.2 Main feedwater line and main steam line up to the containment anchor point
.21 Piping
.22 Valves and fittings, including isolation, safety and relief valves in
main steam line and feedwater line
.23 Supports (piping related)
.24 Insulation
.3 Pressurizing system
.31 Piping
.32 Valves and fittings
.33 Supports (piping related)
.34 Insulation
.35 Pressurizer
.36 Pressurizer relief tank
.37 Cooling equipment
.38 Pump for pressurizer relief tank
223 Reactor auxiliary systems
.1 Volume control system, seal water supply system for main coolant pumps
.11 Piping
.12 Valves and fittings, control valves with annunciator, and magnetic,
check, isolation and other special valves
.13 Supports (piping related)
.14 Insulation
.15 Charge pumps, including motors, supports, fixtures
.16 Tanks, including supports, fixtures
.2 Boric acid and demineralized water supply system and chemical control
system
.21 Piping
.22 Valves and fittings
.23 Supports (piping related)
.24 Insulation
.25 Pumps, including motors, supports, fixtures
.26 Tanks, including supports, fixtures
.3 Coolant purification system
.31 Piping
.32 Valves and fittings
.33 Supports (piping related)
.34 Insulation
.35 Pumps, including motors, supports, fixtures
.36 Tanks, including supports, fixtures
168
169
.84 Insulation
.85 Pumps, including motors, supports, fixtures
.86 Accumulator, including supports, fixtures
.87 Heat exchanger, including supports, fixtures
.9 Other safety systems
For other reactor types (BWR, PHWR, etc.), the respective auxiliary
systems may be introduced in this account instead of the systems listed
above as an example.
224 Reactor ancillary systems
.1 Liquid waste storage and processing system
.11 Piping
.12 Valves and fittings
.13 Supports (piping related)
.14 Insulation
.15 Pumps, including motors, supports, fixtures
.16 Tanks, including supports, fixtures
.17 Ion exchanger
.18 Heat exchanger, including supports, fixtures
.19 Evaporation columns, filter traps, separators, including supports, fixtures
.2 Gaseous waste processing system
Besides waste gas processing, this system also includes the normal
circulation of inert gas inside the nuclear island water systems.
.21 Piping
.22 Valves and fittings, control valves with annunciator, and magnetic,
check, isolation and other special valves
.23 Supports (piping related)
.24 Insulation
.25 Pumps, compressors, blowers, including motors, supports, fixtures
.26 Tanks for storage, buffering, including supports, fixtures
.27 Heat exchanger, coolers, heaters, including supports, fixtures
.28 Recombiners, dryer columns, activated charcoal beds, cold traps,
silica gel beds, including supports, fixtures
.3 Radioactive waste processing system
(solidification of low and medium level radioactive waste inside the plant)
.31 Piping
.32 Valves and fittings
.33 Supports (piping related)
.34 Insulation
170
.4
.5
.6
.7
171
.2
.3
.4
.5
172
Generator
Water system
H2 system
CO2 system
N2 system
Lubrication system
Seal oil system
Excitation system
Other auxiliary installations
(Support structures, valves, cable connections, etc.)
173
174
175
.2
.3
.4
.5
.6
.7
.8
25
176
.3
.4
.5
.6
.7
.8
.9
177
.3
.4
.5
.6
.7
.8
.9
178
Alarm system
Sprinkler system
Mobile installations
Manually operated and hand-held fire fighting equipment
Hose reels and cabinets
Piping system, including valves, hangers, supports
179
.1
.2
.3
.4
.5
.6
.7
Special materials
Initial supply of special (non-fuel and non-structural) moderator and/or
reflector materials and special heat transfer fluids (other than natural water),
gases or liquids (including reactor coolant, intermediate loop heat transport
fluid and turbine cycle working fluids). Initial supply of oil, lubricants, ion
exchange resins, boric acid, and N2, O2, He and CO2 gases.
271 Reactor coolant (if not under fuel cycle, account 150)
272 Moderator (if not under fuel cycle, account 150)
273 Reflector material
274 Intermediate coolant
275 Turbine cycle working fluids
276 Initial materials
.1 Oil
.2 Lubricants
180
.3
.4
.5
.6
28
Simulators
281 Simulator equipment (if not included in owners costs, account 70)
.1 Instruction unit
.2 Simulation computer (main computer)
.3 Software package
30
181
Engineering, design and layout services provided by the supplier(s) and/or A/E
at the plant site
Engineering activities at the site for design or redesign, updating, introduction
of change orders or licensing requirements, re-planning of systems, etc., should
be calculated or estimated under this account.
182
183
184
Commissioning services provided by the supplier(s) and/or A/E at the plant site
All commissioning services, including startup, performed after completion of
the erection work and up to the commercial operation of the plant should be
listed under this account. Deviations from this definition have to be clearly
stated.
185
.1
.2
.3
.4
.5
.6
371 NSSS or NI
372 BONI
373 TG island
374 BOCI
38
186
382 Buildings and structures (details should be specified under account 21)
.1 Field offices with installations
.2 Social buildings: canteen, hospital or medical service, shops, changing
rooms, laboratories, rest rooms, apartment houses
.3 Warehouses, storage sheds, garages
.4 Workshops
.5 Guard houses, fences
.6 Fire fighting installations or measures taken during construction
383 Provisional installations during construction
.1 Water supply
.2 Gas supply (N2, O2, Ar, CO2, etc.)
.3 Electrical supply for welding machines, temporary erection tools, lighting,
ventilation
.4 Steam supply (steam boiler) with distribution system
.5 Compressed air station with distribution system
.6 Fuel for engines, turbines, boilers
.7 Waste storage and treatment
.8 Communication equipment (telephone, telex, telefax, TV and others)
384 Transportation installations not included in accounts 2127
.1
.2
.3
.4
.5
Harbour crane
Gantry
Unloading equipment
Lorries
Scaffolds, ladders, stairways
391 Materials used during the commissioning period (filters, ion exchanger,
chemicals, oil, lubricants, D2O, Na, He, CO2) and needed before commercial
operation
187
188
Supplementary costs
50
51
Spare parts
52
Contingencies
53
Insurance
189
54
Escalation costs
61
62
Fees
71
72
190
191