Sunteți pe pagina 1din 3

64208 Federal Register / Vol. 72, No.

220 / Thursday, November 15, 2007 / Notices

Company, LLC designated as First intervened in the same docket. Protests DEPARTMENT OF ENERGY
Revised Agreement 101. will be considered by the Commission
Filed Date: 10/30/2007. in determining the appropriate action to Federal Energy Regulatory
Accession Number: 20071101–0084. be taken, but will not serve to make Commission
Comment Date: 5 p.m. Eastern Time protestants parties to the proceeding. [Docket No. CP07–447–000]
on Tuesday, November 20, 2007. Anyone filing a motion to intervene or
Docket Numbers: ER08–99–000. protest must serve a copy of that Northern Natural Gas Company; Notice
Applicants: MidAmerican Energy document on the Applicant. In reference of Intent To Prepare an Environmental
Company. to filings initiating a new proceeding, Assessment for the Proposed Ogden
Description: MidAmerican Energy interventions or protests submitted on Compressor Replacement Project and
Company submits an Engineering and or before the comment deadline need Request for Comments on
Procurement Agreement with not be served on persons other than the Environmental Issues
Generation Supply Function of Applicant. November 7, 2007.
MidAmerican (Interconnection
Customer) and the Transmission The Commission encourages The staff of the Federal Energy
Function of MidAmerican. electronic submission of protests and Regulatory Commission (FERC or
Filed Date: 10/30/2007. interventions in lieu of paper, using the Commission) will prepare an
Accession Number: 20071101–0083. FERC Online links at http:// environmental assessment (EA) that will
Comment Date: 5 p.m. Eastern Time www.ferc.gov. To facilitate electronic discuss the environmental impacts of
on Tuesday, November 20, 2007. service, persons with Internet access the Ogden Compressor Replacement
Project involving the abandonment of
Docket Numbers: ER08–100–000. who will eFile a document and/or be
two compressor units by Northern
Applicants: Sempra Energy Trading, listed as a contact for an intervenor
Natural Gas Company (Northern) from
LLC. must create and validate an an existing compressor station in Boone
Description: Sempra Energy Trading, eRegistration account using the County, Iowa, and installation of a
LLC submits a notice of succession that eRegistration link. Select the eFiling compressor unit at an existing
reflects the name change that became link to log on and submit the compressor station within a gas storage
effective 9/30/07 and Fourth Revised intervention or protests. field in Dallas County, Iowa.1 This EA
Rate Schedule 1, et al. will be used by the Commission in its
Persons unable to file electronically
Filed Date: 10/30/2007. decision-making process to determine
Accession Number: 20071101–0082. should submit an original and 14 copies
of the intervention or protest to the whether the project is in the public
Comment Date: 5 p.m. Eastern Time convenience and necessity.
on Tuesday, November 20, 2007. Federal Energy Regulatory Commission,
888 First St NE., Washington, DC 20426. A fact sheet prepared by the FERC
Docket Numbers: ER08–108–000. entitled ‘‘An Interstate Natural Gas
Applicants: Southwest Power Pool, The filings in the above proceedings Facility On My Land? What Do I Need
Inc. are accessible in the Commission’s To Know?’’ was attached to the project
Description: Southwest Power Pool, eLibrary system by clicking on the notice that Northern provided to
Inc. submits revisions to its Open appropriate link in the above list. They landowners with a residence within 1⁄2-
Access Transmission Tariff to reflect are also available for review in the mile of the proposed facilities. This fact
updated of annual values used in Commission’s Public Reference Room in sheet addresses a number of typically
calculation of offer caps for all pivotal Washington, DC. There is an asked questions, including the use of
resources. eSubscription link on the Web site that eminent domain and how to participate
Filed Date: 10/29/2007. enables subscribers to receive e-mail in the Commission’s proceedings. It is
Accession Number: 20071101–0099. notification when a document is added available for viewing on the FERC
Comment Date: 5 p.m. Eastern Time to a subscribed dockets(s). For Internet Web site (http://www.ferc.gov).
on Monday, November 19, 2007. assistance with any FERC Online
Docket Numbers: ER08–109–000. Summary of the Proposed Project
service, please e-mail
Applicants: Midwest Independent FERCOnlineSupport@ferc.gov. or call Northern is proposing to optimize its
Transmission System Operator, Inc. (866) 208–3676 (toll free). For TTY, call ability to transport gas to and from the
Description: Midwest Independent Redfield Gas Storage Field in Dallas
(202) 502–8659.
Transmission System Operator, Inc. County, Iowa by decreasing the amount
submits proposed revisions to its Open Nathaniel J. Davis, Sr., of horsepower (hp) at the Ogden
Access Transmission and Energy Acting Deputy Secretary. Compressor Station (Ogden) in Boone
Markets Tariff on Transition to Auction [FR Doc. E7–22276 Filed 11–14–07; 8:45 am] County, Iowa, and increasing the
Revenue Rights, etc. amount of hp at the Redfield
BILLING CODE 6717–01–P
Filed Date: 10/30/2007. Compressor Station (Redfield) in Dallas
Accession Number: 20071101–0097. County, Iowa. Northern is proposing to
Comment Date: 5 p.m. Eastern Time abandon-in-place two 1,600-hp
on Tuesday, November 20, 2007. horizontal reciprocating compressor
Any person desiring to intervene or to units at Ogden and install one 1,400-hp
protest in any of the above proceedings vertical reciprocating compressor unit at
must file in accordance with Rules 211 Redfield. The location of the project
and 214 of the Commission’s Rules of facilities is shown in Appendix 1.2
Practice and Procedure (18 CFR 385.211
pwalker on PROD1PC71 with NOTICES

