Sunteți pe pagina 1din 8

KERALA STATE ELECTRICITY BOARD

220 KV SUB STATION SUBDIVISION, EDAMON


Replacing damaged 66 KV MOCB pole of the 66KV Ayoor feeder at 220 KV Sub station, Edamon.
DATA SHEET
Sl.
No.

Quantity

Description

Rate
Rs.

Amount
Rs

Demolishing the R.C.C work, having dimensions


250cmX80cmX400cm, upto 50cm from top,
separately stacking the available reinforcement
10 dm3 and clearing away the debris up to a lead of 150m
etc complete as per the direction from dept staff at
site
240.00
Man Mazdoor
7.20
Add 15% extra as per revised SOR 2010 on Rs.
Add 10% CP on Rs. 8.28
Total
Demolishing the R.C.C work at four corner points,
as per drawing, from its center point with
dimensions 250cmx80cmx400cm each for placing
stub bolts after completing item no.4, separately
10 dm3 stacking the available reinforcement and clearing
away the debris up to a lead of 150m etc complete
as per the direction from dept staff at site.

Each

7.20
1.08
0.83
9.11

240.00
Man Mazdoor
Add 15% extra as per revised SOR 2010 on Rs. 7.20
Add 10% CP on Rs. 8.28
Total

Each

7.20
1.08
0.83
9.11

0.03 no.

Per
Unit

0.03 no.

Page 1 of 8

BOARD

EDAMON

r at 220 KV Sub station, Edamon.

Remarks

# Estimates 09 SF6 brks Moozhiyar&Pothencode


# Estimates 09 Replacing ABCB 100MVA

Page 2 of 8

KERALA STATE ELECTRICITY BOARD


220KV SUBSTATION, EDAMON
Details of measurements

Item
No.

Details of works

No

Qty

0.065

#REF!

#REF!

3
#REF!

Demolishing the R.C.C work, having


dimensions 250cmX80cmX400cm, upto
50cm from top, separately stacking the
available reinforcement and clearing away
the debris up to a lead of 150m etc
complete as per the direction from dept
staff at site
Demolishing the R.C.C work at four corner
points, as per drawing, from its center point
with dimensions 250cmx80cmx400cm each
for placing stub bolts after completing item
no.4, separately stacking the available
reinforcement and clearing away the debris
up to a lead of 150m etc complete as per
the direction from dept staff at site.

0.25

0.08

0.5

0.01

0.25

0.08

0.4

0.008

0.25

0.08

0.4

0.008

#REF!
7
#REF!

Reinforcement for RCC work

70 kg/m

Quantity of RCC work


Reinforcement required = 0.032 x 70
Add extra
Total

0.032m3

#REF!
9
#REF!

10

#REF!

Total
Qty

3 Sets

3 Nos

0.065 MT

0.01m3

0.032m3

0.032m3

2.24 Kg
0.76 Kg
3 Kg

1 set

1 set

1 set

KERALA STATE ELECTRICITY BOARD


220 KV SUB STATION SUBDIVISION, EDAMON

Abstract of estimate for replacing damaged 66 KV MOCB pole of 66KV Ayoor feeder at 220 KV
Substation, Edamon.
Sl.
No.

Quantity

Description

Rate
Rs.

Per
Unit

Amount
Rs

Total
Amount
Rs.

3 set

#REF!

#REF!

1 set

#REF!

#REF!

3 nos.

#REF!

#REF!

1 no.

#REF!

#REF!

#REF!

1 MT

#REF!

#REF!

9.11

10 dm3

9.11

#REF!

9.11

10 dm3

29.15

#REF!

#REF!

10 dm3

#REF!

#REF!

#REF!

1 qtl.

#REF!

#REF!

0.065 MT
#REF!

Demolishing the R.C.C work, having


dimensions 250cmX80cmX400cm, upto
50cm from top, separately stacking the
0.01 m3 available reinforcement and clearing away
the debris up to a lead of 150m etc
complete as per the direction from dept
staff at site

0.032 m3

0.032 m3

Demolishing the R.C.C work at four corner


points, as per drawing, from its center point with
dimensions 250cmx80cmx400cm each for
placing stub bolts after completing item no.4,
separately stacking the available reinforcement
and clearing away the debris up to a lead of
150m etc complete as per the direction from
dept staff at site.

#REF!

3 kg
#REF!

Page 7 of 8

1 set

#REF!

1 set

#REF!

#REF!

#REF!

1 set

#REF!

#REF!

#REF!

1 set

#REF!

#REF!

#REF!

1 set
#REF!

10

1 set
#REF!

#REF!

Page 8 of 8

S-ar putea să vă placă și