Sunteți pe pagina 1din 6

Pre on-line inspection pigging

by C Kershaw
McAlpine Kershaw

Contents of this Paper:

Introduction

Pipeline proving

Pipeline cleaning

Monitoring during proving and cleaning runs

Planning a pre on-line inspection pigging operation

Specialist pigs

Summary

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

Pipeline Pigging and Integrity Monitoring Conference: Houston, 1989

Introduction
Pre on-line inspection pigging can be defined as any pigging operation carried out prior to running an on-line
inspection tool. Such tools will be inspecting the pipeline for metal loss, generally by the magnetic flux leakage
technique. In order to ensure that the chosen inspection tool will give optimum performance it is vitally important
that the pipeline is properly prepared by the removal of all extraneous matter. Such matter will include all or some
of the following: ferrous debris (welding rods, brushes, spacers, etc.), coarse debris (stones, timber, etc.), fine
debris (silt, sand, mill scale, etc.), wax(hard and soft) and corrosion products.
Where the amount of deposited matter is relatively light, the running of an on-line inspection dummy tool will
often suffice and properly prepare the pipeline for the live tool run. However in situations where heavy deposits
occur it will be necessary to carry out a progressive pigging programme, especially where the pipeline has not
been previously pigged.
Finally, in addition to the removal of extraneous matter, a further consideration is pipeline geometry, since
reductions in pipeline bore due to dents, buckles, heavy-wall fittings and the like could well be detrimental to the
inspection tool. Pipeline geometry is easily ascertained by the running of an internal geometry pig, a topic which
is covered by another author. However it plays a very important part in preparing the pipeline for on-line
inspection, and generally follows or is integrated into the pre on-line inspection pigging programme.
In preparing this paper the author has utilized over 20 years of experience in the proving and cleaning of
pipelines, with sizes ranging from 2in to 48in diameter.

Pipeline proving
In order to effectively clear a pipeline of all extraneous matter, it will be necessary to run steel-bodied pigs fitted
with cups or discs or a combination of both onto which various cleaning devices (brushes, blades, scrapers,
magnets, etc.) can be attached. However it would not be prudent to run such a pig in circumstances where the
pipeline has never been pigged, and so the pipeline must first be proven to be piggable. Obviously pipelines
which have been successfully pigged do not require proving, in which case this section is irrelevant. For the
purpose of this paper, the worst case will be assumed, this being a pipeline which has adequate pigging facilities
but which has never previously been pigged and therefore no knowledge exists regarding the presence of
extraneous matter and reduction in internal bore. Discussed below are the various proving pigs and techniques
which can be used to minimize the risk of a blockage or a stuck pig.
Foam pigs
As an initial approach, and where absolutely nothing is known about the pipeline, it is prudent to run some form
of foam pig, whether it be soft foam (with or without a polyurethane coating) or medium to high density foam
such as a polly pig. As the running of such pigs is a specialist subject covered by another author, it is not intended
here to go into any depth or detail regarding such pigs. However, if the pipeline operator has any doubts about
utilizing a steel-bodied proving pig, then some kind of foam pig is an ideal alternative.
Spheres
Spheres can be considered for initial proving operations, but it is almost impossible to determine any useful
information following a run through a pipeline. This is due to their ability to squeeze through obstructions and
over debris which might well cause a pig to become stuck or damaged. Therefore a successful sphere run cannot
guarantee that the running of a pig will also be successful. However, in many applications a sphere can and will
perform a useful function in the proving of a pipeline.

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

Pre on-line inspection pigging

Proving pig
In the author's experience the most suitable proving pig utilizes a slim steel body fitted with two or four conical
cups, such as the LBCC and SBCC types produced by T D Williamson, although other manufacturers offer
similar alternatives. Apart from the ability to successfully traverse obstructions as severe as 30% to 40% of the
pipeline diameter, the design of the cup also ensures that only light cleaning is carried out due to its conical shape.
It is therefore an ideal cup to fit to the proving pig, with the likelihood of it becoming stuck due to an
accumulation of debris or reduced pipeline bore being extremely low. Further valuable information can be gained
by fitting the proving pig with two or three aluminium gauging plates probably sized to between 75% and 80% of
the internal bore. If the plates are substantially damaged during the first run, then it indicates that all is not well
and further proving runs may well be necessary. If, on the other hand, the plates emerge relatively undamaged,
then it proves that there are no serious obstructions which reduce the bore to below the plate diameter. In such
circumstances the cleaning programme can commence.
During proving operations it may well be that a degree of pipeline cleaning is also being carried out, especially so
in small-diameter lines. If this is the case, it would be prudent to continue running the proving pig until little or no
debris is removed.
Monitoring of proving run
To assist in evaluating the proving run or runs, the author has developed an accurate and sensitive pressuremonitoring system which is described in detail later in the paper. Additionally, in order to deal with the possibility
of a stuck pig, it is advisable to track some or all of the pigs at suitable intervals along the pipeline route and also
to have the ability of accurately locating the position of a pig in the event that it becomes stuck. Both pig tracking
and pig location are covered by another author.

