Documente Academic
Documente Profesional
Documente Cultură
TRAINING REPORT
ON
STUDENTS NAME:
PRATIK GUPTA
COURSE:
B.E.
BRANCH:
YEAR/ SEM:
COLLEGE:
2ND/4TH
DR. C.V. RAMAN INSTITUTE OF
SCIENCE & TECHNOLOGY, KOTA
INDUSTRIAL NAME:
SUBMITTED BY:
SUBMITTED TO:
PRATIK GUPTA
(EEE 4 TH SEM)
CERTIFICATE
SHALABH SAHRMA
J.P.Patel
Dilip Khalatkar
P.K. DAS
DECLARATION
The training work has been carried out and the
report prepared by me during 20th June to 20th
July 2013 under the guidance of faculties ntpc
ltd/sipat thermal power plant and organised by
employ development centre, human resource
development.
This is the original work carried out by me and
not has been taken from any other sources nor
been submitted to any institute or organisation
as a fulfilment of any other curriculum.
ACKNOWLEDGEMENT
I hereby convey my deep and sincere gratitude in all
humbleness to respected
5. MR. SHALABH SAHRMA
6. MR. J.P.Patel
7. MR. Dilip Khalatkar
8. MR. P.K. DAS
Who provided me with an opportunity to learn under their
gracious guidance, meticulous care and throughout the
training. Their personal supervision and guidance has
enabled me to complete this Project. I also thankfully
acknowledgement the assistance received from MR PRAVIN
PATEL and others for their co-operation during the
preparation of this project report. The project report would
not have been shaped in this form without their
encouragement and guidance.
Contents
1.
Introduction of NTPC
2.
3.
Production of Electricity
4.
5.
6.
7.
8.
9.
10.
11.
12.
D.C. System
13.
Switch Yard
14.
Conclusion
INTRODUCTION OF NTPC
Indias largest power company, NTPC was set up in 1975 to accelerate power
development in India. NTPC is emerging as a diversified power major with
presence in the entire value chain of the power generation business. Apart from
power generation, which is the mainstay of the company, NTPC has already
ventured into consultancy, power trading, ash utilization and coal mining. NTPC
ranked 337th in the 2012, Forbes Global 2000 ranking of the Worlds biggest
companies. NTPC became a Maharatna company in May, 2010, one of the only
four
companies
to
be
awarded
this
status.
The total installed capacity of the company is 41,184 MW (including JVs) with 16
coal based and 7 gas based stations, located across the country. In addition
under JVs, 7 stations are coal based & another station uses naptha/LNG as fuel
and 2 renewable energy projects. The company has set a target to have an
installed power generating capacity of 1,28,000 MW by the year 2032. The
capacity will have a diversified fuel mix comprising 56% coal, 16% Gas, 11%
Nuclear and 17% Renewable Energy Sources(RES) including hydro. By 2032,
non fossil fuel based generation capacity shall make up nearly 28% of NTPCs
portfolio.
NTPC has been operating its plants at high efficiency levels. Although the
company has 17.75% of the total national capacity, it contributes 27.40% of
total power generation due to its focus on high efficiency.
In October 2004, NTPC launched its Initial Public Offering (IPO) consisting of
5.25% as fresh issue and 5.25% as offer for sale by Government of India. NTPC
thus became a listed company in November 2004 with the Government holding
89.5% of the equity share capital. In February 2010, the Shareholding of
Government of India was reduced from 89.5% to 84.5% through Further Public
Offer. The rest is held by Institutional Investors and the Public.
At NTPC, People before Plant Load Factor is the mantra that guides all HR related
policies. NTPC has been awarded No.1, Best Workplace in India among large
organizations and the best PSU for the year 2010, by the Great Places to Work
Institute, India Chapter in collaboration with The Economic Times.
The concept of Corporate Social Responsibility is deeply ingrained in NTPC's
culture. Through its expansive CSR initiatives, NTPC strives to develop mutual
trust with the communities that surround its power stations.
1st
660
2011 June
Running
1st
660
2011 December
Running
1st
660
Running
2nd
500
2007 May
Running
2nd
500
2008 August
Running
Total Five
2980
Sipat
Sipat' is a small developing town, approximately 22 kilometers away from Bilaspur, Chhattisgarh, the
second largest city in Chhattisgarh. It has been in news due to setup of new power plant by NTPC
Limited in that area. The project was started on 2001 by Indian former Prime Minister Mr. Atal Bihari
Vajpayee.NTPC Sipat has total installed capacity of 2980 MW.NTPC Sipat has two stages: Stage-I
comprises 3 units of 660MW each and Stage-II comprises 2 units of 500MW each. The thermal power
generation in NTPC sipat Stage-II is based on "Super Critical Boiler Technology" which is the
advanced technology in thermal power generation. NTPC Limited has helped this town in developing
by providing business prospective in that area and by providing education, healthcare facilities.
