of work is situated.
The fees, if any, of the Arbitrator shall, if required to be paid before award is made and published,
be paid half and half by each of the parties. The cost of the reference and of the award including
the fees, if any, of the Arbitrator shall be in the discretion of the Arbitrator who may direct to and by
whom and in what manner, such costs or any part thereof shall be paid and may fix or settle the
amount of costs to be so paid.
The award of the arbitrator shall be final and binding on both the parties.
Subject to aforesaid the provisions of the Arbitration Act 1940 or any statutory modification or reenactment thereof and the rules made there under, and for the time being in force, shall apply to
the arbitration proceeding under this clause.
For Public Sector Enterprises guidelines as per circular of BPE No. 15.9.86 - BPE (FIN) dtd.
30.03.1989 as amended from time to time will be applicable for resolving any disputes.
51.00 CORRESPONDENCE
The Purchaser shall ordinarily correspond with the Contractor at the address furnished by the
Contractor.
Page 52 of 56
The Contractor shall ordinarily forward two (2) copies of all correspondence relating to this contract
to the Purchaser and two (2) copies to the Consulting Engineer or his representative as may be
requested.
Two (2) copies of all correspondence from the Contractor to Purchasers other Contractors for
associated plants shall be forwarded to the Purchaser and the Consulting Engineer.
All drawings and correspondence to the Purchaser and the Consulting Engineer shall be
transmitted by the Contractor via Air Mail or alternatively by means involving the minimum time of
transit.
52.00 CONTRACT AGREEMENT
If so desired by the Purchaser, a formal Agreement shall be entered into by the Contractor with the
Purchaser for the proper fulfillment of the Contract.
The expenses of completing and stamping the Agreement shall be paid by the Contractor, and the
Purchaser shall be furnished free of charge with an executed stamped counterpart of the
Agreement as also copies of the Agreement as may be required by the purchaser.
Any tender drawing, technical data and / or correspondence which forms the basis of an order or a
contract aforesaid, or which may be furnished by the Contractor for the Purchasers approval or
information as provided under the said order or contract, shall be in English and it is in any other
language, a complete translation in English shall have to be duly furnished. The Purchaser shall
not be bound to consider any tender drawing, technical data or correspondence which is not
furnished in English.
53.00 PAYMENTS
53.01 The payment to the Contractor for the performance of the works under the contract will be made by
the purchaser as per the guidelines and conditions specified herein. All payments made during the
contract shall be on account of payments only. The final payment will be made on completion of all
the works and on fulfillment by the Contractor of all his liabilities under the contract.
53.02 Currency of Payment
The payments for the foreign currency potion of the contract price will be made in the currency of
the bid. If the bid is in a currency other than that of the country of origin of goods, payment may be
made in an amount equivalent to the bid price in the currency of the country of origin. The Indian
Rupees portion of contract price stated in the contractors bid will be paid in Indian Rupees.
53.03 Payment Schedule
Page 53 of 56
The Contractor shall prepare and submit to the Engineer for approval, break-up of the contract
price. The contract price break-up shall be interlinked with the agreed detailed PERT Network of
the Contractor setting forth his starting and completion dates for the various key phases of works.
Any payment under the contract shall be made only after the contractors price break-up is
approved by the Engineer. The aggregate sum of the contractors price break down shall be equal
to the lump sum contract price.
53.04 Application for Payments
The Contractor shall submit application for the payments in the prescribed proforma of the
purchaser.
The foreign contractor shall submit to the Engineer separate applications for payment in different
currencies whenever payment is to be made in more than one currency.
Each such application shall state the amount claimed and shall set forth in details, in the order for
the payment schedule particulars of the works including the works executed at site and of the
equipment shipped/brought on to the site pursuant to the contract up to the date mentioned in the
application and for the period covered since the last preceding certificate, if any.
Every interim payment certificate shall certify the contract value of the works executed up to the
date mentioned in the application of the payment certificate, provided that no sum shall be included
in any interim payment certificate in respect of the works that, according to the decision of the
Engineer, does not comply with the contract, or has been performed, at the date of certificate
prematurely.
Supply
-
80% shall be paid for each consignment dispatched pro-rata against presentation
of each invoices and evidence of shipment/dispatch.
Page 54 of 56
B)
C)
D)
Erection Services
-
80% shall be paid for the progress made during the month on monthly progress
bills against certification by the Engineer.
54.00 MISCELLANEOUS
54.01 Entire Agreement
These General Conditions together with the specification, tender drawing and guaranteed technical
particulars, tender data with subsequent agreed modification thereof shall constitute the entire
Agreement between the parties in respect of the subject matter hereof. No variation or modification
of the contract or waiver of any of the terms and conditions thereof shall be deemed valid unless in
writing and signed by the parties hereto.
54.02 General Conditions of Contract, the tender specifications and other contract / tender documents
are to be taken as mutually explanatory to one another. However, in case of conflict between these
documents, the technical specification, special conditions of the contract and general conditions of
the contract shall have precedence in that order.
54.03 Endorsement of Terms
The failure of either party to endorse at any time any of the provisions of the contract or any rights
in respect thereto or to exercise an option herein provided shall in no way be construed to be a
Page 55 of 56
waiver of such provisions, rights or option or in way to effect the validity of the Contractor. The
exercise by either party of any of his rights here in shall not preclude or prejudice either party from
exercising the same or any other right it may have hereunder.
54.04 Contract Labor Regulation & Abolition
The Contractor shall be responsible for all statutory obligations under Contract Labor (Regulation &
Abolition) Act 1970. E.S.I. and Provident Fund Acts, as applicable, for their labor and staff engaged
in executing this work. The Contractor will also keep the Purchaser indemnified against all claims
and disputes arising out of death or injury to their workmen and staff. It will be necessary for the
contractor to ensure that proper safety measures are followed by their workmen to avoid
accident/damage/loss to life and property. Approved safety belts must be used by their workmen
when working at any height. Charges for above are deemed included in the quoted rates and
accepted amount.
54.05 Recover of Damages
Nothing contained in the conditions or in any other part of this Contract shall be construed as
preventing the Purchaser from the Contractor any damages to which the purchaser may be entitled
in law as a consequence of any breach by the Contractor of any of the terms of this Contract.