Pipeline cleaning
There are two main types of extraneous matter present in a pipeline, namely ferrous and non-ferrous, with each
requiring a different approach. The author generally favours dealing with the non-ferrous debris first, followed by
the ferrous debris, but this can be reversed or even combined to suit individual situations and requirements. The
main reason for commencing with removal of non-ferrous debris is that ferrous debris removal pigs (generally
referred to as magnetic cleaning pigs) need to be substantially built to support the weight of the magnets and
therefore tend to be very aggressive in their cleaning action. This aggressiveness is totally the opposite of what is
initially required to remove the non-ferrous debris, which is best achieved by adopting a gradual approach. The
reason for this is that it is rarely, if ever, known just how much debris exists in the pipeline. It could vary from as
little as a few pounds to several hundred tons, with the distinct possibility of an extremely aggressive pig
becoming stuck due to a massive accumulation ahead of the it if the quantity is particularly high. Therefore, a
cautious but progressive approach is recommended for the removal of non-ferrous debris, followed by magnetic
cleaning to remove ferrous debris
Pipeline cleaning - non-ferrous debris
Following initial proving of the line utilizing foam pigs and/or LBCC-type cups, the first cleaning run should be
carried out also using conical cups such as the Vantage IV type (produced by T D Williamson) or similar.
Although less flexible than the LBCC cups, they still give a good degree of flexibility, and again will tend not to
remove too much debris which might result in a blockage. It should be noted that Vantage IV cups are not
available in sizes of 14in and below, although alternatives are available.
The first cleaning run should be carried out with a steel-bodied pig fitted with two or four Vantage IV-type cups.
The decision as to whether two or four cups should be fitted will depend on circumstances such as pipeline length,
diameter, aggressiveness, preference and the like. During all cleaning runs it would be prudent to continuously
monitor and record the running pressure behind each pig.

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

Pipeline Pigging and Integrity Monitoring Conference: Houston, 1989

Once the pig has been successfully received, an assessment should be made as to how hard it has had to work,
together with its cleaning performance. For instance, if the cups are particularly worn (especially the front cups) it
could indicate that a high degree of cleaning has been carried out, in which case a re-run should be considered
after having fitted new cups. Additional information will be gleaned from a close examination of the pig receiver
and any filters for signs of debris. If, on the other hand, it is considered that little or no cleaning has been
achieved, then a more aggressive approach is required. This can be achieved initially by fitting two discs, one
ahead of the front cup and one ahead of the back cup. Careful thought should be given when deciding on the
diameter of the disc and the Shore hardness. The author prefers to work up gradually regarding aggressiveness,
with the first discs having an outside diameter equal to (or perhaps just under) the inside diameter of the pipeline
and a hardness of 70 degrees Shore A. The object is to work up to fitting four discs to the pig, each having an OD
equal to the pipe ID plus between 0.25 and 0.50 inches, and a hardness of 90 degrees Shore A. If a cautious
approach is adopted, it might take as many as 10 or even 20 or more pig runs before the most aggressive
combination of cups and discs is reached. However, it is up to the pipeline operator or his advisors to decide how
slowly or quickly aggressiveness should be increased, bearing in mind that an over-aggressive pig in a particularly
dirty line might well become stuck.
At some time during the cleaning operation a change from Vantage IV-type cups to standard cups should be
considered for two reasons. Firstly, the standard cups being of non-conical shape are more efficient in supporting
the pig and cleaning the line, and secondly they are considerably cheaper, especially so on large-diameter pigs.
The precise time to change from Vantage IV cups to standard cups will depend on how the cleaning operation is
progressing. Again, the fitting of aluminium gauging plates of between 90% and 95% of the pipeline internal bore
to the initial cleaning pigs will give valuable information regarding the state of the pipeline in relation to its
internal bore.
The author has found that a combination of cups and hard discs is an extremely effective cleaning tool for the
removal of both loose debris and debris adhering to the pipe wall. However, it is recommended that additional
pipe wall cleaning is carried out at some stage during the cleaning operation by fitting brushes or scrapers to the
pig body; it is likely that such cleaning runs will be carried out towards the end of the cleaning programme. Also
some pipeline operators may prefer to use all-disc pigs (no cups fitted), generally referred to as 'bi-dis' due to their
bi-directional capabilities. However the choice of pigs must be left to the pipeline operator or his advisor.
Pipeline cleaning - ferrous debris
During the cleaning operation to remove non-ferrous debris it is likely, especially in fluid pipelines, that a certain
amount of ferrous debris will be removed. However it is usual to complete cleaning operations by running a
magnetic cleaning pig to lift and hold any remaining ferrous debris and bring it through to the receiver. This is
most important as the presence of ferrous debris, especially welding rods, can be detrimental to a successful online inspection run.
A magnetic cleaning pig in its simplest form will be a standard steel-bodied pig with permanent magnets
positioned around its body. More sophisticated pigs will utilize optimum design magnets which can be adjusted
outwards to put them closer to the pipe wall, thereby increasing their effectiveness. Finally, the addition of
magnetized brushes (similar to those of some on-line inspection tools) at the front and rear of the pig will greatly
improve its cleaning ability, since much of the smaller ferrous debris will be collected and held by the brushes. In
relatively-clean pipelines perhaps two runs will be sufficient to remove all ferrous debris, whereas extremely dirty
lines may take as many as ten or more runs to remove all traces. As a rule of thumb it can be reasonably
considered that a line is clean if two consecutive pigs arrive at the receiver with little or no ferrous debris
attached. To increase cleaning capability, it is worth considering joining two pigs together using a flexible
coupling. A combination of two close-coupled pigs is more efficient than running separate pigs, in that it
considerably reduces pigging time. Furthermore it has been found that two close-coupled pigs are more effective
than two separate pigs.