PRODUCTION OF ELECTRICITY
feed water which is transformed by the heat into the steam at high pressure
and temperature. The steam super-heated in further tubes (Super Heater) passes
to the turbine where it is discharged through the nozzles on the turbine blades.
Just the energy of the wind turns the sail of the wind-mill, so the energy of the
steam, striking the blades, makes the turbine rotate.
Coupled to the end of the turbine is the rotor of the generator a large
cylindrical magnet, so that when the turbine rotates the rotor turns with it. The
rotor is housed inside the stator having heavy coils of copper bars in which
electricity is produced through the movement of the magnetic field created by
the rotor. The electricity passes from the stator winding to the step-up
transformer which increases its voltage so that it can be transmitted efficiently
over the power lines of the grid.
The steam which has given up its heat energy is changed back into water in the
condenser so that it is ready for re-use. The condenser contains many
kilometres of tubing through which the colder is constantly pumped. The steam
passing around the tubes looses the heat and is rapidly changed back to water.
But the two lots of water (i.e. boiler feed water & cooling water) must NEVER
MIX. The cooling water is drawn from the river, but the boiler feed water must be
absolutely pure, far purer than the water we drink, if it is not to damage the
boiler tubes. Chemistry at the power station is largely the chemistry of water.
To condense the large quantities of steam, huge and continuous volume of
cooling water is essential. In most of the power stations the same water is to be
used over and over again. So the heat which the water extracts from the steam
in the condenser is removed by pumping the water out to the cooling towers.
The cooling towers are simply concrete shells acting as huge chimneys
creating a draught (natural/mechanically assisted by fans) of air. The water is
sprayed out at the top of towers and as it falls into the pond beneath it is cooled
by the upward draught of air. The cold water in the pond is then circulated by
pumps to the condensers. Inevitably, however, some of the water is drawn
upwards as vapours by the draught and it is this which forms the familiar white
clouds which emerge from the towers seen sometimes.
Why bother to change steam from the turbine back into water if it has to be
heated up again immediately? The answer lies in the law of physics which states
that the boiling point of water is related to pressure. The lower the pressure, the
lower the temperature at which water boils. The turbine designer want as low
boiling point of water as possible because he can only utilize the energy of the
steam when the steam changes back into water he can get NO more work out
of it. So a condenser is built, which by rapidly changing the steam back into
water creates a vacuum. This vacuum results in a much lower boiling point
which, in turns, means he can continue getting work out of the steam well below
100 degree Celsius at which it would normally change into water.
energy.
2.
3. BOBR: - Indian Railway grants only 2.5 hours for Unloading 58 BOBR wagons.
This is an advanced technology in which we use the compressor system.
In Bottom Open Bottom Release (BOBR) technology the wagons are opened
from side. Pressure is applied by the compressor to open the bottom gates of
the wagon so that the coal gets released over the track hopper and wagon
get unloaded quickly.
Various equipment used in CHP: 1. WAGON TIPPLER: - The wagon tippler is a most important device in
thermal power project. The Wagon tippler turns back the wagon at 135degree angle and the structure of the wagon tippler is to be very heavy.
Upper side of the wagon is fixed with the many angles for supporting the
wagon. When the wagon is fixed on the Platform then whole platform is
turned back and the coal fall down in the wagon tippler hopper. The unloading
time of the Rack is 6hours
2. PADDLE FEEDER: - They have been installed on conveyors below the
manual
unloading track hopper. There are 6 nos. of paddle feeders, 3 on
each conveyer. 3 Paddle Feeders of each conveyer move to and fro within a
limiting range. The rotating part of the paddle feeder is called as plough
wheel. Plough wheel has 6 blades. By the rotation of the plough wheel, the
coal of the track hopper gets accumulated between the blades and is
discharged on the conveyor below it.
3. VIBRATING FEEDER: They have been installed below the track
hoppers of wagon tippler. The coal is accumulated over the vibrating feeder
so by giving vibrations to the vibrating feeder we discharge the coal from
track hopper to the conveyors. Their main purpose is to provide uniform
feeding on the conveyors. The vibrating feeders consist of a tray to which
vibrator body is fixed on the rear end.
4. TRANSFER POINTS: -Transfer Point is provided with flap gate and Conveyer.
In transfer Point the coal is transferred from one conveyer to other conveyer.
5.
6.
7.
8.
conveyor. Simultaneously, sand bag marker will fall on the conveyor belt so
that the metal can be searched easily and removed.
9.
10.
TRANSFER TOWER: -Here the coal is send to the Tipper. Transfer Tower is
provided with a coal sampler.