Page 56 of 56
ANNEXURE - IV
ADDENDUM TO TENDER DOCUMENT (COMMERCIAL)
1.0
SCOPE
1.1
The subject enquiry is being issued on turnkey basis with entire responsibility of design,
engineering up to Commissioning and handing over of plant / equipment / system to the Owner.
Owner intends to enter into two separate contracts (if placed) as follows to rationalize tax liability as
per legal provision of country and also for operational convenience.
(a)
Basic design, engineering, supply of equipments and materials including all necessary
accessories, Spares at Site
(b)
Unloading, storage, handling of equipments at site, complete Construction, Erection, Testing and
Commissioning services, Supervision and Training Services
1.2
The Contract-cum-Performance Bank Guarantee for 10% of Total Order Value for both the
contracts shall be furnished by the vendor to the Owner.
2.0
PAYMENT TERMS
2.1
(i)
(ii)
(i)
(ii)
(iii)
Balance 10% payment shall be made after final handing over of equipments to the Owner
at site.
Inland Transportation
Charges for inland transportation shall be paid after the equipment is received at Site against
invoices.
(iii)
2.2
Site Work
(i)
90% against monthly progressive billing duly certified by Site In- charge.
(ii)
10% within 30 days of final handing over of the equipment to Owner at site.
Invoices should be submitted along with certificate stating It is certified that Cenvatable/ VAT
Invoices have been issued in the name of consignee, for full amount of Excise Duty/ Sales Tax/
Service Tax charged in the Invoice, as per rules in force. Vendor agrees to reimburse Excise Duty/
Page 1 of 11
Sales Tax/ Service Tax, if documents are not found to be in order for claiming Cenvat/ VAT
benefits.
2.3
NOTE:
(i)
(ii)
Payment for indigenous supply shall be through Bank against dispatch documents. Payment
through bank shall be as per normal banking procedure.
Direct Payment can be made through e-payment mode through SBI as well as NEFT/RTGS mode
through designated enabled branches. In case of Direct Payment, duly filled Bank Mandate form in
duplicate should be furnished with due authentication from bidders Banker
3.0
3.1
All taxes and duties including Excise Duty and concessional CST/ VAT but excluding Sales Tax on
Works Contract will be paid against Documentary Evidence at actuals limited to amount quoted in
price bids. However, statutory variations (on finished products) will be allowed against
documentary evidence. Vendor shall provide break up along with billing schedule subject to ceiling
limit quoted in price bid.
3.2
Service Tax and E-cess applicable should be clearly indicated with ceiling limit to be paid against
documentary evidence and invoice raised in line with Service Tax Rule to enable NALCO to avail
Cenvat.
3.3
Vendors are required to quote prices inclusive of Works Contract Tax and no variation is payable
on this account. In case vendor insists on WCT variation, rate of WCT and amount should be
mentioned in the bid, without which statutory variation will not be admissible.
3.4
It is to be noted that the Contractor shall be required to submit the documentary evidence(s) for
Excise Duty paid by them to concerned authorities for Owner to claim CENVAT benefit.
3.5
Necessary Cenvatable documents such as Transporters copy of Challan / Bill of Entry Triplicate
Copy for availing Cenvat benefit to be given in NALCOs name indicating consignee as NALCO for
availing Excise Duty, Copy of Registration with Central Excise Authority and any other document
required by the Owner shall be furnished by Contractor to enable Owner to claim CENVAT.
3.6
The classification of goods as per Central Excise Customs Tariffs should be correctly done to
ensure that CENVAT benefits is not lost by the Owner on account of any error on the part of the
Contractor. The Owner shall be at liberty to withhold the payment of cenvatable duties (viz. Central
Page 2 of 11
Excise Duties, Countervailing Duties of Customs etc.) If the requirements as specified in the clause
are not fulfilled by the Contractor. The price of materials shall stand reduced accordingly.
3.7
The Contractor shall furnish the details of Excise Duty and CD/CVD component included his price
for the purpose of cenvat benefit.
The amount of ED and CVD indicated as part of Quoted Price is for information only. Contractor is
required to pay all taxes & duties nevertheless and must furnish Cenvatable documents for the
amount of ED and CVD paid by him, subject to minimum of the amount of ED and CVD indicated
by him in his bid.
3.8
Entry Tax shall be paid by NALCO for consignments coming from outside Orissa. For supplies to
be made from Orissa, Entry Tax shall be paid by Seller and should be mentioned in the Invoices for
reimbursement by NALCO.
4.0
INSURANCE
4.1
The Owner will arrange for insurance of equipment and material under the scope of the Contract as
detailed in Tender Documents - Commercial.
4.2
The Contractor shall deal directly with the Insurance Company. The Contractor will be required to
lodge all the claims of his part of the contract directly and arrange settlement as expeditiously as
possible by complying with the required formalities and proper follow ups.
4.3
The contractor shall bear the entire cost of corresponding with the Insurer and arrange all
documents/informations facilitating inspection/discussions by the officials/surveyors deputed by the
Insurer. The Contractor shall make all efforts to get settlement of claim at the earliest and no time
extension for completion of work will be given for delay on this account.
4.4
In respect of equipment damaged in transit or during erection & commissioning, the contractor shall
arrange for replacement/ repair expeditiously. The replacement cost payable by the owner shall be
limited to the invoice cost of damaged equipment. The cost payable for repair shall be mutually
settled.
4.5
Contractor shall be liable solely to adhere to the requirements of the insurer for settlement of
claims without prejudice to the rights of Contractor / NALCO / Insurer. Following steps are listed,
however not exhaustively, for the information of contractor.
(a)
(b)
(c)
(d)
(e)
Page 3 of 11
4.6
(i)
The Contractor agrees to and does hereby accept full and exclusive liability for the compliance with
all obligations imposed by the Employee State Insurance Act 1948 and the Contractor further
agrees to defend, indemnify and hold Owner harmless for any liability or penalty which may be
imposed by the Central, State or Local authority by reasons of any asserted violation by Contractor
or his Sub-contractor of the Employees State Insurance Act, 1948 and also from all claims, suits or
proceeding that may be brought against the Owner arising under, growing out of or by reasons of
the work provided for by this Contractor, whether brought by employees of the contractor, by third
parties or by Central or State Government authority or any political sub-division thereof.