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

Pre on-line inspection pigging

Monitoring during proving and cleaning runs


As previously mentioned, pig tracking during proving and cleaning operations together with the ability to locate a
stuck pig should be seriously considered. However an additional aid to assessing how the operation is progressing
is to monitor and record running pressure behind the pig. This is best achieved by using a pressure transducer and
strip-chart recorder; a circular clockwork recorder is not suitable. A chart speed of between 6in and 24in per hour
should be selected to give good definition, and it is preferable that the entire pigging run be accommodated on a
single chart. As most charts are around 50ft in length, 6in/hr gives 100 hours of running time and 24in/hr gives 25
hours.
As the purpose of recording the running pressure behind the pig is to enable trends to be assessed, it is likely that
little usable information will be obtained from the first run. However the second and subsequent runs can all be
compared to previous runs to ascertain whether the running pressure is gradually reducing. For instance, the first
chart may indicate a particularly high running pressure due to the presence of high amounts of debris in the line.
Also sudden drops in pressure might be observed where the pig has overrun the debris it was pushing. If, on the
second and subsequent runs, the pressure chart shows a decline in running pressure and fewer sudden drops, it can
be assumed that the cleaning operation is progressing. Once two consecutive runs are identical from a pressure
point of view, it generally indicates that whatever pig was being used is no longer aggressive enough to achieve
useful cleaning. Therefore a more aggressive action, such as the fitting of harder discs, is required. Whilst not an
infallible method of assessing cleaning progress, pressure monitoring is extremely useful in assisting a pipeline
operator during pre on-line inspection pigging.
The author has developed a pressure-monitoring system which works on the back-off technique, where running
pressure behind the pig is electronically processed to produce two outputs to a twin-pen chart recorder (or two
single-pen recorders). The first output is direct pressure which will match the pressure transducer being used (e.g.
0-500psi, 0-1000psi or 0-2000psi, etc.). The second output will be back-off pressure, which is running pressure
plus/minus a preset level; normally a range of +/-50psi is ideal for most applications. The main advantage of the
back-off facility over the direct pressure is that it is far more sensitive and enables even the smallest pressure
fluctuations to be monitored and recorded. Any fluctuations in the running pressure behind the pig (assuming they
do not emanate from the pump or compressor) are due to the pig encountering some form of restriction or
obstruction. This could be of a mechanical nature such as a valve, bend, tee, dent or buckle, or it may be nonmechanical such as debris. If it is debris and the pig is cleaning efficiently, the pressure fluctuations should
eventually disappear over subsequent runs. However mechanical features will remain for all time, since pigging
will not affect them. By careful study of the back-off pressure charts it is usually possible to identify mechanical
features such as valves, tees and forged bends and assume that those pressure fluctuations (if any) remaining
could be due to dents or buckles. This is particularly relevant during the proving runs, and especially if the
gauging plates or even the pig itself is suffering damage, since substantial fluctuation would indicate a significant
reduction in pipeline geometry. In this situation a pipeline operator would probably have to run an internal
geometry pig to accurately assess the situation. It would not be prudent to progress cleaning operations with a
more aggressive pig, as it could become stuck.
It can be seen that pressure monitoring is an extremely useful aid to pigging operations. However in situations
where the input of fluid or gas to the pipeline is particularly erratic, or where pumping is continuously interrupted
due to breakdowns or stoppages, then pressure monitoring and recording becomes less clear. It does rely on flow
into the line being reasonably steady and continuous which is normally the case with most pipeline systems.