and 385.214) on or before 5 p.m. Eastern 1 Northern’s application was filed with the

time on the specified comment date. It Commission under section 7 of the Natural Gas Act.
2 The appendices referenced in this notice are not
is not necessary to separately intervene being printed in the Federal Register. Copies of all
again in a subdocket related to a appendices, other than Appendix 1 (maps), are
compliance filing if you have previously available on the Commission’s Web site at the

VerDate Aug<31>2005 19:50 Nov 14, 2007 Jkt 214001 PO 00000 Frm 00018 Fmt 4703 Sfmt 4703 E:\FR\FM\15NON1.SGM 15NON1
Federal Register / Vol. 72, No. 220 / Thursday, November 15, 2007 / Notices 64209

Land Requirements for Construction this proceeding. A comment period will Intervene should be electronically
Construction of the proposed facilities be allotted for review if the EA is submitted using the Commission’s
would require about 2.1 acres of land published. We will consider all eFiling system at http://www.ferc.gov.
within the existing compressor station comments on the EA before we make Persons without Internet access should
yards. our recommendations to the send an original and 14 copies of their
Commission. motion to the Secretary of the
The EA Process To ensure your comments are Commission at the address indicated
The National Environmental Policy considered, please carefully follow the previously. Persons filing Motions to
Act (NEPA) requires the Commission to instructions in the public participation Intervene on or before the comment
take into account the environmental section below. deadline indicated above must send a
impacts that could result from an action copy of the motion to the Applicant. All
Public Participation
whenever it considers the issuance of a filings, including late interventions,
You can make a difference by submitted after the comment deadline
Certificate of Public Convenience and
providing us with your specific must be served on the Applicant and all
Necessity. NEPA also requires us to
comments or concerns about the project. other intervenors identified on the
discover and address concerns the
By becoming a commentor, your Commission’s service list for this
public may have about proposals. This
concerns will be addressed in the EA proceeding. Persons on the service list
process is referred to as ‘‘scoping’’. The
and considered by the Commission. You with e-mail addresses may be served
main goal of the scoping process is to
should focus on the potential electronically; others must be served a
focus the analysis in the EA on the
environmental effects of the proposal, hard copy of the filing.
important environmental issues. By this
alternatives to the proposal, and Affected landowners and parties with
Notice of Intent, the Commission staff
measures to avoid or lessen environmental concerns may be granted
requests public comments on the scope
environmental impact. The more intervenor status upon showing good
of the issues to address in the EA. All
specific your comments, the more useful cause by stating that they have a clear
comments received are considered
they will be. Please carefully follow and direct interest in this proceeding
during the preparation of the EA. State
these instructions to ensure that your which would not be adequately
and local government representatives
comments are received in time and represented by any other parties. You do
are encouraged to notify their
properly recorded: not need intervenor status to have your
constituents of this proposed action and
• Send an original and two copies of environmental comments considered.
encourage them to comment on their
your letter to: Kimberly D. Bose,
areas of concern. Environmental Mailing List
Secretary, Federal Energy Regulatory
In the EA we 3 will discuss impacts An effort is being made to send this
Commission, 888 First St., NE., Room
that could occur as a result of the notice to all individuals, organizations,
1A, Washington, DC 20426.
construction and operation of the • Label one copy of the comments for and government entities interested in
proposed project under these general the attention of Gas Branch 3. and/or potentially affected by the
headings: • Reference Docket No. CP07–447– proposed project. This includes all
• Geology and soils. 000. landowners who own homes within
• Land use. • Mail your comments so that they distances defined in the Commission’s
• Water resources, fisheries, and will be received in Washington, DC on regulations of certain aboveground
wetlands. or before December 12, 2007. facilities. By this notice we are also
• Cultural resources. The Commission strongly encourages asking governmental agencies,
• Vegetation and wildlife. electronic filing of any comments or especially those in Appendix 2, to
• Air quality and noise.
interventions or protests to this express their interest in becoming
• Endangered and threatened species.
• Hazardous waste. proceeding. See 18 CFR cooperating agencies for the preparation
• Public safety. 385.2001(a)(1)(iii) and the instructions of the EA.
We will also evaluate possible on the Commission’s Web site at
Additional Information
alternatives to the proposed project or http://www.ferc.gov under the
‘‘e-Filing’’ link and the link to the User’s Additional information about the
portions of the project, and make
Guide. Before you can file comments project is available from the
recommendations on how to lessen or
you will need to create a free account Commission’s Office of External Affairs,
avoid impacts on the various resource
which can be created on-line. at 1–866–208–FERC or on the FERC
areas.
We may mail the EA for comment. If Internet Web site (http://www.ferc.gov)
Our independent analysis of the
you are interested in receiving it, please using the eLibrary link. Click on the
issues will be in the EA. Depending on
return the Information Request eLibrary link, click on ‘‘General Search’’
the comments received during the
(Appendix 3). If you do not return the and enter the docket number excluding
scoping process, the EA may be
Information Request, you will be taken the last three digits in the Docket
published and mailed to federal, state,
off the mailing list. Number field. Be sure you have selected
and local agencies, public interest
an appropriate date range. For
groups, interested individuals, affected Becoming an Intervenor assistance, please contact FERC Online
landowners, newspapers, libraries, and In addition to involvement in the EA Support at FercOnlineSupport@ferc.gov
the Commission’s official service list for scoping process, you may want to or toll free at 1–866–208–3676, or for
become an official party to the TTY, contact (202) 502–8659. The
‘‘eLibrary’’ link or from the Commission’s Public
Reference Room, 888 First Street, NE., Washington, proceeding, or ‘‘intervenor’’. To become eLibrary link also provides access to the
DC 20426, or call (202) 502–8371. For instructions an intervenor you must file a motion to texts of formal documents issued by the
pwalker on PROD1PC71 with NOTICES