(ii)
The Contractor agrees to fill in with the Employees State Insurance Corporation, the Declaration
forms, and all forms which may be required in respect of the Contractors or his Sub-contractors
employees, who are employed in the WORK provided for or those covered by ESI from time to
time under the Agreement. The Contractor shall deduct and secure the agreement of his subcontractor to deduct the employees contribution as per the first schedule of the Employees State
Insurance Act from wages and affix the Employees Contribution Card at wages payment intervals.
The contractor shall remit and secure the agreement of his sub-contractor to remit the State Bank
of India, Employees State Insurance Corporation account the Employees contribution as required
by the Act. The Contractor agrees to maintain all Cards and Records as required under the Act in
respect of employees and payments and the contractor shall secure the agreement of his subcontractor to maintain such records. Any expenses incurred for the contributions; making
contributions or maintaining records shall be to the Contractors or his Sub-contractors account.
(iii)
Owner shall retain such sum as may be necessary from the total value of contract until the
Contractor shall furnish satisfactory proof that all contributions as required by the Employees State
Insurance Act, 1948 have been paid. This will be pending on the Contractor when the ESI Act is
extended to the place of work.
4.7
4.8
4.9
on the part of the Contractor, his agents, his employees, his representative and Sub-Contractors or
from riots, strikes and civil commotion. This insurance shall cover all the liabilities of the contractor
arising out of the relevant clauses of enquiry documents.
The hazards to be covered will pertain to all the works which and areas where, the Contrctor, his
Sub-Contractors, his agents and his employees have to perform work pursuant to the contract.
The above are only illustrative list of insurance covers normally required and it will be the
responsibility of the contractor to maintain all necessary insurance coverage to the extent both in
time and amount to take care of all his liabilities either direct or indirect, in pursuance of the
contract.
4.10
4.11
5.0
5.1
5.2
Water supply for construction purpose may be provided by the Owner at one mutually
agreed point at Site. Drinking water will also be made available at one central point at
Site. The Contractor shall make his own arrangement for any further distribution. Such
distribution pipe network shall have the prior approval of the Engineer at Site so as not to
Page 5 of 11
interfere with the layout and progress of other construction works. Supply of water shall be
charged from Contractor at the rates prevailing at Site.
Contractor shall ensure that there is no wastage of water. On completion of the work, the
Contractor shall remove all such work and shall reinstate and make good any work
disturbed to the satisfaction of the Engineer.
(b)
5.3
5.4
(i)
(ii)
All construction activities to complete the plant as per the specifications agreed by the
Owner. The activities shall be included but not limited to building structures, rooms,
foundations for equipments and accessories and stack etc.
(iii)
Labor license for contractor and sub-contractors labor if required / applicable as per State
Govt.
5.5
Protection of Work
The contractor shall have total responsibility for protecting his Works till it is finally taken over by
the Owner. No claim will be entertained by the Owner or the Consultant for any damage or loss to
the Contractors Works and the Contractor shall be responsible for the complete restoration of the
damaged works to its original condition to comply with the specifications and drawings. Should any
such damage to the Contractors Works occur because of other party not under his supervision or
control, the Contractor shall make his claim directly with the party concerned. If disagreement or
conflict or dispute develops between the Contractor and the party or parties concerned regarding
the responsibility for damage to the Contractors Works the same shall be resolved as per the
provisions of the clause entitled Co-operation with other Contractors. The Contractor shall not
cause any delay in the repair of such damaged works because of any delay in the resolution of
such disputes. The Contractor shall proceed to repair the work immediately and no cause thereof
will be assigned pending resolution of such dispute.
Page 6 of 11
5.6
Security
The Contractor shall have total responsibility for all equipments and materials in his custody stored,
loose, semi-assembled and / or erected by him at Site. The Contractor shall make suitable security
arrangements including employment of security personnel to ensure the protection of all materials,
equipment and works from theft, fire, pilferage and any other damages and loss. All materials of
the Contractor shall enter and leave the Project Site only with the written permission of the Owner
in the prescribed manner.
Contractors employees shall wear identification badges while on the work at Site.
5.7
5.8
5.9
5.9.1
The Contractor shall be responsible for any damage resulting from his operations. He shall also be
responsible for protection of all persons including members of public and employees of the Owner
and the employees of other Contractors and Sub-Contractors and all public and private property
including structurs, building, other plants and equipments and utilities either above or below the
ground.
5.9.2
The Contractor will ensure provisions of necessary safety equipment such as barriers, sign-boards,
warning lights and lamps, etc. to provide adequate protection to persons and property. The
Contractor shall be responsible to give reasonable notice to the Owner and the Owner of public or
private property and utilities when such property and utilities are likely to get damaged or injured
Page 7 of 11
during the performance of his works and shall make all necessary arrangements with Owners,
related to removal and/or replacement of such property and utilities.
5.10
Painting
All exposed metal parts of the equipment including piping, structures railing, etc. wherever
applicable, after installation unless otherwise surface protected, shall be first painted with at least
one coat of suitable primer which matches the shop primer paint used, after thoroughly cleaning all
such parts of all dirt, rust, scales, greases, oil and other foreign materials by wire brushing,
scraping or sand blasting, and the same being inspected and approved by the Engineer for
painting. Afterwards, the above parts shall be finished with two coats of a alloyed resin machinery
enamel paints. The quality of the finish paint shall be as per the standards of ISI or equivalent and
to be of the colour as approved by the Owner.
5.11
5.12
6.0
CONSTRUCTION
6.1
6.2
Safety
Contractor shall take all necessary measures to protect the work and workmen against accidents
and occupational disease. They shall observe and comply with all Government safety regulations
as specified by the Owner.
Page 8 of 11
The Contractor shall be responsible for following the proper procedures in reporting accidents or
incident.
The Owners Safety Engineer located in Site will be immediately notified by faster means possible
of any accident which involves the following:
(a)
(b)
(c)
(d)
(e)
(f)
6.3
In case of death, the Contractor shall be responsible for immediately notifying the nearest Indian
Police so that they can make the proper investigation in accordance with the law.
