Documente Academic
Documente Profesional
Documente Cultură
LOCATION
DATE
ELECTRICAL WORKS
OFF DOCK , FELICIANO , DICT
APRIL 8 , 2014
PROGR
Item
I.
II.
III.
IV.
Scope of Works
HIGH-TENSION LINES /PRIMARY METERING
1 Concrete pole and accessories
2 Metering Components/ service entrance
3 Recloser Installation
4 3-100 kva transformer Installation / 220v
Relative
Weight
1-5
6-12
13-19
20-26
27-3
4-10
May
11-17
18-24
1.65%
0.26%
2.47%
0.59%
0.41%
23.75%
2.89%
0.73%
2.89%
SECONDARY LOAD
1 Excavation of secondary lines
2 lay-out / installation of secondary pipes
3 lay-out / installtion of wires
4 MDP installation / termination
5 Reefer rack panel installation / termination
6 Lighting installation / 220v
0.43%
0.71%
45.74%
8.13%
3.28%
0.34%
April
1.70%
0.60%
3.42%
0.05%
0.05%
0.09%
0.05%
0.09%
0.07%
0.07%
0.07%
0.07%
0.07%
0.05%
0.09%
0.05%
0.09%
0.05%
0.09%
0.05%
0.09%
0.05%
0.09%
0.05%
ACCOMPLISHMENT, CASH
FLOWS, AND SLIPPAGE
PREPARED BY:
A.F.. COLINA
PROJECT MANAGER
0.14%
0.14%
0.21%
0.21%
0.21%
0.21%
0.21%
100.0%
0.05%
0.14%
0.14%
0.21%
0.21%
0.21%
0.20%
0.55%
0.97%
15,625.0 41,392.5 41,392.5 61,392.5 61,392.50 61,392.5
57,017.50
159,802.50
282,587.50
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
NOTED BY:
R. PAMPOSA
TADECO ENG'G-SUPERVISOR
#REF!
0.21%
0.21%
1.40%
61,392.5
61,392.50
405,372.50
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
RECOMMENDING APPROVAL :
R.A. TAN
AVP - ENGINEERING
PROGRAM OF WORKS
June
25-31
0.83%
1-8
9-15
16-22
23-29
30-6
July
7-13
14-20
20-26
27-2
0.83%
0.09%
0.09%
1.23%
0.59%
0.09%
1.23%
0.07%
7.92%
1.45%
0.72%
1.45%
0.37%
0.72%
7.92%
7.92%
1.16%
0.41%
0.05%
0.37%
0.72%
0.72%
11.43%
1.16%
0.41%
0.05%
11.43%
1.16%
0.41%
0.05%
1.16%
0.41%
0.05%
0.15%
1.14%
0.15%
0.15%
0.09%
11.43%
1.16%
0.57%
0.57%
1.14%
11.43%
1.16%
0.41%
0.57%
0.15%
1.14%
1.16%
0.41%
0.05%
0.41%
0.05%
0.41%
0.05%
1.55%
17.30%
17.49%
17.34%
1.55%
17.30%
17.49%
17.34%
20.25%
55.08%
450,301.2 5,022,548.4 5,076,314 5,034,560.62
5,878,222.09
15,989,097.05
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
APPROVED BY:
B.B. LICAYAN
SENIOR VP -SVTBSI
23.16%
9.69%
23.16%
9.69%
87.93%
###
2,811,978.2
25,525,446.29
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
9.54%
1.62%
9.54%
1.62%
99.08%
###
470,308.20
28,764,332.66
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
0.46%
0.46%
0.46%
0.46%
100.00%
133,101 133,101
29,030,535.09
#REF!
#REF!
#REF!
PROJECT
LOCATION
DATE
SUBJECT
Item
Scope of Works
I.
POWERHOUSE / METERING
1
Temporary Facilities
2
Transfer Switch / reclosers / primary metering
3
Powerhouse electrical , 220v
4
Genset Panel & Accessories
5
Synchronizing panel system
6
5 MVA Power Transformer
7
Pole line hardwares , arresters
8
Genset / Breakers termination
9
Grounding system
II.
III.
