Documente Academic
Documente Profesional
Documente Cultură
RING ROAD
Innovative approaches and techniques
On May 31, 1969 the Ring Road R1 around the city of Antwerp was
opened to traffic. The R1 is an urban motorway located at
approximately 3 km from the centre of the city. The 14 km long ring
road comprises the J.F. Kennedy tunnel in the southwest and the
Merksem viaduct in the northeast. Several fully directional
interchanges provide the link with 6 radial motorways tying into the
R1. Due to the vicinity of the ring with regard to the city centre local
access and exit ramps are provided as well.
38
T HE A NTWERP
RING ROAD
In addition to the pure technical works, a lot of attention also was paid
to the establishment of an ambitious programme of Less
Disturbance measures in and around Antwerp and to a maximum
recycling of the broken up materials, in favour of the environment.
This comprehensive approach made it possible to execute the works in
a record period of two times approximately five months.
The original pavement on the motorway consisted of asphalt on a base
of lean concrete or unbound coarse aggregates. After a thorough
comparative study of the different alternatives, the main part of the
existing pavement was replaced with a new pavement structure
consisting of 23 cm continuously reinforced concrete (CRCP) supported
by a 5 cm thick bituminous asphalt inter-layer, 25 cm of cement
stabilised asphalt rubble and 15 cm recycled crushed lean concrete. A
fine textured exposed aggregate concrete surface was applied in order
to obtain an excellent skid resistance combined with a reduction of the
rolling noise.
The original pavement in concrete slabs in the Kennedy Tunnel was
replaced with a new pavement of the same type with a similar
foundation as for the CRCP
The innovative techniques that have been used during the realisation
of this ambitious project will undoubtedly contribute to a further
development of CRCP in Belgium and other countries.
The largest number of lanes occurs in the weaving sections of the exits
and entrances of the interchanges. In an attempt to accommodate the
ever-increasing traffic flows the R1 was widened in certain areas. This
is the reason why at present no shoulders are available along certain
parts.
Where compatible with the geometry a crowned cross section is
applied in order to ensure an adequate surface run-off. The minimum
cross slope is 2.5%. Where geometrically required a superelevation is
introduced.
On the interchanges the number of traffic lanes varies from 1 to 2. The
Kennedy Tunnel consists of 3 lanes in each direction.
The changing number of lanes has a considerable impact on the design
of the CRC pavement.
Given the fact that the natural ground water level varied between 2
and 4 m below the natural terrain level, an extensive and permanent
sub-surface drainage system was realised in order to ensure that the
groundwater level in the wide open cut is lowered well below the sub
grade of the ring road pavement. This drainage system along with the
storm water network has a total length of around 170 km.
39
40
T HE A NTWERP
RING ROAD
Considering the large scale of the project and taking into account the
international importance of this transport facility the technical study
was started by an extensive testing programme.
A visual inspection
41
42
This well studied and well planned investment will not only yield an
economic profit on the long term but will also result in less disturbance
of traffic and of the environment.
T HE A NTWERP
RING ROAD
2.5 Recycling
It was a major purpose of the rehabilitation project to apply recycling
of broken-up materials to the maximum possible. This was a logical
consequence of the very large quantities of broken-up and recyclable
materials, of the envisaged short construction period, and last but not
least, of the decision not to create additional traffic flows by hauling
broken-up materials and by supplying new materials.
Due to these circumstances a detailed study was made of the
opportunities for recycling. The envisaged service lifetime of the new
pavement structure, the very large quantities of recyclable materials
and the experiences in Belgium and abroad were taken into account in
this study.
Recycling in itself is not new but the large scale that was at stake was
new and unique in Belgium.
As a result of the recycling study the existing asphalt pavement was
recycled
The existing road base, which mainly consisted of lean concrete and
locally of coarse aggregate, was broken-up and recycled in the
granular new sub-base.
2.5.1 Recycling of the existing asphalt pavement in cement bound asphalt
rubble
There is a growing interest in the use of asphalt rubble as aggregate in
a cement treated base and some applications were already
implemented in the Netherlands, France, Germany and the United
States, mostly with satisfying results. The Belgian experiences with this
type of base layer cement bound asphalt rubble (CBAR) are rather
limited, however, the principle is well known.