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

Pipeline Pigging and Integrity Monitoring Conference: Houston, 1989

Planning a pre on-line inspection pigging operation


It is most important for any pipeline operator who has decided to run an on-line inspection pig for the first time to
give careful thought to the pigging operation to properly prepare the line. The object of pre on-line inspection
pigging is to remove all traces of debris, together with the assessment of reductions in pipeline bore, to ensure that
the running of the live tool will be successful. Furthermore an inspection tool is a very expensive piece of
equipment which is designed to inspect a pipeline and not clean it. Whilst it is often capable of performing an
efficient cleaning function, it is at the expense of reducing its inspection potential or, worse still causing damage,
both of which will necessitate an expensive re-run.
Therefore the pipeline operator must give careful thought to how he is going to achieve a clean pipeline. It may
well be that the line has been regularly pigged and that both internal geometry and cleanliness are assured. In such
cases it may only be necessary to run magnetic cleaning pigs prior to running a dummy tool (provided by the
inspection company) and finally the live tool. On the other hand the line may never have been pigged since
commissioning and could contain large quantities of debris. It must be stressed that pre on-line inspection pigging
operation, if carried out properly, can be very time consuming, and adequate time should therefore be given to
enable the operation to be completed. It is not good engineering practice to rush or curtail an operation simply to
fit in with a pre-chosen inspection date; far better to delay the inspection run or better still give adequate time.
While most pipeline operators will have in-house expertise to plan and execute a pigging programme, some do
not. In this case, expert advice is available from independent consultants who have experience on all types and
sizes of pipeline in many parts of the world. Also pig manufacturers themselves have a lot to offer, although their
expertise can be limited to their own products and they rarely get involved with site operations. Much advice can
be gleaned from the operators of on-line inspection tools, and of course other pipeline operators are usually more
than willing to discuss their own experiences.

Specialist pigs
There will always be situations where a pipeline operator has a unique problem which has to be dealt with on a
one-off basis. This can often be achieved by utilizing purpose-built pigs which may or may not have been
previously used. Such pigs can range from minor improvements to standard pigs to whole new concepts in
pigging technology.
The most notable new pig to emerge in recent times is the pressure by-pass pig developed by the author. It was
specifically developed for pre on-line inspection pigging operations and is used for proving and cleaning. The
front of the pig is fitted with a pressure-relief valve having a diameter of around 40% that of the internal bore of
the line, and the valve is preset to open at a chosen differential pressure. If, during a proving or cleaning run, the
pig builds up a large accumulation of debris ahead of it, the differential pressure across the pig will rise as the pig
begins to work harder. If a non pressure by-pass pig was being used the accumulation of debris ahead of it might
well increase until the pig became stuck or substantially damaged. This cannot happen with a by-pass pig since
once the preset differential pressure is reached the by-pass valve opens thereby by-passing a substantial flow of
fluid or gas through the pig. This results in the debris being jetted or blown away from the front of the pig, after
which time the differential required to run the pig will drop, the by-pass valve will close, and the pig will move
on. This sequence may take place many hundreds of times during a run in a particularly dirty pipeline.

Summary
It is hoped that this paper will give food for thought to pipeline operators contemplating on-line inspection. By
necessity the paper is general in its approach, but the underlying recommendation is to proceed cautiously from an
initial proving run through to the running of an aggressive cleaning pig. Additionally pig tracking, pig location
and pressure monitoring are all recommended to further assist and support the pigging operation. Finally, never
forget that time and money spent in preparation leads to a better chance of achieving a successful on-line
inspection run.

Copyright 2001 Scientific Surveys Ltd. All rights reserved.

S-ar putea să vă placă și