7.0
8.0
8.1
The following is to be read along with Clause 44.02:(a) The payment of minimum wages to Contract Labour shall be as per the rates notified by the
central Government as per Minimum Wages Act,1948 and as adopted by the NALCO
Management from time to time plus any additional element and statutory dues thereon.
Page 9 of 11
(b) The Minimum wage as notified by the Chief Labour Commissioner (central) has a variable
component as Special allowance which is linked to average AICPI for Industrial Workers,
which keeps on changing every six months. The Contractor has to absorb all such variations
due to increase in Minimum wage in their quoted price and no claim whatsoever on this
account shall be entertained.
(c) Where the Minimum wages notified by the concerned State Government are higher than the
rates notified by the Central Government, the States Government rates should apply in
concerned scheduled employment as long as the same remains higher than the Central
Government rates.
(d) The classification on workers in different categories will be as per the notification issued by the
Central Government fixing the minimum wages for the above scheduled appointment.
8.2
The classification of workers in different categories will be as per the notification issued by the
Central government fixing the minimum wages for the above scheduled appointment. Where the
minimum wages notified by the concerned State Government are higher than the rates notified by
Central Government, the State Government rates should apply in concerned scheduled
employments.
9.0
GUARANTEE PERIOD
Guarantee Period shall be 12 months from commissioning (including acceptance of
Performance Guarantee Tests) or 24 months from completion of erection, whichever is earlier.
All other provisions of the clause remain unaltered.
10.0
11.0
CONSTRUCTION POWER
Construction power rate indicated in Tender Documents Commercial is modified as As applicable
at Site in place of Rs. 1/- per KWH.
12.0
(i)
Liquidated Damages (LD) wherever mentioned in NIT documents, is to be read as Price Reduction
Schedule (PRS).
(ii)
The Contractors liability for delay shall not in any case exceed five percent of the total contract
price.
All other provisions of these clauses remain unaltered.
Page 10 of 11
13.0
13.1
In partial modification to clause No. - 29 of GCC - Indigenous the last sentence of this clause is
amended as follows:
In the absence of any such modification, the contractor shall bind to carry out the suggested
variations. Any addition or deletion to price will be discussed between purchaser and contractor
and settled.
13.2
Page 11 of 11
ANNEXURE - V
AGREED TERMS & CONDITIONS (INDIGENOUS)
NALCO, SMELTER PLANT
(FOR INDIGENOUS BIDDERS)
IMPORTANT
1.
This questionnaire must be filled in against all Serial nos. & enclosed with the Un-priced offer.
Non submission or submission of incomplete questionnaire may lead to rejection of the offer.
2.
All commercial terms except the deviations to Tender Documents - Commercial (Indigenous),
Addendum to Tender Documents and other attachments of NIT must be given in this
questionnaire itself and not elsewhere in the quotation. In case of contradiction, the terms
given below shall prevail. The deviations to Tender Documents - Commercial (Indigenous),
Addendum to Tender Documents and other attachments of NIT, if any must be listed in a
separate Annexure.
Sl.
No.
Descriptions
Vendors confirmation
with details
(A)
TECHNICAL:
1. (i)
(ii)
2.
3.
4.
Mandatory Spares
Commissioning Spares
Recommended Spares for One Year
normal operation and maintenance
Special Tools & Tackles
Page 1 of 7
Sl.
No.
Descriptions
Vendors confirmation
with details
5.
(i)
(ii)
6.
7.
(a)
(b)
8.
9.
(i)
(ii)
(iii)
Page 2 of 7
Sl.
No.
Descriptions
Vendors confirmation
with details
10(a)
(b)
(c)
(d)
(e)
11.
12.
13.
Page 3 of 7
Sl.
No.
Descriptions
Vendors confirmation
with details
14.
15.
16.
17.
18.
19.
20.
21.
22(i)
(ii)
(iii)
Page 4 of 7
Sl.
No.
Descriptions
Vendors confirmation
with details
23.
25.
26.
27.
28.
29.
30.
31.
32.
Sl.
No.
Descriptions
Vendors confirmation
with details
33.
34.
35.
Signature:
Date:
Name :
Page 6 of 7
Designation
Seal
SL.
NO.
SUBJECT
DEVIATIONS
CLAUSE NO.
NOTE: This shall be submitted along with the Un - priced Offer. Deviation mentioned anywhere else in the
offer shall not be considered.
Signature:
Date:
Name :
Page 7 of 7
Designation
Seal
Annexure - VI
PRICE SCHEDULE FORMAT
ITEM:
1.0
1.1
1.2
1.3
2.0
2.1
2.2
2.3
ERECTION/ TESTING/
COMMISSIONING SERVICES AT
SITE , SUPERVISION & TRAINING
SERVICES (IN INDIAN Rs.)
(M/s .)
3.0
3.1
3.2
3.3
3.4
3.5
3.6
3.7
Page 2 of 7
ERECTION/ TESTING/
COMMISSIONING SERVICES AT
SITE , SUPERVISION & TRAINING
SERVICES (IN INDIAN Rs.)
(M/s .)
UNLOADING,
STORAGE,
HANDLING
&
TRANSPORTATION OF EQUIPMENT/ MATERIALS AT
SITE
For Main Equipment under Sl. No. - 1.0 above
4.2
For One Year O&M Spares under Sl. No. - 3.0 above
4.3
4.4
4.5
4.6
CONSTRUCTION,
ERECTION,
TESTING,
COMMISSIONING AND PERFORMANCE GUARANTEE
TESTS
5.1
5.2
Erection - Mechanical
5.3
5.4
5.5
5.6
Total
for
Construction,
Erection,
Testing,
Commissioning and Performance Guarantee Tests
5.7
5.8
ERECTION/ TESTING/
COMMISSIONING SERVICES AT
SITE , SUPERVISION & TRAINING
SERVICES (IN INDIAN Rs.)
(M/s .)
5.10
5.11
5.12
Others, if any.
ERECTION/ TESTING/
COMMISSIONING SERVICES AT
SITE , SUPERVISION & TRAINING
SERVICES (IN INDIAN Rs.)
(M/s .)