The product consists of a homogeneous mix of sand, aggregates (in
this case asphalt rubble), batching water and a binder. Belgian
standard specifications only provide cement as a binder for the use in
base layers. A cement content of 4% (of the dry mass) allows achieving
the required compressive strength of 3 MPa after 7 days. After 28 days,
the compressive strength must reach 5 MPa.
For the R1 project, the use of a mixing plant was compulsory.
Adding about 15 to 20 % of sand to the crushed asphalt rubble is
mostly necessary in order to obtain a continuous grading of the
mixture and a maximum density of the base layer after compaction.
The material requirements of asphalt rubble for bases are less strict
than for warm reuse in bituminous mixtures. Homogeneity is less
crucial and more concrete rubble is allowed in the mix.
A CBAR base is in general comparable to a hydraulically bound
aggregate base concerning strength development and Young's
modulus of elasticity. However, the presence of a bituminous mortar
yields, to some extent, a temperature-dependent visco-elastic
behaviour, positively influencing the flexibility of the layer.
43
From this the Pavement Class and the corresponding slab thickness
design are derived. The main variables in the method concern the CBRvalue of the sub grade, the lane distribution factor, the traffic volume
and the percentage of heavy trucks (up to 25 % for the R1), the design
speed and the design period.
The stone grading to be used is 4/7, 7/14 and 14/20 mm. The
amount of 4/7 aggregate has to be at least 20% of the total
granular mix (sand and coarse aggregate). The percentage of sand
was kept as low as possible for as far compatible with an adequate
workability.
44
T HE A NTWERP
RING ROAD
The edge effect in the outer traffic lane can also be avoided by
executing the shoulder pavement in concrete as well.
On the R1 the latter solution has been adopted with the exception of
a few isolated areas where a narrow shoulder was paved in asphalt. In
these areas the CRCP on the mainline was executed with an extra
width of 0.70 m (including the edge striping).
45
46
The lugs are realized by excavating their shape in the sub grade and by
placing the reinforcement and the concrete without the use of any
side forms.
2.11.3 Terminal joints
Unlike an end anchorage treatment terminal joints allow the free
movement of the ends of the concrete. Figure 8 shows the details of
the terminal joint designed for the R1 project. This design is an
improvement of a formerly applied concept in Willebroek, Belgium.
T HE A NTWERP
RING ROAD
Considering the fact that in Belgium the use of the terminal joint type
treatment is rather new, a monitoring programme is set up and started
in order to record the movements and behaviour of the joint under
varying climatic conditions and traffic circumstances.
As opposed to the terminal treatment of the CRCP on the main lanes
one has no choice regarding the type of treatment of the ends of the
CRCP of the auxiliary lanes. Indeed, it is necessary that the behaviour
of the CRCP on the auxiliary lanes be as much as possible the same as
that of the adjoining CRCP on the mainline.
As the CRCP of the main lanes is not subjected to longitudinal cyclic
movements at the location of the intermediate auxiliary lanes, it was
necessary to utilize anchorage abutments to restrain their ends. The
number of transverse lugs was designed so that the residual
movement was limited to 4 mm. This was considered acceptable and
resulted in terminal anchor abutments having 4 lugs each. (This
solution is shown on Figures 2, 5, 6, and 7.)
In addition to these anchor abutments the doubling of the number of
tie bars in the longitudinal joints between the mainline CRCP and the
CRCP on the entrance and exit lanes helps to avoid opening up of
these joints.
Dimensions of the
anchoring abutment
47
3. Construction
48
T HE A NTWERP
RING ROAD
Phased construction : overview of the different phases of concreting in the first(2004) and the second (2005) period
grade traffic was detoured over the new CRCP and only then the
slipform paver was moved to the next section where the same casting
phasing was applied (e.g. 4, 5, 6). This method resulted in only one
transverse construction joint per leave-out. In order to further reduce
the number of transverse joints the contractor eliminated the end of
the day transverse construction joints by executing the paving works in
a continuous operation 24 hours a day. This adapted method of
execution of the CRCP has proven to entail a better pavement surface
finish.
