Documente Academic
Documente Profesional
Documente Cultură
Installation/Ship/Barge/Other:
Location :
RIGGING STRUCTURE
Permit to Work No:
AIMSMTC/BS/001
BS/JHA/001
LIFT PLAN 01
SN-231073-M/CRANE
14.05.2011
13.05.2012
25 TONS
Kgs
3O METRE
Mtrs
2. LOAD DATA
Object to be lifted
Weight of Load
Awkward Shape
CofG
Known,
could
it
change
Certified lifting points
Special rigging required
Special rigging techniques
required
Others
PIPE
1500 KGS
YES
NO*
YES
NO*
YES
YES
YES
NO*
NO*
NO*
20
10
N/A
KGS
KGS
3. RIGGING WEIGHT
Slings
Shackles
Other rigging
4. RIGGING CALCULATION
Description
Object weight (2)
Contingency
Rigging weight (3)
Total weight
Lift height
% of capacity
% safety margin
Weight
1500
N/A
20
1530
4
5%
95%
Units
Kgs
Kgs
Kgs
Kgs
Metre
2. POSSIBLE CONSIDERATIONS
(Tick if relevant and address each point in Step-by-Step section below)
Weight not verified
Lifting of chemicals
Restricted headroom or
confined work area
No lifting point directly above
the load
Appropriate and correctly
installed
Communication requirements
Stability of load
Awkward size/shape/sharp edges
No dedicated lifting points on the load
No certified suspension points for the
lifting equipment
REV1
Yes
NA
Responsible Person
LO
REF
SUPERVISOR
1. Prepare a lifting plan to include all the key element and approved by the supervisor and
PTW approved by OIM
SUPERVISOR
SUPERVISOR/FOREMAN/
TEAMLEADER/ SLINGER
CRANE OPERATOR
4. Pre use check for the Crane assembly, parts by the crane operator
5. Perform operational check for the Crane by the Crane Operator (boom angle, length,
radius, load chart capacity, limit switch etc,)
CRANE OPERATOR
SLINGER
6. Conduct pre use check for 2 pieces of 3 tons wire rope slings
A5 38
SLINGER
SLINGER /BANKSMAN
9. The chocker hitch shall be secured to avoid damage to the wire rope by using a bow
shackles
SLINGER
10. The load shall be attached with 2 taglines placing either direct to the pipe at both end or
at the chocker hitch point by using bowline or clove hitch knots
SLINGER
11. Banksman to communicate to Crane Operator informing that the load is ready to be
lifted
BANKSMAN
12. The Crane Operator shall swing to the direction of the load following the direction of the
banksman
CRANE OPERATOR
13. Banksman to communicate by using hand signal to indicate which type of block to be
used (Used whipline or auxiliary block)
BANKSMAN
14. Banksman to communicate with the Slingers that they are ready for the lift and ensure
everyone is at the correct standing position.
BANKSMAN
15. Banksman to direct the crane operator to lower down the block by using hand signal
(used hoist/block down hand signal)
BANKSMAN
16. Once the block is down at approximately chest level, the banksman shall instruct the
Slinger to attach the wire rope slings to the crane hook
SLINGER /BANKSMAN
17. The banksman then will direct the crane to hoist up slowly until the sling is tension. He
then must confirm that the sling angle and centre of gravity (CoG)
BANKSMAN
18. Once the CoG is confirmed, banksman to instruct the Crane Operator to hoist up the
load at the same time 2 Slingers to control the load using the taglines
SLINGER /BANKSMAN
19. Banksman to direct the crane by hoist up signal until the load is 4 metres high. He then
use boom down and hoist up signal to swing until the load is above point B
BANKSMAN
A8 3.1.4
A5 43
A8 3.1.4
A5 43, 44
A8 3.1.5
A5 42
A8 3.1.5
A5 42
A8 3.1.5
A5 39
A8 2.2.4
A5 39
A8 2.2.4
A5 39
A8 2.2.4
A8 2.2.4
A5 42
A8 2.2.4
A8 3.1.6
A5 39
A8 2.2.4
A5 43 , 39
A5 39
A8 2.2.4
A8 2.2.4
REV1
20. Lower down the load until it properly landed at point B. Slinger to unhook the sling
from the crane hook. Slinger remove the wire rope sling.
SLINGER/BANKSMAN
A5 43
A8 3.1.9
21. Perform post use inspection for all lifting equipment to ensure all are free from defects.
Any faulty equipment found must be reported and recorded
BANKSMAN
A5 44
22. Perform good housekeeping at the work area and send all the equipment back to store.
Defect equipment shall be kept at a quarantine area
SLINGER /BANKSMAN
A5 43 , 44
23. Any waste during the rigging activity must be disposed and segregated as per company
procedures
SLINGER
5. LIFTING EQUIPMENT AND LIFTING ACCESSORIES TO BE USED (Specify type and SWL)
Wire rope slings
Shackle
Type
Type
FWSR
BOW
Capacity
Capacity
3T
3.75 T
Quantity
Quantity
2 pcs
2 pcs
Weight
Weight
20 kg
10 kg
01
01
02
02
6. 2 wooden blocks
02
7. Taglines
02
8. Briefing area
01
9. Safety glass
12 pieces
12 pairs
12 pairs
12. Coverall
12 pairs
03 pair
Routine
Non-Routine
Lift plans shall be written by rigging supervisor and approved by person in charge (PIC) of the lifting
operation.
Lift plans shall be written by an approved lift planner and approved by T.A.
7. PERSONNEL
Personnel
Crane Operator
Banksman
Slinger
Name
01
01
02
Signature
Date
8. APPROVALS
Name
Signature
Date
REV1
REV1