The Price Schedule shall be made available in Un-priced offer also with prices blanked out and written Quoted/ Not Quoted/ Not Applicable, as
the case may be.
2.
3.
The quoted prices shall include charges towards testing & all documentation required as per NIT.
4.
Any correction in the quotation shall be initialed by the bidder, otherwise the offer shall be rejected.
5.
Bidders are required to quote prices inclusive of Works Contract Tax or Orissa VAT on Works Contract and any variation is not payable on this
account. Liability of Works Contract Tax on Erection/ Testing/ Commissioning for Service Contract i.e. Contract C shall be solely of Contractor.
NALCO would deduct WCT in line with NIT provisions while releasing payment to Contractor and deposit the same with Sales Tax Authority and
issue TDS to Contractor from time to time. Contractor will settle WCT directly with the Sales Tax Authority without any liability on the part of
NALCO. Bidders are required to include the WCT into their price, as applicable, and it would be deemed that the same has been taken into
consideration by them, irrespective of whether such WCT amount has been indicated separately or not. Accordingly, there would be no loading (i.e.
there will be no like to like comparison) even if any agency does not indicate such amount or such percentage in their price bid. However, WCT
mentioned in the price schedule by a bidder shall be considered for evaluation of his price.
6.
Applicable Service Tax & E-cess on Service Tax will be paid at actuals subject to documentary evidence limited to the maximum amount quoted.
Page 4 of 7
7.
Entry Tax on supplies against supply of items shall be paid by NALCO directly to Tax authorities.
8.
The sum of quoted prices for relevant divisible package (s) shall be treated as the Contract price(s) for concerned package(s) on lump sum basis.
The contract vis-- vis payment operations shall be done, however, as per approved Billing schedules only.
9.
The Contract (s) prices, will remain firm & unchanged until complete execution excepting for statutory variations, if any on the rates of taxes &
duties included in the Contract price ( as per break ups specified in the Billing schedule) and also excepting for imposition of any fresh statutory
levy/ tax.
10.
In case of award of work, the Contractor has to submit a Billing Schedule for approval of NALCO/RITES. The payment of bills involving Excise duty
shall be made at actuals against submission of Cenvatable ED invoices but limited to the quoted ED & E-cess on ED.
11.
Optional prices shall not be considered for evaluation. However, the optional prices shall be valid during execution of Contract and could be
exercised by NALCO, in case NALCO decides the same.
12.
Supply of spares parts for One Year normal operation and maintenance as per Sl. No. - 3.0 of Price Schedule shall not be considered for
evaluation. However, the prices shall be valid and separate order shall be placed for such spares which are decided by NALCO. Sl. No. - 4.2, 4.5 &
4.6 shall not be considered for evaluation.
Bidder shall submit Price break - up along with quantity and unit price for the Spares for 1 year normal operation and maintenance in priced and un
- priced format.
13.
14.
Bidder shall submit Price break - up along with quantity and unit price for the following in Priced & Un-priced format:
(a)
(b)
(c)
(d)
Mandatory Spares
Commissioning & Start-up Spares
Tools & Tackles
Spares for One Year O&M
Bidders Signature:
Bidders Stamp:
Date:
Page 5 of 7
Unit of
measurement
Lump sum
Quantity
1
Lump sum
03. Design, Manufacture and Supply of Apron feeder (1200 TPH) complete with dribble
conveyor, feeder pans, suitable for underground hopper of tippler complete with drives,
base plates and accessories required for fixing in foundation and other connected
accessories complete.
Lump sum
04. Design, Manufacture and Supply of Receiving belt conveyor system 1200 TPH
guaranteed capacity, 1200 mm belt width suitable for transport of coal received from
apron feeder to existing conveyors BC-103 & BC-115 in plant including pent house,
junction tower complete with stringers, supports, Idlers, Belt, Pulleys, chutes and safety
devices, foundations, supports overhead gallery and trestle etc. with all electricals and
plc control accessories.
05. Design, Manufacture and Supply of Dust control system at Wagon Tippler House,
transfer points of conveyor complete with all civil, mechanical and electricals works.
Lump sum
Lump sum
Lump sum
07. Design and supply of Mono rail hoists of appropriate capacity for equipments, drivers,
pulley and Gear reducers, apron feeder at various location within the terminal points
complete with all accessories.
Lump sum
08. Design and supply of Fire hydrant system covering Wagon Tippler House, Conveyor
Galleries, Transfer House etc. extending from existing fire water grid in the vicinity
within Plant area with all necessary accessories complete.
Lump sum
Page 6 of 7
Unit Price
Description of Item
09. Design and supply of Service water connections at Transfer Towers, tippler house, at
each floor level complete system extending from the existing header near the new track
hopper with all accessories for complete system.
Unit of
measurement
Lump sum
Quantity
1
10. Design and supply of Illumination and lighting system for Wagon Tippler House,
Transfer Towers, Conveyor Galleries and control rooms etc. with all accessories.
Lump sum
11. Design and supply of ACSR cables, rail poles, insulators, hardware fittings, 33KV/6.6KV
transformer complete, breakers, isolators, CT, PT, LA, switch gear, etc. for HT system
as per scope of work.
Lump sum
12. Design and supply of cables, 6.6KV/415V transformer complete, switch gear, panels,
etc. LT system as per scope of work.
Lump sum
13. Supply of all control cables, Panels, PLCs etc. complete for the system.
Lump sum
Page 7 of 7
Unit Price
ANNEXURE - VII
PROFORMA OF CONTRACT CUM PERFORMANCE GUARANTEE BY SELLER/CONTRACTOR
(To be executed on non-Judicial stamped paper of appropriate value)
B.G. No. -
Date:
WHEREAS National Aluminium Company Limited (A Government of India Enterprise), having its Office at
Nalco Bhavan, P/1, Nayapalli, Bhubaneswar - 751 061, Orissa (hereinafter called "the Company/Owner")
which expression shall unless repugnant to the subject or context includes its legal representatives,
successors and assigns), has entered into a contract with M/s. ../ has placed a purchase
order on M/s. (hereinafter referred to as Contractor(s)/Seller(s)) which expression shall
unless repugnant to the subject or context includes their legal representatives, successors and assigns) for
.............................. on the terms and conditions as set out inter alia, in the company Contract No/P.O.