on connecting to eLibrary refer to the last page of intervene according to Rule 214 of the Commission, such as orders, notices,
this notice. Copies of the appendices were sent to Commission’s Rules of Practice and
all those receiving this notice in the mail.
and rulemakings.
3 ‘‘We’’, ‘‘us’’, and ‘‘our’’ refer to the Procedure (18 CFR 385.214). Intervenors In addition, the Commission now
environmental staff of the Office of Energy Projects have the right to seek rehearing of the offers a free service called eSubscription
(OEP). Commission’s decision. Motions to which allows you to keep track of all

VerDate Aug<31>2005 19:50 Nov 14, 2007 Jkt 214001 PO 00000 Frm 00019 Fmt 4703 Sfmt 4703 E:\FR\FM\15NON1.SGM 15NON1
64210 Federal Register / Vol. 72, No. 220 / Thursday, November 15, 2007 / Notices

formal issuances and submittals in site under the ‘‘e-Filing’’ link. The development applicant desiring to file a
specific dockets. This can reduce the Commission strongly encourages competing development application
amount of time you spend researching electronic filings. Please include the must submit to the Commission, on or
proceedings by automatically providing project number (P–12934–000) on any before a specified comment date for the
you with notification of these filings, comments or motions filed. particular application, either a
document summaries and direct links to The Commission’s Rules of Practice competing development application or a
the documents. Go to http:// and Procedure require all intervenors notice of intent to file such an
www.ferc.gov/esubscribenow.htm. filing documents with the Commission application. Submission of a timely
Finally, public meetings or site visits to serve a copy of that document on notice of intent to file a development
will be posted on the Commission’s each person in the official service list application allows an interested person
calendar located at http://www.ferc.gov/ for the project. Further, if an intervenor to file the competing application no
EventCalendar/EventsList.aspx along files comments or documents with the later than 120 days after the specified
with other related information. Commission relating to the merits of an comment date for the particular
issue that may affect the responsibilities application. A competing license
Kimberly D. Bose, of a particular resource agency, they application must conform to 18 CFR
Secretary. must also serve a copy of the document 4.30 and 4.36.
[FR Doc. E7–22291 Filed 11–14–07; 8:45 am] on that resource agency. p. Notice of Intent—A notice of intent
BILLING CODE 6717–01–P k. Description of Project: The must specify the exact name, business
proposed project would consist of: (1) address, and telephone number of the
5350 proposed 20-kilowatt Free Flow prospective applicant, and must include
DEPARTMENT OF ENERGY generating units having a total installed an unequivocal statement of intent to
capacity of 107-megawatts, (2) a submit, if such an application may be
Federal Energy Regulatory proposed transmission line, and (3) filed, either a preliminary permit
Commission appurtenant facilities. The project application or a development
[Project No. 12934–000; FFP Project 48, would have an average annual application (specify which type of
LLC] generation of 468.66-gigawatt-hours and application). A notice of intent must be
be sold to a local utility. served on the applicant(s) named in this
Notice of Application Accepted for l. Location of Application: A copy of public notice.
Filing and Soliciting Comments, the application is available for q. Proposed Scope of Studies Under
Motions To Intervene, and Protests inspection and reproduction at the Permit—A preliminary permit, if issued,
Commission in the Public Reference does not authorize construction. The
November 6, 2007. Room, located at 888 First Street, NE., term of the proposed preliminary permit