11.
12.
BUNKER: - Here the coal is collected from the tipper and stored. The
capacity of the bunker for Stage-I is 4800MT & Stage-II is 8700MT
1.
2.
Carbon filter
Water taken from the river is first sent to the carbon
filter for the removal of carbon contents in the water.
Strong acid cation exchanger
After passing through the carbon
filter, water is sent to the strong acid cation exchanger, which is filled with
the concentrated HCL. The acid produces anions, which get combined with
the cations present in the water.
3.
4.
1.
Bunker
R.C Feeder
Pulverization mill
2.
3.
Ball mail: A ball mill operates normally under suction. A large drum partly
filled with steel balls, is used in this mill .The drum is rotated slowly while
coal is fed in to it .The ball pulverize the coal by crushing.
4.
Contact mail: This mill uses impact principle. All the grinding elements
and the primary air fan are mounted on a single shaft. The flow of air
carries coal to the primary stage where it is reduced to a fine granular
state by impact with a series of hammers.
WATER CYCLE
D.M Plant
Hot well
C.E.P Pump
Low Pressure Heater 1, 2, 3
Derater
Boiler Feed Pump
High Pressure Heater 5, 6
Feed
Regulating station
Economizer
Boiler Drum
1. DERATER: Feed strong tank of water. To produce sufficient pressure before
feeding to B.F.D. .Filter the harmful chemicals.
2. FEED REGULATING STATIONS: Control the quantity of water in to boiler
drum.
3. ECONOMISER: Flux gases coming out of the boilers carry lot of heat. An
economizer extracts a part of this heat from the flue gases and uses it for
heating the feed water.
4.DRAFTS SYSTEM: In forced draft system the fan is installed near the base of
the boiler furnace. This fan forces air through the furnace, economizer, air
preheater and chimney. In an induced draft system, the fan is installed near the
base of Chimney.
STEAM CYCLE
Boiler Drum
Heater
condenser
1.
2.
Ring Header
H.P Turbine
BOILER:
Boiler drum consists two chambers water chamber, steam
chamber. Before Entering in super heater the steam is going in to boiler
drum, where the boiler drum filtered the moisture and stored in to water
chamber.
SUPER HEATER: The function of super heater is to remove the last traces
of moisture from the saturated steam leaving the tube boiler. The
temperature is approx.530 oC.
3.
H.T.SWITCH GEAR
OPERATIONG VOLTAGE - 6.6KV
For low voltage circuits fuses may be used to isolate the faulty circuit. For
voltage higher than 3.3 kV isolation is achieved by circuit breaker.
Requirement of circuit breaker:
1.
2.
After occurrence of fault the switchgears must isolate the faulty circuit as
quickly as possible i.e. keeping the delay to minimum.
It should not operate when an over current flows under healthy condition.
1.
2.
The arc interruption process of air- based circuit breaker is based on the natural
deionization of gases by cooling action. The arc is resilient and can be stretched,
and has a resistance, which can be increased both by length and confinement.
Hence the arc resistance is increased by stretching the arc and as the resistance
increases to higher value, the short circuit current drops to zero and arc is
extinguished.
Reducing the phase difference between the system voltage and the short circuit
current assure that when the are current is interrupt at its zero value, the
recovery voltage has very low value at its not allowed to reach 2-3 times the
value of the system peak voltage, a phenomenon that occurs in most cases,
when arc current is interrupted at low power factor.
1.
2.
247000
Pf
0.85
Volts of stator
15750
Amperes of stator
9050
Volts of rotor
310
Amperes of rotor
2600
Rpm
3000
Hz
50
Phase
Connection
YY
Coolant
Gas pressure
3.5kg/cm-sq.
Insulation class
EXCITATION SYSTEM-
1.
2.
GENERATOR PROTECTION-
1.
2.
3.
4.
5.
6.
7.
TRANSFORMER
TYPE PF TRANSFORMERS
1.
2.
3.
4.
SPECIFICATIONS
Generator transformer (GT-1 & GT-2)
KV
15.75/242
MVA
250
Phase
Hz
50
Connections
Y-D 11
Type of cooling
OFAF/ONAF/ONAN
250/150/100
Rated LV (MVA)
250/150/100
242
15.75
597.14/358.29/238.86
9175.15/5505.09/3670.66
50
55
1150
Phase
Hz
50
Type of cooling
ONAF/ONAN
6600
250
105.9
2655.8
50
55
Potential Transformer
KVA
1000
Phase
Hz
50
Type of Cooling
ONAN
433
87.53
133.5
50
55
D.C SYSTEM
INTRODUCTION:
CHARGING EQUIPMENTS:
The battery charging equipment comprises of trickle charger, quick charger, battery panel, main
distribution board and switch control and signaling board.