1,971,634.00
343,158.00
940,000.00
2,677,800.00
6,258,607.00
262,573.00
196,200.00
9,260.00
HI-TENSION LINES
1
Pole Construction & dressing
2
ACSR wire installation
3
Grounding System
4
Reclosers & accessories
5
Transformer Pad , pedestal & accessories
5
5 MVA Transformer , 13.8 / 440v
6
4000AT Panel , wiring & Accessories
7
Pipes & acc.
8
220v provision & lay-out
345,125.00
180,000.00
27,280.00
1,512,009.00
790,000.00
12,517,214.00
2,039,818.50
951,896.70
649,009.00
610,737.70
2,240,000.00
1,975,200.00
2,878,487.20
36,000.00
3.10%
0.54%
1.48%
4.22%
9.86%
0.41%
0.31%
0.01%
PERCENTILE
PREVIOUS CURRENT TO DATE
80.00%
80.00%
80.00%
80.00%
0.54% 100.00%
0.28% 100.00%
0.04% 75.00%
2.38% 80.00%
1.24% 80.00%
19.71%
3.21% 80.00%
1.50% 75.00%
1.02% 24.00%
0.96%
3.53%
3.11%
4.53%
0.06%
90.00%
80.00%
80.00%
70.00%
2.00%
6.00%
A C C O M P L I S H
RELATIVE WEIGHT
PREVIOUS CURRENT
80.00%
0.00%
80.00%
80.00%
0.00%
80.00%
0.00%
0.00%
2.48%
0.00%
1.18%
3.37%
0.00%
0.33%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
77.00%
80.00%
80.00%
0.00%
80.00%
75.00%
30.00%
0.54%
0.28%
0.03%
1.90%
1.00%
0.00%
2.57%
1.12%
0.25%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.06%
90.00%
80.00%
80.00%
0.00%
70.00%
0.87%
2.82%
2.49%
0.00%
0.04%
0.00%
0.00%
0.00%
0.00%
0.00%
6
IV.
VI
534,955.80
0.84%
40.00%
40.00%
0.34%
0.00%
120,000.00
4,666,004.00
282,221.95
4,459,248.00
12,140.00
0.19%
7.35%
0.44%
7.02%
0.02%
100.00%
90.00%
100.00%
100.00%
100.00%
100.00%
90.00%
100.00%
100.00%
100.00%
0.19%
6.61%
0.44%
7.02%
0.02%
0.00%
0.00%
0.00%
0.00%
0.00%
270,000.00
66,833.40
0.43%
0.11%
90.00%
80.00%
90.00%
80.00%
0.38%
0.08%
0.00%
0.00%
13,676,587.75
21.54%
38.00%
40.00%
8.18%
0.43%
44.56%
0.49%
###
2.00%
100.00%
NOTED BY:
K. PACOLOR
TADECO ENG'G-SUPERVISOR
RECOMMENDING APPROVAL :
R.A. TAN
AVP - ENGINEERING
I S H M E N T
IGHT
TO DATE PREVIOUS
2.48%
0.00%
1.18%
3.37%
0.00%
0.33%
0.00%
0.00%
48,974.37
11,131.97
90,338.43
868.59
-
0.54%
0.28%
0.03%
1.90%
1.00%
0.00%
2.57%
1.12%
0.31%
1,875.77
510.24
8.79
28,802.16
7,862.68
52,420.28
10,702.06
1,591.98
0.87%
2.82%
2.49%
0.00%
0.04%
5,286.62
63,213.86
49,151.69
14.29
AMOUNT
CURRENT
###
-
545.60
38,940.54
TO DATE
###
752,000.00
###
210,058.40
-
345,125.00
180,000.00
21,005.60
###
632,000.00
###
713,922.53
194,702.70
549,663.93
###
###
25,200.00
0.34%
1,802.69
213,982.32
0.19%
6.61%
0.44%
7.02%
0.02%
226.77
308,573.76
1,254.32
313,147.92
2.32
120,000.00
###
282,221.95
###
12,140.00
0.38%
0.08%
1,033.23
56.27
243,000.00
53,466.72
8.62%
###
45.06%
###
APPROVED BY:
B.B. LICAYAN
SENIOR VP -SVTBSI
273,531.76
###
###
###