No.............................. dt............. and various documents forming part thereof herein after referred to as the
said contract which expression include all amendments, modification and/or variation thereto and where
as the Contractor/Seller has agreed for due execution of the entire contract and guarantees its performance
including any parts executed through any others agencies/sub-contractors.
AND WHEREAS one of the conditions of the said contract is that contractor/seller shall furnish to the
owner a Bank Guarantee from a bank for ......% (............. percent) of the total value of the said contract
against due and faithful performance of the said contract including defects liability obligations and the
performance guarantee obligations of the contractor/seller for execution/supplies made under the said
contract.
2.
3.
We undertake to pay to the Company any money so demanded not withstanding any dispute or disputes
raised by the Contractor(s)/Supplier(s) in any suit or proceeding pending before any office, court or Tribunal
relating thereto, our liability under this present being absolute and unequivocal. The payment so made by
us under this bond shall be a valid discharge of our liability for payment there under. Our liability to pay is
not dependent or conditional on the owner proceeding against the contractor(s)/seller(s).
4.
The guarantee herein contained shall not be determined or affected or suspended by the liquidation or
winding up, dissolution or change of constitution or insolvency of the said Contractor(s)/ Seller(s) but shall
in all respects and for all purposes be binding and operative until payment of all money due or liabilities
under the said Contract(s)/Order(s) are fulfilled.
Page 1 of 2
5.
We Bank further agree that the guarantee herein contained shall remain in full force
and effect during the period that would be taken for the performance of the said Contract(s)/Order(s) and
that it shall continue to be enforceable till all the dues of the Company under or by virtue of the said
Contract(s)/Order(s) have been fully paid and its claims satisfied or discharged or till a duly authorised
officer of the Company certifies that the terms and conditions of the said Contract(s)/Order(s) have been
fully and properly carried out by the said Contractor(s) and accordingly discharge this guarantee.
6.
We ................................. Bank further agree with the Company that the Company shall have the fullest
liberty without our consent and without affecting in any manner our obligations hereunder to vary any of the
terms and conditions of the said Contractor(s)/ Order(s) or to extend time of performance by the said
Contractor(s)/Seller(s) from time to time or to postpone for any time or from time to time any of the powers
exercisable by the Company against the said Contractor(s)/Seller(s) and to forbear or enforce any of the
terms and conditions relating to the said Contractor(s)/Seller(s) and we shall not be relieved from our
liability by reason of any such variation or extension being granted to the said Contractor(s)/Seller(s) or for
any forbearance, act or omission on the part of the Company or any indulgence by the Company to the said
Contractor(s)/Seller(s) or by any such matter or thing whatsoever which under the law relating to sureties
would but for this provision have effect of so relieving us.
7.
Notwithstanding anything contained herein before, our liability shall not exceed Rs..
(Rupees .. only) and shall remain in force till .. unless a demand or claim under
this guarantee is made on us within three months from the date of expiry we shall be discharged from all
the liabilities under this guarantee.
8.
We Bank, lastly undertake not to revoke this guarantee during its currency except with the
previous consent of the Company in writing. We further undertake to keep this Guarantee renewed from
time to time at the request of Contractor(s)/Seller(s).
Date:
Corporate Seal of the Bank
......................Bank
By its constitutional Attorney
Signature of duly
Authorised person
on behalf of the Bank
With seal & signature code
BG is to be furnished from any of Nalco approved banks, listed as per Annexure - IX.
Page 2 of 2
ANNEXURE - VIII
PROFORMA FOR BANK GUARANTEE FOR EARNEST MONEY DEPOSIT
(To be executed on non-Judicial stamped paper of appropriate value)
B.G. No_____________
Date____________
1.
WHEREAS National Aluminium Company Limited (A Government of India Enterprise), having its
Office at Nalco Bhavan, P/1, Nayapalli, Bhubaneswar - 751 061, Orissa (hereinafter referred as
"The Owner/ Company" which expression shall unless repugnant to the subject or context includes
its legal representatives, successors and assigns), has issued tender paper vide its Tender No.
.............. for................................... (hereinafter called the said tender) to M/s............................
(hereinafter called the said Tenderer(s) which expression shall unless repugnant to the subject or
context includes their legal representatives, successors and assigns) and as per terms and
conditions of the said tender, the tenderer shall submit a Bank Guarantee for Rs.____________
(Rupees ___________________________ Only) towards earnest money in lieu of cash.
2.
3.
We undertake to pay to the Company any money so demanded notwithstanding any dispute or
disputes raised by the tenderer(s) in any suit or proceeding pending before any office, court or
Tribunal relating thereto, our liability under this present guarantee being absolute and unequivocal.
The payment so made by us under this bond shall be a valid discharge of our liability for payment
there under. Our liability to pay is not dependant or conditional on the owner proceeding against
the tenderer(s).
4.
The guarantee herein contained shall not be determined or affected or suspended by the
liquidation or winding up, dissolution or change of constitution or insolvency of the said tenderer(s)
but shall in all respects and for all purposes be binding and operative until payment of all money
due or liabilities under the said tender are fulfilled.
5.
We _________________ Bank Ltd., further agree that the guarantee herein contained shall remain
in full force and effect during the period that would be taken for the finalisation of the said tender
and that it shall continue to be enforceable till the said tender is finally decided and order placed on
Page 1 of 2
the successful tenderer(s) and/or till all the dues of the Company under/or by virtue of the said
tender have been fully paid and its claims satisfied or discharged or till a duly authorised officer of
the Company certifies that the terms and conditions of the said tender have been fully and properly
carried out by the said tenderer(s) and accordingly discharges the guarantee.
6.
That the Owner/Company will have full liberty without reference to us and without affecting this
guarantee to postpone for any time or from time to time, the exercise of any of the power of the
owner under the tender.
7.
Notwithstanding anything contained herein before, our liability shall not exceed Rs.__________
(Rupees________________________________ Only) and shall remain in force till
__________unless a demand or claim under this guarantee is made on us within three months
from the date of expiry, we shall be discharged from all the liability under this guarantee.
8.
We __________________ Bank, lastly undertake not to revoke this guarantee during its currency
except with the previous consent of the Company in writing. We further undertake to keep this
Guarantee renewed from time to time on the request of the Tenderer(s).