CHARGING EQUATION:
In battery PbO2 used as positive plate and Pb as negative plate.
1.
DISCHARGING PROCESS
2.
CHARGING PROCESS
BATTERY CHARGER:
1.
2.
TRICKLE CHARGER:
This charger is fed from three-phase ac supply and gives a dc-stabilized output at rated full load
current. The variation of the dc output voltage is limited to +/- 1% for 0 to 100% load variation and
simultaneously ac voltage variation of +/- 10% of frequency variation of +/- 5% from 50 Hz.
The rectification is obtained through full bridge controlled silicon rectifier. Stack comprising of these
SCR and three diode with the surge suppression RC network connected across each SCR and diode.
SWITCH YARD
As we know that electrical energy cant be stored like cells, so what we generate
should be consumed instantaneously. But as the load is not constants therefore
we generate electricity according to need i.e. the generation depends upon load.
The yard is the places from where the electricity is send outside. It has both
outdoor and indoor equipments.
SINGLE LINE DIAGRAM OF 220KV SWITCH YARD-
OUTDOOR EQUIPMENTS
INDOOR EQUIPMENTS
1.
BUS BAR
2.
LIGHTENING ARRESTER
3.
WAVE TRAP
4.
BREAKER
5.
CAPACITOR
TRANSFORMER
CORONA RING
7.
EARTHING ROD
8.
CURRENT TRANSFORMER
9.
POTENTIAL TRANSFORMER
LIGHTENING MASK
11.
LIGHTENING MOOSE
RELAYS
2.
CONTROL PANELS
VOLTAGE
6.
10.
1.
CIRCUIT BREAKER:
The code for circuit breaker is 52. An electric power system needs some form of switchgear
in order to operate it safely & efficiently under both normal and abnormal conditions.
Circuit breaker is an arrangement by which we can break the circuit or flow of
current. A circuit breaker in station serves the same purpose as switch but it has
many added and complex features. The basic construction of any circuit breaker
requires the separation of contact in an insulating fluid that servers two
functions:
1.
2.
It extinguishes the arc drawn between the contacts when circuit breaker
opens.
It provides adequate insulation between the contacts and from each
contact to earth.
1.
Compressed air
2.
3.
4.
Sulphur hexafluorides
TYPE
RATED VOLTAGE
245 KV
1050 KV
25 - 40KA
50HZ
2000 A TO 4000 A
220 V DC
220 V DC
LIGHTING ARRESTER:
It saves the transformer and reactor from over voltage and over currents. We
have to use the lightning arrester both in primary and secondary of transformer
and in reactors.
A meter is provided which indicates the surface leakage and internal grading
current of arrester.
1.
2.
In case of red we first de-energize the arrester and then do the operation.
S & S POWER
TYPE
MADRAS
VOLTAGE
245 KV
CURRENT
10 KA
415 VOLTS
220 VOLTS
BUS BAR:
Bus bars generally are of high conductive aluminum conforming to IS-5082 or
copper of adequate cross section .Bus bar located in air insulated enclosures
& segregated from all other components .Bus bar is preferably cover with
polyurethane.
1.
.
Current Transformer Diagram
Application:
1.
They are commonly used in metering and protective relaying in the electrical power
industry where they facilitate the safe measurement of large currents, often in the
presence of high voltages.
2.
The current transformer safely isolates measurement and control circuitry from the
high voltages typically present on the circuit being measured.
3.
Current transformers are used extensively for measuring current and monitoring the
operation of the power grid. The CT is typically described by its current ratio from
primary to secondary. Often, multiple CTs are installed as a "stack" for various uses
(for example, protection devices and revenue metering may use separate CTs).
Similarly potential transformers are used for measuring voltage and monitoring the
operation of the power grid.
4.
The device has at least four terminals, a high-voltage terminal for connection
to the high voltage signal, a ground terminal and at least one set of secondary
terminals for connection to the instrumentation or protective relay. CVTs are
typically single-phase devices used for measuring voltages in excess of one
hundred kilovolts where the use of voltage transformers would be uneconomical.
In practice the first capacitor, C1, is often replaced by a stack of capacitors
connected in series.This results in a large voltage drop across the stack of
capacitors that replaced the first capacitor and a comparatively small voltage
drop across the second capacitor C2, and hence the secondary terminals.
Conclusion
On completion of my vocational training at Feroze Gandhi
Unchahar Thermal Power Project, Unchahar I have come to
know about how the very necessity of our lives nowadays i.e.,
electricity is generated. What all processes are needed to
generate and run the plant on a 24x7 basis.
NTPC Unchahar is one the plants in India to be under
highest load factor for the maximum duration of time and that
to operating at highest plant efficiencies. This plant is an