Take notice that the following Room 2A, Washington, DC 20426, or by would be 36 months. The work
hydroelectric applications have been calling (202) 502–8371. This filing may proposed under the preliminary permit
filed with the Commission and are also be viewed on the Commission’s would include economic analysis,
available for public inspection: Web site at http://www.ferc.gov using preparation of preliminary engineering
a. Type of Application: Preliminary the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental
Permit. number excluding the last three digits in impacts. Based on the results of these
b. Project No.: P–12934–000. the docket number field to access the studies, the Applicant would decide
c. Date Filed: August 6, 2007. document. For assistance, call toll-free whether to proceed with the preparation
d. Applicant: FFP Project 48, LLC. 1–866–208–3676 or e-mail of a development application to
e. Name of the Project: New Madrid FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project.
Bend Project. call (202) 502–8659. A copy is also r. Comments, Protests, or Motions to
f. Location: The project would be available for inspection and Intervene—Anyone may submit
located on the Mississippi River in New reproduction at the address in item h comments, a protest, or a motion to
Madrid County, Missouri and Fulton above. intervene in accordance with the
County, Kentucky. The project uses no m. Individuals desiring to be included requirements of Rules of Practice and
dam or impoundment. on the Commission’s mailing list should Procedure, 18 CFR 385.210, 385.211,
g. Filed Pursuant to: Federal Power so indicate by writing to the Secretary 385.214. In determining the appropriate
Act, 16 U.S.C. 791a–825r. of the Commission. action to take, the Commission will
h. Applicants Contact: Mr. Dan Irvin, n. Competing Preliminary Permit— consider all protests or other comments
FFP Project 48, LLC, 69 Bridge Street, Anyone desiring to file a competing filed, but only those who file a motion
Manchester, MA 01944, phone (978) application for preliminary permit for a to intervene in accordance with the
232–3536. proposed project must submit the Commission’s Rules may become a
i. FERC Contact: Patricia W. Gillis, competing application itself, or a notice party to the proceeding. Any comments,
(202) 502–8735. of intent to file such an application, to protests, or motions to intervene must
j. Deadline for filing comments, the Commission on or before the be received on or before the specified
protests, and motions to intervene: 60 specified comment date for the comment date for the particular
days from the issuance date of this particular application (see 18 CFR 4.36). application.
notice. Submission of a timely notice of intent Comments, protests and interventions
All documents (original and eight allows an interested person to file the may be filed electronically via the
copies) should be filed with: Secretary, competing preliminary permit Internet in lieu of paper. See 18 CFR
Federal Energy Regulatory Commission, application no later than 30 days after 385.2001 (a)(1)(iii) and the instructions
888 First Street, NE., Washington, DC the specified comment date for the on the Commission’s Web site at
pwalker on PROD1PC71 with NOTICES

20426. Comments, protests, and particular application. A competing http://www.ferc.gov under the ‘‘e-
interventions may be filed electronically preliminary permit application must Filing’’ link.
via the Internet in lieu of paper; see 18 conform to 18 CFR 4.30 and 4.36. s. Filing and Service of Responsive
CFR 385.2001(a)(1)(iii) and. the o. Competing Development Documents—Any filings must bear in
instructions on the Commission’s Web Application—Any qualified all capital letters the title

VerDate Aug<31>2005 19:50 Nov 14, 2007 Jkt 214001 PO 00000 Frm 00020 Fmt 4703 Sfmt 4703 E:\FR\FM\15NON1.SGM 15NON1

S-ar putea să vă placă și