Date:
Corporate Seal of the Bank
......................Bank
By its constitutional Attorney
Signature of duly
Authorised person
on behalf of the Bank
With seal & signature code
BG is to be furnished from any of Nalco approved banks, listed as per Annexure - IX.
Page 2 of 2
ANNEXURE - IX
LIST OF STANDARDISED BANKS
SCHEDULED PUBLIC SECTOR BANKS (INDIAN)
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24
Page 1 of 3
Page 2 of 3
:
:
.
3.
Particulars of Bank:
Bank Name
Branch Name
Branch Place
Branch City
Pin Code
Branch Code
MICR No.
(9 Digits code number appearing on the MICR Band of the cheque supplied by the Bank. Please attach Xerox copy of a cheque of
your bank for ensuring accuracy of the bank name, branch name and code number)
Account Type
?
Savings
?
Current
?
Cash Credit
?
Account Number(as appearing in the Cheque
Book)
4.
Page 3 of 3
Annexure - X
Social Accountability 8000 Compliance Format
A.
Basic information
Name of the organization
Address
Telephone No
Name of the Proprietor
Nature of Business
License Number and date of
expiry
Employees
Permanent
Casual
Badli
Temporary
Contracted
B.
Yes/No
Yes/No
Yes/No
Page 1 of 5
___________ Years
Original Copy / Xerox
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Yes/No
Page 2 of 5
Yes/No
Incase of non-performance of any employee, how do you deal with such situations?
Yes/No
Yes/No
Yes/No
How do you ensure that your employees are not discrimination on the basis of cast creed, gender,
religion, age and dieses?
Page 3 of 5
_______ shifts
_______ hours
____________
Yes/No
Rs._______/-
In case, it is yes, what are the general reasons for such deduction?
Page 4 of 5
Yes/No
Yes/No
___________
Yes/No
Yes/No
Yes/No
If yes, what steps you have taken to ensure that they get similar level of protection as afforded to
directly employed employees?
Have you taken care to look into issues related to child labor
Forced labor, health & safety, working hours and remuneration
of your suppliers
Yes/No
We do hereby declare that our organization is committed to social accountability. We will promptly
implement remedial/corrective actions identified against the requirement and promptly inform your
organization. We also declare that the sub contractors/sub suppliers performances are monitored
by us. Moreover, we declare that if invited, we shall participate in awareness program as well as
monitoring program organized by you.
We declare that the above-mentioned information is correct.
Signature:
Designation:
Date
Page 5 of 5
ANNEXURE-XI
PACKING, MARKING, SHIPPING AND DOCUMENTATION
SPECIFICATIONS FOR INDIGENOUS MATERIALS
NALCO
1.0
General
1.1
This specification forms an integral part of the relevant PURCHASE ORDER, in addition to the
specifications, drawings and instructions explicitly listed in the PURCHASE ORDER.
1.2
Seller shall strictly comply with all applicable prescriptions in the specifications. Lack of relevant
information and/or documents shall not absolve the SELLER of his responsibilities and any loss
arising out of non -compliance shall be to suppliers account.
2.0
Project
Name of OWNER, Project location and some other relevant information are as per Bid document.
3.0
Packing
3.1
The packing specifications incorporated herein are supplementary to the internal and external
packing methods and standards as per current rules of IRCA goods tariff Part -I. All packing shall
be done in such a manner so as to reduce volume as much as possible. Fragile articles should
be packed with special packing materials depending on the type of materials.
3.2
Items shipped in bundles must be securely tied with steel wire or strapping. Steel reinforcing
rods, bars, pipes, structural materials, etc. shall be bundled in uniform lengths and the weight
shall be within the breaking strength of the securing wire or strapping.
3.3
All delicate surfaces on equipment/materials should be carefully protected and painted with
protective paint/compound and wrapped to prevent rusting and damage.
3.4
All mechanical and electrical equipment and other heavy articles shall be securely fastened to the
case bottom and shall be blocked and braced to avoid any displacement/shifting during transit.
3.5
Attachments and spare parts of equipment and all small pieces shall be packed separately in
wooden cases with adequate protection inside the case and wherever possible should be sent
along with main equipment. Each item shall be suitably tagged with identification of main
equipment, item denomination and reference number of respective assembly drawing. Each item
of steel structure and equipments shall be identified with two erection markings with minimum
lettering height of 15 mm. Such marking will be followed by connection numbers in indelible
ink/paint. A copy of the packing list shall accompany the material in each package.
3.6
All protrusions shall be suitably protected by providing a cover comprising of tightly bolted
wooden discs on the flanges.
3.7
3.8
Individual cases/bundles must contain the pipes of same size and length.
capped.
Ends should be
Page 1 of 5
3.9
ANNEXURE-XI
Pipes with threaded or flanged ends shall be protected with suitable caps/covers before packing.
Line pipes shall be transported only on Flat bed trailers. Semi low bed/low bed trailer shall not be
used.
The trailers used for transportation of Line Pipes shall be equipped with adequate pipe supports,
having as many round hollow beds as there are pipes to be placed on the bottom of the trailer
bed. Total width of the supports shall be at least 10% of the pipe length. These supports shall be
lined with a rubber protection and shall be spaced in a manner as to support equal load from the
pipes. The rubber protection must be free from all nails and staples where pipes are in contact.
The second layer and the following layers shall be separated from each other with adequate
number of separating layers of protective materials such as straw in plastic covers or mineral
wool strips or equivalent, to avoid direct touch between the coated pipes. All stanchions of
trailers used for transportation shall be covered by non -abrasive material like rubber belts or
equivalent.
Care shall be exercised to properly cover the top of the stanchions and other
positions such as reinforcement of the trailer body rivets etc. to prevent damage to the coated
surface.
3.10
Detailed packing list in waterproof envelope shall be inserted in the package together with
equipment/material. One copy of the detailed packing list shall be fastened outside the package
in waterproof envelope and covered by metal cover.
3.11
The Seller shall be held liable for all damages or breakages to the goods due to the defective or
insufficient packing as well as for corrosion due to insufficient protection.