For the outer ring the new CRCP was executed such that each
subsequent casting width (e.g. 1, 2, 3) was executed over the full
length of the mainline pavement before the next casting width (e.g. 4,
5, 6) was placed. After having completed in such a way the new CRCP
over its full width the at grade traffic at the leave-outs was
subsequently detoured over the new CRCP followed by the paving of
the leave-outs. This phasing of the placement of the CRCP made it
necessary to temporarily terminate the CRCP by two transverse
construction joints, one at each end of the leave-out. Other transverse
construction joints in between were end of the day construction joints.
During the paving works for the inner ring, the contactor adapted the
phasing of the CRCP and the working hours so that the number of
transverse construction joints, which are always delicate zones in the
finished pavement, was reduced to the minimum attainable under the
given circumstances. In between two consecutive leave-outs the CRCP
was first placed over its full width (e.g. 1, 2, 3). Subsequently the at
49
Closer view of the insulating sand layer to prevent the movement at the end of the CRCP
50
T HE A NTWERP
RING ROAD
Open bin trucks were used to transport the concrete from the site
plants to the paver. Tarpaulins are required upon warm weather
conditions.
After application of the surface retarder, the concrete is protected
against drying out or rain by means of a plastic sheet. The next day the
surface mortar layer is washed out. Subsequently the longitudinal
joints are saw cut and chamfered. Then the joint sealant is placed.
The concrete is finally protected against drying by application of a
curing compound.
51
View of the slipform paver and the extra manual vibration of the concrete along
the edges
52
T HE A NTWERP
RING ROAD
53
54
Because of the very intense and heavy traffic on the R1, concrete safety
barriers of the American type F were opted for. This type of barriers
had earlier been constructed in Belgium on the motorway A10 (E40)
between Groot-Bijgaarden en Affligem. The F barrier exists in a high
(H = 1,07 m) and in a low (H = 0,81 m) version. For the R1 the high type
F was applied because of the following two major advantages:
T HE A NTWERP
RING ROAD
In the USA, the F-barrier has been tested according to the NCHRP
Report 350 (National Cooperative Highway Research Program).
According to these testing criteria, this barrier meets Test Level 5,
corresponding to the following crash tests:
55
Delta-bloc of H4b containment level installed on a bridge (siegtal bridge in Siegen, Germany)
56
T HE A NTWERP
RING ROAD
5. Conclusions
The rehabilitation works of the outer Ring of Antwerp have been
successful both in the technical field and in the field of traffic
alleviating measures. This pioneering experience will certainly be
useful for the inner Ring and for the future comparable rehabilitation
project.
On the pure technical level, very useful experience has been gained
with the large-scale execution of CRCP with variable widths. The same
applies to the design and construction of a new type terminal joint
accommodating the movement of the CRCP ends.
One advantage of this project consisted of the fact that it was split-up
into two construction periods, spread over two years and each of
which comprised comparable types and amounts of works. This
enabled both the owner and the contractor to improve the execution
methods and the quality of the works. The findings in the design and
execution of this ambitious project will certainly contribute to the
further development of the CRCP technique in Belgium and elsewhere.
Last but not least the experience with the rehabilitation of the
pavement of the busy Antwerp Ring Road has proven that a high
quality of CRCP can be obtained under difficult circumstances provided
that the phasing and important details of construction are well studied
beforehand and are continuously monitored during construction.
PARTIES INVOLVED
The successful achievement of this challenging rehabilitation
required an intense co-operation between all different parties
involved. In the first place, there is the public authority: the Ministry
of the Flemish Community represented by the ROADS AND TRAFFICS
DIVISION OF ANTWERP (since 2006 depending from the
Infrastructure Agency of the Department Mobility and Transport).
During the study and design phase a project group was created
consisting of experts in different techniques coming from the Road
Administration (local and central services) , from the BELGIAN ROAD
RESEARCH CENTRE (BRRC) and from the multi-disciplinary
engineering company TECHNUM, the latter also being in charge of
the Design and Tender Documents.
During the execution TECHNUM was in charge of the review and
approval of the construction drawings and rendered technical
assistance to the Road Authorities.
57
LESS DISTURBANCE
The greatest challenge of the R1's rehabilitation - even more than
the aim to find the best technical solutions - was to make these
works possible on a traffic artery carrying at some locations up to
200.000 vehicles a day. That's why many people feared total traffic
chaos and the Antwerp business community was extremely worried
when experts had predicted an economic loss of 900 million euro.
58
T HE A NTWERP
RING ROAD
How it ended
Before their start, the rehabilitation works were totally unacceptable
for a lot of people: the economic life in Antwerp would be paralysed
and the city tourism would be reduced to zero. An effort and
investment, never seen before, in accompanying alleviating
measures and communications made it turn out differently. The
nuisance due to the works was accepted and was most of the time
predictable. The business community appreciated the way the works
were performed and thanked the organisers. The population also
has shown its satisfaction.
Effective management from the beginning of the project with
application of concrete measures, good preparation and active
communication show that works on major road systems can be
performed with a relatively slight impact on all parties.
Text based on the article Accompanying measures for rehabilitation
of the Antwerp ring road by Griet Somers, Accessibility Manager,
Less Disturbance Contact Point, Flanders Region, Belgium & Patrick
Debaere, Project Leader, Ministry of the Flemish Community,
Belgium, in the PIARC-magazine ROUTES-ROADS, n 329, 2006.
Co-operation
federations.
with
national
and
international
transport
59
60
T HE A NTWERP
RING ROAD
BIBLIOGRAPHY
1. F. Fuchs (OCW) and A. Jasienski (Febelcem). (1997). punch-out
op Belgische autosnelwegen van doorgaand gewapend beton,
Brussel. (punch out on the Belgian Motorways of CRCP, Brussels)
2. Ir L. Hendrickx. (1998). Geluidsarme betonverhardingen, Brussel.
(Noiseless Concrete Pavements, Brussels)
3. H. Sommer Developments for the exposed aggregate technique
in Austria
4. Ing. M.J.A. Stet. (2003), Betonverhardingen, (Concrete
pavements) Reed Business Information bv, Doetinchem.
5. H. Stinglhammer / H. Krenn. Noise reducing exposed aggregate
surfaces experience and recommendations
6. Federal Highway Administration. (1990). Continuously reinforced
concrete pavement (T 5080.14 & T 5040.29), Washington DC (USA).
7. Studiecentrum Technische Ingenieurs. (1976). Wegenbouw
specialisatiekursus Deel II Cementbetonwegen, Antwerpen. (Study
Centre for Engineers, 1976, Road Construction - Post Graduate
Course, Part II, Cement Concrete Roads)
8. Ministerie van openbare werken Bestuur der wegen. Doorlopend
gewapende betonwegen in Belgi Deel IV eindvoegen en
verankeringen. (Ministry of Public Works, Administration of Roads.
CRCP in Belgium, Part IV terminal joints and anchorages)
9. Ministerie van Vlaamse Gemeenschap departement Leefmilieu
en Infrastructuur. (2000). Standaardbestek 250 voor de
wegenbouw, versie 2.0, Brussel. (Ministry of the Flemish
Community, Department Environment and Infrastructure, 2000,
Standard Specifications 250 for road construction, edition 2.0,
Brussels)
10. Ministerie van de Vlaamse Gemeenschap. Wegstructuren,
Dimensionering en Keuze van de verharding, Brussel. (Ministry of
the Flemish Community, Road Structures, Design and Choice of the
pavement, Brussels.)
11. Cold in-place recycling of pavements with cement, Association
Mondial de la Route - AIPCR World Road Association - PIARC.
August 2002
12. Stabilisatie van afbraakmateriaal van bitumineuze deklagen
met cement, Nationaal centrum voor wetenschappelijk en
technisch onderzoek der cementnijverheid Brussel. (Cement
stabilization of broken up material from bituminous pavements,
National centre for scientific and technical research of the cement
industry, Brussels)
61
Pictures :
Ministry of the Flemish Community, Contractor Van Broekhoven-Van
Gorp-Wegebo, Manu Diependaele, Ken Moons, Omnibeton & Delta
Bloc Europe GmbH, Paul Van Audenhove
Authors :
Manu Diependaele & Dries De Groof,
Technum Engineering Company
Luc Rens, FEBELCEM0