3.12
Packaged equipment or material showing damage, defects or shortages resulting from improper
packaging material or packing procedures or having concealed damage or shortages, at the time
of unpacking shall be to the sellers account.
4.0
Marking
4.1
Each package shall be marked on three sides with proper paints/indelible waterproof ink as
follows:
OWNER
PROJECT
DESTINATION
Purchase Order No..................................................................................................... Net
Wt......................... Kgs
Gross Wt...................................... Kgs.
Dimensions.......................................................X....................X...........................CM.
Package No. (Sl. No. of total packages).........................................................................
Sellers Name.............................................................................................................
4.2
Additional marking such as HANDLE WITH CARE, THIS SIDE UP, FRAGILE or any other
additional indications for protection and safe handling shall be added depending on the type of
material.
4.3
Specific marking with paint for SLINGING and CENTRE OF GRAVITY should be provided for all
heavy lifts weighing 5 Tons and above.
Page 2 of 5
ANNEXURE-XI
4.4
In case of bundles/bags or other packages, wherever marking cannot be stenciled, the same
shall be embossed on metal or similar tag and wired securely at two convenient points.
5.0
Shipment
5.1
Despatch of materials shall be made in accordance with the relevant terms of the Purchase
Order. Any change in mode of transport shall be resorted to only after prior approval in writing.
Seller shall ensure despatch of equipments/materials immediately after they are inspected and
released. All consignments shall be booked in the name of Owner and not under self-basis.
5.2
Despatch by Road
(a)
(b)
The SELLER shall ensure with Transport Company the delivery of materials within a
reasonable transit period. SELLER shall also obtain from transporter, particulars of Lorry
Number, Transporters Challan Number, destination of lorry (if transshipment is involved),
Transporters Agent at destination, if any, etc. and intimate same to General
Manager (Projects), CPP, Nalco, Angul with copy to Resident Construction Manager at
RITES, (respective Project Site).
5.3
Despatch by Rail
5.3.1
Despatch by the shortest possible route. The Seller shall as far as possible, despatch
the materials by the fastest goods train like QTS, Super Express Goods, etc. wherever
such facilities exist.
(b)
(c)
5.3.2
As SMALLS
When the materials that are ready do not make up a wagonload by weight/volume or for minimum
freight payable for a wagon the despatch should be affected as smalls.
SELLER should obtain from the Railway, the particulars of wagon in which the Smalls have
been loaded, station at which sealed, train Number and date/time of movement and transmit the
same to the Resident / Visiting Inspector, General Manager (Projects), CPP-Nalco , RCM-RITES
(concerned Site) for monitoring their movement.
5.3.3
As Wagon Loads
Consignments, though of lesser weight, but otherwise constituting a wagon load by volume
should be dispatched as wagon load paying the freight applicable to a minimum wagon load or
at the smalls rate, whichever is advantageous, as per Rule-164 of IRCA Goods Tariff Part -I (Vol.I)
When consignments call for full wagon(s), indents should be placed with the Railway Station
concerned after predetermining accurately the type and number of wagons required. In case of
Page 3 of 5
ANNEXURE-XI
covered wagons, it should be ensured that the same are watertight. If a particular type of wagon
is in short supply, request should be made to the Railway Authorities to supply the next suitable
type of wagon. Suitable packing in the wagon shall be done, wherever necessary, to ensure
maximum safety of the material in transit.
When ODC packages are involved, the SELLER shall apply to the Railway Authorities with
loading sketches showing overall dimensions and the wagon proposed to be utilized sufficiently in
advance for obtaining movement sanction and to establish firm transportability. Copies of all
such correspondence together with loading sketches should be sent to NALCO and Consultant
RITES. ODC packages shall be loaded, packed and lashed strictly in accordance with the
Railway Regulations. Should there be any delay/difficulty in obtaining the required wagon(s), the
SELLER shall inform Resident Inspector and General Manager (Projects), CPP-Nalco , RCMRITES immediately giving details of the required number of wagons, type, carrying capacity, etc.
and indent number so that the matter may be taken up with the Railway Authorities concerned.
After despatch, SELLER shall obtain from the Railway Authorities, particulars of the wagon/train
number, date of movement and destination junction for the particular train and furnish the same to
General Manager (Projects), CPP-Nalco , RCM-RITES for follow-up action on movement, as
may be necessary.
After despatch of the equipment from dispatching station, if movement of the wagon is held-up
due to improper/loose lashing resulting in shifting of the load and consignment is required to be
readjusted/refixed the vendor shall be responsible to arrange for the same as per Railway
requirements. Similarly, in case some infringement in dimensions of the loaded consignment is
detected by Railway Authorities after its movement from despatching station and if it is required to
be corrected either by adjustment of the load or by cutting a few protrusions the same shall be
arranged by vendor at their cost.
5.4
Shipment by Air
Wherever SELLER is instructed by OWNER/CONSULTANT to airfreight any material, the
SELLER shall take prompt action for the same. Immediately after air shipment is effected, the
Seller shall intimate by Fax / E-mail, the details of airway bill number and date, flight number,
number of packages etc. to the Resident Inspector, Consultant RITES, General Manager
(Projects), CPP-Nalco , Resident Construction Manager -RITES, (respective Project Site).
5.5
Destination
The consignments should be despatched as indicated in bid document/Purchase Order.
5.6
Advance Information
Immediately after a shipment is made, SELLER shall send advance information as to the
particulars of materials, value, Purchase Order Number, date of despatch, railway receipt
number, wagon number/goods consignment note number, truck number, name of transport
company and their destination office/associates address etc./Airway Bill Number and flight details
by way of Fax / E-Mail to Resident / Visiting Inspector, Consultant RITES, Resident
Construction Manager- RITES, (respective Project Site) and NALCO.
5.7
Page 4 of 5
ANNEXURE-XI
The SELLER shall be responsible for any delay in clearance of the consignment at destination
and consequent wharfage/demurrage, if any, due to delay in transmittal of the Railway Receipt,
Consignment Note/Air Way Bill. Copies of such despatch advise together with 2 copies of
invoices and packing lists shall be simultaneously distributed to OWNERs (HO & Site),
Consultants (HO & Site) etc.
6.0
7.0
--x--
Page 5 of 5